roll-out of a dense urban charging network for brighton & hove · roll-out of a dense urban...
TRANSCRIPT
Roll-out of a dense urban charging
network for Brighton & Hove
Sujith Kollamthodi, Practice Director – Policy,
Strategy & Economics
APRIL Meeting of the Transport Group
4th July 2018
2July 2017Unclassified - Public Domain© Ricardo plc 2017
• Ricardo was commissioned by Pebble Power to investigate the feasibility
of rolling out a dense public charging network in Brighton
• City is well-placed to become a leading player in EV deployment:
– Strong local environmental agenda with high levels of public support
– Brighton was the first local authority outside of London to install public
charging infrastructure
– The city has an AQMA, so measures to encourage a shift away from
petrol/diesel vehicles are useful
• However, a significant proportion of households in Brighton do not have
access to off-street parking and there is an aim to start encouraging the
take-up of electric taxis
• Our work focused on:
– Identifying options for on-street charging (residential and destination
charging)
– Identification of options for DC rapid charging to support electric taxis
– Identification of any local grid capacity constraints
• Liaised with UK Power Networks’ connections team to get access to key
grid-related information on future capacity, technical constraints and costs
Roll-out of a dense urban charging network for Brighton & Hove
3July 2017Unclassified - Public Domain© Ricardo plc 2017
Public charging infrastructure has been
found to have an integral role in enabling a
growing electric vehicle market
Source: Hall and Lutsey, Emerging Best Practices for Electric Vehicle Charging Infrastructure, International Council for Clean Transportation, 2017
• Norway and the Netherlands are the leading
electric vehicle markets and have more than 10
times as many public charge points per capita
compared to markets with an average level of EV
penetration
• Other leading markets such as California and
China have three to five times the average
numbers of public charge points per capita.
• Level 2 (charging speeds between 3.3 kW -7.4 kW)
and DC fast charging infrastructure have been
shown to be linked with EV uptake
• The availability of consumer purchase incentives
have also been linked to higher levels of EV uptake
Roll-out of a dense urban charging network for Brighton & Hove
4July 2017Unclassified - Public Domain© Ricardo plc 2017
DC EV charging:
• CCS or CHAdeMO standards (+ other proprietary, e.g. Tesla)
• Mostly used for rapid charging (~50 kW and above)
• Increased interest in ultra rapid chargers (up to 350kW)
ADVANTAGES
• High charging rate
• Does not rely on
vehicle on-board
equipment
DISADVANTAGES
• More expensive hardware and
installation
• Competing standards
• Overuse can reduce battery lifeSource: www.ABB.com Source: www.ionity.eu
AC EV charging:
• Single European charging standard
• Mostly a single plug type (Type 2 connector)
• Single phase or three phase (3 kW to 43 kW)
ADVANTAGES
• Relatively cost effective
• Simplest to install and
connect
• Many installation options
DISADVANTAGES
• Charging power limited
by vehicle charger
• Slower charging rateSource:
www.rolecserve.com Source: ubitricity.comSource: www.pod-point.com
Charging infrastructure – AC and DC charging
5July 2017Unclassified - Public Domain© Ricardo plc 2017
The appropriate power is determined by a number of considerations
• Dwell times and journey distances
• Available capacity in the local grid infrastructure
• Available budget for installing new charging infrastructure
Charging infrastructure – charging rates, power requirements and ease of use
Slow charging Rapid charging
3-7 kW (AC)
8-20 miles/hour
(Domestic / work-
place / destination
charging)
11-22 kW (AC)
30-60 miles/hour
(Destination
charging)
50 kW (DC)
140 miles/hour
(typically for on-
route charging)
120+ kW (DC)
340 miles/hour
(typically for on-
route charging)
Making sure the charge points are easy to use
• Many existing charge points require users to sign up to apps, subscriptions or hold RFID cards
• Initial recommendation for contactless payments for both slow and rapid charging in Brighton
6July 2017Unclassified - Public Domain© Ricardo plc 2017
On-street charging
Requests for on-street residential charge points in
Brighton
Zap-map.com shows that there are currently
only 19 public charge points in the city (11 of
which are in the city centre)
Source: Brighton & Hove City Council
Source: Zap-map.com
7July 2017Unclassified - Public Domain© Ricardo plc 2017
In early 2018, Brighton & Hove City Council was
tendering a street lamp replacement programme
• Opportunity for lamp posts to be installed that incorporate
EV charge points – more cost effective
• Survey of lamp posts to determine which are suitable
locations for charging points
• However, not possible to determine remotely which lamp
posts are suitable in terms of the electricity supply
• This is because the size of the fuse in the lamp posts and
in many cases the size of the low-voltage service cable to
the lamp post is not recorded.
