residential heat pump rebate programme - eskom · pdf file• the purpose of the...
TRANSCRIPT
2
Agenda
• Residential heat pump rebate programme
• Technology
• Conditions of participation in programme – Supplier/Customer
• Process
• Concluding Remarks
• Questions
Item Who
Opening and welcome Andrew Etzinger
Evacuation procedure Venue representative
South Africa’s Electricity Supply-Demand Situation Andrew Etzinger
Heat Pump Rebate programme Nosipho Maphumulo
- Structure of the programme Michael Ndlovu
- Envisaged process Fikile Segole
Way forward and closure Nosipho Maphumulo
3
Annual energy gap for 2010 to 2017 under base case outlook, TWh shortfall
SA electricity supply-demand balance will remain tight until 2015 with 2011/2012 the crucial period
Assumptions Eskom estimate of the IRP2010 moderate load forecast (~250 TWh in 2010); Initial expectation of 6 TWh gap in 2010 did not realise due to lower than expected demand; New build (e.g., Medupi, Kusile, Ingula) & RTS at current dates; REFIT as per IRP1 (1 GW by FY2018); DSM as per base plan (3.9 GW by FY2018); Planned maintenance allocation increased to ~10%
15 14 16 2017 13 11 12 2010
9 TWh is equivalent to ~1000 MW base load capacity
4
Electricity System requirements
Summer Profile (Jan – April)
Winter Profile (May – Aug)
Energy savings required during daylight hours
between 06h00 and 20h00 on weekdays
Mainly energy savings required during
Summer
Peak savings a specific requirement
during winter
The total system load factor is high (±76%) – such a flat profile will require energy rather than load reduction
5
A number of levers have been identified and explored to help close the gap
Supply Side Levers to help close gap1
• Eskom Gx performance: improve forced outage rate by 1% by 2012 and 2% in the next 5 years.
• Increased Gx capacity in existing fleet: There is an opportunity to get about 100MW as existing plant is refurbished by 2012.
• Own-Gen2: Partner with industry to leverage 100MW by 2011 identified by industry (1000MW by 2015 in own-generation options). The key issue is the grid access framework.
• Municipality Gx: unlock existing capacity by assistance & short-term PPA's. Target about 200MW over the next 3 to 5 years.
• Renewables: The renewable feed-in tariff (REFIT) programme is targeting 1025MW by 2013. Government will lead the procurement process and Eskom will be the buyer.
1 Excluding involuntary curtailment of demand or running peaking plant beyond agreed level for MYPD2 tariff 2 Own-Generation includes renewables, co-generation and conventional generation
• Internal Energy Efficiency: Eskom has a 1 billion kWh programme. A significant portion of this saving is in improving the efficiency of converting coal to electricity.
• Additional Eskom DSM: Deliver on 4.1 TWh by FY 2012/13 by leveraging the existing funding allocation through MYPD2.
• Government SWH: Implement the 1 million Government Solar Water Heating project.
• Demand response: Eskom has secured 2000MW of interruptible load and nearly 500MW of incentive based demand response from large industrial customers. Eskom is targeting a further 500MW by winter 2011 from its smaller industrial and commercial customers. There is a potential to ramp this up to about 2500MW in the entire market (including the residential sector).
Demand Side Levers to help close gap1
Contribution to closing the gap has been identified for each lever in constrained (i.e. funding and resources have been secured but further effort is required) and highly constrained (i.e.
specific barriers yet to be resolved) environments
6
Even if we deliver against all opportunities, there will still be significant risk of a gap in the early years
Even pulling all levers …
21 16
10 6
3
27 24
… a gap still exists in some years
-19
14
-14
13
-7
12
6
2011
5
2017
-28
16
-25
15
TWh
Energy saving opportunities identified1
Forecast energy gap if full potential is captured
1 Excludes SADC options as total potential is unconfirmed 2 Examples of constraints: Funding, Policy and legislation, Industry manufacturing, installation and service capacity
Highly constrained
Constrained2
Gap
Decisions required • Levers alone are insufficient to close full gap over whole period
• It is critical that significant work is done to unlock constraints and deliver maximum value on levers identified
• Further measures are still required to bridge the gap in 2011/2012
7
A safety net is needed to close the remaining gap and protect SA in case levers do not deliver
Closing the energy gap
Providing capacity to meet peak demand
In the absence of this system “safety net”, a reduction in planned critical maintenance is the final alternative to national load-shedding A 1% reduction in annual planned outages equates to ~2.3 TWh additional energy available to the system Further postponing critical maintenance creates serious risk to safety of our people and integrity of our assets and is not the preferred option.
• Legislated energy reduction for the ±500 largest industrial consumers (Eskom and Munics)
• A 5% energy reduction will yield a 6 TWh energy saving.
• Encourages movement towards a more energy efficient economy.
• Some concern around impact on economic growth hence the need to provide time to adapt.
