InPlant TrainingA brief account on…

By-Abhishek Bharti

Page 2: Road, Culvert & Bridge Training

Length Of Road= 79 km

A Road Project was going on underR.C.D. , Giridih

No. Of Culverts = 44

No. Of Bridges = 2

Widening and Strengthening of Kowar

Kodarma Road• The Road Passes through many thickly populated villages.• Width of the existing crust is 3 m.• Which is to be widened up to 7 m.• The improvement of this road will uplift the social and economic condition of the area.

Page 3: Road, Culvert & Bridge Training

A typical road section consists of four layers-

The materials used in the above layers has to go through various quality control checks

•Granular Sub Base (GSB)•Wet Mix Macadam (WMM)•Bituminous macadam (BM)•Semi dense bituminous concrete (SDBC)

Page 4: Road, Culvert & Bridge Training

Some of the tests that are done to ensure good quality of the road are-

Water Absorption testAggregate Impact testFlakiness IndexSieve analysisBitumen content test

Page 5: Road, Culvert & Bridge Training

Designing of Pavement

A traffic census had been conducted previously at three points on the road continuously for 7 days to get average daily traffic. Number of CV/day is obtained from it, denoted by ‘P’

Cumulative Traffic is found out as given in IRC 37 -2001.From the Cumulative Traffic, and known CBR value ; we use the Pavement design Catalogue and obtain thickness of all the layers required in the Road.

N = {365*(1+r)^n -1} *D*F*P(1+r)^x r

Page 6: Road, Culvert & Bridge Training

The portion to be widened beyond the existing crust was excavated using the excavator.

Page 7: Road, Culvert & Bridge Training

The GSB was brought from the mixing plant in Dumpers and Dumped at the Site. It was then spread uniformly with the Motor Grader

• The GSB was then compacted in layers such that each layer did not exceed 100 mm compacted thickness.• Next the layer of WMM was spread over the GSB and was compacted in layers.• To fill the voids remaining, stone dust was used, rolling was continued until no more dust could be forced into the voids.•Sprinkling of water is done with continued rolling to obtain well bounded and firmly set surface.

Page 8: Road, Culvert & Bridge Training

Compacted WMM is allowed to completely dry and set before the next pavement is laid.

Page 9: Road, Culvert & Bridge Training

Surface of WMM is swept clean and dust is blown of using compressed air. Once the surface is clean, the Prime coat is sprayed over the surface using sprayer. The surface is allowed to cure for 24 hours.

After 24 hours the Tack coat or binder is uniformly sprayed over the surface. Emulsion is used as binder shall have temperature 20 c to 50 c.

Page 10: Road, Culvert & Bridge Training

Immediately after spraying the tack coat, the layer of BM is laid over it. The BM is brought at site by a Dumper, at that time the temperature of BM should be 120 c.

The Dumper is slowly tilted over the Rack of the Paving machine while both paver and dumper slowly moves forward.

Page 11: Road, Culvert & Bridge Training

The conveyor Belt arrangement in the Paver and leveling plate spreads the BM neatly behind as both Dumper and paver moves forward. The Camber is provided by adjusting the leveling plate.

Page 12: Road, Culvert & Bridge Training

Paving is accompanied with rolling. Any high spots or depressions noticed are corrected by removing or adding material and rolling done over it again. Water is sprinkled over roller wheels to prevent sticking of materials to it.

Rolling must be complete before the temperature of BM falls below 90 c

Page 13: Road, Culvert & Bridge Training

A tack coat is again applied over the BM course. The top wearing course of SDBC is also applied with the same process as BM.

Tolerance level for BM = 6mmTolerance level for SDBC = 4 mm

The rolling is done as such each pass overlaps with at least one third of the track made in preceding pass.

The layer of SDBC is immediately sprinkled with Stone Dust to prevent the sticking of materials to shoes or wheels.Traffic is allowed 24 hours after laying SDBC

Page 14: Road, Culvert & Bridge Training

Hot Thermoplastic compound is used for marking, which is laid with the help of a Road Marking Machinery.Thermoplastic material is homogenously composed of pigments, reflecting glass beads and resins.

