role of account management at ercot ercot – tx set 814_20 discussions 10/25/06
TRANSCRIPT
Role of Account Management at ERCOT
ERCOT – TX SET 814_20 Discussions
10/25/06
2
TX SET 814_20 Discussions
ERCOT and MPs identified known and potential large volumes of 814_20 and other
types transactions.– Recap of Known Types of Large Transaction Volumes
814_20s - Bulk Retires, Meter Changes, Annual Validation, Cycle changes, Address Clean-ups
– Recap of Potential Types of Large Transaction Volumes 814_20s - Profile changes, Rate Changes, Advance Metering Rulemaking, Potential of Nodal, Weather Related
Other Transactions - Opt Ins to the market, TDSP territory changes, Potential Mergers.
– TX SET determined that we needed to look at near-term options and they would continue to investigate long-term options for future TX SET releases (may include elimination of response transactions not needed in market)
– ERCOT and MPs identified options for improvements to 814_20 processing– ERCOT and MPs were to identify High, Medium and Low from an effort
perspective. Costs will not be provided by ERCOT at this time.– ERCOT’s replacement of SeeBeyond with TIBCO (RBP project) may increase
processing capabilities - ** Load/performance testing has not started (est. start early Nov 06)
3
Transaction volumes
Volume vs Capacity - Normal Volumes
0
20,000
40,000
60,000
80,000
100,000
120,0006
/4
6/5
6/6
6/7
6/8
6/9
6/1
0
7/3
0
7/3
1
8/1
8/2
8/3
8/4
8/5
Su M Tu W Th F Sa Su M Tu W Th F Sa
Date
Vo
lum
e All 814s Inbound Only
814s w/o 814_ 20s/814_21s
Capacity
4
Transaction volumes
Clarify this slideInbounds only
Volume vs Capacity - Annual Validation
0
50,000
100,000
150,000
200,000
250,0009
/3
9/4
9/5
9/6
9/7
9/8
9/9
9/1
0
9/1
1
9/1
2
9/1
3
9/1
4
9/1
5
9/1
6
Su M Tu W Th F Sa Su M Tu W Th F Sa
Date
Vo
lum
e All 814s Inbound Only
814s w/o 814_ 20s/814_21s
Capacity
5
High volume options
Option ERCOT
Effort
TDSP
Effort
Notes / Recommendations
A. Manage
transactions, MPs
bundle or break
apart into the 50K
volumes.
Rank - 5
Low 2-High,
1-Low
Note from 1 TDSP – low is relative to
814_20s only, if other transactions – it
would change to High
*risk to CRs (ERCOT processes adds
separate from maintains/retires – if a
retire was received by ERCOT in front
of maintains – it could cause a delay
CRs receiving maintains later after the
processing of retires)
B. ERCOT create a
parking lot for
large
volumes/throttle.
Rank - 4
Med N/A Med effort from ERCOT to automate
throttling capabilities based upon type
(add, maintain, retire)
•Risk – if backlog could cause lower
priority transactions to be delayed for
extended period of time.
6
High volume options
Option ERCOT
Effort
TDSP
Effort
Notes / Recommendations
C. Add CR DUNS to the
814_20 to allow for
immediate forwarding
(like the 867_03)
Rank - 5
High Low High effort from ERCOT to change
the validation process.
•New 814_20 segments (adding the
CR to receive the information) for a
future TX SET release (long term
solution). Change the flow of
814_21s to go back to TDSP when
received from CR.
•Risk – multiple rejects (from both
CR and ERCOT for any validation
done after the forwarding)
•Risk – out of synch conditions if
CR accepts change and ERCOT
rejects.
