saic-a-2006 rev 2

Upload: ramesh-palakkad

Post on 14-Apr-2018

257 views

Category:

Documents


3 download

TRANSCRIPT

  • 7/29/2019 SAIC-A-2006 Rev 2

    1/18

    A4

    Effective Corrosion Control & Preservation Measures

    Inspection Coverage and Responsibilities (Package Clearance)

    Clearly detailed provisions for Retesting after reinstatement Evaluations

    by Inspection. Construction related provisions.

    SAES-L-350,

    Para. 17.2

    Welding of attachment welds for non-pressure containing parts such as

    wear pads.info only

    A10 Coating & insulation, steam tracing & final inspection (Clearances) info only

    A11Support Installations & Reinspection of Systems for Plant Piping

    Alignment, clearances, fabrication tolerances and workmanship. info only

    Instrument impulse l ine testing and completion (tested with sytem) info only

    A6

    A8 Installation of valves not tested in the line (field test and cert req'd) info only

    A9

    SAES-L-350,

    Para. 17.2 &

    SAES-A-004,

    Section 9

    Specifically, Procedure shall detail PLAN or STRATEGY to reach

    "SYSTEM" COMPLETION (Quality Certification) as efficiently as

    possible while accomplishing critical goals of:

    A) Effective Water Removal, Disposal & Lay-Up (Post Test)

    No test fluid shall remain in low spots. Specifically, valve cavities.

    B) Test Vents and Drains (plugged, seal welded & PT'd)

    C) Removal & reconnection of components

    All temporary items installed for testing (e.g., manifolds, valves,

    blinds, spacers, supports) shall be removed. Valves Installed. Items that

    were removed from testing shall be reinstalled. Items, such as

    instrument air tubing, check valve discs reconnected (witnessed). Valve

    line-up & gasket installations meet specifications.

    A7

    Completion of open-ended Piping such as drains, vents and piping

    downstream of pressure relieving devices that discharge directly to the

    atmosphere (excluded from in-situ pressure testing).

    info only

    N/A

    MH's SPENT TRAVEL TIME

    PASS

    General Requirements (Complete SATR-A-2007, listed as Attachment 5 & use SATR-A-2011 & SATR-A-6133)

    SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED

    CONTRACTOR / SUBCONTRACTOR

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 1-Dec-06 Piping-

    QR NUMBER

    PROJECT TITLE WBS / BI / JO NUMBER

    PLANT NO.EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID.

    LAYOUT DRAWING NUMBER

    SCHEDULED INSPECTION DATE & TIME

    REV. NO. PURCHASE ORDER NUMBER

    FAIL

    SAUDI ARAMCO INSPECTION LEVEL

    ITEM

    No.

    CONTRACTOR INSPECTION LEVEL

    A1

    Post Test Reinstatement Procedure & Checklist is required to

    be developed in accordance with & as part of pressure testing.

    This is a pressure testing procedure & test package component to be

    developed during package creation as based on workscope & specific

    "system" requirements.

    Comm ent: A standard post-test checklist does not provid e a

    procedu re for reinstatement. A detailed proc edure to give clear

    field direction along with a checklist for this activ ity sh all be

    subm itted before the start of work.

    SAEP-1160,

    Section 8

    Note

    Note: The Pre-Test Checklist & Attachments 1-4 were left in this

    checklist. Many apply to post-test requirements and shall help Contractor

    develop this procedure & checklist. Further assistance can be provided

    upon request.

    info only

    A2

    Inspection strategies & plans shall be prepared and agreed on prior to

    commencing of testing. This is in common with Pipelines.

    Pipelines simply follow their reinstatement procedure.

    SAES-L-350,

    Para. 17.2

    A3

    QUANTITY INSP.

    SAUDI ARAMCO USE ONLYWORK PERMIT REQUIRED?SAUDI ARAMCO ACTIVITY NUMBER

    RE-INSP DATEREFERENCE

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    A

    ACTUAL INSPECTION DATE & TIME

    SAUDI ARAMCO TIP NUMBER

    EC / PMCC / MCC NO.

    ACCEPTANCE CRITERIA

    A5 Seal welding of threaded connections and NDT associated info only

    Page 1 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    2/18

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED QR NUMBER

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 1-Dec-06 Piping-PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

    ITEM

    No.ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE

    C SAIC-A-2010 Checklist (Reinstatement Procedure & Checklist item required (when bold.

    SPEC CHECK SHALL BE UTILIZED BY SAUDI ARAMCO INSPECTORS FOR FIELD WALK-DOWNS (See E-Library, Folder 25)

    C1

    All joints (flange, threaded, welded or mechanical seals) are left exposed

    for visual leak detection during the strength test.

    A) External coating & priming of joints is allowed only if approved by Insp

    Dept Mgr & proponent Organization Representative.

    B) The pipe itself can be externally primed & coated to a final coat.

    SAES-L-150,

    Para. 7.3

    System

    clearance

    (Controls)

    Final Coating

    & Insulation

    Protection

    Controls

    Plan/Strategy

    C2All permanent flange jointswere inspected, gasket mat'l verified &

    properly torqued. (Review Flange joint report, SAIC-L-2014)

    SAES-L-450,

    Para. 9.4

    Final & Perm

    Gasket Install

    Plug, cap seal

    welding, PT

    C3Drains shall be provided at all low points of the piping system.

    Note: Exceptions are submarine & buried* pipelines (*pump-outs)

    SAES-L-150,

    Para. 6.2

    SAES-L-150,

    Para. 6.3

    Water removal

    Lay-up

    C4Vents and drain valves, both temporary and permanent, conforms with

    the piping class or rating. ( Refer SAES-L-108)

    SAES-L-105,

    Para. 5.9

    Tolerances,

    specs

    C6Expansion joints and spring hangers or spring supports are provided with

    temporary restraints.

    SAES-L-150,

    Para. 6.4

    Final alignment,

    specs

    C5

    Supports are installed. Additional temporary support may be

    installed as required.

    N/A

    C7

    Arc strikes, gouges, and other indications of careless workmanship

    (such as surface porosity, uneven weld profiles, and undercut) shall be

    removed by grinding and inspected by magnetic particle or liquid

    penetrant method.

    SAES-W-011,

    Para. 11.6

    SAES-W-011,

    Para. 11.15.1

    rework

    provisions,

    Controls,

    retesting

    C8Temporary welded attachments to the pipe were ground off and

    inspected by magnetic particle or liquid penetrant method

    SAES-W-011,

    Para. 11.7

    pack heavy

    grease

    C10Isolation valves are verified to have been body and seat tested prior to

    installation through verification of field test certificates.

    SAES-L-108,

    Section 4.7

    Valve

    Installation

    C9All threaded joints and faying surfaces shall be seal welded by a

    continuous fillet weld (required weep holes shall be left unwelded).

    C11All in line valves that are not used as test isolation valves are in open

    position.

    SAES-A-004,

    Para. 7.3.2

    SAES-A-004,

    Para. 7.4.2

    Valve Line-up

    C12During water filling, Permanent vent and drain valves are in open

    position and plugged, after water filling and air venting.

    SAES-A-004,

    Para 8.1.1

    water removal

    C14Disc of check valve is removed, unless check valve has by-pass.

    Method for storage (plastic bag & tie) allows visual verification.

    SAES-A-004,

    Para. 7.4.3

    WITNESS

    POINT

    C13 Drains are provided immediately above check valves (vertical lines).

    Repairs

    C15 Spare taps of orifice flanges are plugged and seal welded.SAES-L-110,

    Para. 8.2

    SAES-A-004,

    Para. 7.2

    C16All threaded joints up to the first block valve of hydrocarbon pipeline are

    seal welded. Thread engagement has been verified & accepted.

    SAES-L-110,

    Para. 8.2

    Reconnect

    C18

    The pressure testing manifold is separately pressure tested to at least

    1.2 times the system test pressure but not less than the discharge

    pressure of the pump used for the pressure testing.

    SAES-A-004,

    Para. 5.5.4Preservation

    C17Process instruments and equipment that may be damaged by the

    strength test pressure are disconnected.

    M&TE

    C19Buried pipeline are adequately bermed or covered to anchor the line

    during pressure test.

    SAES-L-450

    Appendix C

    SAES-A-004,

    Para. 7.3.1

    Inspection

    C20Pressure gages and pressure recorders are calibrated within one (1)

    month before the test. Check stickers at the time of th e test.

    SAES-A-004,

    Para. 7.1.5 (a)

    P&ID Line-up

    C22A bleed valve readily accessible is provided in case immediate

    depressurization is required.

    SAES-A-004,

    Para. 5.5.2

    C21Paddle or spectacle blinds shall be used to isolate test sections.

    Safety of test "implements" has been checked (SAIC-A-2009)

    Page 2 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    3/18

    Reconnect

    C23

    EVALUATE CLEANING (PROCEDURES) & PROPOSED LAY-UPS:

    For pipe up to 12-inch NPS - flushed clean of loose scale/debris or

    scraped prior to commencement of pressure testing per procedureNote 1: If flushing was done with valves in line, cavity cleanliness is

    highly suspect where no low point drains exist. Verify post-test removal

    of scale/debris/water in low points (Check valve cavities).

