sanitation programme for municipalities with less …
TRANSCRIPT
SANITATION PROGRAMME FOR MUNICIPALITIES WITH LESS
THAN 10 000 INHABITANTS - PHASE I
ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK
SUMMARY
July 2018
AFRICAN DEVELOPMENT BANK GROUP
2
Programme Name : Sanitation Programme for Programme Number: P-TN-EB0-004
Municipalities with Less
Than 10 000 Inhabitants
Country : Tunisia Department: RDGN
Division : RDGN.2 Programme Environmental Category: 2
-----------------------------------------------------------------------------------------------------------------
1. INTRODUCTION
In compliance with the country’s Strategic Development Plan “Tunisia 2016-2020” and to improve the
socio-economic, environmental and health conditions of Tunisia’s population by generalising sanitation
services in all of the country’s municipalities, ONAS has embarked on the construction of sanitation
facilities (systems, pumping stations and treatment plants) in 33 municipalities (Phase I) with less than
10 000 inhabitants.
The sanitation of these 33 municipalities will help to improve living, hygiene and environmental health
conditions in small urban centres and contribute to protecting natural resources (water, soil, wildlife and
flora) by reducing the negative impact of discharging crude wastewater into the natural environment
(rivers, lowlands, wadis, etc.). It will adequately address the aspirations and grievances of citizens
affected by the lack of a collective and reliable sanitation system that complies with health protection
and environmental hygiene requirements.
The objective of the programme is to construct new wastewater treatment facilities, and renovate and
modernise existing sanitation systems. These investments will improve wastewater treatment services
for about 150 000 inhabitants, according to estimates, and contribute to limiting soil pollution in the
programme areas.
Once the programme becomes operational, it is expected to generate significant benefits not only
environmentally and socially, but also in terms of health and safety, especially through pollution
prevention. However, the commissioning of sub-projects implemented under the programme may lead
to some environmental and social problems that should be rapidly solved by mitigation and management
measures.
Based on the outcomes of the environmental assessment conducted, ONAS’s capacity to manage this
type of programme and the size of the facilities to be constructed, the programme has been classified
under Environmental Category 2, in accordance with the Bank’s Environmental and Social Assessment
Procedures (ESAPs 2015). It should be noted that any sub-project that may be classified under
Environmental Category 1 will be excluded from the programme and will not be eligible for financing.
The programme has an Environmental and Social Management Framework, an Environmental, Social,
Health and Safety Procedure, and a Land Procurement and Loss Compensation Plan.
This document is the summary of the programme’s Environmental and Social Management Framework
(ESMF), which seeks to:
• Establish a specific environmental and social monitoring framework for sanitation
projects with (i) the definition of procedures for preparing, disseminating,
implementing and updating the environmental and social guidelines used; (ii) the
institution of a system of socio-economic surveys to be conducted prior to works; and
(iii) the establishment of a complaints management procedure;
• Develop a mechanism for the environmental, social monitoring and evaluation of
ONAS’s activities with: (i) the development of environmental and social indicators for
3
monitoring programme activities; (ii) the establishment of a sanitation sector
environmental and social databank; and (iii) the retrospective supervision and
evaluation of activities for the assessment of the effective consideration of
environmental and social measures;
• Develop an environmental and social surveillance mechanism within ONAS based on:
(i) information, education and communication (IEC) on the quality of ONAS’s projects
and environmental actions; (ii) coordination, environmental and social exchanges
between the sanitation sector and other government and non-government institutions;
and (iii) management of complaints from programme beneficiaries and local residents.
2. PROGRAMME DESCRIPTION
The programme comprises three components: (i) Sanitation Facility Development (primary and
secondary systems, transfer systems, pumping stations and treatment plants); (ii) Capacity Building and
Institutional Support; and (iii) Programme Management (engineering studies, land procurement,
operation and technical assistance).
2.1 Sanitation Facility Development
The works to be carried out in small municipalities include:
• The establishment\extension\rehabilitation of sanitation systems, including pumping
stations;
• The construction of new treatment plants and rehabilitation of existing ones.
Table 1: Various Components of Sanitation Sub-Projects in Small/Medium-sized Municipalities
Governorate Municipality
Waste Water
Treatment Plant
(WWTP)
Pumping
Station
Backflow System
(lm) Transfer System
(lm)
Greater Tunis Department
Ben Arous Khlidia Yes 2 2 000 2 000
North Regional Department
Nabeul Dar Allouch Haouria WWTP 2 4 825 3 350
Menzal Horr Korba WWTP 3 3 740 2 000
Azmour Haouria WWTP 1 Ongoing 1 700
Zaghouan Jbel el Oust New WWTP 1 1 560 1 560
Nathour New WWTP Ongoing Ongoing 3 930
Le Kef Nebeur New WWTP 1 760 3 600
Kalâa Khisba New WWTP Ongoing Ongoing 1 300
Siliana Kesra New WWTP 2 500 500
Bizerte Sedjnene New WWTP 0 0 6 700
Béja Amdoun New WWTP Ongoing Ongoing
Guebollat New WWTP 0 0 2 000
Jendouba Oued Mliz New WWTP Ongoing Ongoing 1 120
Beni Mtir New WWTP 2 780 1 200
Centre Regional Department
Kasserine Hidra New WWTP Ongoing Ongoing 1 800
Kairouan Nasrallah New WWTP Common WWTP
1 3 600 3 600
Menzil Mhiri 0 0 3 250
El Alâa Haffouz WWTP 0 1 060 15 800
Monastir Amiret el Hojjej Moknine WWTP 2 572 4 200
Sidi Bennour Moknine WWTP 1 4 740 4 740
Manzel Hayet New WWTP Ongoing Ongoing 0
4
Governorate Municipality
Waste Water
Treatment Plant
(WWTP)
Pumping
Station
Backflow System
(lm) Transfer System
(lm)
Mehdia Mallolech Chebba WWTP 0 0 0
Ouled Chamekh New WWTP Ongoing Ongoing 0
Karkar Manzel Hayet
New WWTP Ongoing Ongoing
Ongoing
Sousse Sidi El Héni New WWTP 4 7 845 10 870
South Regional Department
Tataouine Dhhiba New WWTP 1 1 351 1 351
Rmeda New WWTP 3 2 620 1 800
Sfax Bir A Ben Khalifa New WWTP 1 1 200 2 000
Skhira New WWTP 1 800 800
Tozeur Hammet Jrid New WWTP 1 200 200
Gabes Matmata Jedida New WWTP Ongoing Ongoing Ongoing
Médenine Beni Khdech New WWTP Ongoing Ongoing Ongoing
Kébili Faouar New WWTP 1 1 400 Ongoing
2.2 Capacity Building and Institutional Support
- Study on the operation of sanitation systems in small municipalities (private sector participation);
- Study on the reuse of treated wastewater (TWW) (with pilot sites);
- Design and application of a software package for project planning and implementation;
- Procurement audit and procedures manual.
2.3 Programme Management (engineering studies, land procurement, operation and
technical assistance)
At the regional level (regional departments - RDs):
- Technical assistance for bid opening, monitoring and works control;
- Monitoring of working design;
- Monitoring of land, goods and works procurement;
- Monitoring of works;
- Monitoring of ESMP implementation and any abbreviated resettlement plans (ARPs).
At the central level (central departments):
- General programme coordination;
- Coordination of RD activities (procurements, studies, works monitoring, etc.).
- Programme financial and accounting management;
- Technical assistance to RDs.
The programme is implemented by an Operational Programme Management Unit (OPMU) based at the
ONAS Headquarters.
The programme cost is estimated at EUR 163.3 million.
2.4 Programme Alternatives
The only programme alternative explored is the "without programme" situation, which consists in
maintaining the current situation where domestic or industrial wastewater is discharged mostly into the
natural environment without treatment (wadis or simply streets in front of houses). In practice,
maintaining the current situation would mean further degradation of sanitary conditions and increase in
the pollution load in programme areas, leading to more diseases and deepening poverty that is not
consistent with Tunisia’s sanitation development policy.
