request for proposal for: tau power house new scada...

115
Tender Documents – TAU Power House New SCADA System Project Page 1 Tender No: 8080079501/SCADA Procure, Supply, Install and Commission Tender 5th November 2014 REQUEST FOR PROPOSAL For: TAU Power House New SCADA System Project Te Aponga Uira O Te Tumu-Te-Varovaro (TAU) is the Government Business Enterprise (GBE) responsible for the generation, distribution and retailing of electricity on the island of Rarotonga, Cook Islands. TAU is inviting suitably qualified companies or joint venture companies to submit a bid for design, procurement, supply, factory acceptance testing, installation and commissioning of a new SCADA system at the Avatiu Valley Power Station and the TAU Central Office, Rarotonga, Cook Islands. To initiate progress towards the completion of this project, TAU has developed the attached Contract Documents and specifications for the associated works and now invites interested companies to submit their proposal for this project. Electronic copies of the Tender Documents can be requested from the TAU Project Manager. TAU Project Manager – Alex Napa Te Aponga Uira, PO Box 112, Rarotonga, Cook Islands Ph: (682) 20-054 Fax: (682) 21-944 Email: [email protected] The proposed timeframes for the bidding process are set out below: Deadline for submission of questions: 12 noon Wednesday 19 th November 2014 (CI Time) Deadline for submission of Proposals: 12 noon Wednesday 3 rd December 2014 (CI Time) Assessment Panel: One Week after Tender Closing Notification to preferred Contractors: Four Weeks after Tender Closing Contract negotiations: Four Weeks after Tender Closing Please note that this timeframe is indicative only and may be subject to change.

Upload: others

Post on 27-Sep-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 1

Tender No: 8080079501/SCADA Procure, Supply, Install and Commission Tender

5th November 2014

REQUEST FOR PROPOSAL

For: TAU Power House New SCADA System Project

Te Aponga Uira O Te Tumu-Te-Varovaro (TAU) is the Government Business Enterprise (GBE) responsible for the generation, distribution and retailing of electricity on the island of Rarotonga, Cook Islands. TAU is inviting suitably qualified companies or joint venture companies to submit a bid for design, procurement, supply, factory acceptance testing, installation and commissioning of a new SCADA system at the Avatiu Valley Power Station and the TAU Central Office, Rarotonga, Cook Islands. To initiate progress towards the completion of this project, TAU has developed the attached Contract Documents and specifications for the associated works and now invites interested companies to submit their proposal for this project. Electronic copies of the Tender Documents can be requested from the TAU Project Manager.

TAU Project Manager – Alex Napa Te Aponga Uira, PO Box 112, Rarotonga, Cook Islands Ph: (682) 20-054 Fax: (682) 21-944 Email: [email protected]

The proposed timeframes for the bidding process are set out below: Deadline for submission of questions: 12 noon Wednesday 19th November 2014 (CI Time) Deadline for submission of Proposals: 12 noon Wednesday 3rd December 2014 (CI Time) Assessment Panel: One Week after Tender Closing Notification to preferred Contractors: Four Weeks after Tender Closing Contract negotiations: Four Weeks after Tender Closing Please note that this timeframe is indicative only and may be subject to change.

Page 2: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 2

Conditions of Request for Proposal (RFP) 1 Contents of this RFP

a) This RFP consists of: Conditions of RFP Attachment 1: Terms of Reference Attachment 2: Assessment Criteria Attachment 3: Tender Requirements Attachment 4: Proposal Statement Attachment 5: General Conditions of Contract NZS3916:2013 Attachment 6: Scope and Technical Specification for the TAU Power House New

SCADA System Project Attachment 7: Drawings

b) All amendments to this RFP will be issued on Notice to Tenderers (NTT) via e-mail

to registered contractors. 2 Communications or Clarifications Regarding this RFP

a) All correspondence and questions requiring clarifications relating to this RFP must be in writing, directed to the TAU Project Manager:

TAU Project Manager – Alex Napa Te Aponga Uira, PO Box 112, Rarotonga, Cook Islands Ph: (682) 20-054 Fax: (682) 21-944 Email: [email protected]

b) Tenderers must not discuss this tender process or its subject matter with any third party,

except with the Principal s prior written consent in accordance with this tender process.

In addition, Tenderers must not directly or indirectly provide any form of personal inducement or reward, approach, lobby or attempt to influence any of the Principal‘s representative, evaluation team member or Minister who is directly or indirectly involved with this tender process. Communications relating to existing business arrangements or projects between the Principal and a Tenderer will be maintained with the usual contacts. Any breach of these requirements may lead to the offending party being disqualified from participating in this tender process (at the sole discretion of the Principal).

c) Questions relating to this RFP must be received in writing to the TAU Project

Engineer and copied to the TAU Project Manager by: 12 noon Wednesday 19th November 2014 (CI Time)

Page 3: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 3

d) TAU may choose to issue a ‘Notice to Tenderers’ in response to questions received relating to this RFP. Any Notice to Tenderers will be will be issued by e-mail to registered contractors as soon as practicable.

3 Content of Proposals

a) One proposal must be completed under the following headings:

TAU Power House New SCADA System Project The proposal must comprise the following documentation:

i. A completed Proposal Statement (no longer than two A4 pages). An introduction of the proposal including the identification of the bidding team, associates and subcontractors. Note that the contact person may be questioned during examination of the Proposal, or asked to provide additional information.

ii. A Capability Statement (no longer than three A4 pages):

Addressing the eligibility and assessment criteria as set out in the Attachment 2: Proposal Assessment Criteria attached.

Providing evidence as to why the Contractor/s and suppliers would be suitable to deliver the Assignment set out in Attachment 1: Terms of Reference, giving details of any similar experience and summarising the outcomes achieved.

Identifying any of the General Conditions of Contract set out in Attachment 5 that are not suitable to the Contractor, and proposing alternative wording.

Financial Capability – Tenderer must submit audited financial statements for the past three years – balance sheet and income statements at least.

iii. A Methodology and Work Plan for the project (no longer than three A4 pages) which shows how the Contractor would undertake, manage and schedule the assignment. This should include a proposed personnel-schedule showing time allocated to the project for each team member and any backup or support resources available.

iv. A Curriculum Vitae for each nominated main Contractor, and Sub-contractor(s), (no longer than two A4 pages per applicant).

v. A Lump Sum Price for the duration of the project, including proposed fees, expenses. Note: A detailed breakdown of the Lump Sum Price is required for this proposal. The detailed Lump Sum Price must allow for all the Contractor’s obligations and costs in providing the services detailed in the Terms of Reference. Tenderers are asked to set out their detailed Lump Sum Price as outlined in Attachment 3.

b) Should any page limits stated above be exceeded, the additional pages may be

removed from the Proposal by TAU. Font size should be a minimum of 12 point.

Page 4: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 4

c) All Proposals shall be firm lump sum offers and may not be withdrawn for a period of

90 calendar days following the deadline for submission of Proposals. d) The Proposal is to be signed by a duly authorised officer, for and on behalf of, the

Contractor(s). e) TAU requests that all Proposals conform to these Conditions of Proposal, and

reserves the right to reject any non-conforming Proposal.

4. Submission of Proposals

a) Proposals must be submitted by the following deadline, or may not be considered: 12 noon Wednesday 3rd December 2014 (CI Time)

b) Tenderers must submit one Proposal for the project. c) Proposals must be submitted in hardcopy and or electronic form, as detailed below.

Hardcopies i. Three (3) hardcopies of the completed Proposal (including the completed

schedules and documentation requirements) are to be provided. ii. Proposals should be placed in a sealed envelope addressed as detailed below and

be clearly marked on the outside of the envelope: TAU Power House New SCADA System Project

iii. Hardcopies may be couriered to the address below:

TAU CEO – Apii Timoti Te Aponga Uira Main Office Tutakimoa Rarotonga Cook Islands

Alternatively mailed to:

TAU CEO – Apii Timoti Te Aponga Uira PO Box 112, Rarotonga Cook Islands

Electronic Copies

Page 5: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 5

iv. In addition to the hardcopies, an electronic copy of the completed Proposal (compatible with Microsoft Office 2003) must be electronically emailed to the following tender address:

[email protected] and be clearly marked on the email header:

TAU Power House New SCADA System Project

d) Faxed copies of Proposals will not be accepted.

5. Confidentiality

a) Tenderers are advised that TAU is subject to the Official Information Act 2008. Tenderers should mark their proposals “Commercial - In Confidence” if they wish to protect specific information. TAU will treat all Proposals in the strictest confidence. TAU however, cannot guarantee that information marked as such can be protected if TAU receives a request for information under that Act.

6. The RFP Process

a) Each Contractor shall examine, or be deemed to have examined, the Conditions of RFP, Terms of Reference and Proposal Assessment Criteria and any other information supplied by TAU in writing.

b) In submitting a Proposal in response to this RFP, the proposer accepts and agrees to

be bound by TAU’s Conditions of RFP. c) The cost of preparing and submitting the Proposal shall be borne by the Contractor. d) TAU reserves the right to change, suspend or cancel this RFP, or the contents of the

RFP documentation at any time prior to the full acceptance of a Proposal. e) TAU shall have no liability for any information it provides, or for any cost or loss to

any Applicant, in the event that this RFP is cancelled, suspended or changed. f) TAU reserves the right to negotiate without restriction with Tenderers after the close

of RFP on any matter contained in the Proposal, including fee rates, without disclosing this to any other person.

g) TAU reserves the right to accept or reject any, or all Proposal(s), and to annul the

RFP process, at any time, thereby rejecting all Proposals, prior to any contract being awarded.

7. Evaluation of Proposals

a) Proposals will be evaluated by an Assessment Panel, convened by TAU against the criteria outlined in the attached Assessment Criteria.

Page 6: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 6

b) An interview may be required prior to final selection. Tenderers will be given notification of the Panel’s decision to conduct interviews shortly before the interview date. In the event that interviews are to take place, they may be undertaken as a telephone interview.

c) The lowest price Proposal, or any Proposal, will not necessarily be accepted. d) Each Contractor shall be notified in writing of the acceptance or rejection of its

Proposal as soon as possible. No proposal shall be deemed to be accepted unless and until the Contractor has been notified by TAU in writing.

e) TAU reserves its absolute discretion in the evaluation and selection process.

8. Subject to Contract

a) Following the Proposal evaluations, the preferred Contractor(s) will be contacted and invited to enter into negotiations with a view to entering into a contract with TAU. Such an invitation is not a formal contract offer.

b) Proposals are submitted on the basis that no binding legal relations with TAU are

created unless and until a formal written contract is signed by both TAU and the successful Contractor.

c) The acceptance by TAU of any Proposal, whether with or without negotiation, or the

negotiation with an unsuccessful Contractor, shall not create binding legal relations between TAU and the party whose Proposal has been accepted or which is negotiating with TAU.

d) TAU reserves the right to accept only one or some of the nominated individuals, and

to put together a team from all Proposals submitted and/or commission additional expertise if required.

e) If, in the opinion of TAU and at TAU’s sole discretion, none of the Proposals

submitted are acceptable, TAU reserves the right to enter into negotiations with one or more of the Contractor for a satisfactory offer.

f) TAU shall exercise the right outlined in clause 8e only after notification to all

Contractors that their Proposals were unsuccessful. 9. Contract Negotiations

a) Both parties agree to negotiate in good faith, and on successful conclusion of negotiations, the preferred Contractor will sign a formal contract with TAU.

b) A contract may be extended if additional work is required, at TAU’s sole discretion.

10. Schedule of Quantity and Rates by the Tenderer

Page 7: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 7

a) The Terms of Reference (TOR) (Attachment 1) including Attachment 3 is to be read for the purpose of pricing in conjunction with the Technical Specification for guidance of the Contractor, conditions of contract, the specifications, the drawings, the schedule of service provided.

b) The prices inserted in the schedule of quantities and rates shall be the all-inclusive value of the work described including all costs and expenses which may be required in for the planning, design and installation costs (including permit costs) describing together with all general risks, liabilities on which the tender is to be based.

c) The quantities and the unit prices entered in the project schedule of rates are for the completed work in accordance with the recommended option design and specifications.

d) All the tools, plant, machinery, labour and materials required for satisfactory executions of the work under this contract are to be supplied by the Contractor and his/her rates should include for the same in the cost schedule.

e) The Contractor shall fill in rates of work outlined in the Terms of Reference and shall work out the amounts for the quantities against the items in the schedule.

f) All rates shall include the cost of protective clothing, hand tools, supervision, transportation and any other costs, the cost of the operator, fuel, repairs, overhead, profit, insurance and any other costs associated with the equipment and personnel.

Page 8: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 8

ATTACHMENT ONE: Terms of Reference

1.1 Definition of Terms In this specification, the following terms are used:- ACDB - AC Distribution Board

CIF - Cost, Insurance and Freight (as per Incoterms)

DCDB - DC Distribution Board

FAT - Factory Acceptance Test

SCADA - Supervisory Control and Data Acquisition

TAU - Te Aponga Uira o Tumu-te-Varovaro (Rarotonga Electricity Authority)

TCI - Telecom Cook Islands

a) ‘Tenderer’ shall mean any person or company submitting a quotation for the work

detailed in this document.

b) ‘Plant’ shall mean the equipment to be supplied under this Contract. The Scope of Supply below describes the plant and services to be supplied.

c) ‘Contractor’ shall mean the company(s) contracted to the Principle for the supply and the installation of the SCADA servers, workstations, software and associated equipment.

d) ‘Engineer’ shall mean the Engineer to Contract for TAU

e) ‘Principle’ shall mean the end client, TAU.

f) Staging of the project shall be as defined in Attachment 6, Technical Specification.

1.2 Site

Avatiu Valley Power Station

Avatiu Valley Power Station is situated in the island of Rarotonga in the Cook Islands. The freight/courier address is:

Te Aponga Uira

Tutakimoa P O Box 112 Rarotonga COOK ISLANDS

The Principal’s office is the management, maintenance and operations centre for Avatiu Valley Power Station.

Page 9: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 9

1.3 Scope of Supply The Contractor shall supply the following items and provide services as specified by this document and the attached Appendices.

The Contractor shall supply and engineer:

a) A new SCADA Server for installation at Avatiu Valley Power Station and a separate Back-up Server to be installed at the TAU Main Office

b) A new SCADA Workstation for installation at Avatiu Valley Power Station and a separate back-up Workstation for installation at the TAU Main Office

c) A new SCADA Engineering Workstation for installation at Avatiu Valley Power Station

d) New network equipment (serial servers, network switches, firewall, etc.) as defined in the Technical Specification

e) A new UPS for installation at Avatiu Valley Power Station and a new UPS for the TAU Main Office

f) Fibre / Copper Media converters

g) Factor Acceptance Testing

h) Delivery of configured equipment to site in Rarotonga

i) Installation and commissioning on site

j) Ongoing support

1.4 Exclusions The following are excluded from the Contractor’s Scope of Supply:

a) Supply of single-mode fibres between sites (By Others)

b) Third party equipment to be installed in the control cabinet on the new generator platform

Page 10: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 10

1.5 Programme

The following programme is desired by the Principle:

MILESTONE DATE

Site Visit (not compulsory) During Tender

Tenders for new SCADA System Project close

12 noon Wednesday 3rd December 2014 (CI Time)

Successful Supplier advised and Contract Award

January 2015

Approval of software demonstration and HMI screens

February / March 2015

Factory inspection and testing of SCADA systems

April 2015

Commissioning the SCADA System at the Power Station

May 2015

Tenderer must submit a Works Programme (in Gantt chart format) with the tender submission.

1.6 Schedule of Document Delivery The following schedule for the delivery of documentation and other information relating to the Plant is required by the Principal. The Contractor shall submit to the Principal the following Drawings within the times stated below:

a) With Tender:

Standards compliance documentation

Unscheduled Items Specifications and details

Qualifications and experience of Contractor’s site personnel

Completed Tender Schedules including a Works Programme

b) Two weeks after the Contract Award:

Contract Programme

Safety Procedures

Quality Assurance Manual

Evidence of insurance placement

c) Four weeks after the Contract Award:

Demonstration software and HMI screens

Engineering Schedules / Equipment Schedules

Database template

Page 11: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 11

Panel layouts, schematics and dimensional drawings of wall mounted cabinets and

other interfaces

d) One Week before Factory Acceptance Testing occurring:

Test plan and proposed set-up (simulation etc.)

e) One Month before delivery to site:

Advice of shipping and delivery dates to the Principle

f) Two Weeks after successful completion of workshop tests:

Commissioning test sheets

g) One week after issue of any practical completion certificate:

Operation and Maintenance Manuals, Training Manuals

Three paper copies and two CD ROM disc copies of all manuals

DWG Files of all drawings

All software applications used for configuration

Source code (configuration files, project files, custom set-up files, etc.)

1.7 Delivery

a) The SCADA equipment and wall-mount cabinets, including all accessories and ancillary equipment shall be delivered CIF to the Port of Avatiu at the address stated above.

b) Arrangements for off-loading shall be provided by the Principle.

c) The Supplier shall ship equipment, material and spare parts complete except where partial disassembly is required by transportation regulations or for protection of components. The SCADA equipment shall be packed and shipped as described in this specification.

d) Spare parts shall be delivered at the same time as pertaining equipment and be packed in containers bearing labels clearly designating contents and pieces of equipment for which intended.

e) The expected delivery shall be communicated to the Principal one month before delivery is due to take place, and the final date of delivery shall be confirmed one week before delivery is due to take place.

f) Acceptance of the goods is conditional on receipt of all certification and documentation as laid out in this specification

Page 12: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 12

1.8 Terminal Points The following are the terminal points for this contract:

Responsibility Terminal Point Responsibility

TAU Power Station ACDB - AC CB

Power Station ACDB – Termination to AC CB and cable

Contractor

TAU Central Office ACDB - AC CB

Central Office ACDB – Termination to AC CB and cable

Contractor

TAU Power Station DCDB - DC CB

Power Station DCDB - Termination to DC CB and cable

Contractor

TAU Airport Comms Room DCDB - DC CB

Airport Comms Room DCDB Termination to DC CB and cable

Contractor

TAU Power Station Fibre Optic Patch Panel (Street side)

Power Station Fibre Optic Patch Panel (Building side)

Contractor

TAU Central Office Fibre Optic Patch Panel (Street side)

Central Office Fibre Optic Patch Panel (Building side)

Contractor

TAU Airport PV Plant Fibre Optic Patch Panel (Street side)

Airport PV Plant Fibre Optic Patch Panel (Building side)

Contractor

1.9 Site Visits Site visits can be arranged with TAU; application for a site visit must be in writing and directed to the TAU Project Manager.

TAU Project Manager – Alex Napa Te Aponga Uira, PO Box 112, Rarotonga, Cook Islands Ph: (682) 20-054 Fax: (682) 21-944 Email: [email protected]

All site visits will be arranged and scheduled for the week of the 3rd November, 2014.

Page 13: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 13

ATTACHMENT 2: Assessment Criteria

This tender document is intended to give Tenderers an understanding of the evaluation criteria, which will be adopted by the Principal.

