risk management and assessment for business risktec...
TRANSCRIPT
Bow-tie Lessons Learned Slide 1
Risktec Solutions
Lessons Learned from Real World Application of
Bow-tie Method
2010 International Symposium
BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND NATURE
risk management and assessment for business
www.risktec.com
Bow-tie Lessons Learned Slide 2
Purpose of presentation
Bow-tie method
Example case study
Practical uses and benefits
Tips for successful use
Bow-tie Lessons Learned Slide 3
The “bow-tie” diagramC
on
seq
uen
ces
Process upset
Cau
ses
Preventive
controlsRecovery
preparedness
Bow-tie Lessons Learned Slide 4
In more detail
Hazard Conseq-uence
Threat
Top EventThreat
Threat
Conseq-uence
Conseq-uence
Prevention Mitigation
Barriers
Bow-tie Lessons Learned Slide 5
Example case study
Loss of containment
LPG storage bullets
Torch, pool or flash fire
Third-party interference
Internal corrosion
Overfill bullets
Overpressure bullets
other threats
Unignited VC - buildings
Unignited VC - neighbors
BLEVE
Bow-tie Lessons Learned Slide 6
Overpressure bullets
Loss of containment
What are the preventive controls?
Bullets rated 250/operate
179 psi
Operator monitors
level, P, T & quality.
PAH, LAH, TAH
HH –P trip (179 psi) S/D feed
Two PRVs (250 & 262 psi), sized
for fire case
Bow-tie Lessons Learned Slide 7
What are the mitigative measures?
Torch, pool or flash fire
Gas detection 10% LEL >> alarm, 40% >> plant ESD feed trip & isolation
Detect leak & alarm via
operator rounds or
CCTV. Plant S/D at local ESD buttons
or C/R
Muster & acct for
personnel
Fireproof supports
…8 mitigation measures in total
Multiple muster
areas on site, plus
offsite point
Muster areas impaired
Bow-tie Lessons Learned Slide 8
It’s more than a picture: who’s responsible and what must they do?
Torch, pool or flash fire
Gas detection 10% LEL >> alarm, 40% >> plant ESD feed trip & isolation
Multiple muster
areas on site, plus
offsite point
Muster areas impaired
Instr. Tech
Detect leak & alarm via
operator rounds or
CCTV. Plant S/D at local ESD buttons
or C/R
Operator
Muster & acct for
personnel
Training
Fireproof supports
Mech. Eng.
Safety Eng.Test and calibrate critical instrumentation, ESDs, P
& flow sensors & alarms, F&G detection
Bow-tie Lessons Learned Slide 9
What is the critical documentation?
Operator schedule &training matrix
Torch, pool or flash fire
Gas detection 10% LEL >> alarm, 40% >> plant ESD feed trip & isolation
Detect leak & alarm via
operator rounds or
CCTV. Plant S/D at local ESD buttons
or C/R
Muster & acct for
personnel
Fireproof supports
Multiple muster
areas on site, plus
offsite point
Muster areas impaired
Instr. Tech Operator
TrainingMech. Eng.
Safety Eng.Protective sys. spec. &
performance stds.
Emergency response plan
Review ER provision
PFP spec. & perf. stnds.
Bow-tie Lessons Learned Slide 10
Catalogue of process safety-critical activities
Safety-critical role Instrument Technician
Maintain protective instrumentation
Test (incl. integrity w hazardous area classification) & calibrate critical instrumentation in field locations:
- ESD systems
- P & flow sensors/alarms
- F&G detectors, systems & alarms
- Corrosion injection system alarms
Safety-critical activity Procedure Verification
SAP work order
Completed SAP work
order
Bow-tie Lessons Learned Slide 11
How good are the controls? Example barrier effectiveness rating scheme
Every barrier must be suitable: (1) independent and (2) competent responsible person undertakes critical activity to provide barrier
Barrier Rating Used? Does it work/is it effective?
Very Good Always Always (>99%)
Good Frequently Generally (75% - 99%)
Unknown Unknown/not guaranteed
Unknown/cannot be guaranteed (50% - 75%)
Poor Occasionally Possibly (25% - 50%)
Very Poor Rarely Currently ineffective (<25%)
Un-assessed - Insufficient information
Bow-tie Lessons Learned Slide 12
How good is each control?
Torch, pool or flash fire
Gas detection 10% LEL >> alarm, 40% >> plant ESD feed trip & isolation
Detect leak & alarm via
operator rounds or
CCTV. Plant S/D at local ESD buttons
or C/R
Muster & acct for
personnel
Fireproof supports
Multiple muster
areas on site, plus
offsite point
Muster areas impaired
Instr. Tech Operator
TrainingMech. Eng.
Safety Eng.
Bow-tie Lessons Learned Slide 13
What about overall control?
Every threat and consequence for every hazard must have sufficientbarriers of adequate rating
Requires scheme for assessing overall control– Avoid counting barriers (scheme
should be relative, not absolute)
Bow-tie Lessons Learned Slide 14
Overall control?
Provides a guide for focusing effort on risk reduction, rather than measuring acceptability:– What else can we do?– Can we improve control effectiveness?– Can we add more controls?– Is it practical to do so?
Bow-tie Lessons Learned Slide 15
Can we improve control effectiveness?
Operator
Torch, pool or flash fire
Gas detection 10% LEL >> alarm, 40% >> plant ESD feed trip & isolation
Detect leak & alarm via
operator rounds or
CCTV. Plant S/D at local ESD buttons
or C/R
Muster & acct for
personnel
Fireproof supports
Multiple muster
areas on site, plus
offsite point
Muster areas impaired
Instr. Tech.
TrainingMech. Eng.
Safety Eng.
Recommendation
Confirm muster pt. locations & arrangements appropriate for all credible
major accident scenarios (e.g. outside LFL)
Bow-tie Lessons Learned Slide 16
The complete picture
Display altogether, or one branch at a time
Strengths and weaknesses in process safety clearly visible
– Coloring of barriers
– Coloring of threats & consequences
Bow-tie Lessons Learned Slide 18
How can we use it in practice?
Logical structured approach
Do we have any gaps in risk control?
Communication How do we engage non-risk specialists?
Formal demonstration Can we really demonstrate control?
Specific risks Will we be in control?
Critical roles Do our people know what is expected of them?
Competencies Are competence and control requirements aligned?
Critical procedures Are they complete and effective?
Auditing How can we focus audits on what really matters?
Critical systems and performance standards
What are they?
Bow-tie Lessons Learned Slide 19
What do bow-ties do for you?
1. Improved understanding– Powerful communication tool– Readily understood– Clear identification of links– Keeps sight of big picture– Captures previous incidents
Bow-tie Lessons Learned Slide 20
What do bow-ties do for you?
2. Greater ownership– Encourages wide participation– Promotes positive ownership– Clear identification of roles and
responsibilities
Bow-tie Lessons Learned Slide 21
What do bow-ties do for you?
3. Efficiency gains– Less labor intensive – Helps focus resources– “A picture paints a thousand
words”– Targets critical maintenance,
inspection & testing activities – Avoids reinventing the wheel
Bow-tie Lessons Learned Slide 22
Tips for success
1. Pitch at the right level
2. Involve the right people
3. Use method to full potential
4. Avoid barrier counting but do verify quality of controls
5. Focus on risk reduction
Bow-tie Lessons Learned Slide 23
Summary
Improves understanding and encourages ownership of process safety
Provides missing link between plant, procedures & people (not just a pretty picture)
Provides structured framework for determining whether current control of process safety is good enough
Helps to ensure that risks are managed rather than just analyzed