risk topics and real options in capital budgeting chapter 11 © 2003 south-western/thomson learning

28
Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

Upload: daniella-newman

Post on 31-Dec-2015

219 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

Risk Topics and Real Options in

Capital Budgeting

Chapter 11

© 2003 South-Western/Thomson Learning

Page 2: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

2

Cash Flows as Random Variables Risk is chance that a random variable will take

on a value significantly different from the expected value In capital budgeting the estimate of each future

period's cash flow is a random variable The NPV and IRR of any project are random

variables with expected values and variances that reflect risk

• Thus, the actual value is likely to be different than the mean• The amount the actual value is likely to differ from the

expected is related to the variance or standard deviation

Page 3: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

3

Figure 11.1: The Probability Distribution of a Future Cash Flow as a Random Variable

Page 4: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

4

Figure 11.2: Risk in Estimated Cash Flows

Page 5: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

5

The Importance of Risk in Capital Budgeting

Thus far we've viewed cash flows as point estimates

However, since a project's actual cash flows are estimates we could be making a wrong decision by using point estimates for NPV and IRR

The riskiness of a project's cash flows must be considered when deciding upon a project

Page 6: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

6

The Importance of Risk in Capital Budgeting Risk Aversion

All other things equal, we prefer less risky capital projects to those with more risk

Changing the Nature of the Company A company is a portfolio of projects Thus, if a firm undertakes new projects while ignoring

risk, it could change its fundamental risk characteristics

• A company adopting riskier projects than it used to will become a riskier company

• Will lead to a higher beta• Can generally lead to a stock price reduction

Page 7: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

7

Scenario/Sensitivity Analysis

Involves selecting a worse, most likely and best case for each cash flow Most likely is the cash flow estimate we've worked

with before Recalculate the project's NPV (or IRR) under

each scenario Evaluating a number of scenarios gives a subjective

feel for the variability of the NPV to changes in our assumptions

• Referred to as sensitivity analysis

Page 8: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

8

Computer (Monte Carlo) Simulation Involves making assumptions about the shape of each

future cash flow A computer is used to quickly determine random

observations for each uncertain cash flows and determine numerous possible outcomes (1000s)

Computer then simulates project by constructing a probability distribution of the project's NPV (IRR)

Drawbacks Probability distributions have to be estimated subjectively Project cash flows tend to be positively correlated—hard to

estimate the extent of that correlation Interpretation of results is subjective

Page 9: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

9

Decision Tree Analysis

Decision Tree analysis lets us approximate the NPV distribution if we can estimate the probability of certain events within the project

A decision tree is an expanded time line which branches into alternate paths whenever an event can turn out more than one way The place at which branches separate is called a node Any number of branches can emanate from a node but the

probabilities must sum to 1.0 (or 100%) A path represents following the tree along a branch

• Evaluating a project involves calculating NPVs along all possible paths and developing a probability distribution

Page 10: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

10

Q: The Wing Foot Shoe Company is considering a three-year project to market a running shoe based on new technology. Success depends on how well consumers accept the new idea and demand the product. Demand can vary from great to terrible, but for planning purposes management has collapsed that variation into just two possibilities, good and poor. A market study indicates a 60% probability that demand will be good and a 40% chance that it will be poor.

It will cost $5M to bring the new shoe to market. Cash flow estimates indicate inflows of $3M per year for three years at full manufacturing capacity if demand is good, but just $1.5M per year if it’s poor. Wing Foot’s cost of capital is 10%. Analyze the project and develop a rough probability distribution for NPV.

Exa

mpl

eDecision Tree Analysis—Example

Page 11: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

11

Decision Tree Analysis—Example

A: First, draw a decision tree diagram for the project. Then calculate the NPV along each path.

Exa

mpl

e

$1.5M$1.5M$1.5M

($5M)

$3M$3M$3M

3210

P = .6

P = .4

NPV

$2.461M

$-1.270M

Then calculate the weighted NPV for the tree.

