    Summer internship projectCarried out in JSW

  • 8/3/2019 sachin jindal

    2/14

    Special Thanks To

    Mr. Manoj Kumar Jha (costingmanager)

    Mr. Nitin Tekade (HR Head)Mr. Sanjay Swami( ppc incharge)Mr. Rahgunath Dhumal( S.P.T)

    Mr. Pravin naulakiya(techn.)

  • 8/3/2019 sachin jindal

    3/14

    Introduction

    Company name : JSWProject Topic : optimization of

    production cycle time for the productG I, GL , PPG I, PPGL.Under the guidance of Mr. Manojkumar Jha.

  • 8/3/2019 sachin jindal

    4/14

    Steel industry profile

    100 years old6th largest producer of iron ore in

    worldCapacity (124 ml tonnes 2012 < 275ml tonnes 2020 ).

    Capital investment 100000 cr.Employment for 2 million people.

  • 8/3/2019 sachin jindal

    5/14

    Ab out JSW

    Founder 1952

    1982 - vasind plant1983 - Tarapur plant1994 - Vijaynagar plant

    InvestmentProducts

  • 8/3/2019 sachin jindal

    6/14

    important break troughs

    Indias only fully integrated stainless steelplantIndias only integrated private sector galvanized steel producer Indias only diameter su b merged A rcwelded steel pipes

    World standard sponge ironIndias only integrated green-field steelproject.

  • 8/3/2019 sachin jindal

    7/14

    COLOR CO A TING PRODUCT ION PROCESS

    COLOUR CO ATING

    G A LV A NS ING

    ROLL ING

    P ICKLING

    SL ITTING

  • 8/3/2019 sachin jindal

    8/14

    P roduction cycle

    1Sale order received from marketing dept.analysis of order

    2order ganerated in oracle softwareorder sign b y production/QC dept.

    3spec release ( technical specification)

    4H.R processing

    5 G.L. finishing

    6dispatch

  • 8/3/2019 sachin jindal

    9/14

    Expected time required for each stage

    receivingorders , 1 day

    order ganerating ,

    1 day

    spec

    release ,1 day

    H.Rprocessing ,

    2 day

    G. L.finishing ,

    1 day

    dispatch ,1 day

    Ex pected time required for each process

    receiving ordersorder ganeratingspec releaseH.R processingG. L. finishingdispatch

    Total days required for production ( appx.) = 7 days.

  • 8/3/2019 sachin jindal

    10/14

    ANALYSIS OF DATA

    PROCESS(including all) STANDERD TIME ACTUAL DATESales Order Received ------ 25th April 2011Order Generated In

    Oracle Software

    1 day 25th April 2011

    Spec released. 1 day 26th April 2011Slitting 1 day 20th may 2011Pickling day 21th may 2011

    Rolling day 23rd

    may 2011Galvanizing day 31st may 2011Colour Coating day 31st may 2011Dispatch 2nd june 2011

    Order no. 5024

    Volume :- 100 tones

  • 8/3/2019 sachin jindal

    11/14

    Order no. 5024

    Processing stage Cost at thestage

    Time lag inprocess

    Calculation Amount

    Slitting 35000 24 days. 35000*10%*24/365 230.1Rolling 38000 1 days 38000*10%*1/365 1.12Galvanizing 50000 5 days 50000*10%*5/365 68.49Colour coating 58000 - 90000*10%*0/365 0Dispatch 60000 - 95000*10%*0/365 0

    Total 309.74

    C ost saving after C ost saving after optimization production time.optimization production time.

    C ost saving for whole order

    = 309.74*150

    = 30974 rs

  • 8/3/2019 sachin jindal

    12/14

    A ll orders in b rief O rder no. Standard

    timeActualtime

    volume C ost saving /tonne

    Total C ostsaving

    5024 7 days 37 days 100 tonnes 309.74 rs 30974 rs

    5049 12-15 days 27 days 624 tonnes 109.58 rs. 68377 rs

    5065 11 days 13 days 175 tonnes 41.095 rs 7192 rs5074 7-9 days 17 days 155 tonnes 68.49 rs 10616 rs

    5030 10-11 days 38 days 150 tonnes 309.74 46461 rs

    Total. 1204 tonnes 163162 rs

    Y early production = 500000 Y early production = 500000 tonnestonnes. .

    Approximately saving per year = 163162 * 500000 / 1204Approximately saving per year = 163162 * 500000 / 1204

    = 6,77,58,305= 6,77,58,305 rsrs

  • 8/3/2019 sachin jindal

    13/14

    Recommendation.C ompany can reduce scrap collecting time. i.e. 20-30min by 5-10 min.By reducing fault in machineries by way of maintenanceand repairs of machineries from time to time.

    The inventory should transfer to the ne x t processwithout halt.The firm must use J-I-T inventory control tenchnique inproduction to minimize production process time.The technical specification(spec) should not be lated.

    Their must appropriate link e x ist between all departmentinclude marketing, PP C , costing.

  • 8/3/2019 sachin jindal

    14/14