2.1 Assessment Criteria

TECHNICAL & FINANCIAL ASSESSMENT SHEET

ASSESSMENT CRITERIA % Score

Technical Proposal

1

Technical proposal that demonstrates a strong understanding of the project and its objectives, which ensures that the project’s objectives, outputs and outcomes/impacts are achieved within the project time frame. Outline and description of, tasks and management as part of the contract; identify potential risks and constraints and propose how these will be managed and any workable solutions; and an outline of the main time-linked milestones to be achieved.

20

Work Plan

2

Provide a sound, time-bound work plan demonstrating a strong understanding of the contract and the contract objectives, outlining timeframes, and details of reporting requirements.

15

Company Experience

3

Demonstrated and effective technical skills, resources and experience of the team with experience on design, procure, supply, install, commission, reporting and ongoing support of similar projects provided as references for this RFP.

15

Financial Proposal

4 Value for money 50

TOTAL 100%

Page 14: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 14

The Principal reserves the right to depart from the stated criteria and to consider any information considered relevant, from any source whatsoever. Tenderers should note that the Principal has the discretion to accept, reject or carry on negotiations with regard to any compliant, non-compliant and alternative tenders.

The Principal reserves the right at its sole discretion to accept none or any of the tenders, at any time to withdraw the contract from tender.

2.2 Assessment Panel Guide to Scoring

PERCENTAGE DESCRIPTION

90-100

Demonstrates full coverage of skills, capability and experience as requested, in a strategic, cohesive and structured manner, with no gaps and demonstrated successful practice

80-89 Demonstrates full coverage of skills, capability and experience as requested, with no gaps and demonstrated successful practice

65-79 Demonstrates full coverage of skills, capability and experience as requested, with no gaps

50-64 Demonstrates skills, capability and experience as requested, with some gaps which are not regarded as problematic

40-49 Asserts skills, capability and experience as requested, with some gaps which are not regarded as problematic

20-39 Asserts skills, capability and experience as requested, with some gaps which would need to be addressed

1-19 Some aspects of skills, capability and experience addressed, with major gaps and/or superficial understanding

0 Skills, capability and experience not addressed, or ineffective, or where there are grave concerns

Page 15: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 15

ATTACHMENT 3: Tender Requirements

3.1 Information Required with Tender The following information, together with technical information specified in the individual Schedules below shall be provided with the tender:

a) Complete Schedules A to I

b) A Works Programme commencing from the date of placing the order

c) Detailed information regarding the anticipated performance of the SCADA system

d) Methodology statement outlining the procedure for engineering and programming the SCADA system

e) Operator, maintenance staff and engineering training details, this shall include details of training to be provided, training manuals / documentation, timing and duration.

f) Drawings and documentation as specified in Schedule of Document Delivery.

g) The recommended spares list complete with the cost of each component, lead and delivery times to Rarotonga and the location of the nearest spares stockist or manufacturer.

h) The recommended maintenance requirements and intervals.

i) If the equipment does not comply with the technical specification, this shall be stated and information given on how the equipment varies from the specification. No variance statement in the tender offer shall be read as full compliance with the technical specifications. However, the Client/Principal reserves its rights to accept part or all on non-complying submissions.

j) Company support services (either on site or via remote access), for trouble shooting assistance, service and maintenance, spare parts, source and accessibility of spare parts, equipment and expected delivery times.

k) Company position statement to include financial situation, any pending litigations, current commitments, insurances and the like.

3.2 Assessment of Tenders

a) Assessment of quotations may take into account, cost, Works Programme and conformance with the specification and other factors.

b) In the event of all information requested herein not being supplied with the quotation, the Principal may, at its sole discretion, deem the quotation to be non-conforming and exclude the quotation from further consideration.

c) The lowest priced or any quotation will not necessarily be accepted

3.3 Unscheduled Items

a) Should the Tenderer consider that any item might not be adequately provided for, they shall insert details of such items in the Tender Schedules.

Page 16: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 16

b) All items so inserted into the Tender Schedules shall be described in sufficient detail to indicate justification for them, and shall be separately and clearly priced.

3.4 Schedule of Prices Preamble and General

Schedule of Prices

a) The whole of the work under this Contract shall be priced under the Schedule of Prices.

b) The description of work in the Schedule of Prices is not necessarily complete in all respects and reference should be made to the Contract Documents, which are to be read in conjunction with the Schedule of Prices.

Identification of Payment Items

a) Where an item is listed in the Schedule of Prices for a particular work or service, the total cost of the work or service will be deemed to be covered by the rate or Lump Sum Price tendered for that item. Where no such item is listed for a particular work or service, the cost of the work or service will be deemed to be included in the rates and prices tendered for the item or items of work associated with that work or service. Where a work or service is of a general nature and is not associated with any particular item or items in the Schedule of Prices the cost thereof will be deemed to be included in the rates and prices tendered in the Schedule of Prices generally.

Dimensions

a) The following abbreviations are used in the unit columns of the Schedule of Prices and elsewhere in the Documents:

TERM DEFINITION

LS Lump Sum

each or No. units of work - as described

b) Dimensions quoted in the itemised descriptions in the Schedule of Prices are given in

millimetres except where stated otherwise.

Quantities

a) The quantities given in the Schedule of Prices are estimated only. They are given to form a common basis for tendering and shall therefore not be considered as the final requirements, which will be made in accordance with the Contract Documents.

Rates and Prices

a) All items included in the Schedule of Prices shall be priced and, where applicable, shall be extended, and the extended prices shall, on addition, equal the Tender Price. A price or rate shall be entered against each item in the Schedule of Prices where quantities are stated or not. An item against which no price is entered in the Schedule will be deemed to be covered by the other prices or rates in the Schedule of Prices. The rates and prices inserted in the Schedule of Prices shall be the full inclusive value of the work described

Page 17: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 17

and in all temporary works, and shall cover all general risks, liabilities and obligations set forth or implied in the documents on which the Tender is to be based. The rates shall include the costs of all labour, materials, plant and equipment, tools, transportation, and all other requisites in accordance with the Specification.

b) All costs of complying with the requirements of the Contract, including Contractor’s time-related overhead costs and other charges, will be deemed to be included in the unit rates and prices tendered in the Schedule of Prices for the various items of work.

Correction of Errors

a) Any error in extension or addition, or both, discovered by the Principal or the Contractor in the Schedule of Prices shall be corrected in a manner agreed to between the Contractor and the Principal so that the total of all items in the Schedule of Prices continues to equal the Tender Price.

Project Specific Items

Work Breakdown with Prices.

a) This consists of elements of work with the Prices shown for each element. Because payments shall be due for elements only when they are complete the elements must be clearly described and have clearly identifiable completions. The Principal has listed the elements it requires the Tenderer to include. The Tenderer shall complete the list and the Price for each element, the total of the Prices being the tendered sum. The Tenderer shall show as separate items any significant pieces of Equipment being used and their prices.

b) If an element is subdivided, payment shall be due for the element only when all its sub-elements are completed.

c) The Tenderer shall submit element prices for the work being tendered.

Page 18: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 18

Schedule A: Power House New SCADA System Project - Schedule of Prices The Tenderer shall complete the pricing Schedule below and submit the completed Schedule to the Te Aponga Uira o Tumu-te-Varovaro with its tender.

STAGE 1 - Solar PV Plant and Power Station Existing Plant

ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT

$NZ EXCL. VAT

STAGE 1 – Solar PV Plant and Power Station Existing Plant

1. Miscellaneous 1.1a Preliminary and General 1

1.1b Progress / Design Meetings 1

1.1c Weekly ( by email) and Monthly Reporting (Full report) 1

1.1d General documentation and manuals 1

1.1e Software and features demonstration in Rarotonga 1

1.1f SCADA Standards Manual 1

2. SCADA Hardware

1.2a SCADA / Historian Servers 3

1.2b 6 Port Network Switches 2

1.2c 14 Port Network Switches 4

1.2d Firewall 1

1.2e Workstations 2

1.2f Engineering Station 1

1.2g 4-Port Serial Servers 5

1.2h UPS 2

1.2i Media Converters 3

1.2j Fibre Patch Panels 6

3. SCADA Licenses

1.3a Server 1

1.3b Workstation 1

1.3c Historian 1

1.3d Miscellaneous 1

4. Programming and Configuration

1.4a HMI 1

Page 19: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 19

1.4b Database 1

1.4c Expert System 1

1.4d Standard Historian Reports 1

5. Installation and Commissioning

1.5a Site Installation 1

1.5b Site Testing and Commissioning 1

1.5c Site Training 1

6. Training and Support

1.6a Operator Training 1

1.6b Maintenance and Technical Training 1

1.6c Engineer Training 1

1.6d Six Months On-site Support (specify number of trips) 1

1.6e Offsite (NZ) Training Technician / Engineers 1

7. Other Items

1.7a Spares (Refer to Schedule C) 1

1.7b Optional Items (Tenderer to specify)

1.7c Unscheduled Items (Tenderer to specify)

Total Stage 1 - (Excl. VAT)

Page 20: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 20

STAGE 2 – New Generating Plant

ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT

$NZ EXCL. VAT

STAGE 2 – New Generating Plant

1. Miscellaneous 2.1a Preliminary and General 1

2.1b Progress / Design Meetings 1

2.1c Weekly ( by email) and Monthly Reporting (Full report) 1

2.1d General Documentation and Manuals 1

2. SCADA Hardware

2.2a 14 Port Network Switches 1

2.2b Fibre Patch Panels 1

3. Additional SCADA Licenses if Required*

2.3a Server

2.3b Workstation

2.3c Historian

2.3d Miscellaneous

4. Programming and Configuration

2.4a HMI 1

2.4b Database 1

2.4c Expert System 1

2.4d Standard Historian Reports 1

5. Installation and Commissioning

2.5a Site Installation 1

2.5b Site Testing and Commissioning 1

2.5c Site Training 1

6. Additional Training and Support**

2.6a Operator Training

2.6b Maintenance and Technical Training

2.6c Engineer Training

2.6d Six Months On-site Support (specify number of trips)

2.6e Offsite (NZ) Training Technician / Engineers

Page 21: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 21

7. Other Items

2.7a Optional Items (Tenderer to specify)

2.7b Unscheduled Items (Tenderer to specify)

Total Stage 2 - (Excl. VAT)

* Contractor to offer most cost effective upgrade path for licensing. If a reduced licence will suffice for Stage 1 then this shall be offered, with an upgrade priced for Stage 2. ** Additional training only. The majority of training will have been undertaken as part of Stage 1.

Page 22: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 22

Schedule B: Power House New SCADA System Project - Schedule of Rates

The Tenderer shall complete the rates pricing Schedule below and submit the completed Schedule to the Te Aponga Uira o Tumu-te-Varovaro with its tender.

ITEM DESCRIPTION UNIT RATE * 1 Technician $/hour

2 Engineer $/hour

3 Site Engineer / Technician $/hour

4 Travel to Rarotonga (including return) $/trip

5 On-site expenses in Rarotonga (meals, accommodation, travel, site allowance)

$/day

6 Other personnel (Tenderer to specify)

7

8

9

10

* - All rates to be stated in New Zealand Dollars

Page 23: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 23

Schedule C: Power House New SCADA System Project - Schedule of Recommended Spares

The Tenderer shall complete the Recommended Spares pricing Schedule below and submit the completed Schedule to the Te Aponga Uira o Tumu-te-Varovaro with its tender.

ITEM DESCRIPTION UNIT RATE * 1

2

3

4

5

6

7

8

9

10

* - All rates to be stated in New Zealand Dollars

Page 24: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 24

Schedule D: Power House New SCADA System Project - Escalation, Forex & Payment

The Tenderer shall complete the Schedule below and submit the completed Schedule to the Te Aponga Uira o Tumu-te-Varovaro with its tender.

SCHEDULE D: SCHEDULE OF PRICE – ESCALATION FOREX, INCIDENT OF PAYMENT

VALIDITY OF TENDER

1 The Tenderer shall advise the validity of the tender (this shall not be less than 90 days)

CURRENCY OF TENDER

1

RATE OF EXCHANGE CURRENCY (XXX) EXCHANGE RATE (XXX:NZD)

1 SCADA software and hardware 2 Other (Tenderer to identify item

currency and rate)

3 4 5

ESCALATION ITEM SUBJECT TO ESCALATION (Y/N)

DETAILS OF ESCALATION FORMULA

1 SCADA software and hardware

2 Other (Tenderer to identify item currency and rate)

3

INCIDENTS OF PAYMENT

Tenderer shall estimate the claims expected for the contract items detailed below: This estimate shall be made as a percentage of tendered price for the appropriate item

CONTRACT ITEM DATE PRICE 1 Deposit 2 Sign-off Factory Acceptance Testing 3 Delivery of Equipment to Site 4 Handover

Page 25: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 25

Schedule E: Power House New SCADA System Project - Delivery Schedules

The Tenderer shall complete the Schedule below and submit the completed Schedule to the Te Aponga Uira o Tumu-te-Varovaro with its tender.

SCHEDULE E: DELIVERY SCHEDULES

Item

DESCRIPTION

Guaranteed Delivery Period for: DELIVERY PERIOD

Stage 1 Stage 2

1 Design information and approval drawings from Contract award to delivery to Principle (weeks)

2 Demonstration of software and HMI features from Contract award to delivery to Principle (weeks)

3 Factory Acceptance Testing of SCADA system from Software Demonstration (weeks)

4 Equipment and spares from Factory Acceptance to delivery to Rarotonga (weeks)

5 Operations and Maintenance Manuals from Factory Acceptance to delivery to Principle (weeks)

6

Page 26: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 26

Schedule F: Power House New SCADA System Project - Checklist with Tender

The Tenderer shall complete the Schedule below and submit the completed Schedule to the Te Aponga Uira o Tumu-te-Varovaro with its tender.

ITEM COMMENTS /

1 Completed schedules

2 Guaranteed delivery schedule, and program.

3 SCADA system general description

4 Performance details of the SCADA servers, workstations and software

5 Technical and catalogue information for the SCADA servers, workstations and software

6 The recommended spares list for each assembly including the cost of each component

7 Lead and delivery times for spare parts to TAU Power Station, Rarotonga

8 Training for Operator, Maintenance staff and Engineering and training details

9 Company support services for trouble shooting, spares, etc.

10 Company Position Statement for financial, pending litigation, current commitments, insurances and the like

11 List of equipment not complying with the technical specification, and information on how the equipment varies from the specification

Page 27: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 27

Schedule G: Power House New SCADA System Project - Key People

The Tenderer shall complete the Schedule below and submit the completed Schedule to the Te Aponga Uira o Tumu-te-Varovaro with its tender.

SCHEDULE G: KEY PEOPLE

NO DESCRIPTION KEY PEOPLE DETAILS

Tenderer shall submit details of key people proposed by Tenderer and proposed Subcontractors for this Contract.

1 Key Person #1 – SCADA System Supplier Project Engineer

Name

Location

Contact details

Phone:

Email:

Mail/Courier address

Experience – Key person CV attached (Y/N)

2 Key Person #2 – SCADA System Programmer

Name

Location

Contact details

Phone:

Email:

Mail/Courier address

Experience – Key person CV attached (Y/N)

3 Key Person #3 – Hardware Supplier

Name

Location

Contact details

Page 28: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 28

SCHEDULE G: KEY PEOPLE

NO DESCRIPTION KEY PEOPLE DETAILS

Phone:

Email:

Mail/Courier address

Experience – Key person CV attached (Y/N)

Page 29: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 29

Schedule H: Power House New SCADA System Project - Schedule Information with Offer

The Tenderer shall complete the Schedule below and submit the completed Schedule to the Te Aponga Uira o Tumu-te-Varovaro with its tender.

ITEM COMMENTS

1

2

3

4

5

6

7

8

9

10

11

Page 30: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 30

Schedule I: Power House New SCADA System Project - Schedule of Non-Conformances

The Tenderer shall complete the Schedule below and submit the completed Schedule to the Te Aponga Uira o Tumu-te-Varovaro with its tender.

ITEM COMMENTS

Tenderer shall list all non-conformances with the specification. This shall include and detail all technical alternatives to the specification being proposed.

1

2

3

4

5

6

7

8

9

10

Page 31: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 31

ATTACHMENT 4: Proposal Statement

4.1 CONTRACTOR’S CONTACT DETAILS – Repeat for each Personnel

Contact Person:

Full legal business/ trading names:

Business postal address:

Business phone number:

Business fax number:

Home phone number:

Cellular phone number:

Email address:

Authorised contracting officer / contract signatory:

4.2 CHECKLIST OF ADDITIONAL DOCUMENTS TO BE PROVIDED

1. A Capability Statement (max. one A4 pages):

2. Curriculum Vitae (max. two A4 pages per person)

3. Approach/implementation and Work plan (max. five pages)

4. Tender Schedules

5. All other relevant Documents (eg: Specialist training done, registration etc.

Page 32: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 32

4.3 CONTACT DETAILS OF CONTRACTOR (repeat for each other Sub-contractor)

Contractor Details

Contractor’s name:

Relationship to the Contractor:

Contractor / Joint Contractor / Employee / Sub-contractor / Other

Relevant specialist area(s) / field(s) of expertise or input:

Date(s) when not available: Actual/potential conflicts of interest:

4.4 REFERENCE SITES / PROJECTS

Similar Project - First Reference Site / Project

Client / Project:

Site Location

Site Contact

Postal address:

Project Details

Project Value

Telephone number:

Email address:

Similar Project - Second Reference Site / Project

Client / Project:

Site Location

Site Contact

Postal address:

Project Details

Project Value

Page 33: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 33

Telephone number:

Email Address:

Association to the consultant: Similar Project - Third Reference Site / Project

Client / Project:

Site Location

Site Contact

Postal address:

Project Details

Project Value

Telephone number:

Email Address:

Association to the consultant:

Page 34: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 34

ATTACHMENT 5: General Conditions of Contract: NZS3916:2013

NZS3916:2013 – Conditions of contract for building and civil engineering- Design and Construct. The Contract Documents are this Contract Agreement and the following which form part of this agreement:

(a) The Conditions of Tendering as set out in this RFP

(b) Notices to Tenderers

(c) The Contractor’s Tender

(d) The notification of acceptance of tender

(e) The General Conditions of Contract, NZS3916:2013

(g) Specifications issued prior to the Date of Acceptance of Tender

(h) Drawings issued prior to the Date of Acceptance of Tender

(i) The Schedule of Prices

(j) The following additional documents:

Page 35: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule to Conditions of Tendering Page 1 of 2

NZS 3916:2013 Conditions of contract for building and civil engineering – Design and construct

Schedule to Conditions of Tendering

The Conditions of Tendering are those set out in NZS 3916:2013.

Clause numbers refer to Conditions of Tendering clauses.

