report formats

Upload: anonymous-cikyr0t

Post on 03-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Report Formats

    1/15

    Sl.

    1

    1.1

    1.2

    1.3

    1.4

    2

    2.1

    2.2

    2.3

    3

    3.1

    3.2

    4

    4.1

    4.2

    RE

    FEEDB

    DailyPr

    Weekly

    Monthl

    Minute

    PROCE

    Change

    Materi

    PourCa

    QUALIT

    Non

    Co

    SiteDir

    OTHER

    Tender

    Acciden

    YESKAY

    PORT FO

    CKREPORT

    ogressRep

    ProgressRe

    ProgressR

    of

    the

    Me

    S

    /

    PROCED

    Order

    lApproval

    rd

    Y

    REPORTS

    pliance

    Re

    ctives

    REPORTS

    Comparison

    tReport

    ROMAG

    MATS / T

    TAB

    Rep

    S

    rt(DPR)

    port(WPR)

    eport(MPR

    ting

    (MOM

    URE

    NOTES

    equest

    port

    (NCR)

    Sheet

    ONSULT

    EMPLAT

    E

    OF

    CONT

    rt

    Format

    )

    NCY PV

    S FOR A

    NTS

    . LTD., C

    HO, COI

    ENNAI

    BATOR

    Pag

    2

    3

    4

    8

    9

    1

    1

    1

    1

    1

    1

    e#

    7

  • 8/11/2019 Report Formats

    2/15

    Name of Work:

    Employer:

    LOI No.:

    Contractor:

    SITE

    Slushy Dry

    No.

    No.

    Bags

    Nos

    Remarks for the day: Prepared by: Approved By

    MS Casing Pipe

    IMP.EVENTS/VISITS

    Constraints&Inputsrequired

    LABOUR&MATERIAL

    MAN POWER M A T E R I A L

    DESCRIPTION PLANNED ACTUAL DESCRIPTION UNITRECEIPTS CONSUMPTION

    FOR DAY TILL DATE FOR DAY TILL DATE

    Operator Cement

    Helper

    Drilling

    PL. NEXT DAY CUMM. TILL DATE % COMPPLANNED ACHIEVED

    Piling

    To:

    Site Conditions:

    WORK

    PROGRESS

    ACTIVITY DESCRIPTION LOCATION UNIT TOTAL QTY.FOR THE DAY

    Grouting

    REMARKS

    YESKAY PROMAG CONSULTANCY PVT. LTD.DAILY PROGRESS REPORT

    REPORT DATE

    P

    ROJECT

    Project

    Start Date

    Project Completion

    Dur. in Days: Total Elapsed Balance -

    Normal Day Rainy

    From:

  • 8/11/2019 Report Formats

    3/15

    Project

    Client:

    Contractual Dates

    Contract Duration Total Weeks - Elapsed Weeks - Balance weeks- Delay -

    Major Activities:

    Activitites Planned Next Week

    Inputs Required / Constraints/ Remarks:

    IMPORTANT CRITICAL BEYOND RECOVERY

    TIME STATUS

    Total Duration = Weeks

    Completed Duration = Weeks

    Balance Duration = Weeks

    Remarks

    Commencement - Completion -

    WEEKLY REPORT

    REPORT DATE

    YESKAY PROMAG CONSULTANCY PVT. LTD.

    Prepared by:

  • 8/11/2019 Report Formats

    4/15

    PMC: M/s. YESKAY PROMAG CONSULTANCY PVT LTD.