Binder - 18%Glass beads - 40 %Titanium dioxide - 10%Calcium carbonate - 42%

Page 15: Road, Culvert & Bridge Training

Mostly two types of culverts were constructed along the road. RCC Culvert and Stone Masonry Culvert.

A culvert is a structure that allows waterto flow under a road

Page 16: Road, Culvert & Bridge Training

First excavation pit for the Foundation slab was dug. Foundation slab for both the abutments were casted as one unit.

Series of parallel bars 8 mm dia @ 200 mm c/c are laid on the slabFirst 400 mm of the bar is made to rest on the slab and rest part is folded above at right angles.These bars are called Skin Reinforcement.Formwork for further casting of substructure is fixed.Casting is done in two layers of 200 mm, hence casting of 400 mm was done in one day.

Page 17: Road, Culvert & Bridge Training

According to the shape of the abutment, the skin reinforcements were bent at the desired angle where ever necessary , fixing of formwork and casting was done as usual.

Page 18: Road, Culvert & Bridge Training

At 0.5 m above the ground level, weep holes are provided.Weep holes drain the water that accumulates on either side of the abutment. Diameter of weep holes = 75 mm @ 1m c/c

The construction till Dirt wall is completed in following the usual procedure.

Page 19: Road, Culvert & Bridge Training

Lets see how Stone masonry Culvert was completed till here.

Stone Masonry Culverts are built where good quality stones are readily available. Stones of standard size are joined using mortar one by one.

Page 20: Road, Culvert & Bridge Training

• A string is stretched along the length of the culvert which is used to keep the alignment of the stones correct while placing them. •The stones are placed at the edges first, the flat surface of the stone is kept facing outward to get a good finished surface.

• Weep Holes are provided in the same way as in RCC Culvert.Dirl wall is also made up of stones, smaller size of stones are used in it.

Page 21: Road, Culvert & Bridge Training

After construction till dirt wall is complete, the process for further construction in both types of Culvert is same.

o The reinforcement for the abutment cap is tied and form work is fixed.o Then casting of abutment cap is done.

Page 22: Road, Culvert & Bridge Training

o Abutment cap is cured for at least 1 week then the formwork for slab is fixed.o The reinforcement for slab is tied while keeping the necessary camber.o Concreting of slab is done as usual.o The slab is now cured for 28 days

Page 23: Road, Culvert & Bridge Training

A new bridge was proposed at 16th km of the road over the Irga river

• The old bridge was narrow, damaged and insufficient to carry present traffic load.• It was a five span bridge with total length 123 m.• Hard strata was found at a depth of 20 m• The construction was just started and the location of first pile was well marked.• A metal sheet was folded with the help of a machine into a desired diameter of 1.2 m.• This metal cylinder was used as a casing for the pile

Page 24: Road, Culvert & Bridge Training

• A large tripod is centered over the point of piling• The cylinder is driven at that point and water is filled to make the strata loose.• Next a pile hammer is mounted over the tripod with a system of pulley and cables.• The diameter of the hammer is just enough to fit in the casing.• The hammer is then constantly made to drop from a height of 5 m inside the casing.• This breaks the strata below.

Page 25: Road, Culvert & Bridge Training

• When enough strata is broken down, the mud collected inside the pile gutter, is taken out with the help of one way valve.• This process is continued and it takes near about 5 days to complete the excavation of 20 m.

Page 26: Road, Culvert & Bridge Training

• The reinforcement bars are then tied• 30 bars of 25 mm dia were provided as main steel• Helical Stirrups are provided of dia 10 mm with a spacing of 150 mm c/c.• This reinforcement is then placed inside the pile casing with the help of a crane.• Concrete is then placed inside the pile with Tremie method.•The tremie pipes are coupled together and inserted inside the pile.•It is fitted with a Hopper on top.

Page 27: Road, Culvert & Bridge Training

•The concrete is placed on the top of the Hopper.• whole length of pipe is filled with concrete.• The tremie pipe is lifted up and a slight jerk is given by pulley and cable arrangement.• The concrete gets discharged in the pile, the end of the tremie pipe remains dipped in the concrete so no mud enters the tremie pipe.• This method is continued until concreting for whole of the pile is complete.•The concrete does not get affected due to mud except the top layer.

Page 28: Road, Culvert & Bridge Training