riverside-corona feeder acoustical impact analysis h...exception of unique crossings (e.g., railroad...

91
ACOUSTICAL IMPACT ANALYSIS RIVERSIDE-CORONA FEEDER PROJECT Prepared For: Western Municipal Water District 450 Alessandro Avenue Riverside, CA 92508 Contact: Jack Safely Prepared by: Albert A. Webb Associates 3788 McCray Street Riverside, CA 92506 Contact: Mike Rosa, Associate Environmental Technician September 23, 2009

Upload: others

Post on 01-Mar-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

ACOUSTICAL IMPACT ANALYSIS

RIVERSIDE-CORONA FEEDER PROJECT

Prepared For:

Western Municipal Water District 450 Alessandro Avenue

Riverside, CA 92508 Contact: Jack Safely

Prepared by: Albert A. Webb Associates

3788 McCray Street Riverside, CA 92506

Contact: Mike Rosa, Associate Environmental Technician

September 23, 2009

Page 2: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

i WEBB A L B E R T A. A S S O C I A T E S

TABLE OF CONTENTS SECTION 1 – Executive Summary ............................................................................................. 1 

Findings ....................................................................................................................................... 1 Conclusions .................................................................................................................................. 1 

SECTION 2 – Project Description .............................................................................................. 3 SECTION 3 – Setting .................................................................................................................... 5 

Acoustical Basics ......................................................................................................................... 5 Project Site – Existing Conditions ............................................................................................... 7 Applicable Noise Standards ......................................................................................................... 9 

SECTION 4 – On-Site Construction-Related Noise Levels .................................................... 15 SECTION 5 – Conclusions ......................................................................................................... 29 SECTION 6 – References ........................................................................................................... 30 

References Cited ........................................................................................................................ 30 Document Preparation Staff ...................................................................................................... 31 

List of Figures Figure 1, Proposed Project ........................................................................................................... 4 Figure 2, Typical Decibel Level of Common Sounds .................................................................. 6 Figure 3, Noise Contours for Project Construction – Central Reach (Northern Portion) .......... 19 Figure 4, Noise Contours for Project Construction – Central Reach (Central Portion) ............. 20 Figure 5, Noise Contours for Project Construction – Central Reach (Southern Portion) .......... 21 Figure 6, Noise Contours for Project Construction – Central Feeder Connection ..................... 22 Figure 7, Noise Contours for Project Construction – La Sierra Pipeline ................................... 23 Figure 8, Noise Contours for Project Construction – Mockingbird Connection ........................ 24 Figure 9, Noise Contours for Project Construction – Clay Street Connection – Booster Site 1 .............................................................................................................. 25 Figure 10, Noise Contours for Project Construction – Clay Street Connection – Booster Site 2 .............................................................................................................. 26 Figure 11, Noise Contours for Project Construction – Clay Street Connection – Booster Site 3 .............................................................................................................. 27 Figure 12, Noise Contours for Project Construction – Clay Street Connection – Booster Site 4 .............................................................................................................. 28 List of Tables Table 1, Existing Land Uses of Potentially Affected Properties................................................. 7 Table 2, Land Use Designations of Potentially Affected Properties........................................... 8 Table 3, Applicable Noise Regulations ..................................................................................... 10 Table 4, Anticipated Pipeline Construction Equipment Types and Quantities by Method ...... 15 Table 5, Estimated Construction Equipment Noise Levels at 50 Feet ...................................... 16 Table 6, Noise Contours for Project Construction by Method .................................................. 17 Table 7, Identified Noise Sensitive Receptors Adjacent to Project Alignment ........................ 17

Page 3: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

ii WEBB A L B E R T A. A S S O C I A T E S

Appendices Appendix A – Reference Noise Level Source Information Appendix B – Noise Impact Calculation Printouts

Page 4: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

1 WEBB A L B E R T A. A S S O C I A T E S

SECTION 1 – Executive Summary

This acoustical impact analysis has been performed to determine anticipated noise impacts associated with the proposed Riverside-Corona Feeder Pipeline Realignment project (“project”). The project will be used to deliver water from Riverside and San Bernardino County groundwater basins to communities throughout western Riverside County during drought and emergency periods and when water is otherwise available. The project is an alternative alignment proposed for a portion of the project that was approved in 2005 (Figure 1). The majority of the project involves the construction of pipelines that will be located underground and primarily within existing road rights-of-way. Additional components include pump stations (contained within masonry block enclosures) and a reservoir (i.e., tank). The project site is located within the boundaries of the cities of Colton, Redlands, Rialto, Riverside, and San Bernardino, and unincorporated areas of the counties of Riverside and San Bernardino. Once the project is operational, there are no activities associated with its ongoing use that are anticipated to cause potential adverse noise impacts, apart from periodic maintenance and possible repair work. Impacts from the on-site construction activities are the only anticipated sources of potentially significant noise from the project.

Findings

This acoustical analysis indicates that there will be no operational or long-term noise associated with the project; therefore, construction noise is the only anticipated potentially significant noise source. The project site will traverse five city jurisdictions and two unincorporated county jurisdictions. Construction noise is exempt from regulation in all of these jurisdictions. Exemptions for the two county jurisdictions include limitations under which construction activities can take place, such as the proximity of the construction activity to sensitive receivers, hours of the day that construction activity cannot take place, and/or days on which construction activity cannot take place (e.g., Sundays and/or federal holidays).

Conclusions

Although activities from project construction are likely to increase the overall noise level in the vicinity of the project site, construction-related noise is temporary in nature. While noise from the project’s construction period is exempt from regulation under provisions made by the affected jurisdictions, this report includes analysis of potential worst-case noise levels expected to be generated during the construction phase. Most of the construction work will be performed within existing road rights-of-way. Three primary methods will be employed during the construction process: boring, excavation, and microtunneling.

Page 5: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

2 WEBB A L B E R T A. A S S O C I A T E S

Noise contours are provided in this report (Table 6 and Figures 3, 4, and 5) to help identify potentially impacted land uses. The noise contours indicate worst-case distances to which the 60, 65, 70, and 75 dBA Leq noise impacts could extend from the center of the construction activity, not including the attenuating effects of topography or intervening structures and/or foliage. Specific existing noise-sensitive uses along the project’s alignment, that are located within the anticipated noise contours, include: schools, residences, churches, hospitals, day care centers, and medical clinics. Figures 3, 4, and 5 identify many of these noise sensitive uses.

Page 6: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

3 WEBB A L B E R T A. A S S O C I A T E S

SECTION 2 – Project Description

Western Municipal Water District (WMWD) was formed in order to bring supplemental water to western Riverside County, and currently serves wholesale customers and approximately 24,000 direct retail connections. WMWD’s service area encompasses the cities of Riverside, Norco, Corona, and portions of Murrieta, Temecula, and the communities of Jurupa, Rubidoux, and Elsinore Valley. The WMWD’s service area also includes the Lee Lake Water District, the Box Springs Mutual Water Company, and the Eagle Valley Mutual Water Company. WMWD’s service area consists of 527 square miles and a population of more than 853,000. The project is a proposed pipeline and associated facilities (i.e., pump stations and reservoir) that will be used to deliver water from Riverside and San Bernardino County groundwater basins to communities throughout western Riverside County during drought and emergency periods and when water is otherwise available. The completed project will be located underground with the exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project, the project site is located within the boundaries of the cities of Colton, Redlands, Rialto, Riverside and San Bernardino, and unincorporated areas of the counties of Riverside and San Bernardino. The project is separated into two portions referred to as the northern reach and the central reach. The northern reach will span from near the intersection of Waterman Avenue and Orange Show Road, in the city of San Bernardino, traversing through portions of the cities of Colton and Rialto and unincorporated San Bernardino County, into unincorporated Riverside County along Agua Mansa Road. The alignment then traverses west through unincorporated Riverside County, then south in Clay Street and crosses under the Santa Ana River near Van Buren Boulevard. South of the Santa Ana River, the alignment enters the city of Riverside, where it continues in a south/southeasterly direction and connects to an alignment (approved as part of another project) near the intersection of Jackson Street and Cleveland Avenue. The project also includes facilities located within unincorporated San Bernardino and Riverside counties and the cities of Redlands and Riverside that would connect the project to other facilities. The project also proposes an alternate alignment on the southern leg of the central reach. The alternative alignment would change the proposed realignment between the intersection of Jackson Street and Colorado Avenue, in the city of Riverside, and the intersection of Cleveland Avenue and Irving Street, in the city of Riverside. The alternative alignment of the southern leg would be within the right-of-way of a portion of Colorado Avenue and Monroe Street, instead of within the Jackson Street right-of-way. The proposed realignment will be constructed primarily in the rights-of-way of existing roads, under I-10, I-215, State Route 60 and State Route 91, and under the Santa Ana River and other lesser creeks and drainages. The proposed project will affect properties in several jurisdictions with a variety of land use and zoning designations.

Page 7: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

SAN BERNARDINO COUNTYRIVERSIDE COUNTY

RIVERSIDE POINTOF CONNECTION

RIVERSIDE POINTOF CONNECTION

JCSD POINT OFCONNECTION

JCSD/RCSD POINT OF CONNECTION

WELLFIELDS

SBVMWD METER & TURNOUT

CONNECTIONTO SBVMWD

JCSD-2TURNOUT

TURNOUT No. 3MOCKINGBIRDPUMP STATION

TURNOUT No. 4ARLINGTONPUMP STATION

TURNOUT No. 5

Reach HReach F

Reach E

Northern Reach

Central Reach

Central FeederConnection

Clay StreetConnection

MockingbirdConnectionLa Sierra

Pipeline

Iowa

Ave

UCR

Orange Show Rd

Washington St

Spring St

Hunt

s Ln

Spruce St

Irving St

Marlborough Ave

Mt V

erno

n Ave

Alessandro Blvd

Central Ave

Mich

igan A

ve

Chica

go A

ve

Central Ave

Lincoln Ave

Indiana Ave

Madison Ave

Main

St

Van Buren Blvd

6th St

Jackson St

Tyler St

Magnolia Ave

Ontario Ave

La Sierra Ave

Leste

r Ave

Dufferin St

Victoria Ave

Palmyrita Ave

Adams St

Arlington Ave

Mockingbird Canyon Rd

Fillmore St

Cleveland Ave

Jefferson St

Valley Blvd

Ranc

ho A

ve

Rubido

ux Blvd

Hamn

er A

ve

4th Ave

Sierra

Ave

Magnolia Ave

Central Ave

La Sierra Ave

Mission Ave

Water

man

Ave

Pierce St

Arlington Ave

Doolittle Ave

Van B

uren

Blvd

Indiana Ave

Clay

St

Limonite Ave

Avalon

St

30th St

Market St

Agua Mansa Rd

N St

La

Cade

na

Dr

Sper

ry D

r

Fairway DrAuto

Plaza

Dr

Monroe St

Colorado Ave

CITY OFCORONA

CITY OFNORCO

CITY OFMORENO VALLEY

CITY OFPERRIS

CITY OFRIVERSIDE

CITY OFGRAND TERRACE

CITY OFCOLTON

CITY OFRIALTO

CITY OFSAN BERNARDINO

CITY OFLOMA LINDA

CITY OFFONTANA

CITY OFONTARIO

CITY OFREDLANDS

0 5,000 10,000 15,000Feet

LEGENDR-C Feeder - Northern ReachR-C Feeder - Central ReachRC Feeder Monroe AlternativeR-C Feeder Alignment (to Remain)(Reaches E - H)SBVMWD Pipeline (Existing)Arlington Desalter Pipeline(Primarily Existing)La Sierra Pipeline (Not Constructed/Not a Part)R-C Feeder - La Sierra PipelineAlternative AlignmentsMills Pipeline (Existing)EVMWD Pipeline (Existing)FreewayRoadsCity BoundariesCounty Line