Contract for: TAU Power House New SCADA System Project (8080079501/SCADA)

Clause in Conditions of Tendering

Title and subject matter Specific condition data (Expand cells if required)

102 Issue of documents 102.2 Is a Tender Documents deposit required? No

If yes, the amount of the Tender Documents deposit shall be:

($) Click to enter amount

103 Tenderers to inform themselves 103.1 Is an appointment required to view the Site? Yes

If yes, the appointment details are: TAU Project Manager

Te Aponga Uira, Rarotonga, Cook Islands

Ph: +682 20054

Fax: +682 21944

Email: [email protected]

-

Site Visit Not Compulsory

105 Submission of tenders 105.1 Tenders shall close at: Address to:

TAU Project Manager

Te Aponga Uira,

PO Box 112,

Rarotonga,

Cook Islands

3 December 2014

Noon Cook Island Time

Are electronic tenders acceptable? Yes

If yes, tenders will be acceptable in the following electronic form:

(specify type of file for example Word, PDF)

Electronic – PDF

105.3(c) Is supplementary information required to be submitted with the tender?

Yes

Page 36: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule to Conditions of Tendering Page 2 of 2

Clause in Conditions of Tendering

Title and subject matter Specific condition data (Expand cells if required)

105.3(e) Are the percentages for On-site Overheads and for Off-site Overheads and Profit required to be nominated in the tender?

No (See 9.3.8, 9.3.9, & 9.3.10 of the General Conditions)

Is the Working Day rate in compensation for time-related On-site Overheads and Off-site Overheads and Profit incurred in relation to an extension of time required to be nominated in the tender?

Yes (See 9.3.11 of the General Conditions)

Is the percentage for processing of Variations required to be nominated in the tender?

Yes (See 9.3.15 of the General Conditions)

Are the percentages for On-site Overheads and for Off-site Overheads and Profit to be added to Net Cost in a cost reimbursement contract or for cost reimbursement work required to be nominated in the tender?

Yes (See 2.4.1 of the General Conditions)

If yes, the supplementary information required to be submitted with the tender is:

Refer RFP

105.7 Are the rates included in the Schedule of Prices fully inclusive of all allowances for On-site Overheads and for Off-site Overheads and Profit?

Yes (see 9.3.8, 9.3.9, & 9.3.10 of the General Conditions)

107 Tender evaluation 107.1 The tender evaluation method shall be: Refer RFP

Page 37: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Contract Agreement Page 1 of 2

NZS 3916:2013 Conditions of contract for building and civil engineering – Design and construct

Contract Agreement

CONTRACT FOR TAU Power House New SCADA System Project (Contract name)

CONTRACT NUMBER 8080079501/SCADA (Number)

THIS AGREEMENT is made on Click to enter a date

BETWEEN Click to enter text (‘the Contractor’)

AND Te Aponga Uira (‘the Principal’)

IT IS AGREED as follows:

1. The Contractor shall carry out the obligations imposed on the Contractor by the Contract.

2. The Principal shall pay the Contractor the sum of $ Click to enter text or such greater or lesser sum as shall become payable under the Contract together with goods and services tax at the times and in the manner provided in the Contract.

3. Each party agrees to the terms and conditions as set out in the Contract.

4. The Contract comprises the following documents:

(a) This Contract Agreement;

(b) The notification of acceptance of tender or award of Contract;

(c) The following post-tender documents (Identify any agreed post-tender documents to be included, for example

correspondence or minutes or pre-award meetings dealing with tender tags, and so on):

Click to enter text

(d) Schedule 2: Special Conditions of Contract – Other Conditions of Contract;

(e) Schedule 1: Special Conditions of Contract – Specific Conditions of Contract;

(f) The General Conditions of Contract NZS 3916:2013 (including other Schedules);

(g) The Principal's Requirements;

(h) The Schedule of Prices; ☐ (Select if NOT applicable)

(i) The Contractor’s tender;

(j) Notices to tenderers (give details with dates);

Click to enter text

(k) The Schedule to the Conditions of Tendering;

(l) The Conditions of Tendering; and

(m) The following additional documents: (Identify any additional documents to be included):

Click to enter text

5. The documents comprising the Contract shall be taken as mutually explanatory, but in the case of ambiguity or conflict the priority of documents shall be as listed in clause 4 above, with each document prevailing over a document lower in the list.

6. This Contract shall constitute the entire agreement between the parties. This Contract supersedes all prior negotiations, representations, and warranties, except insofar as the same are expressly incorporated herein.

SIGNED BY Click to enter text or paste signature Authorised Signatory of Contractor

SIGNED BY Click to enter text or paste signature Authorised Signatory of Principal

Page 38: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract Page 1 of 12

NZS 3916:2013 Conditions of contract for building and civil engineering construction – Design and construct

Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract

Contract for: TAU Power House New SCADA System Project (8080079501-SCADA)

Clause in General Conditions

Title and subject matter Specific condition data (Expand cells if required or add a reference to further detail provided in Schedule 2.)

1. INTERPRETATION

1.2 Definitions

The Principal is: Te Aponga Uira

of: Tutakimoa

Avarua

PO Box 112

Rarotonga

Cook Islands

1.2, 10.2 Separable Portions

• Are there any Separable Portions in this Contract? Yes

• If yes, the Separable Portions are as follows and as

further defined in the Contract:

Separable Portion 1 – RFP Stage 1

Separable Portion 2 – RFP Stage 2

2. THE CONTRACT

2.1 Type of contract

2.1.1 This Contract is a: (select one to apply (a) or (b))

(a) Lump sum contract governed by 2.2; ☒

(b) Cost reimbursement contract governed by 2.3. ☐

2.3 Cost reimbursement contract

2.3.1 Allowance(s) which are to be added to Net Cost in a cost reimbursement contract or for parts of the

Contract Works which are required to be carried out on a cost reimbursement basis:

(If percentages are shown as zero or nil, allowances for overheads and profit are deemed to be included in Net Cost.)

• Allowance for On-site Overheads: Not Used (%)

• Allowance for Off-site Overheads and Profit: Not Used (%)

2.3.4 Indicative estimates of the Contract Price:

Are indicative estimates required? No

2.4 Local authority contracts, contracts in public places, and road contracts

2.4.1 Is this Contract a local authority contract to which 2.4.2

applies? Yes

2.4.3 Is this Contract a contract in a public place to which B1 and

B2 of Appendix B apply? No

Page 39: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract Page 2 of 12

Clause in General Conditions

Title and subject matter Specific condition data (Expand cells if required or add a reference to further detail provided in Schedule 2.)

2.4.4 Is this Contract a road contract to which Appendix B

applies? No

If yes, the allowance under B3 shall be:

Click to enter number (number of Working Days)

2.5 Evidence of Contract

2.5.2 How is the Contract Agreement to be executed? (select one to apply, (a) or (b))

(a) As stated in 2.5.2; ☒

(b) In accordance with the following other requirements: ☐ Time Reimburseable basis

2.6 Documents prepared by the Engineer or Principal

2.6.1 Copies of the Contract shall be supplied without charge to

the Contractor in the following electronic form: PDF

2.7 Documents prepared by the Contractor

2.7.2 Copies of documents referred to in 2.7.2 shall be supplied

without charge to the Engineer:

• Number of hard copy sets: Three

• In the following electronic form: PDF and Orignal Form (i.e AutoCAD, MS Word / Excel / Project)

3. BONDS

3.1 Contractor’s Bond

3.1.1 Is a Contractor’s Bond required? No

3.1.2 If yes, the amount of the Contractor’s Bond shall be: ($)

3.2 Principal’s Bond

3.2.1 Is a Principal’s Bond required? No

3.2.2 If yes:

• The amount of the Principal’s Bond shall be: ($) Click to enter amount

• The surety for the Principal’s Bond shall be: Click to enter text

4. SUBCONTRACTS

4.1 General

4.1.4 Is transfer of design agreements required? Yes

5. GENERAL OBLIGATIONS

5.1.10,

5.1.12,

5.1.14,

5.1.15

Time for review of Design Documentation by Engineer (select one to apply, (a) or (b))

(a) 10 Working Days; ☐

(b) Within the following time. ☒ 20 Working Days

Page 40: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract Page 3 of 12

Clause in General Conditions

Title and subject matter Specific condition data (Expand cells if required or add a reference to further detail provided in Schedule 2.)

5.4 Possession of the Site

5.4.1 The Contractor shall be given possession of the Site: (select one to apply, (a) or (b))

(a) 10 Working Days after the Date of Acceptance of

Tender:

(b) On the following date: ☒ Not Required

5.4.3 Limits on the Contractor's right of entry to adjoining

properties are:

Access to adjoining properties is not required.

5.5 Separate Contractors

5.5.1 Separate Contractors who may be carrying out work on the

Site concurrently with the Contract Works are:

Not Required

5.5.2 Are facilities for Separate Contractors required? No

If yes, details of facilities required are: Click to enter text

5.6 Care of the works and Site

5.6.6(f) Further risks specifically excepted are: Not Required

5.10 Programme

5.10.4 Is the programme required to be a Comprehensive

Programme? Yes

5.10.4(e) If yes, other requirements for the Comprehensive

Programme are:

Refer RFP for short and long term deliverables

5.10.5 The Comprehensive Programme shall use the following

software:

MS Project

5.10.6 Updates of the Comprehensive Programme shall be

provided at the following intervals:

Monthly

5.11 Compliance with laws

5.11.3 Exceptions to the Principal’s obligations to obtain licences

under 5.11.3 are:

Nil

5.11.4 Exceptions to the Contractor's obligation to give notices

and obtain other licences under 5.11.4 are:

Nil

5.11.5 Exceptions to the Contractor’s obligation to give notices

and to obtain licences for Temporary Works and for

temporary amenities and services under 5.11.5 are:

Nil

5.17 Safety plan

Is a Site-specific safety plan required to be prepared by the

Contractor? No

5.18 Quality plan

Is a quality plan required to be prepared by the Contractor? Yes

5.19 Traffic management plan

Is a traffic management plan required to be prepared by the

Contractor? No

Page 41: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract Page 4 of 12

Clause in General Conditions

Title and subject matter Specific condition data (Expand cells if required or add a reference to further detail provided in Schedule 2.)

5.20 As-built drawings and operation and maintenance manuals

5.20.1(a) Are as-built drawings required to be prepared by the

Contractor? Yes

5.20.1(b) Are operation and maintenance manuals required to be

prepared by the Contractor? Yes

6. THE ENGINEER

6.1 Appointment of Engineer

6.1.2 The Engineer is: Mr. Stephen Peters

whose professional qualification is: NZCE

8. INSURANCES

8.1 General

8.1.1 The party identified below shall arrange the following

insurances referred to in the following clauses:

8.3 or 8.8 Construction Not required

8.8 Existing structure(s) and contents Not required

8.4 Plant Contractor

8.5 or 8.9 Public liability Contractor

8.5.2 Motor vehicle liability Contractor

8.6 Professional indemnity Contractor

8.1.6 The following forces of nature shall be specifically insured

under 8.3 or 8.8 as applicable:

(a) Landslip: No

(b) Earthquake: No

(c) Tsunami: No

(d) Tornado: No

(e) Cyclone: No

(f) Storm: No

(g) Flood: No

(h) Lightning strike: No

(i) Volcanic activity: No

(j) Hydrothermal activity: No

(k) Geothermal activity: No

8.3, 8.8 Construction insurance

(These items are required to be completed whether the Contractor or the Principal is the insuring party (see 8.1 above))

8.3.2, 8.8 The following shall have their respective interests noted in

the construction insurance policy:

Not Required

Page 42: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract Page 5 of 12

Clause in General Conditions

Title and subject matter Specific condition data (Expand cells if required or add a reference to further detail provided in Schedule 2.)

8.3.3, 8.8 Where construction insurance is required (see 8.1 above), the

amount of insurance to be effected for the Contract Works

and Materials shall be for not less than the sum of the

Contract Price, after the acceptance of the tender or other

offer, plus the following allowances:

(a) An allowance for the Cost of demolition, disposal and

preparation for replacement work, equal to:

(select one to apply, (i) or (ii))

(i) The amount in the right hand column: ($) Not Required

(ii) The percentage in the right hand column of the

Contract Price adjusted as above:

☐ Click to enter % (%)

(b) An allowance for professional fees including the Cost of

clerks of works and inspectors, equal to:

(select one to apply, (i) or (ii))

(i) The amount in the right hand column: ☐ ($) Not Required

(ii) The percentage in the right hand column of the

Contract Price adjusted as above:

☐ Click to enter % (%)

(c) An allowance for items to be incorporated in the

Contract Works, the Cost of which is not included in the

Contract Price, equal to:

(select one to apply, (i) or (ii))

(i) The amount in the right hand column ☐ ($) Not Required

(ii) The percentage of the Contract Price adjusted as

above, stated in the right hand column:

☐ Click to enter % (%)

(d) An allowance for an increase in the Contract Price due

to Variations equal to:

(select one to apply, (i) or (ii))

(i) The amount in the right hand column: ☐ ($) Not Required

(ii) The percentage of the Contract Price adjusted as

above, stated in the right hand column:

☐ Click to enter % (%)

(e) An allowance for increased construction Costs due to

inflation equal to:

(select one to apply, (i) or (ii))

(i) The amount in the right hand column: ☐ ($) Not Required

(ii) The percentage of the Contract Price adjusted as

above, stated in the right hand column:

☐ Click to enter % (%)

8.4 Contractor arranged Plant insurance

Where Plant is required to be insured (see 8.1 above): (select one to apply, (a) or (b))

(a) The Contractor shall insure the following items of Plant

on the Site for the amounts stated:

☐ Not Required

(b) The Contractor shall insure each item of Plant on the

Site having a current market value of more than:

☐ ($) 1000

Page 43: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract Page 6 of 12

Clause in General Conditions

Title and subject matter Specific condition data (Expand cells if required or add a reference to further detail provided in Schedule 2.)

8.5 Contractor arranged public liability insurance

8.5.1 Where required (see 8.1 above), public liability insurance

shall be effected by the Contractor for an amount not less

than:

☒ ($) 10 Million for any one occurrence and

unlimited in the aggregate.

Such public liability insurance may include sub-limits:

• For liability arising out of vibration, weakening or

removal of support, of not less than:

($) Not Required

• For liability under the Forest and Rural Fires Act 1977,

of not less than:

($) Not Required

8.5.2 Where required (see 8.1 above), motor vehicle third party

liability insurance shall be effected for an amount not less

than:

($) 5 Million

8.6 Contractor arranged professional indemnity insurance

8.6.1 Where required (see 8.1 above), professional indemnity

insurance for design by the Contractor shall be effected for

an amount not less than:

• For any one claim: ($) 5 Million.

• And for an amount in the aggregate of: ($) Unlimited in the aggregate.

8.6.2 Sub-limits of liability for design of parts of the Contract

Works by Subcontractors shall be not be less than:

(list specific part(s) of Contract Works and applicable $ sub-limits for any one

claim and for an amount in the aggregate, or state if not required)

Same as per 8.6.1

8.8 Principal arranged construction insurance (refer also to 8.3)

In accordance with 8.7.2, the insurance policy wording title

for 8.8.1 and 8.8.2 (a), (b), and (c) is:

Not Required

In accordance with 8.7.2, the extraordinary exclusions,

conditions, warranties or endorsements to the policy for

8.8.1 and 8.8.2 (a), (b), and (c) are:

Not Required

8.8.1 Where the Principal is required to effect construction

insurance (see 8.1 above):

The lead insurer is: Click to enter text

Address of lead insurer: Click to enter text

The Nominal Deductibles are:

• For damage arising out of the Contract Works: Click to enter text

• For other claims: Click to enter text

• For natural perils: Click to enter text

8.8.2(a) The existing structures are: Click to enter text

• The replacement value to be insured is: ($) Click to enter amount

• The lead insurer is: Click to enter text

• Address of lead insurer: Click to enter text

Page 44: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract Page 7 of 12

Clause in General Conditions

Title and subject matter Specific condition data (Expand cells if required or add a reference to further detail provided in Schedule 2.)

The Nominal Deductibles are:

• For damage arising out of the Contract Works: Click to enter text

• For other claims: Click to enter text

• For natural perils: Click to enter text

8.8.2(b) Other structures in the vicinity are: Click to enter text

• The replacement value to be insured is: ($) Click to enter amount

• The lead insurer is: Click to enter text

• Address of lead insurer: Click to enter text

The Nominal Deductibles are:

• For damage arising out of the Contract Works: Click to enter text

• For other claims: Click to enter text

• For natural perils: Click to enter text

8.8.2(c) Contents insurance:

• The replacement value to be insured is: ($) Click to enter amount

• The lead insurer is: Click to enter text

• Address of lead insurer: Click to enter text

The Nominal Deductibles are:

• For damage arising out of the Contract Works: Click to enter text

• For other claims: Click to enter text

• For natural perils: Click to enter text

8.9 Principal’s option to insure public liability

8.9.1 Where required (see 8.1 above), the Principal shall effect

public liability insurance for an amount not less than:

($) Not Required

The lead insurer is: Click to enter text

Address of lead insurer: Click to enter text

The Nominal Deductible is: Click to enter text

In accordance with 8.7.2:

• the policy wording title is: Click to enter text

• extraordinary exclusions, conditions, warranties, or

endorsements to the policy are:

Click to enter text

8.9.2 Such public liability insurance may include sub-limits for:

(specify as applicable or state ‘not applicable’)

• Liability arising out of vibration, weakening or removal

of support:

($) Click to enter amount

• Liability under the Forest and Rural Fires Act 1977: ($) Click to enter amount

Page 45: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract Page 8 of 12

Clause in General Conditions

Title and subject matter Specific condition data (Expand cells if required or add a reference to further detail provided in Schedule 2.)

9 VARIATIONS

9.3 Valuation of Variations

9.3.9 For On-site Overheads: (select one to apply, (a) or (b))

(a) The prices and rates in the Schedule of Prices are

inclusive of full allowance for On-site Overheads;

(b) The prices and rates in the Schedule of Prices are

exclusive of On-site Overheads and the allowance for

On-site Overheads to be added in accordance with

9.3.9 is:

☐ (select one to apply, (i), (ii), (iii), or (iv))

(i) Agreed percentage: ☐ Not Required (%)

(ii) As nominated in the Schedule of Prices; ☐

(iii) As nominated in the Contractor’s tender; ☐

(iv) A reasonable percentage. ☐

9.3.10 For Off-site Overheads and Profit: (select one to apply, (a) or (b))

(a) The prices and rates in the Schedule of Prices are

inclusive of full allowance for Off-site Overheads and

Profit;

(b) The prices and rates in the Schedule of Prices are

exclusive of Off-site Overheads and Profit and the

allowance for Off-site Overheads and Profit to be

added in accordance with 9.3.10 is:

☐ (select one to apply, (i), (ii), (iii), or (iv))

(i) Agreed percentage: ☐ Click to enter % (%)

(ii) As nominated in the Schedule of Prices; ☐

(iii) As nominated in the Contractor’s tender; ☐

(iv) A reasonable percentage. ☐

9.3.11 For time-related Cost, the Working Day rate in

compensation for time-related On-site Overheads and Off-

site Overheads and Profit in relation to an extension of time

to be applied in accordance with 9.3.11 is:

(select one to apply, (a), (b), (c), or (d))

(a) Agreed rate per Working Day: ☐ ($) Click to enter amount

(b) As nominated in the Schedule of Prices; ☒

(c) As nominated in the Contractor’s tender; ☐

(d) Reasonable compensation. ☐

Page 46: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract Page 9 of 12

Clause in General Conditions

Title and subject matter Specific condition data (Expand cells if required or add a reference to further detail provided in Schedule 2.)

