risk management 1

41
Self Assignment Risk Management By Amit Agarwal

Upload: amit-agarwal

Post on 24-Oct-2014

146 views

Category:

Documents


2 download

DESCRIPTION

Risk Management Part - I

TRANSCRIPT

Page 1: Risk Management 1

Self Assignment

Risk Management

By Amit Agarwal

Page 2: Risk Management 1

OVERVIEW

1. WHAT IS RISK

2. WHAT IS RISK MANAGEMENT

3. INTEGRATED RISK MANAGEMENT

4. PRINCIPLES & CHARACTERISTICS

5. LIFE CYCLE

6. PROCESS CHART

7. CHALLENGES & BARRIERS

9. SUMMARY

8. KEY CONTRIBUTION FACTORS

Page 3: Risk Management 1

What Is “Risk”?

• “Risk is a condition in which there is a possibility of an adverse deviation from a desired outcome that is expected … .” (Vaughn)

• “… the threat that any event or action will adversely affect an organization’s ability to achieve its business objectives and execute its strategies.” (Kloman)

Page 4: Risk Management 1

• RISK = potential loss from inability to achieve a project’s objectives– caused by people, process, system, or external factors

• Risks can result from any combination of factors– people, process, systems, technology, science, or

external events

What Is “Risk”?

Page 5: Risk Management 1

Likelihood of an event occurring. The consequence if such event occurs.

• “….a measure of future uncertainties in achieving project performance goals and objectives within defined cost, schedule, and performance constraints.”

• “...an uncertain event or condition that, if it occurs, has a positive or negative effect on a project objective.”

Risk is…

Page 6: Risk Management 1

Applicability

• Financial, Market, Investment, Credit

• Health

• Environmental

• Business Compliance

• Safety

• Project (Types of Project)

• Security (Cyber, Physical)

• Mission Assurance

GOAL:

IDENTIFY / ASSESS THREAT

MINIMIZE / PREVENT LOSS

TAKE ACTION

Risk Management is applicable to all industries and complex efforts

Supports Decision Analysis Resource Allocation

Page 7: Risk Management 1

…the process of defining and analyzing risk, and then deciding on the appropriate course of action in order to minimize risk, whilst still achieving business goals

…he optimal allocation of resources to arrive at cost affective investment in defensive measures within an organization .It minimizes both cost and risk

…a variety of activities undertaken by an organization to control and minimize threats to the continuing efficiency, profitability, and success of its operations.

…the process of determining the maximum acceptable level of overall risk to and from a proposed activity, then using risk assessment techniques to determine the initial level of risk , if this is excessive, developing a strategy to mitigate appropriate individual risks until the overall level of risk is reduced to an acceptable level.

Risk Management is…

Page 8: Risk Management 1

• The systematic application of management policies, standards, procedures, and practices to the tasks of identifying, assessing, prioritizing, responding to, and monitoring risk– A structured, iterative process with defined scope and objectives– Proactive and anticipatory – Objective is to decrease the probability and/or impact of negative events OR

increase the probability and/or impact of positive events

Risk Management is…

Risk Management needs to be integrated into an organization’s decision making process

Page 9: Risk Management 1

Integrated Risk Management

• Integrate per Webster’s Dictionary: to form, coordinate, or blend into a functioning or unified whole

• Integrated risk management is a continuous, proactive and systematic process to understand, manage and communicate risk from an organization-wide perspective. It is about making strategic decisions that contribute to the achievement of an organization's overall corporate objectives.

• Integrated risk management process includes all disciplines required to support the life cycle of their system (e.g., systems safety, logistics, engineering, producibility, in-service support, contracts, test, earned value management, finance).”

