rou acquisition
DESCRIPTION
This presentation details the various Land & ROU acquisition issues in cross-country pipelines. It illustrates the statutory issues related to ROU. It also highlights PMP act 1962 and other laws.TRANSCRIPT
By
Shri. M.K. Moharana
Ch. Manger-RKPL
Land, ROU Acquisition & Statutory
Issues
April 25-26, 2013
1
India Oil & Gas Pipeline Conference
Why Pipelines
2
Economical
Environment Friendly
Low Risk
Large Volumes
Lesser Risk for Spillage
Salient Features of Pipeline Project
3
A pipeline project involves laying of buried pipeline of
specified length & diameter to transport Natural
Gas/Petroleum Products/Crude oil from one or multiple
supply source & delivery location.
Important components of Pipeline Project are:
Dispatch/Pumping station
IPS/CP stations
SV/CP stations
Receipt stations
Salient Features of Pipeline Project
4
Pipe & Equipment Procurement
Acquisition of Permanent Land for pumping station,
Receiving station and SV stations.
ROU for line pipe laying.
Statutory regulations and clearances.
Laying of Pipeline
Pre Commissioning & Commissioning
Statutory Regulations & Clearances
Laying of a cross country pipeline requires various
clearances from different authorities. Broadly these are:
Authorization from Petroleum & Natural Gas
Regulatory Board for laying of cross country petroleum
liquid & gas pipeline except dedicated lines.
Environment clearance/Permission to lay pipeline
through wild-life/Sanctuary/ eco-sensitive zone.
CRZ clearance, for pipeline passing through CRZ.
Permission for crossing of Roads / Rivers / Canals /
Railway / Wet-lands / Highways etc.
5
Permission for way–leave facility to lay the pipeline in
Port land in case pipeline is to pass through the port
land.
Explosive Clearance from PESO.
Clearance from Pollution Control Board of respective
State Govt.
Approval from Fire Advisor, Ministry of Home Affairs for
the pipeline.
Gazette Notification for Declaration of Prohibited area
for Dispatch/Pumping stn., IPS/CP stn., SV/CP stn. &
receiving stn.
6
Statutory Regulations & Clearances
ROU Acquisition ( under P&MP ACT,1962)
7
ROU Acquisition is done thru competent
Authority appointed for the project.
Request required to be made for services of
state govt. revenue personnel on deputation to
serve as Competent Authority (C.A).
Central gazette notification to declare
appointment of “C.A” under the P&MP ACT for
dealing with cases related to land and further
notifications for acquisition etc.
Competent Authority handles following activities:
Preparation of 3(i) proposal & submission to MoP&NG
3(i) Gazette notification.
Notice Servicing for 3(i)
Hearing of Objection after minimum 21 days notice
Process of ROU Acquisition
8
Preparation of 6(i) proposal & submission to MOP&NG
6(i) Gazette notification.
Notice Serving for 6(i) to the land owners
Distribution of Compensations.
Opening of ROU
Process of ROU Acquisition
9
Process of Land Acquisition
10
Permanent Land Acquisition The requirement of number of permanent land along the pipeline route is determined after detail engineering. Permanent land is required for Despatch Terminal /Receipt Terminal /SV station /IP station. The steps involved are :
Plot Identification
Submission of proposal to concerned authority for acquisition
Process of Land Acquisition
11
Publication of 4(i) gazette notification.
Notice Servicing & Hearing of Objection
6(i) Gazette notification.
Declaration of award
Possession & Registration of land.
12
ROU Compensation:
Restriction is imposed in the ROU notified land on sale
purchase and permanent construction.
Compensation is paid only at the rate of 10% of market
rate of land for the ROU acquired.
Compensation is given based on Government rates
which is much below the prevailing land rates.
Major Challenges in Land/ROU Acquisition
13
ROU Compensation: Solutions
The compensation should be reviewed for amendment to cover inflation burns and other basic necessities of the affected land owners. Recent times have shown scarcity of land and its multi-fold appreciation in a short span of time.
Permanent acquisition of Pipeline ROU can be done
Develop a common corridor which can be utilized for pipeline laying.
Major Challenges in Land/ROU Acquisition
14
Lack of Trust and uproar by local villagers:
Villagers often indulge in violent protest & uproar as they are not aware of the benefits of the pipeline project.
Solution:
Trust can be developed by driving high Corporate Social Responsibility (CSR) activities through affected areas and providing work opportunities to locals.
Major Challenges in Land/ROU Acquisition
15
Approval from various Departments:
DFCC, Irrigation departments etc are not clear about the
provisions provided in pipeline and what standards should be followed for providing approvals.
Solution:
The procedure should be standardized at ministry level.
A standard booklet should be issued to all the concerned.
Common safety parameters should also be provided in the booklet.
Statutory Issues
16
Change in Jurisdiction of Approving authority:
Jurisdictions of canal (LGC) and roads (PIU) were changed
from one authority to another after issue of demand
notes. This lead to submission of fresh applications to new
authorities for approvals, resulting in delay.
Solution:
Approval should be given by the department issuing the
demand note. Any such approval should be honored by all
the authorities, even if jurisdiction is changed in between.
Statutory Issues
17
EIA study /Environmental & Forest clearance
For obtaining Environment & Forest Clearance, Project Proponent
needs to conduct EIA & RA Study of the entire route including
boosting stations. Even Population Density Index needs to studied.
Time elapse to wait for field data collection for EIA study till
monsoon period is over.
Time consuming environmental public hearings required to be
conducted in every districts of each states through which pipeline
shall be traversing .
Solution:
EPH shall be conducted after 30 days of press notification involving
all the stakeholders.
Statutory Issues
Recommendations
18
Expeditious approval of Land Acquisition, Rehabilitation
and Resettlement (LARR) Bill, 2011.
Pipeline industry to be declared as “Infrastructure
Industry”.
To exempt pipeline industry from the purview of MoE&F,
GoI circular dated 30.7.2009 and 21.3.2011
Speedy deputation of Revenue staff and competent
authority by State Govt.
The compensation should be reviewed for amendment
to cover inflation burns and other basic necessities of the
affected.
Recommendations
19
Beneficiaries receiving compensation ought to be
counselled on effective deployment of the large
amounts they receive as lump sum payments.
A major innovation introduced by Haryana in 2010 is
the 'No Litigation Incentive'. Under this incentive,
designed to reduce avoidable litigation around land
acquisition, an additional 20 per cent of the basic rate
of land determined by the Land Acquisition Collector
would be paid as incentive to landowners who do not
challenge the acquisition of their land, and accept the
compensation awarded as final.
20
THANK YOU