robert maxwell (2001)
DESCRIPTION
robert maxwell case studyTRANSCRIPT
A hydrochemical study of the
Glenridding Beck catchment in order to
address chemical fluxes entering the
system as a result of past mining activity.
John Robert Maxwell
This thesis is submitted in part fulfilment
of the requirements for the BSc degree in
Environmental Management at the
University of Lancaster.
December, 2000
John Robert Maxwell
Abstract
Extensive lead mining has taken place at Greenside Mine for over 200 years
until its closure in 1962. The mine is located in the centre of the Glenridding
Beck catchment, which is situated in centre of the Lake District National Park
at the southern end of Lake Ullswater in to which the catchment drains. As a
result of mining activities extensive heavy metal pollution has occurred in the
surface waters in the catchment and subsequently Lake Ullswater from which
water is abstracted for water supply. The hydrology of the catchment was
investigated using the methods of dilution and volumetric gauging, monitoring
the effects of rainfall and a flood frequency analysis. In conjunction with the
discharge measurements lead and zinc concentrations were obtained in order to
predict metal fluxes and subsequently outline the main sources of pollution
within the catchment. Discharges and metal concentrations were obtained on
three occasions in order to assess change with changing catchment conditions.
Results indicate that Swart Beck, a tributary of Glenridding Beck, is the main
source of pollution with subsequent inputs also entering the system from the
disused mine and tailings drainage. Results also indicate that during periods of
high discharges, pH is reduced and subsequently lead is mobilised from
sediments leading to elevated concentrations and thus larger metal fluxes.
Combination of discharge and metal concentrations suggested annual inputs of
141.1kg Pb/yr and 271.9kg Zn/yr in to Lake Ullswater. Although metal
concentrations are not excessive potentially high mass have been occurring for
over 200 years. Climate and landuse change could have significant impacts on
lead mobilisation in the future.
John Robert Maxwell
Contents
1. Introduction 1
1.1 Location 1
1.2 Geology 2
1.3 Background 4
1.4 Catchment Overview 8
1.5 Aims & Objectives 10
1.6 Organisation 11
2. Experimental Methods 12
2.1 Introduction 12
2.2 Sites Investigated 12
2.3 Hydrological Measurements 21
2.4 Water Sampling & Analysis 25
2.5 Rainfall Event Monitoring 28
2.6 Other Data Sources 31
3. Results 33
3.1 Experimental Results 33
3.2 Hydrochemical Change 33
3.3 Rainfall Event Monitoring 37
3.4 Experimental Errors 44
3.5 Analytical Results 46
4. Flood Frequency Analysis 49
4.1 Introduction 49
4.2 Method 49
4.3 Results 50
4.4 Summary 52
John Robert Maxwell
5. Discussion 54
5.1 Introduction 54
5.2 Hydrochemical Change 54
5.3 Water Quality 68
6. Summary and Conclusions 71
References 73
Acknowledgements 75
Appendix A – Procedures 76
Appendix B – Water Analysis 80
Appendix C – pH and Electrical Conductivity Readings 92
Appendix D – Rainfall Event Monitoring Readings 94
Appendix E – Environment Agency Data 98
Appendix F – Rainfall Readings 103
List of Figures
1.1 The location of the Glenridding Beck Catchment. 1
1.2 Map of the Glenridding Beck Catchment. 3
1.3 Spoil on the site of the High Mill. 5
1.4 The resultant tailings dams and the Low Mill site. 6
1.5 Concerned mining features in the catchment. 7
1.6 Downstream Glenridding Beck. 8
1.7 Upstream Glenridding Beck. 9
1.8 Swart Beck. 9
2.1 Schematic map of the sampling points investigated. 13
2.2 Site 1. 14
2.3 Site 2. 14
2.4 Site 3. 15
2.5 Site 4. 16
2.6 Site 5. 17
2.7 Site 6. 17
2.8 Site 7. 18
John Robert Maxwell
2.9 Site 8. 18
2.10 Site 9. 19
2.11 Site 10. 19
2.12 Site 11. 20
2.13 Site 12. 20
2.14 Gulp injection of the dye Rhodamine WT. 22
2.15 The dilution gauging procedure. 23
2.16 The fluorometer logging Rhodamine concentrations. 24
2.17 Volumetric Gauging. 25
2.18 The components of the Flame AAS. 27
2.19 Typical components & output signal of the Graphite Flame AAS. 27
2.20 Schematic diagram showing the basis of the dilution model. 30
3.1 Lead concentrations obtained by the Environment Agency. 38
3.2 Zinc concentrations obtained by the Environment Agency. 39
3.3 Graph showing daily rainfall. 40
3.4 Rainfall Event Monitoring results obtained between 1/7/00-10/7/00. 41
3.5 Rainfall Event Monitoring results obtained between 1/8/00-11/8/00. 42
3.6 Rainfall Event Monitoring results obtained between 1/9/00 –9/9/00. 43
3.7 Q6/Q7 Flow ratios between 8/8/00-11/8/00. 47
3.8 Q6/Q7 Flow ratios between 5/9/00-8/9/00. 47
4.1 Estimated Flood Frequency Curve for Glenridding Beck. 51
4.2 Estimated Flood Frequency Curve for Swart Beck. 52
5.1 Lead concentrations over the sampling period. 60
5.2 Zinc concentrations over the sampling period. 60
5.3 pH readings over the sampling period. 62
5.4 Solution concentrations of lead as a function of pH. 63
5.5 Lead and zinc concentration in bed sediments. 65
5.6 Western tailings failure. 68
John Robert Maxwell
List of Tables
3.1 Discharges obtained on 20/03/00. 33
3.2 Discharges obtained on 23/05/00. 34
3.3 Discharges obtained on 13/06/00. 34
3.4 Sampling Results. 35
3.5 Sampling Results. 36
3.6 Qt/Qb dilution factors. 48
4.1 Catchment characteristics for the two catchment. 50
4.2 Regional growth factors for the North West region. 50
4.3 Flood Studies Report Estimates. 51
5.1 Flow proportions over the sampling period. 55
5.2 Lead and zinc chemical fluxes. 58
5.3 Metal concentrations in soil and tailings material. 66
5.4 Drinking water standards. 69
1 John Robert Maxwell
1. Introduction
Extensive lead mining has taken place in the centre of the Glenridding
Beck catchment for over 200 years. During this time and to the present
day the surrounding water courses and subsequently Lake Ullswater
must have been subject to extensive heavy metal pollution.
Water is abstracted from Lake Ullswater by North West Water for the
supply of water to the Manchester area. Ullswater is also important for
a number of other important factors, it is home to the rare Schelly fish
which is protected under the 1981 Wildlife and Countryside Act, the
lake is part of the River Eden SSSI and for recreational purposes. In all
Lake Ullswater is an important water resource.
1.1 Location
Glenridding is a small village situated in the centre of the Lake District
National Park at the southern end of Lake Ullswater. The Glenridding
Beck Catchment drains an area of 8.37km2 including the eastern slopes
of Helvellyn and surrounding high level topography in to Lake
Ullswater. The valley lies adjacent to Glencoynedale to the north and
Grisedale to the south. Fig 1.1 shows the location of the Glenridding
Beck catchment and fig 1.2 shows a map of the catchment area.
The location of
the catchment
Fig 1.1, The location of the Glenridding Beck Catchment.
2 John Robert Maxwell
Situated in the Glenridding Beck catchment is the extensive, but
disused workings of the Greenside Lead Mine. Greenside Mine is
situated approximately 2km west of the village of Glenridding near to
the confluence of Swart Beck with Glenridding Beck, see fig 1.2 for the
catchment area and locations.
1.2 Geology
The bedrock within the Glenridding Beck catchment is made up of
three main rock types, the Borrowdale Volcanics, the Skiddaw Slates
and Granite. It is only the Borrowdale Volcanic that appear on the
surface within the catchment. These were laid down during volcanic
activity on to older sedimentary rock, the Skiddaw Slates. A later
period of geological activity saw the Lake District dome raised by a
large magma chamber, which cooled and crystallised about 390Ma to
form the Granite intrusion. These two volcanic intrusions caused
contact metamorphism on the surrounding country rock to form the
Skiddaw Slates, although both the Skiddaw slates and the Granite are
still deeply buried under the surface within the catchment.
The Caledonian Orgeny and the Hercynian Orgeny, (mountain building
events) caused folding, fracturing and faulting of the rock. These faults
and fractures allowed water to percolate through and if conditions were
right as they must have been at Greenside a variety of minerals were
deposited to form mineral veins. The veins deposited at Greenside were
of considerable value and size and subsequently the mine exists.
Within the valley are extensive areas of superficial deposits. Glacial,
fluvioglacial and fluvial deposits all feature in the valley. Man has also
significantly altered the geomorphology of the catchment; extensive
spoil heaps have been developed as a result of mining activity.
Fig 1.2, Map of the Glenridding Beck Catchment, the catchment boundary is shown by the line. “Reproduced from Ordnance Survey maps by permission of OrdnanceSurvey on behalf of The Controller of Her Majesty’s Stationery Office, Crown Copyright NC/00/1265”
34 35 36 37 3938
15
16
17
18
North1:25000
4 John Robert Maxwell
1.3 Background
Information contained within the background was obtained from
Adams (1988), Murphy (1996) and Tyler (1998).
1.3.1 Mining History
Both Shaw (1970) in Murphy (1996) and Tyler (1998) suggest that lead
mining is thought to have begun in approximately 1690 but
Postlethwaite (1913) suggests the later stages of the eighteenth century
(Murphy 1996). Earliest Mining began in the upper reaches of the
Swart Beck catchment on the Greenside Fell from where its name was
derived. As mining progressed workings moved gradually down the
valley, the main mine entrance was the Lucy Tongue Level located near
to the confluence of Swart Beck with Glenridding Beck at NGR NY
364175 (see fig 1.2). Tyler (pers com, 11/05/00) noted that the mine
was a prolific producer of lead for over two centuries due to the extent
of rich ore veins at Greenside. The mine finally closed in 1962. The
lower part of the Greenside area is now owned and managed by the
Lake District National Park (LDNP) and the upper part of the site is
jointly owned by the Lake District National Park and the National
Trust. After the site was acquired by the LDNP the site was extensively
landscaped, many buildings knocked down and dangerous areas fenced.
1.3.2 Mining operations and Spoil disposal
During the mines life, extraction and crushing procedures continued to
be improved. Ore from early operations was crushed and sorted by
hand on picking floors, which can still be identified today in the upper
Swart Beck catchment. Two mills, the High and Low were developed
as mechanical crushing and washing plants, the high mill was
abandoned as mining operations moved down the valley. Prior to 1940
there was no recognition of any settling ponds at Greenside, both Tyler
(pers comm 11/05/00) and Murphy (1996) both indicate that
5 John Robert Maxwell
watercourses ran white due to suspended solids. This was due to waste
being discharged directly in to Swart Beck from the crushing plants. It
was not until 1940 after numerous complaints that waste was contained.
Tailings dams were constructed on either side of Swart Beck. The dams
consisted of embankments to contain waste slimes and sluges, water
was then allowed to drain off leaving the waste behind.
It is therefore inevitable that extensive heavy metal pollution must have
occurred within the surface water streams below the mine prior to 1940
and to a less extent after this date. It is the tailings dams that are
thought to be the greatest threat water quality today due to their high
heavy metal content and recent failures. Scott Doherty (1999) and Guy
Weller, (Site Manager LDNP pers comm, 09/06/00) suggest a capping
scheme using a geosynthetic clay liner on both of the resultant tailings
dams to prevent water entering the tailings material. Fig 1.3 shows the
spoil, still devoid of any vegetation on the site of the high mill and the
large collapses in the background. Fig 1.4 shows the resultant tailings
dams on either side of Swart Beck.
Fig 1.3, Spoil on the site of the High Mill and the large collapses in the
background. Photo taken at NGR NY 359178 looking North. The
location can be seen on figs 1.2 and 1.5.
6 John Robert Maxwell
Tailings Dam 2 (West). Swart Beck Tailings Dam 1 (East)
.
LucyTonguelevelentrance
Fig 1.4, The resultant Tailings Dams and the site of the Low Mill. Photo
taken at NGR NY 363172 looking North East. The location can be seen on
figs 1.2 and 1.5.
1.3.3 Water Resources
The mine made extensive use of natural water supplies for its source of
power and for mining operations. Three dams were developed for water
supply; the first was the Top Dam, located in the valley floor of the
upper Swart Beck catchment it supplied the High Mill, the LHLM and
the LTLM. The second was an extensive system of Leats and the third
was the damming of Red Tarn, which supplemented the large reservoir
at Kepple Cove to provide hydroelectric power for the mine and the
village. Greenside mine had a poor record with its dams. In 1877 it is
though that the Top dam was breached, in 1927 the Kepple Cove dam
was breached and again, after repairs, in 1931 (Tyler pers comm.
11/05/00). Both Tyler (1998) and Murphy (1996) indicate the extensive
damage caused by these dam failures to the mine and the village, they
must have also had a large impact on pollution in the catchment. The
remains of the top dam, the Kepple Cove dam and the leat systems can
still be seen today. Leats were man made channels used to carry water
to a desired location. The schematic map shown in fig 1.5 outlines the
catchment and the location of mining features discussed.
The site of theLow Mill
7 John Robert Maxwell
Gle
nrid
ding
Bec
k
Sw
art B
eck
Re d
T
arn
Lak
e U
llsw
ater
Red
Tar
n B
eck
Gle
nrid
ding
Bec
k
Cat
chm
ent b
ound
ary
Top
Dam
(di
suse
d)
Kep
ple
Cov
eD
am (
disu
sed)
Red
Ta r
nD
am (
disu
sed)
Hig
h M
ill
Tai
lings
Dam
s
Nor
th
Col
laps
es
Fig
1.5,
Map
of c
once
rned
feat
ures
in th
e ca
tchm
ent.
Scal
e 1:
2 500
0
Hig
h H
ors
e L
evel
Min
e
Lo
w H
ors
e L
evel
Min
e
Lu
cy T
on
gu
eL
evel
Min
e
8 John Robert Maxwell
1.4 Catchment Overview
Glenridding Beck lies in the floor of a large glaciated valley with steep,
rocky valley sides. Glenridding Beck rises from Lake Ullswater
through the village of Glenridding and rises steeply up to Brown and
Kepple Cove. Glenridding Beck has two main tributaries, the Red Tarn
Beck and Swart Beck (in which the mine Greenside is situated), and
many more perennial streams. The Glenridding and Red Tarn Beck
drain the eastern slopes of Helvellyn. Glacial deposits have led to the
development of marshy areas in flat upper valley areas, Red Tarn is a
glacial tarn and the areas of Kepple Cove and the upper Swart Beck
area both feature marshy areas which were used as dam sites during
mining times.
Glenridding Beck and Swart Beck are typical high energy mountain
streams with a wide range of discharges. Their beds are generally rough
and boulder strewn over their entire course, Glenridding Beck has an
average slope of 0.12m/km and Swart Beck 0.11m/km. Figs 1.5 – 1.7
give an indication of the stream types and their characteristics.
Eastern Tailings dam Glenridding Beck
Swart Beck Western Tailings dam
Fig 1.6, Downstream Glenridding Beck. Photo taken at NGR NY
362176 looking South East
9 John Robert Maxwell
Red Tarn Beck Glenridding Beck
Western Tailings dam
Fig 1.7, Upstream Glenridding Beck, also showing the confluence with
Red Tarn Beck. Photo taken at NGR NY 364174 (Top of Western
Tailings dam) looking South West.