Map revised Sept. 29, 2009. G:\2007\07-0377\Gis\noise_prop_alignment.mxd

Figure 1Proposed ProjectAlignment

Page 4

Page 8: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

5 WEBB A L B E R T A. A S S O C I A T E S

SECTION 3 – Setting

Acoustical Basics

Sound is mechanical energy transmitted by pressure waves in a compressible medium such as air. Noise is generally defined as unwanted or objectionable sound. The effects of noise on people can include general annoyance, interference with speech communication, sleep disturbance, and, in the extreme, hearing impairment. Sound is characterized by various parameters that describe the rate of oscillation of sound waves, the distance between successive troughs or crests, the speed of propagation, and the pressure level or energy content of a given sound wave. In particular, the sound pressure level has become the most common descriptor used to characterize the loudness of an ambient sound level. The unit of measurement used to describe a noise level is the decibel (dB). The human ear is not equally sensitive to all frequencies within the sound spectrum. Therefore, the "A-weighted" noise scale, which weights the frequencies to which humans are sensitive, is used for measurements. Noise levels using A-weighted measurements are written dBA, dB (A), or sometimes just dB. Decibels are measured on a logarithmic scale which quantifies sound intensity in a manner similar to the Richter scale used for earthquake magnitudes. Thus, a doubling of the energy of a noise source, such as the doubling of traffic volume, would increase the noise level by 3 dB; a halving of the energy would result in a 3 dB decrease. A 10 dB increase represents a 10-fold increase in sound intensity, a 20 dB change is a 100-fold difference, 30 dB is a 1,000-fold increase, etc. Any further reference to decibels written as “dB” or “dBA” within this study should be understood to be A-weighted. Figure 2, Typical Decibel Level of Common Sounds shows the relationship of various noise levels to commonly experienced noise events. Average noise levels over a period of minutes or hours are usually expressed as dBA Leq, or the equivalent noise level for that period of time. For example, Leq(3) would represent a three hour average. When no period is specified, a one-hour average is assumed. Noise standards for land use compatibility are stated in terms of the Community Noise Equivalent Level (CNEL) and the Day-Night Average Noise Level (Ldn). is a 24-hour weighted average measure of community noise. The computation of CNEL adds 5 dBA to the average hourly noise levels between 7 p.m. and 10 p.m. (evening hours), and 10 dBA to the average hourly noise levels between 10 p.m. and 7:00 a.m. (nighttime hours). This weighting accounts for the increased human sensitivity to noise in the evening and nighttime hours. Ldn is a very similar 24-hour weighted average, which weights only the nighttime hours and not the evening hours. CNEL is normally about 1 dBA higher than Ldn for typical traffic and other community noise levels.

Page 9: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

6 WEBB A L B E R T A. A S S O C I A T E S

Figure 2 Typical Decibel Level of Common Sounds

Source: California Airport Land Use Planning Handbook (January 2002), Page 6-5

Page 10: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

7 WEBB A L B E R T A. A S S O C I A T E S

Project Site – Existing Conditions

The project site is located within the boundaries of the cities of Colton, Redlands, Rialto, Riverside, and San Bernardino, and unincorporated areas of the counties of Riverside and San Bernardino. The project also proposes an alternate alignment, for its southern leg located in the city of Riverside. The project alignment, and the alternate alignment, would traverse several types of existing and planned land uses. Table 1, Existing Land Uses of Potentially Affected Properties provides a summary of existing land uses which have the potential to be impacted by noise from the project.

Table 1 Existing Land Uses of Potentially Affected Properties

Project Component1 Jurisdiction Existing Land Use(s)

Northern Reach City of San Bernardino Commercial Northern Reach City of Colton Commercial, Residential, Retail Northern Reach City of Rialto Industrial Northern Reach San Bernardino County Industrial Northern/Central Reach Riverside County Residential, Commercial

Central Reach City of Riverside Commercial, Residential, Retail, Institutional and Park

Central Feeder Connection

San Bernardino County, City of Redlands

Agricultural, Residential, Industrial

Clay Street Connection Riverside County Residential, Commercial, Industrial

Mockingbird Connection

Riverside County, City of Riverside Agricultural, Residential

La Sierra Pipeline Riverside County Residential 1 As identified on Figure 1, presented earlier in this report. As indicated in Table 1 above, the project will traverse existing land uses that include residential, commercial, retail, institutional, park, and industrial uses. Table 2, Land Use Designations of Potentially Affected Properties provides a summary of jurisdictional land use designations, as indicated in each agency’s respective general plan, which have the potential, once built out, to be impacted by noise from the project.

Page 11: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

8 WEBB A L B E R T A. A S S O C I A T E S

Table 2 Land Use Designations of Potentially Affected Properties1

Project Component2 Jurisdiction Designated Land Use(s) Northern Reach City of San

Bernardino Industrial Light, Publicly owned Flood Control, Commercial Regional-4 Auto Plaza

Northern Reach City of Colton

Industrial Park, Open Space, General Commercial, High Density Residential, Heavy Industrial, Medium Density Residential, Low Density Residential, Specific Plan

Northern Reach City of Rialto General Commercial, Light Industrial, Community Commercial

Northern Reach San Bernardino County

AM/SP (Agua Mansa Specific Plan)

Northern/Central Reach

Riverside County

Heavy Industrial, Public Facilities, Light Industrial, Commercial Retail, Medium Density Residential, Very High Density Residential, High Density Residential, Medium High Density Residential, Open Space-Recreation, Commercial Office, Business Park, Open Space - Water

Central Reach City of Riverside

Open Space/Natural Resources, Public Facilities/Institutional, Commercial, Business/Office Park, High Density Residential, Mixed Use-Village, Medium High Density Residential, Medium Density Residential, Public Park, Office, Medium High Density Residential, Agricultural/Rural Residential, Very High Density Residential

Central Feeder Connection

San Bernardino County

EV/SD (East Valley Area Plan/Special Development), EV/CG (East Valley Area Plan/General Commercial)

Central Feeder Connection

City of Redlands

Commercial, Low Density Residential, Agriculture

Clay Street Connection

Riverside County

Business Park, Medium Density Residential, Commercial Retail, Low Density Residential, Public Facilities

Mockingbird Connection

Riverside County

Very Low Density Residential, Open Space – Conservation

Mockingbird Connection

City of Riverside

Agricultural, Rural Residential

La Sierra Pipeline Riverside County

Low Density Residential, Rural Mountainous, Open Space – Conservation, Open Space – Recreation, Agriculture, Medium Density Residential, Rural Residential

1 As shown in each agency’s respective general plan. 2 As identified on Figure 1, presented earlier in this report.

Page 12: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

9 WEBB A L B E R T A. A S S O C I A T E S

As indicated in Table 2 above, the majority of the northern reach is located in areas designated as commercial and industrial land uses. The central reach will encounter a more diverse set of designated land uses which include residential and other noise sensitive uses.

Applicable Noise Standards

As discussed previously in this report, the completed project will be located primarily underground; above-ground project facilities, such as reservoirs and fully enclosed pump stations, will not be sources of adverse noise. Once completed, the project will be unmanned (apart from periodic maintenance and possible repair work) and there will be no operational noise associated with its use. Therefore, the noise standards that apply to this project are only those pertaining to temporary construction-related activities. The project site is located within the boundaries of the cities of Colton, Redlands, Rialto, Riverside, and San Bernardino, and unincorporated areas of the counties of Riverside and San Bernardino. Table 3, Applicable Noise Regulations, details the applicable construction-related noise regulations for each of the affected jurisdictions.

Page 13: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

10 WEBB A L B E R T A. A S S O C I A T E S

Table 3 Applicable Noise Regulations

Project Component1 Jurisdiction Applicable Noise Regulation

Northern Reach City of San Bernardino

Municipal Code Chapter 8.54 – Noise Control Section 8.54.060 – Exemptions

H. Construction, operation, maintenance, and repairs of equipment, apparatus, or facilities of park and recreation departments, public work projects, or essential public services and facilities, including, but not limited to, trash collection and those of public utilities subject to the regulatory jurisdiction of the California Public Utilities Commission.

Northern Reach City of Colton

Not applicable.2

Northern Reach City of Rialto

Municipal Code Chapter 9.50 – Noise Control Section 9.50.060 – Exemptions

K. Construction, operation, maintenance, and repairs of equipment, apparatus, or facilities of park and recreation departments, public work projects, or essential public services and facilities, including trash collection and those of public utilities subject to the regulatory jurisdiction of the California Public Utilities Commission.

Northern Reach/Central Feeder Connection

San Bernardino

County

San Bernardino County Development Code Chapter 83.01 – General Performance Standards Section 83.01.080 – Noise

(g) Exempt noise. The following sources of noise shall be exempt from the regulations of this Section:

(3) Temporary construction, maintenance, repair, or demolition activities between the hours of 7:00 a.m. and 7:00 p.m., except on Sundays and federal holidays.

Page 14: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

11 WEBB A L B E R T A. A S S O C I A T E S

Project Component1 Jurisdiction Applicable Noise Regulation

Northern/ Central Reach/Clay Street Connection/Mockingbird

Connection/La Sierra Pipeline

Riverside County

Ordinance No. 847 Section 2 – Exemptions

B. Capital improvement projects of a governmental agency. H. Private construction projects located one-quarter of a mile or more from an inhabited dwelling. I. Private construction projects located within one-quarter of a mile from an inhabited dwelling, provided that:

1. Construction does not occur between the hours of 6:00 p.m. and 6:00 a.m. during the months of June through September, and 2. Construction does not occur between the hours of 6:00 p.m. and 7:00 a.m. during the months of October through May. Exceptions to these standards shall be allowed only with the written consent of the building official.

Page 15: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

12 WEBB A L B E R T A. A S S O C I A T E S

Project Component1 Jurisdiction Applicable Noise Regulation

Central Reach/Mockingbird Connection

City of Riverside

Municipal Code Chapter 7.35 – General Noise Regulations Section 7.35.020 – Exemptions The following activities shall be exempt from the provisions of this title:

E. Right-of-Way Construction. The provisions of this Title shall not apply to any work performed in the City rights-of-way when, in the opinion of the Public Works Director or his designee, such work will create traffic congestion and/or hazardous or unsafe conditions. F. Public Health, Welfare, and Safety Activities. The provisions of this Title shall not apply to construction maintenance and repair operations conducted by public agencies and/or utility companies or their contractors which are deemed necessary to serve the best interests of the public and to protect the public health, welfare, and safety; including but not limited to, trash collection, street sweeping, debris and limb removal, removal of downed wires, restoring electrical service, repairing traffic signals, unplugging sewers, vacuuming catch basins, repairing of damaged poles, removal of abandoned vehicles, repairing of water hydrants and mains, gas lines, oil lines, sewers, storm drains, roads, sidewalks, etc. (Ord. 6917 § 1, 1996; Ord. 6328 § 2, 1996; Ord. 6273 § 1 (part), 1996).

