review of the ercot december 18, 2008 nodal cost benefit study

Upload: robertmccullough

Post on 30-May-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    1/16

    McCulloughResearch

    ReviewoftheERCOT

    December18,2008Nodal

    CostBenefitStudy

    January7,2009

    RobertMcCullough

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    2/16

    ReviewoftheDecember18,2008NodalCostBenefitStudy

    January7,2009

    RobertMcCullough

    2|P a g e

    OverviewOnDecember18,2008,CRA InternationalandReseroConsultingreleasedastudythatconcludedthat

    the benefits of continuing the shift to nodal markets from the existing zonal system significantly

    outweighedthecosts. Theyreportedbenefitsintwodifferentforms. First,theareaofTexasservedby

    ERCOTwouldexperiencea$520millioncostreduction,whilerequiringonly$222million inadditional

    computer programming costs. Second, the new market design would reduce costs to ERCOTs

    consumersby$5.6billion.

    Acarefulreviewrevealsseriousquestionsconcerningitsaccuracyandcraftsmanship. Thescopeofthe

    new study is 2011 to 2020, although only the first two years are actually modeled. The period from

    2013through2020issimplyarepeatedcutandpastefromtheresultsfor2011and2012. Moreover,

    thebenefitsduetothesitingofnewgenerationaresimplyassumedfromtheresultsofthe2004cost

    benefitstudy. Overall,only17%ofthe$520millionsavingsactuallyresultsfromthecomputermodel

    described in the report. The remaining 83% of the benefits are the product of various ad hoc

    adjustments.

    Similarly, the $5.6 billion in consumer benefits are also based on modeling that stops in 2012 even

    thoughresultsarereportedthrough2020. Thissurprisingresultthatashift incomputeralgorithms

    will dramatically reduce revenues for electric generators reproduces the conclusions of the 2004

    study. In both cases, the result relies on the assumption that generator bids are fixed at short term

    marginal costs. Unfortunately, this is not the case inTexasandother areas thathave adoptednodal

    pricing.

    Strategicbidding

    (bids

    vastly

    higher

    than

    marginal

    costs)

    is

    acentral

    feature

    in

    ERCOT.

    In

    any

    market where bids can be easily changed to recapture the assumed revenue loss, such gains for the

    consumerarebothspeculativeandeasilycorrectedbyadjustingthebids. The$5.6billionestimatealso

    containsasignificanterroracriticalratioused inthecalculation isbasedonvaluestakenfromyears

    beforenodalmarketsareactually implemented. Overall,the$5.6billiontracesonly17%tocomputer

    modelingandwiththeresidual83%representingpoorlydocumentedadhocadjustments.

    Noattemptwasmadetocalibratethestudytoactualconditions (knownasbackcasting). Nordidthe

    authors estimate the sensitivity of their results to their assumptions. Since some assumptions were

    unusual,the lackofsensitivitytesting isparticularlyproblematic. Thecostreduction inthetwoyears

    actuallymodeled

    is

    only

    .04%

    of

    annual

    production

    costs,

    aslender

    margin

    in

    aworld

    where

    the

    cost

    of

    oilincreased100%in2008beforefalling75%bytheendoftheyear.

    Theestimateof$222millioninadditionalcomputerprogrammingcostsisalsoproblematic. Inactuality,

    theDecember18,2008studyassumes$429millioninadditionalcomputerprogrammingcoststhatare

    offset by $207 million of additional computer programming costs to refresh the existing market

    design. WhiletheDecemberstudyestimatesmaintenancecostsforthenewcomputerprogramas$14

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    3/16

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    4/16

    ReviewoftheDecember18,2008NodalCostBenefitStudy

    January7,2009

    RobertMcCullough

    Atfirstglance,thistableappearstorepresentaneditorialdecisiontoomitthefullsetofresultsinthe

    interestofbrevity. Acloserreadingmakesclearthattheseyearsaretheonlyyearsusedintheupdated

    study:

    TheNPVfrom2011to2020 isestimatedtobe$339million,assumingthatproduction

    costsandresultingbenefitsobservedforthefirsttwoyearsofoperationremainatthe

    samelevelonaveragethrough2020.2

    ThecompletetablecanbereverseengineeredfromtheprojectedNPVonthefinallinesofTable5:

    Table5:AnnualProductionCostbyScenario(inreal2008dollars)

    ZonalCase NodalCase Benefit(Zonal Nodal)

    ($Million) ($Million) ($Million)

    2009 12,928.6 12,892.0 36.6

    2010 12,319.2 12,277.1 42.1

    2011 12,211.2 12,164.4 46.8

    2012 12,212.0 12,164.0 48.0

    2013 12,211.2 12,164.4 46.82014 12,212.0 12,164.0 48.02015 12,211.2 12,164.4 46.82016 12,212.0 12,164.0 48.02017 12,211.2 12,164.4 46.82018 12,212.0 12,164.0 48.02019 12,211.2 12,164.4 46.8

    2FinalReport,December18,2008,page9.