Western Tailings dam
Swart Beck
Eastern Tailings dam
Lucy Tongue Level
entrance
Fig 1.8, Swart Beck, the confluence with Glenridding Beck is in the
extreme bottom right. Photo taken at NGR NY 366176 looking North
West.
Locations for figs 1.6-1.8 can be identified on fig 1.2 and 1.5.
10 John Robert Maxwell
The catchment is consisted of relatively impermeable rocks with thin
soil cover and unimproved grassland. This tends to indicate high runoff
rates, little infiltration to groundwater and low evapotranspiration rates.
The climate in the catchment is harsh; the annual rainfall is
approximately 2500mm and during the winter month’s high ground is
often frozen.
In 1992 a hydroelectric scheme was developed to provide electricity for
the village at Glenridding. A weir was constructed at NGR NY 363173
in order for water to be abstracted, water is transferred by pipeline to
the power station situated at NGR NY 378169 where the water is
returned after use to Glenridding Beck. The scheme is only permitted to
operate when the discharge at the weir is greater that 60l/s.
1.5 Aims and Objectives
The purpose of this study is to assess the hydrology of the catchment in
order to assess the relative contribution of polluted inputs in to Swart
Beck and Glenridding Beck and metal fluxes entering Lake Ullswater.
This will be done using the following aims:
• To measure the discharge of watercourses in the catchment under
different climatic conditions.
• To take and analyse surface water samples at the discharge
measurement points and selected others for lead and zinc
concentrations.
• To assess the catchment response to rainfall events.
These aims should allow the main sources of surface water pollution to
be identified, their relative inputs in to Swart Beck and Glenridding
Beck, any changes in water chemistry moving downstream, and most
11 John Robert Maxwell
importantly the effect of heavy metal pollution on Lake Ullswater. In
order to achieve these aims water sampling and discharge
measurements are to be undertaken on three separate occasions in an
attempt to obtain results under different climatic and catchment
conditions.
A number of other studies have been carried out concerning
environment implications of Greenside mine in which their results will
aid those of this study, these are as follows:
• The Environment Agency produced a report for the LDNP on the
impact of discharges from Greenside Mine and spoil heaps into
surrounding watercourses and Lake Ullswater. This report presents
heavy metal concentrations in surface waters in the Glenridding
Beck catchment.
• Scott Doherty Associates produced a report for the LDNP titled
Greenside Mine, Glenridding Geo-environmental and Structural
assessment. This report covers a wide range of heavy metal
concentrations in the Greenside area.
• A BSc dissertation project produced by Kember (2000) investigated
heavy metal concentrations contained within sediments in Swart
Beck, Glenridding Beck and Lake Ullswater.
1.6 Organisation
This report will begin the methods employed in order to identify study
sites and the detailed investigation carried out at each of these sites.
Following sections will outline the results obtained, analytical methods
and a discussion section presenting an interpretation of the results and
findings. Conclusions will be drawn relating to relative heavy metal
pollution in the catchment in the final section.
12 John Robert Maxwell
2. Experimental Methods
2.1 Introduction
The experimental methods used within this study are explained and
discussed in this chapter. The first section identifies the sampling sites
used and their selection criteria, following sections outline methods
used for investigation.
2.2 Sites investigated
The following section gives an account of the sampling sites
investigated. Fig 2.1 shows a schematic map of the sampling locations
used for investigation, following this each site is characterised and its
selection criterior is outlined. A figure is presented with each site
description, these also indicate more specifically some of the catchment
characteristics discussed in section 1.4. Sites 1-12 were sampled on
three occasions and sites 13-16 were only sampled on one occasion in
an attempt to investigate the upper Swart Beck catchment; a general
site description and their selection criterior are outlined. Grid reference
locations can be identified on fig 1.2.
Site 1, is located on Glenridding Beck, above the footbridge and the
hydro dam and upstream of any mining activity at NGR NY362173.
This site was selected for background concentrations as no significant
mining activity has been conducted above this point. Fig 2.2 shows site
1.
13 John Robert Maxwell
12
3
45
67
89
1011
12
1314
1516
Gle
nrid
ding
Bec
kL
ake
Ulls
wat
er
Swart Beck
12
4
5
67
8
Wes
tern
Tai
lings
dam
Eas
tern
Tai
lings
dam
Swar
t Bec
k
Gle
nrid
ding
Bec
k
Hy
dro
Dam
Fo
otB
rid
ge
Fig
2.1,
Sch
emat
ic m
aps
of th
e sa
mpl
ing
poin
ts in
vest
igat
ed.
Nor
th
010
0m
0
100m
200
m
14 John Robert Maxwell
Fig 2.2, Site 1, upstream Glenridding Beck. Photo looking upstream.
Site 2, located at NGR NY 365173 and is situated on Glenridding Beck
immediately above the confluence with Swart Beck. This site was used
to assess the change in the water chemistry of Glenridding Beck as it
passes the western tailings dam and to indicate the impact of the input
of Swart Beck on Glenridding Beck. This site also provides data for
chemical balances. Fig 2.3 shows site 2.
Fig 2.3, Site 2, Glenridding Beck upstream of confluence with Swart
Beck. Photo looking upstream.
15 John Robert Maxwell
Site 3 is located immediately below the Low Horse Level entrance on
Swart Beck at NGR NY 363178. This site was selected to provide metal
concentrations from the upper Swart Beck catchment, the site is also
situated above the tailings dams, this will allow their inputs into Swart
beck to be assessed. Fig 2.4 shows site 3
Fig 2.4, Site, Swart Beck downstream of Low Horse Level. Photo
looking upstream.
Site 4 is the discharge from the Lucy Tongue Level mine situated at
NGR NY 364175. This site was selected to assess the input of metals
from drainage of the mine. The discharge can also be easily obtained
here. Fig 2.5 shows site 4.
16 John Robert Maxwell
Fig 2.5, Site 4, mine drainage from the Lucy Tongue Level. Photo
taken looking West, the foot of the western tailings dam is situated
behind the wall in the distance.
Site 5 is located at NGR NY 365175 and is situated on Swart Beck
immediately before the confluence with Glenridding Beck. This site
was selected to assess the change in the metal concentrations from site
3 as Swart beck passes the tailings dams and the mine drainage, site 4.
This site will provide the total metal inputs of Swart beck in to
Glenridding Beck. This site was also selected due to its suitability for
discharge measurement. Fig 2.6 shows site 5.
Site 6 is located at NGR NY 355174 on Glenridding Beck
approximately 40-50 meters downstream of the confluence with Swart
Beck to allow sufficient mixing before sampling. This site was selected
in order to assess the influence of Swart Beck on Glenridding Beck and
thus the dilution effect of the input. Fig 2.7 shows site 6.
17 John Robert Maxwell
Fig 2.6, site 5, Swart Beck before the confluence with Glenridding
Beck. Photo looking upstream, the confluence is immediately below the
photo.
Fig 2.7, Site 6, Glenridding Beck, downstream of confluence with
Swart Beck. Photo looking upstream, the western tailings dam is
behind the building in the top of the photo.
Site 7 is located at NGR NY 367175 on the eastern tailings dam drain
before it enters Glenridding Beck. This site was selected to address the
effect of the tailings material on surface water, discharge measurements
can also be conducted at this site. Fig 2.8 shows site 7.
18 John Robert Maxwell
Fig 2.8, Site 7, eastern tailings dam drain. Photo looking North, the
eastern tailings dam is above the trees in the background.
Site 8 is located at NGR NY 368174 on Glenridding Beck
approximately 40-50 meters downstream of the confluence with the
eastern tailings dam drain. This site was used to assess the impact of
the eastern tailings dam drain on Glenridding Beck and thus the
dilution affect. Fig 2.9 shows the site.
Fig 2.9, Site 8, Glenridding Beck, downstream of eastern tailings dam
drain. Photo looking upstream.
19 John Robert Maxwell
Site 9 is situated at NGR NY 374172 on Glenridding Beck
approximately 50 meters upstream of the footbridge. This site was
selected to monitor any change in water characteristics as Glenridding
Beck moves away from the mine. Fig 2.10 shows the site.
Fig 2.10, Site 9, Glenridding Beck above footbridge. Photo looking
upstream.
Site 10 is situated at NGR NY 379169 on Glenridding Beck at the
western end of Gillside Farm Caravan site. Again this site was
selected to monitor any change occurring in the water characteristics.
Fig 2.11 shows site 10.
Fig 2.11, Site 10, Glenridding Beck at Gillside Caravan Site. Photo
looking upstream.
20 John Robert Maxwell
Site 11 is located at NGR NY 391172 on Glenridding Beck
immediately prior to the confluence with Lake Ullswater. This site aims
to address the metal concentrations entering Lake Ullswater from
Glenridding Beck. Fig 2.12 shows the site.
Fig 2.12, Site 11, Glenridding Beck before the confluence with Lake
Ullswater. Photo looking upstream, the confluence is just to the right of
the photo.
Site 12 is Lake Ullswater located at NGR NY 392172 approximately
50-60 meters south on the shore line of the confluence of Glenridding
Beck with Lake Ullswater. This site was used to assess the impact of
Glenridding Beck and thus Greenside mine on the water quality in Lake
Ullswater. Fig 2.13 shows the site.
Fig 2.13, Lake Ullswater. Photo looking South West, the confluence of
Glenridding Beck is to the left of the photo.
21 John Robert Maxwell
Site 13 is situated at NGR NY 362179 on Swart Beck, upstream of the
Low Horse Level entrance. This site was selected to assess the input
from the Low Horse Level entrance and inputs form further upstream.
Site 14 is situated on Swart Beck immediately below the site of the
High Mill, (shown on fig 1.3) located at NGR NY 362178. This site
was used to assess the inputs from the spoil left on the site of the High
Mill.
Site 15 is located at NGR NY 362179 on Swart Beck above the site of
the High Mill, this site in conjunction with site 14 will determine the
influence of the spoil on metal concentrations in Swart Beck.
Site 16 is situated on Swart Beck above the top dam and consequently
above most mining activity at NGR NY 361179. This site will act as a
background levels for Swart Beck.
Water sampling and discharge measurements were undertaken on
20/03/00, 23/5/00 and 13/06/00 in an attempt to obtain results under
different catchment conditions. A more specific sampling program took
place on 11/05/00 concentrating on the Swart Beck catchment no
discharge measurements were obtained on this day.
2.3 Hydrological Measurements
In order to assess the hydrology of the catchment the methods of
dilution gauging and volumetric gauging were used measure discharge
at given points. A flood frequency analysis and monitoring the effects
of rainfall were also undertaken to further understand the hydrology in
the catchment.
22 John Robert Maxwell
2.3.1 Dilution Gauging
Dilution gauging is an alternative method to velocity area
measurements; it is more appropriate in high turbulence, high velocity
and in rocky or boulder strewn streams such as Swart and Glenridding
Beck’s as no cross sectional area is required but good mixing properties
are. It was therefore most appropriate to use this method.
Dilution gauging is based on the dilution of a known volume and
concentration of a tracer when applied to the flow. The method can be
carried out using a constant rate method or a gulp method; in this case
the latter was used which is an instantaneous injection. The dye
Rhodamine WT was used as a tracer in this case. The concentration of
Rhodamine WT can be determined using a fluorometer located 30-50
meters downstream of the injection point depending upon the mixing
properties of the stream. The 10AU fluorometer manufactured by
Turner Designs was used. The fluorometer was set to log
concentrations every 2 seconds. A known mass M of the dye
Rhodamine WT (around 100mg mixed with stream water) was injected
approximately 30-40 meters upstream of the fluorometer, see fig 2.14
for the Rhodamine WT gulp injection.
Fig 2.14, The gulp injection of the dye Rhodamine WT. Photo taken
approximately 40 meters upstream of site 1.
23 John Robert Maxwell
Background concentration Cb (ML-3) was previously logged for five
minutes by the fluorometer as is the tracer concentration Ct (ML-3) until
the levels return to those of background, which depending on the
discharge was approximately 30-40 minutes. See fig 2.15 (below) for
the equipment set-up and fig 2.16 for the fluorometer logging
Rhodamine concentrations.
The discharge is then calculated from:
∫ −=
)dtC(C
MQ(l/s)
bt
Where the term ∫ − dtCC bt )( is the area under the graph and is
estimated using the trapezium rule:
++×= ∑
−
= 2
CC
2
CtArea
N1N
2i
i1
Where the time axis is split in to N-1 intervals of time t and Ci is the
concentration (Ct-Cb) at time ti.
Dilution gauging was carried out at sites 1, 5, 6 and 9, during the three
sampling days. At each site two cycles were completed.
Fig 2.15, The dilution gauging procedure for the gulp injection. Source:
Gregory & Walling (1973).
24 John Robert Maxwell
Fig 2.16, The fluorometer logging Rhodamine concentrations on
Glenridding Beck. Photo taken at site 6.
Rhodamine is a toxic chemical and injecting this chemical in to natural
water courses can have negative consequences, but due to the
concentrations used (approx. 100mg) its effect will be minimal.
Considering this, approval had to be gained from the Environment
Agency in order to conduct dilution gauging; this was done through the
regional office at Ghyll Mount, Penrith, who approved the request.
Handling of the Rhodamine had to be done wearing suitable protective
clothing, gloves and safety glasses. A Control Of Substances
Hazardous to Health (COSHH) Regulations 1994 was also carried in
conjunction with the Rhodamine WT. The procedure for this can be
seen in appendix A.
2.3.2 Volumetric Gauging
Volumetric gauging is a direct measurement of discharge suitable for
estimating sites with a low discharge. Using a suitable container and a
stop watch a set volume of water is collected and the time taken is
recorded, the discharge is then simply:
Discharge (l/s)=(seconds) Time
(litres) Volume
25 John Robert Maxwell
Volumetric gauging was used at sites 7, and 4 on the three sampling
days. At both sites three discharges were obtained and the average
taken. fig 2.17 shows volumetric gauging in processes at site 4.
Fig 2.17, Volumetric Gauging at site 4.
2.3.3 Rainfall measurement
Daily rainfall measurements are available from my own personal
records. Rainfall is recorded at 8am for the previous 24 hours in a daily
storage gauge. The raingauge is situated in the catchment near the
village of Glenridding at NGR NY 381172.
2.4 Water sampling and analysis
2.4.1 Water Sampling
Water samples were taken at each of the twelve sites referred to in
section 2.2 on each of the three sampling days. Samples were taken in
60ml acid washed bottles and on return to the lab the sample was made
1% acidic with concentrated nitric acid. This is to preserve the sample
in its original condition i.e. to resist any metals sorbing on to sediments
or the bottle walls. Samples were kept in the fridge prior to analysis.
26 John Robert Maxwell
2.4.2 Water analysis
Water samples taken at each of the twelve sites were analysed for lead
and zinc concentrations. This was done using flame atomic absorption
spectrometry (Flame AAS) to analyse zinc concentrations and graphite
furnace atomic absorption spectrometry (GFAAS) for lead
concentrations. Spectrometry methods of analysis are based on the
interaction of electromagnetic radiation and the atoms and molecules
that make up the sample. The electromagnetic radiation is passed
through the sample and is absorbed by the sample and thus reduced,
therefore the greater the absorption the greater the concentration of the
desired metal.
Absorption is linearly related to concentration, therefore both methods
require the preparation of standard solutions. Diluting with distilled
water a 1000ppm zinc and lead solution in to concentrations covering
the entire range of the samples allows the absorption of set
concentrations to be obtained and thus a linear regression model can be
fitted to calculate the concentrations of the samples from their
absorption values (see appendix A for a full procedure). A set of blank
solution’s (distilled water), 10 for flame AAS and 5 for GFAAS, are
also used to correct the absorbency of the standards.