Page 16: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

13 WEBB A L B E R T A. A S S O C I A T E S

Project Component1 Jurisdiction Applicable Noise Regulation

Central Feeder Connection City of Redlands

Municipal Code Title 8 – Health and Safety Chapter 8.06 – Community Noise Control Section 8.06.120 - Exemptions

G. Construction Activity: This chapter shall not apply to noise sources associated with new construction, remodeling, rehabilitation or grading of any property provided such activities take place between the hours of seven o’clock (7:00) A.M. and six o’clock (6:00) P.M. on weekdays, including Saturdays, with no activities taking place at any time on Sundays or federal holidays. All motorized equipment shall be equipped with functioning mufflers.

1 As identified on Figure 1, presented earlier in this report. 2 The city of Colton has not established performance standards with regards to construction-related noise. There is

currently no ordinance, municipal code or general plan standard established to regulate such noise. Based on a telephone conversation with the city’s planning manager (Andrés Soto) on September 8, 2008, construction-related noise is considered exempt.

As indicated in Table 3 above, the cities of San Bernardino, Rialto, and Riverside specifically consider construction of public works projects exempt from noise regulations; there are no restrictions or requirements placed on said exemptions within these jurisdictions. The city of Colton has not established noise standards that apply to construction-related noise. Therefore, based on a telephone conversation with the city’s Planning Manager (Andrés Soto, September 8, 2008), construction-related noise should be considered exempt since this type of noise is currently not regulated by the city. The city of Redlands and the counties of Riverside and San Bernardino do not regulate the level of noise generated by the construction of a project. However, these jurisdictions do regulate the conditions under which construction activities can take place, such as the proximity of construction activity to sensitive receivers, hours of the day that construction activity cannot take place, and/or days on which construction activity cannot take place (e.g., Sundays and/or federal holidays). Apart from the regulations found in the City of Redlands Municipal Code, listed in Table 3, the City of Redlands has no other regulation (e.g., ordinance, General Plan guideline) that applies to construction-related noise. Therefore, to meet applicable noise regulations within the jurisdiction of the city of Redlands, project construction shall not take place during the hours of 6:00 p.m. and 7:00 a.m., nor during any time on Sundays or federal holidays. Apart from the regulations found in the San Bernardino County Municipal Code, listed in Table 3, San Bernardino County has no other regulation (e.g., ordinance, General Plan guideline) that applies to construction-related noise. Therefore, to meet applicable noise regulations within the

Page 17: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

14 WEBB A L B E R T A. A S S O C I A T E S

jurisdiction of unincorporated San Bernardino County, project construction shall not take place during the hours of 7:00 p.m. and 7:00 a.m., nor during any time on Sundays or federal holidays. As shown in Table 3, Riverside County Ordinance No. 847 specifies that construction-related noise is exempt in unincorporated Riverside County, provided that it is located one-quarter of a mile or more from an inhabited dwelling. However, if construction is planned to occur within one-quarter mile of an inhabited dwelling, construction activities shall not take place between the hours of 6:00 p.m. and 6:00 a.m. during the months of June through September or between the hours of 6:00 p.m. and 7:00 a.m. during the months of October through May. Additionally, Ordinance No. 847 allows for exceptions to these restraints with written consent from the Director of Building and Safety.

Page 18: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

15 WEBB A L B E R T A. A S S O C I A T E S

SECTION 4 – On-Site Construction-Related Noise Levels

The affected jurisdictions recognize that construction noise is difficult to control and have therefore established exemptions, or exemptions with conditions, to allow for this potential intrusion. Although construction is considered exempt, or qualifies for exemption, from noise regulation in all of the affected jurisdictions, potential worst-case noise levels associated with project construction are analyzed and discussed in this section. The overall size of the project and the lack of construction-timing details made a location-specific noise analysis infeasible at the time that this analysis was performed. Therefore, noise levels were calculated using worst-case assumptions, and are presented as noise contours that can be applied to the various locations that the project will pass through. This section presents anticipated worst-case construction-related noise levels. Project pipeline construction will involve three main types of methods: boring, excavation, and microtunneling. Each of these methods will involve various types and quantities of equipment. The boring method will be used in areas where the pipeline will cross under major intersections, freeways, or the Santa Ana River; the excavation method will be used in areas where the “open cut trench” technique is feasible (i.e., within street rights-of way); and the microtunneling method will be used as an alternative to the boring or excavation methods where site conditions (e.g., traffic, groundwater, rock, etc.) make microtunneling more cost effective. Construction of the reservoir and pump stations will employ more typical methods and equipment (e.g., backhoe, excavator, etc.). None of the affected jurisdictions’ general plans include reference data for noise levels at a given distance from typical construction methods, such as that anticipated for the reservoir and pump stations. However, assuming construction activities were to occur for 8 hours a day, the CNEL is calculated at 84 dBA at 50 feet from the source, placing the 65 dBA CNEL contour at a distance of about 446 feet. Table 4, Anticipated Pipeline Construction Equipment Types and Quantities by Method itemizes the types and quantities of equipment anticipated to be used for each of the activities, based upon currently available data.

Table 4 Anticipated Pipeline Construction Equipment Types

and Quantities by Method1

Construction Equipment Type

Approximate Quantity Needed for Construction Method

Boring Excavation Microtunneling Backhoe/Loader 1 3 1 Compressor - - 2 - - Crane 1 1 1 Excavator - - 2 - - Generator 2 - - 2 1 This information is based upon preliminary data available during the analysis.

Page 19: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

16 WEBB A L B E R T A. A S S O C I A T E S

Based upon reference noise levels (see Appendix A for source information) Table 5, Estimated Construction Equipment Noise Levels at 50 Feet, presents the estimated individual noise levels produced by the equipment anticipated to be used for pipeline construction, at a uniform distance of 50 feet.

Table 5 Estimated Construction Equipment Noise Levels at 50 Feet 1

Construction Equipment Type

Noise Level at 50 Feet

(dBA Leq) Backhoe/Loader 80 Compressor 80 Crane 85 Excavator 85 Generator 82

1 See Appendix A for reference noise level data and source. Based upon the estimated construction equipment quantities provided in Table 4 and the reference noise levels provided in Table 5, noise contours have been determined for the three pipeline construction methods that are anticipated to be employed. To present a worst-case scenario, those noise contours represent the combined noise level for all of the equipment estimated to be used for each method of pipeline construction, and assumes that every piece of that equipment will be running simultaneously and continuously. Various conditions will be encountered that can be factors in noise propagation. One factor is the height from which the source of the noise is emanating. This factor will be constantly changing throughout the construction process as some of the work will take place below-ground, while other parts of the work will take place above-ground. For the purposes of this analysis, all source noise was modeled above-ground to, again, best represent a worst-case scenario. Another factor affecting noise impacts is the absorptive properties of the surrounding landscape (natural and manmade) that intervenes between a noise source and receiver. The sound-attenuating properties of topography, foliage, ground cover, weather, and existing buildings/barriers were not accounted for in this analysis. Therefore, distances presented in the noise contours are modeled on a hypothetical flat-plane with no obstructions, thereby, considerably overstating probable noise impacts. The noise contours, detailed in Table 6, Noise Contours for Project Construction by Method, estimate worst-case distances from the noise source to the 75, 70, 65, and 60 dBA Leq contours. Sensitive receptors located within the 75 dBA Leq contour will experience periodic noise levels that may exceed 75 dBA.

Page 20: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

17 WEBB A L B E R T A. A S S O C I A T E S

Table 6 Noise Contours for Project Construction by Method 1

Construction Method Type

Distance to Noise Level (in feet) 75 dBA Leq 70 dBA Leq 65 dBA Leq 60 dBA Leq

Boring 240 430 760 1,350 Excavation 340 600 1,075 1,900 Microtunneling 240 430 760 1,350 Standard Construction2 141 250 446 790 1 See Appendix B for printouts of calculations that determined noise levels. 2 Applies to reservoir and pump station construction.

Figures 3 through 12 graphically depict the contour data provided in Table 6. The graphic noise contours were only mapped for the portion of the project referred to as the “Central Reach” which is expected to begin construction within the next two years and projected to be completed by 2013, and for the Central Feeder Connection, Clay Street Connection, La Sierra Pipeline, and Mockingbird Connection. Construction of the “Northern Reach” of the proposed project may not begin for approximately ten years and current mapping of the noise contours for the Northern Reach may not accurately reflect the locations of any sensitive receptors that would exist at the time that construction begins; therefore, the Northern Reach noise contours have not been mapped. New data identifying sensitive receptors should be collected prior to construction of the Northern Reach in order to produce noise contours that reflect conditions at that time. Also indicated on some of the figures are existing noise sensitive receptors nearest to the project’s alignment. These sensitive receivers are identified on the figures by a number which correlates with the existing noise sensitive receptors listed in Table 7, Identified Noise Sensitive Receptors Adjacent to Project Alignment. The data provided in Table 7 was compiled on October 16, 2008 via site reconnaissance and is not intended as a complete list of potentially affected land uses, but rather as a means to call attention to those land uses that are clearly noise sensitive and that have the highest potential for significant impacts.

Table 7 Identified Noise Sensitive Receptors Adjacent to Project Alignment 1, 2

Potentially Affected Receptor3 Address 1 Riverside Christian School 3532 Monroe Street, Riverside CA 92504 2 Parkside Village Apartments 3675 Monroe Street, Riverside CA 92504 3 Presidential Townhomes 3680 Monroe Street, Riverside CA 92504 4 Creekside Senior Apartments 4291 Monroe Street, Riverside CA 92504 5 Hope Community Church 9085 Colorado Avenue, Riverside CA 92503 6 Jackson Elementary 4585 Jackson Street, Riverside CA 92503 7 Cypress Garden Convalescent Home 9025 Colorado Avenue, Riverside CA 92503

Page 21: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

18 WEBB A L B E R T A. A S S O C I A T E S

Potentially Affected Receptor3 Address 8 Arlington High School 2951 Jackson Street, Riverside CA 92503 9 Sherman Indian High School 9010 Magnolia Avenue, Riverside CA 92503 10 Andrew Jackson Apartments 3636 Jackson Street, Riverside CA 92503 11 Church of Jesus Christ of Latter Day Saints 3680 Jackson Street, Riverside CA 92503 12 St. Thomas Church 3774 Jackson Street, Riverside CA 92503 13 St. Thomas K-8 School 9136 Magnolia Avenue, Riverside CA 92503 14 Parkview Community Hospital 3865 Jackson Street, Riverside CA 92503 15 Parkview Community Hospital Medical Ctr. 3865 Jackson Street, Riverside CA 92503 16 St. Michaels Church 4070 Jackson Street, Riverside CA 92503 17 Christian Life Center Church & School 9085 California Avenue, Riverside CA 92503 18 Church of Jesus Christ of Latter Day Saints 4375 Jackson Street, Riverside CA 92503 19 Townhomes (w/ Balconies) 4440-4492 Jackson Street, Riverside CA 92503 20 Faith Lutheran Church 4785 Jackson Street, Riverside CA 92503 21 Whispering Fountains of Riverside Apartments 4790 Jackson Street, Riverside CA 92504 22 Encore Senior Village - Alzheimer’s Center 6280 Clay Street, Riverside CA 92509 23 La Petite Academy Day Care 6212 Clay Street, Riverside CA 92509 24 Riverside Medical Clinic 9250 Clay Street, Riverside CA 92509

1 Compiled on October 16, 2008 via site reconnaissance. 2 This is a partial list and is not intended to represent all of the potentially affected land uses. 3 The numbers in this column correlate with the numbers shown on Figures 3 through 5 of this report.

