santa barbara county reliability project screening report ... h... · 09:002975.cp13.02 santa...

34
09:002975.CP13.02 SANTA BARBARA COUNTY RELIABILITY PROJECT SCREENING REPORT FOR THE PROPOSED PROJECT ALTERNATIVES AND OPTIONS FOR THE PAST WORK APPLICATION NO.: A.1210018 SCH NO.: 2013041070 July 2014 Revised May 2015 California Public Utilities Commission 505 Van Ness Avenue San Francisco, CA 94102 Contact: Jensen Uchida Prepared by: ECOLOGY AND ENVIRONMENT, INC. 505 Sansome Street, Suite 300 San Francisco, CA 94111

Upload: hatuong

Post on 30-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

09:002975.CP13.02

SANTA BARBARA COUNTY RELIABILITY PROJECT SCREENING REPORT FOR THE 

PROPOSED PROJECT ALTERNATIVES AND OPTIONS  FOR THE PAST WORK

APPLICATION NO.: A.12‐10‐018 

SCH NO.: 2013041070  

July 2014 Revised May 2015 

   

California Public Utilities Commission 505 Van Ness Avenue 

San Francisco, CA  94102 Contact: Jensen Uchida 

 

Prepared by:  

ECOLOGY AND ENVIRONMENT, INC. 505 Sansome Street, Suite 300 

San Francisco, CA  94111 

Thispageintentionallyleftblank

09:002975.CP13.02 iii July2014

       able of Contents T Section Page

1  Introduction .................................................................................. 1-1 1.1  SummaryoftheProposedProject.....................................................................................................1‐1 1.2  PastWorkintheProjectArea..............................................................................................................1‐1 1.3  ScopeoftheEnvironmentalImpactReport...................................................................................1‐3 1.4  AlternativesversusOptions.................................................................................................................1‐3 

1.4.1  Alternatives.................................................................................................................................1‐4 1.4.2  Options..........................................................................................................................................1‐4 

1.5  PurposeoftheScreeningReport........................................................................................................1‐4 1.6  PurposeandObjectivesoftheProposedProject.........................................................................1‐4 

1.6.1  Purpose.........................................................................................................................................1‐4 1.6.2  Objectives(DevelopedbytheCPUC)...............................................................................1‐5 1.6.3  CountyofSantaBarbaraSegment3AObjective.........................................................1‐5 1.6.4  Applicant’sStatedObjectives..............................................................................................1‐5 

2  Overview of Evaluation Process ..................................................... 2-1 2.1  ScreenMethodology................................................................................................................................2‐1 2.2  CEQACriteria..............................................................................................................................................2‐1 2.3  Feasibility.....................................................................................................................................................2‐1 2.4  PotentialtoAvoidorLessenSignificantEnvironmentalEffects..........................................2‐2 

2.4.1  SignificantEnvironmentalEffectsoftheProposedProject...................................2‐2 2.4.2  SignificantEnvironmentalEffectsofthePastWorkalongSegment3A...........2‐2 

2.5  NoProjectAlternative.............................................................................................................................2‐3 

3  Alternative Descriptions and Determinations .................................. 3-1 3.1  AlternativeA–ReducetheScopeofWorkalongSegments1,2,and3A..........................3‐1 

3.1.1  ConsiderationofCEQACriteria..........................................................................................3‐1 3.1.2  Conclusion...................................................................................................................................3‐1 

3.2  AlternativeB–InstallSomeStructuresalongSegment4viaHelicopter.........................3‐2 3.2.1  ConsiderationofCEQACriteria..........................................................................................3‐2 3.2.2  Conclusion...................................................................................................................................3‐2 

3.3  AlternativeC–UndergroundSegments3Band4.......................................................................3‐2 3.3.1  ConsiderationofCEQACriteria..........................................................................................3‐2 3.3.2  Conclusion...................................................................................................................................3‐3 

4  Option Descriptions and Determinations ........................................ 4-1 

4.1  OptionA–PaintExistingLWSPolesandTSPalongSegment3A........................................4‐1 4.1.1  ConsiderationofCEQACriteria..........................................................................................4‐1 4.1.2  Conclusion...................................................................................................................................4‐2 

4.2  OptionB–ReplaceExistingLWSPolesandTSPwithWoodPolesalongSegment3A..................................................................................................................................................4‐2 4.2.1  ConsiderationofCEQACriteria..........................................................................................4‐2 4.2.2  Conclusion...................................................................................................................................4‐2 

Table of Contents 

09:002975.CP13.02 iv July2014

4.3  OptionC–RelocatethePortionofSegment3AthatTraversesAgriculturalLandintheShepardMesaCommunitytoUndergroundConduit........................................4‐2 4.3.1  ConsiderationofCEQACriteria..........................................................................................4‐4 4.3.2  Conclusion...................................................................................................................................4‐5 

4.4  OptionD–RelocateSegment3AtoUndergroundConduit....................................................4‐5 4.4.1  ConsiderationofCEQACriteria..........................................................................................4‐5 4.4.2  Conclusion...................................................................................................................................4‐6 

4.5  OptionE–RerouteaPortionofSegment3AalongCasitasPassRoadonLWSPoles................................................................................................................................................................4‐6 4.5.1  ConsiderationofCEQACriteria..........................................................................................4‐6 4.5.2  Conclusion...................................................................................................................................4‐7 

4.6  OptionF–RerouteaPortionofSegment3AalongCasitasPassRoadonWoodPoles................................................................................................................................................................4‐7 4.6.1  ConsiderationofCEQACriteria..........................................................................................4‐7 4.6.2  Conclusion...................................................................................................................................4‐7 

5  Summary of Screening Report ........................................................ 5-1 

6  References .................................................................................... 6-1 

09:002975.CP13.02 v July2014

     ist of Figures L 

     ist of Tables L Table Page Table1:SummaryofPotentiallySignificantEffectsoftheProposedProject.......................................................2‐2 

Table2:Long‐TermSignificantEffectsofPastWorkalongSegment3A................................................................2‐3 

Table3:SummaryofScreeningReport.................................................................................................................................5‐2 

 

Figure Page Figure1:ProjectLocationandElectricalNeedsArea.......................................Error!Bookmarknotdefined.3 

Figure2:OptionC,OptionE,andOptionFLocations......................................................................................................4‐3 

 

List of Tables and Figures 

09:002975.CP13.02 vi July2014

Thispageintentionallyleftblank

09:002975.CP13.02 vii July2014

     ist of Abbreviations and Acronyms L 

applicant SouthernCaliforniaEdisonCompany

Caltrans CaliforniaDepartmentofTransportation

CDP CoastalDevelopmentPermit

CEQA CaliforniaEnvironmentalQualityAct

CPUC CaliforniaPublicUtilitiesCommission

EIR EnvironmentalImpactReport

ENA ElectricalNeedsArea

GIS geographicinformationsystem

GO GeneralOrder

kV kilovolt

LST latticesteeltower

LWS lightweightsteel

NMFS NationalMarineFisheriesService

PEA Proponent’sEnvironmentalAssessment

proposedproject SantaBarbaraCountyReliabilityProject

PTC PermittoConstruct

ROW right‐of‐way

SCE SouthernCaliforniaEdison Company

SR StateRoute

TSP tubularsteelpole

List of Abbreviations and Acronyms 

09:002975.CP13.02 viii July2014

Thispageintentionallyleftblank

09:002975.CP13.02 1‐1 July2014

1 Introduction SouthernCaliforniaEdisonCompany(SCEortheapplicant)filedanapplication(A.12‐10‐018)withtheCaliforniaPublicUtilitiesCommission(CPUC)foraPermittoConstruct(PTC)theSantaBarbaraCountyReliabilityProject(theproposedproject)onOctober26,2012.TheproposedprojectincludesrebuildingandupgradingaportionofSCE’ssubtransmissioninfrastructureinSantaBarbaraandVenturacountiesbetweenthecitiesofSanBuenaventura(Ventura)andCarpinteria(Figure1).

