ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT ALL INDIA COURSE ON PROJECT PLANNING, MONITORING AND CONTROL SYSTEM RK GUPTA Senior Technical Director Head, Analytics & Modelling Division National Informatics Centre New Delhi- 110003 Email: [email protected]

Upload: samuel90

Post on 14-May-2015

2.382 views

Category:

Business


0 download

TRANSCRIPT

Page 1: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

ALL INDIA COURSE ON

PROJECT PLANNING, MONITORING AND

CONTROL SYSTEM

RK GUPTA

Senior Technical Director

Head, Analytics & Modelling Division

National Informatics Centre

New Delhi- 110003

Email: [email protected]

Page 2: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

GENERAL CONCEPT

PROJECT MONITORING

-MACRO MONITORING

-STATUS MONITORING

PROJECT MANAGEMENT

-MICRO MONITORING & CONTROL

-OPERATIONAL MONITORING

DIFFERENT LEVELS OF MONITORING

ON-LINE COMMUNICATION SYSTEM

•COMPUTER AIDED PM MODEL(S) USING NICNET

Page 3: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

Table 1 Status as on 31.3.98

Extent of Time/Cost Overrun in Projects with respect to Original schedule

SNO. SECTOR No. Of. Total Cost(Rs. CRS) Proj. w ith Cost Over run Proj With Time overrun

ProjectsOriginal Anticipated Cost over No. Orig.Cost Anticipated %INCR No Orig. Cost Anticipated Range

Cost Run(%) Cost Base Cost No

Atomic Energy 6 5902.6 11462.3 94.2 3 4889.3 10803 121 5 2455.6 5041.3 6--60

Civil Aviation 9 573 927.4 61.9 7 496.9 851.3 71.3 7 464.2 801.5 11--71

Coal 71 12222.3 13806.8 13 22 5788.9 7526.4 30 39 7559.6 9201.4 6--171

Finance 1 118.3 348.8 194.9 1 118.3 348.8 194.9 1 118.3 348.8 72--72

Fertilizers 4 1912.3 2834.6 48.2 3 1700.1 2622.4 54.3 1 618.4 642.4 25--25

I&B 7 244.8 316.9 29.5 3 76.4 148.6 94.4 6 185.6 257.7 24--120

Mines 3 3884.1 3884.1 0 0 0 0 0 0 0 0 0--0

Steel 10 6789.8 13739 102.3 6 6174.7 13123.8 112.5 10 6789.8 13739 1--66

Petrochemicals 3 3820.7 3852.6 0.8 2 3643.2 3675 0.9 3 3820.7 3852.6 26--32

Petrolium 50 34117.4 34880.4 2.2 6 5407.5 7674.1 41.9 30 24117.4 25415 1--61

Pow er 38 23825.4 42379.8 77.9 26 11073.1 29861.7 169.7 26 11065.2 27342.1 6--124

Heavy Industry 1 75.7 307 305.4 1 75.7 307 305.4 0 0 0 0--0

Railw ays 180 23180.2 32346 39.5 102 11607.9 20817.8 79.3 38 4132 6528.5 6--72

Surface Transport 46 4990.4 7819.6 56.7 30 3466.7 6295.9 81.6 32 4307 6828.8 8--120

Telecommunication 20 1179.8 1444.6 22.4 1 239.7 546 127.8 13 546.9 527.6 3--21

Others 12 5285.8 5749.1 8.8 7 5029.9 5493.2 9.2 5 195.8 219.5 3--47

Total 461 128122.6 176099 37.4 220 59788.3 110095 84.1 216 66376.5 100746.2

Page 4: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

Table 2 Status as on 31.3.98

Extent of Time/Cost overrun in Projects with respect to latest ScheduleSNO. SECTOR No. Of. Total Cost(Rs. CRS) Proj. w ith Cost Over run Proj With Time overrun

ProjectsOriginal Anticipated Cost over No. Orig.Cost Anticipated %INCR No Orig. Cost Anticipated Range