Flame Atomic Absorption Spectrometry
Flame AAS was used to determine the zinc concentration within the
water samples. Fig 2.18 shows a schematic diagram of the typical flame
AAS. The radiation source is a hollow cathode lamp in which the
cathode is constructed of the same material as the metal being analysed.
The flame evaporates the water leaving the metal containing
compounds, which absorb the radiation, and thus is then detected and
the absorption is recorded.
27 John Robert Maxwell
Fig 2.18, The components of the Flame Atomic Absorption
Spectrometer. Source: Radojevic & Bashkin (1999)
Graphite Furnace Atomic Absorption Spectrometry
Graphite furnace AAS involves electrothermal atomisation inside a
graphite tube instead of a flame atomisation (Radojevic & Bashkin
1999), fig 2.19 shows a schematic diagram of a typical GFAAS. This
technique is much more sensitive than that of flames AAS; detection
limits are in the region of 100 – 1000 times lower with GFAAS
atomisation (Radojevic & Bashkin 1999). The lowest detection for lead
in flame AAS is 1ppm where as most of the samples only contain 0-
100ppb therefore GFAAS was used to obtain lead concentrations. In
operation (10-100µl) is inserted into the furnace via a transverse hole
on to a platform. This ensures uniform, reproducible heating profile for
the sample and improves the precision of the measurements.
Fig 2.19, Typical components and output signal of a graphite furnace
atomic absorption. Source: Manahan, S.E. (1988). Quantatitive
Analyitical Chemistry in Fifield & Haines (2000)
28 John Robert Maxwell
2.4.3 pH & Electrical Conductivity
At each of the 12 sites, as described in section 2.2 pH and electrical
conductivity readings were taken in conjunction with the water
sampling on each of the sampling days. Readings were obtained on site
using hand held meters, which were calibrated before use. The
Radiometer PHM 201 was used for pH measurements, this has a
resolution of ±0.01 and a WPA CMD 200 electrical conductivity meter
was used with a resolution of ±0.1µs/cm. One pH reading and three
electrical conductivity readings were taken at each site.
pH measures the concentration of H+ ions in the water and is used to
express the acidity or alkalinity of the solution. Electrical conductivity
is a measure of the ability of water to convey an electrical current.
Conductivity is an approximate measure of the concentration of
inorganic substances within the water and thus can be substituted as a
measurements of total dissolved solids (TDS).
2.5 Rainfall Event Monitoring
Further assessment of the hydrology within the catchment was sought
by the monitoring of electrical conductivity, before, during and after
rainfall events. Electrical conductivity is a measure of the concentration
of inorganic substances in the water. The use of electrical conductivity
to monitor a rainfall event appeared appropriate as rainfall contains few
inorganic substances so the net effect of rainfall must be to dilute the
water previously in the beck’s. Monitoring was undertaken at sites 2, 5,
6, 7 and 8 (see fig 2.1 for sampling locations), to allow flow ratio and
dilution factors to be calculated, before, during and after rainfall,
rainfall conductivity was also recorded. Electrical conductivity
measurements followed the same procedure as described in section
2.4.3. This method aims to show the response of Glenridding Beck,
Swart Beck and the eastern tailings dam drain to rainfall events under
29 John Robert Maxwell
different antecedent conditions, rainfall patterns and the dilution effect
of rainfall. The mixing equations (below) will allow the calculation of
flow ratios of Glenridding Beck (Q2) to Swart Beck (Q5) and
Glenridding Beck (Q6) to the Tailings dam drain (Q7) during the
monitoring period. The flow ratios can be calculated using the
following equation:
Firstly the discharges must balance so:
Q6 = Q2 + Q5 (1)
The electrical conductivity must also balance so therefore:
(Q6 × EC6) = (Q2 × EC2) + (Q5 × EC5) (2)
Inserting (1) in to (2) gives the following:
(Q2 + Q5) × EC6 = (Q2 × EC2) + (Q5 × EC5) (3)
Then expansion and rearrangement of (3) gives the following:
(Q2 × EC6) – (Q2 × EC2) = (Q5 × EC5) – (Q5 × EC6)
⇒ Q2 (EC6 – EC2) = Q5 (EC5 – EC6)
⇒ Q2/Q5 = )EC-EC(
)EC-(EC
26
65
Following the same procedure as above you also get:
Q6/Q7 = )EC-(EC
)EC-EC(
68
87
30 John Robert Maxwell
Where the subscript numbers refer to the site numbers and EC is
electrical conductivity. The enlarged schematic diagram in fig 2.1
shows the survey area.
In order to quantify the dilution effect of rainfall from the conductivity
results a simplistic model can be used to give a dilution factor. It
assumes that all rainfall runs directly in to the surface water streams
and no infiltration or evaporation occurs. This has serious limitations,
and as Dingham (1994) outlines there are many other factors such as
land use, soil type, underlying geology and the antecedent catchment
conditions that will have an influencing factor on the quantity of event
water making up the total flow. Although this method is limited in its
approach it should indicate the dilution effect of rainfall within the
different inputs in the catchment. Fig 2.20 shows a schematic diagram
of the model.
Fig 2.20, Schematic diagram showing the basis of the dilution model.
From fig 2.20 we can say that:
Qt = Qb+Qr (1)
Qt ECt(Total effect)
Qr ECr(Rainfall input)Qb ECb
(Background)
31 John Robert Maxwell
And QtECt = QbECb + QrECr (2)
Then r
bbttr
EC
)ECQ EC(Q Q
+= (3)
Insert (3) into (1)r
bb
r
ttbt
EC
EC Q
EC
ECQ Q Q −+=
⇒
−=
−
R
bb
r
tt
EC
EC1 Q
EC
EC1Q
⇒
−
−
=
r
t
r
b
b
t
EC
EC1
EC
EC1
Q
Q
⇒
=
r
tr
r
br
b
t
EC
EC - EC
EC
EC -EC
Q
Q
⇒ )EC - (EC
)EC-EC(
Q
Q
tr
br
b
t=
Results will aid the assessment of the hydrology within the catchment
and allow the dilution effect of rainfall under different catchment
conditions and the flow ratios to be assessed.
2.6 Other data sources
A study in to surface water pollution by the Environment Agency was
made available, this report contains extensive heavy metal
concentrations over the period 7th November 1999 to 27th February
2000 at many of the same sites as in this study. A report by Scott
Doherty produced on behalf of The Lake District National Park in 1999
titled Greenside Mine, Glenridding Geo-Environmental and Structural
32 John Robert Maxwell
Assessment contains extensive data on heavy metal concentrations in
the area. Data from a colleague’s dissertation project (Kember 2000)
based on heavy metal concentrations in sediments in Swart and
Glenridding Beck’s is also available, again many of the sites are the
same as this study.
33 John Robert Maxwell
3. Results
3.1 Experimental Results
The experimental results fit in to two distinct sections. The first section
contains results from the assessment of change in discharge and metal
concentrations over the sampling period relative to changing catchment
conditions. The second section contains the results of the rainfall event
monitoring which attempt to assess short-term catchment change
resulting from individual rainfall events.
3.2 Hydrochemical Change
3.2.1 Discharge measurements
The following tables (3.1-3.3) show individual discharge measurements
obtained on each of the sampling days. Each table shows each
individual measurement, the average and the range, the location of the
sites can be seen on fig 2.1.
Table 3.1, Discharges in ltrs/sec obtained on 20/03/00
Site Run 1 (l/s)
Run 2(l/s)
Run 3 (l/s)
Average(l/s)
Range(l/s)
1 73.7 59.2 66.5 14.54 6.21 5.45 6.33 6.0 0.885 38.4 37.4 37.9 17 0.68 0.71 0.75 0.71 0.079 112.8 109.4 111.1 3.4
34 John Robert Maxwell
Table 3.2, Discharges in ltrs/sec obtained on 23/05/00
Site Run 1(l/s)
Run 2(l/s)
Run 3(l/s)
Average(l/s)
Range(l/s)
4 4.78 4.15 4.12 4.4 0.665 45.6 45.7 45.7 0.16 112.8 119.8 116.3 77 1.02 0.97 1.05 1.0 0.089 101.6 107.3 104.5 5.7
Table 3.3, Discharges in ltrs/sec obtained on 13/06/00
Site Run 1 (l/s)
Run 2 (l/s)
Run 3(l/s)
Average(l/s)
Range(l/s)
4 5.65 5.29 6.21 5.72 0.925 121.3 109.1 115.2 12.26 223.3 219.7 221.5 3.67 3.13 3.53 2.78 3.15 0.75
In general the range of values obtained is small compared with the
discharge. Site 1 (table 3.1) and site 5 (table 3.3) have considerably
larger ranges, both of these are dilution gauging estimates and this
could be due to insufficient mixing in the stream on these occasions.
3.2.2 Water Chemistry
In conjunction with the discharge measurements metal concentrations
were obtained at the same locations and the other sites described in
section 2.1, this will allow the assessment of change in discharge and
metal concentrations to be analysed under different catchment
conditions. Table 3.4 combines lead and zinc concentrations,
discharges (full results shown above), pH and electrical conductivity at
each site. This provides a summary of results obtained on each
sampling day. Table 3.5 shows heavy metal concentrations, pH and
electrical conductivity obtained on 11/05/00; no discharges were
measured on this day. The results are averages where more than one
measurement was made on the sample; full data sets for these are
available in the following appendices:
20/03/00 23/05/00 13/06/00
SiteDischarge
l/sPb
(ppb)Zn (ppb)
pH±0.01
ECµS/cm± 0.05
Dischargel/s
Pb(ppb)
Zn (ppb)pH
±0.01
ECµS/cm± 0.1
Dischargel/s
Pb (ppb) Zn (ppb)pH
±0.01
ECµS/cm± 0.1
1U/S G/Beck 66.5 -0.50 -11.77 6.18 38.2 -1.29 -2.25 4.63 32.8 3.20 17.74 6.28 30.4
2G/Beck before
Confluence2.95 3.11 6.9 40.7
70.77.00 17.74 6.3 36.6 106 13.15 25.73 6.46 31.9
3Swart
Beck,LHL71.32 58.55 5.91 44.8 61.95 91.71 4.9 41.4 67.90 71.71 4.72 35.1
4Mine Drainage 6 82.63 368.24 7.31 298.3 4.3 73.87 265.63 7.01 300.3 5.72 28.58 265.63 6.22 296.7
5S/Beck before
confluence37.9 34.43 131.58 6.12 82.3 45.7 62.99 137.69 6.74 71.3 115.2 102.25 121.69 6.08 52.5
6G/Beck afterconfluence
19.18 54.50 6.65 57.6 116.3 30.33 67.72 6.48 51.1 221.5 52.47 77.71 6.76 41.9
7Eastern tailings
dam drainage0.71 32.95 941.63 6.54 135.0 1 536.6 445.56 6.56 115.5 3.15 38.04 309.62 5.7 71.1
8G/Beck below
site 722.13 62.61 6.32 58.0 40.70 85.71 5.59 54.7 59.94 79.71 5.09 43.2
9Footbridge
G/Beck111.1 29.02 62.61 6.34 58.6 104.5 46.92 97.70 5.22 54.2 77.86 67.72 4.7 44.4
10G/Beck,
Caravan site28.52 66.67 6.35 61.0 53.66 77.71 6.46 57.5 59.44 75.71 4.74 48.1
11G/Beck mouth 22.13 65.32 6.04 63.5 6.04 48.8 35.55 55.72 5.35 41.4
12Lake Ullswater 3.93 17.98 6.51 55.8 33.96 39.73 5.63 58.1 75.87 315.61 5.89 60.5
Table 3.4, Sampling Results obtained on each of the sampling days.
36 John Robert Maxwell
• Appendix B – Water Analysis,
• Appendix C – pH & Electrical Conductivity.
Weather conditions were recorded on each of the sampling days,
conditions were as follows:
• 20/03/00 – Mainly cloudy, light winds.
• 11/05/00 – Sunny and warm, light winds.
• 23/05/00 – Light Rain, light winds.
• 13/06/00 – Rain and windy.
Table 3.5, Water sampling results obtained on 11/05/00
Sample SiteLead(ppb)
Zinc(ppb) pH ±0.01
Conductivityµs/cm ±0.1
2G/Beck before confluence
4.77 -3.02 7 44.2
3S/Beck, LHL
55.73 86.79 5 47.6
4Mine Drainage
60.91 298.76 7.8 291.7
5S/Beck before confluence
54.18 147.87 6.9 94.5
6G/Beck after confluence
18.92 92.18 6.4 68.3
13Above LHL Adit
70.76 77.81 6.6 47.0
14Below foot bridge &
Dressing floor80.61 56.26 6.7 43.7
15Below old Dam
27.22 95.78 6.6 44.0
16Above most Mining
activity6.48 2.37 6.6 45.3
3.2.3 Environment Agency Data
As was indicated earlier the Environment Agency conducted a study,
which covers a wide range of heavy metal concentrations in surface
waters at many of the same sites as studied in this report. Data is shown
37 John Robert Maxwell
in appendix F, the numbered sites refer to the same sites in this study
and the lettered refer to the following sites:
A. Glenridding Beck down stream of Swart beck, NGR NY 367173.
B. Water trough on eastern tailings dam drain, NGR NY 366173.
C. Swart Beck upstream of LHL adit, NGR NY 362179.
D. Western Tailings dam drain, NGR NY 363173.
E. Eastern Tailings dam, white stain, NGR NY 364173.
Site C was sampled on the 11/05/00 during this study.
Fig 3.1 and fig 3.2 graphically represent the lead and zinc
concentrations obtained by the Environment Agency. Although all the
data is shown not all points are shown to their full extent, due to
magnitude of these values these points had an influence on the overall
appearance of the graph. Actual values can be seen in Appendix F.
3.2.4 Rainfall Data
Daily rainfall data from my own personal records is available. Data
covering the period of October 1999 to September 2000 is shown in
appendix F. This covers both the Environment Agency’s and this study
period, fig 3.3 shows the rainfall data graphically.
3.3 Rainfall event monitoring
Rainfall event monitoring was undertaken on three occasions,
08/07/00–10/07/00, 08/08/00–10/08/00 and 05/09/00–08/09/00 when
conditions allowed monitoring. Full results for the rainfall event
monitoring are shown in appendix D. Figs 3.4-3.6 show the electrical
conductivity and rainfall results graphically.
0
100
200
300
400
500
600
700
800
1 2 3 4 5 10 12 A B C D E
Site
Lea
d C
on
cen
trat
ion
(p
pb
)
07/09/99 14/09/99 05/12/99 12/12/99 02/01/00 09/01/00 30/01/00 06/02/00 27/02/00
Fig 3.1, Lead concentrations obtained by the Environment Agency
0
100
200
300
400
500
600
1 2 3 4 5 10 12 A B C D E
Site
Zin
c co
nce
ntr
atio
n (
pp
b)
07/09/99 14/09/99 05/12/99 12/12/99 02/01/00 09/01/00 30/01/00 06/02/00 27/02/00
Fig 3.2, Zinc concentrations obtained by the Environment Agency.
0
10
20
30
40
50
60
70
80
90
07/11
/99
21/11
/99
05/12
/99
19/12
/99
02/01
/00
16/01
/00
30/01
/00
13/02
/00
27/02
/00
12/03
/00
26/03
/00
09/04
/00
23/04
/00
07/05
/00
21/05
/00
04/06
/00
18/06
/00
02/07
/00
16/07
/00
30/07
/00
13/08
/00
27/08
/00
10/09
/00
Date
Dai
ly R
ain
fall
(mm
)
Fig 3.3, Graph showing daily rainfall in Glenridding.