1.1  Summary of the Proposed Project Thefollowingactivitiesaremajorcomponentsoftheproposedproject: Reconstructionofexisting66‐kilovolt(kV)subtransmissionfacilities,primarilythoselocated

withinthecurrentutilityrights‐of‐way(ROWs)betweenthe“Y”(i.e.,thepointalongthecorridorwhereSegments2,3B,and4converge)inVenturaCountyandtheCarpinteriaSubstationinSantaBarbaraCounty(Segments4and3B);

Installationofmarkerballsonoverheadwire; ModificationofsubtransmissionandsubstationequipmentwithintheCarpinteriaSubstation,

CasitasSubstation,andSantaClaraSubstation; Replacementoflineprotectionrelayswithinexistingsubstationequipmentroomsorcabinetsat

theGettySubstation,GoletaSubstation,OrtegaSubstation,andSantaBarbaraSubstation; InstallationoftelecommunicationsfacilitiesalongSegments1,2,and4andattheCarpinteria

Substation,CasitasSubstation,SantaClaraSubstation,andVenturaSubstation; InstallationofafaultreturnconductoronsubtransmissionstructuresalongSegment3A;and RemovalofsubtransmissioninfrastructurefoundationsinSegments1and2.

1.2  Past Work in the Project Area In1999,SCEcommencedconstructionintheprojectareaonSegments1,2,and3Aandseveralsurroundingsubstations(Figure1).Atthetime,SCEbelievedthattheproposedupgradestosubtransmissionlinesinVenturaandSantaBarbaracountieswereexemptfrompermittingpursuanttoCPUCGeneralOrder(GO)131‐DandtheCaliforniaCoastalAct(CaliforniaPublicResourcesCodeSection30610)becausetheywereconsidered“equivalentfacilitiesorstructures.”However,in2004,residentsoftheShepardMesaareanearCarpinteriaraisedconcernsthatthenewstructuresinSegment3Aweredifferentinappearancefromthepreviousstructures.TheCaliforniaCoastalCommissionandCountyofSantaBarbaraCoastalProgramstaffissuedaStopWorkordertoSCEafterstaffdeterminedthatworkwithintheCoastalZonedidnotqualifyforanexemptionfromaCoastalDevelopmentPermit(CDP)andthataCaliforniaEnvironmentalQualityAct(CEQA)reviewwasrequired.Similarly,theCPUCdeterminedthatthepastworkshouldnothavebeenconsideredexemptfromGO131‐D,andsimilarworkconductedbytheapplicantinthefuturewouldrequireaCEQAreviewandaPTC.

1 Introduction 

09:002975.CP13.02 1‐2 July2014

InsertFigure1

1 Introduction 

09:002975.CP13.02 1‐3 July2014

Between1999and2004,SCEhadalreadyconductedthefollowingunpermittedactivities: SomesubstationmodificationswerecompletedattheCarpinteria,Goleta,IslaVista,Ortega,and

SantaClarasubstations; Newsubtransmissionstructuresanda66‐kVconductorwereinstalledinSegment1fromthe

SantaClaraSubstationtotheCasitasSubstation,andtheexisting66‐kVconductorwasremoved; Newsubtransmissionstructuresanda66‐kVconductorwereinstalledinSegment2from

CasitasSubstationtothe“Y”locatednearCasitasPass,justwestofLakeCasitasinVenturaCounty,andtheexisting66‐kVconductorwasremoved;

Newsubtransmissionstructuresanda66‐kVconductorwereinstalledinSegment3AfromtheCarpinteriaSubstationtotheSantaBarbaraCounty/VenturaCountyline,andexistingwoodsubtransmissionstructureswereremovedortopped;

SubtransmissionstructuresinSegments1and2werepartiallyremoved;and Twofootingsfortubularsteelpoles(TSP),twolightweightsteel(LWS)H‐frames,oneLWSpole,

andtwoswitchesattheGettyTaplocationwereinstalled,andtwowoodH‐framesandonewoodpolewereremoved.

1.3  Scope of the Environmental Impact Report InaccordancewithCEQA,theCPUCisservingastheLeadAgencyfortheenvironmentalreviewprocessandispreparinganEnvironmentalImpactReport(EIR)toevaluatetheenvironmentalimpactsoftheproposedproject.TheEIRwillalsodiscussandanalyzeareasonablerangeofalternativestotheproposedprojectinordertoidentifytheenvironmentallysuperioralternative.TheCPUCwillrelyontheenvironmentalassessmentoftheproposedprojectintheEIRfortheapprovalprocessofSCE’sPTCapplication.CEQAdoesnotrequirereviewofpriorunpermittedactivity,suchasthepastworkintheprojectarea(Fatv.CountyofSacramento[2002]97Cal.App.4th1270;Riverwatchv.CountyofSanDiego[1999]76Cal.App.4th1428).However,theCountyofSantaBarbara,asaResponsibleAgencyunderCEQA,hasrequestedthattheCPUCEIRincludesomelevelofanalysisrelatedtopastworkwithintheCoastalZone(Segment3A).Therefore,theEIRwillidentifylong‐termsignificantimpactsthathaveresultedfromthereconductoringofthesubtransmissionlinealongSegment3Abycomparingcurrentenvironmentalandregulatoryconditionstoconditionsthatexistedatthetimetheworkcommencedin1999.TheanalysisisbasedoninformationthatwascompiledfromtheProponent’sEnvironmentalAssessment(PEA),theapplicant’sresponsestodatarequests,previousfieldinvestigationsconductedbytheapplicant,andestimatesbasedonavailablegeographicinformationsystem(GIS)data.Giventheelapsedtimebetweenpreviousactivitiesandthepresentproposedproject,agoodfaitheffortwasmadetogatherareasonablelevelofdatatocharacterizeimpacts;however,environmentalconditionspriortothepastworkalongSegment3Aareunknownformanyresourceareasorwouldbeunreasonablyoneroustoidentify.TheEIRwillalsodiscussandanalyzeoptionsforreducinganylong‐termsignificantimpactsthatresultedfromthepastworkalongSegment3A.TheCountyofSantaBarbarawillrelyontheenvironmentalassessmentoftheproposedproject,aswellasthelimitedassessmentofimpactsthatresultedfromthepastwork,inordertoapprovearetroactiveCDP.