Cost Run(%) Cost Base Cost No

Atomic Energy 6 11632.1 11462.3 -1.5 0 0 0 0 5 5211.1 5041.3 6--39

Civil Aviation 9 763.4 927.4 21.5 6 664.2 828.3 24.7 7 650.5 801.5 11--41

Coal 71 13107.1 13806.8 5.3 15 5273.1 6125.8 16.2 38 8395.9 9152.9 6--120

Finance 1 348.8 348.8 0 0 0 0 0 1 348.8 348.8 16--16

Fertilizers 4 2106.2 2834.6 34.6 3 1894 2622.4 38.5 1 618.4 642.4 15--15

I&B 7 300.1 316.9 5.6 1 20.2 39.4 95 6 240.9 257.7 12--33

Mines 3 3884.1 3884.1 0 0 0 0 0 0 0 0 0--0

Steel 10 9933.4 13739 38.3 5 8508.6 12314.1 44.7 10 9933.4 13739 1--59

Petrochemicals 3 3820.7 3852.6 0.8 2 3643.2 3675 0.9 3 3820.7 3852.6 26--32

Petrolium 50 33721.6 34880.4 3.4 5 5391.1 7631.9 41.6 30 23721.6 25415 1--49

Pow er 38 34255.4 42379.8 23.7 23 14606.6 22965.2 57.2 25 17087.3 23782.3 2--33

Heavy Industry 1 191.3 307 60.5 1 191.3 307 60.5 0 0 0 0--0

Railw ays 180 27135.6 32346 19.2 85 12796.1 18075.4 41.3 38 5276.6 6528.5 6--69

Surface Transport 46 6026.9 7819.6 29.7 24 3525.4 5318.9 50.9 32 5106.4 6828.8 4--120

Telecommunication 20 1179.8 1444.6 22.4 1 239.7 546 127.8 9 431.2 411.9 4--21

Others 12 5319 5749.1 8.1 6 5000.4 5430.5 8.6 5 195.8 219.5 3--47

Total 461 153725.5 176099 14.6 177 61753.9 85879.9 39.1 210 81038.6 97022.2

Page 5: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

Table 3 Status as on 31.3.98Classification of Projects in Mega, Major and Medium

|-------During 3 Qtr--------------------------| |-------------------------During 4 Qtr------------------------|No. Inv. In Rs. Crores % of Total No. Inv. In Rs. Crores % of Total Exp. Till Qtr.

Mega Projects 43 99832.72 59.5 45 107561.84 61.08 50099.36

Major Projects 185 58154.93 34.66 184 58507.39 33.22 22731.32

Medium Projects 226 9784.37 5.83 232 10029.57 5.7 3830.03

Total 454 167772.02 99.99 461 176098.8 100 76660.71

Page 6: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

Table 4 Status as on 31.3.98

Frequency Distribution Of Projects At the end of 4th Qtr

Name Of the Sector No of Mega Anticipated No. of Major Anticipated No. of Medium Anticipated Total no. of Total Cost

Projects Cost(Rs crores) Projects Cost(Rs crores) Projects Cost(Rs crores) Projects (Rs. Crores)

Atomic Energy 3 10803 3 659.27 0 0 6 11462.27

Civil Aviation 0 0 3 669.08 6 258.36 9 927.44

Coal 4 6021.05 19 5443.79 48 2341.99 71 13806.83

Finance 0 0 1 348.8 0 0 1 348.8

Fertilizers 1 1190 3 1644.56 0 0 4 2834.56

I&B 0 0 0 0 7 316.91 7 316.91

Mines 2 3726.58 1 157.5 0 0 3 3884.08

Steel 3 12214.61 2 1240.22 5 284.13 10 13738.96

Petrochemicals 1 3505 2 347.55 0 0 3 3852.55

Petrolium 12 23557.93 23 10759.22 15 563.21 50 34880.36

Pow er 14 34334.52 19 7809.71 5 235.54 38 42379.77

Heavy Industry 0 0 1 307 0 0 1 307

Railw ays 4 6998.15 77 21266.43 99 4081.38 180 32345.96

Surface Transport 0 0 27 6997.56 19 822.03 46 7819.59

Telecommunication 0 0 3 856.7 17 587.88 20 1444.58

Others 1 5211 0 0 11 538.14 12 5749.12

Total 45 107561.84 184 58507.39 232 10029.57 461 176098.78

Page 7: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

SUMMARY

STATUS AS ON 31ST MAR, 1998STATUS OF ORIGINAL LATEST

PROJECTS

#OF PROJECTS 461 461

#OF PROJECTS 241 284

WITH NO COST

OVER-RUN

#OF PROJECTS 245 251

WITH NO TIME

OVER-RUN

#OF PROJECTS WITH 33 6

NO TIME & COST

OVER-RUN

Page 8: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

STATUS OF CENTRAL SECTOR PROJECTS AS ON 31.3.1998

TOTAL PROJECTS(461)

TIME OVER RUN

(1-171 MONTHS)

COST OVER RUN

(37.4 %)

APPROVED COST

128122.6cr

ESTIMATED COST

176098.8cr

MEDIUM MAJOR MEGA

3830.03cr 22731.32 cr 50099.36cr

Page 9: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

MEGA

BEHIND SCHEDULE ON SCHEDULE

ORIGINAL APPROVED ANTICIPATED COST

COST

Page 10: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

TREMENDOUS GROWTH

-INFORMATION TECHNOLOGY

-COMPUTING POWER

-COMPUTER COMMUNICATION

-INTERNET & SERVICES

* MULTI-MEDIA

* EDI

* WEB-SURVEYING

* ARTIFICIAL INTELLIGENCE

* NEURAL NETWORKS

TIME, COST SAVING, INCREASING EFFICIENCY AND EFFECTIVENESS

WHAT WAS NOT POSSIBLE- NOW POSSIBLE

Page 11: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

STATUS SOFTWARE CONTRACTS IN US

I:OF THE SAMPLED PROJECTS

-50% HAD COST OVERRUNS

-60% HAD TIME OVERRUNS

-29% NEVER DELIVERED

OF THE DELIVERED,

-REQUIRE MAJOR ‘REWORK’ OR MODIFICATIONS

Contd:

Page 12: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

STATUS SOFTWARE CONTRACTS IN US

II. SOFTWARE PROJECTS BY IBM BUDGET > US $6.2 MILLION

-29% OF THE S/W DEVELOPERS WERE PAID, BUT NEVER

DELIVERED

-47% OF THE S/W DELIVERED BUT NEVER USED

-19% OF THE PROJECTS WERE ABONDENED OR REWORK

-3% OF THE PROJECTS COULD BE USED ONLY AFTER

CONSIDERABLE CHANGES

-JUST 2% USED AS DELIVERED

SOFTWARE PROJECTS BY INDIAN COMPANIES INDICATES A RELATIVELY BETTER PERFORMANCE

Page 13: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

MAJOR FACTORS RESPONSIBLE FOR OVERRUNS

-CHANGE IN SCOPE OF PROJECTS OVER A PERIOD OF TIME

-UNDER ESTIMATION OF COST AND TIME AT THE TIME OF PROJECT FORMULATION

-INFLATION CAUSING PRICE CHANGES OF ITEMS AND THUS COST OVERRUN

-EXCHANGE RATE VARIATIONS (ONLY FOR PROJECTS WHICH REQUIRE IMPORT OF EQUIPMENT/MATERIAL)

Page 14: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CO-ORDINATE THE PROJECT WITH OUTSIDE AGENCIES

MAIN CO-ORDINATOR OF PROJECTS TECHNICAL

ASPECTS BETWEEN TOP AND OPERATIONAL LEVEL

EXECUTIVE

ACTUALLY EXECUTE THE PROJECTS AND RESPOSIBLE FOR MEETING OBJECTIVE(S)

DUTIES

ROOT LEVEL (PROJECT SITE)

REGIONAL LEVEL (PROJECT REGIONAL HQS)

CORPORATE LEVEL (PUS’s-CORPORATE OFFICE)

APEX ORGANIZA

TION(S) (CABINAT SECTT.,

FIN. COMM. , MPI)

ADMINISTRATIVE

MINISTRY (CENTRAL/S

TATE MINISTRY)

LEVELS

FLOW OF

OBJECTIVE(S

BUDGET(S)

PLAN(S)

ETC.

FLOW OF

INFORMATION

ACTUAL FIG

ACHIEVEMENTS

ETC.

MANAGEMENT FUNCTIONAL

TOP

MIDDLE

OPERATIONAL

V

IV

III

II

I

LEVELS OF MONITORING IN GOVT. ENVIRONMENT

Page 15: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

TODAY’S PROJECT MANAGEMENT ENVIRONMENT

•MULTI-PROJECT SITES(GEOGRAPHICALLY DISTRIBUTED)

•MULTI-LOCATION OF PROJECT(S)

•MULTI-EXECUTING AGENCIES

•MULTI-COLLABARATION ENVIRONMENT

•MULTI-PRODUCTS

•MULTI-LEVELS OF MONITORING

•MULTI-PROCUREMENT SOURCES

•MULTI-CULTURE HUMAN RESOURCES

•MULTI-DIVISIONS

•MULTI-PROJECT MANAGER

TO EFFECIENTLY MANAGE PROJECT(S) IN SUCH A COMPLEX AND DYNAMIC ENVIRONMENT IS A REAL CHALLENGE TO PROJECT LEADER

Page 16: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

IMPORTANT COMPONENT OF PROJECT MANAGEMENT BODY OF KNOWLEDGE

COMMUNICATION MANAGEMENT

BESIDES,

.SCOPE MANAGEMENT

.TIME MANAGEMENT

.COST MANAGEMENT

.RISK MANAGEMENT

.HUMAN RESOURCE MANAGEMENT

.CONTRACT MANAGEMENT

AND QUALITY MANAGEMENT

Page 17: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

-NEED FOR CAPMS

•MULTI LOCATIONAL PROJECT SITES

(VAST GEOGRAPHICAL SPREAD)

•MULTI LEVEL MONITORING

•MULTI EXECUTION AGENCIES

•SCENARIO GENERATION ANALYSES

Page 18: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

-NIC STRENGTH

EXPERTISE & INFRASTRUCURE NEEDED FOR DEVELOPMENT & IMPLEMENTATION OF ‘CAPMS’ EXISTS

Page 19: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

IMPORTANT

FOR ANY PROJECT MANAGEMENT APPLICATION MOST IMPORTANT

.TIME HORIZON

.IMPLEMENTATION STRATEGY MOST CRUCIAL

-CONSISTENT AND REGULAR FLOW OF INFORMATION

-FROM WHERE, WHAT INFORMATION AND WHEN, -

AVAILABLE FLOW

.COST BENEFITS OF MANUAL VS ‘CAPMS’

-DIFFICULT TO QUANTIFY?