Measures to close the remaining gap
• By deploying “smart metering” technology options for demand response in the smaller customer segments, customers can participate in responding to energy constraints.
• These technologies will also provide customers a tool to better manage their demand and reduce costs.
• Increased operation of OCGTs during critical years • Increasing the OCGT load factor by 5 percent
provides ~1 TWh additional energy p.a. • Creates significant additional cost for Eskom of
~R2bn per TWh additional energy.
Energy Conservation Scheme (ECS)
Additional Demand Response (DR)
Increased use of OCGT
8
Summary
• The current focus is on the energy gap into the foreseeable future • A portfolio of supply and demand solutions are being implemented to address the
projected energy gap • Acceleration of Demand Side Management is a key lever in strengthening security of
supply • Internally Eskom is optimising current DSM processes to make it more attractive to
the market • Eskom would like to better leverage the external market to implement DSM • Eskom will make available additional funding to accelerate the DSM programme • Residential Heat Pumps Rebate Scheme provides a unique opportunity for project
developers to accelerate their businesses with efficient hot water solutions • Eskom would like to partner with yourselves to ensure that we address this challenge • We want to obtain your inputs, issues and concerns in the implementation and
refinement of the residential HP rebate scheme • The objective of today is to listen to you in order for us to develop a solution that will
address the immediate problem • We see this as a springboard to a healthy, long term relationship to support
sustainable energy efficiency in South Africa.
9
Agenda
• Residential heat pump rebate programme
• Technology
• Conditions of participation in programme – Supplier/Customer
• Process
• Concluding Remarks
• Questions
Item Who
Opening and welcome Andrew Etzinger
Evacuation procedure Venue representative
South Africa’s Electricity Supply-Demand Situation Andrew Etzinger
Heat Pump Rebate programme Nosipho Maphumulo
- Structure of the programme Michael Ndlovu
- Envisaged process Fikile Segole
Way forward and closure Nosipho Maphumulo
10 10
Heat Pump Rebate Programme - overview
Purpose of the domestic heat pump rebate programme
• The current heat pump programme only caters for the industrial and commercial sectors utilising the NERSA budget allowance and ESCO model process. It does not cover the residential market.
• The purpose of the residential heat pump rebate programme is to provide financial assistance to the residential market through a rebate, enabling individual customers to purchase energy efficient heat pumps at a rebated cost.
11 11
Residential heat pump rebate programme
• Eskom commissions a supplier to offer his product (heat pump) to the
customer at a discount (rebate).
• The supplier claims the discount/rebate from Eskom.
• This rebate is mutually beneficial to all parties involved
• the supplier sales are increased
• the customer electricity bill reduces,
• Eskom achieves its business objectives
12 12
Residential heat pump rebate programme
• What does it entail?
• The rebate programme is for retrofit purposes where there is an existing working electrical conventional geyser.
• The customer must buy the product from a registered supplier
• Supplier must perform a complete installation
• What is the target Market?
• Middle to high income
• Individual home owners, game lodges, bed and breakfast, metros buying in bulk, municipalities and corporate organisations
• What is the programme duration?
• Up to March 2013 as aligned to MYPD2
13 13
Programme, budgets and targets
• The residential heat pump rebate programme budget is R 250 mil for
saving 54MW
• This is part of the total heat pump programme allowance of R 679 mil,
128 MW over 3 years
• Min of 65 585 units (air to water) to be installed over 3 years
14
Agenda
• Residential heat pump rebate programme
• Technology
• Conditions of participation in programme – Supplier/Customer
• Process
• Concluding Remarks
• Questions
Item Who
Opening and welcome Andrew Etzinger
Evacuation procedure Venue Representative
South Africa’s Electricity Supply-Demand Situation Andrew Etzinger
Heat Pump Rebate programme Nosipho Maphumulo
- Structure of the programme Michael Ndlovu
- Envisaged process Fikile Segole
Way forward and closure Nosipho Maphumulo
15 15
Residential heat pump rebate structure
100 L 200L
Category 1 Rebate = R 3,668
300L
500L 400L
Category 2 Rebate = R 4,320
100 L 500L Heat Pump tank Ranges
The rebate prices to remain unchanged until 31 March 2013
16 16
Supplier requirements
• To meet all the test requirements from SABS on specifications and standards
• The performance testing of the systems will include among others the initial verification of product design, inspection and verification of compliance of installed systems to applicable standards.
• To meet with all Eskom’s requirements
• Suppliers must comply with the existing Eskom ESCo registration process requirements.
• The suppliers must produce a letter of good standing from their parent company to trade and maintain the products they sell.
• The integrated system warranty should be at least 1 year, the compressor should be 5 years and the circulation pump should have a 3 year warranty.
• Agree to hand/submit invoices for rebate claims
• The supplier must meet the requirements first, then register on Eskom data base as a vendor and will be linked to Eskom for payment purposes.
