safety together
TRANSCRIPT
BCA annual report 2005: 030
safety together
BCA annual report 2005: 031
In close co-operation with the industry, BCA continues to ensure
that buildings and structures are designed, constructed and
maintained with safety in mind.
BCA annual report 2005: 032 BCA scrutinises the plans to ensure that Qualified Persons and Accredited Checkers have been carrying out their duties diligently.
BCA annual report 2005: 033
Improved Structural Design Quality for
Complex Projects
BCA maintained its role in scrutinising the plans submitted
by the Qualified Person and Accredited Checker to
ensure that they had been carrying out their duties
diligently, especially for complex projects.
For high-rise buildings, the Qualified Person would be
required to carry out sufficient load tests to verify the
foundation design assumptions. There must also be
adequate number of tests to ascertain the capacity of
the pile. For complex steel projects, the Qualified Persons
now have to present their design concepts and analyses
to BCA, checking for redundancy and robustness to
prevent the disproportionate collapse of structures.
To further improve the quality of structural steelworks,
BCA worked closely with the Institution of Engineers
Singapore and the Association of Consulting Engineers
Singapore to encourage engineers to engage only steel
fabricators accredited by the Singapore Structural Steel
Society for their steelworks. For major projects, Qualified
Persons were further encouraged to appoint an
independent testing agency to check on the quality of
steelworks erected on site.
Safety Actions after Nicoll Highway
Incident
Following the Nicoll Highway incident, BCA took action
to assure the public that buildings near the collapse site
were safe. Our engineers worked round the clock to
inspect and monitor the adjacent buildings to verify
that they were structurally safe. The media was given
a technical briefing at the site on how building safety
assessment was carried out.
To address widespread public concern over the safety
of other Circle Line sites, excavation works were
temporarily suspended while BCA conducted a
comprehensive safety review of the design and
construction of deep excavations at these sites. BCA
reviewed the adequacy of the design of the temporary
works and the monitoring measures at the sites,
deploying 56 engineers and specialists, assisted by three
independent consultants, to perform checks and
inspections over two months. Excavation works were
BCA annual report 2005: 034 BCA broadened the inspection of properties adjacent to Circle Line excavation sites for added assurance.
BCA annual report 2005: 035
finally allowed to resume after BCA had verified that
all adequate safety measures were in place at each site.
BCA also responded to feedback on damage to properties
adjacent to Circle Line excavation sites. Together with
the professional engineers, BCA carried out inspections
on 230 affected buildings. All, but two, were declared
structurally safe. Broadening the checks for added
assurance, BCA further surveyed 700 buildings within
the 100-metre radius of the Circle Line sites.
Reduced Impact of Construction Work on
Nearby Buildings
Recently, BCA further required the Qualified Person to
submit an assessment report on the effect of proposed
excavation works on nearby buildings before
commencing work. This move sought to protect buildings
near construction sites. The report had to take into
consideration factors such as the site conditions, type
and vulnerability of buildings and soil conditions and
propose an appropriate temporary earth-retaining
structure that would minimise the impact of excavation
works on nearby buildings.
In addition, BCA had been promoting the use of an
environmentally friendly piling system for landed
property projects to minimise disturbance and damage
to adjacent properties. From 2002 to 2004, the use of
this piling system had increased from 35% to 60%. As
a result, feedback on excessive vibration or damage to
nearby properties was reduced by 30% during this period.
Enhanced Safety Measures for Deep
Excavation Sites
Paying closer attention to safety measures at deep-
excavation projects, BCA formed a Deep Excavation
Team to carry out audit checks and inspections of critical
deep-excavation sites, ensuring that the builders and
the project teams had fulfilled their statutory duty in
ensuring safety on site.
For projects involving two or more levels of basement,
the professional engineer who designed the temporary
work was required to brief BCA on the temporary works
design and the proposed monitoring measures. The
project builder also had to present the construction
sequence and various site-safety control measures.