-EXPERIENCE

Page 20: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

-MODERN PROJECT MANAGEMENT TOOL - E- MAIL

-IT IS IMPORTANT IN THE PRESENT CONSTRAINT ENVIRONMENT OF

TIME, COST AND RESOURCE

-EFFICIENT, TIMELY AND CLEAR COMMUNICATION IS KEY TO THE

SUCCESS OF A PROJECT COMPLETION

Page 21: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

-ADVANTAGES

CONCISE; EFFICIENT; ON-LINE; HIGHLY RELIABLE

SIMPLE AND VERIFIABLE

MINIMAL TRAINING; COST-EFFECTIVE; MINIMAL

OPERATING COST, FAST AND USER-FRIENDLY

Page 22: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

- SELECTION FROM VARIETY OF SERVICES

-NECESSARY

-RECOMMENDED

-GOOD TO HAVE

Page 23: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

NECESSAY:

ON-LINE:

DIRECTORY; MESSAGE FORMATTING; AVAILABILITY ON MULTI-PLATFORMS

RECOMMENDED:

ON-LINE MESSAGE STORAGE; ON-LINE HELP

Page 24: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

SPECIFIC EVALUATION

•E-MAIL ONLY IF PROJECT MEETS MIN-CRITERIA

•EVALUATE COST-BENEFIT VIS-A-VIS CURRENT COMMUNICATION SYSTEM

•COST-BENEFITS COMPARISON FEATURE DESIRED VS CURRENT COMMUNICATION SYSTEM

Page 25: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

A NATIONWIDE SATELLITE BASED COMPUTER COMMUNICATION NETWORK

Page 26: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CPM/PERT

BASED PROJECT MONITORING SYSTEM

USING

SATELLITE BASED COMPUTER COMMUNICATION

NETWORK

(NICNET)

Page 27: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CPM/PERT BASED MONITORING SYSTEM

FOR

CONSTRUCTION OF FOODGRAIN STORAGES

(FOR FOOD CORPORATION OF INDIA)

CASE STUDY

Page 28: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

OBJECTIVES

• TO MEET THE STORAGE DEMAND OF FOODGRAINS DURING VIII FIVE YEAR PLAN

• APP. 100 STORAGE GODOWNS OF 5,000, 10,000 & 25,000 TONNES CAPACITY HAVE BEEN PLANNED

• TO GENERATE 10 LAKH TONNES STORAGE CAPACITY WITH FINANCIAL OUTLAYS OF APP 100 CRORES

• CONSTRUCTION BEING AN IMPORTANT ACTIVITY IS TO BE COMPLETED WITHIN DEFINED TIME FRAME

• ->CLOSE COMPUTER BASED MONITORING AND CONTROLLING SYSTEM IS ESSENTIAL FOR DIFF. LEVEL OF MONITORING AGENCIES FOR MIN. TIME & COST OVERRUNS.

Page 29: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CONSTRUCTION SITESSNO. SITE STATE CAPACITY(TONS)

BADAMPAHAR ORISSA 10,000

PARSAKHERA UP 5,000

HAMIRPUR HP 1,600

SALEM TAMILNADU 15,000

RATNAGIRI MAHARASHTRA 10,000

GORAKHPUR UP 5,000

CHATHA J&K 5,000

SHOLAPUR MAHARASHTRA 5,000

DOWLESHRAM AP 10,000

ONGOLE AP 5,000

KHAMMAM AP 10,000

BELLARY KARNATAKA 25,000

Page 30: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

OVERALL CO-ORDINATION AND PLANNING

MAIN CO-ORDINATOR OF PROJECTS

TECHNICAL ASPECTS BETWEEN TOP AND OPERATIONAL LEVEL

EXECUTIVES

ACTUALLY EXECUTE THE PROJECTS AND RESPOSIBLE FOR MEETING OBJECTIVE(S)

DUTIES

ROOT LEVEL (PROJECT SITE)

REGIONAL LEVEL (PROJECT REGIONAL HQS)

CORPORATE LEVEL (ED. ENGG. DIR)

PID

CHAIRMAN/ EXEC DIR

FCI

LEVELS

FLOW OF

OBJECTIVE(S

BUDGET(S)

PLAN(S)

ETC.