1.4  Alternatives versus Options Thissectionclarifiesthedifferencebetweentheterms“Alternative”and“Option”forthepurposesofthisScreeningReport.

1 Introduction 

09:002975.CP13.02 1‐4 July2014

1.4.1  Alternatives AlternativeswereidentifiedtoaddresssignificantimpactsoftheproposedprojectandarerequiredunderCEQAGuidelines.CEQAGuidelinesSection15126.6(a)states:

AnEIRshalldescribeareasonablerangeofalternativestotheproject,ortothelocationoftheproject,whichwouldfeasiblyattainmostofthebasicobjectivesoftheprojectbutwouldavoidorsubstantiallylessenanyofthesignificanteffectsoftheproject,andevaluatethecomparativemeritsofthealternatives.AnEIRneednotconsidereveryconceivablealternativetoaproject.Ratheritmustconsiderareasonablerangeofpotentiallyfeasiblealternativesthatwillfosterinformeddecisionmakingandpublicparticipation.

TheEIRwillevaluateandcomparealternativestoidentifytheenvironmentallysuperioralternative.1.4.2  Options Duetothepastworkintheprojectareaanditsrelationshiptotheproposedproject,modificationstotheproposedprojectthatcouldreducethelong‐termsignificantimpactsofthepastworkalongSegment3Ahavebeenidentified.Projectmodifications,or“options,”aresimilartoalternativesinthattheyareidentifiedandscreenedusingsimilarcriteria;however,theterm“option”hasbeenusedtodifferentiatethemfromaCEQAalternative.AsdiscussedinSection1.3,CEQAdoesnotrequiretheevaluationofunpermittedactivities;however,attherequestoftheCountyofSantaBarbara,theEIRwillevaluatetheenvironmentalimpactsofproposedprojectoptions.TheCPUCwillnotincorporateorimplementanyoftheoptions.Rather,theoptionswouldbeimplementedatthediscretionoftheCountyaspartoftheirCDPissuance.

1.5  Purpose of the Screening Report ThisScreeningReportdocuments: Therangeofalternatives/optionsidentifiedandevaluated; Theapproachandmethodsusedforscreeningeachalternative/option;and Adescriptionofeachalternative/optionandtheresultsofthescreeningevaluation(i.e.,the

alternativeseliminatedfromfurtherconsiderationorcarriedforwardforfullanalysisintheEIR).

ThisScreeningReportwillsupplementtheinformationpresentedinChapter3oftheDraftEIRregardingprojectalternatives.AlternativestotheproposedprojectwereidentifiedbytheCPUC,theCountyofSantaBarbara,theapplicantaspartofthePEA,andthepublicduringpublicscoping.Thescreeningprocessidentifiedandevaluatedthreepotentialalternativestotheproposedproject,asdescribedinChapter3ofthisScreeningReport.ThisScreeningReportwillalsosupplementtheinformationpresentedinChapter7oftheDraftEIRregardingprojectoptions.OptionsformodifyingtheproposedprojectwereidentifiedbytheCPUC,theapplicantaspartofthePEA,theCountyofSantaBarbara,andthepublicduringpublicscoping.Thescreeningprocessidentifiedandevaluatedsevenpotentialprojectoptionsthatcouldmitigatethelong‐termsignificantimpactsofthepastworkalongSegment3A,asdescribedinChapter4ofthisScreeningReport.

1.6  Purpose and Objectives of the Proposed Project 1.6.1  Purpose  ThepurposeoftheproposedprojectistoensuretheavailabilityofsafeandreliableelectricalservicetohelpmeetcustomerelectricaldemandwithintheElectricalNeedsArea(ENA)duringemergencyconditions(Figure1).

1 Introduction 

09:002975.CP13.02 1‐5 July2014

1.6.2  Objectives (Developed by the CPUC) Aproject’sstatementofobjectivesdescribestheunderlyingpurposeoftheprojectandthereasonsforundertakingtheproject.Tofulfillthisrequirement,threeobjectivesweredevelopedbytheCPUC,withconsiderationoftheobjectivespresentedinthePEA(seeSection1.6.4).Theobjectives,asdefinedbytheCPUC,wereusedasabasisforthedevelopmentofareasonablerangeofalternatives,aswellasoptionsthatwouldmodifytheproposedprojectasdescribedinSection1.4.2.Thebasicobjectivesoftheproposedprojectareto:1. Providelong‐termreliabilityandcontinuityofservicetotheENA;2. Enhanceoperationalflexibilitybyprovidingtheabilitytotransfertheelectricloadbetween

localsubstationsandremoveexisting220‐kVor66‐kVlinesfromservicewhenneededformaintenancepurposes;and

3. Increaseenergyefficiencyofthe66‐kVsubtransmissionline.1.6.3  County of Santa Barbara Segment 3A Objective AsdescribedinSection1.4.2,althoughnotrequiredbyCEQA,theCountyofSantaBarbarahasanadditionalobjectiverelatedtotheirissuanceofaretroactiveCDP.Inordertobecarriedforwardforconsideration,inadditiontomeetingthemajorityoftheCPUC’sprojectobjectivesinSection1.6.2,aprojectoptionmust:1. Reducealong‐termsignificantimpact1thatresultedfromthepast,unpermittedworkalong

Segment3AintheCoastalZonethatoccurredbetween1999and2004.

1.6.4  Applicant’s Stated Objectives TheobjectiveslistedinSection1.6.2and1.6.3havebeenusedtoscreenalternativesandoptions;however,theapplicantalsoidentifiedthefollowingfourobjectivesinthePEA,whicharelistedfordisclosurepurposes:1. Providelong‐termreliabilityandcontinuityofservicetotheENAintheeventofanatural

disasterorotheroccurrencethataffectsthe220kVtransmissionsystemservingthearea;2. Enhanceoperationalflexibilitybyprovidingtheabilitytotransfertheelectricloadbetween

localsubstationsandremoveexisting220‐kVor66‐kVlinesfromservicewhenneededformaintenancepurposes;

3. Totheextentpracticable,useexistingROWsandfacilitiesconstructedtodatetominimize:a. Environmentalimpacts,b. Constructionschedule,andc. Projectcostandimpactonratepayers;

4. DesignandconstructtheprojectinconformancewithSCE’scurrentengineering,design,andconstructionstandardsforsubstation,transmission,subtransmission,anddistributionsystemprojects(SCE2012).

1Long‐termsignificantimpactsbasedonanindependentassessmentusingCEQAcriteria.

1 Introduction 

09:002975.CP13.02 1‐6 July2014

Thispageintentionallyleftblank

09:002975.CP13.02 2‐1 July2014

2 Overview of Evaluation Process 

2.1  Screen Methodology Theevaluationprocessforthealternativesandoptionsincludeathree‐stepscreeningprocess: Step1:Clarifythedescriptionofthealternative/optiontoallowforcomparativeevaluation; Step2:Evaluatethealternative/optionbycomparingitwiththeproposedprojectandwiththe

CEQAcriteriaforalternatives(Sections2.2through2.4,below).Inaddition,althoughCEQAGuidelinesdonotrequiretheconsiderationofoptionsforreducingimpactsofunpermittedwork,asdescribedinSection1.3and1.6.3,projectoptionsarealsoevaluatedaccordingtotheCEQAcriteria;and

Step3:Determinethesuitabilityofeachalternative/optionforfullanalysisintheEIRbasedontheresultsofStep2.Ifthealternative/optionisunsuitable,eliminateitfromfurtherconsideration.

