santa barbara county reliability project screening report ... h... · 09:002975.cp13.02 santa...
TRANSCRIPT
09:002975.CP13.02
SANTA BARBARA COUNTY RELIABILITY PROJECT SCREENING REPORT FOR THE
PROPOSED PROJECT ALTERNATIVES AND OPTIONS FOR THE PAST WORK
APPLICATION NO.: A.12‐10‐018
SCH NO.: 2013041070
July 2014 Revised May 2015
California Public Utilities Commission 505 Van Ness Avenue
San Francisco, CA 94102 Contact: Jensen Uchida
Prepared by:
ECOLOGY AND ENVIRONMENT, INC. 505 Sansome Street, Suite 300
San Francisco, CA 94111
09:002975.CP13.02 iii July2014
able of Contents T Section Page
1 Introduction .................................................................................. 1-1 1.1 SummaryoftheProposedProject.....................................................................................................1‐1 1.2 PastWorkintheProjectArea..............................................................................................................1‐1 1.3 ScopeoftheEnvironmentalImpactReport...................................................................................1‐3 1.4 AlternativesversusOptions.................................................................................................................1‐3
1.4.1 Alternatives.................................................................................................................................1‐4 1.4.2 Options..........................................................................................................................................1‐4
1.5 PurposeoftheScreeningReport........................................................................................................1‐4 1.6 PurposeandObjectivesoftheProposedProject.........................................................................1‐4
1.6.1 Purpose.........................................................................................................................................1‐4 1.6.2 Objectives(DevelopedbytheCPUC)...............................................................................1‐5 1.6.3 CountyofSantaBarbaraSegment3AObjective.........................................................1‐5 1.6.4 Applicant’sStatedObjectives..............................................................................................1‐5
2 Overview of Evaluation Process ..................................................... 2-1 2.1 ScreenMethodology................................................................................................................................2‐1 2.2 CEQACriteria..............................................................................................................................................2‐1 2.3 Feasibility.....................................................................................................................................................2‐1 2.4 PotentialtoAvoidorLessenSignificantEnvironmentalEffects..........................................2‐2
2.4.1 SignificantEnvironmentalEffectsoftheProposedProject...................................2‐2 2.4.2 SignificantEnvironmentalEffectsofthePastWorkalongSegment3A...........2‐2
2.5 NoProjectAlternative.............................................................................................................................2‐3
3 Alternative Descriptions and Determinations .................................. 3-1 3.1 AlternativeA–ReducetheScopeofWorkalongSegments1,2,and3A..........................3‐1
3.1.1 ConsiderationofCEQACriteria..........................................................................................3‐1 3.1.2 Conclusion...................................................................................................................................3‐1
3.2 AlternativeB–InstallSomeStructuresalongSegment4viaHelicopter.........................3‐2 3.2.1 ConsiderationofCEQACriteria..........................................................................................3‐2 3.2.2 Conclusion...................................................................................................................................3‐2
3.3 AlternativeC–UndergroundSegments3Band4.......................................................................3‐2 3.3.1 ConsiderationofCEQACriteria..........................................................................................3‐2 3.3.2 Conclusion...................................................................................................................................3‐3
4 Option Descriptions and Determinations ........................................ 4-1
4.1 OptionA–PaintExistingLWSPolesandTSPalongSegment3A........................................4‐1 4.1.1 ConsiderationofCEQACriteria..........................................................................................4‐1 4.1.2 Conclusion...................................................................................................................................4‐2
4.2 OptionB–ReplaceExistingLWSPolesandTSPwithWoodPolesalongSegment3A..................................................................................................................................................4‐2 4.2.1 ConsiderationofCEQACriteria..........................................................................................4‐2 4.2.2 Conclusion...................................................................................................................................4‐2
Table of Contents
09:002975.CP13.02 iv July2014
4.3 OptionC–RelocatethePortionofSegment3AthatTraversesAgriculturalLandintheShepardMesaCommunitytoUndergroundConduit........................................4‐2 4.3.1 ConsiderationofCEQACriteria..........................................................................................4‐4 4.3.2 Conclusion...................................................................................................................................4‐5
4.4 OptionD–RelocateSegment3AtoUndergroundConduit....................................................4‐5 4.4.1 ConsiderationofCEQACriteria..........................................................................................4‐5 4.4.2 Conclusion...................................................................................................................................4‐6
4.5 OptionE–RerouteaPortionofSegment3AalongCasitasPassRoadonLWSPoles................................................................................................................................................................4‐6 4.5.1 ConsiderationofCEQACriteria..........................................................................................4‐6 4.5.2 Conclusion...................................................................................................................................4‐7
4.6 OptionF–RerouteaPortionofSegment3AalongCasitasPassRoadonWoodPoles................................................................................................................................................................4‐7 4.6.1 ConsiderationofCEQACriteria..........................................................................................4‐7 4.6.2 Conclusion...................................................................................................................................4‐7
5 Summary of Screening Report ........................................................ 5-1
6 References .................................................................................... 6-1
09:002975.CP13.02 v July2014
ist of Figures L
ist of Tables L Table Page Table1:SummaryofPotentiallySignificantEffectsoftheProposedProject.......................................................2‐2
Table2:Long‐TermSignificantEffectsofPastWorkalongSegment3A................................................................2‐3
Table3:SummaryofScreeningReport.................................................................................................................................5‐2
Figure Page Figure1:ProjectLocationandElectricalNeedsArea.......................................Error!Bookmarknotdefined.3
Figure2:OptionC,OptionE,andOptionFLocations......................................................................................................4‐3
09:002975.CP13.02 vii July2014
ist of Abbreviations and Acronyms L
applicant SouthernCaliforniaEdisonCompany
Caltrans CaliforniaDepartmentofTransportation
CDP CoastalDevelopmentPermit
CEQA CaliforniaEnvironmentalQualityAct
CPUC CaliforniaPublicUtilitiesCommission
EIR EnvironmentalImpactReport
ENA ElectricalNeedsArea
GIS geographicinformationsystem
GO GeneralOrder
kV kilovolt
LST latticesteeltower
LWS lightweightsteel
NMFS NationalMarineFisheriesService
PEA Proponent’sEnvironmentalAssessment
proposedproject SantaBarbaraCountyReliabilityProject
PTC PermittoConstruct
ROW right‐of‐way
SCE SouthernCaliforniaEdison Company
SR StateRoute
TSP tubularsteelpole
09:002975.CP13.02 1‐1 July2014
1 Introduction SouthernCaliforniaEdisonCompany(SCEortheapplicant)filedanapplication(A.12‐10‐018)withtheCaliforniaPublicUtilitiesCommission(CPUC)foraPermittoConstruct(PTC)theSantaBarbaraCountyReliabilityProject(theproposedproject)onOctober26,2012.TheproposedprojectincludesrebuildingandupgradingaportionofSCE’ssubtransmissioninfrastructureinSantaBarbaraandVenturacountiesbetweenthecitiesofSanBuenaventura(Ventura)andCarpinteria(Figure1).