9.3.15 For processing of Variations, the percentage to be paid in

accordance with 9.3.15 is:

(select one to apply, (a), (b), (c), or (d))

(a) Agreed percentage: ☐ Click to enter % (%)

(b) As nominated in the Schedule of Prices; ☐

(c) As nominated in the Contractor’s Tender; ☐

(d) The reasonable Cost of processing Variations. ☒

10. TIME FOR COMPLETION

10.2 Due Date for Completion

10.2.1 The periods to be used for calculating the Due Date for

Completion are:

(a) For the Contract Works: 21 (Working Days)

(b) For any Separable Portions: 21 (Working Days)

10.4 Practical Completion Certificate

10.4.5 Prior to issue of the Practical Completion Certificate: (Select one to apply, (a), (b), or (c))

(a) Producer Statements in the form of Schedule 6 are

required;

(b) Producer Statements as set out in the following parts of

the Contract are required:

(c) Producer Statements are not required. ☐

10.5 Damages for late completion

10.5.1 Liquidated damages shall be applied as follows:

• In respect of the Contract Works: $500 ($ per Working Day)

• In respect of any Separable Portion(s): $500 ($ per Working Day for each Separable Portion)

Click to enter details

10.6 Bonus for early completion

10.6.1 Is a bonus to be payable? No

• If yes, the bonus for the Contract Works is: Click to enter amount ($ per Working Day)

• If yes, bonuses for any Separable Portions are: Click to enter amount ($ per Working Day)

11. DEFECTS LIABILITY

11.1 Defects Notification Period

The Defects Notification Period shall be:

(3 Months unless otherwise stated)

• For the Contract Works: Not Required

• For any Separable Portions: Not Required

Page 47: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract Page 10 of 12

Clause in General Conditions

Title and subject matter Specific condition data (Expand cells if required or add a reference to further detail provided in Schedule 2.)

11.3 Final Completion Certificate

11.3.2 Prior to issue of the Final Completion Certificate: (select one to apply, (a), (b), or (c))

(a) Producer Statements in the form of Schedule 6 are

required;

(b) Producer Statements as set out in the following parts of

the Contract are required:

(c) Producer Statements are not required. ☐

11.5 Warranties

11.5.1 (select one to apply, (a) or (b))

(a) No warranties are required; ☐

(b) The Contractor shall provide warranties as set out in

the Contract for the following items of work:

☒ Refer Schedule 13

11.6 Guarantees

11.6.1,

11.6.2

(select one to apply, (a) or (b))

(a) No guarantees are required; ☒

(b) The Contractor shall provide guarantees in the

following form:

12. PAYMENTS

12.1 Contractor’s payment claims

12.1.3(b)

(iii)

Advances for Materials delivered to the Site (select one to apply, (a) or (b))

(a) Advances for Materials delivered to the Site but which

have yet to be incorporated in the Contract Works shall

not be made;

(b) Advances for Materials delivered to the Site but which

have yet to be incorporated in the Contract Works shall

be made, subject to the following conditions:

☐ Not Required

12.1.3(b)

(iv)

Advances for Temporary Works or Plant (select one to apply, (a) or (b))

(a) Advances for Temporary Works or Plant shall not be

made;

(b) Advances for Temporary Works or Plant shall be made,

subject to the following conditions:

☐ Not Required

12.1.3(b)

(iv)

Advances for Materials not yet on Site (select one to apply, (a) or (b))

(a) Advances for Materials not on Site shall not be made; ☒

(b) Advances for Materials not yet on Site shall be made,

subject to the following conditions:

☐ Not Required

Page 48: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract Page 11 of 12

Clause in General Conditions

Title and subject matter Specific condition data (Expand cells if required or add a reference to further detail provided in Schedule 2.)

12.3 Retention monies

12.3.1,

12.3.2

The percentage to be retained from each progress payment

and the limit of the total sums retained shall be in

accordance with the following:

(select one to apply, (a) or (b))

(a) For the Contract Works, a total retention of:

• 10% on the first $200,000, and

• 5% on the next $800,000, and

• 1.75% on amounts in excess of

$1,000,000, and

• With a maximum total retention when aggregated

of $200,000, and

• With a defects liability retention of half

the total retention.

(b) The retention scale in the right hand column: ☐

12.3.3 Bond in lieu of retention (select one to apply, (a) or (b))

(a) The Contractor may provide a bond in lieu of

retentions;

(b) The Contractor may not provide a bond in lieu of

retentions.

12.8 Cost fluctuations (select one to apply, (a), (b), or (c))

(a) Cost fluctuations shall not be paid; ☒

(b) Cost fluctuations shall be paid in accordance with

Appendix A;

(c) Cost fluctuations shall be paid in accordance with the

method described in:

☐ Click to add reference

12.13 Goods and services tax

12.13.2 Payment Schedules provided by the Engineer: (select one to apply, (a) or (b))

(a) Shall not be in the form of a tax invoice; ☐

(b) Shall be in the form of a buyer created tax invoice and

the parties agree not to issue any other tax invoice for

items covered by the Payment Schedule.

13. DISPUTES

13.4 Arbitration

13.4.3 If required, the arbitrator shall be nominated by the

following Person:

Engineer to Contract

Page 49: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 1 – Special Conditions of Contract – Specific Conditions of Contract Page 12 of 12

Clause in General Conditions

Title and subject matter Specific condition data (Expand cells if required or add a reference to further detail provided in Schedule 2.)

15. SERVICE OF NOTICES

15.1.2 For the purpose of service of written notice:

(a) The address of the Principal is:

Postal address: PO Box 112

Delivery address: Main Office

Avarua

Mark for the attention of: Project Manager

Email address: [email protected]

Other agreed means of electronic communication and

address detail:

Click to enter text

(b) The address of the Contractor is:

Postal address: Click to enter text

Delivery address: Click to enter text

Mark for the attention of: Click to enter text

Email address: Click to enter text

Other agreed means of electronic communication and

address detail:

Click to enter text

(c) The address of the Engineer is:

Postal address: Level 1, PriceWaterhouseCoopers Building

36 Munroe Street

Napier 4110

New Zealand

Delivery address: Click to enter text

Mark for the attention of: Stephen Peters

Email address: [email protected]

Other agreed means of electronic communication and

address detail:

Click to enter text

Page 50: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

McMahon Engineering Consulatncy Ltd h

Parties may modify the specifics of t

NZS 3916:2013 – Schedule 2 – Special Conditions of Contract – Other Conditions of Contract Page 1 of 1

NZS 3916:2013 Conditions of contract for building and civil engineering – Design and construct

Schedule 2 – Special Conditions of Contract – Other Conditions of Contract

(Include here other Special Conditions that modify the General Conditions.)

TAU Power House New SCADA System Project (8080079501-SCADA)

Clause 1.2 Definitions, is to be amended as follows:

Remove GST Invoice

Insert VAT Invoice – A tax invoice for the purpose of the Cook Islands Value Added Tax Act 1997.

All references to GST in the contract to be read as VAT.

Clause 1.4.1 is to be amended to read:

The contract shall be governed by Cook Island Law.

Clause 1.4.2 is to be amended to read:

All prices and payments made under the Contract shall be in New Zealand currency and payable in Cook Islands. All prices and rates are stated exclusive of Cook Islands Valued Added Tax, which is to be added and paid where appropriate. The contractor will register (if required) for VAT in the Cook Islands in the ordinary way.

Schedule 9 – Information on Public Liability Insurance

As an alternative to completing Schedule 9, TAU will accept copies of certificates of currency for public liability clearly stating insurer details, insurance limits, expiry date, policy number and any exclusions to the policy.

Schedules

3 - Form of Contractor’s Performance Bond

4 - Form of Principle’s Bond

5 - Form of Contractor’s Bond in Lieu of Retentions

and

12 - Information on Principle Arranged Construction Insurance

are not required under this contract.

Page 51: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 6 – Form of Producer Statement – Construction Page 1 of 1

NZS 3916:2013 Conditions of contract for building and civil engineering – Design and construct

Schedule 6 – Form of Producer Statement – Construction

ISSUED BY Click to enter text (Contractor)

TO TAU (Principal)

IN RESPECT OF TAU Power House New SCADA System Project (8080079501/SCADA) (Description of Contract Works)

AT Avatiu Valley Power Station, Rarotonga (Address)

Click to enter the Contractor (Contractor) has contracted to TAU (Principal) to carry out and complete certain building works in accordance with a Contract titled TAU Power House New SCADA System Project (‘the Contract’)

I Click to enter name (Duly Authorised Agent) a duly authorised representative of Click to enter text (Contractor) believe on

reasonable grounds that Click to enter text (Contractor) has carried out and completed:

☐ All

☐ Part only as specified in the attached particulars of the contract works in accordance with the Contract

Click to enter details of attached particulars

Click to enter text or paste signature Date Click to enter a date

(Signature of Authorised Agent on behalf of)

Click to enter text

(Contractor)

Click to enter text

(Address)

Page 52: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 7 –Information on Contractor arranged construction insurance Page 1 of 2

NZS 3916:2013 Conditions of contract for building and civil engineering – Design and construct

Schedule 7 – Information on Contractor arranged construction insurance

To whom it may concern:

From Click to enter text (Name of insurance company)

Click to enter text (Branch)

Click to enter text (Address)

We confirm having effected construction insurance for:

Click to enter text (The Contractor)

TAU (The Principal)

In respect of TAU Power House New SCADA System Project (Project title)

Policy wording title is Click to enter text

The following provisions apply:

☐ Project specific policy

☐ Annual run-off policy

☐ Annual cut-off policy

We advise that special terms, copy attached, have been applied to this policy Select yes or no

8.1.6

The following forces of nature are insured:

☐ landslip ☐ earthquake ☐ tsunami

☐ tornado ☐ cyclone ☐ storm

☐ flood ☐ lightning strike ☐ volcanic activity

☐ hydrothermal activity ☐ geothermal activity

8.3.3

The sums insured are (GST exclusive):

Contract Price $ Click to enter amount

(a) Costs of demolition $ Click to enter amount

(b) Professional fees $ Click to enter amount

(c) Value of items supplied free to be incorporated $ Click to enter amount

(d) An allowance for an increase in construction costs $ Click to enter amount

(e) An allowance for increased reconstruction costs $ Click to enter amount

TOTAL SUM INSURED $ Click to enter amount

Page 53: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 7 –Information on Contractor arranged construction insurance Page 2 of 2

The policy deductibles are (GST inclusive): $ Click to enter amount

Non-earthquake $ Click to enter amount

Natural disaster Click to enter % % of Click to enter text minimum of $ Click to enter amount

Other (name) Click to enter text $ Click to enter amount

8.2.3(a)

Construction period from Click to enter a date to Click to enter a date

Insurance maintenance period Click to enter text

Policy expiry date Click to enter a date

Policy cover terms included are:

8.2.2 Discretionary cancellation clause Select yes or no

8.2.3 Reinstatement provision on building and contents Select yes or no

8.2.3 Severally insured Select yes or no

No settlement delay due to exercise of subrogation Select yes or no

8.2.4 Void ab initio for non-payment of premium without prior notification Select yes or no

Policy extensions included are: Sub-limit (if applicable)

8.3.1 Transit (in New Zealand) Select yes or no $ Click to enter amount

8.3.1 Materials in storage (in New Zealand) Select yes or no $ Click to enter amount

Testing and commissioning Select yes or no $ Click to enter amount

Expediting expenses Select yes or no $ Click to enter amount

Overseas airfreight Select yes or no $ Click to enter amount

We undertake that this policy will not be cancelled or amended by us within the period of insurance without written advice

to the insured party which has arranged the insurances.

This insurance issued is subject to the terms and conditions of the policy. We do not warrant that this policy complies

with the requirements of NZS 3916:2013.

Insurance Company Stamp Click to enter text Date Click to enter a date

(Or name of insurance broking company confirming cover)

SIGNED BY Click to enter text or paste signature

SIGNATORY TITLE Click to enter text

(Clause numbers refer to NZS 3916:2013 and are for information only.)

Page 54: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 9 – Information on public liability insurance Page 1 of 2

NZS 3916:2013 Conditions of contract for building and civil engineering – Design and construct

Schedule 9 – Information on public liability insurance

To whom it may concern:

From Click to enter text (Name of insurance company)

Click to enter text (Branch)

Click to enter text (Address)

We confirm having effected public liability insurance to indemnify the Principal and the Contractor against legal liability to

third parties for damage, loss or injury caused by an act or omission of the Contractor arising out of the performance of

the Contract Works.

Click to enter text (The Contractor)

Click to enter text (The Principal)

In respect of Click to enter text (Project title)

Policy wording title is Click to enter text

We advise that special terms, copy attached, have been specifically applied to this project Select yes or no

The following provisions apply:

☐ Annual policy

☐ Project specific policy

Policy expiry date Click to enter a date

8.5, 8.9

The limit of indemnity (GST exclusive) $ Click to enter amount

Sub-limit insured for (GST exclusive)

Vibration, removal, or weakening of support $ Click to enter amount

Forest and Rural Fires Act 1977 $ Click to enter amount

Underground services $ Click to enter amount

Deductible (GST inclusive) is $ Click to enter amount

Deductible for vibration, removal, or weakening of support (GST inclusive) $ Click to enter amount

Deductible for underground services (GST inclusive) $ Click to enter amount

Page 55: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 9 – Information on public liability insurance Page 2 of 2

The policy also covers liability arising out of:

The ownership/use of Plant not required to be registered for road use Select yes or no

The use of hired Plant Select yes or no

The ownership/use of watercraft over 8 m Select yes or no

The ownership/use of aircraft Select yes or no

The use of explosives Select yes or no

8.2, 8.7

Policy cover terms included are:

Reinstatement provisions Select yes or no

Number of reinstatements Click to enter number

Discretionary cancellation clause Select yes or no

Void ab intio for non-payment of premium without prior notification Select yes or no

Severally insured Select yes or no

No settlement delay due to exercise of subrogation Select yes or no

We undertake that this policy will not be cancelled or amended by us without written advice to the insured party which

has arranged the insurances.

This insurance issued is subject to the terms and conditions of the policy. We do not warrant that this policy complies

with the requirements of NZS 3916:2013.

Insurance Company Stamp Click to enter text Date Click to enter a date

(Or name of insurance broking company confirming cover)

SIGNED BY Click to enter text or paste signature

SIGNATORY TITLE Click to enter text

(Clause numbers refer to NZS 3916:2013 and are for information only.)

Page 56: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 10 – Information on Contractor arranged motor vehicle insurance Page 1 of 2

NZS 3916:2013 Conditions of contract for building and civil engineering – Design and construct

Schedule 10 – Information on Contractor arranged motor vehicle insurance

To whom it may concern:

From Click to enter text (Name of insurance company)

Click to enter text (Branch)

Click to enter text (Address)

We confirm having effected motor fleet insurance for

Click to enter text (The Contractor)

In respect of Click to enter text (Project title)

Policy wording title is Click to enter text

We advise that special terms, copy attached, have been applied to this policy Select yes or no

The following provisions apply:

☒ Annual policy

☐ Project specific policy

Policy expiry date Click to enter a date

8.5.2

The limits of liability are (GST exclusive):

Section 2 – Liability $ Click to enter amount

For any one occurrence arising out of the same event

The policy deductibles are:

Section 2 – Liability (GST inclusive) $ Click to enter amount

Plus under age penalties

8.2

Policy cover terms included are:

Section 2 Liability automatic reinstatement Select yes or no

Discretionary cancellation clause Select yes or no

Void ab initio for non-payment of premium without prior notification Select yes or no

No settlement delay due to exercise of subrogation Select yes or no

Page 57: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 10 – Information on Contractor arranged motor vehicle insurance Page 2 of 2

We undertake that this policy will not be cancelled or amended by us within the period of insurance without written advice

to the insured party which has arranged the insurances.

This insurance issued is subject to the terms and conditions of the policy. We do not warrant that this policy complies

with the requirements of NZS 3916:2013.

Insurance Company Stamp Click to enter text Date Click to enter a date

(Or name of insurance broking company confirming cover)

SIGNED BY Click to enter text or paste signature

SIGNATORY TITLE Click to enter text

(Clause numbers refer to NZS 3916:2013 and are for information only.)

Page 58: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 11 – Information on Contractor arranged professional indemnity insurance Page 1 of 1

NZS 3916:2013 Conditions of contract for building and civil engineering – Design and construct

Schedule 11 – Information on Contractor arranged professional indemnity insurance

To whom it may concern:

From Click to enter text (Name of insurance company)

Click to enter text (Branch)

Click to enter text (Address)

We confirm having effected professional indemnity insurance for:

Click to enter text (The Contractor)

In respect of Click to enter text (Project title)

Policy wording title is Click to enter text

We advise that special terms, copy attached, have been applied to this policy Select yes or no

The following provisions apply:

☐ Annual policy

☐ Project specific policy

Policy expiry date Click to enter a date

8.6.1

The limit of indemnity (GST exclusive) $ Click to enter amount any one occurrence

$ Click to enter amount in the aggregate during the period of insurance.

Deductible (GST inclusive) $ Click to enter amount

We undertake that this policy will not be cancelled or amended by us within the period of insurance without written advice

to the insured party which has arranged the insurances.

This insurance issued is subject to the terms and conditions of the policy. We do not warrant that this policy complies

with the requirements of NZS 3916:2013.

Insurance Company Stamp Click to enter text Date Click to enter a date

(Or name of insurance broking company confirming cover)

SIGNED BY Click to enter text or paste signature

SIGNATORY TITLE Click to enter text

(Clause numbers refer to NZS 3916:2013 and are for information only.)

Page 59: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 13 – Form of Contractor (or Subcontractor) warranty Page 1 of 3

NZS 3916:2013 Conditions of contract for building and civil engineering – Design and construct

Schedule 13 – Form of Contractor (or Subcontractor) warranty

THIS AGREEMENT is made on Click to enter a date (insert date)

BETWEEN Te Aponga Uira (‘the Principal’)

AND Click to enter text (‘the Contractor’)

AND Click to enter text (‘the Warrantor’)

DEFINITIONS

‘Warranted Works’ All hardware and software in relation to the Avatiu Valley Power Station

New SCADA System Project

‘Warranty Period’ 1 years from the date of Practical Completion of the Contract Works

BACKGROUND

A The Principal has entered into a contract (the ‘Contract’) with the Contractor for carrying out the Contract Works.

The Warranted Works are part of the Contract Works.

B The Contractor has agreed to arrange for the provision of a warranty in respect of the Warranted Works for the

Warranty Period on the terms set out in this warranty.

C The Warrantor has agreed to provide a warranty in respect of the Warranted Works for the Warranty Period on the

terms set out in this warranty.

IT IS HEREBY AGREED

1 The Warrantor warrants to the Principal that the Warranted Works are as required in the Contract. If not otherwise

specified the works shall be in accordance with good trade practice.