5
For each sub-project and during detailed engineering studies, the selection of the WWTP construction
site alternatives, the transfer/backflow systems layout and the treatment process alternatives will be
analysed. The selection will be based on environmental and social criteria to give preference to the most
natural and human environment-friendly alternative.
3. NATIONAL AND REGIONAL BASELINE ENVIRONMENTAL AND
SOCIAL INFORMATION
At end-2016, the key national sanitation indicators were as follows:
• Total urban population of about 7 million;
• Population connected to the ONAS system: 6.3 million, representing 90.3 % of the total
population. It should be noted that ONAS is not designed to cater for non-urban localities.
• Number of WWTPs: 115
• System length: 16 337 kilometres.
• Out of 260 million cubic metres of wastewater collected, 255.2 million cubic metres are treated
annually, that is a 98.15% treatment rate.
The programme impact area covers 33 municipalities in 19 governorates. These are mostly rural
municipalities whose population does not exceed 10 000.
Table 2: Characteristics of Programme Municipalities Municipality Population Population\Male Population\Female Households Housing Units
Khelidia 4 356.0 2 206.0 2 150.0 1 049.0 1 201.0
Menzel Horr 5 473.0 2 714.0 2 759.0 1 395.0 1 687.0
Azmour 5 057.0 2 486.0 2 571.0 1 281.0 1 545.0
Dar Allouch 4 547.0 2 343.0 2 204.0 1 229.0 1 617.0
Jebel Oust 5 325.0 2 757.0 2 568.0 1 284.0 1 476.0
En Nadhour 7 567.0 3 764.0 3 803.0 1 806.0 2 176.0
Sedjnane 5 228.0 2 602.0 2 626.0 1 290.0 1 498.0
Amdoun 5 356.0 2 655.0 2 701.0 1 324.0 1 672.0
Goubellat 4 128.0 2 091.0 2 037.0 965.0 1 092.0
Beni M'tir 504.0 248.0 256.0 113.0 154.0
Oued Meliz 2 388.0 1 146.0 1 242.0 600.0 838.0
Nebeur 3 557.0 1 720.0 1 837.0 954.0 1 060.0
Kalâat Khasba 2 558.0 1 216.0 1 342.0 692.0 804.0
Kesra 2 729.0 1 315.0 1 414.0 739.0 888.0
Sidi El Héni 2 706.0 1 315.0 1 391.0 639.0 778.0
Menzel Hayet 3 137.0 1 604.0 1 533.0 701.0 935.0
Sidi Bennour 4 520.0 2 149.0 2 371.0 1 045.0 1 199.0
Amiret El Hojjaj 8 121.0 4 119.0 4 002.0 1 679.0 1 778.0
Kerker 7 478.0 3 749.0 3 729.0 1 602.0 1 866.0
Ouled Chamekh 5 120.0 2 262.0 2 858.0 1 126.0 1 420.0
Melloulech 6 919.0 3 338.0 3 581.0 1 536.0 2 030.0
Bir Ali Ben Khelifa 4 905.0 2 426.0 2 479.0 1 208.0 1 421.0
Skhira 11 912.0 5 967.0 5 945.0 2 506.0 2 851.0
El Alâa 3 276.0 1 564.0 1 712.0 783.0 875.0
Nasrallah 5 012.0 2 446.0 2 566.0 1 241.0 1 475.0
Hidra 3 451.0 1 668.0 1 783.0 929.0 1 080.0
Nouvelle Matmata 7 526.0 3 607.0 3 919.0 1 798.0 2 380.0
Beni-Khedech 2 930.0 1 317.0 1 613.0 695.0 909.0
Dhehiba 4 295.0 2 145.0 2 150.0 777.0 986.0
Remada 6 289.0 3 101.0 3 188.0 1 084.0 1 344.0
Hamma el Jarid 4 074.0 1 970.0 2 104.0 953.0 1 048.0
6
The sanitation situation in programme municipalities is characterised by:
- A sanitation system connection rate that varies from 0% to 40 % in the best case
scenario. Black water (from toilets) from households and collective entities (primary
schools, secondary schools, slaughterhouses, public coffee shops, etc.) are channelled
to drainage ditches in the form of cesspools that are cleaned at various frequencies,
depending on the usage. Municipal technical services are responsible, under state
control or subcontracting, for draining off the ditches using cesspool emptying
equipment;
- Disposal of effluents into the natural environment (effluents from wadis, spray areas,
public landfills, etc.) or supplied to farmers as soil admendment products or fertilisers
in spite of all the attendant health risks;
- Disposal of grey water (from sinks, showers and kitchens) outside households into
gutters or directly into the streets, leading to permanent flow of wastewater that causes
the proliferation of disease vectors and odours, especially during warm periods;
- Pollution and wastes that create all kinds of nuisances, especially in the rainy season,
namely: (i) proliferation of odours and disease vectors (mosquitoes and flies); (ii)
production of loaded and highly fermentable licheates; (iii) degradation of the living
environment; (iv) health problems at several levels, etc.;
- In some areas, rise in the water table due to the infiltration of wastewater through many
porous ditches;
- Infiltration of pollutants from ditches to stormwater collection reservoirs (Majels or
Festkia), which poses a health risk;
- Uncontrolled use of faecal sludge by farmers for soil admendment, thereby generating
a disproportionate health risk for them and consumers of any contaminated agricultural
produce;
- Increased financial burden for poor and average-income families as well as public
institutions and collective groupings considering the cost they have to bear to clean their
septic tanks (close to TND 300/month for heavy water consumers, TND 6 to 7/month
for households) ;
- Outbreak of diseases caused by the general lack of hygiene in unclean environments
particularly affecting vulnerable people and school children who are exposed to the risk
of contracting hepatitis A, typhoid fever and diarrhoea, leading to loss of schooling
time;
- Undermining of the well-being and the quality of the environment of the people living near crude wastewater outlets (around natural drainages) or during the accidental
overflow of septic tanks as a result of clogging or lack of means to ensure regular
emptying, etc.
7
4. REGULATORY FRAMEWORK
Tunisia’s domestic policies accord paramount importance to the environment in general, and
environmental and social management arrangements in particular. Specifically, the new 2014
Constitution addresses issues related to climate, environment and natural resource management. Articles
12 and 45 of the Constitution respectively focus on "the judicious exploitation of national resources"
and the role of the State in ensuring "the right to a healthy and balanced environment and participation
in environmental protection".
Tunisia has put considerable effort into developing a varied legal and regulatory arsenal. The legal
instruments governing environmental protection and applicable to the implementation of the Sanitation
Programme for Municipalities with Less Than 10 000 Inhabitants include:
- Tunisia’s new Constitution adopted in 2014 ;
- Law No. 88-91 of 2 August 1988 establishing the National Environmental Protection
Agency (ANPE);
- Law No. 2001-14 of 30 January 2001 simplifying the administrative procedures for the
issuing of authorisations by the Ministry of Environment and Territorial Development;
- Decree No. 2005-1991 of 11 July 2005 repealing the 1991 decree on Environmental
Impact Assessment (EIA);
- Water Code No. 76-75 ;
- Law No. 82-66 of 6 August 1982 on standardisation and Decree No. 85-86 on the
regulation of discharges into the receiving environment;
- Law No. 83-87 on the protection of agricultural land, as amended by Law No. 96-104
of 1996 ;
- Law No. 95-70 of 17 July 1995 on water and soil conservation;
- Forestry Code No.88-20 of 13 April 1988;
- Law No. 30 of 6 March 2000 on the development of agricultural land in public irrigation
areas;
- Law No. 2016-53 of 11 July 2016 laying down conditions for land use and the
expropriation of property for public purpose, which repeals Law No. 76-85 of 11
August 1976 and Law No. 2003-26 of 14 April 2003;
- Law No. 96-41 of 10 June 1996 on wastes and the control of waste management and
disposal;
- Law No. 2007-34 of 4 June on air quality.
Decree No. 2005-1991 of 11 July 2005 repealed the 1991 decree on EIA and introduced many major
changes. It is being revised to incorporate the social dimension. The programme does not require
environmental impact assessment or approval by the ANPE. In accordance with national regulations,
only new water treatment facilities, irrespective of their capacity, are subject to an ESIA. Moreover, and
in accordance with the same decree, existing WWTP connection projects are not subject to an EIA, but
rather to specifications whose content complies with best practice.