2.2  CEQA Criteria CEQAGuidelines(Sections15126.6(a)and(d))requireanEIRtodescribeareasonablerangeofpotentiallyfeasiblealternativesandtoincludesufficientinformationabouteachalternativetoallowmeaningfulevaluation,analysis,andcomparisonwiththeproposedproject.TocomplywithCEQArequirementsfortheevaluationofalternatives,eachalternativeoroptionidentifiedwasevaluatedaccordingtothefollowingcriteria: Wouldthealternative/optionaccomplishallormostoftheprojectobjectives? Wouldthealternative/optionbepotentiallyfeasible(fromaneconomic,legal,andtechnological

perspective)? Wouldthealternativeavoidorsubstantiallylessenanysignificanteffectsoftheproposed

project(includingconsiderationofwhetherthealternative,itself,couldcreatesignificanteffectspotentiallygreaterthanthoseoftheproposedproject)?Inaddition,forprojectoptions,wouldtheoptionreduceanysignificantlong‐termeffectsofpastworkalongSegment3A?

CEQAGuidelinesrequiretheconsiderationofalternativescapableofeliminatingorreducingsignificantenvironmentaleffectseventhoughtheymay“impedetosomedegreetheattainmentofprojectobjectivesorwouldbemorecostly”(Section15126.6(b)).Inthecaseofprojectoptions,theoptionswouldnotreduceasignificantenvironmentaleffectoftheproposedprojectandmayinsomecasesresultinatemporaryincreaseinshort‐termconstruction‐relatedimpacts.However,inordertomeettheCountyofSantaBarbaraobjective,atemporary,lessthansignificantconstruction‐relatedimpactisconsideredacceptableiftheoptionwouldresultinareductionofalong‐termsignificantimpact.

2.3  Feasibility AccordingtoCEQAGuidelines(Section15126.6(f)(1)),amongthefactorsthatmaybetakenintoaccountwhenaddressingthefeasibilityofalternativesincludesitesuitability,economicviability,

2  OverviewofEvaluationProcess 

09:002975.CP13.02 2‐2 July2014

availabilityofinfrastructure,generalplanconsistency,otherplansorotherregulatorylimitations,jurisdictionalboundaries,andproponentcontroloveralternativesites.Forthescreeninganalysis,thepotentialfeasibilityofalternativeswasassessedusingthefollowingconsiderations: TechnicalFeasibility.Isthealternativefeasiblefromatechnologicalperspective,considering

availabletechnology?Arethereanyconstruction,operation,ormaintenanceconstraintsthatcannotbeovercome?

LegalFeasibility.Dolegalprotectionsonlandsprecludeorsubstantiallylimitthefeasibilityofpermittinghigh‐voltagetransmissionlinesandsubstations?Doregulatoryrestrictionssubstantiallylimitthefeasibilityorsuccessfulpermittingofhigh‐voltagetransmissionlinesandsubstations?Isthealternativeconsistentwithregulatorystandardsfortransmissionsystemdesign,operation,andmaintenance?

EconomicFeasibility.Isthealternativesocostlythatitsimplementationwouldbeprohibitive?

2.4  Potential to Avoid or Lessen Significant Environmental Effects CEQArequiresanEIRtodescribealternativesthatwould“avoidorsubstantiallylessenanyofthesignificanteffectsoftheproject”(CEQAGuidelinesSection15126.6(a)).2.4.1  Significant Environmental Effects of the Proposed Project Atthescreeningstage,itisnotpossibletoevaluatealloftheeffectsofalternativesincomparisontotheproposedprojectwithabsolutecertainty,anditmaynotbepossibletoquantifytheeffects.However,itispossibletoidentifyelementsofanalternativethatarelikelytocreateanimpactandrelatethem,totheextentpossible,togeneralconditionsintheproposedprojectarea.Table1presentsasummaryofthepotentiallysignificanteffectsoftheproposedproject.ThistablewaspreparedpriortocompletionoftheEIRanddoesnotincludethedetailedanalysisthatisincludedinChapter4,“EnvironmentalAnalysis.”Table 1: Summary of Potentially Significant Effects of the Proposed Project 

Resource  Potentially Significant Effect 

Aesthetics  Operation of the project components could result in impacts on visual quality within viewsheds of Segments 3B and 4. 

Air Quality  Construction could result in an exceedance of criteria air pollutants above established thresholds. 

Biological Resources  Construction of the project could result in impacts on steelhead trout designated critical habitat, arroyo chub, and avian species. 

Cultural Resources  Construction of some project elements could result in impacts on cultural resources. 

Traffic  Temporary lane closures along Highway 33 and other streets in the project area could result in impacts related to traffic and transportation. 

2.4.2  Significant Environmental Effects of the Past Work along Segment 3A TheCPUChasidentifiedsignificantlong‐termimpactsassociatedwithaestheticsandlandusethatresultedfromSCEconstructionactivitiesalongonSegment3Abetween1999and2004.Basedonthelimitedavailabledata,thepastworkresultedinnootherlong‐termsignificantimpacts.Table2showsthelong‐termsignificantimpactsthatresultedfromSCE’sconstructionactivities.

2  OverviewofEvaluationProcess 

09:002975.CP13.02 2‐3 July2014

Table 2: Long‐Term Significant Effects of Past Work along Segment 3A 

Resource  Long‐Term Significant Effect 

Aesthetics  The replacement of five wood poles within the viewshed of State Route (SR) 150 with four LWS poles and one TSP resulted in a significant long‐term impact on the scenic resources within an eligible state scenic highway from the color and size of the new poles. 

The replacement of 49 wood poles with 49 LWS poles and one TSP resulted in a significant long‐term impact on the visual character of the site and its surroundings and from the color and size of the new poles. 

Land Use  Construction and operation of the existing subtransmission line along Segment 3A conflicts with County of Santa Barbara Article II, Coastal Zoning Ordinance, because applicable approvals and permits were not obtained at the time of construction prior to 2004. 

2.5  No Project Alternative CEQArequiresthataNoProjectAlternativebeconsideredinEIRs(CEQAGuidelinesSection15126.6(e)).ThepurposeofdescribingandanalyzingaNoProjectAlternativeistoallowdecision‐makerstocomparetheeffectsofapprovingtheproposedprojectwiththeeffectsofnotapprovingtheproposedproject.BecausefullconsiderationofaNoProjectAlternativeisrequiredbyCEQA,theNoProjectAlternativewillbeevaluatedintheEIR;however,theNoProjectAlternativeisnotevaluatedinthisScreeningReport.