Page 22: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

7

2021

2423

22

75 dB A Leq

65 dBA Leq70 dBA L

eq

60 dBA Leq

7 5 dBA L

eq

65 dB

A Leq

70 d BA Leq

70 dB

A Leq

60 dBA Leq

65 dBA Leq

75 dB

A Leq

LIMONITE

61ST

CLAY

63RD

64TH

56TH

LINARES

54TH

FELS

PAR

TYLE

R

65TH

LAKESIDE

CRES

T

HUDS

ON

BEAC

H

58TH

GOLF

BAKE

RKENNEDY

60TH

AGAT

E

ARCH

ER

REAGAN

MARIA

JURUPA

CORE

Y

YEAR

LING

LAKEVIEW

KIM

GREENS

DOWNE

Y

KELSEY

STON

E

FAGA

N

IDYL

LWILD

BRIAN

TOMAL

59TH CEDA

R

SPUR

STIRRUP

RUTL

AND

LYNN

NATCHEZ

TOWNSEND

CAMI

NO R

EAL

PAISANO

SNOW

GRAS

S

MARTINGALE

SWING

HOMES

TEAD

AULD

STANDISH

TAMARIND

DAVID

CORRAL

ALTADENA

CARLYLE

PALENCIA

LANSING

THUNDER BAY

JULIAN

BRADFORD

STUDIO

CANDLE LIGHT

BRIDLE PATH

VIRTUE VISTA

MAPL

EVIEW

EL PA

LOMI

NO

EUCA

LYPT

US

BIG MEADOW

GRINNELL

STAR VIEW

LEUCADIA

EVENINGSIDE

WHITNEY

NINA

BIG RIDGE

CLUB

HOUS

E

BIRCHWOOD

LAKA

REN

STONE MIST

HELM

CRES

T

JENN

IFER

HIGH PRAIRIE

TAYO

MANITOBA

TUMB

LEWEE

D

CLAU

BART

ROCKFORD

CARDIFF

VAN

BURE

N

PEDL

EY

63RD

58TH

PEDLEY

AGAT

E59TH

CENTRAL

JURUPA

ARLINGTON

CHAL

LEN

ADAMS

COLORADO

MONROE

RUTL

AND

PHILBIN

CYPRESS

ESSEX

CRES

T

JOJO

BRUCE

LAKE

EILEEN

DOOL

ITTLE

FREM

ONT

GEMENDE

PENNY

MIA

ACOR

N

HILLSIDE

CANTEBURY

ADAIR

WILDER

NESS

PAYT

ON

SAINT PAUL

NEIL

JASM

INE

DALES

SYLVAN

CAMELIA

RAINTREE

REES

AIRPO

RT

PALO

S

TREY

PEMBROKE

GLENCOE

BRUNSWICK

DRIFTWOOD

MADRONA

MALIB

U

WARRE

N

SAN VICENTE

DORI

NDA

TOYON

HARO

LD

LOMITA

HOLLY

TEXAS

FARR

IER

ORDW

AY

VERBENA

HOLL

YRID

GE

ZINNIA

SHANNON

FLIGHT

ED PERKIC

GLENHURST

KITTY HAWK

BEGONIA

REPU

BLIC

PHOE

NIX

INDUSTRIAL

BEAU

JANET

ORANGEWOODPARKER

RAMP

OLYM

PIA

GREEN VALLEY

PEGA

SUS

CATALPA

MONT

GOMER

Y

MONTICELLO

60 dB

A Leq

65 dB

A Leq

70 dB

A Leq75

dBA L

eq

70 dB

A Leq

75 dBA Leq

60 dB

A Leq

70 dB

A Leq

65 dB

A Leq

65 dB

A Leq

60 dB

A Leq

60 dB

A Leq

70 dB

A Leq

65 dBA Leq

60 dBA Leq

75 dBA Leq60 dBA Leq

65 dBA Leq

65 dBA Leq

75 dBA Leq

70 dBA Leq

LEGENDExcavation Noise ContoursJack & Bore or Microtunnelling Noise Contours

Proposed Riverside-Corona FeederNorthern ReachCentral ReachRC Feeder Monroe AlternativeR-C Feeder Alignment (to Remain)Sensitive Receptors (see Table 7)

Map created November 29, 2009. G:\2007\07-0377\Gis\NoiseContourMapSeries0909.mxd

RIVERSIDE FREEWAY

VICTORIA

LIMONITE

VAN BUREN

ARLINGTON

MAGNOLIA

ARLINGTON

JURUPA

LIMONITE

MAGNOLIA

0 1,000 2,000 3,000 4,000Feet

Figure 3Noise Contours for Project

Construction - Central Reach(Northern Portion)

Page 19

Page 23: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

9

8

4

32

1

7

6

5

20

19

1312

1110

15

14

17

16

18

21

2423

22

60 dBA Leq

65 dBA Leq70 dBA Leq

60 dBA Leq

75 dB A Leq

70 dBA Leq

65 dBA Leq70 dBA L

eq

60 dBA Leq

75 dBA Leq

65 dB A Leq

7 5 dBA L

eq

70 dBA Leq

65 dB

A Leq

75 dBA Leq

70 d BA Leq

70 dB

A Leq

60 dBA Leq

65 dBA Leq

75 dB

A Leq

75 dBA Leq

75 dBA Leq

LIMONITE

61ST

CLAY

63RD

64TH

LINARES

FELS

PAR

TYLE

R

65TH

LAKESIDE

CRES

T

HUDS

ON

58TH

BAKE

R

KENNEDY

60TH

ARCH

ER

REAGAN

MARIA

JURUPA

CORE

Y

YEAR

LING

LAKEVIEW

DOWNE

Y

KELSEY

IDYL

LWILD

BRIAN

SPUR

STIRRUP

RUTL

AND

LYNN

NATCHEZ

TOWNSEND

CAMI

NO R

EAL

SNOW

GRAS

S

HOMES

TEAD

AULD

TAMARIND

DAVID

CORRAL

ALTADENA

CARLYLE

PALENCIA

LANSING

THUNDER BAY

JULIAN

BRADFORD

STUDIO

CANDLE LIGHT

EUCA

LYPT

US

GRINNELL

LEUCADIA

NINA

CLUB

HOUS

E

LAKA

REN

HELM

CRES

T

JENN

IFER

HIGH PRAIRIE

TAYO

MANITOBA

TUMB

LEWEE

D

ROCKFORD

CARDIFF

VAN

BURE

N

63RD

58TH

PEDLEY

59TH

VAN B

UREN

CALIFORNIA

CENTRAL

JURUPA

ARLINGTON

CHAL

LEN

ADAMS

COLORADO

JACKSON

MONROE

RUTL

AND

PHILBIN

CYPRESS

ESSEX

WELLS

PICKE

R

CRES

T

JOJO

BRUCE

LAKE

EILEEN

DOOL

ITTLE

FREM

ONT

GEMENDE

DELANO

PENNY

CORW

INMIA

ACOR

N

HILLSIDE

CANTEBURY

ADAIR

WILDER

NESS

PAYT

ON

SAINT PAUL

NEIL

JASM

INE

DUNCAN

ELLE

N

DALES

SYLVAN

CAMELIA

HOPE

RAINTREE

VIA SAN JOSE

REES

AIRPO

RT

PALO

S

TREY

PEMBROKE

GLENCOE

KINGSBURY

HEIDI

BRUNSWICK

DRIFTWOOD

MADRONA

MALIB

U

WARRE

N

SAGE

SAN VICENTE

DORI

NDA

TOYON

HARO

LD

LOMITA

HOLLY

TEXAS

FARR

IER

ORDW

AY

OUIDA

WHEELER

VERBENA

BEL AIR

SHERMAN

HOLL

YRID

GE

ZINNIA

BOLTON

BASSWOOD

SHANNON

FLIGHT

BART

EL

ED PERKIC

GLENHURST

LIONH

EAD

CELLINI

DONALD

KITTY HAWK

SORRENTO

REMINGTON

ORLANDOBEGONIA

REPU

BLIC

MESCALE

PHOE

NIX

ACACIA

DANIEL

INDUSTRIAL

BEAU

JANET

GALWAY

ORANGEWOODPARKER

RAMP

OLYM

PIA

ALBIONGREEN VALLEY

PEGA

SUS

DUVAL

ARNETT

CATALPA

MONT

GOMER

Y

MONTICELLO

DELANO

HY 91

ADAMS

INDIANA

LINCOLN

MONROE

VICTORIA

JACKSON

MAGNOLIA

GIBSON

GRATTON

GARFIELD

DONALD

GAY

ANDREW

HAYES

AUTO

TAFT

ROSLYN

BEL AIR

CROW

ELL

FARNHAM

MCKENZIE

LILA

SHERMAN

EILEEN

WAYNE

HELENA

SHEL

BY

PRIMROSE

STOTTS

VANCE

MELODY

HEIDI MARIE

RUDICILL

ANTARES TURLOCK

CANTEBURY

ACACIA

JANIS

ST LAURENCE

COPLEY

HOYA

MILLER

MISSISSIPPI

MESQUITE

HAWTHORNE

DYKES

SHALIMAR

ARBOLES

AEGEAN

CALL

ARAP

AHOE

AZALEA

VAN BUREN BL ONRP

LESTER

DARWIN

MARISA

ESTRELLITA

BROADMOOR

SHERWOOD

MAR VISTA

MOTOR CIRCLE

LARKINMACARTHUR

SHOREPINE

MAGNOLIA

GARFIELD

MILLER

HY 91

TAFT

HAWTHORNE

60 dB

A Leq

65 dB

A Leq

70 dB

A Leq75

dBA L

eq

70 dB

A Leq

75 dBA Leq

60 dB

A Leq

70 dB

A Leq

65 dB

A Leq

65 dB

A Leq

60 dB

A Leq

60 dB

A Leq

70 dB

A Leq

65 dBA Leq

60 dBA Leq

75 dBA Leq

70 dBA Leq

65 dBA Leq

60 dBA Leq

60 dBA Leq

65 dBA Leq

65 dBA Leq

65 dBA Leq

75 dBA Leq

75 dBA Leq

70 dBA Leq

70 dBA Leq

70 dBA Leq

60 dBA Leq

65 dBA Leq

70 dBA Leq

75 dBA Leq

65 dBA Leq

70 dBA Leq75 dBA Leq

70 dBA Leq

75 dBA Leq

LEGENDExcavation Noise ContoursJack & Bore or Microtunnelling Noise Contours

Proposed Riverside-Corona FeederNorthern ReachCentral ReachRC Feeder Monroe AlternativeR-C Feeder Alignment (to Remain)Sensitive Receptors (see Table 7)

