Page 1: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team
Page 2: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Resource Management in the Corporate Project Management Systems

Vladimir LiberzonVictoria ShavyrinaLiubov Guzhova

Spider Project Team

Page 3: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Introduction

• In this presentation we will discuss proven resource management methodologies, tools and techniques that are used in the corporate project management systems in Russia, Eastern Europe, Brazil.

• The questions during the presentation are welcomed!

Page 4: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Introduction

• We will discuss the following topics:

1. Project Schedule Model Data Structure

2. Corporate Project Management System Requirements

3. Project Resource Constrained Scheduling

4. Project Success Criteria

5. Portfolio Resource Constrained Scheduling

6. Project Performance Measurement

Page 5: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Part 1

Project Schedule Model Data Structure

Page 6: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Data Structure

• The main elements of any project schedule model are:– project activities,– activity dependencies,– resources,– resource assignments,– calendars,– costs,– Work, Resource and Cost Breakdown Structures.

Page 7: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

7

Activities

In the majority of well-known PM software packages project activities are characterized by their duration or effort.

But in most projects it is necessary to set the activity’s physical volume of work.

Activity volume can be measured in physical units (meters, tons, etc.), planned work hours, percents or any other units.

Page 8: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

8

Activities

Activity volume is often used as an initial activity information instead of duration. If assigned resource productivity is defined in volume units per hour then activity duration may be calculated during project scheduling.

Unlike activity duration activity volume does not depend on assigned resources.

Page 9: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

9

Dependencies

Special Requirements: It is necessary to be able to set more than one link

between two activities. Besides the positive and negative time lags, it is useful

to set volume lags, that is preferable in many cases. One of the potential problems with time lags is that slower

performance of the preceding activity may lead to time lag too early completion when expected volume of work was not done. The time lags call for special attention and regular adjustments.

Page 10: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

10

Resources

Resources are divided into two classes: renewable (human resources and mechanisms) and consumable (materials, equipment).

In our software they are not just resource types, but different objects (Resources and Materials).

It makes possible to define that renewable resources consume materials during their work (car consumes gas, etc.).

Page 11: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

11

Complex Resources

Besides the individual resources it is useful to set resource crews (we call them multi-resources) and resource skills (roles).

Multi-resource is the settled group of resources working together (e.g. a team, a crew, a car with a driver, etc.).

Multi-resource can be assigned to activity which means assignment of all resources comprising the multi-resource.

Page 12: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

12

Resource Skills

Resources belong to the same Skill set If they can do the same types of work (share the same skill).

Resources belonging to the same Resource Assignment Skill are interchangeable though individual resources may have the same skills but different productivities performing the same activities.

Page 13: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

13

Calendars

The calendars can be set for all activities, resources and time lags.

Availability of all these calendars is important for the proper project simulation.

Page 14: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

14

Resource Assignments

Assigning resources to activities implies the notion of a team - a group of resources working on an activity together.

The team can include individual resources, multi-resources and skills.

Resources belonging to different teams can work at different time periods. Teams work independently of each other.

An example: resources that work in different shifts belong to different teams.

Page 15: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

15

Resource Assignments

If activity’s initial information is work volume, one should set the productivity of at least one of assigned resources to enable the calculation of the activity duration.

It should be noted that when the skills are assigned, activity duration can be calculated only in the process of scheduling when assigned resources are selected from the skill set.

Page 16: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

16

Resource Assignments

When assigning resource skills, one should either set a total number of resources necessary for activity execution or their total productivity.

Example: a skill set consists of the trucks with different carrying capacity. One may set a number of trucks necessary for the activity execution or the total productivity (dependent on capacities) of all assigned trucks.

Page 17: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

17

Resource Assignments

Resources can be assigned to activities part time. In this case one shall set percentage of assigned

resources utilization (resource workload) together with resource quantity (not just the total percentage calculated by multiplying percents and quantities, that leaves the necessary amount of resources unclear - two resource units with 50% utilization are equivalent to one resource unit used to its full capacity).

Page 18: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

18

Resource Assignments

Another useful option – variable resource assignments. Example:

You may define that the number of resources that may be used at some work is between 2 and 4, and their workload should be not less than 40% and not more than 80%.