$1.077MExpected NPV =

$-.508M40%$-1.270MPoor

$1.585M60%$2.641MGood

ProductProbabilityNPVDemand

The decision tree explicitly

calls out the fact that a big loss is quite possible, although the

expected NPV is positive.

Page 12: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

12

Real Options

An option is the ability or right to take a certain course of action

Real options represent those that exist in a real physical, business sense

Real options frequently occur in capital budgeting Generally increase a project's expected NPV

• This increase is often a good estimate of the option's value

Page 13: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

13

Real Options

For example, suppose a sports apparel company sells jackets/sweatshirts with professional football team insignias and it depends on bank credit to support routine operations Firm usually has a bank loan of $1 million, but if local professional

team makes it to the Super Bowl demand is expected to double and the firm expects to need $2 million in bank credit

• Manager doesn't want to borrow the extra $1M--what if football team doesn't make it to Super Bowl?

• Company can pay a consultant fee to bank in which the bank agrees to lend firm the money if the company wants it

• Commitment fees usually about 1/4% annually of he unborrowed, but committed, amount (or 1/4% x $1M = $2,500)

• Bank charges normal interest rate on money once it is borrowed

• This arrangement gives the business the ability to take advantage of the potential increase, because it has the right (but not the obligation) to borrow the extra $1M

Page 14: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

14

The Abandonment Option

If a project is undertaken and eventually experiences poor demand, it is likely that the project will be abandoned The facilities and equipment (or the cash

flows generated from their sale) must be expected to have better use elsewhere

Page 15: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

15

Valuing Real Options

Real options are generally worth more than their impact on expected NPV because they generally reduce risk However, difficult to place a quantitative value to the risk

reduction

An Approach Through Rate of Return Lower risk should be associated with a lower rate of return in

NPV calculations—leads to a higher NPV calculation• Difficulty lies with choosing the right risk-adjusted rate

The Risk Effect is Tricky The value of real options has to be considered on a case-by-

case basis

Page 16: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

16

Designing for Real Options

Abandonment option—can increase expected NPV and lower risk Contractual obligations can make abandonment tough

Expansion options Frequently require little or no early commitment and should be

planned whenever possible Investment timing options

Allow a firm to delay an investment until it's sure about other relevant issues

Flexibility options Allow company ability to respond more easily to changes in

business conditions

Page 17: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

17

Incorporating Risk Into Capital Budgeting

The cost of capital (k) plays a key role in both NPV and IRR For NPV, k is used as the discount rate

• A higher k leads to a lower NPV, reducing the chance of project acceptance

For IRR, IRR is compared to k• A higher k leads to a lower chance of project

acceptance

Page 18: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

18

Incorporating Risk Into Capital Budgeting

Riskier Projects Should Be Less Acceptable Idea is to make risky projects less acceptable than

others with similar expected cash flows Using a higher, risk-adjusted rate for risky projects

lowers their chance of acceptance

The Starting Point for Risk-Adjusted Rates The current situation of the firm (in terms of risk) is

the starting point

Page 19: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

19

Incorporating Risk Into Capital Budgeting Relating Interest Rates to Risk

Interest rates are made up of a base rate plus a risk premium

Investors demand a higher risk premium and interest rate if they are to bear more risk

In capital budgeting the company is the investor, thus the firm's cost of capital is used as the discount rate for an average risk project

Choosing the Risk-Adjusted Rate for Various Projects Somewhat of an arbitrary process, subjective

Page 20: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

20

Incorporating Risk Into Capital Budgeting Some logic can aid in the process

Replacement projects involved replacing something the firm has already been doing

• Thus, the firm's cost of capital is nearly always appropriate for this type of project

Expansion projects are more risky than the current level, but not much more

• A rule of thumb is to add 1-3% points to the cost of capital New venture projects usually involve much more risk

than current projects• Choosing risk-adjusted rate is difficult and arbitrary

Page 21: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

21

Estimating Risk-Adjusted Rates Using CAPM The Project as a Diversification

If the firm is viewed as a collection of projects, a new venture diversifies the company

A new venture also diversifies the investment portfolios of the firm's shareholders