    4|P a g e

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    5/16

    ReviewoftheDecember18,2008NodalCostBenefitStudy

    January7,2009

    RobertMcCullough

    5|P a g e

    2020 12,212.0 12,164.0 48.0AverageAnnual(20112012) 12,211.6 12,164.2 47.4

    ProjectedNPV

    (2011

    2020)

    86,378

    86,039

    339

    Therowsadded in italicswerenotmodeled intheDecemberstudy,which insteadmodeled2011and

    2012,andthenthesameresultsweresimplycutandpastedfortheremaining80%ofthestudyhorizon.

    This unusual methodology is surprising given the problems that arose in the 2004 study in modeling

    ERCOTsproductioncostsafter2012:

    TCA believes that specific predictive conclusions should not be based on TCA results

    obtained for 2013, and especially 2014. This is because the massive addition of new

    generatingresourcesmodeledforoutyearsisnotsupportedbytransmissionupgrades.3

    Thissame

    conclusion

    also

    occurs

    later

    in

    the

    2004

    report:

    Themidtermtrendcontinuesforanotheryear(2012),butisreversedin2013and2014

    duetodifficultiesassociatedwiththemodelingoffurthercapacityexpansiondecisions

    intheabsenceoftransmissionupgrades.4

    Table34intheNovember2004reportclearlyshowstheproblem:

    3FinalReport,November24,2004,page316.

    4FinalReport,November24,2004,page322.

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    6/16

    ReviewoftheDecember18,2008NodalCostBenefitStudy

    January7,2009

    RobertMcCullough

    In2013,thebenefitsofmovingtoanodalsystemarereducedbyover50%. Inthefollowingyearthe

    resultsactuallyindicatethatthezonalsystemissuperiortothenodalsystem.Althoughitmaymerelybe

    acoincidence,itisinterestingthattheDecember2008studystopsmodelingintheyearwhereproblems

    aroseintheNovember2004study.

    The second componentof nodalbenefits is the potentialadditional precisionofdata forpowerplant

    siting.

    The

    December

    2008

    study

    assumes

    the

    value

    of

    improved

    generation

    siting

    by

    a

    particularly

    arbitraryprocedure:

    Assuming70% inadditionalbenefitsattributable to improvedgenerationsitingovera

    periodof2013 through 2020 (when generation capacitywillbe needed inaddition to

    6|P a g e

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    7/16

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    8/16

    ReviewoftheDecember18,2008NodalCostBenefitStudy

    January7,2009

    RobertMcCullough

    8|P a g e

    Only a small fraction of the reported results come from modeling using current loads, fuel prices,

    generation, and transmission. The vast majority of the results come from ad hoc adjustments the

    reuse of earlier years results in lieu of completing the modeling and proration of results from the

    November2004study.ConsumerPaymentSavingsThe most significant numbers in the December 2008 study concern consumer benefits. The authors

    indicate thatbetween2009and2012consumerswillseeanannualaverage$576.6million insavings

    duetothereimbursementofcongestionrentsandotherbenefits. Thisvalueisthenratioedupby

    the fraction that the average benefits had between 2005 and 2008 to total benefits estimated in

    November2004.

    This approach is extremely speculative. As noted above, the new study represents different years,

    different resources, different fuel prices, and different transmission capabilities. To compound the

    problems,theratiousedisbasedontwoyearswhenthenodalmarketwillnotbeoperating,sotheratio

    itself, regardless of its legitimacy, is in error. Finally, the assumption addressed below, that ERCOT

    generatorswillrestricttheirbidstoshorttermmarginalcost, isbothunrealisticand likelyto leadtoa

    massiveoverestimateoftheconsumerpaymentsavings.