In this case an activity will start if two units of assigned resource are available not less than 40% of their work time, and the team may be increased if additional resources become available. Finishing other assignments resources may apply more of their time to the specified assignment but not more than 80%.

Page 19: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

19

Material assignments

Resources can consume materials in the process of their work, so materials may be applied to resources.

Besides materials can be assigned to activities or resource assignments directly. Material assignments may be defined as fixed quantities, or quantities per hour or volume unit.

In some projects it is necessary to simulate not only material consumption but also production of resources and materials on activities and assignments.

Page 20: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

20

Cost

Usually it is not enough just to define activity and resource costs. It is necessary to know project expenses and revenues, what will be spent on wages, on machinery and equipment, on taxes, etc.

Sometimes it is necessary to allow for multiple currencies. So there is a need to define and assign cost components. Besides setting the cost of an hour of renewable resource

work and the cost of material unit, it is necessary to be able to set the cost directly for activities and assignments.

Page 21: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

21

Cost

People may be paid not only for the hours spent on the task but also by the quantity of work they have done.

It means that labour resource cost that is usually defined by the cost of work hour is not enough.

Frequently it is necessary to set costs for resource assignments (fixed or per unit of volume).

Assignment cost is an example of setting contract costs for the project activities.

Page 22: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

22

Centres

It may be necessary to get different reports on the groups of cost components, materials and resources. That is why Cost, Material and Resource Breakdown Structures and Centres are created and used.

Material centre can include any group of materials. Resource centre can include any group of resources. Cost centre includes selected cost components.

Page 23: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Part 2

Corporate Project Management System

Requirements

Page 24: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Organizing corporate data

• Corporate project management systems have specific requirements that are vital for successful implementation.

• It is necessary to be sure that:– Project costs have the same structure in all projects

(same cost components are used)– Cost Accounts are the same in all projects– The same Project, Phase, Activity, Resource, and

Department coding structures are used in all projects– Activities of the same type have the same characteristics

in all projects (like unit cost, material requirements per work volume unit, etc.)

Page 25: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Organizing corporate data

– Resources that are used in all projects belong to the corporate resource pool

– Resources of the same type share the same characteristics (like production rates, material consumption per work hour)

– Typical resource assignments have the same characteristics in all projects (like productivity, cost, and material requirements)

– Typical processes are modeled in the same way in all projects.

Page 26: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Corporate PM System Requirements

Project Management in the Corporate Project Management System sets certain requirements to the project schedule models development and decision making.

Project schedule models shall be created with the use of: Corporate methodology, WBS templates, Resource, Cost, Material dictionaries, Corporate production norms, unit costs and material

requirements.

Page 27: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Corporate PM System Requirements

Page 28: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Program Databases (Reference-Books)

Page 29: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Typical Fragment Library

Page 30: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Project Management Guidelines

Page 31: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

WBS Template

Page 32: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Multiple WBS

Page 33: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Contract Breakdown Structure

Page 34: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Cost Breakdown Structure

Page 35: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Project Archives

Page 36: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Project/ProgramResource Constrained

Scheduling

Part 3

Page 37: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Project Scheduling Tasks

Page 38: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Resource constrained scheduling

• Resource constrained schedules produced by different PM software are different. The software that calculates shorter resource constrained schedules may save a fortune to its users.

• Simple heuristics used by most PM software does not guarantee satisfactory resource constrained scheduling results.

• That is why we pay most attention to resource-constrained schedule optimization.

Page 39: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Resource constrained scheduling

• This is an example of the simple project but resource constrained schedules created by most PM software for this project are at least two weeks late.

Page 40: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Resource constrained scheduling

• The schedule stability is no less important, especially at the project execution phase.

• That is why our project management software Spider Project features an additional option - the support of the earlier project version schedule (keeping the order of activity execution the same as in selected earlier project schedule).

Page 41: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Sample Project before leveling

• Traditional notion of Critical Path works only in case of unlimited resources availability.

• Let’s consider a simple project consisting of five activities, presented at the next slide:

• Activities 2 and 4 are performed by the same resource.

Page 42: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Sample Project after leveling

• Please pay attention to activities that became critical. Now delaying each of the activities 3, 4 and 5 delays project finish date.

• We call these activities Resource Critical and their sequence comprises Resource Critical Path.

Page 43: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Resource Critical Path

• In many projects it is necessary to simulate financing and production, and calculate project schedules taking into account all limitations (including availability of renewable resources, material supply and financing schedules).