41 John Robert Maxwell
Fig 3.4, Rainfall data (top) and electrical conductivity (bottom) for the period
01/07/00 – 10/07/00
0
5
10
15
20
25
01/0
7/00
02/0
7/00
03/0
7/00
04/0
7/00
05/0
7/00
06/0
7/00
07/0
7/00
08/0
7/00
09/0
7/00
10/0
7/00
Date
Rai
nfa
ll (m
m)
0
10
20
30
40
50
60
70
80
90
100
30/06/00
00:00
01/07/00
00:00
02/07/00
00:00
03/07/00
00:00
04/07/00
00:00
05/07/00
00:00
06/07/00
00:00
07/07/00
00:00
08/07/00
00:00
09/07/00
00:00
10/07/00
00:00
11/07/00
00:00
Date and Time
Ele
ctri
cal c
on
du
ctiv
ity
Site 2 Site 5 Site 6 Site 7 Rainfall
42 John Robert Maxwell
Fig 3.5, Rainfall data (top) and electrical conductivity (bottom) for the period
01/08/00 – 11/08/00.
0
246
8
10
121416
18
01/0
8/00
02/0
8/00
03/0
8/00
04/0
8/00
05/0
8/00
06/0
8/00
07/0
8/00
08/0
8/00
09/0
8/00
10/0
8/00
11/0
8/00
Date
Rai
nfa
ll (m
m)
0
20
40
60
80
100
120
140
31/07/00
00:00
01/08/00
00:00
02/08/00
00:00
03/08/00
00:00
04/08/00
00:00
05/08/00
00:00
06/08/00
00:00
07/08/00
00:00
08/08/00
00:00
09/08/00
00:00
10/08/00
00:00
11/08/00
00:00
Date and Time
Ele
ctri
cal c
on
du
ctiv
ity
uS
/cm
Site 2 Site 5 Site 6 Site 7 Site 8 Rainfall
43 John Robert Maxwell
Fig 3.6, Rainfall data (top) and electrical conductivity (bottom) for the period
01/08/00 – 09/09/00.
0
5
10
15
20
25
30
01/0
9/00
02/0
9/00
03/0
9/00
04/0
9/00
05/0
9/00
06/0
9/00
07/0
9/00
08/0
9/00
09/0
9/00
Date, ra infa l l recorded at 08:00
Rai
nfa
ll (m
m)
0
10
20
30
40
50
60
70
80
90
100
31/08/00 00:00
01/09/00 00:00
02/09/00 00:00
03/09/00 00:00
04/09/00 00:00
05/09/00 00:00
06/09/00 00:00
07/09/00 00:00
08/09/00 00:00
09/09/00 00:00
Date and Time
Ele
ctri
cal C
on
du
ctiv
ity
uS
/cm
Site 2 Site 5 Site 6 Site 7 Site 8 Rainfall
44 John Robert Maxwell
3.4 Experimental Errors
3.4.1 Dilution Gauging
Dilution gauging is generally a reliable and accurate method for the
estimation of discharge, especially in high energy, turbulent and
mountainous streams such as Glenridding and Swart Beck’s. Although
generally accurate, errors do occur, firstly the mass of Rhodamine WT
will be subject to error, this will be small, masses were measured to
0.01mg, an error this small will have little impact on the overall
discharge calculations. Secondly some Rhodamine could be lost on
transfer from the pre-weighed storage bottles to the mixing bucket and
on injection to the stream. This would be minimal, the bottle, its top
and protective gloves were thoroughly washed as was the bucket and
any boulders the Rhodamine came in to contact with after injection.
Thirdly, the Rhodamine must be thoroughly mixed before reaching the
fluorometer, injecting to close will result in insufficient mixing and
consequently affect the concentrations logged and the discharge
estimated. In order to avoid this error, sites must be selected carefully,
in order to avoid large pools that will hold the Rhodamine. The
injection location should be located sufficiently upstream of the
Fluorometer to allow full mixing. During the sampling days, discharges
were measured at the downstream sites first to avoid any error from
Rhodamine previously injected moving downstream. Finally logging
longer background concentrations (prior to Rhodamine injection) will
give a more representative average and allowing a longer flushing
period (after injection) may improve the estimation slightly.
45 John Robert Maxwell
3.4.2 Volumetric Gauging
Volumetric gauging can be a crude estimation of discharge. One of the
largest errors in this method will be collection, due to the nature of the
sites not all water would be collected, in order to improve collection
methods, water would need to be deflected in to a more concentrated
area for collection. Volume measurements were measured to the
nearest litre or ±0.5 litres and the time in which it was collected would
also be subject to some error. Lengthening the collection time,
improving the collection method and the accuracy of the volume
measurement would significantly improve the discharge estimation.
3.4.3 Rainfall measurement
Rainfall is measured in a daily storage gauge, which is set above
ground level; this will tend to under estimate the rainfall. Rainfall is
recorded with an accuracy of ±0.25mm. Installing the raingauge at
ground level with an anti splash grid or using a tipping bucket gauge
would significantly increase the accuracy of the measurements.
3.4.4 pH and Electrical conductivity
Calibration of both pH and electrical conductivity meters with standard
solutions before each use will increase the accuracy of the readings.
The resolutions of the readings are as follows, pH ±0.01 and EC ±0.1,
which in the case of this study the error will be small and insignificant.
3.4.5 Water sample analysis
The preparation of the standard solutions is likely to contain the largest
error. Dilution of a standard 1000ppm lead into 10-100ppb and zinc in
46 John Robert Maxwell
to 100-1000ppb could incorporate a number of errors, this was always
done as accurately as possible but errors are inevitable. In general the
regression lines for absorbence and concentration fitted the data well
with r2 values >0.99 which suggests little error in the preparation. The
detection limits of the flame/graphite AAS could also have an impact
on the results, any concentration below the detection limit will be
recorded as a zero absorption and thus a zero concentration. Increasing
the range of standard solutions, blanks and the number of
measurements made on each sample will give increased accuracy.
The water sample itself could introduce error, there is the chance that
some of the metal was lost due to sorption on to either the bottle walls
or any sediment, metals could also be mobilised from any sediment
contained with in the sample. These effects could have an overall
impact on the concentrations obtained although this should be minimal
as acid washed sample bottles were used and each sample was acidified
on return to the lab this will have limited this source of error.
3.5 Analytical Results
3.5.1 Introduction
Analysis of the electrical conductivity results obtained during the
rainfall event monitoring period are analysed using the methods
outlined in section 2.5.
3.5.2 Flow Ratios
Figs 3.7 and 3.8 show the flow ratios of Glenridding Beck (Q6) to the
eastern tailings dam drain (Q7) obtained during the monitoring. The
calculated results for the flow ratio of upstream Glenridding Beck (Q2)
to Swart Beck (Q5) appeared to follow no recognisable patterns during
47 John Robert Maxwell
all three monitoring periods. It is thought that there are a number of
other factors affecting the results such as the abstraction by the
hydroelectric scheme between sites 1 and 2, the calculated ratios can be
seen in appendix D, these results are therefore not presented
graphically.
Fig 3.7, Q6/Q7 flow ratios for the period 08/08/00 – 11/08/00.
Fig 3.8, Q6/Q7 flow ratios for the period 05/09/00 – 08/09/00
3.5.3 Dilution Factors
Table 3.6 below shows the dilution factors of Qt/Qb obtained during
each rainfall event monitored. Results were obtained using the
simplistic model and equations presented in section 2.5.
020406080
100120
08/08/0012:00
09/08/0000:00
09/08/0012:00
10/08/0000:00
10/08/0012:00
11/08/0000:00
Date and Time
Rat
io o
f Q
6/Q
7
0
50
100
150
200
05/09/0012:00
06/09/0000:00
06/09/0012:00
07/09/0000:00
07/09/0012:00
08/09/0000:00
08/09/0012:00
Date and Time
Rat
io o
f Q
6/Q
7
48 John Robert Maxwell
Table 3.6, Qt/Qb dilution factors as a result of rainfall inputs.
Site8/7/00-9/7/00
12.5 mm
8/8/00-10/8/00
9 mm
5/9/00-6/9/00
18mm
7/9/00-8/9/00
12mm
2 1.33 1.28 2.0 2.5
5 1.59 1.6 2.49 3.11
6 1.5 1.31 2.35 2.83
7 1.56 1.21 1.67 1.6
8 1.31 2.36 2.8
49 John Robert Maxwell
4. Flood Frequency Analysis
4.1 Introduction
The Flood Studies Report (1975) provides a method for estimating
flood frequency characteristics from the catchment characteristics.
There is no gauging station within the catchment and therefore to
assess flood magnitudes and their return periods in the catchment it
appeared appropriate to use this method to approximate the flood
characteristics of the catchment.
4.2 Method
The Flood Studies Report (1975) outlines the mean annual flood Qmaf
can be estimated from the following 6 variable equation:
Qmaf=C*area0.94STMFRQ0.27S1085 0.16Soil1.23RSMD 1.03(1+lake)-0.85m3s-1
Where C is a regional coefficient for the North West region, area is the
catchment area (km2), STMFRQ is a stream frequency index
(junctions/km2), S1085 is the stream slope (m/km), Soil is the soil index
based on infiltration and runoff, RSMD is the net 1 day rainfall of a 5
year return period (mm) and Lake is the proportion of lakes in the
catchment. The Standard error for the 6 variable equation estimate for
ln(Qmaf) is approximately 0.168. Using the following equation it is
possible to estimate the uncertainty in the estimate of Qmaf.
Qmaf ± σmaf = exp [ln (Qmaf) ± 0.168]
The catchment characteristics for the Glenridding and Swart Beck
catchments are shown in table 4.1. These estimates can also be used to
create a flood frequency curve for the catchments. This is obtained by
multiplying Qmaf by the regional growth factors shown in table 4.2.
50 John Robert Maxwell
Table 4.1, Catchment characteristics for the two catchments.
Characteristic Glenridding Beck Swart Beck
Area km2 8.37 2.54
STMFRQ j/km2 5.85 8.66
S1085 m/km 0.12 0.11
Soil 0.5 0.5
RSMD mm 96.287 97.132
Lake 0.04 0
Table 4.2, Regional growth Factors for the Northwest region.
Return Period (years) Growth Factor
5 1.19
10 1.38
20 1.58
50 1.85
100 2.08
4.3 Results
Using the six variable equation presented in section 4.2 the mean
annual flood, Qmaf was calculated for Glenridding and Swart Beck’s.
Using the regional growth factors estimates the magnitude of floods for
a given return period are also calculated. These estimates are shown in
table 4.3
51 John Robert Maxwell
Table 4.3, Flood studies report estimates
Return Period Glenridding Beck Swart Beck
1 8.20 3.06
5 9.76 3.64
10 11.32 4.22
20 12.96 4.83
50 15.17 5.66
100 16.10 6.00
These are the best fit estimates, due to the error in the estimation using
the 6 variable equation these estimates have a large range. Fig 4.1
(Glenridding Beck) and 4.2 (Swart Beck) show the flood frequency
curves together with the 95% confidence limits shown by the error bars
for both catchments.
Fig 4.1, The estimated flood frequency curve for Glenridding Beck
with the 95% confidence limits shown by the error bars.
0
5
10
15
20
25
1 10 100
Return Period (log)
Pre
dict
ed D
isch
arge
m3/
s
52 John Robert Maxwell
Fig 4.2, The estimated flood frequency curve for Swart Beck with the
95% confidence limits shown by the error bars.
4.4 Summary
The Flood Studies Report estimates indicate the magnitude of flood
discharges in the catchment. Compared to those discharges measured
the mean annual flood in the Glenridding Beck catchment is likely to
be in order of 37 times greater and that of Swart beck is likely to be in
order of 26 times greater. This indicates the huge variation in
discharges within the catchment; it also indicates the high energy
nature of the catchment.
Although these estimates provide an indication of flood magnitudes in
the catchment the error in these estimates has to be considered. The
95% estimate for the mean annual flood on Glenridding Beck has a
range of 5.86-11.47m3s with a best fit estimate of 8.2 m3s and the range
for Swart Beck is 2.18-4.28 m3s with a best fit estimate of 3.06 m3s.
This uncertainty in the estimates is likely to be due to extrapolations in
the model. Firstly the Northwest region covers an area stretching from
0
2
4
6
8
10
1 10 100
Return Period (log)
Pre
dic
ted
Dis
char
ge
m3/
s
53 John Robert Maxwell
Cheshire plane to the Lake District, the spatial variability in physical
characteristics over this area is large and therefore the regional
coefficient and the growth factors could have an influence on the
results. Secondly the catchment characteristics are presented in the
1975 report, over this 25 year period changes in land use and climate
could have altered the nature of the catchment characteristics and
subsequently introduce added error in to the estimate. Although the
method has produced flood magnitude estimates they should only be
treated as predictions due to the error in the estimates.
The Flood Studies has recently been proceeded by the Flood
Estimation Handbook and methods used in the new edition may
produce better estimates, as the report has only recently been published
it was considered appropriate to use the older and wider used Flood
Studies Report method.
54 John Robert Maxwell
5. Discussion
5.1 Introduction
The following chapter will analyse and discuss the results gathered in
this study and attempt to outline the significant sources of pollution and
their relative contributions in the catchment. Combination of all result
should allow patterns and processes concerning heavy metals and the
hydrology in the catchment to be addressed.
5.2 Hydrochemical Change
5.2.1 Introduction
The first section will discuss the nature of the hydrology in the
catchment, emphasising on the discharges measured during the
sampling period, this will lead in to a section concerning chemical
fluxes which will attempt to identify the main pollution sources and
their impact in the catchment.
5.2.2 Hydrology
The hydrology within the Glenridding Beck catchment and especially
around the mine area was assessed by methods previously discussed.
Table 5.1 below shows flow proportions of the relative contributions
on each sampling occasion.
Discharges were lowest on 20/03/00 and increased through the
sampling period to there highest on 13/06/00 (tables 3.1 – 3.4). This is
reflected well in the flow proportions (Table 5.1). It appears that as the
discharges increase so does the proportion of the flow of Swart Beck
and the tailings dam drain to that of Glenridding Beck. This suggests a
55 John Robert Maxwell
Table 5.1, Flow proportions on each sampling day, relative to site 8,
Glenridding Beck downstream on the eastern tailings dam drain.
20/03/00 23/05/00 13/06/00 Average
2 - Upstream
Glenridding Beck63.2% 60.2% 47.2% 56.9%
5 - Swart Beck 30.4% 35.2% 48.8% 38.1%
4 - Mine Drainage 5.7% 3.7% 2.5% 4%
7 - Eastern Tailings
dam drain0.7% 0.9% 1.4% 1%
quicker response of Swart beck to rainfall and thus a flashier
hydrograph. Looking at the catchment characteristics presented in the
Flood Studies Report (1975) the Swart Beck catchment has a higher
STMFRQ indicating a larger drainage density and the Swart Beck
catchment contains no lakes. This could explain the flashier response to
rainfall.
Fig 3.3 shows daily rainfall from 07/10/99 to 10/09/00, this covers the
Environmental Agency’s sampling program and this study. Looking at
the rainfall patterns and discharges the discharges tend to respond to
individual rainfall events rather than wet periods, although the
antecedent condition will have an effect on magnitude of the discharge
and the response rate. This is reflected in the discharges measured on
13/06/00, there was 2mm of rain on that day and 10.5mm over the six
days previous and the discharges were the highest of those measured.
In comparison, discharges measured on 23/05/00 were lower, there had
been no rain for two days but over the six days previous there had been
a total of 55mm. This suggests that the bulk of the discharge is made
up of event water rather than baseflow.