1.1 Summary of the Proposed Project Thefollowingactivitiesaremajorcomponentsoftheproposedproject: Reconstructionofexisting66‐kilovolt(kV)subtransmissionfacilities,primarilythoselocated
withinthecurrentutilityrights‐of‐way(ROWs)betweenthe“Y”(i.e.,thepointalongthecorridorwhereSegments2,3B,and4converge)inVenturaCountyandtheCarpinteriaSubstationinSantaBarbaraCounty(Segments4and3B);
Installationofmarkerballsonoverheadwire; ModificationofsubtransmissionandsubstationequipmentwithintheCarpinteriaSubstation,
CasitasSubstation,andSantaClaraSubstation; Replacementoflineprotectionrelayswithinexistingsubstationequipmentroomsorcabinetsat
theGettySubstation,GoletaSubstation,OrtegaSubstation,andSantaBarbaraSubstation; InstallationoftelecommunicationsfacilitiesalongSegments1,2,and4andattheCarpinteria
Substation,CasitasSubstation,SantaClaraSubstation,andVenturaSubstation; InstallationofafaultreturnconductoronsubtransmissionstructuresalongSegment3A;and RemovalofsubtransmissioninfrastructurefoundationsinSegments1and2.
1.2 Past Work in the Project Area In1999,SCEcommencedconstructionintheprojectareaonSegments1,2,and3Aandseveralsurroundingsubstations(Figure1).Atthetime,SCEbelievedthattheproposedupgradestosubtransmissionlinesinVenturaandSantaBarbaracountieswereexemptfrompermittingpursuanttoCPUCGeneralOrder(GO)131‐DandtheCaliforniaCoastalAct(CaliforniaPublicResourcesCodeSection30610)becausetheywereconsidered“equivalentfacilitiesorstructures.”However,in2004,residentsoftheShepardMesaareanearCarpinteriaraisedconcernsthatthenewstructuresinSegment3Aweredifferentinappearancefromthepreviousstructures.TheCaliforniaCoastalCommissionandCountyofSantaBarbaraCoastalProgramstaffissuedaStopWorkordertoSCEafterstaffdeterminedthatworkwithintheCoastalZonedidnotqualifyforanexemptionfromaCoastalDevelopmentPermit(CDP)andthataCaliforniaEnvironmentalQualityAct(CEQA)reviewwasrequired.Similarly,theCPUCdeterminedthatthepastworkshouldnothavebeenconsideredexemptfromGO131‐D,andsimilarworkconductedbytheapplicantinthefuturewouldrequireaCEQAreviewandaPTC.
1 Introduction
09:002975.CP13.02 1‐3 July2014
Between1999and2004,SCEhadalreadyconductedthefollowingunpermittedactivities: SomesubstationmodificationswerecompletedattheCarpinteria,Goleta,IslaVista,Ortega,and
SantaClarasubstations; Newsubtransmissionstructuresanda66‐kVconductorwereinstalledinSegment1fromthe
SantaClaraSubstationtotheCasitasSubstation,andtheexisting66‐kVconductorwasremoved; Newsubtransmissionstructuresanda66‐kVconductorwereinstalledinSegment2from
CasitasSubstationtothe“Y”locatednearCasitasPass,justwestofLakeCasitasinVenturaCounty,andtheexisting66‐kVconductorwasremoved;
Newsubtransmissionstructuresanda66‐kVconductorwereinstalledinSegment3AfromtheCarpinteriaSubstationtotheSantaBarbaraCounty/VenturaCountyline,andexistingwoodsubtransmissionstructureswereremovedortopped;
SubtransmissionstructuresinSegments1and2werepartiallyremoved;and Twofootingsfortubularsteelpoles(TSP),twolightweightsteel(LWS)H‐frames,oneLWSpole,
andtwoswitchesattheGettyTaplocationwereinstalled,andtwowoodH‐framesandonewoodpolewereremoved.
1.3 Scope of the Environmental Impact Report InaccordancewithCEQA,theCPUCisservingastheLeadAgencyfortheenvironmentalreviewprocessandispreparinganEnvironmentalImpactReport(EIR)toevaluatetheenvironmentalimpactsoftheproposedproject.TheEIRwillalsodiscussandanalyzeareasonablerangeofalternativestotheproposedprojectinordertoidentifytheenvironmentallysuperioralternative.TheCPUCwillrelyontheenvironmentalassessmentoftheproposedprojectintheEIRfortheapprovalprocessofSCE’sPTCapplication.CEQAdoesnotrequirereviewofpriorunpermittedactivity,suchasthepastworkintheprojectarea(Fatv.CountyofSacramento[2002]97Cal.App.4th1270;Riverwatchv.CountyofSanDiego[1999]76Cal.App.4th1428).However,theCountyofSantaBarbara,asaResponsibleAgencyunderCEQA,hasrequestedthattheCPUCEIRincludesomelevelofanalysisrelatedtopastworkwithintheCoastalZone(Segment3A).Therefore,theEIRwillidentifylong‐termsignificantimpactsthathaveresultedfromthereconductoringofthesubtransmissionlinealongSegment3Abycomparingcurrentenvironmentalandregulatoryconditionstoconditionsthatexistedatthetimetheworkcommencedin1999.TheanalysisisbasedoninformationthatwascompiledfromtheProponent’sEnvironmentalAssessment(PEA),theapplicant’sresponsestodatarequests,previousfieldinvestigationsconductedbytheapplicant,andestimatesbasedonavailablegeographicinformationsystem(GIS)data.Giventheelapsedtimebetweenpreviousactivitiesandthepresentproposedproject,agoodfaitheffortwasmadetogatherareasonablelevelofdatatocharacterizeimpacts;however,environmentalconditionspriortothepastworkalongSegment3Aareunknownformanyresourceareasorwouldbeunreasonablyoneroustoidentify.TheEIRwillalsodiscussandanalyzeoptionsforreducinganylong‐termsignificantimpactsthatresultedfromthepastworkalongSegment3A.TheCountyofSantaBarbarawillrelyontheenvironmentalassessmentoftheproposedproject,aswellasthelimitedassessmentofimpactsthatresultedfromthepastwork,inordertoapprovearetroactiveCDP.
1.4 Alternatives versus Options Thissectionclarifiesthedifferencebetweentheterms“Alternative”and“Option”forthepurposesofthisScreeningReport.