Map created November 29, 2009. G:\2007\07-0377\Gis\NoiseContourMapSeries0909.mxd

RIVERSIDE FREEWAY

VICTORIA

LIMONITE

VAN BUREN

ARLINGTON

MAGNOLIA

ARLINGTON

JURUPA

LIMONITE

MAGNOLIA

0 1,000 2,000 3,000 4,000Feet

Figure 4Noise Contours for Project

Construction - Central Reach(Central Portion)

Page 20

Page 24: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

9

8

4

32

1

7

6

5

20

19

1312

1110

15

14

17

16

18

21

60 dBA Leq

65 dBA Leq70 dBA Leq

60 dBA Leq

70 dBA Leq

75 dBA Leq

65 dBA Leq

7 5 dBA L

eq

70 dBA Leq

75 dBA Leq

70 d B A Leq

60 dBA Leq

65 dBA Leq

75 dBA Leq

75 dBA Leq

VAN B

UREN

CALIFORNIA

CENTRAL

ARLINGTON

CHAL

LEN

ADAMS

COLORADO

JACKSON

MONROE

RUTL

AND

PHILBIN

CYPRESS

WELLS

PICKE

R

JOJO

BRUCE

LAKE

EILEEN

DOOL

ITTLE

GEMENDE

DELANO

PENNY

CORW

INMIA

HILLSIDE

CANTEBURY

ADAIR

SAINT PAUL

NEIL

DUNCAN

ELLE

N

SYLVAN

CAMELIA

HOPE

RAINTREE

VIA SAN JOSE

REES

AIRPO

RT

PALO

S

TREY

PEMBROKE

GLENCOE

KINGSBURY

HEIDI

BRUNSWICK

DRIFTWOOD

MADRONA

MALIB

U

WARRE

N

SAGE

SAN VICENTETOYON

HARO

LD

LOMITA

HOLLY

TEXAS

OUIDA

WHEELER

VERBENA

BEL AIR

SHERMAN

ZINNIA

BOLTON

BASSWOOD

SHANNON

FLIGHT

BART

EL

GLENHURST

LIONH

EAD

CELLINI

DONALD

SORRENTO

REMINGTON

ORLANDO

BEGONIA

MESCALE

PHOE

NIX

ACACIA

DANIEL

BEAU

JANET

GALWAY ALBION

GREEN VALLEY

PEGA

SUS

DUVAL

ARNETT

CATALPA

MONT

GOMER

Y

MONTICELLO

DELANO

HY 91

ADAMS

INDIANA

LINCOLN

MONROE

VICTORIA

JACKSON

DUFFERIN

MAGNOLIA

CLEVELAND

MYERS

IRVING

GIBSON

GRATTON

VAN BUREN

GARFIELD

DONALD

GAY

ANDREW

HAYES

AUTO

TAFT

ROSLYN

BEL AIR

CROW

ELL

FARNHAM

MCKENZIE

LILA

SHERMAN

EILEEN

WAYNE

HELENA

SHEL

BY

PRIMROSE

STOTTS

VANCE

MELODY

HEIDI MARIE

RUDICILL

LOYOLA

WICHITA

ANTARES TURLOCK

CANTEBURY

ACACIA

JANIS

ST LAURENCE

COPLEY

HOYA

MILLER

MISSISSIPPI

MESQUITE

HAWTHORNE

DYKES

SHALIMAR

ARBOLES

AEGEAN

CALL

ARAP

AHOE

AZALEA

VAN BUREN BL ONRP

LESTER

SAIN

T LAW

RENC

E

LITCHFIELD

DARWIN

MARISA

ESTRELLITA

BROADMOOR

SHERWOOD

MAR VISTA

MOTOR CIRCLE

LARKIN

MARTINEZ

STOCKTON

MACARTHUR

BUTTERFIELD

SHOREPINE

MAGNOLIA

GARFIELD

MILLER

HY 91

VICTORIA

TAFT

HAWTHORNE

65 dBA Leq

60 dBA Leq

75 dBA Leq

70 dBA Leq

65 dBA Leq

60 dBA Leq

60 dBA Leq

65 dBA Leq

65 dBA Leq

65 dBA Leq

75 dBA Leq

75 dBA Leq

70 dBA Leq

70 dBA Leq

60 dBA Leq

65 dBA Leq

70 dBA Leq

75 dBA Leq

65 dBA Leq

70 dBA Leq75 dBA Leq

75 dBA Leq70 dBA Leq

70 dBA Leq

65 dBA Leq

60 dBA Leq

75 dBA Leq

LEGENDExcavation Noise ContoursJack & Bore or Microtunnelling Noise Contours

Proposed Riverside-Corona FeederNorthern ReachCentral ReachRC Feeder Monroe AlternativeR-C Feeder Alignment (to Remain)Sensitive Receptors (see Table 7)

Map created November 29, 2009. G:\2007\07-0377\Gis\NoiseContourMapSeries0909.mxd

Figure 5Noise Contours for Project

Construction - Central Reach(Southern Portion)

RIVERSIDE FREEWAY

VICTORIA

LIMONITE

VAN BUREN

ARLINGTON

MAGNOLIA

ARLINGTON

JURUPA

LIMONITE

MAGNOLIA

0 1,000 2,000 3,000 4,000Feet

Page 21

Page 25: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

CITY OFREDLANDS

60 dBA Leq

65 dBA Leq70 dBA Leq

75 dBA Leq

I- 10

Alaba

ma S

t

Neva

da St

Texa

s St

Pioneer Ave

Lugonia Ave

6th S

tRedlands Blvd

Park Ave

Clay S

t

State

Hwy 3

0

Colton Ave

San Bernardino Ave

Citrus Ave

Sun Ave

State St

Iowa S

t

Stuart Ave

Olive Ave

Oran

ge S

t

Brockton Ave

New

York

St

Almond Ave Ohio

St

Palmetto Ave

Colum

bia St

9th S

t

Mill St

5th S

t

Pennsylvania Ave

Heral

d St

Orange Tree Ln

Wash

ington

St

New

Jerse

y St

Buck

eye S

t

Eureka St

Alta S

t

High Ave

Vine St

Domestic Ave

Cente

r St

Doyle Dr

Industrial Park Ave

Plum Tree Ln

Kendall St

Indian

a Ct

Holly Ln

3rd St

Beatie Ln

Waters Ct

G:\2007\07-0377\Gis\Additional_Central_Feeder_Connection.mxd

Figure 6Noise Contours for Project Construction - Central Feeder Connection

0 2,0001,000 Feet

LegendCentral Feeder PipelinePotential Well Field

Page 22

Page 26: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

R I V E R S I D ER I V E R S I D E

60 dBA Leq65 dBA Leq

70 dBA Leq

75 dBA Leq

70 dBA Leq75 dBA Leq

60 dBA Leq

65 dBA Leq

Lake Mathews

La Sierra

Mc Allister

Dufferin

Victoria John

Cleveland

Canal

Tin Mine

El SobranteFillmore Praed

Indiana

Blackburn

MyersHarrison

Lake Knoll

Lake Pointe

Wickham

Lyon

RichlandSterling

Tyler

Paine Sagittarius

MillardNational

Citrus Wood

Trail End

G:\2007\07-0377\Gis\LaSierraPipelineNoiseContours.mxd

0 2,4001,200 Feet

LegendLaSierraPipelineContoursRiverside-Corona Feeder - La Sierra PipelineR-C Feeder Alignment (to Remain)(Reaches E - H)Mills Pipeline (Existing)

Figure 7Noise Contours for Contruction - La Sierra Pipeline

Page 23

Page 27: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

MOCKINGB IRD CAN YON RD

GR EE NV IE W D R

Mockingbird CanyonWater Line

Mills Gravity Line

TRACT34059

VA N B U R E N B LV

PI C K P L

SALL

Y LN

CONS

TA B LE RD

FIR E

T HOR

N AV

E

REGE

NCY

RANC

H RD

LOVE

BIRD

LN

L A U R E L D R

HERI

TAGE

GRO

VE R

D

VAN BU RE N B LV

IRV ING ST

LOT 20

60 dBA

Leq

65 dBA Leq

70 dB

A Leq

75 dBA Leq

60 dB

A Leq

65 dBA Leq

7 5 dB A L

e q

60 dBA Leq

70 dBA Leq

65 dB

A Leq

70 dB

A Leq

75 dB

A Leq

60 dBA Leq

65 dBA Leq

70 dBA Leq

75 dBA Leq

Map created September 30, 2009. G:\2007\07-0377\Gis\MockingbirdNoiseContours.mxd

Figure 8Noise Contours for

Construction - MockingbordConnection

0 400 800 1,200Feet

Source: County of Riverside, 2008.

LEGENDPossible TankMockingbird ConnectionR-C Feeder Alignment (to Remain)(Reaches E - H)Proposed BoosterStationExisting WaterPipelineExisting MockingbirdBooster StationLot20