2  OverviewofEvaluationProcess 

09:002975.CP13.02 2‐4 July2014

Thispageintentionallyleftblank

09:002975.CP13.02 3‐1 July2014

3 Alternative Descriptions and Determinations 

Thealternativesscreeningprocessidentifiedandevaluatedthreepotentialalternativestotheproposedproject.ThissectiondescribeseachofthealternativesidentifiedandexplainswhytheywereretainedforfurtherconsiderationintheEIRorwereeliminated.EachalternativethatwasdeterminedtomeetCEQAorothercriteriaforalternatives(Sections2.2through2.4)wasretainedforfurtherconsiderationintheEIR.ThisScreeningReportevaluatesthefollowingalternativestotheproposedproject:AlternativeA. ReducetheScopeofWorkalongSegments1,2,and3AAlternativeB. InstallSomeStructuresalongSegment4viaHelicopterAlternativeC. UndergroundSegments3Band4

3.1  Alternative A – Reduce the Scope of Work along Segments 1, 2, and 3A AlternativeAwasidentifiedbytheCPUC.Underthisalternative,theexisting30foundationsand15toppedsubtransmissionwoodpolesalongSegments1,2,and3Awouldnotberemoved.Allremainingsegments,substationsupgrades,andothermajorworkwouldbeconstructedasdescribedintheproposedproject.3.1.1  Consideration of CEQA Criteria Project Objectives  AlternativeAwouldmeetallprojectobjectives(Section1.6.2).Feasibility  AlternativeAwouldbefeasiblefromatechnical,legal,andeconomicperspective.Environmental Effect AlternativeAwouldavoidorreducepotentiallysignificanteffectsoftheproposedproject(Table1).AllowingthetoppedpolesandabandonedstructuresfromthepastworktoremaininplacewouldreducetheamountofgrounddisturbancethatwouldoccurduringconstructionandwouldreducetheamountofNOXandPM10emissionsproducedduringconstruction.Leavingthetoppedpolesandabandonedstructuresinplacewouldnotcreateanyimpacttothevisualquality,asthesestructuresarepartofthe2012environmentalbaselineconditions.3.1.2  Conclusion  RETAINED.AlternativeAwouldbefeasible,meetallprojectobjectives,andwouldavoidorsubstantiallylessenpotentialsignificantimpactsoftheproposedprojectonairquality.Therefore,thisalternativewasretainedforfurtherconsiderationintheEIR.

3  Alternative Descriptions and Determinations 

09:002975.CP13.02 3‐2 July2014

3.2  Alternative B – Install Some Structures along Segment 4 via Helicopter AlternativeBwasidentifiedbytheCPUC.Underthisalternative,equipment,materials,andworkerswouldbedeliveredtoConstructionSites116through125viahelicopter.Subtransmissionstructuresandconductorswouldbeinstalledwithhelicopterassistance.ThisalternativewouldavoidtheneedtoperformroadimprovementswithinNationalMarineFisheriesService(NMFS)‐designatedcriticalhabitatforsteelheadtroutorwithinstreamsthatdrainintoNMFS‐designatedcriticalhabitat.Allremainingsegments,substationsupgrades,andothermajorworkwouldbeconstructedasdescribedintheproposedproject.3.2.1  Consideration of CEQA Criteria Project Objectives  AlternativeBwouldmeetallprojectobjectives(Section1.6.2).Feasibility  AlternativeBwouldbefeasiblefromatechnical,legal,andeconomicperspective.Environmental Effect AlternativeBwouldavoidorreducepotentiallysignificanteffectsoftheproposedproject(Table1).Accessingconstructionsites116through125withahelicopterwouldavoidpotentiallysignificantimpactstoNMFS‐designatedcriticalhabitatforsteelheadtroutfromtheestablishmentofaccessroads.Thereducedamountofconstructionwouldalsolessenpotentialsignificanteffectstoculturalresources.AlthoughthisalternativemayreducePM10emissionsduringconstruction,itwouldlikelyresultingreaterNOXemissionsfromincreasedhelicopteroperations. 3.2.2  Conclusion  RETAINED.AlternativeBwouldbefeasible,meetallprojectobjectives,andwouldavoidorsubstantiallylessenpotentialsignificantimpactsoftheproposedprojectonbiologicalandculturalresources.Therefore,thisalternativewasretainedforfurtherconsiderationintheEIR.

3.3  Alternative C – Underground Segments 3B and 4 AlternativeCwasidentifiedbythePEA.Underthisalternative,the66‐kVsubtransmissionlinealongSegments3Band4wouldbeinstalledinnewundergroundconduitwithintheexistingROW.Theexistinglatticesteeltowers(LSTs)andwoodguystubsalongSegment3Band4wouldberemoved.Theapplicantmayneedtoobtainnewencroachmentpermits,asmanyoftheexistingROWsonlyprovidesoverheadaccess.Allremainingsegments,substationsupgrades,andothermajorworkwouldbeconstructedasdescribedintheproposedproject.3.3.1  Consideration of CEQA Criteria Project Objectives  AlternativeCwouldmeetmostoftheprojectobjectives(Section1.6.2).ProjectObjective3(increaseenergyefficiencyofthe66‐kVsubtransmissionline)wouldnotbemetunderthisalternative.Feasibility  AlternativeCwouldnotbefeasiblefromatechnicalandeconomicperspective.Thesteep,mountainous,androckyterrainintheprojectareamakesthisalternativetechnicallyinfeasible.Insomeareas,thecurrentlinespansgulliesandhilltopswherethereiscurrentlylimitedspaceforlaydownareasandequipment.Itwouldbeinfeasibletopositiontrenchingandblastingequipmentintheseareas.Inaddition,thecosttoundergroundasubtransmissionlineis4to14timesthecostofbuildingatransmissionlineaboveground(notincludingthecostofobtainingROWs)(PSCW2011).ThecostofundergroundinginsuchterrainwouldbeprohibitivelyexpensivetoSCE.

3  Alternative Descriptions and Determinations 

09:002975.CP13.02 3‐3 July2014

Environmental Effect AlternativeCwouldavoidpotentiallysignificantlong‐termimpactsonthevisualqualityfromviewsofSegment4alongStateRoute(SR)192,whichisbeingconsideredbytheCityofCarpinteriaforfuturedesignationasascenichighway.Additionally,thisalternativewouldavoidcreatingvisualcontrastinthearea.Duringconstruction,thisalternativewouldtemporarilyincreaseenvironmentaleffectsassociatedwithairemissions,noise,agriculture,andbiologicalandculturalresources.Additionally,thehillsaboveCarpinteriacontaindocumentedculturalresources.Theblasting,trenching,andlargeamountofvegetationremovalthatwouldberequiredforimplementingthisalternativewouldresultinagreaterriskofimpactstobothdocumentedandundocumentedculturalresourcesthantheproposedproject.Inaddition,blastingandtrenchingalongsteepslopescouldleadtogreaterslopeinstabilityissuesandgeologichazardsinboththeshort‐andlong‐term.Impactsduetogeologichazardscouldbeconsideredsignificant.3.3.2  Conclusion ELIMINATED.AlternativeCwouldmeetmostoftheprojectobjectives,andwouldlessenasignificantimpactoftheproposedprojectonaesthetics;however,thisalternativeiseconomicallyandtechnicallyinfeasibleandcouldleadtoasignificantimpactrelatedtogeologichazards.Therefore,thisalternativewaseliminatedfromfurtherconsideration.