BCA annual report 2005: 036 BCA published posters and advertisements to remind the public the importance of window safety.
BCA annual report 2005: 037
Other Actions on Building Safety
BCA continued to take strict enforcement action against
parties who flouted the building regulations. These
moves aimed to send a strong message to remind
industry players that building safety could not be
compromised. During the year, BCA revoked a total of
32 permits, and since 1999, BCA had prosecuted 69
project parties.
Enforcement actions were also taken against building
owners who put up unauthorised structures that posed
a hazard to the public. These owners were given a
choice to retain the structures if they engaged a Qualified
Person to inspect them and submit plans for approval.
Otherwise, they must be removed. BCA would issue
notices to owners to demolish those that are unsafe.
To share experiences with the industry, BCA organised
two seminars on Achieving Quality Structural Steel
Works and Enhancing Building Security during the year.
Two circulars to industry professionals and practitioners
were also issued to emphasise the importance of carrying
out construction site checks and tests on structural
materials to ensure compliance with the design codes
and specifications.
New Legislation on Exterior Features
Recognising that falling windows and other exterior
features could pose serious threats to public safety, BCA
amended the Building Control Act to regulate the design
and installation of exterior features. It was made effective
on 1 October 2004. Relevant provisions were also
introduced in the new Building Maintenance and Strata
Management Act to make building owners responsible
for their maintenance after installation.
Specifically for windows, a minimum safety performance
standard was introduced in the Building Control
Regulations for new installations. Building owners were
also required to appoint approved window contractors
to carry out a one-off retrofitting of existing casement
windows fitted with aluminium rivets. A 12-month grace
period, which would end by 30 September 2005, was
granted for this retrofitting exercise.
BCA annual report 2005: 038 BCA introduced the staircase storey shelter as an alternative to household shelters to meet changing needs of consumers.
BCA annual report 2005: 039
To raise public awareness of the window legislation,
advertorials in four languages were published in local
newspapers, and information on the legislation and
maintenance of windows made available on both BCA's
and the Housing and Development Board's websites.
Building Maintenance and Strata
Management
The new Building Maintenance and Strata Management
Act came into effect on 1 April 2005. It was committed
to a Select Committee for consideration before being
passed in Parliament at its third reading on 19 October
2004.
Significant changes included enhanced provisions for
building maintenance for public safety and the
introduction of a two-tier management corporation
system for more effective management of mixed-use
strata developments. Other new provisions included
staged implementation of large development projects
and a rebuttable statutory presumption of liability for
inter-floor leakage. The administration of the Strata
Titles Boards was also transferred to the Ministry of
National Development from the Ministry of Law.
In March 2005, BCA published a layperson’s guide
entitled Strata Living in Singapore on the new Building
Maintenance and Strata Management Act targeted at
homeowners.
More Civil Defence Shelter Solutions
In response to changing needs, the staircase storey
shelter was introduced as an alternative to household
shelters in July 2004. BCA worked closely with precasters
to develop several buildable solutions on precast
household and staircase shelter components for landed
houses and condominiums. BCA also participated in a
series of blasts tests carried out by Singapore Civil
Defence Force and the Defence Science & Technology
Agency to validate shelter components and to optimise
design requirements.
BCA annual report 2005: 040 Providing stand-off distance from a building with bollards is one of the ways to enhance the security of buildings.
BCA annual report 2005: 041
Protective Engineering Against Terrorism
To further enhance the security of buildings, BCA led
a multi-agency workgroup, comprising agencies from
the Ministry of National Development and the Ministry
of Home Affairs, to study and propose suitable measures
to protect against the threat of terrorism.
Resulting from these efforts, a booklet entitled Enhancing
Building Security was published. The booklet aimed to
keep building owners, developers and building
professionals aware of the need for security and
protection of buildings and highlighted practical and
cost-effective security measures and design
considerations that could help lessen the severity of a
terrorist attack on a building. The booklet was distributed
to owners of about 2,000 industrial and commercial
buildings and other stakeholders in February 2005.