8
Table 3: Classification of Sanitation Projects by Decree No. 2005-1991
ANNEX I ANNEX II
Category A
(Plant subject to a notice not
exceeding 21 days)
Category B
(Plant subject to a notice not exceeding 3
months)
Specifications
(Low environmental impact
project)
1) Projects EXPLICITLY subject to EIA and EMP or specifications in accordance with Decree No. 2005-
1991
RS
Project in areas irrigated by treated
wastewater for agricultural purposes
(explicit)
RS Urban wastewater treatment plants
(explicit)
Industrial wastewater treatment plants
(explicit)
2) Projects subject to EIA and ESMP or specifications by ANALOGY in accordance with Decree No. 2005-1991
Household refuse management
plants < 20 T/D (sludge
management plants by
analogy)
Household refuse management plants >
20 T/D (sludge management plants by
analogy)
Water transmission and
transfer canals (wastewater
pipes by analogy)
It is worth noting that Decree No. 2005-1991 is being revised to incorporate social aspects and comply
with international environmental and social standards.
Overall, environmental management is the responsibility of the Ministry of Local Governments and
Environment and the various agencies under its supervision, namely:
• The National Sanitation Board (ONAS);
• The National Environmental Protection Agency (ANPE);
• The National Waste Management Agency (ANGED); and
• The Coastline Protection and Development Agency (APAL).
Other ministries and entities concerned by environmental issues include: the Ministry of Public Health;
the Ministry of Agriculture and Water Resources; the Ministry in charge of Budget; the Ministry in
charge of Land Tenue, industrialists and non-governmental organisations (NGOs).
5. IDENTIFICATION OF POTENTIAL PROGRAMME ENVIRONMENTAL
AND SOCIAL IMPACTS
In general, the impacts of a sanitation project are positive. They help to improve the quality of life of the population directly concerned, in addition to contributing to preserving the natural environment and
providing an unconventional source of irrigation water and sludge for reuse in agriculture and industry
(reuse of dry sludge in cement factories). Therefore, the programme will implement TWW reuse pilot
projects in at least five municipalities. These projects that are consistent with the country’s integrated
water resources management policy will help not only to meet the needs of some regions that lack water,
but also to promote the use of TWW in various sectors, create new uses and contribute to settling the
populations in small localities by offering them the opportunity to locally enhance their existing
resources or create new sources of income.
Regarding risks and negative impacts, the ESMF considered ONAS’s various activities as comparable
to those to be carried out under the programme and the impacts already identified in previous studies
and projects.
9
5.1 Impacts during the Construction Phase
Sanitation facility development and construction project works generate nuisances for the natural and
human environment. These nuisances include: (i) land use and change of land use; (ii) alteration of the
natural and biological environment by soil and biodiversity degradation; (iii) generation of various
nuisances, especially the production of various wastes, construction site effluents, noises and vibration;
and (iv) traffic disruption by the movement of machines and vehicles, and dust and combustion gas
emissions. The level of these impacts is measured based on their scope, intensity and extent that vary
according to their environment. A preliminary analysis shows that the scope of these impacts should be
limited and restricted in space and time, considering that the programme will comprise no facility that
generates major or irreversible negative impacts.
Aspects Major Potential Negative Impacts
Land issue Procurement of small land and rights of way, change of land use and land tenure
regularisation
Environmental nuisances Noise and vibration, dust and combustion gas emission (greenhouse gases),
production of wastes (household, special and hazardous, construction site
excavations, etc.), water discharges
Social impacts Disruption of road traffic and the movement of persons
Danger, safety and
occupational health risks
Exposure to various on-site risks and hazards: working at a height without
protection, risk of asphyxia while working in closed areas, insufficient protection
while working at depth (trench, fall, etc.), road accident, hydrocarbon storage,
employment not compliant with the labour code
5.2 Impacts during the Operation Phase
Impacts during the operation phase are controlled by ONAS, considering that its trade is the operation of WWTPs.
ONAS manages over 170 WWTPs and is already establishing an ISO 14001 environmental management system
in treatment plants. The impacts identified are summarised in the table below.
Facility
Concerned Environmental and Social Aspects Environmental and Social Impacts
Wastewater
treatment plant
(WWTP)
Land
Production of screening, cleaning and
desilting by-products
Water bypass in the event of a breakdown or other hazards
Quality of effluents at the inlet and
outlet of the WWTP and performance
measure
Air quality analysis (existence or
absence of an air freshener system)
Energy consumption
Decanting of other effluents (non-
collective systems and others)
TWW intended for reuse (agriculture,
replenishment of water tables)
Drop in the value of land around WWTPs
Environmental nuisances and health risks
related to the management of cleaning products
and equipment maintenance
Risk of surface water, water table and marine
environment contamination
Risk of treated water contamination by trace
metals
Bad odours and complaints from local
inhabitants
High energy cost (cost of a cubic metre treated)
Disruption of the WWTP process, output and
performance
Health and trace metal accumulation risk (soil
and water table)
Pumping
stations Odours
Disposal of cleaning and screening
wastes
Effluent quality
Industrial effluents and intrusion of
illegal discharges
Energy consumption
Bad odour-related nuisances and complaints
from local inhabitants
Effluent bypass in the natural environment and
risk of environmental and health nuisances
Environmental contamination by wastes,
sludge and cleaning sand
Relatively high cost of lifting a cubic metre of
effluent (energy)
Wastewater and
effluents Domestic wastewater
Stormwater
Industrial effluents
Health risks for facility operators and users,
especially farmers
Surface water contamination
10
Cooling water Water table contamination
Marine and beach pollution
Risks related to trace elements (heavy metals)
Collection and
supply systems De-clogging activities and cleaning of
collectors, manholes, inlets and sewer
drains, and as appropriate, stormwater
overflows and grit and connection
chambers
Waste disposal
Industrial effluent monitoring
Control of intrusions and accidents
(illegal discharges)
Exposure health risks for operators and
workers
Production of wastes (wastes, sludge and sand)
and their impacts on the natural environment
and health
Disruption of traffic and the movement of
people during maintenance works and
maintenance of systems
Sanitation
sludge
management
dumps
Wastewater sludge
Industrial effluent sludge
Risk of water table contamination (leachates
and metals)
Bad odours and complaints from local
inhabitants
Health risks for operators
6. PROCEDURES FOR ASSESSING POTENTIAL ENVIRONMENTAL AND
SOCIAL IMPACTS SPECIFIC TO PROGRAMME SUB-PROJECTS AND
PROCEDURAL MEASURES
The programme has identified 33 sub-projects based on the strategic sanitation study conducted in 2015
on 80 municipalities with less than 10 000 inhabitants. The list includes 24 new WWTPs and 9 sub-
projects for connection to existing WWTPs and, eventually, rehabilitation. Considering that detailed
engineering studies (including specific impact assessments in accordance with national law) are
ongoing, the ESMF has developed a procedure to take into account Donor environmental procedures in
the environmental analysis approach. The process is summarised below.
6.1 Stage 1: Description and Eligibility
The objective of Stage 1 is to ascertain that each sub-project is eligible for financing based on the E&S
policies of the AfDB and its financial partner EBRD, which exclude any Environmental Category 1 sub-
project. In this regard, the procedure has developed specific forms to be filled to guide the work of the
Environmental and Social Monitoring Unit (ESMU).
6.2 Stage 2: Risk Assessment and Management, and Environmental, Social, Health and
Safety (ESHS) Impacts
This stage includes the process to be followed to conduct environmental and social assessments. In that
connection, ONAS will consult the general terms of reference defined by ANPE for the activity sectors
concerned by the preparation of an ESIA as well as any supplementary social assessments according to
Donor requirements.
The ESIA and the ESMP must be prepared using a progressive and iterative approach to help ONAS to
decide on the feasibility of its sub-project or envisage other alternatives to arrive gradually at a least risk
solution.