1 Introduction
09:002975.CP13.02 1‐4 July2014
1.4.1 Alternatives AlternativeswereidentifiedtoaddresssignificantimpactsoftheproposedprojectandarerequiredunderCEQAGuidelines.CEQAGuidelinesSection15126.6(a)states:
AnEIRshalldescribeareasonablerangeofalternativestotheproject,ortothelocationoftheproject,whichwouldfeasiblyattainmostofthebasicobjectivesoftheprojectbutwouldavoidorsubstantiallylessenanyofthesignificanteffectsoftheproject,andevaluatethecomparativemeritsofthealternatives.AnEIRneednotconsidereveryconceivablealternativetoaproject.Ratheritmustconsiderareasonablerangeofpotentiallyfeasiblealternativesthatwillfosterinformeddecisionmakingandpublicparticipation.
TheEIRwillevaluateandcomparealternativestoidentifytheenvironmentallysuperioralternative.1.4.2 Options Duetothepastworkintheprojectareaanditsrelationshiptotheproposedproject,modificationstotheproposedprojectthatcouldreducethelong‐termsignificantimpactsofthepastworkalongSegment3Ahavebeenidentified.Projectmodifications,or“options,”aresimilartoalternativesinthattheyareidentifiedandscreenedusingsimilarcriteria;however,theterm“option”hasbeenusedtodifferentiatethemfromaCEQAalternative.AsdiscussedinSection1.3,CEQAdoesnotrequiretheevaluationofunpermittedactivities;however,attherequestoftheCountyofSantaBarbara,theEIRwillevaluatetheenvironmentalimpactsofproposedprojectoptions.TheCPUCwillnotincorporateorimplementanyoftheoptions.Rather,theoptionswouldbeimplementedatthediscretionoftheCountyaspartoftheirCDPissuance.
1.5 Purpose of the Screening Report ThisScreeningReportdocuments: Therangeofalternatives/optionsidentifiedandevaluated; Theapproachandmethodsusedforscreeningeachalternative/option;and Adescriptionofeachalternative/optionandtheresultsofthescreeningevaluation(i.e.,the
alternativeseliminatedfromfurtherconsiderationorcarriedforwardforfullanalysisintheEIR).
ThisScreeningReportwillsupplementtheinformationpresentedinChapter3oftheDraftEIRregardingprojectalternatives.AlternativestotheproposedprojectwereidentifiedbytheCPUC,theCountyofSantaBarbara,theapplicantaspartofthePEA,andthepublicduringpublicscoping.Thescreeningprocessidentifiedandevaluatedthreepotentialalternativestotheproposedproject,asdescribedinChapter3ofthisScreeningReport.ThisScreeningReportwillalsosupplementtheinformationpresentedinChapter7oftheDraftEIRregardingprojectoptions.OptionsformodifyingtheproposedprojectwereidentifiedbytheCPUC,theapplicantaspartofthePEA,theCountyofSantaBarbara,andthepublicduringpublicscoping.Thescreeningprocessidentifiedandevaluatedsevenpotentialprojectoptionsthatcouldmitigatethelong‐termsignificantimpactsofthepastworkalongSegment3A,asdescribedinChapter4ofthisScreeningReport.
1.6 Purpose and Objectives of the Proposed Project 1.6.1 Purpose ThepurposeoftheproposedprojectistoensuretheavailabilityofsafeandreliableelectricalservicetohelpmeetcustomerelectricaldemandwithintheElectricalNeedsArea(ENA)duringemergencyconditions(Figure1).
1 Introduction
09:002975.CP13.02 1‐5 July2014
1.6.2 Objectives (Developed by the CPUC) Aproject’sstatementofobjectivesdescribestheunderlyingpurposeoftheprojectandthereasonsforundertakingtheproject.Tofulfillthisrequirement,threeobjectivesweredevelopedbytheCPUC,withconsiderationoftheobjectivespresentedinthePEA(seeSection1.6.4).Theobjectives,asdefinedbytheCPUC,wereusedasabasisforthedevelopmentofareasonablerangeofalternatives,aswellasoptionsthatwouldmodifytheproposedprojectasdescribedinSection1.4.2.Thebasicobjectivesoftheproposedprojectareto:1. Providelong‐termreliabilityandcontinuityofservicetotheENA;2. Enhanceoperationalflexibilitybyprovidingtheabilitytotransfertheelectricloadbetween
localsubstationsandremoveexisting220‐kVor66‐kVlinesfromservicewhenneededformaintenancepurposes;and
3. Increaseenergyefficiencyofthe66‐kVsubtransmissionline.1.6.3 County of Santa Barbara Segment 3A Objective AsdescribedinSection1.4.2,althoughnotrequiredbyCEQA,theCountyofSantaBarbarahasanadditionalobjectiverelatedtotheirissuanceofaretroactiveCDP.Inordertobecarriedforwardforconsideration,inadditiontomeetingthemajorityoftheCPUC’sprojectobjectivesinSection1.6.2,aprojectoptionmust:1. Reducealong‐termsignificantimpact1thatresultedfromthepast,unpermittedworkalong
Segment3AintheCoastalZonethatoccurredbetween1999and2004.
1.6.4 Applicant’s Stated Objectives TheobjectiveslistedinSection1.6.2and1.6.3havebeenusedtoscreenalternativesandoptions;however,theapplicantalsoidentifiedthefollowingfourobjectivesinthePEA,whicharelistedfordisclosurepurposes:1. Providelong‐termreliabilityandcontinuityofservicetotheENAintheeventofanatural
disasterorotheroccurrencethataffectsthe220kVtransmissionsystemservingthearea;2. Enhanceoperationalflexibilitybyprovidingtheabilitytotransfertheelectricloadbetween
localsubstationsandremoveexisting220‐kVor66‐kVlinesfromservicewhenneededformaintenancepurposes;
3. Totheextentpracticable,useexistingROWsandfacilitiesconstructedtodatetominimize:a. Environmentalimpacts,b. Constructionschedule,andc. Projectcostandimpactonratepayers;
4. DesignandconstructtheprojectinconformancewithSCE’scurrentengineering,design,andconstructionstandardsforsubstation,transmission,subtransmission,anddistributionsystemprojects(SCE2012).
1Long‐termsignificantimpactsbasedonanindependentassessmentusingCEQAcriteria.
09:002975.CP13.02 2‐1 July2014
2 Overview of Evaluation Process
2.1 Screen Methodology Theevaluationprocessforthealternativesandoptionsincludeathree‐stepscreeningprocess: Step1:Clarifythedescriptionofthealternative/optiontoallowforcomparativeevaluation; Step2:Evaluatethealternative/optionbycomparingitwiththeproposedprojectandwiththe
CEQAcriteriaforalternatives(Sections2.2through2.4,below).Inaddition,althoughCEQAGuidelinesdonotrequiretheconsiderationofoptionsforreducingimpactsofunpermittedwork,asdescribedinSection1.3and1.6.3,projectoptionsarealsoevaluatedaccordingtotheCEQAcriteria;and
Step3:Determinethesuitabilityofeachalternative/optionforfullanalysisintheEIRbasedontheresultsofStep2.Ifthealternative/optionisunsuitable,eliminateitfromfurtherconsideration.