    Random veri f icat ion involves Inspect ion of valve cavi t ies.

    This is a standard comm ent or addit ion to the punch l ist .

    Note 2: Internal Cleaning procedure for pipe size larger than 14 inch

    shall be submited for review and approval) See SATIP-L-108.

    Flushing Cert is available in the test package for review

    SAES-A-004,

    Para. 7.1.2

    Inspection

    Excellence

    Water removal

    & Preservation

    & LAY-UP

    (Follow-up)

    C24

    All pressure containing components of pipeline, except instruments that

    may be damaged by the test pressure, were physically verified to be

    included in test using P&ID, ISOs (Pressure Test Diagram)

    SAES-A-004,

    Para. 5.6.1

    Verify correct

    specs all special

    processes

    C26

    Use SAIC-A-2011 along with this

    checklist (inspection efficiency)

    whenever walkdown is done on

    the same day as press. testing

    As Referenced

    C25PRE-TEST SPEC CHECK

    SEE ATTACHMENT 4.

    REMARKS:

    REFERENCE DOCUMENTS:

    1. SAES-A-004, General Requirements for Pressure Testing, (30 March, 2005)

    2. SAES-L-105, Piping Material Specifications, (30 March, 2005)

    3. SAES-L-108, Selection of Valves, (30 March, 2005)4. SAES-L-110, Limitations on Pipe Joints and Components, (30 March, 2005)

    5. SAES-L-150, Pressure Testing of Plant Piping and Pipelines, (30 September, 2003)

    6. SAES-L-350, Construction of Plant Piping, (30 September, 2003)

    7. SAES-L-450, Construction of On-Land and Near-Shore Pipelines, (30 September, 2003)

    8. SAES-W-011, Welding Requirements for On-Plot Piping, (30 March, 2005)

    Contractor / Third-Party Saudi AramcoConstruction Representative* PMT Representative

    Name, Initials and Date:

    Work is Complete and Ready for Inspection:

    Name, Initials and Date:

    T&I Witnessed QC Record Reviewed W ork Verified

    QC Inspector PID Representative

    Name, Initials and Date:

    Performed Inspection Work / Rework May Proceed

    Name, Initials and Date:

    T&I Witnessed QC Record Reviewed W ork Verified

    QC Supervisor Proponent and Others

    Name, Sign and Date:

    Quality Record Approved:Name, Organization,

    Initials and Date:

    T&I Witnessed QC Record Reviewed W ork Verified

    *Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 1-Dec-06 Piping-PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

    ITEM

    No.ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE

    Page 3 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    4/18

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 1-Dec-06 Piping-

    Attachment 1 -- SAEP-1160 Section 8 (Test Pkg Minimum Content)

    Attachment 2 -- NEMA TC 2 (Type EPC-40-PVC)

    Page 4 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    5/18

    Attachment 2 -- TEST PACKAGE FLOW CHART

    Test Package (or Test System) No

    Test Pack

    Preparation Engineering Contractor QC

    Pre-Test

    Punch

    Listing

    (NOTE: Use form SATR-A-2007)

    Construction Contractor QC

    S. Aramco

    Pre-Test

    PunchListing

    SAPMT PID Proponent(By Request)

    Clear 'A'

    Items Construction Contractor QC

    Clear

    S. Aramco

    'A' ItemsConstruction Contractor QC SAPMT PID

    Flushing &

    Cleanliness Construction Contractor QC SAPMT PID Proponent

    (By Request)

    Pressure

    Testing Construction Contractor QC SAPMT PID Proponent

    System

    Lay-Up Construction Contractor QC SAPMT PID Proponent

    (By Request)

    Reinstate

    System

    Final Insp

    (Contractor)Construction Contractor QC SAPMT

    S. Aramco

    Final Insp

    for MCCSAPMT PID Proponent

    Page 5 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    6/18

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 1-Dec-06 Piping-

    Attachment 3 -- Pressure Testing Matrix for On-Plot Piping (Incl. UG Utilities, FW & Plumbing)

    ON-PLOT NEW B31.1 & B31.3 CODE PRESSURE PIPING (SATIP-A-004 Series)

    SYSTEM TEST PRESS

    & DURATION

    TEST CONSIDERATIONS & NOTES

    Process

    Piping

    As Calculated*

    30 mins (min)

    Piping Line Class List (Hydrotest Spec) lists all new process piping line classes (strength test

    required per code) with exceptions for Service Test and other tests as noted below. NDE in lieu of

    pressure test may be performed if requested & approved by SA Insp. Dept. Mgr. Process requestsper Sect 5 of SAES-A-004, and at a minimum, 30 days ahead of testing.

    *Note: Unless limited by flanges, valves or other component (exceptions below), hydrostatic strength test pressures for every section of new

    constructed line shall produce a hoop stress in pipe of 90% SMYS at test temperature. See Exceptions Below.

    Lube & Seal Oil

    Systems

    See Notes

    30 mins (min)

    *Lube & seal oil piping is pressure tested with its own fluid at 1.5 times design pressure or 100 psig,

    whichever is greater. Chemical cleaning precedes pressure testing. Joints shall be completely

    cleaned* (oil free) before testing. *Baby Powder works best to clean/dry joints

    Note: Leaks are common, difficult to identify as "active" or "non-active". Perform preliminary tests to identify all leaks, especially at flanged and

    threaded joints. When evaluating leakage, utilize clean dry cloths to identify "active" leaks for repair. Oil residue found after wiping the joints (check

    low points carefully) is cause for clean and retest. Always wait a minimum of 30 mins after wiping joints before reevaluation.

    Underground

    Process Piping

    As Calculated

    See Notes

    A) Test prior to backfilling (all joints exposed) & maintain test pressure for a minimum of 2 hrs B) If

    justifiable (safety) & line must be back-filled, a 24 hr recorded test (Chart Recorder) reqd.

    Flare Lines

    (24" & above)

    See Notes

    30 mins (min)

    Flare lines 24-inch NPS & larger with a design pressure of 75 psig or lower may be strength tested

    pneumatically (75 psig is tested at 1.1 factor or 82 psig) per Para. 345.5 of ASME B31.3Note: Test limits shall be downstream of isolation valves (beyond PZVs & locked valves for equipment). Portions of the test may be less than 24

    inches from these valves to the flare header branch connection. Flare system Isolation Valves receive a pneumatic seat test at 5 psig in lieu of a high

    pressure seat hydrotest. Conduct this test on a weekend to minimize personnel exposure. Perform a stored energy calc when requested by

    Company. Test limits utilize blind flanges at removed isolation valve locations. Follow Pneumatic Testing SATIP.

    Vacuum Piping See Notes30 mins (min)

    Tested to 1.5 times the differential external pressure, but not less than 15 psig.

    Air & Inert Gas

    (150 psig max)

    SERVICE TEST &

    Soap Bubble Test

    30 mins (min)

    Perform a preliminary soap bubble test at 5-10 psig after construction is complete & threaded joints

    are checked for engagement (two full visible thread rule). Coordinate with Compressor and Receiver

    Service tests and final gasket installation.

    LP Steam

    (60 psig max)

    SERVICE TEST

    30 mins (min)

    Coordinate with system Service tests and construction completion.

    Weld-Plus-Ends Soap Bubble LeakTest at 5-10 psig

    Weld-Plus-Ends shall be subjected to a pneumatic pressure test of 5 to 10 psig in the annulus

    between the gasket and the seal weld. It shall be examined for leaks using a soap solution.

    Existing Plant

    Piping

    Incl. Tie-Ins

    As Calculated*

    30 mins (min)

    For revalidation purposes of existing plant piping, the test pressure shall be minimum required by the

    Code ASME B31.3. The actual wall thickness of the piping and flange rating shall be determined and

    taken into consideration when calculating the test pressure. In case of flanged tie-in connections, a

    flange tester is utilized to conduct hydrostatic testing of flange butt weld.

    RETESTING

    REQMTS

    See Notes Systems that already passed a successful pressure test require RETEST IF subjected to new

    welding activities (Modifications, repair to pressure boundary) OR IF PWHT is reqd*.

    Note: Seal welds of threaded connections & Attachment welds of non-pressure containing parts, such as wear pads DO NOT REQUIRE RETEST

    UNLESS THE LINE REQUIRES PWHT (Including attachment welds & seal welds to the pressure boundary).

    REPAIR

    EXISTING

    PIPING

    See Notes Every existing plant piping & pipeline, after repairs or alterations have been made that affect the

    integrity of the pressure containing parts, shall successfully pass a hydrostatic test. The test pressure

    shall be in accordance with the requirements of the applicable code.

    Note: SAEP-310 requirements apply as well for pressure testing after Repairs, Upgrades, Refurbishment, etc

    Open-EndedPiping

    EXEMPT,VISUAL EXAM

    Drains, vents & piping downstream of pressure relieving devices that discharge directly to theatmosphere (max internal pressure 10 psig) are EXEMPT from testing. Drain holes installed, etc

    Note: Test Package SIS Sheet shows design data & "EXEMPT" under required test pressure. Line(s) shall be visually examined.