Page 10: Risk Management 1

Providing insights into three key areas

Project Performance– Combines previously disparate project analysis and execution into an

actionable framework for the project manager– Requires dialog and collaboration between engineering, scheduling and

management groups– Creates a “total risk profile” for projects to fully assess potential delays to

delivery and increases in cost

Project Investment– Provides a framework to develop detailed plans for risk mitigation and

identify associated costs– Tracks progress of investment against specific mitigation activities– Assists decision makers in prioritizing investment against high impact risks

and effects

Page 11: Risk Management 1

Oversight– Responds to government policy guidance and industry best practices in risk

management– Provides auditable trail of risks, cost changes and schedule progress for

industry and government clients– Creates transparency in developing project budget and reserve

requirements when used prior to project start date

Providing insights into three key areas

Page 12: Risk Management 1

Risk Management Objectives

Post-Loss Objectives Pre-Loss Objectives

Survival Economic Efficiency

Continuity of Operations Reduction in Anxiety

Earnings Stability Meeting Externally

Continued Growth Imposed Obligations

Social Responsibility Social Responsibility

Page 13: Risk Management 1

…create Value

…be an integral Part of Organizational processes

…be a part of decision making

…explicitly address uncertainty

…be systematic & structured

…based on best available information

…be tailored / customized

…take into account human factors

…be transparent & inclusive

…be dynamic, iterative & responsive to change

…be capable of continual improvement & enhancement

Principles

Risk Management Should…

Page 14: Risk Management 1

A clear and consistent Risk Management champion

Requirements supported by leadership and stakeholders

A close partnership with users and stakeholders

Mature risk management processes

Established thresholds and criteria for proactively implementing defined risk mitigation plans

Resourced risk mitigation plans

Periodic risk assessments

Integrated data environments that maximize participation

Characteristics

Characteristics

Page 15: Risk Management 1

A documented and mature risk management process

Quantitative assessments of risk impacts estimated against cost and schedule baselines

Defined risk filtration criteria

Risk reduction at the lowest level of the organization

A defined set of risk consequence definitions for performance, schedule, and cost

Structured approached for communicating risk across multiple programs/organizational levels

Approaches

Successful Approach

Page 16: Risk Management 1

Stages in Risk Management Life Cycle

Stages Activity

Risk Management Planning Deciding how to approach & plan the risk management activities for the project

Risk Identification Determining which risks are likely to affect a project & documenting their characteristics

Qualitative Risk Analysis Characterization & analyzing risks & prioritizing their effects on project objectives

Quantitative Risk Analysis Measuring the probability & consequences of risks

Risk Response Planning Taking steps to enhance opportunities & reduce threats to meeting project objectives

Risk Monitoring & Control Monitoring known Risks, Identifying new risks, reducing risks & evaluating the effectiveness of risk reduction

Page 17: Risk Management 1

Risk Management LifecycleThe risk lifecycle applies across all parts of a program or project. .

FoundationalElements

HazardStrategicFinancial

Operational

Risk Areas

Governance

Programs

IT Investments

Procurement

Legislature

Strategic Planning

Risk Management

Human Capital

Department

Operations

PeopleTechnology

Process

5. Monitor, Assure & Escalate

4. Design &

Test Controls

3.Respond to

Risks

2.Assess & Measure

Risks

1. IdentifyRisks

Compliance

ExecutionComponents

Managing Risk

Page 18: Risk Management 1

Risk Identification

Identified Risks Rank

Inter-Agency / Department Actions 1

Changing Design Requirements 2

Cost estimating techniques 3

Legal / Regulatory / Ethics

Investigations and Audits

Contractor stability / quality 4

Natural Disasters

Roles of gov’t and contractor defined

Seasonality/Cyclicality

Identified Risks Rank

Budget and Funding Issues

Grants Management

Scientific Integrity and Agency ReputationThird Party Strategy / Execution / IntegrationEnvironmental liabilities / concernsValue for cost (value to taxpayers)Stakeholder Demand / Preference Changes

Political Issues 8

Hundreds of insignificant risks can easily distract from a few critical.

Identified Risks Rank

Financial Management

Hazardous materials handling 5

Technology

Terrorism and Emerging Diseases 6Capability Advancement

Insurance Coverage

Labor Disputes / Actions

Personnel and HR Issues 7

Identify the Top (relevant) Risks

Page 19: Risk Management 1

Risk Identification

Document Reviews

Brain Storming

Delphi Technique / Interviewing

SWOT Analysis

Checklists

Assumption Analysis

Flow Charting

Techniques

Page 20: Risk Management 1

Qualitative & Quantitative Risk AnalysisEvaluate each risk and its impact on cost, scope, and schedule.

