Lesson risk assessment form
School: Oriel High School Room: MM3
Person(s) carrying out risk assessment: Annie Hawkins Date: 09/05/13
Class: Yr 8
Step 1: Assess individual criteria for each risk Step 2: Total each category and highlight assessmentNo significant risk 0 0-4 Little significant risk LSR
Low risk, satisfactory 1 5-8 Some risk but possible to control SRC
Moderate risk. Some action required 2 9-12 Risk is significant and action required.
Report to be made
RSA
Potentially high in certain situations. Action to
control required
3 13+ Immediate action required. Report to
senior managers and record actions.
Activity must not be carried out until
problem(s) is controlled or eliminated.
IAR
High risk. Urgent action to control or eliminate 4
Workspace and resources Comments
1a space and size 0 Students will be using soldering irons set up in twoareas of the room. There is no trip hazard however
students need to be made aware that the wires are
hazardous if burned. Students will need to be shown
how to use a soldering iron safely.
1b layout 3
1c complexity of equipment 3
1d sufficiency and quality of equipment 0
Total 6 LSR SRC RSA IAR
Nature of curriculum and organisation Comments
2a type and range of activity 3
2b individual and group work 0
2c Length of session 0
2d Scheme of work 0
Total 3 LSR SRC RSA IAR
Management of learning Comments
3a staff and safety training 0
3b staff experience and competence 0
3c Staff control and motivation of pupils 2
3d level of additional support 0
Total 2 LSR SRC RSA IAR
Nature and number of pupils in the group Comments
4a pupils ability to self-organise 0 Keep an eye on behaviour and noise level throughout
the lesson. Any students misusing equipment ordemonstrating potentially hazardous behaviour will
miss a go on soldering and will be one step behind- if
behaviour continues the student will be removed from
their table to sit alone and will have an after school
detention where they will need to catch up.
4b potential behaviour problems 3
4c pupils with disabilities 0
4d pupils with language/learning difficulties 0
Total 3 LSR SRC RSA IAR
Step 3: Total all four categories and highlight overall risk assessment
Action to be taken Overall total 14
Aware of students positions in theroom
Aware of students behaviour Aware of the condition of the
tools/machines being used and ensure
0-12 Generally safe working environment
13-20 Some risk which needs attention and monitoring
21-35 Action required. Report to senior staff and safetyrepresentative. Address before teaching
36+ Serious health and safety risk requiring urgent
-
7/30/2019 Risk Assessment Year 8 Sc
2/2
Note that this risk assessment may refer to departmental risk assessments, CLEAPSS assessments or BS4163 as appropriate. Action to be taken should be completed in all
eventualitieseven if None necessary is the response. Analysis/report may be continued overleaf.
that appropriate tools are being used in
the correct and safe way
attention and inspection. Full written report
required. Do not teach until addressed.