    Instrument

    Impulse Lines

    As Calculated*

    30 mins (min)

    Whether piping or tubing, between the root isolation valve and the instrument isolation shall be

    pneumatically pressure tested (air or nitrogen) at 1.25 X design pressure of the piping system or

    process equipment to which it is connected. Test duration shall not be less than 30 minutes.

    Note: Instrumentation that could be damaged due to the test shall be disconnected. When pneumatic test is not practical (pressure greater than

    1000 psig, physical configuration, etc.) test with liquid or water. (Flush, test & dry clean using a quality of water not harmful to lines).

    Internally FBE

    Coated Lines

    As Calculated*

    30 mins (min)

    For internally Fusion Bonded Epoxy (FBE) coated piping system, the test pressure shall not exceed

    5,000 psi for APCS 100, 101, 103 systems & 3,000 psi for APCS 102 System

    Note:ALL Welding shall be completed (Design Issue), all internal coating and Holiday Testing PRIOR TO pressure testing.

    Page 6 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    7/18

    Sampling Lines See Note Test as an integral part with the piping or equipment to which it is connected.

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2

    Vessel & Tank

    Trim (Piping)

    See Note Test separately (separate package) as required. Exemptions include sight glasses &

    other instruments. Strength or Service test associated piping based on service

    Note:ALL Code Piping construction (in-situ) that is not VENDOR supplied shall be tested. Utility = Service Test, Process = Strength Test

    Skid-Mounted

    Piping (Vendor)

    EXEMPT IF TESTED BY VENDOR

    per 01-SAMSS-010

    (exceptions noted)

    1. When testing with adjacent Lube oil system piping (no leaks = acceptance).

    2. When code repairs are made to skid-mounted piping to correct misalignment,

    physical damage or any modifications in-situ, pressure test the affected spools.

    FIELD HYDROTESTING OF NEW VALVES (SAES-L-108, Section 4.7 & SATIP-L-108 & SAIC-L-2042)

    Test Location See Note Location shall be specified by proponent & PID approved. SAIC-A-2031 Sect. J

    Field Testing of

    New Valves

    See Note All new valves designated for isolation service (as specified by the Proponent) shall be

    subjected to high pressure hydrostatic seat test prior to installation in line.

    Exception See Note Low pressure pneumatic seat test at 5 psig shall be substituted for high pressurehydrostatic seat test for flare system valves. Identify & Segregate Early!!!

    Exemption See Note Buttweld & socketweld end valves in NPS 2 inches and smaller are exempt

    Procedure(Checklist Item D4)

    See Note Test procedures, pressures, durations, & leakage acceptance criteria shall be equal to

    those that the valves were originally purchased to. All resilient (soft) seated isolation

    valves shall have zero leakage. See SAIC-L-2042

    Note: Proponent specifies those Line Classes and valves subject to field hydrotesting. Valves received shall be carefully identified & given a unique

    ID number for installation into the correct Line Class based on visual verification of construction stamp. Valves shall be given a unique ID &

    corresponding test report document upon receipt, Valve ID shall be controlled, documents transferred into appropriate Test Pkg & Database (PipingSystem, Line Class, Line Number, Location) per SAEP-1160. Procedure identifies all critical aspects of Valve Testing incl Receipt Inspection (internal

    visual exam by qualified Inspector), pressure test, ambient lay-up (corrosion protection per mfg instructions & follow-up preservation reqmts) &

    segregation control to prevent "mixing valves". Controlled System for Valve Placement exists.

    SPECIFIC TESTING REQUIREMENT SUMMARY (ALL SA APPLICATIONS PER SAES-L-150, Section 6)6.1 Plant Piping - Pressure testing of On-Plot Plant Piping shall be per SAES-L-150. See Section D of this Checklist.

    6.2 Cross-Country Pipelines - Pressure testing of cross country pipelines shall be per SAES-L-150. See Section C of this Checklist.

    6.3 Pressure Vessels - Hydrostatic testing for new vessels (shop or field fab) shall be conducted as follows:

    ASME Section VIII, D1 to SAMSS-004, Para 16.3.8.1. & ASME Section VIII, D2 to 32-SAMSS-004, Para 16.3.8.2

    Hydrostatic testing for existing vessels shall be conducted per SAES-D-008, Paragraph 10.1.

    Pneumatic test as approved by Insp Dept Mgr (UG-100 of ASME SEC VIII D1, OR T-4 of ASME SEC VIII D2)

    6.4 Heat Transfer Equipment - Hydrostatic tests for existing equipment shall be per SAES-D-008.

    For pneumatic testing, refer to same as above for Vessels (UG-100 of ASME SEC VIII D1, OR T-4 of ASME SEC VIII D2)

    Boilers receiving Hydrostatic test (new, field fabricated boilers) shall be in accordance with 32-SAMSS-021.Boiler pressure test After Repair or Alteration, refer to SAES-D-008 & National Board Insp Code, NB-23.

    Boiler Hydrostatic test during T&Is shall be per test pressure as specified on boiler's safety instruction sheet.

    Heater Tube (coil) Assy Hydrostatic test for new, field fabricated heater tube assembly shall be per 32-SAMSS-029.

    Heat Exchanger Tube bundles removed from X-chgr (maintenance) get in-situ shell side test per SAES-D-108 prior to return to service

    Fin Fan X-chgr is strength tested (as stamped) in-situprior to final acceptance (new project), & whenever transported.

    6.5 Tanks - For new, field fabricated tanks, & existing tanks, hydrostatic testing shall be per 32-SAMSS-006 for large, low pressure welded tanks;

    or 32-SAMSS-005 for atmospheric steel tank, as applicable.

    6.6 Fire Protection Systems - Pressure test new & existing fire protection systems (SAES-B-017, GI-1781.001).

    6.7 Refrigerant Piping Systems - Refrigerant piping serving building air conditioning systems shall be tested according to the requirements of SAES-

    K-001 and the Uniform Mechanical Code (UMC), Section 1520.

    6.8 Potable Water Systems - Potable water piping inside buildings shall be tested per the reqmts ofUniform Plumbing Code (UPC). Exceptions

    to UPC requirements are listed in SAES-S-060. THERE ARE 3 MAJOR EXCEPTIONS FOR INSPECTION AWARENESS

    Potable water piping outside of buildings shall be tested per the requirements of SAES-S-040 (SAES-S-070, Section 18).

    6.9 Utility Piping Systems - Utility systems, including irrigation piping & water distribution mains, shall be tested per SAES-S-070, Sect 18

    6.10 Industrial Drainage and Sewers - Industrial drainage and sewers shall be tested per SAES-S-020 (SAES-070, Section 18).

    6.11 Sanitary Sewers - Sanitary sewer systems within buildings shall be tested per reqmts of the Uniform Plumbing Code (UPC). Exceptions to

    UPC requirements are listed in SAES-S-060. THERE ARE 3 MAJOR EXCEPTIONS FOR INSPECTION AWARENESS

    Sanitary sewer lines outside of buildings shall be tested in accordance with SAES-S-070 Section 18.

    6.12 Storm Water Drainage Systems - Test per SAES-S-030 (SAES-S-070, Section 18) Note: Only OWS portions are tested.

    6.13 Miscellaneous Building Services Piping - Steam & condensate piping outside the jurisdiction of ASME B31.3, heating & cooling water piping,

    vacuum & compressed air system piping for building services shall be tested per ASME B31.9, Building Services Piping.

    6.14 Gas Cylinders - Gas cylinders shall be tested per Saudi Aramco Bottled Gas Manual. (Application - New Labs, etc)

    6.15 Valves - Valves shall be tested in accordance with SAES-L-108, Section 4.7

    6.16 Non Metallic Piping - Such as RTR, Thermoplastic, PVC/UPVC & CPVC shall be tested per SAES-S-070, Section 18.

    31-Dec-05

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 1-Dec-06 Piping-

    Page 7 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    8/18

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 1-Dec-06 Piping-

    Attachment 4 - SPEC CHECK INSTRUCTIONS1) Test Package Review Tool & Special Process Clearance Verification BEFORE Hydrotest.

    a. Use Spec-Check along with SAIC-A-2003 (Checklist for Hydrotest Package Review) & this checklist.

    b. Check test package Bill of materials against piping line class requirements (See sample Spec Check)

    c. Check NDT requirements in SPEC-CHECK against NDT enclosed in given test packages. Check for correct NDT

    extent specified and correct NDT methods. Check NDT reports and compare RT field markings to the test reports.d. Check RT reports closely for repairs (repair shots, penalties) & field verify the markings exist on the correct joint.