Discharges from the mine drainage (site 4) do not follow the same
pattern. The highest discharge occurred on the 20/03/00, when those of
56 John Robert Maxwell
Swart and Glenridding Beck’s were at their lowest. Looking at the
discharges in comparison with rainfall data (fig 3.3) it appears that the
higher discharges occur after wetter periods rather than individual
rainfall events. This is shown on 20/03/00 where previous month’s
rainfall of 291.5mm resulted in a high discharge and the low discharge
on 23/05/00 followed only 89mm in the previous month. The month
previous to 13/06/00 had 136mm of rainfall and is reflected with a mid
range discharge. This evidence would suggest that the mine drainage
component in made up from groundwater and does not respond to
individual rainfall events. The conductivity also remained constant at
this site throughout the sampling period representing no dilution effects
by rainfall.
The rainfall event monitoring attempted to assess the dilution effect as
a result of rainfall. The results can be seen on figs 3.4-3.6 and in
appendix D. Analysis of results can be seen in section 3.4.
Analysis and calculation of flow ratios and dilution factors has
indicated the effect of rainfall on various sources in the catchment.
Firstly looking at the dilution factors. Driest antecedent conditions
occurred on 8/7/00-9/7/00 and on each monitoring there after
conditions appear to get wetter, see fig 3.3. This suggests that as the
catchment gets wetter so the dilution of the beck’s by rainfall increases,
Swart Beck’s dilution factor is always the greatest, suggesting again
that its response to rainfall is quicker and flashier than any other
sources in the catchment.
The flow ratios of Glenridding Beck to the eastern tailings dam drain
(Q6/Q7) suggest that the tailings dam has a longer lag time than that of
Glenridding Beck, the peak on both graphs (figs 3.4 & 3.5) represents
the increase of flow of Glenridding Beck in comparison to that of the
tailings dam drain. What is noticeable is the flashier peak of fig 3.5,
when the catchment is overall wetter. Looking at the dilution factors
57 John Robert Maxwell
for the tailings dam drain (site 7) they have the smallest dilution
factors, except on 8/7/00-9/7/00. This comparison suggests that the
tailings has a large storage capacity and as it dries out it tends to absorb
rainfall and has little and delayed response or dilution as a result of
rainfall inputs.
The rainfall monitoring has shown that rainfall does have a significant
dilution effect on both Glenridding Beck and Swart Beck but the
response and dilution of the tailings dam drain tends to be slow and
limited. It has again indicated that the majority of the total flow is
likely to be made up from event water rather than baseflow.
5.2.3 Chemical Fluxes
Combining and multiplying the discharges and metal concentrations
allows the estimation of annual fluxes of dissolved lead and zinc in
kg/yr. This will allow the main pollution sources to be identified and
their impacts assessed. Table 5.2 show the chemical fluxes at various
sites, site locations can be seen on fig 2.1. Some of the discharges were
extrapolated to obtain discharges for closely related sites where metal
concentrations were available.
It is clear from the flux values that Swart beck (site 5) is the main
source of pollution. Its impact on Glenridding Beck can be seen by the
increase of the average annual flux of 158.6 Pb kg/yr and 279.4 Zn
kg/yr from sites 2, upstream Glenridding Beck to site 6, downstream of
the confluence with Swart Beck. The mine drainage (site 4) and the
eastern tailings dam drain (site 7) have small mass fluxes but
comparing them with the flow proportions shown in table 5.1 their
fluxes are large when comparing them to the proportion of flow from
site 2. Therefore sites 4 and 7 are also considered to be significant
pollution sources in the catchment. Interestingly the lead and zinc
58 John Robert Maxwell
Table 5.2, Lead and zinc chemical fluxes
20/03/00 23/05/00 13/06/00
Site Pb kg/yr Pb kg/yr Pb kg/yrAverage Pb flux
kg/yrRangekg/yr
2 6.2 15 44 21.7 37.84 15.6 10 5.2 10.3 10.45 41.2 90.8 371.5 167.8 330.36 63.1 111.2 366.5 180.3 303.47 0.74 16.9 3.8 7.1 16.29 101.6 154.6 543.9 266.7 442.3
Site Zn kg/yr Zn kg/yr Zn kg/yrAverage Zn flux
kg/yrRangekg/yr
2 6.5 39.6 86 44.0 79.54 69.7 36 47.9 51.2 33.75 157.3 198.4 442.1 265.9 284.86 179.1 248.37 542.8 323.4 363.77 21.1 14.1 30.6 21.9 16.59 219.4 322 473 338.1 253.6
fluxes increase between site 8 and 9. On a further inspection of the area
below site 8 two small drains similar in nature and size to that of the
eastern tailings dam drain were discovered. Electrical conductivity at
these two sites were 85.9µs/cm and 111.8µs/cm respectively; this may
reflect high metal contents and could explain the increase of metals and
subsequently the fluxes between sites 8 and 9.
In all the effect on Lake Ullswater is large considering that these kind
of inputs (probably greater during mining periods) will have been
occurring now for over 2 centuries. Using the discharges obtained at
site 9 and the metal concentrations at site 11 (using estimated values of
30ppb lead and 60ppb zinc for the 23/05/00 as no sample was obtained
from this site on this day) the average mass fluxes entering Lake
Ullswater from this study are predicted as:
• Lead – 141.6 kg/yr.
• Zinc – 271.9 kg/yr.
These values will be under estimated; the discharge will increase
slightly between site 9 and 11 and thus the flux will also increase. The
59 John Robert Maxwell
annual estimated lead flux is greater than three times that of 44kg/yr
predicted by the Environment Agency (2000). This estimate was
probably obtained by modelling discharges and using metal
concentrations obtained during their study, although the Environment
Agency do not state the method used in their report. It is therefore
considered that the annual metal fluxes predicted in this study will give
a more accurate prediction. One point to note here is the large range of
metal fluxes (see table 5.2) obtained over the three sampling periods
and therefore extrapolating these to predict average yearly estimates
may not give an accurate representation. Considering the magnitude of
floods modelled by the Flood Studies Report (1975) outlined in chapter
4, if the metal concentrations remain at similar levels during winter
months which is likely, the fluxes will increase dramatically during
these events. This is likely to increase the yearly fluxes significantly, as
it is unlikely that the discharge levels will go much lower than those
measured on 20/03/00 in an average year.
5.2.4 Pollution Sources
The previous section has outlined that Swart beck is the dominant
pollution source, figs 5.1 and 5.2 show lead and zinc concentrations
obtained during the sampling, site references can be identified on fig
2.1. Full values for some results at site 7 are not shown to their full
extent as these large values distorted the rest of the graph.
The pollution at site 5 appears to be a cumulative effect over the course
of Swart Beck, figs 5.1 and 5.2 show sites 13, 14 & 15 all have high
lead and zinc concentrations. These sites are all in the upper Swart
Beck catchment around the area of the high mill. These concentrations
combined with the inputs from the Low Horse level (site 3), site 4,
Lucy tongue level mine drainage and drainage from the two tailings
dams make the concentrations at site 5 high and have a subsequent
effect on Glenridding Beck.
60 John Robert Maxwell
Fig 5.1, Lead concentrations obtained over the sampling period.
Fig 5.2, Zinc concentrations obtained over the sampling period.
The results show some recognisable patterns; firstly site 1, upstream of
mining activity shows little sign of containing any metals. This
indicates any increase must be pollution occurring as a result of mining
activity. The increase of lead and zinc concentrations at site 6, from
0
20
40
60
80
100
120
140
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Site
Pb
Co
nce
ntr
atio
n (
pp
b)
20/03/00 11/05/00 23/05/00 13/06/00
0
50
100
150
200
250
300
350
400
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Site
Zn
Co
nce
ntr
atio
n (
pp
b)
20/03/00 11/05/00 23/05/00 13/06/00
61 John Robert Maxwell
those at site 2 shows the result of the input of Swart Beck on
Glenridding Beck. Site 8, Glenridding Beck below the eastern tailings
dam shows an increase in both metals as a result of the input of the
tailings drain.
High metal concentrations at site 3 indicate significant pollution in the
upper Swart Beck catchment. Site 16, above most mining activity in
the Swart Beck catchment little sign of pollution (see fig 5.1 & 5.2),
again this shows background levels and indicates the magnitude of
pollution occurring from mining activities. These results also show the
contribution of the area surrounding the site of the high mill, high
levels in this area will explain the high levels obtained at site 3
throughout the sampling program, it also indicates that Swart Beck has
high lead and zinc concentrations over most of its length as a result of
numerous polluted contributions.
Figs 3.1 and 3.2 show the metal concentrations obtained by the
Environment Agency’s study; their levels obtained tend to have similar
concentrations to those obtained in this study. Sites D and E (see
section 3.5 for their descriptions) have very high lead and zinc levels.
Although these sites have high lead and zinc contents their discharges
are minimal, this is the reason why they were not considered in this
study, this results in a limited impact on the Beck’s and subsequently
Lake Ullswater although they will add to the cumulative effect to
Swart Beck. One point to note here is the increase in the concentrations
of lead on 27/02/00, which is similar the patterns observed on 13/06/00
during this study. In conclusion heavy metal pollution appears to be
occurring mainly in Swart Beck from the sites of the Low and High
Mills, mine drainage’s and the tailings drainage and also in
Glenridding Beck from the eastern tailings dam drainage.
62 John Robert Maxwell
5.2.5 pH and metal concentrations
The previous two sections have looked at metal fluxes and
concentrations, in both of these sections it is apparent that through this
study and that of the Environment Agency there are variations in metal
concentrations, especially that of lead. Fig 5.3 shows pH readings
obtained during the sampling period. This graph shows that the pH was
generally lower on 13/06/00 when the discharge and lead
concentrations were at their highest. This could be due the washing out
of organic material in the catchment during rainfall events and as a
result lowering the pH and thus mobilising lead from sediments.
Fig 5.3, pH readings obtained during the sampling program.
Looking at the results for the 13/06/00, lead concentrations (fig 5.1)
and pH (fig 5.3) sites 6 to 11 show a clear pattern, as the pH is reduced
in the beck the lead concentration increases. This could be the
desorption of lead from bed sediments in to solution. Jain and Ram
(1995) indicate that adsorption of lead rises from 13.8% at pH 4.0 to
42% at pH 6.0 on the River Kali, India. Fig 5.4 shows the desorption of
lead from various sediments at Greenside obtained by Barnes (2000),
results indicate that as the pH of the solution is reduced so the
4
4.5
5
5.5
6
6.5
7
7.5
1 2 3 4 5 6 7 8 9 10 11 12
Site
pH
20/03/00 23/05/00 13/06/00
63 John Robert Maxwell
desorption of lead from sediments increases, this would explain
patterns observed.
Fig 5.4, Solution concentration as a function of pH. Source Barnes
(2000)
Results obtained by Barnes suggest that at pH 6 almost all lead will be
sorbed on to sediments and as the pH decreases lead is subsequently
mobilised.
Zinc does not appear to follow this pattern, the concentrations appear
to remain constant with only slight variations, Jain and Ram (1995)
indicate that the adsorption of zinc on to bed sediments rises from 2%
at pH 4.0 to 15% at pH 6.0. This little difference in adsorption
indicates that zinc is not readily adsorbed to sediments under differing
pH, this would indicate why zinc concentrations remain at steady
concentrations under different catchment conditions.
Although the Environment Agency did not record pH in conjunction
with their water sampling, looking at the explanation given earlier,
washing out of organic material will be maximised during runoff and
infiltration from rainfall. Applying this theory to the results obtained in
this study to the Environment Agency’s results provides additional
0
100
200
300
400
500
600
2 3 4 5 6 7 8
pH
So
luti
on
co
nce
ntr
atio
n (
pp
m)
Tailings material Soil Fine bed sediment Coarse bed sediment
64 John Robert Maxwell
support for this hypothesis. The zinc concentrations appear to remain
steady with a few variations over the sampling period. The lead
concentrations obtained on the 27/02/00 are markedly higher than
others obtained during the study. Comparing this to rainfall (fig 3.3 and
Appendix E) there was 52mm of rainfall between 08:00 on 26/02/00
and 08:00 on 27/02/00. As previously discussed this must have resulted
in a high discharge and subsequently if the same patterns were
followed the pH is likely to have been lowered considerably due to
organic material, which would result in mobilisation of the lead, this
again appears to have been the case. The elevated levels obtained
during this study on 13/06/00
There is also evidence to indicate the fact that lead is being adsorbed
on to bed sediments from solution. On the 20/03/00 and 11/05/00 the
lead concentrations are lower at site 5, downstream Swart Beck than at
site 3, upstream Swart Beck (see fig 5.1) even after further inputs of
metals, but the pH increases on both occasions (see fig 5.3). It
therefore appears that as the pH is reduced the lead is mobilised from
the bed sediments, and thus increases the concentration in solution as is
indicated by both Jain and Ram (1995) and Barnes (2000). This
appears to happen during periods of higher discharges resulting from
rainfall inputs.
5.2.6 Sediment chemistry
In conjunction with this study, Kember (2000) studied heavy metal
concentrations in the bed sediments in the surface water courses in the
catchment. Fig 5.5 shows the results obtained by Kember H (2000).
65 John Robert Maxwell
Fig 5.5, Concentrations of lead and zinc in bed sediments, where the
sites refer to the same as this study and site A refers to the Water
trough on eastern tailings dam drain NGR NY 366173. Source:
Kember (2000).
The results show that the concentrations of lead bound to sediments are
highest in Swart Beck, levels also have a tendency to be reduced as
Glenridding Beck moves away from the mining region which links in
with the results of this study to again suggest that Swart Beck is the
main source of pollution. This is shown by the very low level of lead
(9ppb) in the sediments at site 1, upstream Glenridding Beck and the
high levels in Swart Beck, sites 3, 5, 13 & 14, which are the four
highest concentrations. The high levels in sediments at these sites
corresponds well with high levels in the water samples, (see figs 5.1 &
5.2), which is likely to be due to the mobilisation from the heavily
contaminated sediments. Notice here that the sites on the eastern
tailings dam drain and the mine drainage are low in comparison to
those of Swart and Glenridding Becks. Generally zinc levels are low
compared to those of lead which again suggests that zinc is not readily
absorbed to the sediments.
0
10000
20000
30000
40000
50000
60000
1 3 4 5 6 7 9 10 11 12 13 14 A
Site
Co
nce
ntr
atio
n (
pp
m)
Lead Zinc
66 John Robert Maxwell
Scott Doherty (1999) assessed metal concentrations in soil samples
around the High Mill and the Low Horse Level Mine, the Lucy Tongue
Level Mine and in the tailings material. Their results can be seen in
table 5.3 below.
Table 5.3, Metal concentrations in soil and tailings samples in the
Swart Beck catchment. Source: Scott Doherty (1999).
Metal High Mill &
LHLM (ppm)
Lucy Tongue
Level Mine
(ppm)
Tailings
Dams
(ppm)
Arsenic 59 - 203 37-240 75-170
Cadmium 3.6 - 115 2.7 - 50 3 – 46
Copper 92 - 560 97 - 753 46 – 220
Lead 8840 - 80200 8380 - 86400 2390 – 17400
Zinc 697 - 12300 758 - 7460 360 – 5050
Barium 622 - 9330 352 - 1020 71 - 1130
Their report indicates that all concentrations fall in to the contaminated
range in the Greater London Council (GCL) guidelines for
contaminated soils and those of Zinc fall partly in to the heavily
contaminated range. Lead concentrations are significantly elevated and
fall in to the heavily contaminated to unusually contaminated range.