The content of the ESIA must be participatory and comprise the following elements at least: (i) a detailed
project description; (ii) an analysis of the initial project site and its environment; (iii) an analysis of
project environmental impacts; (iv) proposal of recommended negative impact mitigation measures and
related cost estimates; and (v) proposal of an Environmental and Social Management Plan (ESMP)
together with an environmental monitoring programme.
11
Review and approval of environmental and social assessment reports: at the national level, for projects
subject to an ESIA according to Decree No. 2005-1991, the review of the ESIA and the ESMP is the
responsibility of ANPE, which notifies its approval by issuing an environmental compliance certificate.
The ESIA/ESMP as well as any other supplementary study will also be transmitted to AfDB and its
financial partner for approval.
Information and dissemination of environmental and social assessment reports: once the ESIA, the
ESMP and, eventually, the ARP, if required, are approved, ONAS, for purposes of transparency and
accountability, particularly regarding the key stakeholders, will place the said documents at the disposal
of the public in municipalities, delegations, governorates and regional sanitation offices, and on its
website. Donors will provide support for such dissemination.
The procedure states that consultation timeframes must enable the consideration of useful feedback from
persons and groups that would also have consulted the key documents produced (ESIA, ESMP and
ARP) and the revision of the documents.
As part of strengthening ONAS’s communication policy, ESMU will establish a database for monitoring
the environmental and social status of ONAS’s activities. The database will be fed with data provided
and communicated by environment focal points. The data will help to inform ONAS’s key
environmental and social indicators. An annual environmental and social status report will be produced
by ESMU and posted on ONAS’ website. The template of the ONAS annual environmental and social
status report has been specified in the procedure.
6.3 Stage 3: Project Implementation and Monitoring
E&S clauses: the procedure provides for the incorporation of subproject-related additional
environmental and social clauses (as identified in the ESMP(s)) in the bidding documents during project
launching in the studies or works phase, or when leasing out the operation of ONAS’ WWTPs and other
facilities. A sample price schedule has been prepared and provided in the procedure.
Implementation of environmental and social measures: the contractors legally and contractually
responsible for implementing the ESMP during the construction phase will also undertake to strengthen:
(i) the participation of the local population concerned; (ii) the mainstreaming of the gender dimension;
and (iii) complaints management. In addition, as project owner, ONAS will strengthen social
communication through its current citizen space on its website.
Measures implementation monitoring/evaluation: during programme implementation, the contractor(s)
responsible for programme implementation will report to ONAS on the implementation of the
environmental and social measures provided for, in accordance with the programme documents
(ESMP), the status of mitigation measures and the outcomes achieved. Monitoring the implementation
of programme environmental, social, health and safety measures is described in the table below.
Responsibility Monitoring Reference Framework Periodicity Reporting
Works
contractor’s HSE
Officer
Construction site’s
health, safety and
environmental
performance
Works contractor’s
contract terms
Works contractor’s HSE
Management Plan
approved by ONAS
Continuous
during works
Monthly report to
ONAS’ Regional ESHS
Officer
(form available)
Wastewater
treatment plant
operator’s HSE
Officer
ESHS performance of the
wastewater treatment
plant
Works contractor’s HSE
Management Plan
approved by ONAS
Continuous
Monthly report to
ONAS’ Regional ESHS
Officer
12
Responsibility Monitoring Reference Framework Periodicity Reporting
ONAS’ Regional
ESHS Officer
ESHS performance of the
wastewater collection
and treatment facilities of
small towns of the region
covered by the Sanitation
Programme for
Municipalities with Less
Than 10 000 Inhabitants
Tunisia’s legislation
Programme ESHS
Procedure
Monthly visit
to each small
town
Semi-annual report to
ONAS’ Regional ESHS
Officer
and to OPMU’s ESHS
Team
OPMU’s ESHS
Team
Field control of six sub-
projects: 3 most efficient
and three least efficient
Programme ESHS
Procedure
Semi-annual
during works
Good and bad practice
sharing note to all
Regional ESHS Officers
ONAS’ Central
ESHS Officer
OPMU’s ESHS
Team Programme’s ESHS
Performance
Tunisia’s legislation
AfDB and EBRD E&S
policies
ESHS procedure of the
Sanitation Programme for
Municipalities with Less
Than 10 000 Inhabitants
Environmental and Social
Action Plan
During works Semi-annual report to
AfDB and EBRD
ONAS’ Central
ESHS Officer
After works Annual report to AfDB
and EBRD
To ensure its implementation, the programme has included a technical assistance that will solicit the
services of an independent expert/ group of experts responsible for ascertaining contractors’ compliance
with the actions and measures provided for in the ESMPs that will be adjusted if necessary, or in case
of failure to comply.
7. ADDITIONAL MEASURES TO BE INCLUDED IN SUB˗PROJECT ESMP
Based on programme environmental impact assessment, a battery of measures has been proposed for
each sub-project development phase.
7.1 Measures during WWTP Design
During WWTP design study and sizing, some rules and recommendations contained in the technical
specifications of facilities should be considered to facilitate the management of facilities and ensure
their efficiency in producing a discharge that complies with standards.
Table 4: General Recommendations and Specifications to be Considered in the Design and during the Operation of the Sanitation System
Ref. Elements Recommendations and Specifications to be Considered
I General Recommendations and Specifications for the Sanitation System
1.1 Selection of
sanitation system
❖ Based on the comprehensive study of the physical features of the study area and socio-
economic conditions
1.2 Stormwater drainage
system
❖ Must be sized to dispose of runoff rates resulting from the heaviest rainfall at a given
frequency (2.5 years or 10 years, depending on the size of the urban centre)
1.3 Disposal plan layout ❖ The water disposal plan layout must be prepared by making utmost use of the
topography of the land to ensure, as much as possible, a gravitational flow with
sufficient flow speeds. It is necessary to limit the number of lift and pumping stations
for economic reasons and owing to operating conditions
1.4 Selection of receiving
environment
❖ As much as possible, avoid discharging wastes into closed water environments (lakes,
ponds, etc.), owing to their fragile ecological balance
❖ Avoid directly discharging wastes into seashore sensitive areas (near beaches, gulfs,
unfavourable sea currents, etc.)
❖ Ensure the watertightness of the system at the crossing of water tables to avoid their
pollution and control the volume of infiltrated water
❖ Avoid constructing the plant in a flood-prone area
1.5 Limit the release of
nauseating odours
❖ Provide for sufficient flow speeds to avoid the formation of permanent deposits
❖ Provide system head sections with a flush
❖ Avoid cascade lifting
13
Ref. Elements Recommendations and Specifications to be Considered
❖ Increase the flow speed in airlift pumps (reduce wastewater residence under anaerobic
conditions)
II Specifications for Wastewater Treatment Plants (WWTPs)
2.1 Screening ❖ The flow speed through partially plugged screens must be maintained within the range
of 0.6 m/s and 1.2 m/s
❖ Change screen wash pumps from manual to automatic
❖ Provide for the possibility of isolating screens to ensure their maintenance and repair
(cofferdam).