    Note: If discrepancies exist, simply review the film and follow NDT checklists for RT (Clear direction exists here).

    e. Shop/Field Weld NDT requirements vary and need to closely checked for omission of work. (10% shop, 100% fld)

    f. Check PWHT reports against material spec requirements (service, thickness, etc). Verify visually PWHT was done

    g. Check BHT reports against spec requirements (sweet & sour services). Verify roundness of Brinnell indentation.

    h. PMI OK markings exist on those joints PMI examined. Verify markings to correct joint.

    i. Check color codings of materials to assure correctly specified material was used in piping systems.

    2) Check field installations (Pre-Hydro Walkdown, Surveillances) for following special processes:

    a. Gasket Installation HOLD POINT FOR CONTRACTOR - Visual before installation, Color code Table

    CRITICAL: COLOR CODES EXIST FOR ALL GASKETS (TABLE COVERS ALL GASKETS IN ALL LINE CLASSES)

    b. Bolting Installation & Torque (Bolts, Nuts, Lubricants, Friction Factors, See Torque Tables)

    c. Valve Installations (Check Valves installed against SAES-L-105 Spec Table Attached)d. Piping specs and piping schedules cab be included

    e. Check Spectacle plates, blinds, spacers, Jack screws, etc for SPECIFIC SASD DRAWING conformance.

    f. Check miscellaneous material elements (Class & pressure ratings for weld bosses, fittings) & Limitations (L-110)

    g. Check WPS and any special instructions needed per welding (invaluable tool for Control)

    3) Perform FOCUSED ASSESSMENTS with both CHECKLISTS & SPEC-CHECK

    4) Perform Focused Assessments with Spec-Check alone on all specified Materials

    5) Perform Focused Assessments with Spec-Check alone on Special Construction Processes.

    6) Perform Post-Hydro Checks in the field (Reinstatement, FEIL, Pre-Commissioning, Commissioning)

    a. During Reinstatement, Use Spec-Check along with SAIC-A-2010 (Checklist for Hydrotest Reinstatement) to

    ensure correct installation (Bolting, valves, etc)

    b. During FEIL walkdowns, use Spec-Check during accumulation of Field Exception Items List (FEIL)

    c. During Final walkdowns, use Spec-Check one last time (Pre-Commissioning, Commissioning)

    7) Add notes for: WPS Review/Compilation after Review of Line Class Tables, Valve Spec codes, flanges,

    special walk down notes, supports, etc by using a numerical code and hand written notes on back!

    SPEC-CHECK can be modified for any item. Ensure the best quality on your project! Check all specs

    Test Package Review Notes1. Check status sheet for signoffs.

    2. Check Index against contents

    3. Pressure Test Data Sheet Check drawing numbers against actual enclosed Check excluded equipment & especially if there are any P&ID notes Check pressure test value proposed to assure limiting factor is correct (usually a flange)4. Do a Weld Tracker NDT report review (detailed) Compare completed Special Process reports (RT, MT, PT, PWHT, BHT, PMI, etc)

    Compare against list of outstanding NDT (Backlog of Penalty & Repairs)5. Review P&IDs and isometrics against spec check for line class required materials (drawings often are in error)Note: Make note on cover in Punch list Accepted by PID Field verify against Spec/B.O.MThis is especially critical for Sour Service & Special Service lines.Note: Ensure orifice flange reports are included & any NDT specified6. Check hydrotest diagram Manifold arrangement sketches must show all elements, & manifold construction/insp must be per SAIC-A-2009Caution: Ensure test pressures do not exceed manifold element ratings (Valves are next size up for systems tested)Example 1: Class 300 # systems(1125 psi) would utilize a Class 600 Isolation valves in test manifolds at minimum.Example 2: A manifold with 800# gate valves will not be used in testing 600# systems (2250 psig)Reason: You are testing against the valve seat (closed position) & this is rated for 1.1 times test pressure, not 1.5.

    See Next Page for Spec Awareness (Basis for Spec Check on Projects)

    Page 8 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    9/18

    SPEC AWARENESSPIDs ATTENTION TO SPECS & SPEC-Check(Piping Line Class Specs, WPS, NDT Specs, PWHT, PMI, etc) on Projects:Initial Review of SPECS1. Carefully recheck Contractor Piping Specs (Line Class Summary & Tables) as early as possible during or just

    after Design is complete (as soon as they are issued and available).2. This is done by checking Contractors specs against Line Class Material requirements listed in SAES-L-105. Givespecial attention to critical systems & systems above 300#.3. Average large projects can have as many as 50 different piping specs & details can be very hard to pick up in the

    field. Pipelines have fewer specs and are easier to manage. THIS INCLUDES THE MAZE OF GASKETS!!!4. Time taken for early review only takes an experienced plant inspector 2 days of review. Findings (often humanerror) can be critical. Help prevent unplanned shutdowns on your projects & find substandard material specs beforethey are installed or before they enter service.5. Carefully check Contractor Special Process SPECS (WPS, NDT, PWHT, etc) as early as possible (as soon asthey are issued and available).6. This is done by checking Contractors Special Process Specs against code and SA requirements (SAES-W-011,Sect 17 for NDT & 13 for PWHT). SAES-W-012 is similar to SAES-W-011 in this respect7. Ensure that notes are included in these SPECS that require increased NDT based on field welding and other

    code considerations.8. Clear violations such as our weekly highlight example (such as specs and drawings that use 3000# fittings on a900# system instead of required 6000# fitt ings) must be itemized & brought to SAPMT attention early.See attached Sample Weekly Highlight.9. After all SPECS submitted by Contractor are accepted ... CREATE your custom SPEC-CHECK (sampleattached with instructions).Commentary: This is a valuable review and exercise for all inspectors. Have all inspectors trained in this task forself-reliance during future projects. This teaches critical lessons in Materials*, specification requirements* andsubstandard installation identification*.*FACT: MOST INSPECTORS ARE WEAK REGARDING KNOWLEDGE OF SPECIFICATIONS & ARE UNAWAREOF MANY CRITICAL REQUIREMENTS! SPEC CHECK PUTS THESE DOWN ON PAPER (BY SYSTEM)

    Test Package Review & Pre-Hydro Walkdow

    1. Follow-up (after initial specification review/approval) can also include checking ISO drawings and bill of materialsagainst approved specs before Pre-Hydro Walkdown2. USE YOUR CUSTOM SPEC-CHECK on every new plant project as the perfect walk down and test packagereview tool. Important Note: Never assume drawings or test packages are correct. Never assume NDE % & PWHT,PMI, etc performed/not performed by contractor is correct.Inspectors must be taught a systematic review method for test packs with focus on Specs.A thorough test package review system is a page by page review that takes only 15 minutes per package & checksevery page and every weld & all materials for completeness/correctness. Omission of Special Process work byContractor is widespread & frequent, most often unintentional and simply due to a lack of AWARENESS.

    Surveillance & Focused Assessment1. Use SPEC-CHECK on routine surveillance.

    2. Create a custom SPEC-CHECK for focused assessments on Valves.Incorrect valve installation is very common with valves placed in the wrong service (swapped, mislocated, mismark)3. Create a custom SPEC-CHECK for focused assessments on small diameter piping (UT purposes). Past projectshave seen as many as 20% of all piping segments installed of the wrong schedule of piping (J-80, RT Refinery). Ivisit projects and find numerous substandard installations very often (human error, again). On your project,order/request/perform/get Contractor to do random checks of small diameter piping segments (2 & below). I do itmyself with a 2-man crew with me, piping schedules in hand on all my projects & run at about a 2% reject rate.4. Create a custom SPEC-CHECK for focused assessments on PWHT & BHT. Past projects have seen poorpractice with failure to follow 12-step BHT procedure per NACE RP-0472 App A.5. Turn your project surveillance into an effective and efficient Inspection asset that is valuable to Projects.

    SHARE SPEC CHECK WITH YOUR CONTRACTOR FOR QUALITY

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 1-Dec-06 Piping-

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

    Page 9 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    10/18

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    Plug, cap seal

    welding, PT

    N/A

    Final alignment,

    specs

    rework

    provisions,

    Controls,

    retesting

    RE-INSP DATEITEM

    No.ACCEPTANCE CRITERIA REFERENCE PASS N/A

    Tolerances,

    specs

    WITNESS

    POINT

    Final & Perm

    Gasket Install

    Water removal

    Lay-up

    Final Coating

    & Insulation

    Protection

    Controls

    Plan/Strategy

    Valve Line-up

    pack heavy

    grease

    C4Vents and drain valves, both temporary and permanent, conforms with

    the piping class or rating. ( Refer SAES-L-108)

    SAES-L-105,

    Para. 5.9

    C5

    Supports are installed. Additional temporary support may be

    installed as required.

    SAES-A-004,

    Para 8.1.1

    Buried pipeline are adequately bermed or covered to anchor the line

    during pressure test.

    SAES-L-450

    Appendix C

    SAES-L-110,

    Para. 8.2Spare taps of orifice flanges are plugged and seal welded.

    All threaded joints up to the first block valve of hydrocarbon pipeline are

    seal welded. Thread engagement has been verified & accepted.

