rte lebranchu compensation and transient studies onalong ehv overheadline
TRANSCRIPT
Compensation and transient studies on a long EHV overhead line
Illustration with the AGADIR-LAAYOUNE 400kV overhead line project
Study background
Issue Very weak 225kV network
Long antenna (approx. 1200km) Low production Low loads Low short-circuit power
3
PE2 PE1
PE3
Technical solution Extension of the northern 400kV
network to the south Double circuit 400kV overhead line
between Agadir and Laâyoune
LAAYOUNE
Ait MELLOULIMI MKOURNETIZNITGUELMIME
TANTANPHOS .B
CHICHAOUA
AGADIR
ST
EP
A.M
OM
N
Oed TEIMA
Dakhla
Bou
jdou
r
Incoming generators in the southern part of the grid Winfarms (~ 800 MW) in the south Reversal of the usual power flow Heavy loaded 225 kV network Distorted voltage profile Temporary disturbances
Study:
Steady state analysis Transient overvoltage studies Transit capacity optimization
(series compensation)
Modelling
Many different phenomena
Different frequencies Power frequency (50 Hz) Low frequency (~ 500 Hz) Transient disturbances (~ 5 kHz)
Different simulation cases Load flow Temporal Frequency scan
References: Guide CEI 60071-4: Computational guide to insulation co-ordination and modelling of electrical
networks Brochure CIGRE n°39: GUIDELINES FOR REPRESENTATION OF NETWORK ELEMENTS
WHEN CALCULATING TRANSIENTS
One schematic for all cases…
Future network development
Border of the circuit: Propagation # 1/f
For low frequency studies: Thevenin equivalent at 50 Hz
Completion with the southern 225kV grid
6
AGADIRLAAYOUNE
1
1 1
1
1
1
1
2
2
2
2
2
2
2
Components modelling (1)
Basics models, non frequency-dependent: R, L et C
Lines: FD model for temporal simulations PI-exact model for frequency scans
Generators:
+ +
+
ZnO
+
+
Geometrical data
Components modelling (2)
Transformers: standard low frequency model
Trans form er DataBCTRAN
Coupling considerations
Components modelling (3)
Specificity: auto-transformer
UHV – ULV
Winding 1 parameters
ZHV-LV
ULVULVUHV
Winding 2 parameters
LV parameters
HV parameters
2
LVHV
HVLV-HV U -U
U . Z
Validation by simulating the factory tests…
Modelling of magnetic saturation:
Validation of the model
Quite impossible to validate so complicated a network To many components Very simplified modelling Which data to compare to?
Load-flow simulations Compilation of the model No misconnections of the components Production / consumption configurations
Time domain simulations Compilation of the model Predicted behaviour
Shunt compensation
No-load compensation
Determination of the total reactive power needed Energization of the line (extremity disconnected): 800 Mvar needed
Which compensation scheme? Intermediary substations needed? Which repartition between substations? Reactors on the line or in the substation? Many steps needed? New specifications for reactors? Common mode?
10 cases studied:
12
No-load compensation (2)
Observation of the voltage profile along the line Line connected at Agadir substation Line connected at Laâyoune substation Line connected to both substations
13
On-load compensation
Evolution of the compensation needs with the load Progressive increase of the
generated power
Adaptation of the compensation
Final compensation scheme: No intermediary substation Line reactors, all connected with
circuit breaker=>new operation rules
Minimal step = 40Mvar
Transient studies
Temporary overvoltage
Load drop Windfarms power generation variation
Single phase fault
Three phase fault
16
overvoltage = 1.2 pu
Switching overvoltage (1)
Frequency scan Different configurations
• Substation analysed
• Lines configuration
• Compensation scheme
Identification of potentially harmful situations
Statistical studies for each scenario Parameter variation
• Apparition of the fault
• Opening time of the circuit breakers
• Closing time of the circuit breakers
Maximum overvoltage
Statistical studies have no ending…
17
Switching overvoltage (2)
18
Local loadsClosing time of the circuit breaker
One circuit of the 400kV line connectedOne autotransformer energization
Remanent flux
Transformer energization
Neutral grounding reactor
Closing time of the circuit breaker
Single phase faultSingle phase opening of the circuit breaker
Single phase reclosure of the breaker
Fault clearing
Surge arresters in the substationsInsertion resistors in the circuit breakers (R = 400 Ω, t = 10 ms)
Closing time of the circuit breaker
Single-phase fault3-phase opening of the circuit breakers (1 circuit)
3-phase reclosure of the breaker
Fault clearing
Mitigation means
Statistical parameter
ScenarioExamples of study cases
Series compensation
Series compensation
Why compensating? 225kV => stability constraint
What solutions? Series capacitors Phase shifting transformer FACTS (UPFC, …)
Method: Amount of compensation
• Increase of the power generation
• Stability limit in faulty conditions• Determination of the optimal compensation rate
Objective: stability limit = thermal limit
Compensation scheme
20
Impact of the localisation of the capacitors (1)
21
V1 V2
Vc
I
∆V
V1
V2I
Vc
0 5 10 15 20 25 30-800
-600
-400
-200
0
200
400
600
800
time (ms)
Vol
tage
V1V2VcI
line
Voltage profile along the 400 kV line
Impact of the localisation of the capacitors (2)
22
V1 V2
Vc
I
V1
V2
I Vc
∆V
0 5 10 15 20 25 30-600
-400
-200
0
200
400
600
time (ms)
Vol
tage
V1V2VcI
line
Voltage profile along the 400 kV line
Impact of the localisation of the capacitors (3)
0,75
0,80
0,85
0,90
0,95
1,00
1,05
-50 50 150 250 350 450 550 650
Distance (km)
Vo
ltag
e (p
u)
Compensation at LAAYOUNE Compensation at AGADIR
Compensation at 2 substations Compensation at 3 substations
Laâyoune Agadir
Voltage Low voltage if condensed
compensation Intermediary substation
slightly interesting
Transmitted power ~ no impact
Final compensation scheme: No intermediary
substation Capacitors balanced
between both the substations
Consequences on resonant phenomena
Y1
Y2
D = (Y1-Y2) / Y1
fR
D > 5%
(50-fR) = F0 ± 3 Hz
No impact on transient overvoltage studies
Further SSR studies needed
Impedance at Laâyoune 400 kV substation – transformers disconnected
Impedance at Laâyoune 225 kV substation
Impedance at Safi 400 kV substation
Conclusion
Main points
Definition of the simulation schematic Which phenomenon? What level of detail? Validation?
Operation usages Simulation cases based on operation usages Operation usages adapted to simulation results
Parametric studies Prior work is important Which end criteria?