Page 24

Page 28: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

G:\2007\07-0377\Gis\BoosterSite1_NoiseContours.mxd

RIVERSIDE-CORONAFEEDER

WATERLINE

PROPOSED SITE 4

PROPOSED SITE 2

PROPOSED SITE 3

Union Pacific RailroadVAN BUREN BLVD

58TH ST

CLAY

ST

PEDL

EY R

D

HUDS

ON S

T

BALD

WIN AVE

LAKEVIEW AVE

60TH ST

ARCH

ER S

T

63RD AVE

KENNEDY ST

GREE N S DR

GOLF ST

KELSEY PL

FAGA

N RD

MAIN ST

RUNNING GAIT LN

STUDIO PL

NORTHWOOD DR

VAN BUREN BLVD

63RD ST

LIMONITE AVE

PEDL

EY R

D

PROPOSED CLAY STGRADE SEPARATION

60 dBA Leq

65 dBA Leq

70 d B A Leq

75 dB

A Leq

Figure 9Noise Contours for Construction -

Clay Street Connection - Booster Site 1

0 590295 Feet

Page 25

Page 29: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

G:\2007\07-0377\Gis\BoosterSite2_NoiseContours.mxd

PROPOSED SITE 4

PROPOSED SITE 3

PROPOSED SITE 1

RIVERSIDE-CORONAFEEDER

WATERLINE

Union Pacific Railroad

VAN BUREN BLVD

58TH ST

CLAY

ST

PEDL

EY R

D

HUDS

ON S

T

BALD

WIN AVE

LAKEVIEW AVE

60TH ST

ARCH

ER S

T

63RD AVE

KENNEDY ST

GREEN S DR

GOLF ST

KELSEY PL

FAGA

N RD

MAIN ST

RUNNING GAIT LN

STUDIO PL

NORTHWOOD DR

VAN BUREN BLVD

PEDLEY R D

63RD ST

LIMONITE AVE

JCSD POINTOF CONNECTION

PROPOSED CLAY STGRADE SEPARATION

60 dBA Leq

65 dBA Leq

70 dB A Leq

75 dB

A Leq

Figure 10Noise Contours for Construction -

Clay Street Connection - Booster Site 2

0 600300 Feet

Page 26

Page 30: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

G:\2007\07-0377\Gis\BoosterSite3_NoiseContours.mxd

PROPOSED SITE 4

PROPOSED SITE 2

PROPOSED SITE 1

RIVERSIDE-CORONAFEEDER

WATERLINE

Union Pacific Railroad

VAN BUREN BLVD

58TH ST

CLAY

ST

PEDL

EY R

D

HUDS

ON S

T

BALD

WIN AVE

LAKEVIEW AVE

60TH ST

ARCH

ER S

T

63RD AVE

KENNEDY ST

GREE NS DR

GOLF ST

KELSEY PL

FAGA

N RD

MAIN ST

RUNNING GAIT LN

STUDIO PL

NORTHWOOD DR

VAN BUREN BLVD

PEDLEY R D

63RD ST

LIMONITE AVE

JCSD POINTOF CONNECTION

PROPOSED CLAY STGRADE SEPARATION

60 dBA Leq

65 dBA Leq

70 dB A Leq

75 dB

A Leq

Figure 11Noise Contours for Construction -

Clay Street Connection - Booster Site 3

0 590295 Feet

Page 27

Page 31: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

G:\2007\07-0377\Gis\BoosterSite4_NoiseContours.mxd

PROPOSED SITE 1

RIVERSIDE-CORONAFEEDER

WATERLINE

PROPOSED SITE 3

PROPOSED SITE 2

Union Pacific RailroadVAN BUREN BLVD

58TH ST

CLAY

ST

PEDL

EY R

D

HUDS

ON S

T

BALD

WIN AVE

LAKEVIEW AVE

60TH ST

ARCH

ER S

T

63RD AVE

KENNEDY ST

GREEN S DR

GOLF ST

KELSEY PL

FAGA

N RD

MAIN ST

RUNNING GAIT LN

STUDIO PL

NORTHWOOD DR

VAN BUREN BLVD

PEDLEY R D

63RD ST

LIMONITE AVE

JCSD POINTOF CONNECTION

PROPOSED CLAY STGRADE SEPARATION

60 dBA Leq

65 dBA Leq

70 dB A Leq

75 dB

A Leq

Figure 12Noise Contours for Construction -

Clay Street Connection - Booster Site 4

0 600300 Feet

Page 28

Page 32: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

29 WEBB A L B E R T A. A S S O C I A T E S

SECTION 5 – Conclusions

An acoustical analysis has been performed for the Riverside-Corona Feeder project. There is no operational or long-term noise associated with the project; therefore, construction noise is the only anticipated potentially significant noise source. The project site will traverse five city jurisdictions and two unincorporated county jurisdictions. Construction noise is exempt from regulation in all of these jurisdictions. One city (Redlands) and two county (San Bernardino and Riverside) jurisdictions include limitations placed on their exemptions which specify the conditions under which construction activities can take place, such as the proximity of construction activity to sensitive receivers, hours of the day that construction activity cannot take place, and/or days on which construction activity cannot take place (e.g., Sundays and/or federal holidays). Although activities from the project construction are likely to increase the overall noise level in the vicinity of the project site, construction-related noise is temporary in nature. While noise from the project’s construction period is exempt from regulation under provisions made by the affected jurisdictions, this report includes analysis of potential worst-case noise levels expected to be generated during the construction phase. Most of the construction work will be performed within existing road rights-of-way. Standard construction methods will be employed for the reservoir and pump station construction. Three primary methods will be employed for the pipeline construction process: boring, excavation, and microtunneling. Noise contours are provided in this report (Table 6 and Figures 3, 4, and 5) to help identify potentially impacted land uses from all of the aforementioned construction methods. The noise contours indicate worst-case distances to which the 60, 65, 70, and 75 dBA Leq noise impacts could extend from the center of the construction activity, not including the attenuating affects of topography or intervening structures and/or foliage. Specific existing noise sensitive uses along the project’s alignment that are located within the anticipated noise contours include schools, residences, churches, hospitals, day care centers, and medical clinics. Figures 3, 4, and 5 identify many of these noise sensitive uses.

Page 33: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

30 WEBB A L B E R T A. A S S O C I A T E S

SECTION 6 – References

References Cited

The following documents were referred to as general information sources during the preparation of this document. They are available for public review at the locations abbreviated after each listing and spelled out at the end of this section. Some of these documents are also available at public libraries and at other public agency offices. Federal Transit Administration, Transit Noise and Vibration Impact Assessment, International Congress and Exposition on Noise Control Engineering, May 2006. (Available at http://www.akrf.com/knowledge/white_papers/Construction%20Noise%202008%20INCE.pdf)

City of Rialto, Municipal Code, LexisNexis, 2008. (Available at http://municipalcodes.lexisnexis.com/codes/rialto/)

City of Rialto, General Plan. (Available at the City of Rialto Planning Department.)

City of Riverside, Municipal Code. (Available at http://www.riversideca.gov/municode/)

City of Riverside, General Plan (Available at http://aquarius.riversideca.gov/plnimage7/Browse.aspx?dbid=2&startid=25416)

Riverside County, Municipal Code, LexisNexis, 2003. (Available at http://municipalcodes.lexisnexis.com/codes/riversideco/)

Riverside County, General Plan. (Available at http://www.rctlma.org/genplan/content/gp.aspx)

City of San Bernardino, Municipal Code. (Available at http://www.ci.san-bernardino.ca.us/residents/municipal_code.asp)

City of San Bernardino, General Plan. (Available at http://www.ci.san-bernardino.ca.us/depts/devserv/planning/default.asp)

San Bernardino County, Development Code. (Available at http://www.sbcounty.gov/landuseservices/DevCode/Default.asp)

San Bernardino County, General Plan. (Available at http://www.sbcounty.gov/landuseservices/General%20Plan%20Update/Default.asp)

City of Colton, Municipal Code, LexisNexis, 2003. (Available at http://bpc.iserver.net/codes/colton/index.htm)

City of Colton, General Plan, Community Systems Associates, Inc., 1987. (Available at http://www.ci.colton.ca.us/CD_Plan.html)

Page 34: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

31 WEBB A L B E R T A. A S S O C I A T E S

Document Preparation Staff ALBERT A. WEBB ASSOCIATES 3788 McCray Street Riverside, CA 92506 951.686.1070 Mike Rosa, Associate Environmental Technician Laura Hudson, Project Coordinator

Page 35: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

WEBB A L B E R T A. A S S O C I A T E S

Appendix A

Reference Noise Level Source Information

Page 36: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Noise Assessments for Construction Noise Impacts

Weixiong Wua AKRF, Inc., 440 Park Avenue, 7th floor, New York, NY, 10016, USA.

ABSTRACT Construction noise is one of the most disruptive noise sources in New York City. Large-scale projects especially can take more than a decade to complete, and often be located in areas with various sensitive noise receptors. When these projects are being built, on-site construction equipment operation along with construction vehicle movement on surrounding roadways can cause dramatic increases in ambient noise levels at near noise-sensitive receptors. In addition, construction activities would occurs not only during weekday daytime periods, but also sometimes in the weekday nighttime periods or weekends. To assess a potential construction noise impact, the City Environmental Quality Review (CEQR) Technical Manual1 is used when preparing an environmental impact statement (EIS). For most cases, adverse noise impacts often occur at near noise receptors during the construction without implementing mitigation measures. To eliminate or minimize these impacts is among the most challenging noise issues for noise analyses. This paper will illustrate certain methods for construction noise mitigation measures for large-scale development projects, to meet the CEQR noise criteria. The purpose of this study is to present practical and feasible mitigation techniques to reduce construction noise levels. Finally, noise analysis results for a typical large-scale project (the Atlantic Yards Arena project) will be presented using these mitigation measures.

1 INTRODUCTION Construction noise analyses were completed by using construction noise mitigation plans

for typical large-scale construction projects in New York City, including First Avenue Properties in Midtown Manhattan, Fordham University Lincoln Center, Columbia University’s proposed new campus in Manhattanville in West Harlem, the new Yankee Stadium in the Bronx, and the Atlantic Yards Arena in Brooklyn. All of these sites are located in areas with high population densities and many noise-sensitive receptors. When these projects are built, construction activities will occur during normal weekday daytime periods, and construction for some of the projects will occasionally take place during the nighttime and on weekends as well.

Noise analyses were performed to identify the potential for significant adverse impacts that could result from construction noise. In general, noise analyses are conducted by: • Determining sensitive receptor locations where construction-generated noise will be

significantly increased; • Measuring existing noise levels at sensitive receptor locations; • Using appropriate mathematical models to predict construction noise levels; • Determining noise impacts based on related noise ordinance standards; and • Providing mitigation measures if any noise impacts will occur.

a [email protected]

miker
Text Box
http://www.akrf.com/knowledge/white_papers/Construction%20Noise%202008%20INCE.pdf
Page 37: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

shielding benefits. Once building foundations are completed, delivery trucks will operate behind noise barriers.

• Noise barriers will be used to provide shielding. For example, the construction sites will have a minimum 8-foot-high barrier, with a 15-foot-high barrier adjacent to residential and other sensitive locations. In addition, truck deliveries will take place behind these barriers once building foundations are completed.

• Noise curtains and equipment enclosures will be used to shield sensitive receptor locations. Table 1 shows an example of equipment noise levels using the emission and the path

control techniques for a noise analysis of the Fordham University Lincoln Center project. The emission noise levels came from the noise level standards specified in the Citywide Construction Noise Mitigation of the Department of Environmental Protection of New York City or the Transit Noise and Vibration Impact Assessment of Federal Transit Administration4. The mandated noise levels were achieved by using quieter equipment, better engine mufflers, and refinements in fan design and improved hydraulic systems. Noise levels with path control included using noise barriers, enclosures, acoustical panels, and curtains, whichever feasible and practical.

Table 1: Maximum Noise levels at 50 feet with emission and path control, dBA re 20µPa.

Equipment List Emission Noise

Level Mandated Noise

Level Noise Level with

Path Controls Asphalt Paver 85 85 75 Asphalt Roller 85 74

Backhoe/Loader 80 77 Compressors 80 67

Concrete Pump 82 79 Concrete Trucks 85 79

Cranes 85 77 Cranes (Tower Cranes) 85 85 75

Delivery Trucks 84 79 Drill Rigs 84 84 74

Dump Trucks 84 79 Excavator 85 77

Excavator with Ram Hoe 90 90 80 Fuel Truck 84 79 Generators 82 68

Hoist 85 80 70 Impact Wrenches 85 85 75

Jack Hammer 85 82 72 Mortar Mixer 80 63 Power Trowel 85 85 75

Powder Actuated Device 85 85 75 Pump (Spray On Fire Proof) 82 76

Pump (Water) 77 76 Rebar Bender 80 80 Rivet Buster 85 85 75 Rock Drill 85 85 75

Saw (Chain Saw) 85 75 Saw (Concrete Saw) 90 85 75

Saw (Masonry Bench) 85 76 Saw (Circular & Cut off) 76 76

Saw (Table Saw) 76 76 Sledge Hammers 85 85 75

Street Cleaner 80 80 Tractor Trailer 84 79

Vibratory Plate Compactor 80 80 Welding Machines 73 73

miker
Text Box
http://www.akrf.com/knowledge/white_papers/Construction%20Noise%202008%20INCE.pdf
Page 38: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Table 3: Predicted construction noise levels in 2008, dBA re 20µPa. Source Controls