2.2 CEQA Criteria CEQAGuidelines(Sections15126.6(a)and(d))requireanEIRtodescribeareasonablerangeofpotentiallyfeasiblealternativesandtoincludesufficientinformationabouteachalternativetoallowmeaningfulevaluation,analysis,andcomparisonwiththeproposedproject.TocomplywithCEQArequirementsfortheevaluationofalternatives,eachalternativeoroptionidentifiedwasevaluatedaccordingtothefollowingcriteria: Wouldthealternative/optionaccomplishallormostoftheprojectobjectives? Wouldthealternative/optionbepotentiallyfeasible(fromaneconomic,legal,andtechnological
perspective)? Wouldthealternativeavoidorsubstantiallylessenanysignificanteffectsoftheproposed
project(includingconsiderationofwhetherthealternative,itself,couldcreatesignificanteffectspotentiallygreaterthanthoseoftheproposedproject)?Inaddition,forprojectoptions,wouldtheoptionreduceanysignificantlong‐termeffectsofpastworkalongSegment3A?
CEQAGuidelinesrequiretheconsiderationofalternativescapableofeliminatingorreducingsignificantenvironmentaleffectseventhoughtheymay“impedetosomedegreetheattainmentofprojectobjectivesorwouldbemorecostly”(Section15126.6(b)).Inthecaseofprojectoptions,theoptionswouldnotreduceasignificantenvironmentaleffectoftheproposedprojectandmayinsomecasesresultinatemporaryincreaseinshort‐termconstruction‐relatedimpacts.However,inordertomeettheCountyofSantaBarbaraobjective,atemporary,lessthansignificantconstruction‐relatedimpactisconsideredacceptableiftheoptionwouldresultinareductionofalong‐termsignificantimpact.
2.3 Feasibility AccordingtoCEQAGuidelines(Section15126.6(f)(1)),amongthefactorsthatmaybetakenintoaccountwhenaddressingthefeasibilityofalternativesincludesitesuitability,economicviability,
2 OverviewofEvaluationProcess
09:002975.CP13.02 2‐2 July2014
availabilityofinfrastructure,generalplanconsistency,otherplansorotherregulatorylimitations,jurisdictionalboundaries,andproponentcontroloveralternativesites.Forthescreeninganalysis,thepotentialfeasibilityofalternativeswasassessedusingthefollowingconsiderations: TechnicalFeasibility.Isthealternativefeasiblefromatechnologicalperspective,considering
availabletechnology?Arethereanyconstruction,operation,ormaintenanceconstraintsthatcannotbeovercome?
LegalFeasibility.Dolegalprotectionsonlandsprecludeorsubstantiallylimitthefeasibilityofpermittinghigh‐voltagetransmissionlinesandsubstations?Doregulatoryrestrictionssubstantiallylimitthefeasibilityorsuccessfulpermittingofhigh‐voltagetransmissionlinesandsubstations?Isthealternativeconsistentwithregulatorystandardsfortransmissionsystemdesign,operation,andmaintenance?
EconomicFeasibility.Isthealternativesocostlythatitsimplementationwouldbeprohibitive?
2.4 Potential to Avoid or Lessen Significant Environmental Effects CEQArequiresanEIRtodescribealternativesthatwould“avoidorsubstantiallylessenanyofthesignificanteffectsoftheproject”(CEQAGuidelinesSection15126.6(a)).2.4.1 Significant Environmental Effects of the Proposed Project Atthescreeningstage,itisnotpossibletoevaluatealloftheeffectsofalternativesincomparisontotheproposedprojectwithabsolutecertainty,anditmaynotbepossibletoquantifytheeffects.However,itispossibletoidentifyelementsofanalternativethatarelikelytocreateanimpactandrelatethem,totheextentpossible,togeneralconditionsintheproposedprojectarea.Table1presentsasummaryofthepotentiallysignificanteffectsoftheproposedproject.ThistablewaspreparedpriortocompletionoftheEIRanddoesnotincludethedetailedanalysisthatisincludedinChapter4,“EnvironmentalAnalysis.”Table 1: Summary of Potentially Significant Effects of the Proposed Project
Resource Potentially Significant Effect
Aesthetics Operation of the project components could result in impacts on visual quality within viewsheds of Segments 3B and 4.
Air Quality Construction could result in an exceedance of criteria air pollutants above established thresholds.
Biological Resources Construction of the project could result in impacts on steelhead trout designated critical habitat, arroyo chub, and avian species.
Cultural Resources Construction of some project elements could result in impacts on cultural resources.
Traffic Temporary lane closures along Highway 33 and other streets in the project area could result in impacts related to traffic and transportation.
2.4.2 Significant Environmental Effects of the Past Work along Segment 3A TheCPUChasidentifiedsignificantlong‐termimpactsassociatedwithaestheticsandlandusethatresultedfromSCEconstructionactivitiesalongonSegment3Abetween1999and2004.Basedonthelimitedavailabledata,thepastworkresultedinnootherlong‐termsignificantimpacts.Table2showsthelong‐termsignificantimpactsthatresultedfromSCE’sconstructionactivities.
2 OverviewofEvaluationProcess
09:002975.CP13.02 2‐3 July2014
Table 2: Long‐Term Significant Effects of Past Work along Segment 3A
Resource Long‐Term Significant Effect
Aesthetics The replacement of five wood poles within the viewshed of State Route (SR) 150 with four LWS poles and one TSP resulted in a significant long‐term impact on the scenic resources within an eligible state scenic highway from the color and size of the new poles.
The replacement of 49 wood poles with 49 LWS poles and one TSP resulted in a significant long‐term impact on the visual character of the site and its surroundings and from the color and size of the new poles.
Land Use Construction and operation of the existing subtransmission line along Segment 3A conflicts with County of Santa Barbara Article II, Coastal Zoning Ordinance, because applicable approvals and permits were not obtained at the time of construction prior to 2004.
2.5 No Project Alternative CEQArequiresthataNoProjectAlternativebeconsideredinEIRs(CEQAGuidelinesSection15126.6(e)).ThepurposeofdescribingandanalyzingaNoProjectAlternativeistoallowdecision‐makerstocomparetheeffectsofapprovingtheproposedprojectwiththeeffectsofnotapprovingtheproposedproject.BecausefullconsiderationofaNoProjectAlternativeisrequiredbyCEQA,theNoProjectAlternativewillbeevaluatedintheEIR;however,theNoProjectAlternativeisnotevaluatedinthisScreeningReport.