2 This warranty shall be in addition to and shall not derogate from any manufacturer’s warranty or any warranty

implied by law or the Defects Notification Period in the Contract, attaching to any part of the Warranted Works.

3 Warrantor’s obligations

3.1

The Warrantor agrees that, if within the Warranty Period the Warrantor is advised by the Principal in writing of any defect

in the Warranted Works for which the Warrantor is liable under the terms of this warranty, the Warrantor will promptly

take steps to remedy the defect.

3.2

Any remedial work which the Warrantor is liable to undertake under this warranty shall be carried out:

(a) To the standard required by the Contract;

(b) In a prompt and timely manner;

(c) Without unnecessary inconvenience to any occupants;

(d) At the Warrantor’s Cost; and

(e) Subject to reasonable access being provided to the Warrantor for the purpose of carrying out the remedial work.

Page 60: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 13 – Form of Contractor (or Subcontractor) warranty Page 2 of 3

3.3

Where the Cost of replacement of work and/or Materials is out of all proportion to the consequences of the defect, or

where the defect may not be reasonably capable of rectification without substantial expense which is out of all proportion

to the Cost of the Warranted Works:

(a) If the defect is reasonably able to be rectified by repair rather than by replacement, the Warrantor’s obligation

under this warranty shall be only to repair or otherwise make good the defect;

(b) The Warrantor may propose reasonable monetary compensation in lieu of remedying the defect; or

(c) The Warrantor may propose a combination of both repair and compensation.

3.4

The Principal shall consider the Warrantor’s reasonable proposals and the parties shall endeavour in good faith to reach

agreement. Where agreement cannot be reached, the dispute shall be resolved in accordance with clause 7.

4 Failure by Warrantor to perform remedial work

4.1

If the Warrantor fails to promptly, adequately and satisfactorily carry out the remedial work or to propose acceptable

repair or compensation, the Principal may then arrange for the remedial work to be carried out by others.

4.2

The Principal shall first give the Warrantor 10 Working Days notice, or such other reasonable time as agreed by the

Principal, to carry out and complete the remedial work. If the Warrantor does not do so within that time, the Principal may

then advise the Warrantor in writing that the work will be carried out by other Persons.

4.3

In such an event, the Warrantor is not released from its obligations under this warranty, which continue in full force and

effect, except for the defect remedied by the Principal or by another Person contracted by the Principal.

4.4

The reasonable Cost of remedial work carried out by such other Persons including all reasonable Costs of the Principal

shall be paid to the Principal by the Warrantor on demand.

5 Exclusions

The Principal agrees that the Warrantor is not liable for any defect or damage caused by:

(a) Wilful act or negligence of the Principal or any Person other than the Warrantor;

(b) Fire, explosion, earthquake, war, subsidence, slips, faulty materials, or workmanship other than caused by the

defect in the Warranted Works;

(c) Any force of nature which the Warrantor could not have reasonably foreseen;

(d) Any neglect or unnecessary delay by the Principal in giving notice to the Warrantor of a defect in the Warranted

Works becoming apparent;

(e) Design faults, errors, or discrepancies, unless the Warrantor undertook the design of the part of the Warranted

Works that is the subject of the defect;

(f) Use of the Warranted Works by the Principal or any other Person in any manner or for any purpose not being the

intended manner of use or purpose of the Warranted Works;

(g) Failure by the Principal or other Person to maintain the Warranted Works in accordance with good practice and any

manufacturer’s stated or recommended instructions or requirements; or

(h) Fair wear and tear.

Page 61: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 13 – Form of Contractor (or Subcontractor) warranty Page 3 of 3

6 Assignment

The Principal may assign the benefit of this warranty to any Person.

7 Disputes

Any dispute between the Principal and the Warrantor arising out of this warranty is to be referred to arbitration before a

sole arbitrator. If, within 15 Working Days of notice of dispute, the Principal and the Warrantor cannot agree on a single

arbitrator, either party may request the President of the Arbitrators’ and Mediators’ Institute of New Zealand to appoint an

arbitrator.

In witness of which this deed has been executed.

SIGNED on behalf of the Contractor by:

Click to enter text or paste signature

Director

SIGNED on behalf of the Warrantor by:

Click to enter text or paste signature

Director

Click to enter text or paste signature

Director

SIGNED on behalf of the Principal by:

Click to enter text or paste signature

Director

Click to enter text or paste signature

Director

NOTE – The warranty shall be executed by the Warrantor and the Principal in the manner required for execution of a deed. Any of these

parties which are a company shall execute the warranty by having it signed, under the name of the company, by two or more directors.

If there is only one director, it is sufficient if the Warranty is signed under the name of the company by that director, but the signature

shall be witnessed by another person. The witness shall not only sign but shall also add his or her occupation and address.

Alternatively, companies may execute under power of attorney. Any party which is a body corporate (other than a company) shall

execute by affixing its seal, which shall be attested in the manner provided for in the rules of, or applicable to, the body corporate. In the

case of a party who is an individual, the party shall sign and the signature shall be witnessed by another person. The witness shall not

only sign but shall also add his or her occupation and address.

Page 62: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 14 – Agreement for off-site Materials Page 1 of 4

NZS 3916:2013 Conditions of contract for building and civil engineering – Design and construct

Schedule 14 – Agreement for off-site Materials

THIS AGREEMENT is dated the Click to enter day day of Click to enter month 20 Click to enter year

BETWEEN Te Aponga Uira (‘the Principal’)

AND Click to enter text (‘the Contractor’)

AND Click to enter text (‘the Warrantor’)

INTRODUCTION:

A By a contract dated the Click to enter day day of Click to enter month 20 Click to enter year and known as Click to

enter text (‘the Contract’) made between the Principal and the Contractor, the Contractor agreed to carry out the

work and obligations imposed on the Contractor by the Contract (‘the Contract Works’).

B The Contractor and the Subcontractor have entered into a subcontract for the performance of part of the Contract

Works and/or the supply of Materials described in Schedule A to this agreement (‘the Materials’) and intended to be

used by the Contractor and/or the Subcontractor in the Contract Works.

C The Contractor or the Subcontractor (as nominated in Schedule C) (‘the Bailee’) proposes to store the Materials at

the premises of the Bailee (‘the Premises’) as identified in Schedule B as bailee for the Principal, for the purpose of

storage, fabrication, sub-assembly, or as otherwise required for the Contract Works prior to being delivered to the

Site for incorporation into the Contract Works.

D The Contractor has requested the Principal to authorise the Engineer to certify payment for the Materials

notwithstanding that the Materials have not been delivered to the Site.

E The Principal has agreed to authorise the Engineer to certify payment for the Materials, notwithstanding that the

Materials have not been delivered to the Site, subject to all the provisions of this agreement having been fulfilled.

SCHEDULE A

Description of Materials inclusive of work performed on them:

Click to enter text

SCHEDULE B

The location in New Zealand at which the Materials will be stored is:

Click to enter text

SCHEDULE C

‘The Bailee’ shall be:

☐ The Contractor

OR

☐ The Subcontractor

Page 63: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 14 – Agreement for off-site Materials Page 2 of 4

IT IS AGREED AS FOLLOWS:

1. THE Materials to which this agreement relates are those described in Schedule A to this agreement, all of which

Materials are currently on the Premises identified in Schedule B.

2. THE Premises identified in Schedule B are in the sole control of the party identified in Schedule C and that party

shall act as bailee of the Materials until such time as the Materials are delivered to the Site or taken possession of

by the Principal.

3. THE undertakings, warranties, covenants, agreements and other obligations of the Contractor or the Subcontractor

shall bind and be deemed to have been given or assumed by each of them severally and by both of them jointly.

4. THE Contractor and the Subcontractor agree that they will cause the Materials to be set apart at the Premises and

be clearly and visibly marked individually or in sets as being the property of the Principal and their destination as

being the Site. The method used to mark the Materials and the procedures by which the mark is applied to the

Materials shall be as required by the Contract or as otherwise approved by the Principal.

5. NEITHER the Contractor nor the Subcontractor will permit, allow, or cause the Materials to be taken away from the

Premises, except:

(a) For the purpose of being transported to the Site and used in the Contract Works; or

(b) That the Principal may at its sole discretion take possession of the Materials for use other than for the

Contract Works;

provided that:

(c) Where the Principal takes possession of any Materials under clause 5(b) above, and the Contractor thereby

suffers delay or the Contractor or the Subcontractor incurs additional cost, the taking of possession shall be

treated as a Variation under the Contract, unless the taking of possession is pursuant to clauses 14.2.1 or

14.2.2 of the Contract; and

(d) Where the Principal takes possession of any Materials under clause 5(b) above, and additional work has

been carried out on those Materials since being paid for by the Principal, the Principal shall pay the

Contractor for that additional work in accordance with the Contract before taking possession of the Materials.

6. THE Engineer, upon being satisfied that the Materials have been set apart and marked as required by this

agreement, and upon the Contractor providing satisfactory evidence that the requirements of clauses 12 and 20

below have been fully satisfied, shall include in any Payment Schedule issued by the Engineer under the Contract

a sum representing the reasonable value of such Materials calculated in accordance with the Contract.

7. UPON the Principal having made payment for the Materials, less any retentions or deductions prescribed in the

Contract, title to such Materials shall immediately vest in the Principal free of all security interests, charges and

encumbrances of any nature whatsoever.

8. WHERE the Contractor receives payment for Materials and the Subcontractor is entitled to some or all of the

Principal’s payment, the Contractor shall promptly pay the Subcontractor for such Materials.

9. UPON the request of the Subcontractor, the Engineer shall advise the Subcontractor whether the Contractor has

received any payment from the Principal for such Materials.

10. THE Contractor and the Subcontractor agree that the Materials will be held by the Contractor or the Subcontractor

solely as bailee for the Principal and such bailment will constitute a security interest in favour of the Principal for the

purpose of the Personal Property Securities Act 1999 (‘the PPSA’).

11. THE Principal shall (at the Contractor’s reasonable cost) register a financing statement on the Personal Property

Securities Register (‘the PPSR’) listing the Principal as secured party and the Contractor and the Subcontractor as

debtors for any security interest arising from the bailment of the Materials referred to in this agreement.

12. THE Bailee shall promptly do all things including executing any documents and providing all information which the

Principal requires to ensure that the Principal receives and maintains at all times a first ranking security interest in

the Materials. This shall include procuring from any third party who has registered a financing statement against

the Bailee, a waiver, in a form acceptable to the Principal, of any security interest or claim which might otherwise

extend to the Materials or their proceeds.

Page 64: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 14 – Agreement for off-site Materials Page 3 of 4

13. THE Bailee shall not discharge or amend any financing statement registered under clause 11 above without the

prior written consent of the Principal.

14. NOTHING in sections 114(1)(a), 133, and 134 of the PPSA shall apply to this agreement.

15. ANY rights of the Contractor and the Subcontractor as debtors under sections 116, 120(2), 121, 125, 126, 127,

129, 131, and 148 of the PPSA shall not apply to this agreement.

16. THE Bailee hereby grants to the Principal reasonable, free, and unencumbered right of access to the Premises to:

(a) Inspect the Materials, and verify or undertake the marking and setting apart of the Materials;

(b) Take possession of the Materials for the purpose of delivery to the Site and inclusion in the Contract Works;

(c) Remove the Materials from the Premises for the purpose of delivery to the Site and inclusion in the Contract

Works; and

(d) Take possession of the Materials for use other than for the Contract Works,

and in each case in a manner that does not cause damage to any other property at the Premises. The Bailee shall

take all steps and do all things as shall be necessary to ensure that the Principal obtains access to the Premises

for the purposes of this agreement.

17. THE Bailee shall not, except as permitted in clause 5, remove or cause or permit the Materials to be moved from

the Premises. The Bailee shall nevertheless be responsible to the Principal for any loss or damage thereto and for

any costs of storage or handling.

18. THE Bailee shall, when required to do so by the Contractor or the Principal, arrange for the transportation of the

Materials to the Site. Such transportation shall be at the cost of the Bailee in all things including loading, unloading,

and freight.

19. WHERE the Materials are not insured under the construction policy provided in accordance with 8.3.1

or 8.8.1 of the Contract, the Bailee shall, at its expense:

(a) Effect a material damage insurance policy covering all of the Materials subject to this agreement in the name

of the Principal to the satisfaction of the Principal, as provided in 8.2.1 of the Contract for the full duration of

the off-site storage. Such insurance may include an exclusion for loss or damage sustained during

processing;

(b) Effect a transit insurance policy for transit of all the Materials from the Premises to the Site in the name of the

Principal to the satisfaction of the Principal, as provided in 8.2.1 of the Contract for the full duration of the off-

site storage.

20. WITHIN 15 Working Days of the date of this agreement, the Bailee shall furnish the Principal and the Contractor

with evidence of such insurance.

21. THE Bailee represents and warrants to the Principal and to the Contractor (where applicable) that:

(a) It has good and clear title to the Materials;

(b) It has the ability to assign and transfer the Materials to the Principal or the Contractor; and

(c) The Materials will be transferred to the Principal or the Contractor free of any security interest.

22. THE Bailee undertakes that, if it charges or mortgages all or any part of its property (either real or personal),

assets, or undertaking, it will obtain written confirmation from the chargee or mortgagee that the charge or the

mortgage over such property, assets, or undertaking does not extend to the Materials once they have been paid for

by the Principal or the Contractor (as applicable).

23. NOTHING in this agreement shall be deemed to limit, waive, or affect the Engineer’s powers under the Contract to

order the removal from the Site or the Premises of Materials which are not in accordance with the Contract and the

substitution by the Contractor at its own risk and expense of proper Materials. Nothing in this agreement shall be

deemed to limit, waive or affect any other powers conferred on the Engineer and/or the Principal under the

Contract.

24. EACH party shall pay its own costs of and incidental to the negotiation, preparation, execution, and any

amendment of this agreement.

Page 65: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 14 – Agreement for off-site Materials Page 4 of 4

25. WORDS and phrases in this agreement shall have the same meanings as are ascribed to them under the Contract

except where the context or any express provision of this agreement requires otherwise.

SIGNED BY Click to enter text or paste signature (Authorised Signatory)

of Click to enter text (Principal)

SIGNED BY Click to enter text or paste signature (Authorised Signatory)

of Click to enter text (Contractor)

SIGNED BY Click to enter text or paste signature (Authorised Signatory)

of Click to enter text (Subcontractor)

Page 66: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 15 – Practical Completion Certificate Page 1 of 1

NZS 3916:2013 Conditions of contract for building and civil engineering – Design and construct

Schedule 15 – Practical Completion Certificate

This Practical Completion Certificate is issued under 10.4.3(a) or 10.4.4.

Contract for Avatiu Valley Power Station

New SCADA System (8080079501/SCADA) (Contract name and number if applicable)

Principal Te Aponga Uira (Insert name of Principal)

Contractor Click to enter text (Insert name of Contractor)

This certificate relates to:

☐ (a) The whole of the Contract Works referred to above;

☒ (b) The following Separable Portion

Seperable Portion 1 – PV Plant and Power Station

Receipt of the Contractor’s notice dated Click to enter a date and issued in accordance with 10.4.2 is acknowledged.

In accordance with ☒ 10.4.3(a) or ☐ 10.4.4 (select one), the Engineer certifies that the Contract Works or Separable

Portion to which this certificate relates qualify for a Practical Completion Certificate under 10.4, notwithstanding that there

may be minor omissions and/or minor defects (as listed in the attached schedule) which satisfy the criteria in 10.4.1 (a),

(b), and (c).

The Contractor is required to remedy all of the listed omissions or defects within the period stated in the attached

schedule against the relevant omission or defect, or at the latest within 10 Working Days of the date of this certificate.

Practical Completion was achieved

on Click to enter a date at Click to enter time.

Signed by the Engineer Click to enter text or paste signature

Name Click to enter text

Date Click to enter a date

SCHEDULE

The following omissions and/or defects have been assessed as being of a minor nature satisfying the criteria in

10.4.1(a), (b), and (c) and were identified during an inspection carried out by the Engineer or Engineer’s Representative

on Click to enter a date

(List minor omissions and defects )

Click to enter text

Page 67: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 16 – Final Completion Certificate Page 1 of 1

NZS 3916:2013 Conditions of contract for building and civil engineering – Design and construct

Schedule 16 – Final Completion Certificate

This certificate is a Final Completion Certificate issued under 11.3.1.

Contract for Avatiu Valley Power Station

New SCADA System (8080079501/SCADA) (Contract name and number if applicable)

Principal Te Aponga Uira (Insert name of Principal)

Contractor Click to enter text (Insert name of Contractor)

This certificate relates to:

☐ (a) The whole of the Contract Works referred to above;

☒ (b) The following Separable Portion

Seperable Portion 1 – PV Plant and Power Station

In accordance with 11.3.1, the Engineer certifies that the Contract Works or Separable Portion to which this certificate

relates qualify for a Final Completion Certificate issued under 11.3

on Click to enter a date at Click to enter time.

Signed by the Engineer Click to enter text or paste signature

Name Click to enter text

Date Click to enter a date

Page 68: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 17 – Deed of novation Page 1 of 3

NZS 3916:2013 Conditions of contract for building and civil engineering construction – Design and construct

Schedule 17 – Deed of novation

THIS DEED is made on Click to enter a date (‘the Effective Date’)

BY Click to enter text (‘the Principal’)

Click to enter text (‘the Contractor’)

Click to enter text (‘the Consultant’)

IT IS MADE IN THE FOLLOWING CIRCUMSTANCES

A The Principal and the Consultant are parties to Click to enter text entered into on Click to enter a date, a copy of

which is attached and marked ‘A’ (‘the Contract’).

B With effect on and from the Effective Date, the Principal wishes to:

(i) Transfer all of its rights and obligations under the Contract to the Contractor, and

(ii) Be released from its obligations under the Contract.

C With effect on and from the Effective Date, the Contractor wishes to accept the transfer of all the Principal’s rights

and obligations under the Contract.

THE PARTIES AGREE

1. THIS deed shall take effect from the date of its execution (‘the Effective Date’).

2. THE Principal:

(a) Transfers to the Contractor all of its rights and obligations under the Contract;

(b) Warrants it has performed all of its obligations under the Contract up to the Effective Date; and

(c) Shall remain liable to the Consultant for any breach of the Contract by the Principal which occurred prior to

the Effective Date.

3. THE Contractor:

(a) Accepts the transfer with effect from the Effective Date;

(b) Confirms that, as from the Effective Date:

(i) The Contractor is substituted for the Principal under the Contract as if it had originally executed the

Contract in place of the Principal

(ii) All references in the Contract to the Principal are to be read and construed as if they were references to

the Contractor

(iii) The Contractor may exercise all the Principal’s rights under the Contract;

(c) Shall perform all of the Principal’s obligations under the Contract from the Effective Date.