    FAIL

    C22

    QR NUMBER

    PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006

    SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED

    1-Dec-06 Piping-

    Repairs

    SAES-L-108,

    Section 4.7

    Valve

    Installation

    SAES-W-011,

    Para. 11.7

    Arc strikes, gouges, and other indications of careless workmanship

    (such as surface porosity, uneven weld profiles, and undercut) shall be

    removed by grinding and inspected by magnetic particle or liquid

    penetrant method.

    SAES-W-011,

    Para. 11.6

    All in line valves that are not used as test isolation valves are in open

    position.

    SAES-L-150,

    Para. 6.2

    SAES-L-150,

    Para. 6.3

    C

    C3

    C2All permanent flange jointswere inspected, gasket mat'l verified &

    properly torqued. (Review Flange joint report, SAIC-L-2014)

    SAES-L-450,

    Para. 9.4

    Isolation valves are verified to have been body and seat tested prior to

    installation through verification of field test certificates.

    C8

    Expansion joints and spring hangers or spring supports are provided with

    temporary restraints.

    SAES-L-150,

    Para. 6.4

    Temporary welded attachments to the pipe were ground off and

    inspected by magnetic particle or liquid penetrant method

    C7

    Drains shall be provided at all low points of the piping system.

    Note: Exceptions are submarine & buried* pipelines (*pump-outs)

    C1

    All joints (flange, threaded, welded or mechanical seals) are left exposed

    for visual leak detection during the strength test.

    A) External coating & priming of joints is allowed only if approved by Insp

    Dept Mgr & proponent Organization Representative.

    B) The pipe itself can be externally primed & coated to a final coat.

    SAES-L-150,

    Para. 7.3

    System

    clearance

    (Controls)

    C12

    C14

    During water filling, Permanent vent and drain valves are in open

    position and plugged, after water filling and air venting.

    C6

    C11

    C10

    SAES-A-004,

    Para. 7.3.2

    C13 Drains are provided immediately above check valves (vertical lines).SAES-A-004,

    Para. 7.4.2

    SAES-A-004,

    Para. 7.2

    SAES-L-110,

    Para. 8.2

    SAES-A-004,

    Para. 5.5.4

    A bleed valve readily accessible is provided in case immediate

    depressurization is required.

    SAES-A-004,

    Para. 5.5.2

    C21Paddle or spectacle blinds shall be used to isolate test sections.

    Safety of test "implements" has been checked (SAIC-A-2009)

    SAES-A-004,

    Para. 7.3.1

    SAIC-A-2010 Checklist (Reinstatement Procedure & Checklist item required (when bold.

    P&ID Line-up

    water removal

    Reconnect

    M&TE

    C16

    The pressure testing manifold is separately pressure tested to at least

    1.2 times the system test pressure but not less than the discharge

    pressure of the pump used for the pressure testing.

    C17Process instruments and equipment that may be damaged by the

    strength test pressure are disconnected.

    Preservation

    Inspection

    C9All threaded joints and faying surfaces shall be seal welded by a

    continuous fillet weld (required weep holes shall be left unwelded).

    SAES-W-011,

    Para. 11.15.1

    C15

    Disc of check valve is removed, unless check valve has by-pass.

    Method for storage (plastic bag & tie) allows visual verification.

    SAES-A-004,

    Para. 7.4.3

    SPEC CHECK SHALL BE UTILIZED BY SAUDI ARAMCO INSPECTORS FOR FIELD WALK-DOWNS (See E-Library, Folder 25)

    C20Pressure gages and pressure recorders are calibrated within one (1)

    month before the test. Check stickers at the time of th e test.

    SAES-A-004,

    Para. 7.1.5 (a)

    C18

    C19

    Page 10 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    11/18

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    RE-INSP DATEITEM

    No.ACCEPTANCE CRITERIA REFERENCE PASS N/AFAIL

    QR NUMBER

    PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED

    1-Dec-06 Piping-

    C26

    Use SAIC-A-2011 along with this

    checklist (inspection efficiency)

    whenever walkdown is done on

    the same day as press. testing

    As Referenced

    QC Inspector PID Representative

    1. SAES-A-004, General Requirements for Pressure Testing, (30 March, 2005)

    2. SAES-L-105, Piping Material Specifications, (30 March, 2005)

    3. SAES-L-108, Selection of Valves, (30 March, 2005)4. SAES-L-110, Limitations on Pipe Joints and Components, (30 March, 2005)

    5. SAES-L-150, Pressure Testing of Plant Piping and Pipelines, (30 September, 2003)

    6. SAES-L-350, Construction of Plant Piping, (30 September, 2003)

    7. SAES-L-450, Construction of On-Land and Near-Shore Pipelines, (30 September, 2003)

    8. SAES-W-011, Welding Requirements for On-Plot Piping, (30 March, 2005)

    Name, Initials and Date:

    Performed Inspection Work / Rework May Proceed

    Name, Initials and Date:

    Construction Representative*

    Name, Initials and Date:

    Work is Complete and Ready for Inspection: T&I Witnessed

    Name, Initials and Date:

    PMT Representative

    REFERENCE DOCUMENTS:

    REMARKS:

    *Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

    T&I Witnessed QC Record Reviewed

    Name, Sign and Date:

    QC Record Reviewed

    Work Verified

    Contractor / Third-Party

    Quality Record Approved:Name, Organization,

    Initials and Date:

    T&I Witnessed QC Record Reviewed W ork Verified

    Saudi Aramco

    Work Verified

    QC Supervisor Proponent and Others

    Verify correct

    specs all special

    processes

    C24

    All pressure containing components of pipeline, except instruments that

    may be damaged by the test pressure, were physically verified to be

    included in test using P&ID, ISOs (Pressure Test Diagram)

    SAES-A-004,

    Para. 5.6.1Reconnect

    C25PRE-TEST SPEC CHECK

    SEE ATTACHMENT 4.

    Inspection

    Excellence

    Water removal

    & Preservation

    & LAY-UP

    (Follow-up)

    C23

    EVALUATE CLEANING (PROCEDURES) & PROPOSED LAY-UPS:

    For pipe up to 12-inch NPS - flushed clean of loose scale/debris or

    scraped prior to commencement of pressure testing per procedureNote 1: If flushing was done with valves in line, cavity cleanliness is

    highly suspect where no low point drains exist. Verify post-test removal

    of scale/debris/water in low points (Check valve cavities).

    Random veri f icat ion involves Inspect ion of valve cavi t ies.

    This is a standard comm ent or addit ion to the punch l ist .

    Note 2: Internal Cleaning procedure for pipe size larger than 14 inch

    shall be submited for review and approval) See SATIP-L-108.

    Flushing Cert is available in the test package for review

    SAES-A-004,

    Para. 7.1.2

    Page 11 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    12/18

    Attachment 2 -- NEMA TC 2 (Type EPC-40-PVC)

    Review Procedure - Post Test Reinstatement & Checklist Piping-SAIC-A-2006 1-Dec-06

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

    Attachment 1 -- SAEP-1160 Section 8 (Test Pkg Minimum Content)

    Page 12 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    13/18

    Review Procedure - Post Test Reinstatement & Checklist Piping-SAIC-A-2006 1-Dec-06

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

    S. Aramco

    Pre-Test

    Punch

    ListingSAPMT PID Proponent

    (By Request)

    Clear 'A'

    Items Construction Contractor QC

    Clear

    S. Aramco

    'A' ItemsConstruction Contractor QC SAPMT

    SAPMT

    Construction Contractor QC SAPMT

    Construction

    S. Aramco

    Final Insp

    for MCCSAPMT PID

    Reinstate

    System

    Final Insp

    (Contractor)Construction Contractor QC

    Flushing &

    Cleanliness

    Proponent

    Proponent

    System

    Lay-Up Construction Contractor QC SAPMT PID Proponent

    (By Request)

    Pressure

    Testing

    Attachment 2 -- TEST PACKAGE FLOW CHART

    PIDContractor QC SAPMT

    Test Pack

    Preparation Engineering Contractor QC

    Pre-Test

    Punch

    ListingConstruction Contractor QC

    PID Proponent

    (By Request)

    (NOTE: Use form SATR-A-2007)

    PID

    Test Package (or Test System) No

    Page 13 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    14/18

    As Calculated*

    30 mins (min)

    Whether piping or tubing, between the root isolation valve and the instrument isolation shall be

    pneumatically pressure tested (air or nitrogen) at 1.25 X design pressure of the piping system or

    process equipment to which it is connected. Test duration shall not be less than 30 minutes.

    Note:ALL Welding shall be completed (Design Issue), all internal coating and Holiday Testing PRIOR TO pressure testing.

    Internally FBE

    Coated Lines

    As Calculated*

    30 mins (min)

    For internally Fusion Bonded Epoxy (FBE) coated piping system, the test pressure shall not exceed

    5,000 psi for APCS 100, 101, 103 systems & 3,000 psi for APCS 102 System

    Note: Instrumentation that could be damaged due to the test shall be disconnected. When pneumatic test is not practical (pressure greater than

    1000 psig, physical configuration, etc.) test with liquid or water. (Flush, test & dry clean using a quality of water not harmful to lines).