3  Alternative Descriptions and Determinations 

09:002975.CP13.02 3‐4 July2014

Thispageintentionallyleftblank

09:002975.CP13.02 4‐1 July2014

4 Option Descriptions and Determinations 

Thescreeningprocessidentifiedandevaluatedsevenprojectoptionsthatwouldreducethesignificantlong‐termimpactsofthepastworkalongSegment3Aviamodificationstotheproposedproject.ThissectiondescribeseachoftheoptionsidentifiedandexplainswhytheywereretainedforfurtherconsiderationintheEIRorwereeliminated.EachoptiondeterminedtomeettheCEQAcriteria(Sections2.2through2.4)wasretainedforfurtherconsiderationintheEIR.TheEnvironmentalEffectdiscussionforeachoptionbelowdescribestheenvironmentaleffectsfromtheremovaloftheexistingsubtransmissionline,asappropriate,andtheconstructionoftheprojectoption.TheEnvironmentalEffectdiscussiondoesnotincludeimpactsfromconstructionoftheexistingsubtransmissionlinebecausetheenvironmentaleffectsarethesameforeveryoptionandaredescribedinChapter7oftheEIR.ThisScreeningReportevaluatesthefollowingoptionsforSegment3Aoftheproposedproject:OptionA. PaintExistingLWSPolesandTSPalongSegment3AOptionB. ReplaceExistingLWSPoleswithWoodPolesalongSegment3AOptionC. RelocatethePortionofSegment3AthatTraversesAgriculturalLandintheShepard

MesaCommunitytoUndergroundConduitOptionD. RelocateSegment3AtoUndergroundConduitOptionE. SubmitPoleSpecificationsandPlansforPoles182and183totheCountyofSanta

BarbaraOptionF. RerouteaPortionofSegment3AalongCasitasPassRoadonLWSPolesOptionG. RerouteaPortionofSegment3AalongCasitasPassRoadonWoodPoles

4.1  Option A – Paint Existing LWS Poles and TSP along Segment 3A OptionAwasidentifiedbytheCPUC.Underthisoption,theexistingLWSpolesandTSPalongSegment3Awouldbepaintedtoreducecontrastwiththesurroundingenvironmentalsetting.4.1.1  Consideration of CEQA Criteria Project Objectives  OptionAwouldmeetallprojectandCountyofSantaBarbaraobjectives(Sections1.6.2and1.6.3).Feasibility  OptionAwouldbefeasiblefromatechnical,legal,andeconomicperspective.Environmental Effect OptionAwouldreducethesignificantlong‐termaestheticimpactthatresultedfromthereplacementofwoodpoleswithtallerLWSpolesandaTSPalongSegment3A(Table2).Noneofthestructuresinstalledbetween1999and2004alongSegment3Awouldneedtoberemoved.Onlypaintingactivitieswouldneedtobeconductedtocompletethisoption.Paintingactivitieswouldhavenegligibleenvironmenteffectsonairquality,traffic,andbiologicalresources.

4  Option Descriptions and Determinations 

09:002975.CP13.02 4‐2 July2014

4.1.2  Conclusion  RETAINED.OptionAwouldbefeasible,meetallprojectandCountyofSantaBarbaraobjectives,andreducethesignificantlong‐termaestheticimpactthatresultedfromthepastworkalongSegment3A.Therefore,thisoptionwasretainedforfurtherconsiderationintheEIR.

4.2  Option B – Replace Existing LWS Poles and TSP with Wood Poles along Segment 3A 

OptionBwasidentifiedbytheCPUC.Underthisoption,theexistingLWSpolesalongSegment3Awouldbereplacedone‐for‐onewithcomparablysized,newwoodpoles,similartothepolesthatexistedpriortothepastworkcompletedbetween1999and2004.TheTSPconstructedbetween1999and2004wouldnotbereplacedbecauseawoodpolecouldnotaccommodatetheweightofthecurrentconductor.4.2.1  Consideration of CEQA Criteria Project Objectives  OptionBwouldmeetallprojectandCountyofSantaBarbaraobjectives(Sections1.6.2and1.6.3).Feasibility  OptionBwouldbefeasiblefromatechnical,legal,andeconomicperspective.Environmental Effect OptionBwouldreducethesignificantlong‐termaestheticimpactsthatresultedfromthereplacementofwoodpoleswithtallerLWSpolesalongSegment3A(Table2).Beforeinstallationofthenewwoodpoles,thisoptionwouldrequiretheremovalofTSPandLWSpolesthatwereinstalledbetween1999and2004alongSegment3A.Constructionofthisoptionwouldtemporarilyincreaseenvironmentaleffectsassociatedwithairemissions,noise,agriculture,traffic,andbiologicalandculturalresources.4.2.2  Conclusion RETAINED.OptionBwouldbefeasible,meetallprojectandCountyofSantaBarbaraobjectives,andreducethesignificantlong‐termaestheticimpactsthatresultedfromthepastworkalongSegment3A.Therefore,thisoptionwasretainedforfurtherconsiderationintheEIR.

4.3  Option C – Relocate the Portion of Segment 3A that Traverses Agricultural Land in the Shepard Mesa Community to Underground Conduit 

OptionCwasidentifiedbytheCPUC,CountyofSantaBarbara,andpublic.Underthisoption,newundergroundconduitwouldreplace0.88mileofexistingLWSpolestraversingagriculturallandintheShepardMesacommunitywithintheexistingROW(Figure2).Thisoptionwouldrequiretheconstructionofapproximately13new55‐foot‐tallwoodpolesneartheundergroundsubtransmissionlinetodistributepowertothesurroundingShepardMesacommunity.Thesepoleswouldalsocontainthird‐partylinesforcontinuedcableandtelecommunicationsservices.ThisoptionwouldrequiretwonewTSPriserpoles—oneateachendoftheundergroundedlinetotransitionthelineaboveandbelowground.TheapplicantmayneedtoobtainnewencroachmentpermitsasmanyexistingROWsonlyprovideoverheadaccess,andthecurrentROWmayincludeexistingundergroundinfrastructurethatwouldneedtobeavoidedsuchaswater,sewer,andgaslines.Inaddition,thedistributionpoleswouldneedtobeoffsetfromthealignmentoftheundergroundsubtransmissionline,whichcouldalsorequiretheacquisitionofnewROWs.Nofaultreturnconductorwouldberequiredwiththisoption.