09:002975.CP13.02 3‐1 July2014
3 Alternative Descriptions and Determinations
Thealternativesscreeningprocessidentifiedandevaluatedthreepotentialalternativestotheproposedproject.ThissectiondescribeseachofthealternativesidentifiedandexplainswhytheywereretainedforfurtherconsiderationintheEIRorwereeliminated.EachalternativethatwasdeterminedtomeetCEQAorothercriteriaforalternatives(Sections2.2through2.4)wasretainedforfurtherconsiderationintheEIR.ThisScreeningReportevaluatesthefollowingalternativestotheproposedproject:AlternativeA. ReducetheScopeofWorkalongSegments1,2,and3AAlternativeB. InstallSomeStructuresalongSegment4viaHelicopterAlternativeC. UndergroundSegments3Band4
3.1 Alternative A – Reduce the Scope of Work along Segments 1, 2, and 3A AlternativeAwasidentifiedbytheCPUC.Underthisalternative,theexisting30foundationsand15toppedsubtransmissionwoodpolesalongSegments1,2,and3Awouldnotberemoved.Allremainingsegments,substationsupgrades,andothermajorworkwouldbeconstructedasdescribedintheproposedproject.3.1.1 Consideration of CEQA Criteria Project Objectives AlternativeAwouldmeetallprojectobjectives(Section1.6.2).Feasibility AlternativeAwouldbefeasiblefromatechnical,legal,andeconomicperspective.Environmental Effect AlternativeAwouldavoidorreducepotentiallysignificanteffectsoftheproposedproject(Table1).AllowingthetoppedpolesandabandonedstructuresfromthepastworktoremaininplacewouldreducetheamountofgrounddisturbancethatwouldoccurduringconstructionandwouldreducetheamountofNOXandPM10emissionsproducedduringconstruction.Leavingthetoppedpolesandabandonedstructuresinplacewouldnotcreateanyimpacttothevisualquality,asthesestructuresarepartofthe2012environmentalbaselineconditions.3.1.2 Conclusion RETAINED.AlternativeAwouldbefeasible,meetallprojectobjectives,andwouldavoidorsubstantiallylessenpotentialsignificantimpactsoftheproposedprojectonairquality.Therefore,thisalternativewasretainedforfurtherconsiderationintheEIR.
3 Alternative Descriptions and Determinations
09:002975.CP13.02 3‐2 July2014
3.2 Alternative B – Install Some Structures along Segment 4 via Helicopter AlternativeBwasidentifiedbytheCPUC.Underthisalternative,equipment,materials,andworkerswouldbedeliveredtoConstructionSites116through125viahelicopter.Subtransmissionstructuresandconductorswouldbeinstalledwithhelicopterassistance.ThisalternativewouldavoidtheneedtoperformroadimprovementswithinNationalMarineFisheriesService(NMFS)‐designatedcriticalhabitatforsteelheadtroutorwithinstreamsthatdrainintoNMFS‐designatedcriticalhabitat.Allremainingsegments,substationsupgrades,andothermajorworkwouldbeconstructedasdescribedintheproposedproject.3.2.1 Consideration of CEQA Criteria Project Objectives AlternativeBwouldmeetallprojectobjectives(Section1.6.2).Feasibility AlternativeBwouldbefeasiblefromatechnical,legal,andeconomicperspective.Environmental Effect AlternativeBwouldavoidorreducepotentiallysignificanteffectsoftheproposedproject(Table1).Accessingconstructionsites116through125withahelicopterwouldavoidpotentiallysignificantimpactstoNMFS‐designatedcriticalhabitatforsteelheadtroutfromtheestablishmentofaccessroads.Thereducedamountofconstructionwouldalsolessenpotentialsignificanteffectstoculturalresources.AlthoughthisalternativemayreducePM10emissionsduringconstruction,itwouldlikelyresultingreaterNOXemissionsfromincreasedhelicopteroperations. 3.2.2 Conclusion RETAINED.AlternativeBwouldbefeasible,meetallprojectobjectives,andwouldavoidorsubstantiallylessenpotentialsignificantimpactsoftheproposedprojectonbiologicalandculturalresources.Therefore,thisalternativewasretainedforfurtherconsiderationintheEIR.
3.3 Alternative C – Underground Segments 3B and 4 AlternativeCwasidentifiedbythePEA.Underthisalternative,the66‐kVsubtransmissionlinealongSegments3Band4wouldbeinstalledinnewundergroundconduitwithintheexistingROW.Theexistinglatticesteeltowers(LSTs)andwoodguystubsalongSegment3Band4wouldberemoved.Theapplicantmayneedtoobtainnewencroachmentpermits,asmanyoftheexistingROWsonlyprovidesoverheadaccess.Allremainingsegments,substationsupgrades,andothermajorworkwouldbeconstructedasdescribedintheproposedproject.3.3.1 Consideration of CEQA Criteria Project Objectives AlternativeCwouldmeetmostoftheprojectobjectives(Section1.6.2).ProjectObjective3(increaseenergyefficiencyofthe66‐kVsubtransmissionline)wouldnotbemetunderthisalternative.Feasibility AlternativeCwouldnotbefeasiblefromatechnicalandeconomicperspective.Thesteep,mountainous,androckyterrainintheprojectareamakesthisalternativetechnicallyinfeasible.Insomeareas,thecurrentlinespansgulliesandhilltopswherethereiscurrentlylimitedspaceforlaydownareasandequipment.Itwouldbeinfeasibletopositiontrenchingandblastingequipmentintheseareas.Inaddition,thecosttoundergroundasubtransmissionlineis4to14timesthecostofbuildingatransmissionlineaboveground(notincludingthecostofobtainingROWs)(PSCW2011).ThecostofundergroundinginsuchterrainwouldbeprohibitivelyexpensivetoSCE.
3 Alternative Descriptions and Determinations
09:002975.CP13.02 3‐3 July2014
Environmental Effect AlternativeCwouldavoidpotentiallysignificantlong‐termimpactsonthevisualqualityfromviewsofSegment4alongStateRoute(SR)192,whichisbeingconsideredbytheCityofCarpinteriaforfuturedesignationasascenichighway.Additionally,thisalternativewouldavoidcreatingvisualcontrastinthearea.Duringconstruction,thisalternativewouldtemporarilyincreaseenvironmentaleffectsassociatedwithairemissions,noise,agriculture,andbiologicalandculturalresources.Additionally,thehillsaboveCarpinteriacontaindocumentedculturalresources.Theblasting,trenching,andlargeamountofvegetationremovalthatwouldberequiredforimplementingthisalternativewouldresultinagreaterriskofimpactstobothdocumentedandundocumentedculturalresourcesthantheproposedproject.Inaddition,blastingandtrenchingalongsteepslopescouldleadtogreaterslopeinstabilityissuesandgeologichazardsinboththeshort‐andlong‐term.Impactsduetogeologichazardscouldbeconsideredsignificant.3.3.2 Conclusion ELIMINATED.AlternativeCwouldmeetmostoftheprojectobjectives,andwouldlessenasignificantimpactoftheproposedprojectonaesthetics;however,thisalternativeiseconomicallyandtechnicallyinfeasibleandcouldleadtoasignificantimpactrelatedtogeologichazards.Therefore,thisalternativewaseliminatedfromfurtherconsideration.