2.2 De-silting ❖ Use mechanised aerated grit chambers each time that the size of the plant so requires
❖ Schedule frequent sand extraction and washing
❖ Increase the size of aerated grit chambers, with an appropriate hydraulic loading
❖ Adjust the scheduling of sand extraction sequences
2.3 Primary settling ❖ Apply low hydraulic loading to avoid carrying sludge during hydraulic overloading
(during rain)
❖ Schedule frequent extraction of decanted sludge to avoid foul odour
2.4 Aeration ❖ Give preference to membrane diffusers for efficient aeration management
❖ Immersed railings with bubble diffusers must be isolable and adjustable
❖ Use double speed boosters for maximum management flexibility
❖ Sound insulation and ventilation of booster compartments are compulsory
❖ Where many settling tanks are used, each tank should have a booster. Air circuits must
be interchangeable (adapted winnowing system)
❖ An emergency booster is advisable even for small facilities
❖ Provide for dust filters
❖ Drain cocks should be fixed at low points
❖ Steel and stainless steel should not be juxtaposed (corrosion cell)
❖ The presence of compounds that are aggressive to elastomers (hydrocarbons) in
wastewater should be checked
2.5 Agitation ❖ The aeration and agitation functions must be separated to optimise nitrogen elimination
and prevent deposits during the shutdown of aeration
❖ Mixed liquor flow speed at the tank bottom must be above or equal to 35 cm/s
❖ The capacity of stirrers varies depending on the geometry of the tanks
2.6 Clarification ❖ Frequently extract sludge from the bottom of clarifiers to prevent their fermentation.
Sludge residence at the bottom of clarifiers must not exceed 2 hours
❖ Ensure extensive upstream denitrification to prevent denitrification in the clarifiers that
could lead to sludge flotation
❖ The bottom scraper should be easily pulled out by the operator, especially without having
to empty the decanter. Bottom rollers are forbidden
❖ Louvre-like bottom scrapers (discontinuous) increase sludge residence. Scrapers made of
a single continuous blade are recommended
III Specifications for Sludge Treatment
3.1 Sludge thickening ❖ Sludge must not be resident in the thickener for long to prevent its fermentation
❖ Preferably use cover thickeners
❖ Hydraulic loading must not be high to avoid sludge overflow
3.2 Sludge digestion ❖ Digester sludge intake must be regular and, as much as possible, continuous
❖ There should be a scum breaker mechanism to prevent the consolidation of the floating
layer on the surface of the digester
3.3 Lagooning ❖ The plant must be located at a low point (to ensure gravity supply), at a place where
dominant winds contribute to aerating surface water column
❖ There should be no trees within 10 metres of the plant as their roots could create
preferential flows in the dykes
❖ The land should be selected in such a way as to ensure gravitational flow right to the
receiving environment
❖ The geometry of the lagooning tanks must be selected so as to minimise dead bands and
short circuits
❖ Dykes surrounding tanks must be sufficiently large to enable the movement of machines
14
7.2 Mitigation Measures during the Construction Phase
7.2.1 Framework for Mitigating Impacts on the Construction Site
In general, the construction site should be installed on an authorised site selected beforehand by ONAS.
It should be easily accessible, located near the project site and at least 400 metres from residential areas,
fenced and clearly signalled. The measures include provisions to limit impacts and nuisances related to
the movement of machines and impacts on the soil, particularly farmland. Construction materials (sand,
gravel, debris, etc.) should be stored on the construction site far from the workers’ camp to avoid dust
emissions and sound nuisances caused by the movement of machines and vehicles.
The impact mitigation framework includes the storage of hydrocarbons, flammable and/or hazardous
products (hydrocarbons, mineral oils and other flammable and/or hazardous products) and specifies,
among other things, storage conditions and the control of accidental spills.
In case of an accident and/or a fire on the construction site, an Emergency Response Plan (ERP) prepared
beforehand by the Contractor in charge of works will be implemented.
7.2.2 Framework for Mitigating Construction Site Noises and Sound Nuisances
The ESMF specifies the thresholds for noise exposure as defined by World Health Organization (WHO)
standards for residential (local residents) and work (employees) areas. It also includes monthly
campaigns to measure the noise level on the construction site and its surrounding areas. The measured
noise level will be compared with the level recommended by WHO and levels recommended for various
occupational settings by the International Organization for Standardization (ISO).
7.2.3 Construction Site Solid Waste Management
Solid waste will be managed in accordance with Law No. 96-41 of June 1996 backed by the following
additional measures:
Inert waste, household and similar waste: the procedure in force specifies the methods of collecting
(containers) and sorting waste: (i) inert waste, depending on the existence of a waste recycling sector,
especially construction waste; (ii) household and similar waste to be disposed of in municipal landfills;
(iii) unused excess debris to be channelled to the nearest municipal landfill and/or ANGED.
Hazardous waste: the appropriate measures considered concern waste oils at the Tunisian Lubricants
Company (SOTULUB), which is the main company that processes and recycles waste, oil-contaminated
rags, filters and other special waste to be channelled to the Hazardous Waste Treatment Centre for
processing after informing and consulting ANGED, and used batteries collected and stored at the
construction site before returning them to producers (for example, the Tunisian Battery Company –
ASSAD).
7.2.4 Construction Site Liquid Waste and Wastewater Management
Workers’ camp liquid waste management: installation of watertight drainage ditches for wastewater
collection to be drained periodically, and channelling of wastewater to the nearest wastewater treatment
plant (WWTP) by an approved company.
Construction site liquid waste management: where the construction site has a machine cleaning and
maintenance platform, clear water from the machine and vehicle washing water collection ditch will be
collected and reused in watering roads to reduce dust emissions.
15
7.2.5 Gas and Dust Emission Mitigation Measures
The Tunisian Standard NT 106.04 for ambient air quality will be applied, in addition to the watering of
roads and traffic areas, and the maintenance and regular technical control of all construction site
machines and vehicles in accordance with the regulations in force to avoid excessive fuel consumption
and reduce exhaust fumes, particularly greenhouse gases (GHGs).
7.2.6 Soil Erosion and Facility Silting Control Measures
The Contractor will endeavour to limit the risk of soil erosion, flooding of the construction site, roads
and feeder roads, farm-to-market roads and the silting of water works. The Contractor must prevent
groundwater contamination by draining stormwater and excavation floor water towards existing
drainage channels.
7.2.7 Management of Concession Holder Networks
The Contractor is contractually obliged to take all the necessary measures to prevent any damage to the
piping, pipes, various cables, roads and road networks crossed during works execution. As-built
drawings will be prepared in full consultation with the concession holders concerned to implement the
potential system displacement operations.
7.2.8 Hygiene and Safety Measures
Proper construction site organisation includes taking appropriate safety measures to protect local
residents and workers against the risk of accidents associated with the execution of works and the
movement of machines, ensuring strict compliance with safety and hygiene instructions in accordance
with the regulations in force and signs on the construction site (prohibition of access, speed limits for
machines on the construction site and roads, and the shoring up of excavations).
The Contractor is contractually obliged to provide personal protective equipment – PPE (helmets,
gloves, protective footwear, goggles, etc.) to construction site workers and to sensitise workers and
visitors on their use.
7.2.9 Site Restoration upon Completion of Works
Site restoration is a contractual clause reinforced by a special mention in case of accidental damage,
which the Contractor is bound to correct at his own expense.
7.3 Measures during the Operational Phase
7.3.1 WWTP Water Quality Monitoring Framework
A programme to control and monitor the quality of crude water before the WWTP inlet and after treatment will be designed to monitor the plant’s performance. Analyses and observations will be
conducted upstream and downstream of the WWTP. The aim will be to monitor the flow and quality of
water at the WWTP inlet (crude water) and outlet (treated wastewater) to identify anomalies that may
affect the performance of the WWTP. Water samples will be collected and analysed using an automated
sampler as much as possible to ensure that treated wastewater is consistent with the NT 106.02 standard.
The frequency of water collection and analysis is specified in the section on environmental monitoring.
ONAS has a non-compliance early warning mechanism that involves the intervention of the WWTP
manager.
16
Regarding the storage pond containing treated wastewater to be reused to water public spaces, the
parameters of analysis also concern the biological and bacterial quality of treated wastewater: heavy
metals, Escherichia coli, faecal coliforms and salmonella and helminthic eggs, vibrio cholerae and
viruses, in keeping with the NT 106.03 standard.
7.3.2 Framework for Monitoring Water Quality in the Receiving Environment
Where WWTP wastewater is discharged into a river or lake receiving wastewater from the upstream
basin, biological and bacterial quality analysis will be carried out in three plants, namely: the ONAS
discharge point (WWTP outlet), a plant downstream of the ONAS discharge point (where there is natural
flow) and a plant after mixture with the wastewater released upstream (wastewater from a source other
than the WWTP). The main parameters to be monitored are suspended solids (SS), chemical oxygen
demand (COD), five-day biochemical oxygen demand (BOD5), nitrogen, phosphorus and
bacteriological parameters.