    Thecalculationdescribedonpage34oftheDecember2008reportis:

    1. Identifytheconsumerpaymentsavingsfor2005through2014fromtheNovember2004report$7.3billion.

    2. Averagethecongestionrentsfor2009through2012fromtherevisedmodelusedintheDecember2008study.

    3. Averagethecongestionrestsfor2005through2008fromtheoriginalmodelusedintheNovember2004report.

    4. Dividethe2004modelresultbythe2008modelresultgettingafactor1.29.5. Dividethe2004valueforconsumerpaymentsavingsby1.29toget$5.6million.

    Thiscalculation issounusualthat it isdifficulttoseeanyeconomic logic in itsderivation. There isno

    reason

    to

    believe

    that

    there

    is

    any

    logical

    comparison

    between

    market

    conditions

    in

    2005

    through

    2008

    asestimated fouryearsagoandthecurrent forecast for2009 through2012. Even ifthemarkets

    were similar, despite the changes in generation, fuel prices, and transmission, the appropriate

    comparisonwoulduseyearsinwhichthenodalmarketwasactuallyoperating,not2009and2010when

    ithasnotyetstarted.

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    9/16

    ReviewoftheDecember18,2008NodalCostBenefitStudy

    January7,2009

    RobertMcCullough

    LocalCongestRentfor

    2011and2012

    17%

    Ratioto2004Study's

    Values

    for

    Consumer

    Benefits

    83%

    AssumedValuesConstitutes83%ofTotalConsumerBenefitsfromShiftingtoNodalMarkets

    Aside from the illogic of the calculation, the economics of this argument are also suspect. ERCOT is

    characterized by a severely oligopolistic market structure of many buyers and few sellers. Strategic

    biddingisacontinuingfeatureofERCOTsmarketswithbidsandpricesoftenatmultiplesofshortterm

    marginal cost. If, as the authors assume, local congestion rents reduced the revenues of producers,

    economic theory would lead one to expect that strategic bidding may increase to recover the

    generatorsrevenues.

    ThemajorgeneratorinERCOT,Luminant,routinelysubmitsbidsat$300/MWh. Wheninvestigatedby

    theTexasPublicUtilitiesCommission,Luminantdefendeditsstrategicbiddingpracticesbyarguingthat

    suchhighbidswererequiredtocoveritstotalcostsofgeneration. Whileitsargumentmighthavehada

    poorgrounding ineconomics, it was a perfectly logical argument fora price leader in an oligopolistic

    market. IfLuminantsactualcosts increasedafternodalmarketswereadoptedbyERCOT, it is logical

    thatitwouldaddthecoststoitsstrategicbids,notpassivelyacceptareductioninincome.

    9|P a g e

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    10/16

    ReviewoftheDecember18,2008NodalCostBenefitStudy

    January7,2009

    RobertMcCullough

    10|P a g e

    BackcastingAn important featureoftheNovember2004reportwasanattempttotest itsaccuracyagainstactual

    pricesandoperationsfor2003. Thisisastandardstepforanycomplexcomputermodel. Backcasting

    results for the November 2004 model were poor: overall ERCOT forecasts were 25.4 $/MWh against

    actual prices of $29.1/MWh. This represents an error on theorderof15%,a fairly poorshowing for

    forecastingthepreviousyear.

    The December study dispenses with backcasting altogether. This omission is puzzling since the

    December2008modelforecastedtwoyears(2009and2010)ofnospecialinteresttothependingpolicy

    decision. These two years are not used in the calculations (with the exception of their erroneous

    inclusionintheratiousedtoassumeconsumerbenefits)sincethenodalmarketisnotforecasteduntil

    2011. Belowisanexplanationbyyear:

    2007 Notmodeledasabackcast

    2008 Notmodeledasabackcast

    2009 Nodal market not in operation modeled but not used in the present value of

    productioncostsavings

    2010 Nodal market not in operation modeled but not used in the present value of

    productioncostsavings

    2011 Nodal market in operation modeled and used in present value of production cost

    savings

    2012 Nodal market in operation modeled and used in present value of production cost

    savings

    2013 Nodalmarketinoperationnotmodeledandresultsassumedtobeequalto20112012

    2014 Nodalmarketinoperationnotmodeledandresultsassumedtobeequalto20112012

    2015 Nodalmarketinoperationnotmodeledandresultsassumedtobeequalto20112012

    2016 Nodalmarketinoperationnotmodeledandresultsassumedtobeequalto20112012

    2017 Nodalmarketinoperationnotmodeledandresultsassumedtobeequalto20112012

    2018 Nodalmarketinoperationnotmodeledandresultsassumedtobeequalto20112012

    2019 Nodalmarketinoperationnotmodeledandresultsassumedtobeequalto20112012

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    11/16

    ReviewoftheDecember18,2008NodalCostBenefitStudy

    January7,2009

    RobertMcCullough

    11|P a g e

    2020 Nodalmarketinoperationnotmodeledandresultsassumedtobeequalto20112012

    Intheabsenceofabackcast,thereisnoevidencethattheDecemberstudyisabletoreproduceprices

    andoperationsinERCOTwithanyaccuracywhatsoever.