Objective: Complete entire Project by 2010 within budget

Natural Environ.

Political

Social

Technological

Inter-Dept/Agency

Infrastructure

Personnel

Process

Technology

major weather event

dominate party change

constituent priority shift

technology innovationreorganization

Inte

rnal

Ris

ksEx

tern

al R

isks

Page 21: Risk Management 1

Qualitative :Probability Impact Matrix

Ordinal & cardinal Ranking

SWOT Analysis

Force Field Analysis

Quantitative:Sensitivity Analysis

Expected Monetary Value

Decision Tree Analysis

Simulation

Program Evaluation & Review Technique (PERT)

Techniques

Qualitative & Quantitative Risk Analysis

Page 22: Risk Management 1

Risk Response

Corrective Actions Inter-Agency Technology Risk NPolicies and ProceduresManagement Review & ApprovalsScenario PlanningContingency PlanningTraining and rehearsalsPhysical and Cyber SecurityEquipment Performance & DesignDocumentationCommunications plansPerformance IndicatorsSystem Controls / MonitoringPhysical Controls / MonitoringInspections / Audit Other

Choose the corrective actions, execute, and evaluate effectiveness.

Identify corrective actions Monitor effectiveness of actions

Page 23: Risk Management 1

Sample risk: Technology advances and innovation require design changes.1. Evaluate potential benefits of new technology. RKS Quarterly Conduct workshops, seek input2. Involve key stakeholders that are knowledgeable about technology innovation. AKH On-going Identify stakeholder liaison responsible

for maintaining buy-in3. Refine communications approach and execution to address on-going findings. VM Monthly Appoint communications coordinator to

maintain channels4. Update long-term roadmap for incorporation of key RNS Bi-

annuallyConduct routine roadmap updates to maintain buy-in

Q1 ‘09 Q2 ‘09 Q3 ‘09 Q4 ‘09 Q1 ‘10 Q2 ‘10 Q3 ‘10

Very High

High

Medium

Low

Very Low

# 1

#2,3

#2,3,4

#2,3

#2,3,4 Planned Actual

Incremental Mitigated Risk(Perform Cost/Benefit Analysis)

Corrective actions result in mitigated risk, but come with a cost.

Cor

rect

ive

Act

ions

Res

idua

l Ris

k

Contd…

Page 24: Risk Management 1

Monitoring & Control

Very Low Very

High

VeryHigh

Inhe

rent

(Gro

ss) R

isk

Current Residual (Net) Risk

310 Risk reduced to an acceptable levelRisk reduction occurring, not completeFurther action required

Corrective Action Status5 6

31

87

4 9

2

Inherent (Gross) Risk (without mitigation/controls) Residual (Net) Risk (without mitigation/controls)

Very High > 5 days disruption of core operational activities; long term impact to reputation; may result in government investigation

No viable mitigation plan in place, the risk event would likely overwhelm the agency

High 3 to 5 days disruption of core operational activities; concern that could result in an action; may result in official inquiry

Heroic efforts would be needed to manage the event

Medium Between 1 and 2 days disruption of core operational activities; unfavorable media coverage

Fairly well-prepared – base mitigation plans are in place; organization has talent/resources to manage through the event

Low Between 2 and 8 hours disruption of core operational activities; brief unfavorable media coverage

Mitigation responses, contingency plans and programmed responses have been or are being established

Very LowLess than 2 hours of disruption of core operational activities; no media coverage, unlikely to have an impact on the NIH appropriation

Mitigation responses, contingency plans and programmed responses are established, rehearsed on a periodic basis and revised as conditions change

Complete set of risks must be considered to understand the risk profile.

Example Risks:

1) Technology Innovation

2) Departmental Reorganization

Page 25: Risk Management 1

ResponseAvoidance

Transference of Deflect

Mitigation

Acceptance

Contingency

Reserves

Fallback Plan

Monitoring & ControlWorkarounds

Change Requests

Feedback into Risk Management Plan

Techniques

Risk Response, Monitoring & Control

Page 26: Risk Management 1

Integrated Risk Management extracts actionable information from traditionally stove-piped data streams

Enables critical decision making

Risk Exposure?