4  Option Descriptions and Determinations 

09:002975.CP13.02 4‐3 July2014

Insert Figure 2:    

4  Option Descriptions and Determinations 

09:002975.CP13.02 4‐4 July2014

This page intentionally left blank   

4  Option Descriptions and Determinations 

09:002975.CP13.02 4‐5 July2014

4.3.1  Consideration of CEQA Criteria Project Objectives  OptionCwouldmeetallprojectandCountyofSantaBarbaraobjectives(Sections1.6.2and1.6.3).Feasibility  Undergroundingthetransmissionlineinaflatanddevelopedareaisafeasibleoption.OptionCwouldbefeasiblefromatechnical,legal,andeconomicperspective.Environmental Effect OptionCwouldreducethesignificantlong‐termaestheticimpactsthatresultedfromthereplacementofwoodpoleswithtallerLWSpolesalongSegment3A(Table2).Constructionofthisoptionwouldincluderemovalofthe12LWSpolesandwoodguystubsthatwereinstalledbetween1999and2004alongSegment3A.Duringconstruction,thisoptionwouldtemporarilyincreaseenvironmentaleffectsassociatedwithairemissions,noise,agriculture,traffic,andbiologicalandculturalresources.4.3.2  Conclusion  RETAINED.OptionCwouldbefeasible,meetallprojectandCountyofSantaBarbaraobjectives,andreducethesignificantlong‐termaestheticimpactsthatresultedfromthepastworkalongSegment3A.Therefore,thisoptionwasretainedforfurtherconsiderationintheEIR.

4.4  Option D – Relocate Segment 3A to Underground Conduit TheCPUCandSantaBarbaraCountyidentifiedOptionD.Underthisoption,Segment3AwouldincludetheinstallationofnewundergroundconduittosupportthesubtransmissionlinemainlyentirelywithinCaltransROWalongFoothillRoadandCasitasPassRoad.NoundergroundconduitwouldbeinstalledthroughthecenterofwithintheShepardMesacommunity;however,duetotheexistenceofoverheadelectricalfacilitiesaswellaspossibleundergroundinfrastructure,OptionDmayrequiredeviatingoutsideofCaltransROWandacquiringadditionaleasementsonprivateland,asneeded.TheapplicantwouldneedtoobtainnewencroachmentpermitsfornewROWastheirexistingeasementsonlyprovideoverheadaccessandwouldlikelynotcontainsufficientspacetoaccommodatebothadistributionlineandanundergroundsubtransmissionline.ThisoptionswouldalsorequiretwonewTSPriserpoles—oneateachendoftheundergroundedlinetotransitionthelineaboveandbelowground.Nofaultreturnconductorwouldberequired.TheexistingdistributionandthirdpartylineslocatedwithinSegment3AwouldremainwithintheexistingoverheadROW.Theexisting49LWSpoleslocatedalongSegment3Awouldberemovedandreplacedwith55‐foottallwooddistributionpoles.Theexisting35woodpoleslocatedalongSegment3Awouldbetoppedorremovedandreplacedwithwooddistributionpolesasneeded.IntheShepardMesacommunity,13wooddistributionpoleswouldbeconstructedintheexistingROW.4.4.1  Consideration of CEQA Criteria Project Objectives  OptionDwouldmeetmostoftheprojectobjectives(Section1.6.2).ProjectObjective3(increaseenergyefficiencyofthe66‐kVsubtransmissionline)wouldnotbemetunderthisalternative..ThisoptionwouldmeettheCountyofSantaBarbaraobjective(Section1.6.3).Feasibility  Undergroundingthetransmissionlineinaflatanddevelopedareaisafeasibleoption.OptionDwouldbefeasiblefromatechnical,legal,andeconomicperspective.

4  Option Descriptions and Determinations 

09:002975.CP13.02 4‐6 July2014

Environmental Effect OptionDwouldreducethesignificantlong‐termaestheticimpactsthatresultedfromthereplacementofwoodpoleswithtallerLWSpolesandaTSPalongSegment3A(Table2).Constructionofthisoptionwouldincluderemovalofthe50LWSpoles,oneTSP,andwoodguystubsinstalledduringpastworkalongSegment3A,aswellastheremovalof35existingwoodpolesthatareconsideredtobeinsufficientlygoodconditionandwereleftinplaceduringtheconstructionactivitiesthatoccurredbetween1999and2004.Duringconstruction,thisoptionwouldtemporarilyincreaseenvironmentaleffectsassociatedwithairemissions,noise,agriculture,traffic,andbiologicalandculturalresources.4.4.2  Conclusion  RETAINED.OptionDwouldbefeasible,meetmostoftheprojectobjectivesandmeettheCountyofSantaBarbaraobjective,andreducethesignificantlong‐termaestheticimpactsthatresultedfromthepastworkalongSegment3A.Therefore,thisoptionwasretainedforfurtherconsideration.

4.5  Option E – Reroute a Portion of Segment 3A along Casitas Pass Road on LWS Poles 

OptionEwasidentifiedbythePEA.Underthisoption,the66‐kVconductorontheexistingLWSpoleslocatedintheShepardMesacommunity,southofShepardMesaDriveandwestofRinconRoad/SR150,wouldberelocatedwithintheCaliforniaDepartmentofTransportation(Caltrans)roadside2alongSR192/CasitasPassRoad(Figure2).ThenewroutewoulddivergefromtheexistingroutebyfollowingSR192fromitsjunctionwithSR150attheeasternterminusofSegment3AtotheSR192andShepardMesaRoadintersection.ThisnewroutewouldinstallLWSpolesoneitherthenorthorsouthsideofSR‐192.TheexistingdistributionfacilitiesthatarepresentlylocatedalongSR192wouldbetransferredtothenewsubtransmissionpolesifthenewLWSpoleswereinstalledonthesouthsideofSR192.IfthenewLWSpoleswereinstalledonthenorthsideofSR192,theexistingdistributionfacilitieswouldremaininplace,thusresultinginpolelinesalongbothsidesoftheroadway.TheapplicantwouldneedtoobtainnewROWsforthisoption.TheexistingtoppedwoodpolesintheShepardMesacommunitywouldremaininplacefordistributionandthird‐partylines.4.5.1  Consideration of CEQA Criteria Project Objectives  OptionEwouldmeetallprojectandCountyofSantaBarbaraobjectives(Sections1.6.2and1.6.3).Feasibility  OptionEwouldnotbefeasiblefromalegalperspective.ThewidthoftheCaltransROWintheareavaries,butgenerallyis40feetwide,whichiscenteredoveranapproximate24‐foot‐wideroad(Senet2013);therefore,thereisanapproximate7‐footroadsideoneachsideoftheroad.However,structureswouldhavetobeplacedatleast20feetfromtheouteredgeoftheroadbedinaccordancewithSection309.1(c)oftheHighwayDesignManual(Caltrans2013).Therefore,itwouldnotbefeasibletobuildthestructureswithintheCaltransROW.Environmental Effect Thelong‐termsignificantaestheticimpactoftheexistingsubtransmissionlinewouldnotbereduced,asthisoptionwouldtransfertheimpacttoviewshedsalongSR192/CasitasPassRoad.

2Ageneraltermdenotingtheareaadjoiningtheouteredgeoftheroadbedtotherightofwayline.