    AssumptionsTheauthorsstateonpage68:

    A. Marginal Cost Bidding: All generation units are assumed to bid marginal cost(opportunity cost of fuel plus nonfuel VOM plus opportunity cost of tradable

    permits).

    To

    the

    extent

    that

    real

    markets

    are

    not

    perfectly

    competitive,

    the

    model

    tendstounderestimateprices.7

    This decision to make this assumption is not surprising. The original November 2004 report

    madeasimilarassumption:

    The assumption of shortrun marginal cost bidding can be overridden, implementing

    strategicbiddingbehavior,buttheeffortrequiredtodothisisconsiderable;priortothe

    contractingprocess,theCBCGchosenottopursuethisapproach.Notethatthroughout

    this report the use of the term marginal cost means refers to shortrun marginal

    costs.8

    Unfortunately,this isapoorassumptionforamodeldesignedtosimulatemarketprices. Ina

    condition of perfect competition, bids will approximate marginal cost. The critical condition

    precedentisperfectcompetition. ERCOTmeetsfewoftheconditionsofperfectcompetition,

    andstrategicbiddingisacontinuingprobleminERCOTadministeredmarkets.

    Recently,LuminantsettledacomplaintbyTexasregulatorsforstrategicbidding.9 Attheheart

    of the investigation was the appropriateness of TXUs exercise of market power. In practice,

    TXUtendstobidthevastmajorityofitsresourcesat$300/MWHregardlessofthemarginalcost

    oftheunits.10

    7FinalReport,December18,2008,page68.

    8FinalReport,November24,2004,page33.

    9NoticeofViolation,Docket34061,March28,2007.

    10Ibid.,page26. Thetermsbidcurveandmarginalcostwereadded.

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    12/16

    ReviewoftheDecember18,2008NodalCostBenefitStudy

    January7,2009

    RobertMcCullough

    TXUsstrategicbiddingwasobviously importantwitnessthecomplaintfiledbyPUCstaff. Moreover,

    the deviation between the marginal cost of coal units and $300/MWh bids dwarfs any possible

    efficiencyadvantageslikelytoresultfrommoreprecisepricinginthenodalmodel.

    Modelingofstrategicbidding isachallenge. Oligopolisticpricingdecisionsarecomplexandvarywith

    circumstances. As noted above, when the largest single market participant makes strategic bids for

    thousands of megawatts, it is imprudent to ignore this information when modeling. In the example

    takenfromthePUCcomplaint,thesignificantdifferenceinpricesisadifferenceof$200/MWh. Thebias

    thisassumptionwillcreateinthemodelingdwarfstherelativelysmallproductioncostdifferencesinthe

    December

    2008

    report.

    The most important operational assumption after bidding behavior is the cost of natural gas. The

    authorsdonotincludedetailedinformationonnaturalgasandcoalpricesusedintheirmodel.Thereis,

    however,ashortdiscussionofthesourcesofthenaturalgasforecastsonpages68and69. Preparedin

    a year of unprecedented fuel price volatility, the authors make the decision to base forecasts on the

    2008 EIAs natural gas forecast published a year ago. The Energy Information Administration makes

    forecastsonbothanannualandamonthlybasis. EIAsannualforecastsarereleasedinmidDecember,

    12|P a g e

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    13/16

    ReviewoftheDecember18,2008NodalCostBenefitStudy

    January7,2009

    RobertMcCullough

    thus making the 2008 forecast a full year out of date. While using forecasts from a year ago would

    normally be defensible, 2008 was hardly a normal year. Within 2008 prices for natural gas used for

    electricgeneration

    increased

    over

    50%

    by

    July

    2008

    and

    in

    the

    latter

    portion

    of

    the

    year,

    they

    fell

    even

    moreprecipitously.