FLOW OF

INFORMATION

ACTUAL FIG

ACHIEVEMENTS THROUGH ON-LINE COMP COM.NETWORK NICNET)

MANAGEMENT FUNCTIONAL

TOP

MIDDLE

OPERATIONAL

V

IV

III

II

I

LEVELS OF MONITORING AT FOOD CORPN. OF INDIA

Page 31: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

MONITORING ON MONTHLY BASIS-

•FLOW OF INFORMATION USING NICNET:

•MONITORING LEVELS

1. CHAIRMAN, FCI

2. ED, ENGG DIVISION

3. REGIONAL/PROJECT SITES

Page 32: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

IMPLEMENTATION OF MONITORING SYSTEM FOR ALL SITES

•PERT NETWORK FOR REMAINING 26 SITES

•INPUT FOR ALL 26 SITES

•CHECKING OF NETWORK

•STATUS AS ON DATE(INPUT)

•GENERATION OF MONITORING REPORTS

Page 33: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

MONITORING REPORTS (TIME)

•INTEGRATED SCHEDULES

•GANTT/PERT CHARTS(THROUGH HPM)

•MILE STONE PROGRESS

•ORIGINALLY/UPDATED PROJECT SCHEDULES

•COST SCHEDULES

•TIME OVERRUNS WITH REASONING

•ANALYSIS AND FEEDBACK TO PROJECT SITES

Page 34: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

IMPLEMENTATION LOGISTICIDENTIFICATION OF PERSONS AT

•FCI PROJECT/REGIONAL SITES

•NIC STATES/DISTRICT SITES

•FCI HQS

•FCI ENGG. DIVISION

HARDWARE/SOFTWARE

•PC/AT OR HIGHER

•HPM VER 3.0

•DOS VER 3.0

•MS-WINDOWS

NOTE:-SIX PERSONS (TECHNICAL) AT FCI, ENGG. DIVISION

FOR RUNNING THE SYSTEM ON MONTH TO MONTH BASIS

- INITIALLY THE SYSTEM COULD BE AT NIC, HQS FOR A PERIOD OF 3 TO 4 MONTHS

Page 35: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

MAIN MENU

1. ADD DATA

2. EDIT DATA

3. PREPARE DATA FOR TRANSMISSION

4. EXIT

HIGHLIGHT OPTION WITH OR AND PRESS

OR PRESS APPROPRIATE NO.

MAIN MENU OF MODULE-1 IMPLEMENTED AT FIELD LEVEL.

Page 36: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

MAIN MENU

1. ADD NEW PROJECT

2. EDIT PROJECT DATA

3. PROCESS MONTH’S DATA

4. POST EXPORTING JOB

5. PRINT REPORTS

6. EXIT

HIGHLIGHT OPTION WITH OR AND PRESS

OR PRESS APPROPRIATE NO.

MAIN MENU OF MODULE-2 IMPLEMENTED AT PID OF FCI.

Page 37: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

REPORT MENU1. INTEGRATED SCHEDULE OF CONSTRUCTION

2. GANTT CHART (THROUGH HPM)

3. MILESTONE PROGRESS

4. OVERALL PROJECT SUMMARY

5. ORIGINAL PROJECT SCHEDULE

6. PERT CHART (THROUGH HPM)

7. UPDATED PROJECT SCHEDULE

8. SUMMARY EXPENDITURE STATEMENT

9. RETURN TO MAIN MENU

HIGHLIGHT OPTION WITH OR AND PRESS

OR PRESS APPROPRIATE NO.

MAIN MENU OF MODULE-2 IMPLEMENTED AT PID OF FCI.

Page 38: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

FLOW OF INFORMATION FOR THE IMPLEMENTATION OF CPM/PERT BASED MONITORING SYSTEM (TIME

MANAGEMENT)

FCI Hqs

ED (Engg) FCI

A

B

C

D

CHAIRMAN FCI

ED (PID) FCI

PROJECT SITES FCI

REGIONAL SITES FCI

NIC HQS

DELHI (BARAKHAM

BA ROAD)

DELHI (NEHRU PLACE)

PHYSICAL

HANDLING

1

2

3

9

10

1

2

3

9

10

1

2

3

4

5

15

29 PC/XT ++

N

I

C

N

EN T

INTEGRATED REPORTS

PROJECT SITES

REGIONAL HQS

NIC STATE/DISTRICT CENTRES

Page 39: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CONSTRUCTION OF FOOD STORAGE GODOWN REPORT 1

INTEGRATED SCHEDULE OF CONSTRUCTION OF PROJECTS AS ON 17/12/98

Sitename Capicity Planned Planned Planned

In Tonnes Start Finish Duration(Days)

BADAMPAHAR 10000 30/06/91 21/07/92 387

CHATA 5000 14/10/91 15/10/92 367

GORAKHPUR 8340 21/10/91 8/11/92 384

HAMIRPUR 1670 7/7/91 2/5/92 300

PARSAKHERA 5000 12/8/91 2/9/92 387

RATNAGIRI 10000 13/11/91 7/4/93 511

SALEM 15000 17/06/91 29/11/92 531

Page 40: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CONSTRUCTION OF FOOD STORAGE GODOWN Report Number 3