4. THE Consultant:

(a) Consents to the transfer;

(b) Releases the Principal from all of its obligations under the Contract for the period following the Effective Date

(but for of any breach of the Contract that occurred prior to the Effective Date);

(c) Confirms that, as from the Effective Date:

Page 69: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 17 – Deed of novation Page 2 of 3

(i) The Contractor is substituted for the Principal under the Contract as if it had originally executed the

Contract in place of the Principal

(ii) All references in the Contract to the Principal are to be read and construed as if they were references to

the Contractor

(iii) The Contractor may exercise all of the Principal’s rights under the Contract;

(d) Shall remain liable to the Principal for any breach of the Contract by the Consultant which occurred prior to

the Effective Date.

5. THE terms of the Contract continue in full force and effect.

6. EACH party is to pay its own costs (including, without limitation, legal expenses) in entering into this deed.

7. EACH party is, at its own expense and at the request of any other party, to execute and deliver or cause its

successors and permitted assigns to do all things as may be reasonably requested by that other party to obtain the

full benefit of this document according to its true intent.

8. AN amendment to this deed will only be effective if it is in writing and signed by all parties.

9. THIS deed shall be construed and take effect in accordance with the laws of New Zealand.

EXECUTED as a deed

SIGNED on behalf of the Principal by:

Click to enter text or paste signature

Director

Click to enter text or paste signature

Director

SIGNED on behalf of the Contractor by:

Click to enter text or paste signature

Director

Click to enter text or paste signature

Director

SIGNED on behalf of the Consultant by:

Click to enter text or paste signature

Director

Click to enter text or paste signature

Director

NOTE –

(1) A copy of the design agreement being transferred (‘the Contract’) shall be attached and marked ‘A’.

(2) This deed shall be executed by the Contractor, the Principal, and the Consultant in the manner required for execution of a deed.

Any of these parties which are a company shall execute the bond by having it signed, under the name of the company, by two or

more directors. If there is only one director, it is sufficient if the deed is signed under the name of the company by that director, but

the signature shall be witnessed by another person. The witness shall not only sign but shall also add his or her occupation and

Page 70: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

NZS 3916:2013 – Schedule 17 – Deed of novation Page 3 of 3

address. Alternatively, companies may execute under power of attorney. Any party which is a body corporate (other than a

company) shall execute in the same manner as a company by persons in a comparable position to a company director or

otherwise in accordance with section 9 of the Property Law Act 2007. In the case of a party who is an individual, the party shall

sign and the signature shall be witnessed by another person. The witness shall not only sign but shall also add his or her

occupation and address.

Page 71: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Attachment 6:

Scope and Technical Specifications for the TAU Power House New SCADA System

Project

Page 72: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Attachment 6 Scope and Technical Specification for the TAU Power House New SCADA System Project - 4 Nov 14for the TAU Power House New SCADA System Project Page 2

Glossary

AVR Automatic Voltage Regular

CPU Central Processing Unit

DNP3 Distributed Network Protocol (v3)

D-UPS Diesel - Uninterruptable Power Supply

EtherNet/IP Industrial Ethernet specific to Rockwell equipment

FAT Factor Acceptance Testing

HV High Voltage

HMI Human Machine Interface (user screen)

HVAC Heating, Ventilation and Air-Conditioning

IEC International Electro-technical Commission

I/O Inputs / Outputs

KVM Keyboard, Video and Mouse

LAN Local Area Network

LV Low Voltage

MECL McMahon Engineering Consultancy Ltd

MODBUS Modicon Bus

OLE Object Linking and Embedding

OPC OLE for Process Control

PI Process Information

RAID Redundant Array of Independent disks

RTU Remote Terminal Unit

SCADA Supervisory Control and Data Acquisition

SNMP Simple Network Management Protocol

SQL Structured Query Language

TAU Te Aponga Uira

TCI Telecom Cook Islands

TCP/IP Transmission Control Protocol/Internet Protocol

Page 73: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 3

Table of Contents

1  SCOPE AND GENERAL ................................................................................................................. 6 1.1  Overview ......................................................................................................................................................................... 6 

1.2  This Tender .................................................................................................................................................................... 7 

1.3  Stage One – Airport PV Integration and Power Station Existing Equipment Migration ................................... 8 

1.4  Stage Two – New Gensets ........................................................................................................................................... 8 

1.5  Stage Three – Future Plant and Sites .......................................................................................................................... 8 

2  TECHNICAL REQUIREMENTS ....................................................................................................... 9 2.1  Hardware ........................................................................................................................................................................ 9 

2.1.1  SCADA Servers and Historian .............................................................................................................. 9 

2.1.2  Operator Workstations ........................................................................................................................... 9 

2.1.3  Printers ................................................................................................................................................. 10 

2.1.4  Network Equipment ............................................................................................................................. 10 

2.1.5  Device Servers ..................................................................................................................................... 10 

2.1.6  Corporate Interface .............................................................................................................................. 11 

2.1.7  Uninterruptable Power Supplies .......................................................................................................... 11 

2.1.8  Racks ................................................................................................................................................... 11 

2.1.9  Fibre Optics ......................................................................................................................................... 12 

2.2  Software ........................................................................................................................................................................ 14 

2.2.1  General Requirements ......................................................................................................................... 14 

2.2.2  Communication Protocols ................................................................................................................... 14 

2.2.3  Data Types ........................................................................................................................................... 14 

2.2.4  Tag Names ........................................................................................................................................... 15 

2.2.5  SCADA Server Operating System ....................................................................................................... 16 

2.2.6  Operator Workstations ......................................................................................................................... 16 

2.2.7  SCADA Server Failover ...................................................................................................................... 16 

2.2.8  Expert System Programming Software ................................................................................................ 16 

2.2.9  Response Time .................................................................................................................................... 17 

2.2.10  Diagnostic Software ........................................................................................................................ 17 

2.2.11  Time Synchronisation ..................................................................................................................... 17 

2.3  HMI Functionality ....................................................................................................................................................... 18 

2.3.1  Overview ............................................................................................................................................. 18 

2.3.2  Specific Display Requirements ............................................................................................................ 19 

2.3.3  Miscellaneous HMI Functions ............................................................................................................. 20 

2.4  Scalability ...................................................................................................................................................................... 23 

3  ELECTRICAL GENERAL REQUIREMENTS ................................................................................ 24 3.1  Language and Units ..................................................................................................................................................... 24 

Page 74: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 4

3.1.1  Language ............................................................................................................................................. 24 

3.1.2  Units of Measurement ......................................................................................................................... 24 

3.2  Manuals ......................................................................................................................................................................... 24 

3.2.1  General ................................................................................................................................................ 24 

3.2.2  Quality Assurance Manual .................................................................................................................. 24 

3.2.3  Operating and Maintenance Manuals .................................................................................................. 25 

3.3  Drawings and Documentation ................................................................................................................................... 26 

3.4  Design Approvals and Information .......................................................................................................................... 27 

3.4.1  Approvals ............................................................................................................................................ 27 

3.5  Workmanship and Materials ...................................................................................................................................... 27 

3.6  Preferred Equipment ................................................................................................................................................... 28 

3.7  Packing and Shipping .................................................................................................................................................. 28 

3.7.1  Packing ................................................................................................................................................ 28 

3.7.3  Hazardous Areas .................................................................................................................................. 29 

3.8  Electrical Works ........................................................................................................................................................... 29 

3.8.1  General ................................................................................................................................................ 29 

3.8.2  Site Induction Requirements................................................................................................................ 29 

3.8.3  General Technical Requirements ......................................................................................................... 29 

3.8.4  Local Environment .............................................................................................................................. 29 

3.8.5  Available Utilities ................................................................................................................................ 30 

3.9  Equipment .................................................................................................................................................................... 30 

3.9.1  PLC / Control Cubicles ........................................................................................................................ 30 

3.9.2  Equipment Labels ................................................................................................................................ 31 

3.9.3  Cables - General .................................................................................................................................. 31 

4  WORK METHODOLOGY .............................................................................................................. 31 4.1  SCADA Standards Manual ......................................................................................................................................... 33 

4.2  Software Development ............................................................................................................................................... 33 

4.3  SCADA System Configuration .................................................................................................................................. 33 

4.4  Points Database ........................................................................................................................................................... 34 

4.5  Expert System Software Development ..................................................................................................................... 34 

5  INSTALLATION ............................................................................................................................. 34 5.1  Installation of Wall Mounted Cubicles ..................................................................................................................... 35 

5.2  UPS ................................................................................................................................................................................ 35 

5.3  SCADA Servers and Historian .................................................................................................................................. 35 

5.4  Workstations ................................................................................................................................................................ 35 

5.5  Firewall .......................................................................................................................................................................... 36 

6  TESTING AND COMMISSIONING ................................................................................................ 36 6.1  Factory Testing ............................................................................................................................................................ 36 

Page 75: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 5

6.2  Site Commissioning Tests .......................................................................................................................................... 36 

6.2.1  Setup and Pre-commissioning ............................................................................................................. 36 

6.2.2  Site Commissioning ............................................................................................................................. 36 

6.3  Handover - Stage One ................................................................................................................................................ 37 

6.4  Handover – Stage 2 ..................................................................................................................................................... 37 

6.5  Handover Subsequent Stages ..................................................................................................................................... 37 

7  TRAINING ...................................................................................................................................... 37 

8  SUPPORT ...................................................................................................................................... 38 8.1  On Site Support ........................................................................................................................................................... 38 

8.2  Remote Support ........................................................................................................................................................... 38 

8.3  Software ........................................................................................................................................................................ 38 

8.4  Drawings and Documents .......................................................................................................................................... 38 

9  EXCLUSIONS ................................................................................................................................ 39 

Page 76: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 6

1 Scope and General

1.1 Overview

The Government of the Cook Islands has embarked on the introduction of local renewable power

generation in its consumer base. The Cook Islands government wishes to achieve a target of 50%

renewable energy generation by 2015 and 100% by 2020. The main source of renewable energy will

be solar power in the form of photovoltaic cells.

The existing power station on the island of Rarotonga contains seven diesel gen-sets ranging from

0.6MW to 2.7MW. There is an additional 0.8MW hire set. A number of these are reaching the end

of their useful life. The power station is to be extended with the addition of three new, 1.6MW

diesel generators. The oldest of the existing generators will be decommissioned first, with the

remaining following as appropriate.

As part of the upgrade a new SCADA system is required to provide better monitoring and control

of the generators and feeders as well as providing for the new PV generation rapidly being installed

on the network.

A new 960kWp solar array has recently been commissioned near the airport, feeding directly into

the 11kV distribution network, with further generation planned in the near future either by TAU or

by the private sector. There are also incentives for customers to install their own solar generation,

which is limited to 2kW per household.

The diagram below is a high-level view of the proposed SCADA system and its interfaces:

Page 77: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 7

Figure 1 - SCADA Overview Diagram

1.2 This Tender

THIS TENDER IS FOR THE FOLLOWING:

Stage One – Equipment supply, software configuration, FAT, Installation and Commissioning

Stage Two - (Separable Portion) - Equipment supply, software configuration, FAT, Installation

and Commissioning

Stage Three – Allowance for future capacity / supported upgrade path

The stages are described below:

Diesel UPS

System*

Voltage Control Resistors*

Local Diesel Generation**

Local Photovoltaic Generation**

Remote Photovoltaic Generation*

HV Switchgear**

Distribution Network*

Long Term Historian (PI or integrated) **

Operator Workstations (TAU

Office) **

* Future requirement ** Included in SCADA initial phase

Outer Islands

SCADA System

Expert System

Embedded Solar Generation

Operator Workstation (Power Station) **

Pumped

Storage Hydro*

Page 78: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 8

1.3 Stage One – Airport PV Integration and Power Station Existing Equipment Migration

The immediate aim is to provide a new SCADA system that will enable remote control and

monitoring of the new airport 960kWp PV installation, as well as existing equipment at the Power

Station.

The recently completed solar plant at the airport has a number of interfaces, such as the 11kV

switchgear, cluster controller, LV switchboard and an RTU. These will be monitored and the

output from the solar plant controlled via the new SCADA system.

The existing ComAP generator controllers and GE Multilin electrical protection relays will also be

connected to SCADA.

Once this stage is complete, it will allow remote monitoring and control of all of the 11kV power

generation on the island.

A historian will also be included in the initial phase, which will store power-system data for later

analysis and trending. Refer to drawing 214.035-E1000_01.

1.4 Stage Two – New Gensets

The three new 1.6MW generators controllers will interface with the SCADA system. New

protection relays and ancillary equipment associated with the new generators will be integrated into

the new SCADA system. Refer to drawing 214.035-E1001_01.

1.5 Stage Three – Future Plant and Sites

As the amount of solar generation increases, equipment such as a D-UPS system and network

voltage-control resistors will be installed on the network to provide voltage and frequency stability.

These will need to interface with the Expert System that will adjust set points automatically as

appropriate.

In the future equipment will be installed that measures voltage at distribution transformers. This

information is important, as there is a large amount of embedded solar generation being installed by

consumers on the low voltage network. The devices will communicate with SCADA via small-scale

radios or the cellular 2G/3G network. The Expert System will use this information to control load

to ensure the voltage is maintained within tolerance.

Ultimately, the SCADA system will need to be scalable to allow monitoring of generation installed

on the outer islands. The communications link will be via satellite communications or via a cellular

network. Refer to drawing 214.035-E1002_01 and 02.

Page 79: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 9

2 Technical Requirements

2.1 Hardware

The Contractor shall provide at least the following equipment. All hardware shall be designed for

continuous use in an industrial control centre environment.

2.1.1 SCADA Servers and Historian

Two SCADA servers shall be supplied, one for the Power Station and one for the TAU Main

Office. A separate long-term data server for installation in the TAU Main Office shall also be

supplied. Below is the minimum specification for the three servers:

High speed 32-bit or 64-bit central processing units with two or more cores (or two or more

processors) and with processor clock speed of at least 2.6GHz

Minimum of 8GB main RAM memory (expandable)

Hot swappable 300GB RAID 5 Hard Disk Drive array

DVD read/write drive

Minimum 2 x 10/100/1000 Ethernet LAN interfaces

Dual hot-swap power supplies and fans

At least four USB ports and one RS232 port

101 key AT-keyboard or equivalent keyboard

24” monitor

PC speaker

Tape back-up module for historian

The servers shall be currently available models at time of installation.

2.1.2 Operator Workstations

Two triple-screen operator workstations shall be provided. One shall be installed in the Power

Station and one installed in the TAU Main Office. An Engineering Workstation (single screen)

shall be installed in the Power Station. Below is the minimum workstation specification:

High speed Intel 32-bit or 64-bit central processing units with dual core (or dual processors)

and with processor clock speed of at least 2.6GHz

Minimum of 4GB main RAM memory (expandable)

High availability disk drive system (RAID 1)

DVD read/write drive

2 x 10/100/1000 Ethernet LAN interfaces

Page 80: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 10

101 key AT-type keyboard or equivalent keyboard

Suitable graphics card(s) and support for 3 x colour monitors

At least three USB ports

Audio output port and speakers

Minimum 24”, high resolution LCD monitors capable of a resolution of 1920 x 1200 pixels

The PCs shall be currently available models at time of installation.

2.1.3 Printers

One dedicated laser colour printer shall be supplied for each location (for graphics, event logging,

reports, etc.)

2.1.4 Network Equipment

The Power Station LAN shall be based on TCP/IP protocol transported over an Ethernet network.

Network components shall support 10/100/1000 Mbit/s Ethernet as appropriate. Network

interface hardware shall have sufficient processing capacity and bandwidth to cater for peak

throughput without affecting overall performance.

At plant level, the network equipment shall be of the industrial hardened type and be capable of

continuous operation under the site environmental conditions.

Managed Ethernet network components, such as the network switches in the power station shall

support SNMP. Suitable configuration software shall be supplied which will allow the user to easily

modify the configuration of the network devices.

All network equipment installed on site shall obtain power either from the DC battery system or

from the site UPS.

Devices shall be able to restart and initialise automatically according to the restart configuration.

Appropriate critical alarms from these devices provided via SNMP shall be accepted and reported

to the SCADA alarm system.

2.1.5 Device Servers

For serial devices to utilise the Ethernet network, device servers are required. These shall

incorporate the following:

4 x serial ports with terminal connections

1 x 100M Ethernet port

The device server shall contain a buffer to store serial data on loss of Ethernet connectivity. Once

Ethernet connectivity is restored, the buffered data will be sent. The buffer size shall be

expandable.

Page 81: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 11

2.1.6 Corporate Interface

A separate, stand-alone firewall shall be provided to separate the corporate network from the

SCADA network. The firewall shall be fully configurable and support the following features:

IEEE 802

Network Administration Control

IPSec Encryption

Intrusion Prevention Service

The network access policy shall be developed in conjunction with TAU IT representatives and the

firewall shall implement this policy.

2.1.7 Uninterruptable Power Supplies

The workstations and servers shall be powered from a UPS supply. A 2000W UPS shall be

supplied for both the Power Station control room and the TAU main office.

The UPS shall provide a minimum of four hours back-up time, and be supplied with monitoring

software which will enable an orderly shutdown of the attached servers and workstations once the

battery voltage reaches a pre-set level.

2.1.8 Racks

All equipment shall be installed in new 19” racks as follows:

Location Equipment

Ava

ilabl

e Po

wer

Su

pply

SCA

DA

Se

rver

/ H

isto

rian

Net

wor

k Sw

itch

Med

ia

Con

vert

er

SM P

atch

Pa

nel

TCI F

ibre

Tr

ay*

Pow

er

Dis

trib

utio

n

Fire

wal

l

STAGE 1

Airport Solar Array TBC ● ● ● ●

TAU Main Office New UPS ● ● ● ● ● ● ●

Existing Control Room 24VDC/ New UPS

● ● ●●● ● ● ●

Existing Generator Hall 24VDC ● ● ●

Switchroom 2 24VDC ● ● ●

Switchroom 1 (Moved to Switchroom 3 in future) 24VDC ● ● ●

STAGE 2

New Power Station Pad (Outdoor) 24VDC ● ● ●

Table 1 – Equipment and quantity to be installed in wall-mounted or outdoor cabinets

Page 82: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 12

* Free issued equipment

The wall mounted racks shall contain a lockable door and be sealed to ingress protection level IP21.

A standard design approach shall be followed for all the panels. The Contractor shall consult with

TAU to confirm the exact location of the new control panels and to check if there is any existing

rack space that can be used.

The new outdoor enclosure for the new generators shall be sealed to ingress protection level IP65.

2.1.9 Fibre Optics

A new fibre ring shall be created within the Power Station, including the new generator pad (in

Stage 2) and the two switchrooms. Within the main building, including the switchrooms, this shall

be using 50/125 µm FX multimode, factory terminated patch cables suitable for industrial

applications. In Stage 2, new armoured fibre-optic cables, with a minimum of 12 cores, shall be

installed between the existing Power Station and the new generator building. The connector-type

for all connections within the Power Station shall be SC, unless this option is not available from

third-party equipment providers.

2.1.9.1 TAU Scope of Work for Communication Link installation

TAU will ensure that a communication link exists between the TAU Main Office, Power Station

and the new PV plant at the airport as shown below:

Figure 2 - Proposed Communication Network

The connection will be provided at the power station site via a Contractor supplied, 12-way patch

panel. New single-mode to multi-mode media converters shall be provided and installed in the new

wall mounted cabinets as described in Table 1.