• True critical path should account for all schedule constraints including resource and financial limitations.

• We call it Resource Critical Path (RCP) to distinguish it from the traditional interpretation of the critical path definition.

Page 44: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Resource Critical Path

• The calculation of RCP is similar to the calculation of the traditional critical path with the exception that both early and late dates (and corresponding activity floats) are calculated during forward and backward resource (and material, and cost) levelling.

• This technique permits to obtain resource constrained floats.

• Activity resource constrained float shows the period for which activity execution may be delayed without postponing project finish within the current schedule with the set of resources available in this project.

Page 45: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Super Float

Page 46: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Resource Dependencies

Page 47: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

RCP and Critical Chain

Page 48: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Scheduling

Page 49: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Project Success Criteria

Part 4

Page 50: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Project Success Criteria

• If project success criteria are set as finishing project on time and under budget then proper decision making will be complicated.

• Project managers will not be able to estimate if it is reasonable to spend more money but to finish the project earlier.

• We suggest to set one integrated criterion of the project/program success or failure.

• For this it is necessary to estimate the cost of time for current project.

Page 51: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

• The delay of project finish date usually increases project cost, and acceleration means saving some money.

• So each day of project delay means some money losses and finishing project earlier means additional profit.

• Estimating these profits and losses we can define the cost of the project day (maybe separate and different for acceleration and delay).

Project Success Criteria

Page 52: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

• Another option – to set the profit (NPV) that should be achieved at some point in time basing on the forecast of the revenues that will be obtained after the project will deliver its results.

• Such success criterion permits to weight time and money making managerial decisions for project investors.

• At the next slide you may see the project schedule that is calculated without allowing for project financial restrictions. There are periods when project has no money to proceed.

Project Success Criteria

Page 53: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

• This schedule was calculated without considering financial limitations.

• Expected profit to the specified date is $231,141.

Project Success Criteria

Page 54: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

• This schedule of the same project was calculated considering financial and supply limitations.

• The profit to the same date is $196,692, approximately $35,000 lower.

Project Success Criteria

Page 55: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

• Project Manager may analyze different options like borrowing money or delaying payments.

• To be able to weight options and to select the best it is necessary to consider not only expenses but also revenues and financing.

• Proper project (program, portfolio) schedule model is the powerful tool that helps to select the best decisions.

Project Success Criteria

Page 56: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio

Resource Constrained Scheduling

Part 5

Page 57: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

• Project Portfolio shall be planned to maximize the benefits for the organization.

• Usually the benefits mean maximizing portfolio NPV that looks similar to the project success criterion.

• For projects it is clear that shorter schedule means smaller expenses and faster payback. If resource-constrained schedule has minimal duration it means minimal expenses or maximal profit.

• It is not that simple for project portfolio.

Page 58: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

• Minimizing total portfolio duration does not mean maximizing NPV.

• Though total duration become shorter some projects may finish later than possible thus postponing receiving project revenues. Overall NPV may become lower than for longer portfolio duration but faster achievement of first projects results.

• Let’s look at the sample portfolio that consists of 6 projects.• At the next slide portfolio schedule was calculated without

considering resource constraints.

Page 59: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

Page 60: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

• Resource Constrained schedule calculated without setting project priorities makes NPV (that is calculated at the same moment) much lower because resource limitations delay project performance and achieving expected profits.

• Spider Project permits to create any number of parallel WBS for projects and portfolios.

• Next slide shows full structure and then we will look at the structure that shows only investment phases of all projects.

• At this structure we will see project finish dates.

Page 61: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

Page 62: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

Page 63: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

• After resource leveling:• Last project will finish on 18 November 2015 • Expected NPV=14,413,316

• Now let’s calculate the resource-constrained portfolio schedule applying project priorities.

• The result is on the next slide.

Page 64: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

Page 65: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

• After resource leveling with project priorities:• Last project will finish on 14 January 2016 • Expected NPV=17,093,327

• Last project finished two months later but NPV increased by 2.6 millions.

• Conclusion: always set project priorities. In this example any set of priorities lead to better results than multitasking.