Path Controls Trucks Behind

Barriers Noise Receptor

Elevation Level

Worst Period Leq(1) Leq(1) Decrease Leq(1) Decrease Leq(1) Decrease

Total Decrease

A 1st Floor 85 82 -3 76 -6 67 -9 -18 B 1st Floor 89 85 -4 78 -7 70 -8 -19 C 1st Floor 88 83 -6 79 -3 70 -9 -18 D 3rd Floor 87 82 -5 78 -4 73 -5 -14 E 3rd Floor 79 74 -5 69 -5 67 -3 -12 F 3rd Floor 78 73 -5 71 -2 64 -7 -14 G 15th Floor 81 76 -5 76 0 76 0 -5 H 15th floor 73 69 -5 68 -1 66 -2 -7 I 30th Floor 85 80 -5 78 -2 77 -1 -8

4 CONCLUSION With construction noise mitigation plans, construction activities for large-scale projects

examined above can reduce noise levels significantly at sensitive noise receptors adjacent to construction sites. Based on the noise analyses results, noise control techniques were developed to identify and develop practical mitigation measures that were incorporated into the projects to substantially reduce potential construction noise impacts. Key findings are summarized below:

• Before taking mitigation measures, a logical and realistic review of construction schedule is necessary. • Eliminate unnecessary equipment on site. • As early in the construction period as possible, replace diesel-powered equipment with electrical-

powered equipment. • Where feasible, use quiet equipment (for dominant noise equipment). • Noisy equipment needs be located away from sensitive receptor locations and shielded from sensitive

receptor locations. • Delivery trucks should be located adjacent to noisy streets or behind noise barriers. • 3 to 6 dBA reduction can be obtained with source control techniques. • 2 to 7 dBA reduction can be obtained with path control techniques for receptors at lower

elevation levels. • 3 to 9 dBA reduction can be obtained by placing delivery trucks behind noise barriers for

receptors at lower elevation levels. • A maximum reduction of 19 dBA can be obtained with noise source and path control

techniques. • If possible schedule louder activities; to times people are less sensitive to noise intrusions. • Limited benefits of noise reduction can be expected by using path control techniques for

receptors at higher-level floors.

5 REFERENCES [1] New York City Environmental Quality Review (CEQR) Technical Manual, Chapter 3R

Noise, New York, 2001. [2] New York City Noise Code, Subchapter 5, New York City Department of

Environmental Protection, 2005. [3] Citywide Construction Noise Mitigation, Chapter 28, Department of Environmental

Protection of New York City, 2007 [4] Transit Noise and Vibration Impact Assessment, May 2006, Federal Transit

Administration. [5] CadnaA is the computerized software developed by DataKustik.

Page 39: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Western Municipal Water District Riverside-Corona Feeder Project Acoustical Impact Analysis

WEBB A L B E R T A. A S S O C I A T E S

Appendix B

Noise Impact Calculation Printouts

Page 40: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

NOISE IMPACT ADDITION WORKSHEET12/15/2008

11:52 AM

Entered by: Mike

W.O.: 2007-0377

Project:City/CountyAgency:

Noise ImpactThreshold:

Location:Obs. Location:

Conditions:

Quantity Noise Level (dBA) Equivalent Pressure Units

0 - - - -0 - - - -1 51.4 137,174.20 - - - -1 56.4 433,782.90 - - - -2 56.4 434,812.90 - - - -

Total Pressure Units: 1,005,770.1

Generator

Riverside-Corona Feeder

Boring Method1,350 feet from center point of construction

multiple

- -

Compressor

60.0 dBACombined Boring Method noise level from all sources:

Construction Site

Noise Source

Asphalt Paver

Welding Machines

Asphalt RollerBackhoes/Loaders

CraneExcavator

G:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (60 dBA).xlsaddition v1.1a

Page 41: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1350.0 feet51.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1350.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Backhoes/Loaders

ReferenceNoise Data Source:

Printed on 12/15/2008 at 11:52 AMG:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (60 dBA).xlsbackhoe-loader v2.0

Page 42: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1350.0 feet56.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1350.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Crane

ReferenceNoise Data Source:

Printed on 12/15/2008 at 11:52 AMG:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (60 dBA).xlscrane v2.0

Page 43: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1350.0 feet53.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet82.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1350.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Generator

ReferenceNoise Data Source:

Printed on 12/15/2008 at 11:52 AMG:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (60 dBA).xlsgenerator v2.0

Page 44: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

NOISE IMPACT ADDITION WORKSHEET12/15/2008

11:55 AM

Entered by: Mike

W.O.: 2007-0377

Project:City/CountyAgency:

Noise ImpactThreshold:

Location:Obs. Location:

Conditions:

Quantity Noise Level (dBA) Equivalent Pressure Units

0 - - - -0 - - - -1 56.4 432,825.50 - - - -1 61.4 1,368,714.40 - - - -2 61.4 1,371,964.30 - - - -

Total Pressure Units: 3,173,504.2

Generator

Riverside-Corona Feeder

Boring Method760 feet from center point of construction

multiple

- -

Compressor

65.0 dBACombined Boring Method noise level from all sources:

Construction Site

Noise Source

Asphalt Paver

Welding Machines

Asphalt RollerBackhoes/Loaders

CraneExcavator

G:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (65 dBA).xlsaddition v1.1a

Page 45: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

760.0 feet56.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

760.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Backhoes/Loaders

ReferenceNoise Data Source:

Printed on 12/15/2008 at 11:54 AMG:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (65 dBA).xlsbackhoe-loader v2.0

Page 46: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

760.0 feet61.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

760.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Crane

ReferenceNoise Data Source:

Printed on 12/15/2008 at 11:54 AMG:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (65 dBA).xlscrane v2.0

Page 47: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

760.0 feet58.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet82.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

760.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Generator

ReferenceNoise Data Source:

Printed on 12/15/2008 at 11:54 AMG:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (65 dBA).xlsgenerator v2.0

Page 48: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

NOISE IMPACT ADDITION WORKSHEET12/15/2008

11:57 AM

Entered by: Mike

W.O.: 2007-0377

Project:City/CountyAgency:

Noise ImpactThreshold:

Location:Obs. Location:

Conditions:

Quantity Noise Level (dBA) Equivalent Pressure Units

0 - - - -0 - - - -1 61.3 1,352,082.20 - - - -1 66.3 4,275,659.40 - - - -2 66.3 4,285,811.80 - - - -

Total Pressure Units: 9,913,553.3

Generator

Riverside-Corona Feeder

Boring Method430 feet from center point of construction

multiple

- -

Compressor

70.0 dBACombined Boring Method noise level from all sources:

Construction Site

Noise Source

Asphalt Paver

Welding Machines

Asphalt RollerBackhoes/Loaders

CraneExcavator

G:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (70 dBA).xlsaddition v1.1a

Page 49: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

430.0 feet61.3 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

430.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Backhoes/Loaders

ReferenceNoise Data Source:

Printed on 12/15/2008 at 11:57 AMG:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (70 dBA).xlsbackhoe-loader v2.0

Page 50: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

430.0 feet66.3 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

430.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Crane

ReferenceNoise Data Source:

Printed on 12/15/2008 at 11:57 AMG:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (70 dBA).xlscrane v2.0

Page 51: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

430.0 feet63.3 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet82.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

430.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Generator

ReferenceNoise Data Source:

Printed on 12/15/2008 at 11:57 AMG:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (70 dBA).xlsgenerator v2.0

Page 52: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

NOISE IMPACT ADDITION WORKSHEET12/15/2008

11:59 AM

Entered by: Mike

W.O.: 2007-0377

Project:City/CountyAgency:

Noise ImpactThreshold:

Location:Obs. Location:

Conditions:

Quantity Noise Level (dBA) Equivalent Pressure Units

0 - - - -0 - - - -1 66.4 4,340,277.80 - - - -1 71.4 13,725,163.50 - - - -2 71.4 13,757,753.40 - - - -

Total Pressure Units: 31,823,194.6

Generator

Riverside-Corona Feeder

Boring Method240 feet from center point of construction

multiple

- -

Compressor

75.0 dBACombined Boring Method noise level from all sources:

Construction Site

Noise Source

Asphalt Paver

Welding Machines

Asphalt RollerBackhoes/Loaders

CraneExcavator

G:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (75 dBA).xlsaddition v1.1a

Page 53: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

240.0 feet66.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

240.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Backhoes/Loaders

ReferenceNoise Data Source:

Printed on 12/15/2008 at 11:59 AMG:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (75 dBA).xlsbackhoe-loader v2.0

Page 54: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

240.0 feet71.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

240.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Crane

ReferenceNoise Data Source:

Printed on 12/15/2008 at 11:59 AMG:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (75 dBA).xlscrane v2.0

Page 55: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

240.0 feet68.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet82.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

240.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Generator

ReferenceNoise Data Source:

Printed on 12/15/2008 at 11:59 AMG:\2007\07-0377\Noise\calculations\Boring - Const. Equip. RNL Projections (75 dBA).xlsgenerator v2.0

Page 56: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

NOISE IMPACT ADDITION WORKSHEET12/15/2008

12:00 PM

Entered by: Mike

W.O.: 2007-0377

Project:City/CountyAgency:

Noise ImpactThreshold:

Location:Obs. Location:

Conditions:

Quantity Noise Level (dBA) Equivalent Pressure Units

0 - - - -0 - - - -3 53.2 207,756.22 51.4 138,504.21 53.4 218,994.32 56.4 437,988.60 - - - -0 - - - -

Total Pressure Units: 1,003,243.3

Generator

Riverside-Corona Feeder

Excavation1,900 feet from center point of construction

multiple

- -

Compressor

60.0 dBACombined Excavation noise level from all sources:

Construction Site

Noise Source

Asphalt Paver

Welding Machines

Asphalt RollerBackhoes/Loaders

CraneExcavator

G:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (60 dBA).xlsaddition v1.1a

Page 57: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1900.0 feet48.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1900.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Backhoes/Loaders

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:00 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (60 dBA).xlsbackhoe-loader v2.0

Page 58: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

- -

Mitigated Noise Level:

Compressor

ReferenceNoise Data Source:

- -- -- -

0.0 feet- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1900.0 feet

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1900.0 feet48.4 dBA- -- -- -- -- -

Printed on 12/15/2008 at 12:00 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (60 dBA).xlscompressor v2.0

Page 59: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1900.0 feet53.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1900.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Crane

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:00 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (60 dBA).xlscrane v2.0

Page 60: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

- -

Mitigated Noise Level:

Excavator

ReferenceNoise Data Source:

- -- -- -

0.0 feet- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1900.0 feet

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1900.0 feet53.4 dBA- -- -- -- -- -

Printed on 12/15/2008 at 12:00 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (60 dBA).xlsexcavator v2.0

Page 61: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

NOISE IMPACT ADDITION WORKSHEET12/15/2008

12:02 PM

Entered by: Mike

W.O.: 2007-0377

Project:City/CountyAgency:

Noise ImpactThreshold:

Location:Obs. Location:

Conditions:

Quantity Noise Level (dBA) Equivalent Pressure Units

0 - - - -0 - - - -3 58.1 648,999.52 56.4 432,666.31 58.4 684,105.52 61.4 1,368,211.00 - - - -0 - - - -

Total Pressure Units: 3,133,982.3

Generator

Riverside-Corona Feeder

Excavation1,075 feet from center point of construction

multiple

- -

Compressor

65.0 dBACombined Excavation noise level from all sources:

Construction Site

Noise Source

Asphalt Paver

Welding Machines

Asphalt RollerBackhoes/Loaders

CraneExcavator

G:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (65 dBA).xlsaddition v1.1a