Two piezometers will be placed on the water table located near the WWTP and the receiving
environment: one in the WWTP and the other near the WWTP downstream wastewater-receiving environment in the direction of flow of the water table1. A control piezometer should be selected
upstream of the WWTP discharge point and adopted as a baseline to measure the impact on the water
table. Two piezometer readings will be taken yearly, one at the end of the rainy season and the other at
the end of the dry season. The readings will concern: (i) the piezometric level; and (ii) the physico-
chemical quality (BOD5, COD, salinity, total nitrogen, total phosphorus and the biological water
quality: Escherichia coli, total coliforms, faecal coliforms and salmonella).
On the water table located near water reuse areas, a control piezometer will be placed in/near each reuse
perimeter in the direction of the water table flow to monitor the water quality and the impact of reuse.
The piezometer will preferably be placed within the perimeter or on a site within a radius not exceeding
400 metres around the perimeter in the direction of the water table flow. Two readings will be taken
yearly, one at the end of the rainy season and the other at the end of the dry season. The readings will
concern: (i) the piezometric level; and (ii) the physico-chemical quality (BOD5, COD, salinity, total
nitrogen, total phosphorus and the biological water quality: Escherichia coli, total coliforms, faecal
coliforms and salmonella).
A groundwater point will be selected upstream of the perimeter and/or reuse area to serve as control in
order to monitor the impact of reuse on the water table.
7.3.3 Framework for Climate Change Adaptation
As a climate change adaptation measure, the programme includes a Wastewater Reuse Component
under which five pilot sites will be set up. This action will enable ONAS to implement some actions in
the small municipalities alongside the works executed to improve the quality of wastewater from major
WWTPs.
7.3.4 Framework for Risk and Hazard Management
WWTPs are classified, unhealthy and hazardous facilities and, hence, require the adoption of strict
safety and hygiene measures from design to personal protection, hygiene and control of hazards. The
WWTP operator must provide personal protective equipment (PPE) such as mono-frame goggles,
respiratory protective equipment (disposable FFP 2 half-mask respirators, gas filters, full-face masks,
etc.), waterproof gloves, etc., as well as work clothes. This equipment should be selected based on the
risks incurred by workers and adapted, regularly maintained and stored in a clean and dry place. Personal
protective equipment supplement collective prevention measures. Hygiene measures help to limit risk
of contamination faced by workers. They should be simple, well-known and implemented by workers.
1 Use existing wells if they are located within 400 metres to 500 metres from the WWTP in the direction of the flow of the water table.
17
In keeping with the regulations governing classified facilities, WWTPs should be the subject of hazard
studies, as well as a plan for the prevention of accidents included in works execution studies. These
studies should include:
- The hazards and risks incurred in interventions in sanitation facilities;
- The prevention of risks in interventions in confined spaces;
- Regulatory requirements and related documents, in keeping with the Labour Code;
- The protective equipment necessary for the operation of WWTPs;
- Measures to prevent the main risks associated with the operation of WWTPs and
sanitation facilities (falling, drowning, noxious gases, etc.).
7.4 Summary of Environmental and Social Measures:
18
Table 5: The Environmental and Social Management Framework to be used during the Execution of Sanitation Works
Potential Environmental Impact Proposed Actions Entity
Responsible
Control/
Monitoring Estimated Cost (TND) Timeframe
1. Institution Building
Disruption of the natural and socio-
economic environment in the
project area
Appoint an environmental and social focal point (ESFP) in ONAS. ONAS FP Considered by ONAS Immediate
Appoint a hygiene and safety (HSE) officer within the Company. Contractor ONAS Included in the contract At project start-up
Recruit an environmental consultant to provide technical support to ONAS in
supervising ESMP implementation. ONAS PF/ONAS ONAS At project start-up
Building the capacity of ONAS and
companies in construction site
environmental management
procedures and guidelines.
Train the senior officers of ONAS in construction site ESMP implementation
and monitoring procedures.
Train the technicians of public works and civil engineering companies in the
mainstreaming of the environmental and social aspects at the construction site
and compliance with regulations.
Sensitize construction workers on compliance with environmental, safety and
hygiene rules and regulations.
ONAS ONAS ONAS
At project start-up
and periodically
during the
execution of
works.
2. Construction Site Installation
Installation of the construction site
Select a location for the installation of the construction site.
Approve the construction site selected by ONAS’ ESFP, in consultation with the
ESMU.
Contractor RPGES
ANPE Included in the contract
Before project
start-up
Define storage areas for building materials, hydrocarbons, water, and waste.
Comply with product storage rules.
Adopt best practices for managing nuisances at the construction site (dust
emissions, wastewater, waste, traffic, noise, etc.).
Contractor RPGES
ANPE Included in the contract At project start-up
3. Construction Site Impact Management Measures
Land tenure- and land use-related
issues.
Changes in land use.
Impact on the population.
Land tenure regularisation:
Compensate project-affected persons.
ONAS
ONAS/Land
Tenure
Service
Considered by the
project Immediate
Restore land.
Restore access roads.
Restore the networks of project-affected concession holders.
Contractor RPGES
ANPE
Modification of the landscape.
Restore land near the project area.
Collect, reuse and/or evacuate excess debris from the construction site to an
approved landfill.
Restore installations (SP, technical premises, buildings, WWTPS, etc.) on the
construction site natural landscape by planting hedges in green spaces.
Avoid traffic in the farmlands located near the construction site right-of-way.
Reinforce signals at the construction site.
Contractor Contractor/
RPGES Included in the contract
Upon project start-
up
Risk of water table and soil
contamination by construction site Dig a watertight wastewater drainage ditch. Contractor
ANPE/
RPGES Included in the contract
Upon project start-
up
19
Potential Environmental Impact Proposed Actions Entity
Responsible
Control/
Monitoring Estimated Cost (TND) Timeframe
sewage: wastewater, contaminated
water from the construction site
(cleaning of vehicles and machines,
emptying of excavations, etc.).
Ensure that the ditch is drained regularly by a company approved by ONAS and
that wastewater is transferred to the nearest WWTP for treatment.
Dig a machine and car wash water drainage ditch and build a machine
maintenance platform on the construction site, if necessary.
Equip the machine and car wash water drainage ditch with an oil
separator/degreaser.
Drain clear water and reuse it to water roads.
Regularly maintain the oil separator and channel the waste grease to approved
treatment centres.
Risk of contamination of surface
water, the water table and soil by
waste oil and fuel leakages.
Equip fuel storage tanks and watertight waste oil retention tanks with sand.
Drain oil-contaminated sand to a specific landfill.
In the absence of a specific platform, prohibit the execution of equipment
maintenance operations at the construction site.
Contractor ANPE/
RPGES Included in the contract
Upon project start-
up
Risk related to machine and vehicle
movement.
Disruption of road traffic and the
movement of people and animals
Design a traffic plan for the movement of machines and vehicles in the project
area.
Provide for the required safety and security measures during the transportation
of construction site equipment and materials.
Cover trucks transporting debris and building materials (sand, gravel, etc.) with
tarpaulins.
Install the required roads signs (machine and truck exit and speed limit).
Water access roads to the construction site and near urban centres and farmlands.
Contractor
ANPE/Traffic
control police/
RPGES
Included in the contract Upon project start-
up
Impact of the accumulation of
construction site waste on water
resources, farmlands and the health
of workers and local residents.
Household waste.
Miscellaneous waste: wood, metals,
plastics, etc.
Special waste: used oils, used oil
filters and grease towels, batteries
and tyres, etc.
Construction waste.
Excess debris.
Collect and dispose of household waste into a controlled landfill.
Ensure the collection and recovery of used oils and filters by SOTULUB.
Collect and store excess debris and construction waste in an area reserved for
that purpose at the construction site and dispose of them into an appropriate
landfill (authorisation by ANGED and municipalities).
Reuse topsoil to develop green spaces.
Collect, sort and place waste (plastics, metal, wood, cardboard, etc.) at the
disposal of recyclers.
Prepare an appropriate area to store waste before channelling it to the landfill for
treatment.
Traceability: register the various types and monthly quantities of waste produced
at the construction site.
Contractor
ANPE
ANGED
Municipalities
RPGES
Included in the contract Upon project start-
up
Occupational hazards at the
construction site. Sensitize and train construction workers on safety and hygiene rules and
regulations. Contractor ONAS
RPGES Included in the contract
Upon project start-
up
20
Potential Environmental Impact Proposed Actions Entity
Responsible
Control/
Monitoring Estimated Cost (TND) Timeframe
Protect hazard-prone areas by adopting appropriate safety measures (work at a
height or in excavations, risk of falling objects, etc.).