    Note: Seal welds of threaded connections & Attachment welds of non-pressure containing parts, such as wear pads DO NOT REQUIRE RETEST

    UNLESS THE LINE REQUIRES PWHT (Including attachment welds & seal welds to the pressure boundary).

    Open-EndedPiping

    EXEMPT,VISUAL EXAM

    Drains, vents & piping downstream of pressure relieving devices that discharge directly to theatmosphere (max internal pressure 10 psig) are EXEMPT from testing. Drain holes installed, etc

    REPAIR

    EXISTING

    PIPING

    See Notes Every existing plant piping & pipeline, after repairs or alterations have been made that affect the

    integrity of the pressure containing parts, shall successfully pass a hydrostatic test. The test pressure

    shall be in accordance with the requirements of the applicable code.

    Note: SAEP-310 requirements apply as well for pressure testing after Repairs, Upgrades, Refurbishment, etc

    Instrument

    Impulse Lines

    Air & Inert Gas

    (150 psig max)

    SERVICE TEST &

    Soap Bubble Test

    30 mins (min)

    Perform a preliminary soap bubble test at 5-10 psig after construction is complete & threaded joints

    are checked for engagement (two full visible thread rule). Coordinate with Compressor and Receiver

    Service tests and final gasket installation.

    LP Steam

    (60 psig max)

    SERVICE TEST

    30 mins (min)

    Coordinate with system Service tests and construction completion.

    RETESTING

    REQMTS

    Process

    Piping

    Note: Leaks are common, difficult to identify as "active" or "non-active". Perform preliminary tests to identify all leaks, especially at flanged and

    threaded joints. When evaluating leakage, utilize clean dry cloths to identify "active" leaks for repair. Oil residue found after wiping the joints (check

    low points carefully) is cause for clean and retest. Always wait a minimum of 30 mins after wiping joints before reevaluation.

    Underground

    Process Piping

    As Calculated

    See Notes

    A) Test prior to backfilling (all joints exposed) & maintain test pressure for a minimum of 2 hrs B) If

    justifiable (safety) & line must be back-filled, a 24 hr recorded test (Chart Recorder) reqd.

    Tested to 1.5 times the differential external pressure, but not less than 15 psig.

    Weld-Plus-Ends

    See Notes

    Note: Test Package SIS Sheet shows design data & "EXEMPT" under required test pressure. Line(s) shall be visually examined.

    TEST PRESS

    & DURATION

    TEST CONSIDERATIONS & NOTES

    As Calculated*

    30 mins (min)

    Piping Line Class List (Hydrotest Spec) lists all new process piping line classes (strength test

    required per code) with exceptions for Service Test and other tests as noted below. NDE in lieu of

    pressure test may be performed if requested & approved by SA Insp. Dept. Mgr. Process requestsper Sect 5 of SAES-A-004, and at a minimum, 30 days ahead of testing.

    Lube & Seal Oil

    Systems

    See Notes

    30 mins (min)

    *Lube & seal oil piping is pressure tested with its own fluid at 1.5 times design pressure or 100 psig,

    whichever is greater. Chemical cleaning precedes pressure testing. Joints shall be completely

    cleaned* (oil free) before testing. *Baby Powder works best to clean/dry joints

    *Note: Unless limited by flanges, valves or other component (exceptions below), hydrostatic strength test pressures for every section of new

    constructed line shall produce a hoop stress in pipe of 90% SMYS at test temperature. See Exceptions Below.

    ON-PLOT NEW B31.1 & B31.3 CODE PRESSURE PIPING (SATIP-A-004 Series)

    Note: Test limits shall be downstream of isolation valves (beyond PZVs & locked valves for equipment). Portions of the test may be less than 24

    inches from these valves to the flare header branch connection. Flare system Isolation Valves receive a pneumatic seat test at 5 psig in lieu of a high

    pressure seat hydrotest. Conduct this test on a weekend to minimize personnel exposure. Perform a stored energy calc when requested by

    Company. Test limits utilize blind flanges at removed isolation valve locations. Follow Pneumatic Testing SATIP.

    Flare Lines

    (24" & above)

    See Notes

    30 mins (min)

    Flare lines 24-inch NPS & larger with a design pressure of 75 psig or lower may be strength tested

    pneumatically (75 psig is tested at 1.1 factor or 82 psig) per Para. 345.5 of ASME B31.3

    Vacuum Piping See Notes30 mins (min)

    SYSTEM

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 1-Dec-06

    Attachment - Pressure Testing Matrix for On-Plot Piping (Incl. UG Utilities, FW & Plumbing)

    Piping-

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

    Soap Bubble Leak

    Test at 5-10 psig

    Weld-Plus-Ends shall be subjected to a pneumatic pressure test of 5 to 10 psig in the annulus

    between the gasket and the seal weld. It shall be examined for leaks using a soap solution.

    Existing Plant

    Piping

    Incl. Tie-Ins

    As Calculated*

    30 mins (min)

    For revalidation purposes of existing plant piping, the test pressure shall be minimum required by the

    Code ASME B31.3. The actual wall thickness of the piping and flange rating shall be determined and

    taken into consideration when calculating the test pressure. In case of flanged tie-in connections, a

    flange tester is utilized to conduct hydrostatic testing of flange butt weld.

    Systems that already passed a successful pressure test require RETEST IF subjected to new

    welding activities (Modifications, repair to pressure boundary) OR IF PWHT is reqd*.

    Page 14 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    15/18

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 1-Dec-06 Piping-

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

    Procedure(Checklist Item D4)

    See Note Test procedures, pressures, durations, & leakage acceptance criteria shall be equal to

    those that the valves were originally purchased to. All resilient (soft) seated isolation

    valves shall have zero leakage. See SAIC-L-2042

    Vessel & Tank

    Trim (Piping)

    See Note Test separately (separate package) as required. Exemptions include sight glasses &

    other instruments. Strength or Service test associated piping based on service

    Note:ALL Code Piping construction (in-situ) that is not VENDOR supplied shall be tested. Utility = Service Test, Process = Strength Test

    All new valves designated for isolation service (as specified by the Proponent) shall be

    subjected to high pressure hydrostatic seat test prior to installation in line.

    Exception See Note

    Note: Proponent specifies those Line Classes and valves subject to field hydrotesting. Valves received shall be carefully identified & given a unique

    ID number for installation into the correct Line Class based on visual verification of construction stamp. Valves shall be given a unique ID &

    corresponding test report document upon receipt, Valve ID shall be controlled, documents transferred into appropriate Test Pkg & Database (PipingSystem, Line Class, Line Number, Location) per SAEP-1160. Procedure identifies all critical aspects of Valve Testing incl Receipt Inspection (internal

    visual exam by qualified Inspector), pressure test, ambient lay-up (corrosion protection per mfg instructions & follow-up preservation reqmts) &

    segregation control to prevent "mixing valves". Controlled System for Valve Placement exists.

    FIELD HYDROTESTING OF NEW VALVES (SAES-L-108, Section 4.7 & SATIP-L-108 & SAIC-L-2042)

    Test Location See Note Location shall be specified by proponent & PID approved. SAIC-A-2031 Sect. J

    Field Testing of

    New Valves

    See Note

    Exemption See Note Buttweld & socketweld end valves in NPS 2 inches and smaller are exempt

    Sampling Lines See Note Test as an integral part with the piping or equipment to which it is connected.

    Boilers receiving Hydrostatic test (new, field fabricated boilers) shall be in accordance with 32-SAMSS-021.Boiler pressure test After Repair or Alteration, refer to SAES-D-008 & National Board Insp Code, NB-23.

    Boiler Hydrostatic test during T&Is shall be per test pressure as specified on boiler's safety instruction sheet.

    Hydrostatic testing for existing vessels shall be conducted per SAES-D-008, Paragraph 10.1.

    Pneumatic test as approved by Insp Dept Mgr (UG-100 of ASME SEC VIII D1, OR T-4 of ASME SEC VIII D2)

    6.4 Heat Transfer Equipment - Hydrostatic tests for existing equipment shall be per SAES-D-008.

    For pneumatic testing, refer to same as above for Vessels (UG-100 of ASME SEC VIII D1, OR T-4 of ASME SEC VIII D2)

    SPECIFIC TESTING REQUIREMENT SUMMARY (ALL SA APPLICATIONS PER SAES-L-150, Section 6)6.1 Plant Piping - Pressure testing of On-Plot Plant Piping shall be per SAES-L-150. See Section D of this Checklist.

    6.2 Cross-Country Pipelines - Pressure testing of cross country pipelines shall be per SAES-L-150. See Section C of this Checklist.

    6.3 Pressure Vessels - Hydrostatic testing for new vessels (shop or field fab) shall be conducted as follows:

    ASME Section VIII, D1 to SAMSS-004, Para 16.3.8.1. & ASME Section VIII, D2 to 32-SAMSS-004, Para 16.3.8.2

    1. When testing with adjacent Lube oil system piping (no leaks = acceptance).

    2. When code repairs are made to skid-mounted piping to correct misalignment,

    physical damage or any modifications in-situ, pressure test the affected spools.