Page 62: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1075.0 feet53.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1075.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Backhoes/Loaders

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:02 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (65 dBA).xlsbackhoe-loader v2.0

Page 63: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

- -

Mitigated Noise Level:

Compressor

ReferenceNoise Data Source:

- -- -- -

0.0 feet- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1075.0 feet

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1075.0 feet53.4 dBA- -- -- -- -- -

Printed on 12/15/2008 at 12:02 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (65 dBA).xlscompressor v2.0

Page 64: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1075.0 feet58.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1075.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Crane

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:02 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (65 dBA).xlscrane v2.0

Page 65: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

- -

Mitigated Noise Level:

Excavator

ReferenceNoise Data Source:

- -- -- -

0.0 feet- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1075.0 feet

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1075.0 feet58.4 dBA- -- -- -- -- -

Printed on 12/15/2008 at 12:02 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (65 dBA).xlsexcavator v2.0

Page 66: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

NOISE IMPACT ADDITION WORKSHEET12/15/2008

12:04 PM

Entered by: Mike

W.O.: 2007-0377

Project:City/CountyAgency:

Noise ImpactThreshold:

Location:Obs. Location:

Conditions:

Quantity Noise Level (dBA) Equivalent Pressure Units

0 - - - -0 - - - -3 63.2 2,083,333.32 61.4 1,388,888.91 63.4 2,196,026.22 66.4 4,392,052.30 - - - -0 - - - -

Total Pressure Units: 10,060,300.7

Generator

Riverside-Corona Feeder

Excavation600 feet from center point of construction

multiple

- -

Compressor

70.0 dBACombined Excavation noise level from all sources:

Construction Site

Noise Source

Asphalt Paver

Welding Machines

Asphalt RollerBackhoes/Loaders

CraneExcavator

G:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (70 dBA).xlsaddition v1.1a

Page 67: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

600.0 feet58.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

600.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Backhoes/Loaders

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:04 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (70 dBA).xlsbackhoe-loader v2.0

Page 68: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

- -

Mitigated Noise Level:

Compressor

ReferenceNoise Data Source:

- -- -- -

0.0 feet- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

600.0 feet

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

600.0 feet58.4 dBA- -- -- -- -- -

Printed on 12/15/2008 at 12:04 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (70 dBA).xlscompressor v2.0

Page 69: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

600.0 feet63.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

600.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Crane

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:04 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (70 dBA).xlscrane v2.0

Page 70: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

- -

Mitigated Noise Level:

Excavator

ReferenceNoise Data Source:

- -- -- -

0.0 feet- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

600.0 feet

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

600.0 feet63.4 dBA- -- -- -- -- -

Printed on 12/15/2008 at 12:04 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (70 dBA).xlsexcavator v2.0

Page 71: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

NOISE IMPACT ADDITION WORKSHEET12/15/2008

12:05 PM

Entered by: Mike

W.O.: 2007-0377

Project:City/CountyAgency:

Noise ImpactThreshold:

Location:Obs. Location:

Conditions:

Quantity Noise Level (dBA) Equivalent Pressure Units

0 - - - -0 - - - -3 68.1 6,487,889.32 66.4 4,325,259.51 68.3 6,838,835.82 71.4 13,677,671.50 - - - -0 - - - -

Total Pressure Units: 31,329,656.1

Generator

Riverside-Corona Feeder

Excavation340 feet from center point of construction

multiple

- -

Compressor

75.0 dBACombined Excavation noise level from all sources:

Construction Site

Noise Source

Asphalt Paver

Welding Machines

Asphalt RollerBackhoes/Loaders

CraneExcavator

G:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (75 dBA).xlsaddition v1.1a

Page 72: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

340.0 feet63.3 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

340.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Backhoes/Loaders

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:05 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (75 dBA).xlsbackhoe-loader v2.0

Page 73: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

- -

Mitigated Noise Level:

Compressor

ReferenceNoise Data Source:

- -- -- -

0.0 feet- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

340.0 feet

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

340.0 feet63.3 dBA- -- -- -- -- -

Printed on 12/15/2008 at 12:05 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (75 dBA).xlscompressor v2.0

Page 74: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

340.0 feet68.3 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

340.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Crane

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:05 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (75 dBA).xlscrane v2.0

Page 75: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

- -

Mitigated Noise Level:

Excavator

ReferenceNoise Data Source:

- -- -- -

0.0 feet- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

340.0 feet

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

340.0 feet68.3 dBA- -- -- -- -- -

Printed on 12/15/2008 at 12:05 PMG:\2007\07-0377\Noise\calculations\Excavation - Const. Equip. RNL Projections (75 dBA).xlsexcavator v2.0

Page 76: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

NOISE IMPACT ADDITION WORKSHEET12/15/2008

12:07 PM

Entered by: Mike

W.O.: 2007-0377

Project:City/CountyAgency:

Noise ImpactThreshold:

Location:Obs. Location:

Conditions:

Quantity Noise Level (dBA) Equivalent Pressure Units

0 - - - -0 - - - -1 51.4 137,174.20 - - - -1 56.4 433,782.90 - - - -2 56.4 434,812.90 - - - -

Total Pressure Units: 1,005,770.1

Generator

Riverside-Corona Feeder

Microtunneling1,350 feet from center point of construction

multiple

- -

Compressor

60.0 dBACombined Microtunneling noise level from all sources:

Construction Site

Noise Source

Asphalt Paver

Welding Machines

Asphalt RollerBackhoes/Loaders

CraneExcavator

G:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (60 dBA).xlsaddition v1.1a

Page 77: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1350.0 feet51.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1350.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Backhoes/Loaders

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:07 PMG:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (60 dBA).xlsbackhoe-loader v2.0

Page 78: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1350.0 feet56.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1350.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Crane

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:07 PMG:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (60 dBA).xlscrane v2.0

Page 79: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

1350.0 feet53.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet82.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

1350.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Generator

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:07 PMG:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (60 dBA).xlsgenerator v2.0

Page 80: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

NOISE IMPACT ADDITION WORKSHEET12/15/2008

12:08 PM

Entered by: Mike

W.O.: 2007-0377

Project:City/CountyAgency:

Noise ImpactThreshold:

Location:Obs. Location:

Conditions:

Quantity Noise Level (dBA) Equivalent Pressure Units

0 - - - -0 - - - -1 56.4 432,825.50 - - - -1 61.4 1,368,714.40 - - - -2 61.4 1,371,964.30 - - - -

Total Pressure Units: 3,173,504.2

Generator

Riverside-Corona Feeder

Microtunneling760 feet from center point of construction

multiple

- -

Compressor

65.0 dBACombined Microtunneling noise level from all sources:

Construction Site

Noise Source

Asphalt Paver

Welding Machines

Asphalt RollerBackhoes/Loaders

CraneExcavator

G:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (65 dBA).xlsaddition v1.1a

Page 81: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

760.0 feet56.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

760.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Backhoes/Loaders

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:08 PMG:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (65 dBA).xlsbackhoe-loader v2.0

Page 82: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

760.0 feet61.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

760.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Crane

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:08 PMG:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (65 dBA).xlscrane v2.0

Page 83: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

760.0 feet58.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet82.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

760.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Generator

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:08 PMG:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (65 dBA).xlsgenerator v2.0

Page 84: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

NOISE IMPACT ADDITION WORKSHEET12/15/2008

12:09 PM

Entered by: Mike

W.O.: 2007-0377

Project:City/CountyAgency:

Noise ImpactThreshold:

Location:Obs. Location:

Conditions:

Quantity Noise Level (dBA) Equivalent Pressure Units

0 - - - -0 - - - -1 61.3 1,352,082.20 - - - -1 66.3 4,275,659.40 - - - -2 66.3 4,285,811.80 - - - -

Total Pressure Units: 9,913,553.3

Generator

Riverside-Corona Feeder

Microtunneling430 feet from center point of construction

multiple

- -

Compressor

70.0 dBACombined Microtunneling noise level from all sources:

Construction Site

Noise Source

Asphalt Paver

Welding Machines

Asphalt RollerBackhoes/Loaders

CraneExcavator

G:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (70 dBA).xlsaddition v1.1a

Page 85: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

430.0 feet61.3 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

430.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Backhoes/Loaders

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:09 PMG:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (70 dBA).xlsbackhoe-loader v2.0

Page 86: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

430.0 feet66.3 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

430.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Crane

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:09 PMG:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (70 dBA).xlscrane v2.0

Page 87: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

430.0 feet63.3 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet82.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

430.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Generator

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:09 PMG:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (70 dBA).xlsgenerator v2.0

Page 88: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

NOISE IMPACT ADDITION WORKSHEET12/15/2008

12:10 PM

Entered by: Mike

W.O.: 2007-0377

Project:City/CountyAgency:

Noise ImpactThreshold:

Location:Obs. Location:

Conditions:

Quantity Noise Level (dBA) Equivalent Pressure Units

0 - - - -0 - - - -1 66.4 4,340,277.80 - - - -1 71.4 13,725,163.50 - - - -2 71.4 13,757,753.40 - - - -

Total Pressure Units: 31,823,194.6

Generator

Riverside-Corona Feeder

Microtunneling240 feet from center point of construction

multiple

- -

Compressor

75.0 dBACombined Microtunneling noise level from all sources:

Construction Site

Noise Source

Asphalt Paver

Welding Machines

Asphalt RollerBackhoes/Loaders

CraneExcavator

G:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (75 dBA).xlsaddition v1.1a

Page 89: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

240.0 feet66.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet80.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

240.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Backhoes/Loaders

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:10 PMG:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (75 dBA).xlsbackhoe-loader v2.0

Page 90: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

240.0 feet71.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet85.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

240.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Crane

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:10 PMG:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (75 dBA).xlscrane v2.0

Page 91: Riverside-Corona Feeder Acoustical Impact Analysis H...exception of unique crossings (e.g., railroad overpass) and the associated facilities. As shown in Figure 1, Proposed Project

Albert A. Webb Associates

Reference Noise Level Projection Worksheet

Project: Entered By: MikeCity/County Agency: W.O.: 2007-0377

Subject Noise Source:

Unmitigated Noise Level:

Distance: Leq: Lmax: L2: L8: L25: L50:

Observer Elevation: Noise Source Elevation:Observer Height: Noise Source Height:

Distance: Dist. to Barrier: Barrier Height: Leq: Leq: Lmax: Lmax: L2: L2: L8: L8: L25: L25: L50: L50:

PR

OJE

CT

ED

DA

TA

0.0 feet5.0 feet

240.0 feet68.4 dBA- -- -- -- -- -

Weixiong Wu, Noise Assessment for Construction Noise Impacts, International Congress and Exposition on Noise Control Engineering, October 2008.

RE

FER

EN

CE

DA

TA

50.0 feet82.0 dBA- -- -- -- -- -

0.0 feet8.0 feet

- -

Riverside-Corona Feedermultiple

Unmitigated Noise Level:

240.0 feet

- -- -- -

0.0 feet- -

- -

Mitigated Noise Level:

Generator

ReferenceNoise Data Source:

Printed on 12/15/2008 at 12:10 PMG:\2007\07-0377\Noise\calculations\Microtunneling - Const. Equip. RNL Projections (75 dBA).xlsgenerator v2.0