Impact Relationships?

Goals Too Risky?

Which Design?

More Reserves?

Major Drivers?

Adequately Mitigated?

Traditional Approach

Page 27: Risk Management 1

Risk Analysis

Cost Analysis

Schedule Analysis

Program Manager

Decision

Integrated Approach

Page 28: Risk Management 1

Risk Management Process

Quantify Risk– Cost, Schedule, PerformanceEvent AnalysisRelational analysis with existing risks and open issuesCost / Schedule ImpactsProbability ofOccurrence (RP)Impact of Occurrence (RI)

Identify Potential RisksEnter in Risk RegisterAssumption TestingData About the RiskUnderstand the Risk

Risk Exposureis High or Moderate

Risk Exposureis Low

Risk Management IPTEstablish Risk TriggersHandling StrategyContingency PlanAssign Resources

Escalate?Implement Handling StrategyUpdate IMSModification / Change OrderMonitor ActionsReassess

Risk Handling Replanning

Revised Handling Plan

Risk Has Been Handled

Risk Watch List

RIOM Board Consensus

Database

Program and Risk Management Tools

Contingency Plan

Step 1: Identify and Document Step 2: Analyze and Assess

Step 3: Select Handling Plan

Step 4: Handle and Monitor

Step 5:Handling

Step 3bStep 3a

Step 7: Document Step 6: Closeout

RIO

M B

oard

R

eass

essm

ent

Key Planned Re-planningLessons Learned

Page 29: Risk Management 1

Challenges

• Top 3 challenges in applying risk management– Improving risk communication– Political obstacles to risk-based resource allocation– Lack of strategic thinking

• Lack of comprehensive risk management strategies that are well integrated with program, budget, and investment decisions

• There have been attempts at acquisition reform to address the following areas:

A. Decisions regarding which programs to keepB. Developing approaches to better analyze and prioritize needsC. Better management of development cyclesD. Establish knowledge-based cost and schedule estimatesE. Detailed systems engineering planning

Page 30: Risk Management 1

Barriers to IntegrationBarriers

Lack of a clear and consistent Risk Management champion

Unclear or non-existent Decision rights

Silos of analyses and reporting of different risk types

Maturity

Technology, governance, process and people

Communication internal and external to the program/organization

Culture (How does the organization operate?)

Perception of a risk manager and roles/responsibilities

Every PM wants to do it their way

Organizational barriers regarding focal point of risk management

Page 31: Risk Management 1

Defining decision rights are an important aspect of a comprehensive risk management program

Clear Decision Rights Result in…Clear decision-making authority results in effective and efficient decision-making…– Places decision rights with those with

the knowledge and information to make the best decision

– Reduces the risk of poor decisions– Reduces inefficient second-guessing

What are Decision Rights?The underlying mechanics of how and by whom decisions are truly made in an organization

Unclear Decision Rights Causes…Unclear decision-making authority results in senior management involvement in too many issues…

…while lack of empowerment at the front-line can result in poor customer service and reduced employee satisfaction

Decision Making

Page 32: Risk Management 1

Cost-benefit analysis

Evaluation of frequency/severity

After-tax net present value analysis

Risk Map

Total Cost of Risk

Ethical considerations

Legal Requirements

Commercial Requirements

“Do not risk more than you can afford”

“Do not risk a lot for a little”

Tools & Techniques

Decision Making

Page 33: Risk Management 1

Programs with mature risk management processes have the following components

1. Structured process for risk identification2. Comprehensive risk baseline and categories3. Risk root cause analysis methodology4. Quantitative risk likelihood and risk consequence definitions5. An established risk management board or similar risk decision-making body

with robust participation6. A strong, defined risk management lead or champion for the program

Risk Management Maturity Scale• Calibrates the maturity of

individual program risk processes

• Guides enhancements needed to standardize approaches

Page 34: Risk Management 1

Risk Management Maturity Scale

Low: Coordinated Risk Management

STILL NEED TO ADDRESS:

– Common taxonomy– Alignment of risk

categories– Integrated toolset – Clarity in criteria and

thresholds for assessments

– Ownership– Decision Making

High: Integrated Enterprise Risk Management

Comprehensive risk agenda that exists throughout the entire organizationRisk management focus are cross-risk / cross-functional and aligned with strategic imperatives

– Linked to strategic and operational decision-making

Embedded in corporate cultureRisks are assessed and integrated across technical and agency performance elements, cost, and scheduleIntegrated tool set

MATURITY LEVEL

TIME/EFFORT

Page 35: Risk Management 1

Different Organizational Levels Face Different Types of Risks

- How does a risk to one program affect the delivery of other related programs?- Which external stakeholders have the ability to influence the success of one or more programs?- How can a successful risk mitigation strategy for one program be leveraged by other programs?

- Is the project on track to meet or exceed its threshold requirements?- How do current risk levels impact the ability to meet critical schedule milestones?- Which design solution provides the optimal balance between capital and operating costs?

- What are the technical performance risks associated with delivering a given requirement or capability?- How will assembly, integration, and test schedules be impacted by a given risk event?- What are the cost impacts of delays in subcontractor deliveries?

Risks ultimately should be filtered to the lowest level possible for ownership and mitigation

Enterprise Level

Program Level

Project Level

Subproject Level

RISKS

Page 36: Risk Management 1

Risk Management can inform decision rights within an organization

Questions

What are most vulnerable areas of the business/organization/acquisition/program/project/capability and what are the key risks that these areas face?

Is there a systematic and comprehensive approach for identifying and assessing these risks and is it communicated?

Is there a consistent and well defined approach to risk prioritization?

Does the process add value to decision analysis or is it merely a reporting mechanism?

Are decision rights aligned appropriately with risk tolerance? – Level of risk assessed can determine required level of decision-making within

the organization

Page 37: Risk Management 1

Key Contributors to Success

Risk Management promotes a clear value proposition

Program input actively sought for framework development.

A clear and consistent risk sponsor.

• Demonstrate how resources will be saved or more efficiently applied

• Demonstrate how information will be more widely shared

• Establish working group or other forum

• Gather feedback prior to go-live• Promotes buy-in

• Sustains participation

• Creates understanding of information• Defines linkages

Integrate Cost, Schedule and Risk personnel

COMMUNICATION

Page 38: Risk Management 1

What’s in it for me???C

ontr

acto

r Pr

ojec

t Man

ager

sFr

ont L

ine

Engi

neer

Prog

ram

M

anag

ers

Top

Man

agem

ent

Mid

dle

Man

agem

ent

Leaders, managers, and staff alike benefit from risk management.

•Higher impact programs•Better control of the overall portfolio•Stronger focus on long-term rather than short-term•Time to focus on areas currently neglected

•More predictable cost estimates•Less chaotic days, that are more productive•More visibility in project activities•Fewer and simpler reporting requests

•Better client relationships•More predictable quality of life•Mechanism to raise issues and have resolved•More follow-on work

Page 39: Risk Management 1

Con

trac

tor

Proj

ect M

anag

ers

Fron

t Lin

e En

gine

erPr

ogra

m

Man

ager

sTo

pM

anag

emen

tM

iddl

eM

anag

emen

tCritical success factors…

•Seek and maintain senior leadership sponsorship•Establish common language for risk management•Integrate risk management across programs•Focus on changing the culture, not on executing the tactics

•Assign ownership of risks as appropriate (gov’t, contr.)•Coordinate risk management across project•Focus on the value to all of managing risk, not the burden

•Raise ALL risks identified “on the ground”•Designate operational accountability for corrective actions •Make risk management a priority

Everyone has a role to play in making risk management part of the culture.

Page 40: Risk Management 1

Summary

Executive sponsorship does not use risk management as a blunt instrument

Management team must be informed and committed

Accurately size the risk management effort to the Project

Do not bury the risk management functions in the bowels of the organization—Private sector companies have a CRO

Cost Estimators, Schedulers, and Risk Management personnel collectively make up the risk management core team

Communication within Risk Management Core Team

Page 41: Risk Management 1

Tata Power

Risk Mitigated

By Amit Agarwal

Thank You