The combination of the results obtained by Kember (2000) and Scott
Doherty (1999) suggest that the tailings material has lower than
expected metal concentrations, but neither do the water sample results
indicate excessive lead concentrations although on 23/05/00 lead
concentration was 536.6µg/l but it was noted that the water had a
cloudy appearance which could be due to the washing out of the
tailings material. Results obtained by Barnes (2000) (see fig 5.4) also
indicate the tailings material has the lowest lead concentrations and
those in soil are the highest.
67 John Robert Maxwell
Although the tailing material have significantly lower lead
concentrations than the surrounding soil, Scott Doherty (1999) indicate
that levels still fall in the heavily to unusually contaminated range.
There have been recent failures in the western tailings dam during
flood events, resulting in tailings material entering both Swart and
Glenridding Beck and subsequently Lake Ullswater (Guy Weller pers
comm 09/06/00). Due to the high energy nature of Glenridding and
Swart Beck tailings material is likely to be transported effectively,
during such events this would pose a major threat to water quality in
the catchment and subsequently Lake Ullswater. Fig 5.6 shows the
result of the 1989 failure on the western tailings dam.
The significantly higher levels recorded in soil samples suggest a threat
from leaching to surface water courses. Scott Doherty (1999)
determined the potential for leaching of metals in to water courses
indicate that lead, cadmium and zinc fall above the Dutch intervention
levels. As results indicated in this study and that of the Environment
Agency, higher discharges resulted in elevated lead concentrations, this
could suggests that metals are also being leached, in addition to
mobilisation from bed sediments as a result of a lower pH. It therefore
appears that the combination of both factors appears to significantly
increase levels in surface waters and subsequently Lake Ullswater
during higher discharge periods.
These higher discharge periods and especially those indicated by the
Flood Studies Report (1975) will allow significant sediment transport.
Transport of contaminated sediments could in turn further contaminate
the sediments and surface waters in Glenridding Beck and
subsequently Lake Ullswater which in turn during higher discharge and
subsequently lower pH, lead mobilisation could significantly elevate
lead concentrations in Glenridding Beck and Lake Ullswater.
68 John Robert Maxwell
Fig 5.6, The result of the 1989 tailings failure on the western tailings
dam the eastern tailings dam is to the right of the photo. Photo taken at
NGR NY 366174 looking North West.
5.3 Water Quality
To put the pollution occurring in the catchment and subsequently Lake
Ullswater into context, this section aims to look at drinking water
quality standards as water is abstracted by North West Water PLC for
water supply from Lake Ullswater. Table 5.4 bellow shows the advised
drinking water standards by various directives and policies.
Although these are the current standards the Department of
Environment, Transport and the Regions (DETR) will set out tighter
lead standards in the new ‘Drinking Water Directive’. The new
standards will be 25ppb with in five years of the directive and within
15 years the standard will be 10ppb, which bring the UK standards in
to line with the WHO recommendations, see table 5.4.
Although the current directive states 50ppb this is a maximum
allowable concentration, looking at the results, many of the measured
concentrations exceed 50ppb lead, and that of Lake Ullswater also
69 John Robert Maxwell
exceeds the maximum limit on 27/02/00 and 13/06/00. Considering the
WHO recommendations and the new UK Drinking Water Directive, all
but sites 1, 2 and 16 which are upstream of most mining activity,
exceed the recommended concentration of 10ppb lead with the
exeption of Lake Ullswater on 20/03/00. All zinc concentrations fall
well below the recommended levels in this study, although some levels
were recorded above 5000ppb by the Environment Agency but these
were small discharges from the tailings dams. It is likely that Lake
Ullswater will have a lower concentration of metal as it moves away
from Glenridding Beck but this would require further study.
Table 5.4, Drinking Water Standards. Source Twart et al. (1994) &
Fifield & Haines (2000)
Metal World Health
Organisation
(WHO) 1993
recommendation
EC Directive
1980, Maximum
UK Regulations
1989, Maximum
Lead 10ppb 50ppb 50ppb
Zinc 3000ppb 5000ppb 5000ppb
Overall concentrations of lead in Glenridding Beck and Lake Ullswater
approach and exceed the maximum level stated by the EC and UK
directives for drinking water where as zinc levels fall significantly
below the maximum stated concentrations. The higher lead levels,
especially in the sediments could have serious consequences for water
supply and the ecology of Lake Ullswater in the future. Factors such as
land use change, eutrophication and climate change may have
significant effects due to the mobilisation of lead from sediments than
the magnitude of the current problem occurring from the discharges.
Metal concentrations are not currently excessive and although they are
having an impact on the water quality below the mining region.
Although levels are elevated it unlikely that these concentrations will
70 John Robert Maxwell
pose any significant threat to humans, animals or fish at their current
concentrations.
71 John Robert Maxwell
6. Summary and Conclusions
This study in to surface water discharges and chemical fluxes has
provided some useful results. It is clear that previous mining has and is
having a significant effect on the water quality in the Glenridding Beck
catchment. The following points summarise the results and conclusions
from this study:
1. This study has assessed the hydrology outlining a quick flashy
response to rainfall, especially that of the Swart Beck catchment.
2. The study has provided predicted annual metal fluxes of 141.1kg
Pb/yr and 271.9kg Zn/yr in to Lake Ullswater in which the lead
flux exceeds the Environment Agency’s prediction by three
times.
3. It has shown that metal concentrations upstream of mining
activity in both Swart and Glenridding Beck are nearly zero.
4. It has indicated that Swart Beck is the main pollution source with
in the catchment. Mine and tailings drainage are also considered
to be having a significant impacts.
5. The study has indicated that rainfall has an overall dilution effect
on surface waters but due to reduced pH during higher discharge
periods, lead is subsequently mobilised and concentrations
increase.
6. It has shown that the Tailings dams have a limited impact to
rainfall inputs and that metal concentrations are not excessively
high.
72 John Robert Maxwell
7. It has indicated that water quality is generally poor below the
mining region and in Lake Ullswater with levels approaching and
exceeding the maximum allowable concentrations for drinking
water.
8. Factors such as changing land use and climate change could have
adverse impacts on metal concentrations in surface waters and
Lake Ullswater
Although this study has provided an indication of heavy metal
pollution in the Glenridding Beck catchment under different catchment
conditions it has provided a large scope for further study in to heavy
metal concentrations and pollution within the catchment. The following
list provides scope for further investigation as a result of this study:
1. A longer term study of discharges and metal concentrations to
provide a more accurate prediction on metal fluxes patterns and
processes.
2. Link together sampling of surface water and bed sediments in
an attempt to correlate sorption and desorption of lead and zinc
under different catchment conditions.
3. Further assess metal concentrations in, and the dilution effect of
Lake Ullswater.
4. Assess the dilution effect of rainfall over a longer term using
logging probes, and investigate other factors influencing the
results of this study.
73 John Robert Maxwell
References
Abbasi, S.I, Abbasi, N & Soni, R. (1998). Heavy Metals in the Environment.
Mittal Publications, New Delhi.
Adams, J. (1988). Mines of the Lake District. The Dalesman Publishing Co,
Kendal.
Barnes C. E. (2000). BSc Environmental Management Thesis investigating the
desorption of Lead from sediments at Greenside (in progress). Lancaster
University, Lancaster.
Dingham, S.L. (1994). Physical Hydrology, Prentice and Hall, London.
Fifield, F.W. & Haines, P.J. (2000). Environmental Analytical Chemistry.
Blackwell, Oxford.
Herschy, R.W. (1995). Stream flow Measurement. Chapman & Hall, London.
Environment Agency (2000). A Report on the Impact of Discharges from
Greenside Mine and Spoil Heaps into surrounding Watercourses and
Ullswater.
National Environmental Research Council. (1975). Flood Studies Report,
White Friars Press LTD, London.
Gregory, K.J. & Walling, D.E. (1973). Drainage Basin Form and Process.
Edward Arnold, London.
Jain, K. J. & Ram, D. (1995). Adsorption of Lead and Zinc on bed sediments
of the River Kali. Water Resources 31 (1) 154 – 162.
74 John Robert Maxwell
Kember, H.M. (2000). A study of metal contamination of sediments within
Lake Ullswater and the Glenridding Beck catchment, BSc Environmental
Science Thesis, Lancaster University, Lancaster.
Moor, J.W. & Ramamoorthy, S. (1984). Heavy Metals in Natural Waters
Applied Monitoring and Impact Assessment. Springer-Verlag, New York.
Murphy, S. (1996). Grey Gold. Men, Mining & Metallurgy at the Greenside
Lead Mine in Cumbria, England 1825 to 1962. Moiety, Warwickshire.
Radojevic, M & Bashkin, V.N. (1999). Practical Environmental Analysis. The
Royal society of Chemistry, Cambridge.
Scott Doherty Associates. (1999). Greenside Mine, Glenridding Geo-
environmental and Structural assessment.
Shaw, E.M. (1994). Hydrology in Practice, Prentice and Hall, London.
Twart, A.C., Law, F.M., Crowley, F.W. & Ratnayaka, D.D. (1994). Water
Supply, Edward Arnold, London.
Tyler, I. (1998). Greenside and the Mines of the Ullswater Valley. Blue Rock
Publications, Threlkeld.
75 John Robert Maxwell
Acknowledgements
My thanks go to numerous people and organisations that have assisted in the
preparation of this study, these are as follows:
Dr. Andrew Binley for his assistance with this study, both during the
fieldwork and his guidance through the preparation of the report, Tristan
Adams and Anita Ghosh and for their assistance during the sampling days and
during the water sample analysis. Helen Kember, also for her assistance during
the fieldwork but mainly for providing the results of her sediment analysis and
to Chris Barnes for allowing use of his data. Thanks must also go to Ann
Wilkinson for her knowledge and assistance during the water analysis and
Charles Blakeley for his help in the preparation for the fieldwork days.
Ian Tyler from Threlkeld Quarry and Mining museum for his valuable
background information and to Guy Weller of the Lake District National Park
for his time and information concerning management of the site. Thanks must
also go to Messrs Lightfoot of Gillside Farm, Glenridding for allowing access
to and over their land for sampling purposes.
76 John Robert Maxwell
Appendix A - Procedures
Information required on the COSHH form
The following section outlines the information required to complete the
COSHH form.
Title of Experiment/Procedure:
Fluorometric stream gauging using Rhodamine WT.
20Y solution to be used (200g/l)
Maximum amount per experiment – 100mg (preweighed) mixed with 5litres
of stream water and injected in to the stream.
Details of Substance:
• Rhodamine WT (20Y. solution) Liquid.
• Hazard category: Medium.
• Exposure potential: low.
• Exposure limit: none.
• Risk category: Low.
Measures to be adopted:
• Rhodamine WT to be stored in pre-weighed bottles and kept closed.
• Rubber gloves and safety goggles to be worn when handling.
• Rhodamine will be applied to river, any unused will be returned.
• In the case of emergency flush eyes, skin, clothing with plenty of water.
• In the case of spillage flush with water.
• Any first aid procedure, flush with water.
77 John Robert Maxwell
Preparation of Standard Solutions and water sample analysis.
The following equation is useful in the preparation. It gives the volume of
standard required to make a standard of a given concentration.
standard ofion Concentrat
flask of volume required ppm take toVolume
×=
E.g. to make 50ml of a 10ppm solution from a 1000ppm solution:
5.01000
5010=
× i.e. take 0.5ml of the 1000ppm solution and add 49.5ml of
distilled water to create the 10ppm standard.
During the preparation of standard solutions use acid washed bottles and
distilled water for dilution ONLY.
Lead standards
From a 1000ppm lead solution dilute it down using 50ml flasks to create a
10ppm solution and then from the 10ppm solution create a 250ppb.
Now using 25ml flasks prepare the following concentrations, 10, 20, 30, 40,
50 & 75ppb from the 250ppb solution.
Also prepare 5 blank solutions using distilled water only.
Analyses takes place on the graphite AAS, set up the machine using the
operation instructions. Firstly analyse the standards and blanks and correct the
standards with the average blank absorbance. Plot absorbance of the standards
against the specific standard concentration and fit a linear regression model
through the data points using the least squares estimate from the following
procedure or by using the function in Microsoft excel:
The linear line has the form, â'xá' +='y
Where 'α and x'β are the best estimates of α and xβ and 'y is the predicted y.
78 John Robert Maxwell
The sum of squared errors is given by:
∑=
−=N
i
ii yy1
)'(SSE 2
The least squares estimates of α and xβ are:
xySS
SSâ
x
xy' and ' βα −==
Where,
2
11
2
1
1)( 2
−== ∑∑∑
===
−
N
i
i
N
i
i
N
i
ix xN
xxxSS
−=−= ∑ ∑∑ ∑
= == =
−
N
i
N
i
ii
N
i
N
i
iiiXixy yxN
yxyyxSS1 11 1
1))((
Then calculating the correlation coefficient will indicate the strength of the
relationship; this is done by the following:
yx
xy
SSSS
SSr =
Where
2
11
2
1
2 1)(
−=−= ∑∑∑
===
N
i
i
N
i
i
N
i
iy yN
yyySS
If the regression line fits with r2 >0.99 continue and analyse samples once, if
not create another set of standard solutions before proceeding. If any sample
has an absorption greater than that the standards, either dilute the sample or
create another standard to cover the entire range. Finally calculate the
concentration of the samples using the linear regression model.
Zinc
From a 1000ppm zinc solution dilute it down using 50ml flasks to create a
100ppm solution and then from the 100ppm solution create a 10ppb.
Now using 25ml flasks prepare the following concentrations, 200, 400, 600,
800 & 1000 from the 10ppm solution.
Also create 10 separate blank solutions using distilled water only.
79 John Robert Maxwell
Analyses takes place on the flame AAS, set up the machine using operation
instructions, firstly analyse the standards and blanks and correct the standards
with the average blank absorbance. Plot absorbance of the standards against
the specific concentration and fit a linear regression model through the data
points using the least squares estimate in order to calculate the sample
concentrations, (using the same procedure as for the lead above). If any
sample has an absorption greater than of the highest standards, either dilute the
sample or create another standard to cover the entire range.