    $

    $2.00

    $4.00

    $6.00

    $8.00

    $10.00

    $12.00

    $14.00

    $/MWh

    EIAShortTermandAnnualForecastsforNaturalGas

    2008AEO December2008STEO

    Forecasting fossil fuel prices has become increasingly difficult over the past few years and the use of

    superannuatedforecastsisanextremelybadstepinanymodelingexercise. Notwithstanding,thedated

    naturalgasforecast,theuseofasinglerelativelyoptimisticpointforecast isnolongerappropriate

    regardless

    of

    its

    source

    or

    age.

    The

    standard

    approach

    to

    this

    problem

    is

    to

    prepare

    sensitivities

    for

    high, medium, and low fossil fuel prices so that decisionmakers can see the impactof unpredictable

    fossilfuelpricesonthemodelresults.

    Additionalassumptionsandcalculationsarepoorlydocumentedormissing,including:

    1. NPVcalculationsforsystemcosts2. NPVcalculationsforcustomersavings

    13|P a g e

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    14/16

    ReviewoftheDecember18,2008NodalCostBenefitStudy

    January7,2009

    RobertMcCullough

    3. UPLANresults4. GEMAPSresults5. SOxandNOxrequirementsandforecastedcosts6. Plantassumptions.

    Theauthorsalsoneveraddresstherealdiscountrate,avaluethatoftendrivesresultsinmodelswhere

    costsandbenefitsoccuratverydifferenttimesinthefuture. ThisistrueoftheDecemberstudywhere

    computer programming costs largely occur before the onset of the nodal market. The estimated

    benefits, of course, result only after nodal market implementation. It should be noted also that the

    authorsadopt thediscount rate from theNovember2004study inspiteof theturmoil in theworlds

    financialmarketsandtheglobalrecession.

    ComputerProgrammingCostsPerhaps most mysterious is the expected cost to complete the computer programming for the nodal

    market. Althoughnotexplicitlystated,thetotalexpectedbill isontheorderof$750million,ofwhich

    $322.1 has already been spent.11 Table 13 identifies a present value of future expenditures of $430

    million.12 Whilebeyondthescopeofthisreview,thepriceforthisrelativelystraightforwardcomputer

    program is quite high by industry standards, especially for a single state with limited interties to the

    surroundingmarkets. Table15showsthefullcostofthecomputerprogrammingexercise:

    14|P a g e

    11FinalReport,December18,2008,page11.

    12Ibid.,page40.

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    15/16

  • 8/14/2019 Review of the ERCOT December 18, 2008 Nodal Cost Benefit Study

    16/16

    ReviewoftheDecember18,2008NodalCostBenefitStudy

    January7,2009

    RobertMcCullough

    16|P a g e

    programasarelativebargainat$14.1millionperyearoverthe firstdecadeof itsoperation,which is

    approximately onethird of the maintenance costs for the existing program. Assuming that the zonal

    programsmaintenance

    costs

    have

    been

    overstated

    by

    afactor

    of

    three,

    this

    would

    increase

    the

    net

    cost

    to continue the nodal program by $106 million, yielding a net going ahead cost of $326 million, as

    opposed to $222 million. Alternatively, if maintenance costs of the nodal program are assumed to

    matchthecostsofthezonalprogram,thetotalgoaheadcostswould increaseto$452milliondollars,

    insteadofthereported$222million.

    Ineithercase,theconclusioninTable15appearsvastlyunderstated.

    ConclusionsThe December 18, 2008 study has a number of problems. These appear significant enough that the

    conclusions of thestudy areeffectivelyspeculative. Inaddition, thestudy is poorlydocumentedand

    dependsonanumberofunusualassumptions.

    1. Thestudyhasonlymodeledtwoyearsofthetenyearperiodunderanalysis. Thisfailingaffectsboth the estimate of production costs and consumer benefits. The current modeling ends

    beforetheyearwhenthe2004modelappearedtohavesignificantproblems.

    2. Thestudyhasnotverifiedtheirmethodologybydoingabackcast. Intheabsenceofabackcast,theresultscannotbedependedupontoevenremotelyreproduceconditionsinERCOTmarkets.

    3. Several assumptions are highly questionable. The study assumes marginal cost bidding bymarket participants even though this is not present in ERCOT. In addition, the study uses anatural gas forecast from a year ago a curious choice in such volatile times. Other

    assumptions are undocumented or simply copied from a study four years out of date the

    discountrate,forexample.

    4. The costs of the additional computer programming appear high very high and theassumptions appear inconsistent. The high maintenance costs assumed for the existing

    operationalzonalmodelappeartobejustafractionoftheassumedmaintenancecostsofthe

    new,unfinishedandvastlymorecomplex,nodalmodel.