3 Alternative Descriptions and Determinations
09:002975.CP13.02 3‐4 July2014
Thispageintentionallyleftblank
09:002975.CP13.02 4‐1 July2014
4 Option Descriptions and Determinations
Thescreeningprocessidentifiedandevaluatedsevenprojectoptionsthatwouldreducethesignificantlong‐termimpactsofthepastworkalongSegment3Aviamodificationstotheproposedproject.ThissectiondescribeseachoftheoptionsidentifiedandexplainswhytheywereretainedforfurtherconsiderationintheEIRorwereeliminated.EachoptiondeterminedtomeettheCEQAcriteria(Sections2.2through2.4)wasretainedforfurtherconsiderationintheEIR.TheEnvironmentalEffectdiscussionforeachoptionbelowdescribestheenvironmentaleffectsfromtheremovaloftheexistingsubtransmissionline,asappropriate,andtheconstructionoftheprojectoption.TheEnvironmentalEffectdiscussiondoesnotincludeimpactsfromconstructionoftheexistingsubtransmissionlinebecausetheenvironmentaleffectsarethesameforeveryoptionandaredescribedinChapter7oftheEIR.ThisScreeningReportevaluatesthefollowingoptionsforSegment3Aoftheproposedproject:OptionA. PaintExistingLWSPolesandTSPalongSegment3AOptionB. ReplaceExistingLWSPoleswithWoodPolesalongSegment3AOptionC. RelocatethePortionofSegment3AthatTraversesAgriculturalLandintheShepard
MesaCommunitytoUndergroundConduitOptionD. RelocateSegment3AtoUndergroundConduitOptionE. SubmitPoleSpecificationsandPlansforPoles182and183totheCountyofSanta
BarbaraOptionF. RerouteaPortionofSegment3AalongCasitasPassRoadonLWSPolesOptionG. RerouteaPortionofSegment3AalongCasitasPassRoadonWoodPoles
4.1 Option A – Paint Existing LWS Poles and TSP along Segment 3A OptionAwasidentifiedbytheCPUC.Underthisoption,theexistingLWSpolesandTSPalongSegment3Awouldbepaintedtoreducecontrastwiththesurroundingenvironmentalsetting.4.1.1 Consideration of CEQA Criteria Project Objectives OptionAwouldmeetallprojectandCountyofSantaBarbaraobjectives(Sections1.6.2and1.6.3).Feasibility OptionAwouldbefeasiblefromatechnical,legal,andeconomicperspective.Environmental Effect OptionAwouldreducethesignificantlong‐termaestheticimpactthatresultedfromthereplacementofwoodpoleswithtallerLWSpolesandaTSPalongSegment3A(Table2).Noneofthestructuresinstalledbetween1999and2004alongSegment3Awouldneedtoberemoved.Onlypaintingactivitieswouldneedtobeconductedtocompletethisoption.Paintingactivitieswouldhavenegligibleenvironmenteffectsonairquality,traffic,andbiologicalresources.
4 Option Descriptions and Determinations
09:002975.CP13.02 4‐2 July2014
4.1.2 Conclusion RETAINED.OptionAwouldbefeasible,meetallprojectandCountyofSantaBarbaraobjectives,andreducethesignificantlong‐termaestheticimpactthatresultedfromthepastworkalongSegment3A.Therefore,thisoptionwasretainedforfurtherconsiderationintheEIR.
4.2 Option B – Replace Existing LWS Poles and TSP with Wood Poles along Segment 3A
OptionBwasidentifiedbytheCPUC.Underthisoption,theexistingLWSpolesalongSegment3Awouldbereplacedone‐for‐onewithcomparablysized,newwoodpoles,similartothepolesthatexistedpriortothepastworkcompletedbetween1999and2004.TheTSPconstructedbetween1999and2004wouldnotbereplacedbecauseawoodpolecouldnotaccommodatetheweightofthecurrentconductor.4.2.1 Consideration of CEQA Criteria Project Objectives OptionBwouldmeetallprojectandCountyofSantaBarbaraobjectives(Sections1.6.2and1.6.3).Feasibility OptionBwouldbefeasiblefromatechnical,legal,andeconomicperspective.Environmental Effect OptionBwouldreducethesignificantlong‐termaestheticimpactsthatresultedfromthereplacementofwoodpoleswithtallerLWSpolesalongSegment3A(Table2).Beforeinstallationofthenewwoodpoles,thisoptionwouldrequiretheremovalofTSPandLWSpolesthatwereinstalledbetween1999and2004alongSegment3A.Constructionofthisoptionwouldtemporarilyincreaseenvironmentaleffectsassociatedwithairemissions,noise,agriculture,traffic,andbiologicalandculturalresources.4.2.2 Conclusion RETAINED.OptionBwouldbefeasible,meetallprojectandCountyofSantaBarbaraobjectives,andreducethesignificantlong‐termaestheticimpactsthatresultedfromthepastworkalongSegment3A.Therefore,thisoptionwasretainedforfurtherconsiderationintheEIR.
4.3 Option C – Relocate the Portion of Segment 3A that Traverses Agricultural Land in the Shepard Mesa Community to Underground Conduit
OptionCwasidentifiedbytheCPUC,CountyofSantaBarbara,andpublic.Underthisoption,newundergroundconduitwouldreplace0.88mileofexistingLWSpolestraversingagriculturallandintheShepardMesacommunitywithintheexistingROW(Figure2).Thisoptionwouldrequiretheconstructionofapproximately13new55‐foot‐tallwoodpolesneartheundergroundsubtransmissionlinetodistributepowertothesurroundingShepardMesacommunity.Thesepoleswouldalsocontainthird‐partylinesforcontinuedcableandtelecommunicationsservices.ThisoptionwouldrequiretwonewTSPriserpoles—oneateachendoftheundergroundedlinetotransitionthelineaboveandbelowground.TheapplicantmayneedtoobtainnewencroachmentpermitsasmanyexistingROWsonlyprovideoverheadaccess,andthecurrentROWmayincludeexistingundergroundinfrastructurethatwouldneedtobeavoidedsuchaswater,sewer,andgaslines.Inaddition,thedistributionpoleswouldneedtobeoffsetfromthealignmentoftheundergroundsubtransmissionline,whichcouldalsorequiretheacquisitionofnewROWs.Nofaultreturnconductorwouldberequiredwiththisoption.