TAU Main Office

Communication Tower

Control Room

Manager’s Office New Fibre

Existing Fibre

Avatiu Valley Power Station

PV Plant Airport

Page 83: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 13

Page 84: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 14

2.2 Software

2.2.1 General Requirements

The software systems shall be based on industry-accepted generic standards, issued or endorsed by

independent international technical standards organisations or on de facto standards that have been

adopted by multiple clients and a large body of users. This requirement shall preclude single

vendor proprietary systems.

The systems supplied shall be based on modular hardware and software system components

ensuring:

Portability of software across diverse equipment platforms, ensuring hardware vendor

independence

Scalability of all system software to allow operation without structural alteration or

reconfiguration

Interoperability of hardware from different vendors on the same network as well as

compatibility of third party software packages on various hardware platforms

Flexibility to easily locate hardware and software units at the point where they can be most

effectively used and managed

Reliability through network redundancy and client-server operations

The key emphasis shall be to ensure that parts of the system can be upgraded without disturbing

the integrity of the remaining items. The system shall have both vertical and horizontal upgrade

paths with access to a wide range of third party software applications.

All source code, software tools and related documentation shall be handed over to TAU on

completion.

2.2.2 Communication Protocols

The SCADA system shall contain the following certified, open protocol drivers:

DNP3/IP Master certified to Level 3

MODBUS TCP/IP Master

EtherNet/IP (for Generator 7 PLC)

References of successful integration using the above protocols shall be provided with the Tender.

2.2.3 Data Types

The SCADA system shall operate as a Modbus Master for Power Station Data and a DNP3 Master

for interfaces to the new PV systems.

Modbus function codes supported shall include at least the following:

Page 85: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 15

Function Code Description

1 Read Coils

2 Read Discrete Inputs

5 Write Single Coil

4 Read Input Registers

3 Read Holding Registers

6 / 16 Write Single Register / Write Multiple Registers

Table 2 - Modbus Function Codes to be supported

DNP3 object codes supported shall include at least the following:

Object Number Variation Description

2 2 Binary Input With Time

10 1 Binary Output

12 1 Control Relay Output Block

20 5 32-bit Binary Counter Without flag

30 3 32 Bit Analogue Input Without Flag

30 4 16-bit Analogue Input Without flag

32 3 32 Bit Analogue Change Event with Time

40 1 32-bit Analogue Output Status

40 2 16-bit Analogue Output Status

41 1 32-bit Analogue Output Block

41 2 16-bit Analogue Output Block

Table 3 – DNP3 Object and Variation Numbers

For consistency, all scaling and inverting shall take place at the SCADA Master Station.

2.2.4 Tag Names

Alphanumeric tag names with a minimum length of 250 characters shall be supported.

Page 86: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 16

2.2.5 SCADA Server Operating System

The SCADA servers and long-term historian servers shall run either Microsoft Windows Server

2012 or later operating system, or a commercially supported Linux based operating system.

2.2.6 Operator Workstations

The SCADA workstations and shall run the Microsoft Windows 7 or later operating system.

2.2.7 SCADA Server Failover

The SCADA servers shall be capable of manual and automatic failover. One server (in the Power

Station) will be designated as the ‘main’ server. The server installed in the TAU Main Office shall

be designated as ‘standby’.

Both critical data on both server databases shall be closely synchronised allowing for a smooth

transition during failover. Synchronised data shall include at least the following:

Real-time database

Alarm status (acknowledged, active, inhibited, etc.)

Expert System parameters and status

Time stamping

Trends

Long term historian data (can be buffered)

Dedicated monitoring software shall be used to monitor the performance of both servers and

initiate a fail-over if an error is detected on the main server.

A failover between the two servers shall be completed in no more than 20 seconds. Once the

system has failed to the standby server in the TAU Main Office, the main server must not regain

control without manual operator confirmation. Manual changeover between servers for testing

purposes shall be possible.

Synchronisation issues and any differences in configuration between the two servers shall be

alarmed.

2.2.8 Expert System Programming Software

The programming language of the Expert System software shall comply with the IEC 61131-3

standard.

All real-time data, pre-set values and virtual points shall be available for processing by the Expert

System programming software.

The Vendor shall supply examples and template modules commonly used in similar industries.

Page 87: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 17

A method of closely simulating the programming logic shall be included as standard. This will

prevent untested software being released onto the live system. The simulator shall allow all

variables and parameters to be monitored and include the ability to step-through the logic for

debugging purposes.

The programming application shall use a check-in, checkout process for audit purposes and

tracking.

The Expert System (and any updates) software shall be downloadable onto the live operational

servers without the need for a system restart.

2.2.9 Response Time

The update time from a command sent to a remote device and the associated feedback being

received by SCADA shall be as follows:

Critical control (trip, CB operation) – 2 seconds or less

Analogue set-point update – 5 seconds or less

The response time shall be accurately simulated and measured during the FAT.

2.2.10 Diagnostic Software

Diagnostic software shall be provided to monitor the health of the server software and hardware.

Facilities shall be provided to gather on-line statistics at specified time intervals about server CPU

utilisation, CPU idle time, input/output waits, number of input/output transfers, number of CPU

pre-emptions and other useful information to enable system loading and performance to be

analysed.

Diagnostics should, as far as possible, present a logical and consistent interface to the user so that

they are as simple to operate as possible. Where possible they shall provide printouts of the test

performed and the results obtained.

2.2.11 Time Synchronisation

The new SCADA system shall act as an NTP client. There will be an existing NTP server

connected to the network at the Power Station. The existing NTP server at the Power Station shall

be the master time source for all the connected SCADA equipment.

Page 88: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 18

2.3 HMI Functionality

2.3.1 Overview

The Vendor's standard approach for the human machine interface (HMI) shall be followed, where

possible, to minimise customisation. Typing activities required to execute functions shall be

minimised.

The operator interface shall be via two functionally identical workstations. All functions shall be

capable of simultaneous utilisation on both workstations. Any display may be presented on any of

the workstation screens at any one time.

The operator shall monitor and control the Power Station electrical network using on-screen

buttons via a cursor-pointing device, keys on an alphanumeric keyboard and screen displays with

function activation points. The arrangement should ensure that there is a logical content on each

page, that there is logical navigation between pages, plant and functions, and that the graphics make

use of the appropriate features of the new system.

The Vendor shall provide a consistent interface, which maintains identical procedures from one

application to another. The new SCADA system HMI shall enable the following:

A modern ‘windows’ approach shall be provided for HMI with moveable, sizable and scrollable

windows

Support for at least six multiple simultaneous windows on one screen and at least eight multiple

simultaneous windows across two or more screens for the multi-screen workstations

Pan and zoom capability on maps, worldviews and single line diagrams, with automatic de-

clutter to hide or reveal detail depending on level of zoom

Switchable layers on maps, worldviews and single line diagrams

Drop down and pop-up context sensitive menus

Context sensitive tool bars, with buttons or icons, to access more commonly used functions

Pop-up tips that provide abbreviated help for a feature when the screen cursor hovers over the

button, icon or symbol

Active bus-bar display which will automatically determine whether a part of the network should

be live, based on circuit breaker status and voltage inputs

Drag and drop capability

Availability of many different fonts and letter styles

Manual ‘hand-dressed’ status points and objects

Configurable alarms. The alarms shall be able to be filtered, prioritised and inhibited.

Static and dynamic, context-related function keys

Display update frequency of no more than 100ms

Page 89: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 19

Fully keyboard and mouse operable

Operator inputs and database changes logged and checked for validity before updating

database. The operator shall be warned about invalid inputs.

2.3.2 Specific Display Requirements

2.3.2.1 System Status

The HMI shall show the following system status information in a corner on all screens:

Workstation operational mode

Server connection status (main / standby)

Logged in person and access level

Date / Time

The HMI shall include dedicated screens showing the following system status information:

A communications block diagram and real-time status of the communication system, including

the status of each link.

A control system display

2.3.2.2 Alarms

The SCADA system shall include a comprehensive alarm management system. Functionality shall

include at least the following:

Prioritisation – Each alarm shall be capable of being allocated a priority that will affect how it

is handled. For example, high priority alarms configured to appear at the top of the list.

Filtering – Each alarm shall be capable of being allocated a priority, area, type of plant and

other metadata that can be used for filtering purposes.

Multiple States and Colours – Active, active-and-acknowledged, cleared, cleared-and-

acknowledged, etc. states shall exist. Each state shall be capable of being allocated a different

appearance.

An audible alarm device shall be supplied which will indicate an alarm has been activated. The

audible alarm shall be configurable to distinguish between critical and non-critical alarms.

2.3.2.3 Function Keys

The HMI screens shall contain large function keys symbols representing the function keys on the

workstation keyboard. Special commands shall be assigned to each key, such as invoking

commonly viewed screens, initiating special functions, launching an application or execute a control

command.

Page 90: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 20

The functionality of the keys may be fixed, where the function is the same in all contexts or

dynamic, where the function of the key depends on which screen is being displayed at the time.

2.3.2.4 Overview HMI Screens

The overview HMI screens shall include at least the following:

Power Station 11kV Single Line Diagram

Airport PV Single Line Diagram

Real-time Network Power Flows

Generator Electrical Information – including capability diagram

Engine Mechanical Data

Other screen may require developing after consultation with TAU operational staff.

2.3.2.5 Dynamic Displays

Each dynamic data field shall be displayed with its respective database attributes. These attributes

shall be presented using colour changes, attached character tags, background/foreground colour

reversals, blinking or other techniques.

There shall be no restrictions to the presentation of any database information at any screen location

or any workstation display.

The HMI configuration shall allow for dynamic bus-bar displays. By linking voltage signals and

circuit breaker status inputs, the bus bars and other associated HV connections such as cables can

be shown as energised or de-energised. For example, if one bus bar has a live VT input, any

interconnecting bus bars will also be live, as long as the interconnecting circuit breaker is closed.

This feature is particularly useful for switching or during an outage.

Real-time power flows shall also be shown dynamically using directional arrows.

2.3.3 Miscellaneous HMI Functions

2.3.3.1 Virtual Post-it Notes

A window based text editor shall be provided to enter free format text messages that can be posted

on to any of the HMI screens. Text messages will be entered for operator instructions, entries to

display notepads, entries to event diaries or logbooks, work orders, etc.

2.3.3.2 Manual Database Points

A number of database points may not be telemetered and as such require manual activation. For

example a HV switch may be ‘normally-closed’ and only opened during maintenance. The HMI

shall allow for manual points, where the ‘normal’ status may be overridden, ensuring the HMI

reflects the network configuration accurately.

Page 91: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 21

Manual overriding of dynamic points shall be made possible in cases where the communications are

lost to a device. This may be prior to a planned communications outage or during a fault. The

manually set status shall reset once communications have been re-established.

2.3.3.3 Database Management and Editing

The standard database management system (DBMS) database editing facilities shall be provided.

Points shall be able to be updated and downloaded into the live database without the need for any

part of the system to be re-started. In addition, operator information displays shall be provided to

show all database point attributes.

Real-time raw data screens shall be provided, which in simple table format show the raw input

data(without scaling or inverting), for commissioning and testing purposes.

2.3.3.4 Translating and Scaling Raw Data

Analogue values and error codes will be received in raw (unscaled) format. The HMI configuration

software shall allow raw points to be easily scaled (and error codes translated) without the need for

customised script.

A calculations display shall be provided that lists all calculations associated with a data-point.

2.3.3.5 HMI Configuration Software

The Vendor shall provide software allowing the configuration of the HMI displays. This shall be

MS Windows based, intuitive, easy to use and flexible.

A standard library of common power system objects shall be included as well as the facility to

create customised objects. It shall include a feature where global changes can be applied. For

example, a change to an object should automatically follow through to all objects of that type.

It shall be easy to toggle between development mode and test mode. In test mode, the ‘live’

version of the screen under development shall be displayed. Manual forcing of database points

shall be enabled whilst in test mode which will show the effect on the HMI displays.

2.3.3.6 Access Levels

Workstation users shall be assigned to different levels of access, according to the functional

requirements of the users. The workstation levels shall restrict the users to specific functions only

of the control system. The limitations may be functional, operational or geographic.

Workstation mode shall generally be assigned to a user when they log on. It will be pre-assigned

for each possible user.

The levels shall include:

View-only shall provide view-only functionality

Page 92: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 22

Operator Mode shall provide those functions, alarms/events and presentation applicable to the

operation of the power station and the HV network. Set-points can be altered in this mode.

Supervisor Mode shall provide the operator mode functions as well as allowing this user to

configure operator settable parameters.

System Engineer/Programmer Mode allows access to all parts of the system including

Expert System control functions. Database and display maintenance, programming, application

module testing and system configuration changes shall be undertaken in this mode.

Remote Access Mode via the web browser client allows corporate TAU staff with the correct

authority, the capability of remotely accessing the graphic displays, events, alarms and other

system operational information. No supervisory control shall be allowed in this mode and

access shall be controlled by passwords.

Administrator Mode allows domain/system level administration privileges.

Engineering and maintenance access to the SCADA servers and historian shall be by administrators

only.

2.3.3.7 Login and Security

Users of the SCADA system shall be required to ‘login’ with a user name and password to perform

any functions on the system. The SCADA login shall be independent from any operating system

login. The present logged-in user (and level) shall be indicated on each HMI screen.

A hierarchical range of login roles shall be provided as defined above. The privileges for each level

shall be user configurable (by a user who has the access level to do this).

A separate unique password shall be provided for each user. When logging in to the system, each

user shall be given access privileges at a level set for the particular user.

A record of login and log-off activity shall be recorded. The access security logging in system shall

also apply to the back-up operator workstation and the engineering workstation.

2.3.3.8 Web Viewer

The SCADA system shall incorporate a web server that allows clients on the TAU corporate LAN

with suitable authority to view some or all operational SCADA pages. The Web Viewer interface

shall require a login authority. Corporate access to the SCADA system shall be via a new firewall.

2.3.3.9 Historian

The historian shall be capable of storing up to five years’ worth of data. The database shall be SQL

based allowing easy interrogation using standard database analysis software. The Vendor shall

provide appropriate analysis software, either proprietary or from a proven third party.

Accepting data from other TAU systems shall be possible via a standard OPC interface.

Page 93: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 23

Reports generated on the historian shall be exportable to standard Microsoft applications such as

Word and Excel. A web viewer shall be included to allow corporate staff to view a number

standard reports from the most up-to-date historian data. Typically, this may be the total amount

of PV output over a period, or the number of times a particular event has occurred.

The historian shall allow TAU IT staff to easily archive and back-up data using tape drives. Ideally,

this shall be completed automatically on a daily basis.

2.4 Scalability

The SCADA system shall be scalable (either initially or via a planned upgrade path) to allow for

future addition of the following functionality:

Network voltage control equipment (Diesel UPS or voltage reduction resistors).

Monitoring of the embedded photovoltaic generation at distribution transformer.

New primary plant (additional switchgear, diesel generation, solar farms).

Pumped storage hydro.

When required remote island monitoring of diesel and photovoltaic generation.

The Vendor shall provide the most cost effective upgrade path, such as only offering the licences

for the present requirements, with the option of upgraded later.

Page 94: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 24

3 Electrical General Requirements

3.1 Language and Units

3.1.1 Language

The English language shall be used on all drawings and in all documents and wherever anything is

required by the Contract, to be written, marked, printed or engraved.

3.1.2 Units of Measurement

Wherever practicable, Systeme International d’Unites (SI) units shall be used.

3.2 Manuals

3.2.1 General

The Contractor shall provide the following manuals:

Safety Manual

Quality Assurance Manual

Operation and Maintenance Manuals

3.2.2 Quality Assurance Manual

The Contractor shall operate and maintain a quality management system conforming to AS/NZS

ISO 9001 or approved equivalent. The Contractor shall take and keep records of quality inspections

and tests as evidence that the requirements of the Contract have been met.

The Quality Assurance Manual shall include but not be limited to the following:

a) Project management and organisation chart

b) Design plan

c) Quality plan

d) Qualifications and experience of key personnel

e) Sub-contractor quality assurance plans

f) Inspection and test plans

g) Statutory certificates

h) Reports on non-conforming work and corrective action

i) Results of all inspections and tests undertaken prior to delivery.

During the course of the Contract the Contractor shall register and maintain all quality

documentation in an up-to-date centralised file and make this available for inspection by the

Principal or its representative at all reasonable times.

Page 95: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 25

The Contractor shall complete Field Installation Checklists as certification that installation activities

have been completed in accordance with the appropriate specification. Field Installation Checklists

shall be prepared by the Contractor and forwarded to the Principal on a progressive basis. All Field

Installation Checklists shall be completed by the Contractor as a pre-commissioning activity.

3.2.3 Operating and Maintenance Manuals

The Contractor shall provide Operating and Maintenance Manuals for all equipment supplied

under this Contract (i.e. servers, HMI configuration software, etc.). The information required from

the Contractor shall conform to the Principle’s standard requirements detailed below:

General

The format of the Operating and Maintenance Manuals shall be provided in electronic and paper

format and comprise instructions, diagrams and drawings which shall be sufficiently comprehensive

to facilitate the training of the staff and to enable the operation and maintenance of the equipment

to be performed in a safe and efficient manner.

The Contractor shall supply a comprehensive operation and maintenance instruction manuals for

the equipment supplied, written in the English language, as part of the contract. Four hard copies

and one compiled PDF copy on CD/DVD shall be supplied. They shall contain full

documentation of the Goods and shall be in a form agreed prior to binding. If not readily

identifiable from the drawings the necessary ordering details shall be listed in the manual.

Format

The format of manuals shall contain the following as a minimum requirement:-

Stationery: The Operations and Maintenance manuals shall be produced on good quality A4

size paper and placed in a suitable A4 – 4-hole ring-binder.

Index: An index which conveniently and logically sets out the format of the Operating and

Maintenance Manuals. Part of this index shall be a contents tick sheet. This format is a

minimum requirement. All items shall be listed regardless of actual document contents. Items

included are to have a tick in the appropriate box.

Installation: A general description of the installation in regard to location and function. The

description should include all process parameters associated with the installation and should be

supported by general arrangement drawings.

Operation: Operating instructions are required for all items of equipment and shall contain

the operating procedures of the systems, in addition to the emergency and abnormal conditions

procedures.

Procedures: The operating procedures shall be set out in step-by-step instructions with each

step numbered in correct logical sequence and include:-

Page 96: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 26

o Login procedures

o Restarting servers, workstations and sub-systems

o Switching between main and standby servers

o Report generation

o In service checks and limits including routine test procedures.

o Adding a new I/O point to the system

Design: A design and technical section which shall include:-

o Detailed descriptions of equipment components and systems including detailed

drawings where available

o Technical data for all plant as installed.

o Test and performance data.

o Schematic and logic diagrams

o A list of alarms detailing alarm initiator location and setting for alarm operation

and re-set.