7
High volume options
Option ERCOT
Effort
TDSP
Effort
Notes / Recommendation
D. TDSP to automate
systems to break
814_20s outbound
files into 50K
bundles
Rank - 5
Low 2-High,
1-Low
*risk to CRs of putting maintains
after retires, risk to CRs to receive
large volumes – note from 1 TDSP –
low is relative to 814_20s only, if
other transactions – it would change
to High
*risk of still needing coordination
with ERCOT limit of 1 50K file per
day
8
High volume options
Option ERCOT
Effort
TDSP
Effort
Notes / Recommendation
E. The prioritization of
814_20s from #2
plus building a
separate pipe for
814_20 flow
Rank - 1
Med N/A •With RBP, effort went from High to
Med to split 814_20s into own pipe
(addition could prioritize based upon
type – add, maintain (can we break out
further by type?) and retire)
•Risk – backlog could cause lower
priority transactions to be delayed for
extended period of time.
•Pipe would need to be large enough
to not cause backlog.
•Could impact CRs with the greater
volumes.
9
High volume options
Option ERCOT
Effort
TDSP
Effort
Notes / Recommendation
F. ERCOT to increase
capacity of current
processing
architecture for 814s
Rank - 2
High N/A High effort due to architecture
change.
Could impact CRs with the greater
volumes.
* ERCOT To Do – get clarification
about the 2 pipelines vs. 1
pipeline to distinguish option #6
from option #5
10
High volume options
Option ERCOT
Effort
TDSP
Effort
Notes / Recommendation
G. High Volume
Transaction Lane
Rank - 3
High N/A * ERCOT To Do – get Clarification
– if create a 2nd pipe for 814_20s
could it be reused for other
transaction types.
H. Processing of a .csv
file instead of TX SET
transactions
Rank - 5
High Low High effort due to program
systems to receive .csv files
11
Bring back to 10/25 TX SET meeting
ERCOT to get additional information from development teams to the clarifying questions. Will bring back to 10/25 meeting.
– ERCOT To Do – get clarification about the 2 pipelines vs. 1 pipeline to distinguish option #6 from option #5
• Building a separate processing pipe for 814_20s is med effort as it’s a deployment configuration change within the architecture.
• Increasing current capacity to 200K or 300K is high effort as we don’t have the metrics from the TIBCO deployment (scheduled for Dec 2006). May require significant changes to scale the applications within the Retail Transaction Processing arena (PF, TIBCO, Siebel) to meet those levels.
– ERCOT To Do – get clarification – if create a 2nd pipe for 814_20s could it be reused for other transaction types.
• It would take some configuration changes to use for other transaction types. If you used it for other transaction types, the priority 814_20s would be competing with other priority transactions
– ERCOT To Do – get clarification – could an 814_03 get stuck behind an 814_20?• Within SeeBeyond, there are separate processes (1 for initiating and 1 for 814_20s) that
flow into the same inbound, depending on when transactions are received, the 814_03s could be behind 814_20s. This will continue with TIBCO. The additional SIR in Feb will split them out. Once files are packaged for outbound, the outbound processing runs every 5-10 minutes/ system configured by transaction type and quantity, once they are past SeeBeyond, there is minimal chance for 814_03s to get behind 814_20s
12
Bring back to 10/25 TX SET meeting
ERCOT to come to next TX SET meeting with more details around the recommendations selected. Will bring back to 10/25 meeting.
– ERCOT reviewed the recommendations ranked by TX SET (of Low or Med effort by ERCOT) to evaluate what could be implemented near-term in the Feb 2007 release. Here is what is recommended:
Automate the 814_20s throttling capabilities within current processing pipe (all 814s)
a. Automation to allow for system to adjust automatically when other 814s are lower (after hours and weekends)
b. Still handling daily volumes of up to 100K andc. Prioritization of the 814_20s through the pipe by 1st Adds, 2nd
Maintains, 3rd Retires
Building a separate processing pipe for 814_20/814_21 processinga. To handle daily volumes of up to 100K and b. Prioritize the 814_20s through the pipe by 1st Adds, 2nd Maintains,
3rd Retires
13
What’s next for TX SET?
Reminder - 814_20 processing - Until near-term recommendations are implemented – ERCOT encourages TDSPs to continue to communicate to ERCOT any large volumes of 814_20s to be managed through current market processes (bundles and manual intervention by ERCOT and TDSPs).
• Long Term analysis continues at TX SET