    6.16 Non Metallic Piping - Such as RTR, Thermoplastic, PVC/UPVC & CPVC shall be tested per SAES-S-070, Section 18.

    6.11 Sanitary Sewers - Sanitary sewer systems within buildings shall be tested per reqmts of the Uniform Plumbing Code (UPC). Exceptions to

    UPC requirements are listed in SAES-S-060. THERE ARE 3 MAJOR EXCEPTIONS FOR INSPECTION AWARENESS

    Sanitary sewer lines outside of buildings shall be tested in accordance with SAES-S-070 Section 18.

    6.12 Storm Water Drainage Systems - Test per SAES-S-030 (SAES-S-070, Section 18) Note: Only OWS portions are tested.

    6.13 Miscellaneous Building Services Piping - Steam & condensate piping outside the jurisdiction of ASME B31.3, heating & cooling water piping,

    vacuum & compressed air system piping for building services shall be tested per ASME B31.9, Building Services Piping.

    6.14 Gas Cylinders - Gas cylinders shall be tested per Saudi Aramco Bottled Gas Manual. (Application - New Labs, etc)

    6.15 Valves - Valves shall be tested in accordance with SAES-L-108, Section 4.7

    6.9 Utility Piping Systems - Utility systems, including irrigation piping & water distribution mains, shall be tested per SAES-S-070, Sect 18

    6.10 Industrial Drainage and Sewers - Industrial drainage and sewers shall be tested per SAES-S-020 (SAES-070, Section 18).

    Heater Tube (coil) Assy Hydrostatic test for new, field fabricated heater tube assembly shall be per 32-SAMSS-029.

    Skid-Mounted

    Piping (Vendor)

    EXEMPT IF TESTED BY VENDOR

    per 01-SAMSS-010

    (exceptions noted)

    Low pressure pneumatic seat test at 5 psig shall be substituted for high pressure

    hydrostatic seat test for flare system valves. Identify & Segregate Early!!!

    6.8 Potable Water Systems - Potable water piping inside buildings shall be tested per the reqmts ofUniform Plumbing Code (UPC). Exceptions

    to UPC requirements are listed in SAES-S-060. THERE ARE 3 MAJOR EXCEPTIONS FOR INSPECTION AWARENESS

    Potable water piping outside of buildings shall be tested per the requirements of SAES-S-040 (SAES-S-070, Section 18).

    6.7 Refrigerant Piping Systems - Refrigerant piping serving building air conditioning systems shall be tested according to the requirements of SAES-

    K-001 and the Uniform Mechanical Code (UMC), Section 1520.

    6.6 Fire Protection Systems - Pressure test new & existing fire protection systems (SAES-B-017, GI-1781.001).

    6.5 Tanks - For new, field fabricated tanks, & existing tanks, hydrostatic testing shall be per 32-SAMSS-006 for large, low pressure welded tanks;

    or 32-SAMSS-005 for atmospheric steel tank, as applicable.

    Fin Fan X-chgr is strength tested (as stamped) in-situprior to final acceptance (new project), & whenever transported.

    Heat Exchanger Tube bundles removed from X-chgr (maintenance) get in-situ shell side test per SAES-D-108 prior to return to service

    Page 15 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    16/18

    f. Check miscellaneous material elements (Class & pressure ratings for weld bosses, fittings) & Limitations (L-110)

    Test Package Review Notes1. Check status sheet for signoffs.

    3) Perform FOCUSED ASSESSMENTS with both CHECKLISTS & SPEC-CHECK

    h. PMI OK markings exist on those joints PMI examined. Verify markings to correct joint.

    7) Add notes for: WPS Review/Compilation after Review of Line Class Tables, Valve Spec codes, flanges,

    i. Check color codings of materials to assure correctly specified material was used in piping systems.

    CRITICAL: COLOR CODES EXIST FOR ALL GASKETS (TABLE COVERS ALL GASKETS IN ALL LINE CLASSES)

    Manifold arrangement sketches must show all elements, & manifold construction/insp must be per SAIC-A-2009

    e. Check Spectacle plates, blinds, spacers, Jack screws, etc for SPECIFIC SASD DRAWING conformance.

    g. Check WPS and any special instructions needed per welding (invaluable tool for Control)

    4) Perform Focused Assessments with Spec-Check alone on all specified Materials

    6) Perform Post-Hydro Checks in the field (Reinstatement, FEIL, Pre-Commissioning, Commissioning)

    ensure correct installation (Bolting, valves, etc)

    c. During Final walkdowns, use Spec-Check one last time (Pre-Commissioning, Commissioning)

    d. Piping specs and piping schedules cab be included

    6. Check hydrotest diagramNote: Ensure orifice flange reports are included & any NDT specifiedThis is especially critical for Sour Service & Special Service lines.

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 1-Dec-06

    Attachment 4 - SPEC CHECK INSTRUCTIONS

    2. Check Index against contents

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    1) Test Package Review Tool & Special Process Clearance Verification BEFORE Hydrotest.

    Piping-

    Note: If discrepancies exist, simply review the film and follow NDT checklists for RT (Clear direction exists here).

    Caution: Ensure test pressures do not exceed manifold element ratings (Valves are next size up for systems tested)Example 1: Class 300 # systems(1125 psi) would utilize a Class 600 Isolation valves in test manifolds at minimum.

    g. Check BHT reports against spec requirements (sweet & sour services). Verify roundness of Brinnell indentation.

    a. Use Spec-Check along with SAIC-A-2003 (Checklist for Hydrotest Package Review) & this checklist.

    Check drawing numbers against actual enclosed

    extent specified and correct NDT methods. Check NDT reports and compare RT field markings to the test reports.

    b. Bolting Installation & Torque (Bolts, Nuts, Lubricants, Friction Factors, See Torque Tables)

    c. Valve Installations (Check Valves installed against SAES-L-105 Spec Table Attached)

    SPEC-CHECK can be modified for any item. Ensure the best quality on your project! Check all specs

    Compare completed Special Process reports (RT, MT, PT, PWHT, BHT, PMI, etc)

    Example 2: A manifold with 800# gate valves will not be used in testing 600# systems (2250 psig)

    c. Check NDT requirements in SPEC-CHECK against NDT enclosed in given test packages. Check for correct NDT

    b. Check test package Bill of materials against piping line class requirements (See sample Spec Check)

    e. Shop/Field Weld NDT requirements vary and need to closely checked for omission of work. (10% shop, 100% fld)

    f. Check PWHT reports against material spec requirements (service, thickness, etc). Verify visually PWHT was done

    2) Check field installations (Pre-Hydro Walkdown, Surveillances) for following special processes:

    a. Gasket Installation HOLD POINT FOR CONTRACTOR - Visual before installation, Color code Table

    d. Check RT reports closely for repairs (repair shots, penalties) & field verify the markings exist on the correct joint.

    3. Pressure Test Data Sheet

    Compare against list of outstanding NDT (Backlog of Penalty & Repairs)5. Review P&IDs and isometrics against spec check for line class required materials (drawings often are in error)Note: Make note on cover in Punch list Accepted by PID Field verify against Spec/B.O.M

    5) Perform Focused Assessments with Spec-Check alone on Special Construction Processes.

    a. During Reinstatement, Use Spec-Check along with SAIC-A-2010 (Checklist for Hydrotest Reinstatement) to

    b. During FEIL walkdowns, use Spec-Check during accumulation of Field Exception Items List (FEIL)

    special walk down notes, supports, etc by using a numerical code and hand written notes on back!

    Check excluded equipment & especially if there are any P&ID notes Check pressure test value proposed to assure limiting factor is correct (usually a flange)4. Do a Weld Tracker NDT report review (detailed)

    Reason: You are testing against the valve seat (closed position) & this is rated for 1.1 times test pressure, not 1.5.

    See Next Page for Spec Awareness (Basis for Spec Check on Projects)

    Page 16 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    17/18

    SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

    Review Procedure - Post Test Reinstatement & Checklist SAIC-A-2006 1-Dec-06

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    Piping-

    PIDs ATTENTION TO SPECS & SPEC-Check(Piping Line Class Specs, WPS, NDT Specs, PWHT, PMI, etc) on Projects:

    SPEC AWARENESS

    Initial Review of SPECS1. Carefully recheck Contractor Piping Specs (Line Class Summary & Tables) as early as possible during or just

    after Design is complete (as soon as they are issued and available).2. This is done by checking Contractors specs against Line Class Material requirements listed in SAES-L-105. Givespecial attention to critical systems & systems above 300#.3. Average large projects can have as many as 50 different piping specs & details can be very hard to pick up in the

    field. Pipelines have fewer specs and are easier to manage. THIS INCLUDES THE MAZE OF GASKETS!!!