• To determine exactly which locations are suitable the
contractor undertaking the lamp post replacement work
must investigate which locations are suitable.
• UK Power Networks’ Engineering Design
Standard for EV charge point connections:
– No more than 10 charger connections per LV
main
– Maximum Power Rating cannot be higher than
the power rating listed against each fuse
current rating
• In practice this means that only those lamp
posts with a fuse rated at 16A or higher are
suitable for charging points and only at up to
3.68 kW
On-street charging
8July 2017Unclassified - Public Domain© Ricardo plc 2017
• Long-list of potential sites developed
• Each site is expected to consist of five 50 kW DC chargers, and five 22 kW AC chargers: giving a
peak required demand capacity of 360 kW (288 kW connection required once diversity factor of 0.8
applied).
• UKPN guidance on infrastructure costs and available capacity also used to support the analysis
DC rapid charging sites for electric taxis - overview
Provision and installation of 300 metres of HV cable £35,000
800 kVA substation £20,000
Provision and installation of LV cabling £4,400
Metering panel £800
HV joint to the network £2,900
Operation and maintenance costs £1,800
TOTAL £64,900
9July 2017Unclassified - Public Domain© Ricardo plc 2017
DC rapid charging sites for electric taxis – available capacity at primary substations
Site Firm Capacity (MW) 2016/17 Maximum
Demand (MW)
2021/22 Estimated
Max Demand (MW)
Available Capacity
2021/22 (MW)
Brighton Town 11kV 66.10 45.00 46.30 19.80
Hangleton 11kV 20.80 14.10 14.50 6.30
Kemp Town 11kV 23.80 14.90 15.20 8.60
Moulsecoomb 11kV 23.80 21.30 21.60 2.20
North Shoreham 11kV 22.90 16.80 17.10 5.80
Portslade 11kV 43.90 16.60 17.10 26.80
Queens Park 11kV 22.50 15.30 15.90 6.60
Rottingdean 11kV 22.60 11.70 11.80 10.80
South Hove 11kV 21.70 18.10 19.00 2.70
Southwick 11kV 19.10 12.60 12.80 6.30
The Droveway 11kV 36.60 22.10 22.40 14.20
Withdean 11kV 20.40 14.30 14.70 5.70
• Most primary substations have available capacity for EV charging infrastructure
• Three exceptions (in red) - may incur higher reinforcement costs
10July 2017Unclassified - Public Domain© Ricardo plc 2017
Possible DC rapid charging sites for electric taxis – illustrative examples
• Withdean primary substation is 150 metres away, and has 5.7 MW
of capacity available.
• The site is not overly built up and traffic management for the
works should be straightforward.
• The existing substations may have sufficient capacity, in which
case only LV cabling works is required
• Alternatively the existing transformer at one or both of the
substations could be replaced with a higher capacity unit. The
existing substations appear to be GRP (Glass Reinforced Plastic)
packet type, with good access such that modifications can be
made.
• Alternatively a new secondary substation may be required
• Conclusion: Excellent potential DC rapid charging hub
location and potential for slow/medium charging facilities
Withdean charging hub
11July 2017Unclassified - Public Domain© Ricardo plc 2017
Possible DC rapid charging sites for electric taxis – illustrative examples
• The parking locations are some distance from the
substations – HV cabling required – high cost
• It appears significant traffic management for
works would be required
• The area is fed from the Moulsecoomb primary
substation which has capacity constraints in future
years
• There may be spare capacity from the existing
substation at Natal Road which has (2 x 500kVA)
meaning only LV works would be required.
• Conclusion: Poor location
Lewes Road charging hub
12July 2017Unclassified - Public Domain© Ricardo plc 2017
Summary and conclusions
• Pebble Power and Brighton & Hove City Council now have clear information on how to take forward
plans for installing on-street charge points and DC rapid charging hubs
• We have provided information on logistical issues, technical constraints, grid capacity issues and
estimated costs for different installations
• We have also reviewed the market for charge point providers and made clear recommendations
based on Pebble Power’s specific objectives for Brighton (i.e. the need for contactless payment
mechanisms)
• Key points
– On-street charging infrastructure can be more cost effective if combined with street lamp
replacement programmes – BUT, can mean that charge point power is limited to 3.7 kW
– Need to also consider the maximum number of charge points that could be installed on a given
street, taking into account grid constraints
– For DC charging hubs, it is essential to consider current and future grid capacity constraints, the
costs of any reinforcement and cabling works and also the costs of traffic management should
extensive works be required
13July 2017Unclassified - Public Domain© Ricardo plc 2017
Contact for queries:
Sujith Kollamthodi
Practice Director – Policy, Strategy & Economics
Ricardo Energy & Environment
01235 753526