4 Option Descriptions and Determinations
09:002975.CP13.02 4‐4 July2014
This page intentionally left blank
4 Option Descriptions and Determinations
09:002975.CP13.02 4‐5 July2014
4.3.1 Consideration of CEQA Criteria Project Objectives OptionCwouldmeetallprojectandCountyofSantaBarbaraobjectives(Sections1.6.2and1.6.3).Feasibility Undergroundingthetransmissionlineinaflatanddevelopedareaisafeasibleoption.OptionCwouldbefeasiblefromatechnical,legal,andeconomicperspective.Environmental Effect OptionCwouldreducethesignificantlong‐termaestheticimpactsthatresultedfromthereplacementofwoodpoleswithtallerLWSpolesalongSegment3A(Table2).Constructionofthisoptionwouldincluderemovalofthe12LWSpolesandwoodguystubsthatwereinstalledbetween1999and2004alongSegment3A.Duringconstruction,thisoptionwouldtemporarilyincreaseenvironmentaleffectsassociatedwithairemissions,noise,agriculture,traffic,andbiologicalandculturalresources.4.3.2 Conclusion RETAINED.OptionCwouldbefeasible,meetallprojectandCountyofSantaBarbaraobjectives,andreducethesignificantlong‐termaestheticimpactsthatresultedfromthepastworkalongSegment3A.Therefore,thisoptionwasretainedforfurtherconsiderationintheEIR.
4.4 Option D – Relocate Segment 3A to Underground Conduit TheCPUCandSantaBarbaraCountyidentifiedOptionD.Underthisoption,Segment3AwouldincludetheinstallationofnewundergroundconduittosupportthesubtransmissionlinemainlyentirelywithinCaltransROWalongFoothillRoadandCasitasPassRoad.NoundergroundconduitwouldbeinstalledthroughthecenterofwithintheShepardMesacommunity;however,duetotheexistenceofoverheadelectricalfacilitiesaswellaspossibleundergroundinfrastructure,OptionDmayrequiredeviatingoutsideofCaltransROWandacquiringadditionaleasementsonprivateland,asneeded.TheapplicantwouldneedtoobtainnewencroachmentpermitsfornewROWastheirexistingeasementsonlyprovideoverheadaccessandwouldlikelynotcontainsufficientspacetoaccommodatebothadistributionlineandanundergroundsubtransmissionline.ThisoptionswouldalsorequiretwonewTSPriserpoles—oneateachendoftheundergroundedlinetotransitionthelineaboveandbelowground.Nofaultreturnconductorwouldberequired.TheexistingdistributionandthirdpartylineslocatedwithinSegment3AwouldremainwithintheexistingoverheadROW.Theexisting49LWSpoleslocatedalongSegment3Awouldberemovedandreplacedwith55‐foottallwooddistributionpoles.Theexisting35woodpoleslocatedalongSegment3Awouldbetoppedorremovedandreplacedwithwooddistributionpolesasneeded.IntheShepardMesacommunity,13wooddistributionpoleswouldbeconstructedintheexistingROW.4.4.1 Consideration of CEQA Criteria Project Objectives OptionDwouldmeetmostoftheprojectobjectives(Section1.6.2).ProjectObjective3(increaseenergyefficiencyofthe66‐kVsubtransmissionline)wouldnotbemetunderthisalternative..ThisoptionwouldmeettheCountyofSantaBarbaraobjective(Section1.6.3).Feasibility Undergroundingthetransmissionlineinaflatanddevelopedareaisafeasibleoption.OptionDwouldbefeasiblefromatechnical,legal,andeconomicperspective.
4 Option Descriptions and Determinations
09:002975.CP13.02 4‐6 July2014
Environmental Effect OptionDwouldreducethesignificantlong‐termaestheticimpactsthatresultedfromthereplacementofwoodpoleswithtallerLWSpolesandaTSPalongSegment3A(Table2).Constructionofthisoptionwouldincluderemovalofthe50LWSpoles,oneTSP,andwoodguystubsinstalledduringpastworkalongSegment3A,aswellastheremovalof35existingwoodpolesthatareconsideredtobeinsufficientlygoodconditionandwereleftinplaceduringtheconstructionactivitiesthatoccurredbetween1999and2004.Duringconstruction,thisoptionwouldtemporarilyincreaseenvironmentaleffectsassociatedwithairemissions,noise,agriculture,traffic,andbiologicalandculturalresources.4.4.2 Conclusion RETAINED.OptionDwouldbefeasible,meetmostoftheprojectobjectivesandmeettheCountyofSantaBarbaraobjective,andreducethesignificantlong‐termaestheticimpactsthatresultedfromthepastworkalongSegment3A.Therefore,thisoptionwasretainedforfurtherconsideration.
4.5 Option E – Reroute a Portion of Segment 3A along Casitas Pass Road on LWS Poles
OptionEwasidentifiedbythePEA.Underthisoption,the66‐kVconductorontheexistingLWSpoleslocatedintheShepardMesacommunity,southofShepardMesaDriveandwestofRinconRoad/SR150,wouldberelocatedwithintheCaliforniaDepartmentofTransportation(Caltrans)roadside2alongSR192/CasitasPassRoad(Figure2).ThenewroutewoulddivergefromtheexistingroutebyfollowingSR192fromitsjunctionwithSR150attheeasternterminusofSegment3AtotheSR192andShepardMesaRoadintersection.ThisnewroutewouldinstallLWSpolesoneitherthenorthorsouthsideofSR‐192.TheexistingdistributionfacilitiesthatarepresentlylocatedalongSR192wouldbetransferredtothenewsubtransmissionpolesifthenewLWSpoleswereinstalledonthesouthsideofSR192.IfthenewLWSpoleswereinstalledonthenorthsideofSR192,theexistingdistributionfacilitieswouldremaininplace,thusresultinginpolelinesalongbothsidesoftheroadway.TheapplicantwouldneedtoobtainnewROWsforthisoption.TheexistingtoppedwoodpolesintheShepardMesacommunitywouldremaininplacefordistributionandthird‐partylines.4.5.1 Consideration of CEQA Criteria Project Objectives OptionEwouldmeetallprojectandCountyofSantaBarbaraobjectives(Sections1.6.2and1.6.3).Feasibility OptionEwouldnotbefeasiblefromalegalperspective.ThewidthoftheCaltransROWintheareavaries,butgenerallyis40feetwide,whichiscenteredoveranapproximate24‐foot‐wideroad(Senet2013);therefore,thereisanapproximate7‐footroadsideoneachsideoftheroad.However,structureswouldhavetobeplacedatleast20feetfromtheouteredgeoftheroadbedinaccordancewithSection309.1(c)oftheHighwayDesignManual(Caltrans2013).Therefore,itwouldnotbefeasibletobuildthestructureswithintheCaltransROW.Environmental Effect Thelong‐termsignificantaestheticimpactoftheexistingsubtransmissionlinewouldnotbereduced,asthisoptionwouldtransfertheimpacttoviewshedsalongSR192/CasitasPassRoad.
2Ageneraltermdenotingtheareaadjoiningtheouteredgeoftheroadbedtotherightofwayline.