Equip workers with PPE (helmets, protective footwear, gloves, goggles, etc.).
Provide for a first aid kit.
Install signs on roads and construction site access roads.
Strengthen control, safety, security and hygiene measures.
4. Rehabilitation and Restoration of the Construction Site Upon Completion of Works
Disruption of farmlands.
Contamination of soil by
wastewater, waste, etc.
Contamination of water by
hydrocarbons and waste oil
leakages.
Dismantle construction site installations.
Rehabilitate septic tanks.
Rehabilitate pits and construction site water collection basins, and treat
contaminated sludge.
Rehabilitate the fuel storage site.
Collect and channel waste to appropriate landfills.
Contractor
ONAS
ANPE
RPGES Included in the contract
Upon project
completion
Table 6: Environmental and Social Management Framework to be used during the Operation of Sanitation Facilities
Proposed Measure Monitoring and Control Actions Frequency and
Assessment
Institution Responsible/
Concerned
Entity
Responsible
Estimated Cost
(TND)
Institutional support and
capacity building
Appointment of ONAS’ Environmental and Social Focal Point
(ESFP).
Appointment of an EO in the WWTP’s Operating Service (sub-
branch).
Appointment of focal points (CRDA, municipalities, Industry,
Health, etc.).
Fielding of a periodic environmental intelligence mission upstream
and downstream of the WWTP.
Periodic reporting (monthly, quarterly and yearly). Technical
assistance in environmental and social management, if need be.
Designation of a civil society association (if necessary) to support
public consultation, communication and complaints management.
Monthly
ONAS (RPGES/EO-WWTP
CRDA/Focal Point
Health/Focal point
Industry/Focal Point
Municipality/Focal Point
ANPE/Focal Point
TA/ESMP
ONAS Envisaged by
ONAS
Building the capacity of the RPGES and the EO of the WWTP.
Building the capacity of the Operating Service and the Health,
Safety and Environment (HSE) Officer of the concession holder
(in case of a private operation).
Information, Education and Communication (IEC) of actors,
beneficiaries and civil society.
Periodic
ONAS (RPGES/EO-WWTP
CRDA/Focal Point
Health/Focal Point
Industry/Focal Point
Municipality/Focal Point
ANPE/Focal Point
TA/ESMP
ONAS Provided in
technical assistance
21
Proposed Measure Monitoring and Control Actions Frequency and
Assessment
Institution Responsible/
Concerned
Entity
Responsible
Estimated Cost
(TND)
Monitoring water quality
(CWW, TWW,
groundwater (EDN),
surface water (EDS))
Industrial waste control: major classified facilities producing
heavy metals, hydrocarbons, oils and fats/phenols.
Monitoring of the volume and quality of water at the inlet/outlet of
the WWTP.
Monitoring the volume and quality of treated wastewater intended
to be reused for agricultural purposes: storage station and basin.
Monitoring the quality of water tables: 3 stations: control, at the
WWTP and in the irrigation area using treated wastewater.
Monitoring the quality of surface water (wadi, lake, sea, etc.): 2
stations: upstream and downstream of ONAS’ discharge points.
Monthly
Monthly
Monthly
Half-yearly
ONAS (RPGES/EO-WWTP
CRDA/Focal Point
Health/Focal point
Industry/Focal Point
Municipality/Focal Point
ANPE/Focal Point
TA/ESMP
ONAS **
Monitoring of noise and
sound nuisances at the
WWTP, SP and other
equipment (vehicles and
maintenance equipment)
Measurement of noise in at least two plants: the WWTP (premises
and work areas): dB01 and SP: dB02 ... B0i.
Measurement of noise 200 metres around the WWTP and SP (at
least 2 plants)
Monthly
ONAS (RPGES/EO-WWTP
Health/Focal Point
TA/ESMP
ONAS **
Monitoring the quality of
ambient air and foul odours:
H2S and other GHGs
Measurement of H2S in at least two plants: WWTP and SP.
Fuel consumption during operation (rolling stock and generators).
Energy consumption (electricity and gas)
Calculation of WWTP GHG emissions.
Monthly
Monthly
Monthly
ONAS (RPGES/EO-WWTP
Health/Focal Point
Municipality/Focal Point
ANPE/Focal Point
TA/ESMP
ONAS **
Management of WWTP
waste and sludge
Collection, storage and disposal of pretreatment waste into
approved landfills and implementation of SP and system
maintenance operations (sand, grease, oil, etc.)
Management of sewage sludge: quantity, quality, quantity reused
and reuse sector
Daily
ONAS (RPGES/EO-WWTP
Health/Focal Point
Municipality/Focal Point
ANGED/Focal Point
TA/ESMP
ONAS **
Monitoring soil quality
Monitoring of moisture content and soil organic matter
Monitoring of heavy metals in the soil (compare with a control
metal).
Annual CRDA
TA/ESMP (if necessary) CRDA **
Health & safety
surveillance
Preventive measures:
Monitoring of the health status of workers in the WWTP.
Monitoring of the health status of workers in the irrigation area.
Monitoring health status in the project area.
Monthly
ONAS (RPGES/EO-WWTP
CRDA/Focal Point
Health/Focal Point
TA/ESMP
ONAS
CRDA
Health
**
Emergency Response Programme (ERP):
Treatment of mosquito breeding grounds within the WWTP site.
Treatment of mosquito breeding grounds outside the WWTP
(systems and SP)
Monthly
ONAS (RPGES/EO-WWTP
Health/Focal Point
Municipality/Focal Point
TA/ESMP
ONAS **
**: The financial estimate is being done, in consultation with ONAS.
22
8. SUB-PROJECT MONITORING AND SUPERVISION ARRANGEMENTS
8.1 Institutional Arrangements
The Environmental and Social Monitoring Unit (ESMU) will control and supervise the implementation
of the ESMF. It will be backed by the services of technical assistance experts provided for under the
programme.
At the local level, institutional arrangements will be organised in ONAS regional departments. An
environmental and social focal point (ESFP) will be part of the staff of each department concerned.
He/she will be in charge of implementing the environmental and social management framework. ESFPs
will also receive support and advice from the central services of ONAS in general, and ESMU in
particular, as well as from the decentralised services of various ministries and national agencies.
An Environment Officer (EO) will be appointed in each WWTP (branch). The EO will be the only
interlocutor of the ESFP and ESMU for ONAS and various project stakeholders. Where a project is
implemented by a construction company or through an operation lease, a Hygiene, Safety and
Environment (HSE) Officer will act as the interlocutor of the focal point and the environment officers
of the WWTP. HSE experts will be responsible for updating the ESMP at project start-up, under the
supervision and guidance of ESMU. These experts will ensure that the Contractor implements the
ESMP. It should be noted that ANPE will also be responsible for control, which falls within its remit as
a public entity, during the construction and operation phases.
Figure 1 below presents a diagram of the relationships between ESMU and various stakeholders and
partners.
Figure 1: Institutional Organisation Chart
23
8.2 WWTP Environmental and Social Surveillance and Monitoring Procedures Manual
The following monitoring templates and forms have been developed for the programme:
- Pro-ESMP.01 : Recruitment of an EMP Consultant
- Pro-ESMP.02 : Appointment of the Environment Officer of the WWTP
- Pro-ESMP.03 : Appointment of focal points
- Pro-ESMP.04 : Template of WWTP ESMP supervision reports
- Pro-ESMP.05 : Template of ONAS’ annual environmental and social management report
- Pro-ESMP.06 : Capacity building
- Pro-ESMP.07 : Monitoring of the quality of wastewater discharges
- Pro-ESMP.08 : Monitoring of noise nuisance within and around the WWTP
- Pro-ESMP.09 : Monitoring of gas emissions
- Pro-ESMP.10 : WWTP waste management
- Pro-ESMP.11 : Monitoring of soil quality in PPI
The table below summarises the environmental surveillance criteria used in a WWTP and in related
facilities.