80 John Robert Maxwell
Appendix B – Water Analysis
Lead Analysis: Sampled 20/03/00
StandardsAbs [Pb]/ppb Blanks Standards Corrected
0.021 10 0 Abs (corrected) [Pb]/ppb0.042 20 0 0.0208 100.064 30 0.001 0.0418 200.081 40 0 0.0638 300.103 50 0 0.0808 40
Mean Blank = 0.0002 0.1028 50
Samples
Site Number Abs Absx491.91x-0.4982 = Pb/ppb1 0 -0.502 0.007 2.953 0.146 71.324 0.169 82.635 0.071 34.436 0.04 19.187 0.068 32.958 0.046 22.139 0.06 29.02
10 0.059 28.5211 0.046 22.1312 0.009 3.93
Lead Calibration Graph
y = 491.91x - 0.4982
R2 = 0.99860
10
20
30
40
50
60
0 0.02 0.04 0.06 0.08 0.1 0.12Absorbance
Pb/
ppb
81 John Robert Maxwell
Zinc Analysis: Sampled 20/03/00
Absorption on standardsConcentration 1st abs 2nd abs 3rd abs mean abs
0 0 0.003 0.002 0.001667200ppb 0.052 0.052 0.051 0.051667400ppb 0.103 0.103 0.101 0.10233333600ppb 0.154 0.149 0.152 0.15166667800ppb 0.206 0.202 0.196 0.20133333
1000ppb 0.253 0.246 0.242 0.247
Blanks Standards correctedBlanks abs Abs
(corrected)[Zn]/ppb
1 0 0.001867 02 -0.002 0.051867 2003 0.001 0.102533 4004 0 0.151867 6005 0.003 0.201533 8006 -0.001 0.247200 10007 -0.0018 -0.0029 0
10 0Mean Blank -0.0002
Zinc Calibration Graph
y = 4057x - 11.767
R2 = 0.9998
-2000
200400600800
10001200
0 0.05 0.1 0.15 0.2 0.25 0.3Absorbance
Zn/
ppb
82 John Robert Maxwell
SamplesSite Number 1st abs 2nd abs 3rd abs Mean abs Absx4057x-11.767=Zn/ppb
1 0 0 0 0 -11.772 0.002 0.004 0.005 0.00366667 3.113 0.019 0.015 0.018 0.01733333 58.554 0.092 0.096 0.093 0.09366667 368.245 0.034 0.036 0.036 0.03533333 131.586 0.015 0.017 0.017 0.01633333 54.507 0.234 0.236 0.235 0.235 941.638 0.019 0.018 0.018 0.01833333 62.619 0.018 0.019 0.018 0.01833333 62.61
10 0.018 0.02 0.02 0.01933333 66.6711 0.02 0.02 0.017 0.019 65.3212 0.006 0.01 0.006 0.00733333 17.98
83 John Robert Maxwell
Lead Analysis: Sampled 11/05/00
Standards Blanks Standards Corrected
Abs [Pb]/ppb Abs Abs (corrected) [Pb]/ppb0.025 10 00.04 20 0 0.025 100.055 30 0 0.04 200.083 40 0 0.055 300.099 50 0 0.083 400.147 75 Mean Blank = 0 0.099 50
0.147 75
SamplesSite Number Abs Absx518.4-1.2938 = Pb/ppb
2 0.0117 4.773 0.11 55.734 0.12 60.915 0.107 54.186 0.039 18.92
13 0.139 70.7614 0.158 80.6115 0.055 27.2216 0.015 6.48
Lead Calibration Graph
y = 518.4x - 1.2938
R2 = 0.9949
0
20
40
60
80
0 0.05 0.1 0.15 0.2Absorbance
Pb/
ppb
84 John Robert Maxwell
Zinc Analysis: Sampled 11/05/00
Absorption on standardsConcentration 1st abs 2nd abs 3rd abs mean abs
0 0 0.001 0.001 0.0006667200ppb 0.039 0.039 0.039 0.0390000400ppb 0.077 0.077 0.076 0.0766667600ppb 0.113 0.113 0.114 0.1133333800ppb 0.151 0.152 0.151 0.15133331000ppb 0.186 0.186 0.185 0.1856667
Blanks 1st abs 2nd abs 3rd abs mean abs
1 0 -0.001 -0.001 -0.0006672 -0.001 -0.001 -0.001 -0.0013 0 0 0 04 0 0 0 05 -0.001 -0.002 -0.001 -0.0013336 0 0 -0.001 -0.0003337 0 0.001 0.002 0.0018 -0.001 0.001 0.002 0.00066679 0.001 0 0.001 0.000666710 -0.002 -0.001 -0.001 -0.001333
MeanBlank
-0.000233
Standards CorrectedAbs (corrected) [Zn]/ppb
0.0009 00.039233 2000.076900 4000.113566 6000.151566 8000.185900 1000
Zinc Calibration Graph
y = 5388.9x - 10.206
R2 = 0.9998
-200
0
200
400
600
800
1000
1200
0 0.05 0.1 0.15 0.2Absorbance
Zn/
ppb
85 John Robert Maxwell
SamplesSite Number 1st abs 2nd abs 3rd abs Mean abs Absx5388.9-10.206=Zn/ppb
2 0.001 0.002 0.001 0.0013333 -3.023 0.018 0.018 0.018 0.018 86.794 0.057 0.058 0.057 0.0573333 298.765 0.029 0.03 0.029 0.0293333 147.876 0.019 0.019 0.019 0.019 92.18
13 0.016 0.016 0.017 0.0163333 77.8114 0.013 0.012 0.012 0.0123333 56.2615 0.003 0.002 0.002 0.0196667 95.7816 0.02 0.019 0.02 0.0023333 2.37
86 John Robert Maxwell
Lead Analysis: Sampled 23/05/00
Standards Blanks Standards CorrectedAbs [Pb]/ppb Abs Abs (corrected) [Pb]/ppb
0.025 10 0 0.025 100.04 20 0 0.04 200.055 30 0 0.055 300.083 40 0 0.083 400.099 50 0 0.099 500.147 75 Mean Blank = 0 0.147 75
SamplesSite Number Abs Absx518.4-1.2938 = Pb/ppb
1 0 -1.292 0.016 7.003 0.122 61.954 0.145 73.875 0.124 62.996 0.061 30.337 0.106 53.66, Diluted by 10x, therefore concentration is 536.68 0.081 40.709 0.093 46.92
10 0.106 53.661112 0.068 33.96
Lead Calibration Graph
y = 518.4x - 1.2938
R2 = 0.9949
0
20
40
60
80
0 0.05 0.1 0.15 0.2Absorbance
Pb/
ppb
87 John Robert Maxwell
Zinc Analysis: Sampled 23/05/00
Absorption on standardsConcentration 1st Abs 2nd Abs 3rd Abs Mean Abs
0 0.003 0.004 0.002 0.003000200ppb 0.03 0.035 0.034 0.033000400ppb 0.065 0.069 0.067 0.067600ppb 0.102 0.1 0.1 0.1006667800ppb 0.13 0.139 0.133 0.1341000ppb 0.166 0.171 0.17 0.169
BlanksBlanks 1st Abs 2nd Abs 3rd Abs Mean Abs
1 0.001 0.001 0.002 0.00133332 0.002 0.004 -0.001 0.00166673 0.001 0.004 -0.001 0.00133334 0.001 0.002 0.002 0.00166675 0.002 -0.001 -0.002 -0.0003336 0.005 -0.001 0.002 0.0027 0.003 0.002 0.004 0.0038 0.003 -0.002 0.003 0.00133339 0 0.001 0.003 0.001333310 0.001 -0.001 0.001 0.0003333
Mean Blank 0.0013667
Standards correctedAbs (corrected) [Zn]/ppb
0.001633 00.031633 2000.065633 4000.099300 6000.132633 8000.167633 1000
Zinc Calibration Graph
y = 5997.5x + 1.7441
R2 = 0.9996
0
200
400
600
800
1000
1200
0 0.05 0.1 0.15 0.2Absorbance
Zn/
ppb
88 John Robert Maxwell
SamplesSite Number 1st Abs 2nd Abs 3rd Abs Mean Abs Absx5997.5+1.7441=Zn/ppb
1 -0.002 0 0 -0.000667 -2.252 0.004 0.002 0.002 0.0026667 17.743 0.014 0.017 0.014 0.015 91.714 0.043 0.043 0.046 0.044 265.635 0.022 0.022 0.024 0.0226667 137.696 0.01 0.016 0.007 0.011 67.727 0.073 0.074 0.075 0.074 445.568 0.015 0.013 0.014 0.014 85.719 0.017 0.015 0.016 0.016 97.7010 0.014 0.012 0.012 0.0126667 77.711112 0.007 0.005 0.007 0.0063333 39.73
89 John Robert Maxwell
Lead Analysis: Sampled 13/06/00
Standards Blanks Standards CorrectedAbs [Pb]/ppb Abs Abs (corrected) [Pb]/ppb
0.001 0 0 0.001 00.011 10 0 0.011 100.034 20 0 0.034 200.056 30 0 0.056 300.086 40 0 0.086 400.103 50 Mean Blank = 0 0.103 500.146 75 0.146 750.297 150 0.297 150
SamplesSite Number Abs Absx497.74x+1.2074 = Pb/ppb
1 0.004 3.202 0.024 13.153 0.134 67.904 0.055 28.585 0.203 102.256 0.103 52.477 0.074 38.048 0.118 59.949 0.154 77.86
10 0.117 59.4411 0.069 35.5512 0.15 75.87
Lead Calibration Graph
y = 497.74x + 1.2074
R2 = 0.9973
020406080
100120140160
0 0.1 0.2 0.3 0.4Absorbance
Pb/
ppb
90 John Robert Maxwell
Zinc Analysis: Sampled 13/06/00
Absorption on standardsConcentration 1st Abs 2nd Abs 3rd Abs Mean Abs
0 0.003 0.004 0.002 0.003000200ppb 0.03 0.035 0.034 0.033000400ppb 0.065 0.069 0.067 0.067600ppb 0.102 0.1 0.1 0.1006667800ppb 0.13 0.139 0.133 0.1341000ppb 0.166 0.171 0.17 0.169
BlanksBlanks 1st Abs 2nd Abs 3rd Abs Mean Abs
1 0.001 0.001 0.002 0.00133332 0.002 0.004 -0.001 0.00166673 0.001 0.004 -0.001 0.00133334 0.001 0.002 0.002 0.00166675 0.002 -0.001 -0.002 -0.0003336 0.005 -0.001 0.002 0.0027 0.003 0.002 0.004 0.0038 0.003 -0.002 0.003 0.00133339 0 0.001 0.003 0.001333310 0.001 -0.001 0.001 0.0003333
Mean Blank 0.0013667
Standards correctedAbs (corrected) [Zn]/ppb
0.001633 00.031633 2000.065633 4000.099300 6000.132633 8000.167633 1000
Zinc Calibration Graph
y = 5997.5x + 1.7441
R2 = 0.9996
0
200
400
600
800
1000
1200
0 0.05 0.1 0.15 0.2Absorbance
Zn/
ppb
91 John Robert Maxwell
SamplesSite Number 1st Abs 2nd Abs 3rd Abs Mean Abs Absx5997.5+1.7441=Zn/ppb
1 0.004 0.002 0.002 0.0026667 17.742 0.003 0.004 0.005 0.004 25.733 0.014 0.011 0.01 0.0116667 71.714 0.045 0.046 0.041 0.044 265.635 0.02 0.02 0.02 0.02 121.696 0.014 0.012 0.012 0.0126667 77.717 0.051 0.051 0.052 0.0513333 309.628 0.011 0.014 0.014 0.013 79.719 0.013 0.01 0.01 0.011 67.7210 0.01 0.013 0.014 0.0123333 75.7111 0.01 0.01 0.007 0.009 55.7212 0.051 0.053 0.053 0.0523333 315.61
92 John Robert Maxwell
Appendix C – pH & Electrical Conductivity readings
Readings obtained on 20/03/00Site 1st EC 2nd EC 3rd EC Mean EC pH
1 39.3 36.5 38.8 38.2 6.182 41.1 40.7 40.4 40.7 6.93 44.2 46.5 43.6 44.8 5.914 297 297 301 298.3 7.315 82 82.3 82.5 82.3 6.126 57.4 57.8 57.7 57.6 6.657 135 135 135 135.0 6.548 58.1 58 58 58.0 6.329 57.4 59.1 59.4 58.6 6.34
10 62.2 60.4 60.4 61.0 6.3511 63.7 62.5 64.2 63.5 6.0412 55 55.8 56.7 55.8 6.51
Readings obtained on 11/05/00 on Swart BeckSite 1st EC 2nd EC 3rd EC Mean EC pH
2 45.8 43.2 43.6 44.2 73 47.3 47.9 47.6 47.6 54 289 290 296 291.7 7.85 96.2 94 93.4 94.5 6.96 66.4 69.4 69 68.3 6.4
13 47.7 46.8 46.4 47.0 6.614 44.6 43.8 42.6 43.7 6.715 43.8 43.6 44.7 44.0 6.616 41.8 47.7 46.5 45.3 6.6
Readings obtained on 23/05/00Site 1st EC 2nd EC 3rd EC Mean EC pH
1 30.6 33.8 33.9 32.8 4.632 37.1 36.1 36.7 36.6 6.33 42.1 41.1 41.1 41.4 4.94 301 299 301 300.3 7.015 71.9 70.4 71.6 71.3 6.746 52.4 50.9 49.9 51.1 6.487 118 114.3 114.1 115.5 6.568 55.4 54.4 54.4 54.7 5.599 55.1 53.3 54.1 54.2 5.22
10 57.3 57.6 57.6 57.5 6.4611 48.6 48.7 49 48.8 6.0412 59.6 57.3 57.3 58.1 5.63
93 John Robert Maxwell
Readings obtained on 13/06/00Site 1st EC 2nd EC 3rd EC Mean EC pH
1 30.8 30.9 29.6 30.4 6.282 31.5 32.1 32.2 31.9 6.463 34.6 35.6 35 35.1 4.724 293 299 298 296.7 6.225 52.5 52.2 52.7 52.5 6.086 41.4 42.1 42.2 41.9 6.76
7 71.9 70.8 70.6 71.1 5.78 43.1 43.3 43.3 43.2 5.099 44 44.2 44.9 44.4 4.7
10 49.5 48.1 46.8 48.1 4.7411 41.7 40.3 42.2 41.4 5.3512 59.2 60.7 61.5 60.5 5.89
94 John Robert Maxwell
Appendix D – Rainfall event monitoring results
All electrical conductivity readings are in µµs/cm
Readings taken on 8/7/00 at 10:30am after a dry period and before rainfall.
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 39.6 39.4 39.5 39.5 Q2/Q5= 0.5902785, Swart Beck 61.9 62.4 62.9 62.46, G/beck d/s S/beck 53.7 54 54 53.97, Spoil Drain 86 86.9 87.1 86.66667
Readings taken on 9/7/00 at 9:30am after 10.5mm of rain overnight starting approx.22:00.Rainfall Electrical Conductivity was 9uS/cm
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 31.8 31.5 32 31.76667 Q2/Q5= 0.6411295, Swart Beck 44.4 45.7 45.9 45.333336, G/beck d/s S/beck 40 40 40.1 40.033337, Spoil Drain 69.8 70.8 70.9 70.5
Readings taken on 9/7/00 at 18:30pm after a further 2 mm of rainfall during the day.Rainfall Electrical Conductivity was 9uS/cm
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 32.2 31.8 32.2 32.06667 Q2/Q5= 0.5291265, Swart Beck 42.6 41.9 43.2 42.566676, G/beck d/s S/beck 38.6 39 39.2 38.933337, Spoil Drain 59.1 58.8 59.1 59
Readings taken on 10/7/00 at 18:30pm after a further 23.5mm of overnight rainfall.Results were obtained approx. 8-10 hours after rainfall had ended.Rainfall Electrical Conductivity was 9.7uS/cm
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 29.2 29.4 29.4 29.33333 Q2/Q5= 0.5287775, Swart Beck 43.4 43.4 43.7 43.56, G/beck d/s S/beck 38.4 38.6 38.8 38.67, Spoil Drain 67.7 67.1 68.1 67.63333
95 John Robert Maxwell
Readings taken on 8/8/00 at 19:30am after a dry period and before rainfall.
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 42.6 43 42.4 42.66667 Q6/Q7= 52.263165, Swart Beck 89.6 91 90.8 90.46667 Q2/Q5= 2.3117786, G/beck d/s S/beck 57 57.2 57.1 57.17, Spoil Drain 125.2 124.1 124.4 124.56678, d/s Spoil Drain 58.5 58.1 58.5 58.36667
Readings taken on 9/8/00 at 18:00 during 6mm of rainfall beginning at 9:00.Rainfall Electrical Conductivity was 5.3uS/cm
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 38.6 38.6 38.7 38.633335, Swart Beck 73.4 73.3 73.4 73.36667 Milky/cloudy look to water6, G/beck d/s S/beck 49.9 50 50.1 50 Q6/Q7= 110.04357, Spoil Drain 134.6 135.5 135.3 135.1333 Q2/Q5= 2.0557188, d/s Spoil Drain 50.9 50.8 50.6 50.76667
Readings taken on 10/08/00 at 7:00 after a further 3mm of rainfall overnight.Rainfall Electrical Conductivity was 5.5uS/cm
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 34.6 34.4 34 34.33333 Q6/Q7= 52.848485, Swart Beck 58.2 58.4 58.4 58.33333 Q2/Q5= 1.3003196, G/beck d/s S/beck 45 44.4 44.9 44.766677, Spoil Drain 104.1 104 103.9 1048, d/s Spoil Drain 45.8 45.9 45.9 45.86667
Readings taken on 10/08/00 at 18:00 after no further rainfall.