4 Option Descriptions and Determinations
09:002975.CP13.02 4‐7 July2014
4.5.2 Conclusion ELIMINATED.OptionEwouldmeetalloftheprojectandCountyofSantaBarbaraobjectives,butthisoptionwouldnotbefeasibleandwouldnotreduceasignificantimpact.Therefore,thisoptionwaseliminatedfromfurtherconsideration.
4.6 Option F – Reroute a Portion of Segment 3A along Casitas Pass Road on Wood Poles
OptionFwasidentifiedbytheCPUC.SimilartoOptionE,underthisoption,the66‐kVconductorontheexistingLWSpoleslocatedintheShepardMesacommunity,southofShepardMesaDriveandwestofRinconRoad/SR150,wouldberelocatedwithintheCaltransroadsidealongSR192/CasitasPassRoad(seeFigure2).ThenewroutewoulddivergefromtheexistingroutebyfollowingSR192fromitsjunctionwithSR192fromitsjunctionwithSR150attheeasternterminusofSegment3AtotheSR192andShepardMesaRoadintersection.ThisnewroutewouldinstallwoodpolesoneitherthenorthorsouthsideofSR192.TheexistingdistributionfacilitiesthatarepresentlylocatedalongSR192wouldbetransferredtothenewsubtransmissionpolesifthenewwoodpoleswereinstalledonthesouthsideofSR192.IfthenewwoodpoleswereinstalledonthenorthsideofSR192,theexistingdistributionfacilitieswouldremaininplace,thusresultinginpolelinesalongbothsidesoftheroadway.TheapplicantwouldneedtoobtainnewROWsforthisoption.TheexistingtoppedwoodpolesintheShepardMesacommunitywouldremaininplacefordistributionandthird‐partylines.4.6.1 Consideration of CEQA Criteria Project Objectives OptionFwouldmeetallprojectandCountyofSantaBarbaraobjectives(Sections1.6.2and1.6.3).Feasibility OptionFwouldnotbefeasiblefromalegalperspective.ThewidthoftheCaltransROWintheareavaries,butgenerallyis40feetwide,whichiscenteredoveranapproximate24‐footwideroad(Senet2013);therefore,thereisanapproximate7‐footroadsideoneachsideoftheroad.However,structureswouldhavetobeplacedatleast20feetfromtheouteredgeoftheroadbedinaccordancewithSection309.1(c)oftheHighwayDesignManual(Caltrans2013).Therefore,itwouldnotbefeasibletobuildthestructureswithintheCaltransROW.Environmental Effect OptionFwouldreducethesignificantlong‐termaestheticimpactsthatresultedfromthepastworkalongSegment3A.TheuseofwoodpoleswithintheShepardMesaareawouldreducetheimpacttovisualqualitythatresultedfromthepastworkalongSegment3A.4.6.2 Conclusion ELIMINATED.OptionFwouldmeetalloftheprojectandCountyofSantaBarbaraobjectivesandreducelong‐termsignificantaestheticimpacts,butthisoptionwouldnotbefeasible.Therefore,thisoptionwaseliminatedfromfurtherconsideration.
4 Option Descriptions and Determinations
09:002975.CP13.02 4‐8 July2014
Thispageintentionallyleftblank
09:002975.CP13.02 5‐1 July2014
Chapter 5
5 Summary of Screening Report
ThissectionpresentsasummaryoftheconclusionsfromSections3and4.Eachalternativeandoptionidentifiedbytheapplicant,CPUC,theCountyofSantaBarbara,andpublicarelistedinTable3alongwithasummaryofthescreeningresults.BasedontheanalysispresentedinthisScreeningReport,thefollowingalternativeswillbecarriedforwardforfullanalysisinChapter5oftheEIR:AlternativeA ReducetheScopeofWorkalongSegments1,2,and3AAlternativeB InstallSomeStructuresalongSegment4viaHelicopterThefollowingoptionswillbecarriedforwardforanalysisinChapter7oftheEIR:OptionA: PaintExistingLWSpolesandTSPalongSegment3AOptionB: ReplaceExistingLWSPoleswithWoodPolesalongSegment3AOptionC: RelocatethePortionofSegment3AthatTraversesAgriculturalLandintheShepard
MesaCommunitytoUndergroundConduitOptionD: RelocateSegment3AtoUndergroundConduit
5 Summary of Screening Report
09:002975.CP13.02 5‐2 July2014
Table 3: Summary of the Screening Report
Alternatives Carried Forward In PEA
Project Objectives
CountyObj. Feasible Environmental Effect of the Proposed Project
Obj. #1
Obj. #2
Obj. #3
Proposed Project Alternatives
A Reduce the Scope of Work along Segments 1, 2, and 3A
Yes No N/A Yes Would avoid potentially significant impacts on air quality from NOX and PM10 emissions.
B Install Some Structures along Segment 4 via Helicopter
Yes No N/A Yes Would avoid potentially significant impacts on biological and cultural resources.
C Underground Segments 3B and 4 No Yes N/A No Would avoid potentially significant aesthetic impacts.
Options for the Past Work along Segment 3A
A Paint Existing LWS Poles and TSP along Segment 3A
Yes No Yes Would reduce the significant long‐term aesthetic impacts that resulted from the past work along Segment 3A.
B Replace Existing LWS Poles with Wood Poles along Segment 3A
Yes No Yes Would reduce the significant long‐term aesthetic impacts that resulted from the past work along Segment 3A.
C Relocate the Portion of Segment 3A that Traverses Agricultural Land in the Shepard Mesa Community to Underground Conduit
Yes No Yes Would reduce the significant long‐term aesthetics impacts that resulted from the past work along Segment 3A.
D Relocate Segment 3A to Underground Conduit
Yes No Yes Would reduce the significant long‐term aesthetic impacts that resulted from the past work along Segment 3A.
E Reroute a Portion of Segment 3A along Casitas Pass Road on LWS Poles
No Yes No Would not reduce a significant long‐term that resulted from the past work along Segment 3A.
F Reroute a Portion of Segment 3A along Casitas Pass Road on Wood Poles
No No No Would reduce the significant long‐term aesthetic impacts that resulted from the past work along Segment 3A.
09:002975.CP13.02 6‐1 July2014
Chapter 6
6 References Caltrans(CaliforniaDepartmentofTransportation).2013.HighwayDesignManual.Website:
http://www.dot.ca.gov/hq/oppd/hdm/hdmtoc.htm.AccessedSeptember3,2013.PSCW(PublicServiceCommissionofWisconsin).2011.UndergroundElectricTransmissionLine.
MaySCE(SouthernCaliforniaEdisonCompany).2012.Proponent’sEnvironmentalAssessment:Santa
BarbaraCountyReliabilityProject(October26),asamendedbyresponsesfromSCEtoCPUCrequestsforadditionalinformation.
Senet,Steve.2013.CaliforniaDepartmentofTransportationDistrict5EncroachmentPermit
Engineer.PersonalConversationwithBonnyO’ConnorofEcologyandEnvironment,Inc.,onSeptember3,2013.