INTEGRATED SCHEDULE OF CONSTRUCTION OF OBJECTS AS ON 17/12/91

Milestone Planned Date Project/Act. Date

Name Description Earliest Latest Earliest Latest

HAMCK1 Confirm Aw ard Letter Issue 19/11/91 19/01/91 28/12/9128/12/91

Delay(Days) 39 Reason : Delay Due To Approval of AA &ES

HAMCK2 Confirm DPC Completion 4/1/92 4/1/92 12/2/92 12/2/92

Delay(Days) 39 Reason :

HAMCK3 Confirm Top tie Lintel Completion 13/02/92 13/02/92 23/3/92 23/3/92

Delay(Days) 39 Reason :

HAMCK4 Confirm WBM - 3 Layers Completion 19/03/92 19/03/92 13/4/92 13/4/92

Delay(Days) 25 Reason :

HAMCK5 Confirm Sheeting and Wind Tie Completion 6/3/92 6/3/92 14/4/92 14/4/92

Delay(Days) 39 Reason :

HAMCK6 Confirm Flooring Completion 31/03/92 31/03/92 9/5/92 9/5/92

Delay(Days) 39 Reason :

HAMCK7 Confirm Handing Completion 1/5/92 1/5/92 10/6/92 10/6/92

Page 41: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CONSTRUCTION OF FOOD STORAGE GODOWN Report Number - 4

INTEGRATED SCHEDULE OF CONSTRUCTION OF PROJECTS AS ON 20/02/92

Site Id # Site Capacity Planned Projected Delay

Name (Tonnes) Start Finish Duration Finish Duration (Days)

HIMACHAL PRADESH

20/02/92 HAMIRPUR 1670 7/7/91 2/5/92 300 20/7/92 379 79

J & K

20/02/92 CHATHA 5000 14/10/91 15/10/92 367 3/11/92 386 19

MAHARASHTRA

20/02/92 RATNAGIRI 10000 13/11/91 7/4/93 511 17/4/93 521 10

ORRISA

20/02/92 BADAMPAHAR 10000 30/06/91 21/7/92 387 28/9/92 456 69

TAMILNADU

20/02/92 SALEM 15000 17/06/91 29/11/92 531 18/1/93 581 50

U.P

20/02/92 GORAKHPUR 8340 21/10/91 8/11/92 384 19/11/92 395 11

U.P

20/02/92 PARSAKHERA 5000 12/8/91 2/9/92 387 1/10/92 416 29

Page 42: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CONSTRUCTION OF FOOD STORAGE GODOWN Report No. 5

UPDATED PROJECT SCHEDULE AS ON 20/02/92

SITE NAME:BADAMPAHAR CAPACITY (TONNES):10000

Task Earliest Latest Total

Code Description Start Finish Start Finish Float

BAD001 Preliminary Survey 30/06/91 19/7/91 30/06/91 19/7/91 0

BAD002 Preliminary Estimate 20/07/91 29/7/91 20/07/91 29/7/91 0

BAD003 Detailed Estimate 30/07/91 18/8/91 30/07/91 18/8/91 0

BAD004 Notice Inviting Tender 19/08/91 28/8/91 19/08/91 28/8/91 0

BAD005 Admn. Apprl. & Expnd. Sanction 30/07/91 28/8/91 30/07/91 28/8/91 0

BAD010 Tendering 29/8/91 27/1/91 29/8/91 27/1/91 0

BAD012 Scruitinig & Aw ard 28/09/91 11/11/91 28/09/91 11/11/91 0

BAD013 Mobilisation & Layout 12/11/91 26/11/91 12/11/91 26/11/91 0

BAD016 Eartw ork & Plain Cement Concrete 27/11/91 10/12/91 27/11/91 10/12/91 0

BAD017 Foundations & Column Upto Plinth level 11/12/91 28/12/91 11/12/91 28/12/91 0

BAD018 Col. 1st. & 2nd Lift 29/12/91 11/1/92 29/12/91 11/1/92 0

BAD019 Brickw ork upto Plinth Level & DPC 29/12/91 11/1/92 29/12/91 11/1/92 0

BAD023 Brickw ork 1st & 2nd Lift 12/1/92 31/01/92 12/1/92 31/01/92 0

BAD027 Brickw ork 3rd & 4th Lift 1/2/92 20/02/92 1/2/92 20/02/92 0

BAD029 Brickw ork 5th Lift & vent.Fixing 21/02/92 1/3/92 21/02/92 1/3/92 0

BAD033 Top Tile Lintel 2/3/92 16/03/92 2/3/92 16/03/92 0

BAD034 Truss Erection 17/03/92 31/3/92 17/03/92 31/3/92 0

BAD041 Roof Sheeting & w indties 1/4/92 30/04/92 1/4/92 30/04/92 0

BAD043 InnerPlaster 1/5/92 15/05/92 1/5/92 15/05/92 0

BAD046 Flooring 16/5/92 5/6/92 16/5/92 5/6/92 0

BAD050 Painting,w /w & c/w ,glass fixing & finishing 6/6/92 5/7/92 6/6/92 5/7/92 0