• Next priority option is the worst but still better than leveling without applying project priorities,

Page 66: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

Page 67: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

• After resource leveling with these priorities:• Last project will finish on 31 December 2015 • Expected NPV=15,014,726

• Now let’s delete multi-project 6 from our portfolio.• The multi-project 6 looked attractive but we have limited

resources and without project 6 we will accelerate the execution of other projects.

• The result is on the next slide

Page 68: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

Page 69: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Portfolio Success Criterion

• After resource leveling with the same priorities but without multi-project 6:

• Last project will finish on 26 May 2014 • Expected NPV=16,674,013• Deleting profitable project from the portfolio we accelerated

other projects for 1.5 years and will earn additional 1.65mln.• Conclusion: project selection for including into corporate

portfolio shall be confirmed by the whole portfolio leveling.• Even most profitable project may lead to large losses if the

resources are limited and shared by portfolio projects.

Page 70: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Performance Management

Part 6

Page 71: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Performance Measurement

• Project activities have volumes, durations, require materials and have costs.

• Measuring activity performance it is necessary to measure all these parameters.

• Estimating % complete is not clear - % of what?• If 70% of volume was done, 50% of activity duration was

passed, 80% of money and all materials were spent then what is % complete?

Page 72: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Performance Measurement

• Project status information is not sufficient for decision making.

• If project is 10 days behind the schedule is it good or bad?

• If a month ago project was 25 days behind the schedule, two months ago project was 40 days behind the schedule, then only 10 days delay now is very good achievement.

• Project trend information is much more useful for decision making than the information on project status.

Page 73: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Trend Analysis

• Project Performance Management shall be based on trend analysis.

• It is necessary to discover problems as soon as possible and, by analyzing trends of the major project parameters, the project manager can quickly understand if there are problems with project performance.

Page 74: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Trend Analysis

• It is natural to analyze trends of those data that are used in the success criterion definition.

• If we defined that the project performance will be considered successful if cash flow forecast for the specific date exceeds the target value then we will analyze if this forecast is growing or not.

• Negative trend shows problems in project performance and requires consideration of corrective actions.

Page 75: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Project Archives

• It is necessary to be able to restore and analyze trends of any project parameter.

• It is possible only if project archives are properly stored and can be analyzed.

• Spider Project keeps project archives and can restore trends of any user selected parameter from the project start to the current date.

Page 76: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

What is missed

• We have no sufficient time for discussing risk management methods and tools.

• Without risk management even most accurate project scheduling is not reliable,

• Any schedule model requires time and cost contingency reserves (project time and cost buffers) that shall be calculated and added to the deterministic project goals.

• Calculating necessary contingency reserves is Risk simulation task.

Page 77: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Conclusions

Page 78: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Tips for CorporateProject Management

1. Corporate Project Management requires common methodology, templates, reference-books that are used in all corporate projects.

2. Most norms and standards are applied to the activity volume physical units (m, t, m3, piece, etc.). So it is necessary to create project schedule and to monitor project performance basing on physical quantities (volumes of work) measurement.

3. It is necessary to create a library of project fragments that may be used for fast and reliable development of the detailed project computer models.

Page 79: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

4. There is a need for Project Management Office – organizational unit that develops corporate project management norms and standards, manages corporate databases and libraries, and manages Project Portfolio, creating and updating portfolio schedule and analyzing portfolio performance.

5. Portfolio and Program Schedule Models includes the models of individual projects and shall be resource and cost loaded.

Tips for CorporateProject Management

Page 80: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

6. It is necessary to set integrated project and portfolio success criteria.

7. It is necessary to be able to calculate project and portfolio schedules considering not only resource but also financial and supply constraints.

8. The choice of projects for their inclusion in the Project Portfolio shall be justified by scheduling the portfolio model that includes project schedules and analyzing their impact on the portfolio success criteria.

Tips for CorporateProject Management

Page 81: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

9. It is necessary to avoid multitasking and always apply priorities to the portfolio projects.

10. It is necessary to keep project and portfolio archives and to analyze trends of project and portfolio parameters.

11. If trends are negative then corrective actions shall be considered even if the project/portfolio status is good.

12. Risk simulation shall be applied basing on the solid resource management foundation and corporate standards for scheduling. Applied to the simplified models, without considering resource constraints, it is not only useless but dangerous – creates wrong illusions.

Tips for CorporateProject Management

Page 82: Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team

Thank YouFor Attending!