Table 7: Environmental Surveillance of Sanitation Facilities Components/Activities Monitoring and Evaluation Indicators Responsibility Rate
1. Air quality
Pumping station H2S content
Quantity by instrument
Station manager
Environmental and Social
Focal Point (ESFP)
5/7 days
WWTP H2S content
Quantity by instrument
Station manager
Environmental and Social
Focal Point (ESFP)
5/7 days
2. Noise pollution
Pumping stations Sound level measurement
(<80 dB)
Station manager
Environmental and Social
Focal Point (ESFP)
Weekly
WWTP boosters Sound level measurement
(< 80 dB)
Station manager
Environmental and Social
Focal Point (ESFP)
Weekly
3. Measures envisaged for the management of non-recoverable waste
Screening products Quantity stored Station manager Weekly
De-oiling products Quantity stored Station manager Weekly
Grit removal products Stock position Station manager Weekly
Non-marketed digested /dry
sludge Stock position Station manager Weekly
4. Measures to protect ground water, surface water and receiving water bodies
Overflow of pumping stations Registered, date and reason Station manager Occasionally
Overflow of the WWTP Registered, date and reason Station manager Occasionally
5. Monitoring the quality of wastewater and sludge in the WWTP
Wastewater at the inlet Quality analysis/Average 24-hour
sample WWTP Laboratory 5/7 days
Treated water from the
secondary sedimentation tank
Quality analysis/Average 24-hour
sample WWTP Laboratory 5/7 days
Stabilised/dry sludge Quality analysis/Average 24-hour
sample WWTP Laboratory 5/7 days
Gas composition Quality analysis/Average 24-hour
sample WWTP Laboratory 5/7 days
24
9. COMMUNICATION AND CONSULTATION ARRANGEMENTS
The ESMF has proposed a public consultation framework that aims to ensure the social acceptability of
projects and activities at the community level by establishing a network for sharing information on
environmental issues and on the projects among all actors. The consultation process addresses the need
to fully involve the population in identifying needs and monitoring/evaluating activities to promote
control by citizens, the sharing of knowledge and expertise, participation, and social efficiency.
Similarly, the involvement of local inhabitants guarantees project sustainability inasmuch as it enables
them to own the project and its objectives.
To comply with this comprehensive approach, ONAS is expected to prepare two master plans, namely:
- A plan for communicating with non-governmental organisations;
- A plan for coordinating activities with stakeholders.
The ESMF will be open for public consultation through the Validation Committee comprising the main
donors and representatives of various ministries involved in environmental and social management in
Tunisia. The public will also be involved to express their opinion regarding the design of the
environmental impact assessments of sub-projects and to peruse the ESIA reports systematically posted
on ONAS’ official website.
10. REQUIREMENTS FOR TRAINING AND BUILDING CAPACITY IN ESMF
IMPLEMENTATION
To ensure the sound implementation of the ESMF, the institutional framework hinges on the
establishment of a new Department of Quality, Safety and Environment (DQSE). The Environmental
and Social Monitoring Unit (ESMU) in charge of environmental and social management in general will
be attached to the new DQSE.
ONAS’ Environmental and Social Monitoring Unit (ESMU) will play its environmental and social
management role only if it is provided, on a regular basis and as much as possible in real time, with the
required skilled human resources and information on the status of projects being implemented, and
equipment and infrastructure being operated and their performance, as well as any anomalies and
malfunctions that may occur. To that end, it is necessary to prepare an organisational and technical
capacity-building plan that includes:
- Reinforcing the central level with qualified human resources (a socio-economist
responsible for communication, complaints management, etc.);
- Appointing, at the regional level, focal points as Environment Officers in ONAS’
departments as well as environmental and social branches in each WWTP;
- Organising various training sessions on environmental and social management for
ESMU senior officers and workers.
Since the participatory process instituted by this ESMF will involve the local population, national
entities (ministries and institutions involved), local NGOs and regional partners, the framework provides
for a training and capacity-building plan. The plan is aimed at helping various target groups to
understand public consultation procedures and to ensure the implementation of various phases of public
consultation in accordance with the principles of this ESMF and the requirements of various
international donors by:
25
- Preparing a simplified guide for various target groups to enable them to better
understand and apply the provisions contained in the ESMF regarding the participatory
approach;
- Organising training sessions on public consultation. It is important for the trainers
involved in these training sessions to have the required skills in managing relations with
the public and NGOs, interactive communication, mediation and synthesis.
Concerning complaints management and despite the presence of a “civic interface” on ONAS’ official
website and a toll-free number, the complaints management practices in force are not harmonised,
monitored or evaluated. It is necessary to adopt an action plan to strengthen the communication and
complaints management systems. The plan will include:
- Upgrading the existing system to include the complaints management mechanism
(CMM), ensure information reciprocity to address citizens’ complaints and resolve any
potential social conflict in time;
- Preparing practical and didactic guides to: (i) provide concise information aimed at
facilitating the understanding of the different elements of a communication and
complaints management system; and (ii) present concrete examples to receive, process
and handle various claims. These guides and others will be used as materials for
providing training and assistance for understanding and implementing this ESMF;
- Providing training and technical assistance to build the skills of ONAS’s senior officers
and workers in the participatory approach, environmental and social communication,
and complaints management.
11. ESMF IMPLEMENTATION COST
The ESMF implementation cost covers mainly the training of senior staff, the design and production of
communication and awareness leaflets, the recruitment of environmental and social approach specialists
who will be incorporated into the ESMU as technical assistance staff, and the land procurement plan.
The overall cost estimate is broken down as follows:
Table 8: Breakdown of Programme Cost by Component, including ESMF Implementation Cost
Component/Sub-component Estimated Cost in Million
TND EUR
A Development of Sanitation Facilities 446.9 148.6
B Capacity Building and Institutional Support (including E&S aspects) 3.0 1.0
C Programme Management:
- Environmental and social technical assistance over a 4-year
period, of which 18 months of permanent presence of the
Technical Assistance staff (TA)
- Land Procurement Plan implementation cost
41.3 13.7
Total 491.2 163.3
12. CONCLUSION
The environmental assessment is deemed positive considering that each sub-project is relatively small,
Tunisian regulations provide for the conduct of an ESIA and the implementation of an ESMP for each
new WWTP, as well as the environmental and social management procedures established and adopted
by ONAS. Programme implementation will significantly contribute to improving the living conditions
of inhabitants of target municipalities and protecting the natural environment against the sources of
pollution and degradation. The programme will have no major negative impact on the environment.
26
It will be recalled that any sub-project that has been classified under Environmental Category 1
following the conduct of specific environmental impact assessments will not be included in the
programme, in keeping with the eligibility criteria for financing under this programme. The measures
recommended and arrangements proposed for managing various sub-projects are vital elements for
leveraging and ensuring the sustainability of sanitation facilities, and will help to properly manage
environmental and social risks.
13. REFERENCE DOCUMENTS AND CONTACT PERSONS
13.1 Reference Documents
- Mission for the Design of an Environmental and Social Management Master Plan and
Assistance to ONAS’ Environmental and Social Monitoring Unit – CEFED/SEETE
Group, January 2018 edition.
- Land Procurement and Loss Compensation Framework – ONAS, June 2018.
- Tunisia: Small Towns Sanitation Programme – ONAS –Environmental, Social, Health
and Safety Procedures – Alpage Environmental and Social, March 2018 edition.
- Tunisia: ONAS’ Small Towns Sanitation Programme –– Stakeholder Participation Plan
– Alpage Environmental and Social, April 2018 edition.
- Tunisia: ONAS’ Small Cities Sanitation Programme –Environmental and Social
Assessment Report – Alpage Environmental and Social, March 2018 edition.
- ONAS’ Environmental Policy.
13.2 Contact Persons
For ONAS
Mrs Waslati Dhouha, Programme Monitoring Officer, E-mail: [email protected]
For the AfDB
Mr BenSassi Belgacem, Chief Water and Sanitation Engineer, RDGN.2, E-mail:
Mrs Beya BCHIR, Environmentalist, SNSC/RDGN, E-mail: [email protected]