1SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
Integrated ProjectIntegrated Project
Co-operative Systems for Road Safety Co-operative Systems for Road Safety
““Smart Vehicles on Smart Roads”Smart Vehicles on Smart Roads”
SP1 – SAFESPOTSP1 – SAFESPOT
In-Vehicle Sensing and PlatformIn-Vehicle Sensing and Platform
Elena Bianco
Centro Ricerche FIAT (Italy), [email protected]
SP1 SAFEPROBE Co-leader
SAFESPOTSAFESPOTSAFESPOTSAFESPOT
2SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1
WP1.5 Test and Validation
WP Leader: CRF
3SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1 – WP 1.5
WP1.1Technical Management
WP1.2Needs and
Requirements
WP1.3Specifications
WP1.4Implementations and
Prototypes
WP1.5Test and Validations
Vehicle Probe Use Cases
Internal Data Fusion Specification
In-vehicle HW Platform Development
Validation Plan
System Analysis of Useful Data
Environment Data Acquistion Specification
Data Fusion Algorithms Development and Implementation
In-lab Tests
RequirementsCooperative Data
Fusion SpecificationIn-vehicle SW Platform
Development In-vehicle Platform
validation
Data Refinement Specification
Data communication implementation
Performance Analysis
HW Platform Specification
Cooperative onboard sensors
SW Platform Specification
Development of probe vehicles
SAFEPROBEIn-Vehicle Sensing and Platform
4SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1 – WP 1.5
WP MAIN GOALS
• To define a validation plan
• To test the functionality of the overall system
• To do a performance analysis
In order to achieve these results the following working steps will be planned:
Task 1.5.1 Validation Plan (Leader ICCS)
Task 1.5.2 In-lab test (Leader BOSCH)
Task 1.5.3 In-vehicle platform validation (Leader CRF)
Task 1.5.4 Performance Analysis (Leader VOLVO)
5SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1 – WP 1.5
WORK PLAN
6SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1 – WP 1.5
WORK PLAN
Work-packageNo
Workpackage title Leader Person-months
Startmonth
Endmonth
WP1.5 Test and Validation CRF 55 M 25 M 36
Partners CRF REGIENOV
VOLVO BOSCH PIAGGIO IBEO
SVDO ICCS MMSE
Person-months
20 1 3 11 7 1 1 8 3
7SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1 – WP 1.5
WP DELIVERABLES LIST
Deliverables No
Deliverable title
Nature Due Date
Type Partner responsible
Brief Description
D1.5.1 Test plan design
R M27 RE ICCS, CRF Test plan design for testing and validation of the SAFESPOT in-vehicle platform
D1.5.2 In – vehicle platform test results
R M34 PU CRF, BOSCH
Public results of the in- vehicle platform test
D1.5.3 Performance analysis
R M36 RE VOLVO Performance analysis in the situations defined in the test plan design
8SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1 – WP 1.5
TASK 1.5.1 Validation Plan
Leaded by ICCS – Other Partners involved: CRF, REGIENOV
Start month: 25 - End month: 27
Main Activities
1. Analysis of the methodologies to be used for the
a. In-lab test;
b. In -vehicle platform validation;
c. Performance analysis phase.
2. Definition of the kind of measurement required
3. Definition of the possible test tracks where testing the demonstrator vehicles
Final result
D1.5.1 Test plan design for testing and validation of the SAFESPOT in-vehicle platform
9SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1 – WP 1.5
TASK 1.5.2 In-lab test
Leaded by BOSCH – Other Partners involved: CRF, SVDO, ICCS
Start month: 27 - End month: 30
Main activity
1. To evaluate through in-lab tests the correct functionality of the SAFESPOT in-vehicle platform based on the what stated:
a. in the HW (Task 1.3.5);
b. in the SW specifications tasks (Task 1.3.4);
c. in the validation plan (D1.5.1)
Final result
Technical and functional tests of the hardware and software modules
integrated in the SAFEPROBE test bed will be done.
10SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1 – WP 1.5
TASK 1.5.3 In-vehicle platform validation
Leaded by CRF – Other Partners involved: REGIENOV, VOLVO, PIAGGIO, IBEO, MMSE
Start month: 29 - End month: 34
Main activities
1. Performance of on-board vehicle functionality test
2. Performance of in-depth system optimisation work
3. Integration of the SAFESPOT in-vehicle platform on the demonstrator vehicles provided by CRF, VOLVO, PIAGGIO.
4. Tuning and optimisation of the main parameters defined for the system functionality directly on the selected test-sites.
5. Consolidation of the in-vehicle platform in order to be utilise for the development of the cooperative applications and functions.
Final result D1.5.2 In – vehicle platform test results
11SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1 – WP 1.5
TASK 1.5.4 Performance Analysis
Leaded by VOLVO – Other Partners involved: CRF, PIAGGIO, SVDO
Start month: 32 - End month: 36
Main activities
1. System verification based on:
a. the specifications set in WP1.3
b. the use cases and test scenarios defined in the D1.2.1
2. Collection, data and performance analysis of the SAFESPOT in-vehicle system from both theoretical and on-road tests analysis.
3. Test and verification of driving situation recognition (e.g. slippery road, etc) in real driving mode.
Final result
D1.5.3 Performance analysis in the situations defined in the test plan design
12SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1 – WP 1.5
PARTNERS WORK DISTRIBUTIONCRF
WP 1.5 leaderTask 1.5.3 leaderDefinition of test methodologies with the other partners involved in the task. CRF In –lab and in – vehicle system validation and test On- road test trials and data analysisCo-responsibility with ICCS of the deliverable D1.5.1Co-responsibility with BOSCH of the deliverable D1.5.2
REGIENOV
Definition of test methodologies with the other partners to be used to test and validate the results of the SAFEPROBE subproject. In-Vehicle platform validationSpecification of the In-Vehicle test scenarios and test plan to be deployed by REGIENOV to test and validate the elements of
SAFEPROBE results to be incorporated into the west test site.
13SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1 – WP 1.5
PARTNERS WORK DISTRIBUTIONVOLVO
Task 1.5.4 leaderResponsibility of the deliverable D1.5.3 On-road test and analysis of the SAFESPOT system.Performance analysis of the SAFESPOT system from both theoretical
analysis and on-road tests analysis.
BOSCHTask 1.5.2 leaderParticipation to Functional and performance tests according to validation plan (test cases) of SAFEPROBE HW and SW modules, test reporting.Co-responsibility with CRF of the deliverable D1.5.2
PIAGGIOCollection and analysis of data from the on-road test trials related to the motorcycle.Performing validation tests using the test plan design.
14SAFESPOT Project Kick off Meeting February 16th and 17th 2006 Rome
SAFESPOT – SP1 – WP 1.5
PARTNERS WORK DISTRIBUTION
IBEOSupport of the test and validation of the cooperative on-board sensors
SVDOTest and verification of data acquisition algorithms in Lab-environmentTest and verification of driving situation recognition (e.g. slippery road,
etc) in real driving mode.
ICCSTask 1.5.1 leaderDevelopment of the validation plan Testing and evaluation of the cooperative data fusion system in the test
bed Co-responsibility with CRF of the deliverable D1.5.1
MMSE
Contribution to the in-vehicle functionality test of the whole sub-systems