BAD051 Site Clearance & Handing Over 6/7/92 20/07/92 6/7/92 20/07/92 0

BADCK1 Confirm Aw ard Letter Issue 11/11/91 11/11/92 11/11/91 11/11/92 0

Page 43: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CONSTRUCTION OF FOOD STORAGE GODOWN Report No. 7

UPDATED PROJECT SCHEDULE AS ON 20/02/92

SITE NAME:BADAMPAHAR CAPACITY (TONNES):10000

Task Earliest Latest Total

Code Description Start Finish Start Finish Float

BAD001 Preliminary Survey 30/06/91 19/7/91 30/06/91 19/7/91 0

BAD002 Preliminary Estimate 20/07/91 7/10/91 20/07/91 7/10/91 0

BAD003 Detailed Estimate 8/10/91 27/10/91 8/10/91 27/10/91 0

BAD004 Notice Inviting Tender 28/10/91 6/11/91 28/10/91 6/11/91 0

BAD005 Admn. Apprl. & Expnd. Sanction 8/10/91 6/11/91 8/10/91 6/11/91 0

BAD010 Tendering 7/11/91 6/12/91 7/11/91 6/12/91 0

BAD012 Scruitinig & Aw ard 7/12/91 20/01/92 7/12/91 20/01/92 0

BAD013 Mobilisation & Layout 21/01/92 4/2/92 21/01/92 4/2/92 0

BAD016 Eartw ork & Plain Cement Concrete 5/2/92 18/02/92 5/2/92 18/02/92 0

BAD017 Foundations & Column Upto Plinth level 19/02/92 7/3/92 19/02/92 7/3/92 0

BAD018 Col. 1st. & 2nd Lift 8/3/92 21/03/92 8/3/92 21/03/92 0

BAD019 Brickw ork upto Plinth Level & DPC 8/3/92 21/03/92 8/3/92 21/03/92 0

BAD023 Brickw ork 1st & 2nd Lift 22/3/92 10/4/92 22/3/92 10/4/92 0

BAD027 Brickw ork 3rd & 4th Lift 11/4/92 30/04/92 11/4/92 30/04/92 0

BAD029 Brickw ork 5th Lift & vent.Fixing 1/5/92 10/5/92 1/5/92 10/5/92 0

BAD033 Top Tile Lintel 11/5/92 25/05/92 11/5/92 25/05/92 0

BAD034 Truss Erection 26/5/92 9/6/92 26/5/92 9/6/92 0

BAD041 Roof Sheeting & w indties 10/6/92 9/7/92 10/6/92 9/7/92 0

BAD043 InnerPlaster 10/7/92 24/07/92 10/7/92 24/07/92 0

BAD046 Flooring 25/7/92 14/08/92 25/7/92 14/08/92 0

BAD050 Painting,w /w & c/w ,glass f ixing & f inishing 15/8/92 13/09/92 15/8/92 13/09/92 0

Page 44: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

APPRAISAL REPORT

NATHPA JHAKRI POWER CORPORATION LIMITED

TCS-ISP STUDY FOR PROJECT MANAGEMENT FUNCTION

AUG.,93

GOVT. OF INDIA

NATIONAL INFORMATICS CENTRE

PLANNING COMMISSION

NEW DELHI

Page 45: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

PRESENT MONITORING/INFORMATION FLOW AT NJPC

.Targets

. Plans

. Schedules

. Directions

etc.

CORPORATE

OFFICE

(DELHI)

SITE OFFICES .Nathpa .Jhakri

.Progress Reporting .Civil .Electrical Infrastructure Delay-reasons

Page 46: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

FREQUENCY OF PRESENT INFORMATION

FLOW

(Design/Drawing - schedule)

Design

Office

PPM

CELL

PPM

CELL

Shimla

Design

Progress

Monthly

Page 47: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

FREQUENCY OF PRESENT INFORMATION FLOW

(Time & Cost Schedule)PPM CELL

Contractor/njpc

nathpa

jhakhri

Corporate Office CPD

DELHI

MONTHLY REVIEWS MEETINGS

EXTERNAL AGENCIES (QUARTERLY)

Monthly Progress

. .

.