    900# system instead of required 6000# fitt ings) must be itemized & brought to SAPMT attention early.See attached Sample Weekly Highlight.9. After all SPECS submitted by Contractor are accepted ... CREATE your custom SPEC-CHECK (sample

    4. Time taken for early review only takes an experienced plant inspector 2 days of review. Findings (often humanerror) can be critical. Help prevent unplanned shutdowns on your projects & find substandard material specs beforethey are installed or before they enter service.5. Carefully check Contractor Special Process SPECS (WPS, NDT, PWHT, etc) as early as possible (as soon asthey are issued and available).6. This is done by checking Contractors Special Process Specs against code and SA requirements (SAES-W-011,

    against approved specs before Pre-Hydro Walkdown2. USE YOUR CUSTOM SPEC-CHECK on every new plant project as the perfect walk down and test packagereview tool. Important Note: Never assume drawings or test packages are correct. Never assume NDE % & PWHT,PMI, etc performed/not performed by contractor is correct.Inspectors must be taught a systematic review method for test packs with focus on Specs.

    Sect 17 for NDT & 13 for PWHT). SAES-W-012 is similar to SAES-W-011 in this respect7. Ensure that notes are included in these SPECS that require increased NDT based on field welding and other

    code considerations.

    substandard installation identification*.

    8. Clear violations such as our weekly highlight example (such as specs and drawings that use 3000# fittings on a

    have seen as many as 20% of all piping segments installed of the wrong schedule of piping (J-80, RT Refinery). I

    *FACT: MOST INSPECTORS ARE WEAK REGARDING KNOWLEDGE OF SPECIFICATIONS & ARE UNAWAREOF MANY CRITICAL REQUIREMENTS! SPEC CHECK PUTS THESE DOWN ON PAPER (BY SYSTEM)

    Test Package Review & Pre-Hydro Walkdow

    attached with instructions).Commentary: This is a valuable review and exercise for all inspectors. Have all inspectors trained in this task forself-reliance during future projects. This teaches critical lessons in Materials*, specification requirements* and

    A thorough test package review system is a page by page review that takes only 15 minutes per package & checksevery page and every weld & all materials for completeness/correctness. Omission of Special Process work by

    1. Follow-up (after initial specification review/approval) can also include checking ISO drawings and bill of materials

    Contractor is widespread & frequent, most often unintentional and simply due to a lack of AWARENESS.

    Surveillance & Focused Assessment1. Use SPEC-CHECK on routine surveillance.

    2. Create a custom SPEC-CHECK for focused assessments on Valves.Incorrect valve installation is very common with valves placed in the wrong service (swapped, mislocated, mismark)3. Create a custom SPEC-CHECK for focused assessments on small diameter piping (UT purposes). Past projects

    4. Create a custom SPEC-CHECK for focused assessments on PWHT & BHT. Past projects have seen poorpractice with failure to follow 12-step BHT procedure per NACE RP-0472 App A.5. Turn your project surveillance into an effective and efficient Inspection asset that is valuable to Projects.

    SHARE SPEC CHECK WITH YOUR CONTRACTOR FOR QUALITY

    visit projects and find numerous substandard installations very often (human error, again). On your project,order/request/perform/get Contractor to do random checks of small diameter piping segments (2 & below). I do itmyself with a 2-man crew with me, piping schedules in hand on all my projects & run at about a 2% reject rate.

    Page 17 of 18

  • 7/29/2019 SAIC-A-2006 Rev 2

    18/18

    4 Valves (400 SS Trim) tested in-line removed, cleaned, & lubricated for Amb lay-up ditto

    12 All Temporary Test Components (spools, test blinds, gaskets etc) are removed ditto

    15 All Start-up items installed (strainers, filters, other items restricted from test) ditto14 Check Valves and internals reinstalled (Internal Cleanliness & gasket check) ditto

    NOTES: a. Above Items are samples for form use only.

    b. Re-instatement Procedure shall detail specific items to be used in this Re-

    Instatement checklist (per SAEP-1160, Sect. 8). The above 17 items are a sample

    of such a procedure checklist.

    c) Indicate " No Post Test items. " as applicable

    d). QA col is reviewed/initialed/dated prior to package certification to verify

    completeness

    I

    T

    E

    M

    Reinstatement (Post-Test) Checklist Items &

    Description (Option per Note 5 Above)

    Reference &

    Applicable

    SATIP

    A

    or

    B

    Origi-

    nator

    ETC

    (Note 6)

    Verified

    complete

    by QC

    Concur

    PID Insp

    SAES-A-007,

    Para 6.2B DEF-1/4/07

    RLC

    1/4/07

    ABC/QC 1/1/2007

    ABC/QCStart-up date =

    5/1/2007

    ABC/QC 1/4/2007

    SAES-L-110,

    Section 5A

    SAEP-351,

    Proj DwgsB

    DEF-1/4/07RLC

    1/4/07

    DEF-1/1/07RLC

    1/1/07

    ABC/QC 1/4/2007

    SAES-L-108,

    Section 5A

    SAES-L-108,

    Section 6B

    DEF-1/1/07RLC

    1/1/07

    SAES-L-109,

    Section 8A

    ABC/QC 1/1/2007

    1/1/2007

    6) ETC = Expected Time of Completion or Expected Start-up Date if ETC date is unknown (affects lay-up considerations)

    DEF-1/1/07RLC

    1/1/07

    SAES-L-109,

    Section 8A

    DEF-1/1/07RLC

    1/1/07

    Note: "B" items not complete during re-instatement (by approved procedure) shall be transferred to "zFEIL Form 6133" (Attachment 2)

    1 Seal weld threaded nipples from headers to root valves at (5) locations (hydrocarbonservice) per SAES-L-109, Section 8.

    Origi-

    nator

    ETC

    (Note 6)

    2 Guides are in direct contact with piping horizontal run at 3 locations (6mm gap req'd).Relocate guides per drawing. These are welded to the pressure boundary.

    ABC/QC 1/1/2007

    ABC/QC

    6 Install permanent gaskets at flange sets 1, 4, 5, 6 on ISO dwgs per approved torquetables and install spectacle blinds oriented as per approved P&ID.

    4) "B" items are completed during re-instatement per an approved Procedure before final inspection by Company (per procedure).

    Verified

    complete by

    QC

    Concur

    PID Insp

    I

    T

    E

    M

    Pre-Pressure Test Checklist Items & Description ReferenceA or

    B

    5) See SATR-A-2011 for Re-instatement Checklist Form.

    QR NUMBER

    NOTES: a. Above Items are samples for form use.

    b. Indicate " No Punch items. " as applicable

    c. QA col is reviewed/initialed/dated prior to package certification to verify

    completeness

    4 Check valve is oriented in the wrong direction (flow arrow). Reverse check valve toassure correct flow direction. Reposition valve & restore internals immediately after

    test, COMPANY to witness.5 Piping clearance to structural bracing is 15 mm in violation of SAES-L-310, Sect 12.

    (50 mm spacing req'd). Engineering!

    7 Completely remove all water and debris from low point/valve cavity for the (3) in-lineValves (8" - 300 #) with SS 400 trim, do so immediately after test. Clean with dry

    compressed air and relubricate sealing surfaces with approved lubricant in preparation

    for "ambient" lay-up specified in test package.

    8

    WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

    SAUDI ARAMCO TEST REPORTSATR NUMBER

    3 Check valve upstream clearance is not five (5) pipe diameters (40" req'd, 20" actual),in violation of SAES-L-108.

    TEST SYSTEM No./Test Pack No.

    DATE APPROVED

    EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION

    1-Oct-06 MECH-Pre-Pressure Test Checklist (Form) SATR-A-2007PROJECT TITLE

    PLANT NO.

    WORK PERMIT REQNATURE OF TESTDRAWING NUMBER (P&ID/ISO) / REV. No. PRESSURE TEST DIAGRAM

    Notes:

    SAUDI ARAMCO TIP (SATIP) NUMBER

    1) This Form shall be used in conjunction with applicable Pre-Pressure Test Checklist. Refer to applicable SATIPs & See Attachment 1

    2) "A" items are items required to be completed before pressure test can proceed.

    3) "B" items are post-test items to be cleared immediately after pressure test (within 24 hours) with Inspection witness per procedure.

    1 Flushing & hydrotest complete and documented as accepted. ReinstatementProcedure

    2 All test vents & drains plugged and seal welded ditto

    3 Lines drained and lay-up per customer approved specification ditto

    5 Jacking screws, process blinds (spectacles, spades, etc) correctly installed ditto

    6 Spring Hangers & components (bellows, etc) adjusted per mfg instructions. ditto

    7 Weepholes plugged with heavy grease (reinforcement pad air test complete) ditto

    8 Chain wheel operators installed ditto

    9 All instruments, control valves & check valves reinstalled in correct flow position ditto

    10 Restriction orifice/flow elements installed ditto

    11 Relief Valves are Pop tested/calibrated, tagged and SAP approved/installed ditto

    13 Correct bolts/gaskets are installed and torqued per SAEP-351 requirements ditto

    16 Chemical Cleaning completed and documented

    17 Final Line Check complete & meets all special process specs. See Spec Check.

    ATTACHMENT 5 (Guide for Post-Test Reinstatement Checklist by Contractor)

    SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05

    SATIP Activity No. SUPPORTING SAIC Number SAIC QR No.