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 35.6 35.6 35.6 35.6 Q6/Q7= 48.057145, Swart Beck 65.1 64.9 65.1 65.03333 Q2/Q5= 1.6358216, G/beck d/s S/beck 46.6 46.8 46.9 46.766677, Spoil Drain 103.7 104 104.3 1048, d/s Spoil Drain 47.9 47.9 48 47.93333
96 John Robert Maxwell
Readings taken on 5/9/00 at 18:00am after a dry period and before rainfall.
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 36.2 36.1 36 36.1 Q6/Q7= 44.933335, Swart Beck 66.8 67 67.1 66.96667 Q2/Q5= 1.2313256, G/beck d/s S/beck 49.6 50.2 50 49.933337, Spoil Drain 96.5 95.6 95.5 95.866678, d/s Spoil Drain 51 50.8 51 50.93333
Readings taken on 6/9/00 at 08:30 after 18mm of rainfall starting early morning & finishing07:30Rainfall Electrical Conductivity was 10uS/cm
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 23.2 23.1 22.9 23.06667 Brown tinge to water.5, Swart Beck 32.7 33.1 32.6 32.8 Brown tinge to water.6, G/beck d/s S/beck 26.9 27.1 27 277, Spoil Drain 64.3 65.9 65.5 65.23333 Q6/Q7= 162.85718, d/s Spoil Drain 27.3 27.3 27.1 27.23333 Q2/Q5= 1.474576
Readings taken on 6/9/00 at 13:30 after no further rainfall.
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 27.3 27.3 27.1 27.23333 Q6/Q7= 34.8755, Swart Beck 42.7 42.5 42.5 42.56667 Q2/Q5= 1.7380956, G/beck d/s S/beck 33.1 32.7 32.7 32.833337, Spoil Drain 61.3 61.7 61.6 61.533338, d/s Spoil Drain 33.6 33.5 33.8 33.63333
Readings taken on 6/9/00 at 19:00 after no further rainfall.
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 30.4 30.5 30.4 30.43333 Q6/Q7= 35.857145, Swart Beck 52.9 52.7 52.8 52.8 Q2/Q5= 1.7727276, G/beck d/s S/beck 38.6 38.4 38.5 38.57, Spoil Drain 64.1 64.5 64.3 64.38, d/s Spoil Drain 39.2 39.2 39.2 39.2
97 John Robert Maxwell
Readings taken on 7/9/00 at 9:00 after 1mm of rainfall during a rainfall event.
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 34.1 34.1 33.9 34.03333 Q6/Q7= 31.45, Swart Beck 61.8 61.7 61.6 61.7 Q2/Q5= 1.2192516, G/beck d/s S/beck 46.4 46.6 46.5 46.57, Spoil Drain 73.6 73 73.9 73.58, d/s Spoil Drain 47.3 47.3 47.4 47.33333
Readings taken 0n 7/9/00 at 13:30 during rainfall after a further 4 mm.
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 32.4 32.3 32.4 32.36667 Q6/Q7= 52.045, Swart Beck 56.6 56.5 56.3 56.46667 Q2/Q5= 1.8690486, G/beck d/s S/beck 40.8 40.7 40.8 40.766677, Spoil Drain 85 85 84.9 84.96667 Milky/cloudy look to water.8, d/s Spoil Drain 41.5 41.6 41.7 41.6
Readings taken on 7/9/00 at 17:30 at the end of the rainfall event after a further 7mm of rain.Rainfall Conductivity was 12us/cm
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 20.8 20.8 20.9 20.83333 Brown tinge to water.5, Swart Beck 27.9 28 28 27.96667 Brown tinge to water.6, G/beck d/s S/beck 24.2 24.2 24.2 24.2 Q6/Q7= 64.833337, Spoil Drain 50.3 50.8 50.5 50.53333 Q2/Q5= 1.1188128, d/s Spoil Drain 24.6 24.6 24.6 24.6
Readings taken on 8/9/00 at 8:00 after no further rainfall.
Site 1st EC 2nd EC 3rd EC Mean EC2, u/s G/Beck 24.6 24.6 24.6 24.6 Q6/Q7= 66.444445, Swart Beck 41.8 41.7 41.7 41.73333 Q2/Q5= 0.9107816, G/beck d/s S/beck 33.6 33.5 33.6 33.566677, Spoil Drain 53.5 53.9 54 53.88, d/s Spoil Drain 33.8 33.9 33.9 33.86667
Appendix E – Environmental Agency data
Site Date Sampled Lead ppb Cadmium ppb Chromium ppb Zinc ppb Nickel ppb Copper ppb1 07/09/99 <0.4 <0.1 <0.5 <0.5 <5 <0.52 07/09/99 6.31 0.326 <0.5 28 <5 <0.53 07/09/99 38.2 0.783 <0.5 73.8 <5 <0.54 07/09/99 92.4 2.67 <0.5 265 <5 2.495 07/09/99 53.4 1.88 <0.5 148 <5 0.684
10 07/09/99 38.3 0.887 <0.5 75.5 <5 0.84312 07/09/99 32.8 0.828 <0.5 71.6 <5 0.817A 07/09/99 31.7 0.845 <0.5 70.1 <5 0.697B 07/09/99 110 6.75 <0.5 297 <5 0.775C 07/09/99 41.5 0.829 <0.5 80.3 <5 <0.5D 07/09/99 259 120 <0.5 10600 23.1 3.2E 07/09/99 13.4 190 <0.5 15200 46.4 1.71
1 14/09/99 <0.4 <0.1 <0.5 <5 <5 <0.52 14/09/99 5.59 0.365 <0.5 33.6 <5 <0.53 14/09/99 41.7 0.873 <0.5 90.1 <5 <0.54 14/09/99 41.4 2.48 <0.5 236 <5 1.855 14/09/99 47.4 1.94 <0.5 155 <5 0.601
10 14/09/99 44.3 1.25 <0.5 110 <5 0.95112 14/09/99 31.8 0.987 <0.5 89.1 <5 0.949A 14/09/99 29.8 1.09 <0.5 85.5 <5 <0.5B 14/09/99 71.4 7.75 <0.5 338 <5 0.563C 14/09/99 41.7 0.827 <0.5 87.8 <5 <0.5D 14/09/99 247 114 <0.5 9510 22.6 4.92E 14/09/99 9.86 204 <0.5 15500 49.9 5.66
Site Date Sampled Lead ppb Cadmium ppb Chromium ppb Zinc ppb Nickel ppb Copper ppb1 05/12/99 <0.4 <0.1 <0.5 <5 <5 <0.52 05/12/99 7.27 0.374 <0.5 33.3 <5 <0.53 05/12/99 48.2 0.79 <0.5 77.6 <5 <0.54 05/12/99 91.2 2.68 <0.5 256 <5 2.195 05/12/99 54.7 1.7 <0.5 141 <5 0.556
10 05/12/99 37.4 0.976 <0.5 84.7 <5 0.87812 05/12/99 27.2 0.873 <0.5 79.1 <5 0.781A 05/12/99 24.8 0.832 <0.5 71.5 <5 0.605B 05/12/99 80.5 8.51 <0.5 335 <5 0.86C 05/12/99 46.3 0.794 <0.5 79.4 <5 <0.5D 05/12/99 180 326 <0.5 30100 58 9.56E 05/12/99 16.2 205 <0.5 17200 52.9 2.33
1 12/12/99 <0.4 <0.1 <0.5 <0.5 <5 <0.52 12/12/99 36.1 <0.1 <0.5 <0.5 <5 <0.53 12/12/99 53.1 0.739 <0.5 68.1 <5 <0.54 12/12/99 88.6 2.88 <0.5 273 6.17 2.015 12/12/99 63.2 1.31 <0.5 108 <5 0.502
10 12/12/99 40 0.835 <0.5 74.1 <5 0.73712 12/12/99 35.7 0.747 <0.5 67.2 <5 0.952A 12/12/99 48.2 0.82 <0.5 69.8 <5 1.02B 12/12/99 63.2 11.1 <0.5 434 <5 1.19C 12/12/99 44.3 0.664 <0.5 64.6 <5 <0.5D 12/12/99 626 160 <0.5 14400 32.8 4.95E 12/12/99 24.5 214 <0.5 1840 60.3 5.08
Site Date Sampled Lead ppb Cadmium ppb Chromium ppb Zinc ppb Nickel ppb Copper ppb1 02/01/00 <0.4 <0.1 <0.5 <5 <5 <0.52 02/01/00 1.49 <0.1 <0.5 <5 <5 <0.53 02/01/00 44.1 0.652 <0.5 63.7 <5 >0.54 02/01/00 87.5 2.58 1.06 250 <5 2.485 02/01/00 58.8 1.23 0.614 110 <5 0.513
10 02/01/00 51.1 1.45 <0.5 126 <5 0.84212 02/01/00 25.8 0.6 <0.5 56.9 <5 0.69A 02/01/00 68 1.97 <0.5 164 <5 0.517B 02/01/00 56.5 7.96 <0.5 341 <5 <0.5C 02/01/00 54.5 0.706 <0.5 72.2 <5 <0.5D 02/01/00 1190 168 <0.5 15200 37.5 5.18E 02/01/00 13.2 244 <0.5 20600 64.5 4.34
1 09/02/00 0.869 <0.1 <0.5 <5 <5 <0.52 09/02/00 1.17 <0.1 <0.5 <5 <5 <0.53 09/02/00 35.9 0.714 <0.5 71 <5 <0.54 09/02/00 82.3 2.71 <0.5 253 <5 1.555 09/02/00 44 1.35 <0.5 122 <5 <0.5
10 09/02/00 51.8 0.958 <0.5 83.7 <5 0.8412 09/02/00 28.9 0.755 <0.5 67.3 <5 0.582A 09/02/00 22.8 0.723 <0.5 60.1 <5 <0.5B 09/02/00 87.9 8.19 <0.5 358 <5 0.629C 09/02/00 44.1 0.781 <0.5 76.4 <5 <0.5D 09/02/00 198 129 <0.5 11400 25.4 1.55E 09/02/00 17.2 230 <0.5 9.66 62.3 2.92
Site Date Sampled Lead ppb Cadmium ppb Chromium ppb Zinc ppb Nickel ppb Copper ppb1 30/02/00 0.584 <0.1 <0.5 >5 >5 <0.52 30/02/00 22.1 0.629 <0.5 54.8 >5 <0.53 30/02/00 51 0.662 <0.5 65.6 >5 <0.54 30/02/00 137 2.88 3.6 273 >5 1.65 30/02/00 90.1 1.73 <0.5 136 >5 0.882
10 30/02/00 41.8 1.1 <0.5 96.8 >5 <0.512 30/02/00 27.2 0.59 0.65 54.5 >5 0.929A 30/02/00 48.5 1.08 <0.5 94.5 >5 0.895B 30/02/00 153 4.82 <0.5 264 >5 0.89C 30/02/00 49.3 0.673 <0.5 66.2 >5 0.612D 30/02/00 320 80.4 9.5 6690 11.9 3.02E 30/02/00 10.7 226 <0.5 19800 57.7 3.85
1 06/02/00 <0.4 <0.1 <0.5 <5 <5 <0.52 06/02/00 24.4 0.552 <0.5 44.1 <5 <0.53 06/02/00 64.3 0.721 <0.5 69.9 <5 <0.54 06/02/00 92.4 2.59 <0.5 258 <5 1.255 06/02/00 66.9 1.26 <0.5 106 <5 0.549
10 06/02/00 65.4 0.934 <0.5 79.6 <5 0.99912 06/02/00 39.5 0.56 <0.5 50.5 <5 0.907A 06/02/00 55.3 1 <0.5 77.5 <5 0.567B 06/02/00 76.5 6.6 <0.5 285 <5 0.671C 06/02/00 44.6 0.584 <0.5 59.2 <5 <0.5D 06/02/00 366 86.8 <0.5 7850 17.7 4.5E 06/02/00 10.2 226 <0.5 20500 53.1 3.88
Site Date Sampled Lead ppb Cadmium ppb Chromium ppb Zinc ppb Nickel ppb Copper ppb1 27/02/00 4.23 0.471 <0.5 6.32 <5 1.032 27/02/00 44.1 11.8 <0.5 13.1 <5 1.293 27/02/00 250 100 <0.5 75.6 <5 1.244 27/02/00 441 342 <0.5 340 <5 1.335 27/02/00 550 81.8 <0.5 104 <5 2.16
10 27/02/00 271 39.5 0.543 50.2 <5 2.0712 27/02/00 172 20.6 0.539 48.5 <5 2.77A 27/02/00 262 38.4 <0.5 49.6 <5 2.58B 27/02/00 2080 67.1 <0.5 432 <5 3.92C 27/02/00 233 43.2 3.94 78.7 <5 1.15D 27/02/00 8590 287 3.94 9110 46.8 54.4E 27/02/00 46.4 12.5 <0.5 17700 53.4 5.24
103 John Robert Maxwell
Appendix F – Rainfall readings taken in Glenridding at NGR NY 381172
Date Oct1999
Nov1999
Dec1999
Jan2000
Feb2000
Mar2000
Apr2000
May2000
Jun2000
July2000
Aug2000
Sep2000
1 18 13 21 4 22 6 0 0 0 0 16 252 38 31 18 2 10 12 1 0 0 1.5 16 4.53 10 12 71 15 3 50 9 0 17 12 7 24 2 20.5 16.5 8 9 2 1 0 4 0 1 05 0 53 2 19 5 0 0.5 0 7 0 0 06 0 40 32 40 10 7 0 0 3.5 1 1 187 2 1 43 8 14 11 0 0 4.5 9 0 18 7 2 21 35 30.5 18 0 0 6 1 1 119 2 1 79 5 10 30 2 0 0.5 10.5 0 3
10 1 0 17 1 45 1 0 0 0 23.5 9 611 4 0 11 13 2 3 7 0 0 1 1 412 1 0 15.5 60 25 0 6 0 2 0 0 013 0 0 5.5 10 1.5 1 6 0 2 1 9 214 0 0 0 1 0 2 5 0 2 2 12 215 0 0 0 0 5 2 0 0 0 0 0.5 216 0 5 1 0 25 2 0 0 5 0 9 3.517 0 0 32 0 2 0 6 16 0 0 6 018 0 0 0 0 9 0 6 22 0 0 9 1719 0 0 0 1 15 0 3 12 24 0 18 120 0 1 0 1 0 0 28 3 2.5 0 2 3821 0 0 12 1.5 16 0 17 2 0.5 0 2 022 17 0 3 4 1 1.5 10 0 0 0 7.5 2323 12 3 38 0 1.5 0 7 0 0 0 0 624 14 14.5 66 1 9 24 1 8 0 0 0 125 12 0 37 1 6 6 7 1.5 0 0 0 4526 2 27 20 0 2 0 10 5 0 0 7 327 0 10 15.5 1.5 52 0 13 13.5 15 0 5 19.528 9 38 1 10 32 0 3 0 13 1 0 3729 1 52 0 38 25 0 0 2.5 4 0 0 330 5 7 6 5 0 0 0 3 0 0 231 17 0.5 33 0 4 1 0
Total 174 331 584.5
318 387.5 178.5 148.5 89.5 115.5 64.5 139 279.5
Yearly total= 2810