Page 48: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CAPMS - TCS METHODOLOGY

A. Time Schedule & Financial Aspects

Daily Weekly Progress Report

Database

BOQ

Bill Tracking System

%completion based on .quantities executed or .Time spent or .Time remaining

CORE PROJECT MANAGEMENT SYSTEM

.Revised Time Schedules .Cash-Flow Statements . Variance (Schedule and Cost) .Project Finish Dates .Cost to complete .Estimated Actual Cost etc

+Contractors

+

Project Sites

Progress Report (Time & Cost)

input output

Page 49: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CAPMS - TCS METHODOLOGY

b. Engineering - Planning & monitoring

(Shimla Office)

FIG - 8b

DESIGN

PROGRESS

Design/

Drawing

Mgt

System

Latest

Design/Drawing

Schedules

Contractors

For Execution

Page 50: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CAPMS-TCS METHODOLOGY

C. RDBMS - Bill Tracking System

Progress .Construction .Quantity Executed (From measurement book)

Bill Tracking System

Corporate Office For Payment Contractors

Project Sites

(Nathpa/Jhakri) RDBMS

D. MMS- Material Monitoring System

(For major raw materials)

Page 51: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

COMPUTER AIDED PROJECT MANAGEMENT SYSTEM (Recommended)

CONSOLIDATED

DATA

CORE PROJECT MANAGEMENT SYSTEM

QUALITY CONTROL SYSTEM

BOQ SYSTEM

BILL TRACKING SYSTEM

MATERIAL MONITORING SYSTEM

DESIGN SCHEDULE SYSTEM

REVISED TIME SCHEDULE (PACKAGE OVERALL) PROJECTED FINISHED DATES PERT/GANTT CASHFLOW STATEMENTS COST-TO-COMPLETE ESTIMATED ACTUAL COST VARIANCE (SCHEDULE COST) REPORTS FOR EXTERNAL AGENCIES

NORMAL REPORTS .FINANCIAL PROGRESS & FUTURE REQUIREMENTS .STATUS REPORTS .BILLING .DRAWING .EXCEPTIONAL REPORTS .QUALITY CONTROL

DESIGN DATE SCHEDULES

PERT-REPORTS

CPMS

Page 52: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

CAPMS-TCS METHODOLOGY

C. RDBMS - Bill Tracking System

Progress .Construction .Quantity Executed (From measurement book)

Bill Tracking System

Corporate Office For Payment Contractors

Project Sites

(Nathpa/Jhakri) RDBMS

D. MMS- Material Monitoring System

(For major raw materials)

Page 53: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

FREQUENCY OF PRESENT INFORMATION FLOW

(Time & Cost Schedule)PPM CELL

Contractor/njpc

nathpa

jhakhri

Corporate Office CPD

DELHI

MONTHLY REVIEWS MEETINGS

EXTERNAL AGENCIES (QUARTERLY)

Monthly Progress

. .

.

Page 54: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

SIMULATION SOFTWARE FOR NETWORK BASED PROJECT MANAGEMENT

•CPM/PERT INDICATES THE ACTIVITIES TO BE CONTROLLED THROUGH CRITICAL PATH

•FOR PLANNING AUTHORITIES IT GIVES THE PROBABILITY OF BEING ON THE CRITICAL PATH

No. of simulation(s)

Page 55: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

SOFTWARE REQUIREMENT

-BEING A SPECIALISED MANAGEMENT ACTIVITY, REQUIRE SPECIAL SOFTWARE

-NUMBER OF COMMERCIALYY SOFTWARE PACKAGES AVAILABLE

-SELECTION SHOULD BE NEED BASED

--KEEPING INTO MIND NOT ONLY PRESENT BUT ALSO

FUTURE REQUIREMENT(S)

-FOR SMALL AND ONE TIME APPLICATION

--DOS BASED PACKAGE IS REQUIRED

-FOR PROJECT BEING IMPLEMENTED AT MULTIPLE LOCATIONS AND BEING MONITORED BY MANY PEOPLE AT DIFFERENT LEVEL (SAME LOCATION)

--WINDOWS-95/NT- CLIENT SERVER TECHNOLOGY

--UNIX/ XENIX / ODT BASED PACKAGE IS REQUIRED

Page 56: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

“NEED BASED PROJECT MANAGEMENT SOFTWARE SELECTION”

INTEGRATED OBJECTIVES

NOT ONLY PRESENT NEEDS BUT FUTURE ALSO

VERY IMPORTANT ASPECT OF PROJECT MANAGEMENT

Page 57: ROLE OF COMPUTER COMMUNICATION NETWORK IN PROJECT MANAGEMENT

SOFTWARE DEVELOPMENT TOOLS

LOW MEDIUM HIGH

HPM PROMAN PRIMAVERA

INSTAPLAN AUTOPLAN QUICKNET

SUCESSPLAN MS PROJECT TIMELINE

SUPER PROJECT CRITICA

PROMIS

GUIDELINE

COMPUTER MODEL: NEED BASED S/W SELECTION

- OR TECHNIQUE - MIQGP