Trouble Shooting: A trouble shooting process based on symptoms and including suggested

frequency of inspection of components and frequency of routine maintenance. The programme

shall include details of the points at which measurements should be taken, details of the normal

readings at those points and the possible reasons for abnormal readings.

Site Test Appendix: Manuals shall include an Appendix for insertion of site commissioning

and acceptance test results.

Software: All software associated with the project shall be included in CD/DVD format as

part of the Operation and Maintenance Manual (included in a CD wallet with the hard copy).

3.3 Drawings and Documentation

The Contractor shall produce at least the following:

Standards Manual

Panel layout drawings

Connection diagrams

Schematics

Patching tables

Points list showing available points and recommended points

Detailed SCADA overview showing device addresses, channels, protocols, etc.

Drawings and documentation shall be submitted to the Principle for review and approval.

Page 97: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 27

3.4 Design Approvals and Information

3.4.1 Approvals

“Drawings” mean drawings, manuals, reports, calculations, documents schedules, lists,

programmes, data, quantities and other listed below for the Works.

All approvals by the Principal shall be limited to procedural approval only. Approval of drawings,

samples, prototypes, workmanship methods, and other matters whatsoever pursuant to the

Contract or in respect of the Works shall not be deemed to be waived or prejudicially affect any

right of the Principal or diminish in any way the Contractor’s responsibilities, or widen the

incidence of responsibility in respect of the work or Contract in any way or to derogate from or

affect any other requirements.

If permits are issued subject to conditions affecting the Works, the Contractor shall refer such

conditions to the Principal to enable consultation with the Authorities regarding such conditions.

No such conditions shall become a Variation unless confirmed in writing by the Principal.

The Contractor shall submit to the Principal by e-mail for approval HMI screens, drawings,

calculations, schedules, programmes, details, lists and other documents as required.

After examination, the Principal will return one copy of the Drawing to the Contractor within two

weeks of receipt. The return copy will be marked as:

Approved

Approved as Noted

Returned for Amendment

The notations “Approved” and “Approved as Noted”, shall mean that the Principal has satisfied

himself as to the general compliance of the Drawing with the requirements of the Contract and

does not have any further comment, but such approval, with or without notes, shall not relieve the

Contractor of any of his obligations under the terms of the Contract. Any work undertaken before

the receipt of the relevant approval shall be at the Contractors risk and any changes necessary to

comply with the Contract shall be made at no additional cost to the Principal or delay to the

Contract Key Dates. If the Drawing is returned marked “Returned for Amendment”, the

Contractor shall amend the Drawing and submit the revision within two weeks of receipt.

If urgent approval of any Drawing is required, the Contractor shall so notify the Principal when

submitting the Drawing.

3.5 Workmanship and Materials

Workmanship shall be of first class commercial quality and in accordance with the best shop

practice.

Page 98: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 28

Unless otherwise specified, materials and components used for the Works specified shall be new

and unused. Materials and components shall conform to the standards current at the time of

execution of the Agreement.

3.6 Preferred Equipment

The table below shows the preferred equipment for the project:

Equipment Preferred Supplier

Network Equipment MOXA / Hirchmann

Control Panels / Junction Boxes Rittal

Fuse Terminals / Terminals Weidmuller

Fibre patch panels Dynamix

Table 4 - Preferred Equipment List

Any deviation from the preferred equipment shall be agreed with TAU prior to ordering.

3.7 Packing and Shipping

3.7.1 Packing

All equipment supplied by the Contractor shall be adequately packed and protected for shipment.

The Contractor shall ensure that the equipment shall be protected against corrosion, weather

damage, condensation, distortion or damage by vermin and the ingress of foreign matter.

Packing of any equipment shall comply with the approved shipping preparation and packing

procedures and shall include but not be limited to the following:

Equipment shall be properly packed

Equipment shall be shipped in weather proof and watertight containers unless otherwise agreed

with the Principal

Containers, crates or packages shall be checked for defects internally and externally prior to

packing

Weights and lifting points shall be clearly visible on each package

Equipment shall be not wrapped in plastic unless it is coupled with adequate moisture

absorbent material, such as silica gel

For any imported components, packing material shall comply with import and export regulations.

All wood packing in each consignment shall be free from bark and all visible signs of insect and

fungal attack at the time of shipment. Furthermore, the importation of packing materials such as

second-hand sacking, hays, straw, chaff, rice husks and peat shall be prohibited. The Contractor

shall be responsible for obtaining approval of the packing timber and materials before Delivery.

Page 99: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 29

Invoices and packing lists shall state the type of packing used and certify that none of the

prohibited material has been included.

The Principal may require to inspect and approve the packing before the items are dispatched but

the Contractor shall be entirely responsible for ensuring the packing is suitable for transit and such

inspection shall not exonerate the Contractor from any loss or damage to faulty packing.

3.7.2 Unloading and Storage at Site

The Contractor shall at Site place the Works in the Contractor’s storage area in the following

manner:

Place any containers or any packages in locations as directed by the Principal.

Certify that the contents of any container or any package agree with the said packing lists.

Remove from site any unwanted packing debris and any empty containers immediately after

completion of unloading at Site.

3.7.3 Hazardous Areas

No sections of the installation are within hazardous areas or require hazardous equipment ratings.

3.8 Electrical Works

3.8.1 General

This section covers the general requirements for all electrical works to be provided by the

Contractor and shall be read in conjunction with the Schedules and Drawings.

3.8.2 Site Induction Requirements

The Contractor shall be required to comply with all of the site requirements including compliance

to all isolation, induction, site safety, first aid and emergency procedures. The Contractor shall

ensure that all site personnel have all of the requisite certification for site.

3.8.3 General Technical Requirements

The design and installation of the electrical works shall comply with the following standards and

specifications:

The latest requirements of AS / New Zealand Standard AS/NZS 3000:2007, Electrical

Installations, known as the Australia / New Zealand Wiring Rules

3.8.4 Local Environment

The following service conditions apply:

Site elevation is less than 100m above sea level

Ambient temperature range +15°C to +45°C

Page 100: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 30

100% humidity can occur

The dust / air ratio will be less than 200mg/m³

Air is salt laden with high potential for corrosion

Wind loading – cyclone conditions can occur (up to 350km/h)

Seismic – earthquake risk minimal but needs to be taken into account

The Contractor shall only supply materials and fittings that are suitable for the local environment

and ambient conditions.

3.8.5 Available Utilities

The following utilities are available on site;

Electricity 415 / 240 V AC, 50 Hz, 3 phase, 1 phase

Station 24Vdc supply for control systems and protection

Compressed air at 100 psi

Water – creek and rain water

3.9 Equipment

3.9.1 PLC / Control Cubicles

All PLC / Control cubicles shall be manufactured from standard cubicle designs (Rittal or similar)

complete with:

316 Grade Stainless Steel construction for outdoor cubicles

Original supplier’s surface finish

IP21 rating minimum for all indoor floor mounted cubicles

IP21 rating minimum for indoor all wall mounted cubicles

IP56 rating minimum for all outdoor floor mounted cubicles

IP56 rating minimum for outdoor all wall mounted cubicles

All equipment to be mounted on a removable painted gear plate

Full width two piece undrilled aluminium gland plate

Plinth for floor mounted cubicles

Strengthened back-plate or superstructure for wall mounted units

Three point securing location lockable doors with lockable operating handles

Door operated fluorescent light (All panels)

Heater and thermostat (one per PLC)

Page 101: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 31

Earth bar and copper earth straps to all doors

External panel label (traffolyte or similar)

All equipment labelled with schematic item designation (traffolyte or similar)

All internal wiring copper

Internal wiring secured in slotted cable PVC trunking

3.9.2 Equipment Labels

Control panels, junction boxes, and equipment within panels shall be labelled with a non-

ambiguous name, code, or tag numbered as appropriate, and as used in the drawings prepared by

the Contractor. Panels shall be clearly labelled front and rear. The English language shall be used

throughout.

Equipment labels shall be engraved with black lettering on a white background on UV stabilised

acrylic or similar material. Labels shall be fixed by small screws or studs. Self- adhesive labels shall

not be used.

Unless otherwise specified, letter height shall typically be;

Instrumentation, Miscellaneous items - 3 mm

Main titles, for tag number and service description - 6 mm

Control Panel, Junction Boxes, Main Equipment nameplate designation - 10 mm

Naming shall be confirmed with the Principal before manufacture.

3.9.3 Cables - General

All cables shall be copper.

4 Work Methodology

The scope includes hardware and software supply, engineering and software development, site

installation and commissioning.

The flowchart below shows the work methodology for the project:

Page 102: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 32

Figure 3 - Work Methodology Flowchart

After contract award the Vendor, or nominated system-integration subcontractor, shall produce a

number of demonstration screens to facilitate the development of a Standards Manual. The

demonstration screens shall show the proposed screen navigation, standard symbol libraries and

any special Vendor-specific features. An example of all the items in Section 2.3 HMI Functionality

shall be included in the demonstration to the Principal’s representatives. This demonstration and

subsequent discussions will take place in Rarotonga.

After input from the Principal, the Vendor shall commence development of the new SCADA

system, including the development of the Standards Manual.

Contract Award

Develop Demonstration Screens:

Navigation Common symbols Special features Typical HMI screens (note

1)

Accept

Produce Standards Manual

Develop I/O List and Database

Final Screens Linked to

Database Points

Demonstrate to TAU

FAT and training

SAT

Expert System Functional Description (Timing TBC)

Handover and Training

End Rarotonga Location

Yes

Yes

Yes

No

No

No

Note 1: Generator Overview SLD Protection PV

Page 103: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 33

4.1 SCADA Standards Manual

The Vendor shall development a standards manual in conjunction with the Principal. Shortly after

Contract Award, the Vendor shall create a number of HMI screens for demonstration to TAU staff

in Rarotonga. The demonstration screens shall be based as close as possible to the Vendor’s

standard product and include at least the following:

Proposed navigation of screens (overview screen, generator screens, alarms)

Standard power system / generation symbols library

Any special features that may be particularly useful to TAU operators

Examples of similar systems already in operation

Once the Principal has provided comment from the demonstration, the Vendor shall produce a

Standards Manual specific to TAU requirements. The Standards Manual shall define the following:

Screen navigation and hierarchy (single-line overviews, generator capability screens, alarms

screens, default trends, diagnostics, monitoring, raw data screens etc.)

HMI screen graphics (colours, multi-state indicators, faceplates, symbols)

Alarms (Number of priorities, colours, alarm states, tagging standard, etc.)

Tag naming convention to ensure consistency

Fonts and sizes to be used for various applications

Security access levels, including definitions of the specific privileges at each level

The Modbus, DNP3 and EtherNet/IP points lists

To avoid a large amount of customisation, the Vendor's standard libraries, objects and screens shall

be used where possible.

The Standards Manual shall be the reference document for all configuration and programming of

the SCADA system as well as future additions and upgrades.

4.2 Software Development

The Vendor, or its nominated system-integration subcontractor, shall be responsible for developing

the software of the TAU SCADA system. This shall be under the supervision of the Principal. All

source code, installation disks, documentation and configuration files shall be given over to TAU at

handover.

4.3 SCADA System Configuration

SCADA system configuration shall include producing the following based on the approved

Standards Manual:

Page 104: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 34

HMI screens including overviews, symbols, pop-up screens, function buttons and any special

features requested by TAU during the initial demonstration

Alarm screens

Default trend screens

User accounts

Linking symbols to database points

Translation /scaling of raw data received from remote devices

Installation of software on final, TAU owned, hardware

Configuration of network equipment

Packaging and shipping to Rarotonga

Screen dumps of all screens shall be issued to the Principal for comment and approval.

4.4 Points Database

Producing the points-database shall include the following work:

Creating the points database, including translation / scaling of points

Setting up and configuring the main and standby SCADA servers, including the operating

system

Setting up and configuring the Historian server including the operating system and analysis

software

Point-to-point testing of database points through to workstation HMI screens prior to formal

FAT

4.5 Expert System Software Development

The Expert System software shall be developed once the exact requirements are understood and

the Functional Descriptions made available. This will most likely be after the PV plant system has

been connected to SCADA. The Vendor shall allow a PC Sum in the pricing schedule for

programming, testing and commissioning the Expert System software.

5 Installation

The Contractor shall be responsible for the installation of the new equipment on site. The

Contractor shall use local sub-contractors as a priority unless it is more cost effective to use

overseas contactors. The following work shall be undertaken by the Contractor.

Page 105: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 35

5.1 Installation of Wall Mounted Cubicles

All wall-mounted panels shall be securely fastened to walls in the location shown in the drawings by

the use of tapped holding down bolts, chemically held concrete inserts, Unistrut fasteners, rawl

plugs or the like. No fibre compression plugs shall be used.

Wall mounted cabinets are required in the following locations, however the Contractor shall consult

with TAU to determine whether suitable space is available in existing racks.

Power Station Control Room (Stage 1)

TAU Main Office(Stage 1)

Airport PV substation(Stage 1)

Power Station Generator hall (Stage 1)

Switchroom 1 (Stage 1)

Switchroom 2 (Stage 1)

New Power Station building (Stage 2)

Where panels are to be mounted to unfinished concrete or block walls, Unistrut or similar rails shall

be provided and installed to provide an air gap between the panels and the walls.

5.2 UPS

One new UPS shall be installed in the Power Station Control room and a second new UPS installed

in the TAU Main Office. The UPS may be a floor-mounted unit, or rack mounted. The

Contractor shall confirm space availability and preference with TAU prior to ordering and

installing.

5.3 SCADA Servers and Historian

The new SCADA servers and historian shall be installed in 19” racks in the Power Station control

room and the TAU Main Office. The contractor shall confirm the exact location with TAU prior

to installation.

5.4 Workstations

The workstations shall be installed on the appropriate operation desks in the Power Station control

room and TAU Main Office. The contractor shall confirm the exact location with TAU prior to

installation.

The Engineering Workstation shall be install on a separate desk in the Power Station control room

to separate it from live operations.

Page 106: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 36

5.5 Firewall

The firewall shall be installed in a 19” rack in the TAU Main Office. The contractor shall confirm

the exact location with TAU prior to installation.

6 Testing and Commissioning

The Vendor shall provide the following testing:

6.1 Factory Testing

Functional tests shall be performed on each sub-system to prove that it operates is in accordance

with this specification.

Communications sub-systems shall be assembled as far as possible so their function can be tested.

Tests shall be performed on all fibres of a representative length of each type of fibre optic cable

used. In addition, the communications equipment shall be integrated and interconnected as far as

possible in the factory and tested as a full system or sub-system under simulated conditions that as

closely as possible represent final installation.

Tests may be witnessed by the TAU at their discretion. The equipment shall only dispatched once

written test results have been approved by TAU engineers.

The FAT will also provide a suitable opportunity for Operator Training. The Contractor shall liaise

with TAU representatives to facilitate such training.

6.2 Site Commissioning Tests

6.2.1 Setup and Pre-commissioning

The Contractor shall be present on site for pre-commissioning works including, powering up and

checking equipment, establishing communications and testing and some initial point-to-point

checks. Further commissioning may be undertaken by MECL.

6.2.2 Site Commissioning

Prior to handover, the Vendor shall carry out Tests on Completion. The tests shall be carried out

in the presence and to the satisfaction of the Principal. The Tests on Completion shall verify the

correct functioning of individual parts of the Works and of systems involving more than one item

of equipment.

The tests shall include tests for correct functionality and operating characteristics plus other tests as

may be directed by the Principal.

If any portion of the Works fails to pass the Tests on Completion then tests on that portion shall, if

required by Principal, be repeated within a reasonable time upon the same terms and conditions.

Page 107: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 37

All costs and losses incurred by Principal in consequence of such failure and/or by such repetition

shall be borne by the Vendor.

6.3 Handover - Stage One

As there are separable portions to this project, formal handover of the new SCADA system to

Principal shall be completed at the end of Stage 1. This shall be when all PV SCADA and Existing

Power Station Equipment points have been ‘point-to-point’ tested and signed by the Principal.

Point-to-point testing shall include both workstations, the historian and the web-server.

A Practical Completion Certificate shall be issued by the Principal. This may include a list of minor

defects that shall be completed within the defined timeframe on the certificate.

The Contractor shall provide the following at handover:

As-built drawings (red marked up drawings are acceptable)

All source code and related documentation shall be handed over to the Principal on

completion.

Operation and Maintenance Handbook

Application software installation disks (operating system, HMI configuration, database setup

and maintenance, etc.)

6.4 Handover – Stage 2

The exact timing of Stage 2 is still to be confirmed. Handover of this stage will be handled with a

separate Certificate of Practical Completion.

6.5 Handover Subsequent Stages

Handover of subsequent stages will be via separate Certificates of Practical Completion.

7 Training

The Vendor shall be responsible for the training of engineers and technicians to understand,

manage, operate, test and repair the SCADA system. The course content will differ depending on

the category of the trainee. Operator Training may be undertaken during acceptance testing.

Topics covered shall include:

Configuration and connection of equipment

Operation of plant equipment using the SCADA system

Fault finding techniques and equipment maintenance

Page 108: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 38

The Vendor shall provide course material, equipment and trainers to train the Principal’s personnel.

Such training shall consist in formal training in operation, hardware, equipment and software

maintenance.

Training shall be provided in the Vendor's country during equipment assembly and factory testing

and on site during commissioning activities. When training is conducted outside Rarotonga, the

Vendor shall be responsible for all costs (including communications, documentation, office

facilities, etc.), organisation and running of the training.

Annual refresher training shall be included as an option.

8 Support

8.1 On Site Support

The Vendor shall offer on-site support for the first six months after handover. The Vendor shall

allow for a fixed number of on-site support visits in the offer.

8.2 Remote Support

The Vendor shall also provide remote support (with appropriate cyber security) using remote

desktop software allowing minor fixes to be applied to the server operating system, SCADA

software or historian. Any updates must be applied under the supervision of the Principal’s

engineers.

8.3 Software

All source code, installation disks, operating systems, configuration files and related documentation

shall be handed over to the Principal on completion of the project. This shall include any special

cables required for configuring or diagnostics.

8.4 Drawings and Documents

All drawings, manuals and documentation related to the project shall be given to the Principal on

completion. AutoCAD files shall be included as part of the documentation.

Page 109: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

TAU Power House New SCADA System Project

Page 39

9 Exclusions

The following exclusions apply:

Installation of single-mode fibres between sites. This will be by others.

Page 110: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this

Tender Documents – TAU Power House New SCADA System Project

Page 36

ATTACHMENT 7: Drawings

Drawings

7.0 Power Station SLD

24.006-E0001 sheet 01 11kV Single Line Diagram

7.1 SCADA Architecture Drawings

214.035-E1000-01 - Control System Overview – Stage 1 214.035-E1001-01 - Control System Overview – Stage 2 214.035-E1002-01 - Control System Overview – Stage 3 214.035-E1002-02 - Control System Overview – Stage 3

Page 111: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this
Page 112: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this
Page 113: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this
Page 114: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this
Page 115: REQUEST FOR PROPOSAL For: TAU Power House New SCADA …procurement.gov.ck/wp-content/.../Request-for-Proposal-TAU...Projec… · To initiate progress towards the completion of this