4  Option Descriptions and Determinations 

09:002975.CP13.02 4‐7 July2014

4.5.2  Conclusion  ELIMINATED.OptionEwouldmeetalloftheprojectandCountyofSantaBarbaraobjectives,butthisoptionwouldnotbefeasibleandwouldnotreduceasignificantimpact.Therefore,thisoptionwaseliminatedfromfurtherconsideration.

4.6  Option F – Reroute a Portion of Segment 3A along Casitas Pass Road on Wood Poles 

OptionFwasidentifiedbytheCPUC.SimilartoOptionE,underthisoption,the66‐kVconductorontheexistingLWSpoleslocatedintheShepardMesacommunity,southofShepardMesaDriveandwestofRinconRoad/SR150,wouldberelocatedwithintheCaltransroadsidealongSR192/CasitasPassRoad(seeFigure2).ThenewroutewoulddivergefromtheexistingroutebyfollowingSR192fromitsjunctionwithSR192fromitsjunctionwithSR150attheeasternterminusofSegment3AtotheSR192andShepardMesaRoadintersection.ThisnewroutewouldinstallwoodpolesoneitherthenorthorsouthsideofSR192.TheexistingdistributionfacilitiesthatarepresentlylocatedalongSR192wouldbetransferredtothenewsubtransmissionpolesifthenewwoodpoleswereinstalledonthesouthsideofSR192.IfthenewwoodpoleswereinstalledonthenorthsideofSR192,theexistingdistributionfacilitieswouldremaininplace,thusresultinginpolelinesalongbothsidesoftheroadway.TheapplicantwouldneedtoobtainnewROWsforthisoption.TheexistingtoppedwoodpolesintheShepardMesacommunitywouldremaininplacefordistributionandthird‐partylines.4.6.1  Consideration of CEQA Criteria Project Objectives  OptionFwouldmeetallprojectandCountyofSantaBarbaraobjectives(Sections1.6.2and1.6.3).Feasibility  OptionFwouldnotbefeasiblefromalegalperspective.ThewidthoftheCaltransROWintheareavaries,butgenerallyis40feetwide,whichiscenteredoveranapproximate24‐footwideroad(Senet2013);therefore,thereisanapproximate7‐footroadsideoneachsideoftheroad.However,structureswouldhavetobeplacedatleast20feetfromtheouteredgeoftheroadbedinaccordancewithSection309.1(c)oftheHighwayDesignManual(Caltrans2013).Therefore,itwouldnotbefeasibletobuildthestructureswithintheCaltransROW.Environmental Effect OptionFwouldreducethesignificantlong‐termaestheticimpactsthatresultedfromthepastworkalongSegment3A.TheuseofwoodpoleswithintheShepardMesaareawouldreducetheimpacttovisualqualitythatresultedfromthepastworkalongSegment3A.4.6.2  Conclusion  ELIMINATED.OptionFwouldmeetalloftheprojectandCountyofSantaBarbaraobjectivesandreducelong‐termsignificantaestheticimpacts,butthisoptionwouldnotbefeasible.Therefore,thisoptionwaseliminatedfromfurtherconsideration.

4  Option Descriptions and Determinations 

09:002975.CP13.02 4‐8 July2014

Thispageintentionallyleftblank

09:002975.CP13.02 5‐1 July2014

Chapter 5

5 Summary of Screening Report 

ThissectionpresentsasummaryoftheconclusionsfromSections3and4.Eachalternativeandoptionidentifiedbytheapplicant,CPUC,theCountyofSantaBarbara,andpublicarelistedinTable3alongwithasummaryofthescreeningresults.BasedontheanalysispresentedinthisScreeningReport,thefollowingalternativeswillbecarriedforwardforfullanalysisinChapter5oftheEIR:AlternativeA ReducetheScopeofWorkalongSegments1,2,and3AAlternativeB InstallSomeStructuresalongSegment4viaHelicopterThefollowingoptionswillbecarriedforwardforanalysisinChapter7oftheEIR:OptionA: PaintExistingLWSpolesandTSPalongSegment3AOptionB: ReplaceExistingLWSPoleswithWoodPolesalongSegment3AOptionC: RelocatethePortionofSegment3AthatTraversesAgriculturalLandintheShepard

MesaCommunitytoUndergroundConduitOptionD: RelocateSegment3AtoUndergroundConduit

5  Summary of Screening Report 

09:002975.CP13.02 5‐2 July2014

Table 3: Summary of the Screening Report 

Alternatives Carried Forward In PEA

Project Objectives 

CountyObj.  Feasible  Environmental Effect of the Proposed Project 

Obj. #1 

Obj. #2 

Obj. #3 

Proposed Project Alternatives 

A  Reduce the Scope of Work along Segments 1, 2, and 3A 

Yes No N/A Yes  Would avoid potentially significant impacts on air quality from NOX and PM10 emissions. 

B  Install Some Structures along Segment 4 via Helicopter 

Yes No N/A Yes  Would avoid potentially significant impacts on biological and cultural resources. 

C  Underground Segments 3B and 4  No Yes N/A No  Would avoid potentially significant aesthetic impacts.

Options for the Past Work along Segment 3A 

A  Paint Existing LWS Poles and TSP along Segment 3A 

Yes No Yes  Would reduce the significant long‐term aesthetic impacts that resulted from the past work along Segment 3A. 

B  Replace Existing LWS Poles with Wood Poles along Segment 3A 

Yes No Yes  Would reduce the significant long‐term aesthetic impacts that resulted from the past work along Segment 3A. 

C  Relocate the Portion of Segment 3A that Traverses Agricultural Land in the Shepard Mesa Community to Underground Conduit 

Yes No Yes  Would reduce the significant long‐term aesthetics impacts that resulted from the past work along Segment 3A. 

D  Relocate Segment 3A to Underground Conduit 

Yes No Yes  Would reduce the significant long‐term aesthetic impacts that resulted from the past work along Segment 3A. 

E  Reroute a Portion of Segment 3A along Casitas Pass Road on LWS Poles 

No Yes No  Would not reduce a significant long‐term that resulted from the past work along Segment 3A. 

F  Reroute a Portion of Segment 3A along Casitas Pass Road on Wood Poles 

No No No  Would reduce the significant long‐term aesthetic impacts that resulted from the past work along Segment 3A. 

09:002975.CP13.02 6‐1 July2014

Chapter 6

6 References Caltrans(CaliforniaDepartmentofTransportation).2013.HighwayDesignManual.Website:

http://www.dot.ca.gov/hq/oppd/hdm/hdmtoc.htm.AccessedSeptember3,2013.PSCW(PublicServiceCommissionofWisconsin).2011.UndergroundElectricTransmissionLine.

MaySCE(SouthernCaliforniaEdisonCompany).2012.Proponent’sEnvironmentalAssessment:Santa

BarbaraCountyReliabilityProject(October26),asamendedbyresponsesfromSCEtoCPUCrequestsforadditionalinformation.

Senet,Steve.2013.CaliforniaDepartmentofTransportationDistrict5EncroachmentPermit

Engineer.PersonalConversationwithBonnyO’ConnorofEcologyandEnvironment,Inc.,onSeptember3,2013.

6  References 

09:002975.CP13.02 6‐2 July2014

Thispageintentionallyleftblank