17 17
Technology
Supplier
Letter of Authority (LOA)
(NRCS)
SARS receipt
not LOA
Safety - SABS or Test Africa
SABS Tests/Verify
Efficiencies
Eskom Quality Department
Eskom IDM Acceptance
1St April Implementation
18
Conditions of the rebate programme Customer requirements and conditions:
1. Customers who are eligible for a rebate are those who have existing electrical water heating elements, the programme is for retrofitting only.
2. No rebate will be given to customers who have already installed the heat pump prior to its formal announcement.
3. All the requirements and attachments as stipulated in the application must be completed in full in order to qualify for rebate payment. It is the customer responsibility to ensure the supplier as well as the system is accredited on the heat programme at the time of installation.
4. The system installed must be registered and accredited as part of the Eskom heat pump programme.
5. Customer will have to fill the rebate forms at the point of sale with his/her details, i.e. ID number, house address, tank size, details of the unit bought, date of installation, and the installer name.
18
19
Conditions of the rebate programme cont …
6. The system must be supplied and installed by an accredited supplier/installer of the heat pump programme.
7. The customer is responsible for ensuring that the system has been installed in accordance with his/her requirements.
8. Should the customer choose to use a heat pump system that does not meet the requirements of the heat pump programme, Eskom and its agents will not be held responsible in any way for the quality of the system or the installation.
19
20
Agenda
• Residential heat pump rebate programme
• Technology
• Conditions of participation in programme – Supplier/Customer
• Process
• Concluding Remarks
• Questions
Item Who
Opening and welcome Andrew Etzinger
Evacuation procedure Venue representative
South Africa’s Electricity Supply-Demand Situation Andrew Etzinger
Heat Pump Rebate programme Nosipho Maphumulo
- Structure of the programme Michael Ndlovu
- Envisaged process Fikile Segole
Way forward and closure Nosipho Maphumulo
21
High level process
Register Supplier
Rebate Claim
Verify Installation
Exceptions
Process Payment
21
M & V
Internal Eskom Process - Any requirements from external stakeholders will be communicated as required
22
Shape Process description
Activity
Start / End of Process
Role
Decision
Document / Deliverable
Input/Output
Process mapping key
Shape Role description
HP Admin*
Heat Pump Suppliers/Installer
M&V
Technical Audit
Customer
22
* HP Admin is the entity that will administer this programme
23
Supplier registration
Registered as Eskom
Vendor
HP Admin
HP Supplier/ Installer
23
Intent on joining HP
Rebate Programme
Quality Review
Quality Dept
Provide Quality Review
Questions
Answer Quality Review
Questions
Quality Report
Initiate Registration with Eskom as Vendor
Review Successful
Eskom Vendor Registration
Process
Registration Admin
1 3
2
5
4
1. Quality Review questionnaire
1. Vendor Registration Documents
24
Rebate claim
Purchase HP System
Install HP System
Sign Installation & Declaration
Form
Submit all documentation to
Eskom
Verify Claim
Complete missing
information
Not verified Verified
7
5
4
3
2
6
1. Claim Form 2. Customer
Pack
1. Claim Form (signed) 2. Copy Invoice 3. Bulk Claim Form
Registered as Eskom
Vendor
(Batch Submission)
Advertise HP Systems
1
HP System Installed
HP Admin
HP Supplier/ Installer
Customer
24
Claim docs verified
25
Payment process
Claim docs verified
Log receipt of claim
Receive notification of claim status
Finance
Submit to SAP for payment
Make Payment
Claim Not Successful
Claim Successful
Complete Outstanding Information
1
4
3
5
2
1. Copy Installation & Declaration Form (signed)
2. Copy Invoice 3. Proof of Address 4. Electricity Bill / Box # 5. Customer Details 6. Registered installer 7. Accredited HP system 8. Rebate payment date
HP Admin
Payment Received
6
HP Supplier/ Installer
25
Successful Claim
Un-Successful Claim
26
Agenda
• Residential heat pump rebate programme
• Technology
• Conditions of participation in programme – Supplier/Customer
• Process
• Concluding Remarks
• Questions
Item Who
Opening and welcome Andrew Etzinger
Evacuation procedure Venue representative
South Africa’s Electricity Supply-Demand Situation Andrew Etzinger
Heat Pump Rebate Programme Nosipho Maphumulo
- Structure of the programme Michael Ndlovu
- Envisaged process Fikile Segole
Way forward and closure Nosipho Maphumulo
27
Way forward
Item Opening and Welcome
Evacuation Procedure
South Africa’s Electricity Supply-Demand Situation
Heat Pump Rebate Scheme
Application and registration of suppliers as ESCOs
Registration of ESCOs as ESKOM vendors Submission of required info to Eskom IDM to register on the rebate scheme
Submission of all systems for SABS approval, when SABS is ready
Submission of claims according to Eskom Heat Pump rebate requirements