Diversifiable and Non-Diversifiable Risk for Projects Projects have two levels of diversifiable risk because they are

effectively in two portfolios at once• Some risk is diversified away within the firm's portfolio of projects• Some risk is diversified away by the shareholders' investment

portfolios The remaining risk is known as systematic risk

Page 22: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

22

Estimating the Risk-Adjusted Rate Through Beta The Security Market Line (SML) can be used to

determine a risk-adjusted rate for a new venture project SML: kx = kRF + (KM - kRF)bX

Where bX is beta, or the measure of a company's systematic risk If a capital budgeting project is viewed as a business in a

particular field, it may make sense to use a beta common to that field in the SML to estimate a risk-adjusted rate for analysis of the project This method is most appropriate when an independent, publicly

traded firm can be found that is in the same business as the new venture (pure play firm)

• Pure play firm must be solely in the business of the new venture

Page 23: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

23

Estimating the Risk-Adjusted Rate Through Beta—Example

Q: Orion Inc. Is a successful manufacturer of citizens band (CB) radios. Management is considering producing a sophisticated tactical radio for sale to the 'Army, but is concerned because the military market is known to be quite risky.

  The military radio market is dominated by Milrad Inc., which holds a 60% market share. Antex Radio Corp. Is another established competitor with a 20% share. Both Milrad and Antex make only military radios. Milrad's beta is .4 and Antex's is 2.0 Orion's beta is 1.1. The return on an average publicly traded stock (kM) is about 10%. The yield on short-term treasury bills (kRF) is currently 5%. Orion's cost of capital is 8%.

  The military ratio project is expected to require an initial outlay of $10 million. Subsequent cash inflows are expected to be $3 million per year over a five-year contract.

  On the basis of a five-year evaluation, should Orion undertake the project?

Exa

mpl

e

Page 24: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

24

Estimating the Risk-Adjusted Rate Through Beta—Example

S: The military radio business division would clearly be more risky than Orion's current business projects given the high betas of Milrad and Antex vs. Orion. Milrad and Antex are both pure play firms, but since Milrad is the market leader it probably has less risk than Antex. We need to use a beta from a company that will be in a similar position as our own firm; thus, we will use Antex's beta of 2.0 to evaluate the military radio project.

 First, we calculate the risk-adjusted beta for the project:

K = 5% + (10% - 5%)2.0 = 15.0%

Note that this rate is considerably higher than Orion's current 8% cost of capital.

 

Exa

mpl

e

Page 25: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

25

Estimating the Risk-Adjusted Rate Through Beta—Example

S: Next calculate the proposed project's NPV using the 15% risk-adjusted rate:

NPV = -$10.0M + $3M[PVFA15,5]= -$10M + $3M[3.3522]= $0.1M

 

 

NOTE: If the project had been evaluated at Orion's 8% cost of capital, it would have lead to an NPV of $2.0M; however, adjusting for risk has shown the project to be only marginal.

Exa

mpl

e Since the NPV is barely positive, the project is

marginal at best.

Page 26: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

26

Problems with the Theoretical Approach The biggest problem is finding a pure play firm

from which to obtain an appropriate beta Betas of conglomerates are influenced by other

divisions (in other industries) Thus, we have to estimate betas by using firms in

similar (but not exactly) the same businesses• Reduces the credibility of the technique

Another problem is that systematic risk may not be the only risk that is important If total risk is what's really important, it would lead to

an even higher risk-adjusted rate

Page 27: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

27

Projects in Divisions—The Accounting Beta Method

If a pure play division is found within a corporation, may be able to estimate the beta of that division using the accounting beta method Develop a beta for the division from its accounting

records (rather than stock price data)• Regress historical divisional return on equity against the

return on a major stock market index• Slope of the regression line represents the division's beta

Page 28: Risk Topics and Real Options in Capital Budgeting Chapter 11 © 2003 South-Western/Thomson Learning

28

A Final Comment on Risk in Capital Budgeting

Virtually every firm uses capital budgeting techniques but only a few overtly try to incorporate risk

Business managers do recognize risk but they do it judgmentally