    MONTHLY REPORT

    for the month of _______

  • 8/11/2019 Report Formats

    5/15

    Project

    Client:

    Contractor : Shore Piling Work

    Contract for Pile work

    Contract Duration Total Weeks - Elapsed Weeks - Balance weeks - Delay -

    Major Activ ities during th e Month:

    Cumulative Activities upto end of the Month

    Ac tiv iti tes Planned for Next Month/ ( Balan ce work)

    Inputs Required / Constraints:

    IMPORTANT

    CRITICAL

    BEYOND RECOVERY

    TIME STATUS FINANCIAL STATUS

    Total Duration = WeeksCompleted Duration = Weeks

    Balance Duration = Weeks

    Remarks Prepared by:

    REPORT DATE

    Commencement - Completion -

    YESKAY PROMAG

    CONSULTANCY PVT LTD

    Monthly Report Front Sheet

    Sheet 1 of 3

  • 8/11/2019 Report Formats

    6/15

    Sheet 2 of 3

    As per

    BOQRevised

    Up to last

    month

    This

    monthCumulative

    Remarks:

    Prepared by: Approved by

    STATUS OF LABOUR RESOURCE

    Remarks

    Achieved

    Activity

    STATUS SHEET

    REPORT DATE

    STATUS OF MAJOR ACTIVITIES

    Expected Date

    YESKAY PROMAG

    CONSULTANCY PVT LTD

    %ge Achieved

    Expected Date

    LABOUR

    Sl.

    No.

    Unit

    Short

    fall

    Total Nos

    Sl.

    No.

    Short

    fall

    STATUS OF MATERIALS / EQUIPMENTS

    Sl.

    No.

    MATERIAL /

    EQUIPMENTUnit Planned Available

    Available

    (Avg)Planned

    Remarks

  • 8/11/2019 Report Formats

    7/15

    Sl.

    No.PACKAGES

    Tender

    Release

    Tender

    ReceiptBid Review Negotiation Issue LOI

    Sl.

    No.BILL DETAILS Bill Submitted Bill Certified

    Submitted to

    Client

    Amount

    Certified

    Due date of

    Payment

    Comments:

    Prepared by: Approved By

    TE

    REPO

    TENDER EVENT SCHEDULE

    YESKAY PROMAG CONSULTANCY PVT LTD

    PAYMENT TRACKER

  • 8/11/2019 Report Formats

    8/15

    REPORT DATE

    SI.NO ATTENDEES DESIGNATION

    Sl No DESCRIPTION AUTHOR ACTION BY

    ISSUES DISCUSSED IN PREVIOUS MEETINGS AND STILL PENDING

    YESKAY PROMAG CONSULTANCY PVT LTD

    COMPA

    ISSUES DISCUSSED IN PREVIOUS MEETINGS AND CLOSED. WILL BE DELETED IN TH

  • 8/11/2019 Report Formats

    9/15

    Name of Work:

    Employer:

    LOI No.:

    Contractor:

    Sl No.

    Original Contract

    Net change by previously authorized change order

    Contract sum prior to this Change Order

    Contract Sum increased or decreased by this change order

    Revised contract sum including this Change Order

    Net Change (All inclusive)

    Description

    Amount (Rs .)Overall Cost Implication

    Amount i n Rs .

    Signature

    Date

    REMARKS

    PMC Engineer

    Safety

    Engineer

    DISCLAIMER

    Signature

    Date

    Contractor:

    1.

    Signature

    Date

    The contract is changed as shown below. It is further understood and agreed that this adjustment constitutes compensation in full for all costs

    attributable to this change and / or for all delays, if any, related thereto and for performance of this change order within the contract period. All other

    terms and conditions of the Contract Documents shall remain in effect and this does not constitute a waiver of the requirements thereof.

    YESKAY PROMAG CONSULTANCY PVT LTDCHANGE ORDER

    REPORT DATE

    PROJECT

    Project

    Start Date

    Project Completion

    SUMMARY

    Signature by the Contractor confirms the Contractor's agreement with the commercial terms to the Contract amount set in the Change Order

    OVERALL

    Developer

    Site Engineer

  • 8/11/2019 Report Formats

    10/15

    Name of Work:

    Employer:

    LOI No.:

    Contractor:

    Variation from Specification

    Signature

    Signature:

    Project Manager

    YESKAY PROMAG CONSULTANCY PVT LTDMATERIAL APPROVAL REQUEST

    REPORT DATE

    Project

    Start Date

    Signature

    Date

    REMARKS

    AEC Promag Eng ineer

    Signature

    Date

    Consultant

    Signature

    Date

    Product Manufacturer

    Country of Origin Supplier

    PROJECT

    Item

    Project Completion

    MAR No. Rev:

    Specification Clause B.Q. Drawing

    SUMMARY

    COMMENTS

    Comments:Status

    A - Approved

    B - Approved as noted

    C - Not Approved - Resubmit as no ted

    Date of Submission

    Signed by:

    Approval Requ ired by

    Contractor

    Space Description

  • 8/11/2019 Report Formats

    11/15

    Name of Work:

    Employer:

    LOI No.:

    Contractor:

    FORMWORK

    DETAILS

    Plumbing

    Cover

    Final Clean

    Services (To be signed off by services contractors)

    Mechanical Electrical

    YESKAY PROMAG CONSULTANCY PVT LTDPOUR CARD

    REPORT DATE

    PROJECT

    Project

    Start Date

    Project Completion

    Type/Cleaned/Oiled

    False Work

    Key/W-bar/Joints

    Line/Level

    Joints/Security

    Blackouts/Fixings

    Pre- Concreting Pour Height

    Placing Arrangement

    Reinforcement Spacing

    Type/Size/Clean Fixing/Chairs

    AEC Promag Engineer

    During Concreting

    Contractor'sEngineer

    Contractor'sProject Manager

    Concrete Temp Ambient Temp Slump

    COMMENTS

    Post Concreting Clean up Cubes

    CubesCompactionAlignmentCuringLevel

    Curing Making good Stripping

    Contractor's Engineer Contractor's Project Manager AEC Promag's Project Manager

  • 8/11/2019 Report Formats

    12/15

    Name of Work:

    Employer:

    LOI No.:

    Contractor:

    Work re-checked and in compliance

    Signature

    DETAILS

    Issued by:

    Signature

    Type of Work:

    YESKAY PROMAG CONSULTANCY PVT LTDNON COMPLIANCE REPORT

    REPORT DATE

    PROJE

    CT

    Project

    Start Date

    Project Completion

    NCR No.

    Your work does not comply with contract requirements.

    Non Compliance:

    You are required to rectify the works by

  • 8/11/2019 Report Formats

    13/15

    Name of Work:

    Employer:

    LOI No.:

    Contractor:

    Immediately implement the following. Incase of change of contract terms, quote proposal must be submitted within 3 working days.(in

    case non receipt of reply, it will be assumed for no revision and acceptance.)

    DESCRIPTION:

    OVERALL COST IMPLICATION:

    ATTACHMENTS:

    To:

    S D Rev/Date

    Subject:

    Submit an itemized quotation within 3 working days for changes in Contract and or contract time related to the following. Do not

    proceed until approved.

    Proceed with the following with no change in Contract sum/Contract time. If you consider this is a change to your contract, do not

    proceed and submit cost proposal within 3 working days.

    ACTION

    REQUIR

    ED

    PROJECT

    ACTION REQUIRED: (For information only)

    YESKAY PROMAG CONSULTANCY PVT LTDSITE DIRECTIVE

    REPORT DATE

    Project

    Start Date

    Project Completion

    S D No.

    DETAILS

    Agreed Date Reviewed Date

    Contractor: AEC Promag (PMC)

    Signature

    Received by

    NamePosition Signature

    Issued by

  • 8/11/2019 Report Formats

    14/15

    Alt #

    YESKAY PROMAG CONSULTANCY PVT LTDTENDER COMPARISON SHEET

    REPORT DATE

    PRO

    JECT

    Project

    Start Date

    Project Completion

    Name of Work:

    Employer:

    LOI No.:

    SIGNATURES

    AEC

    Promag

    SM

    COMPARISON

    AEC Promag PM

    Opened in the Presence of:

    Signature Signature Signature

    Tender Participant Names Base Tender Tender Bond Addenda acknowledged

    Contractor:

    VP (Projects), AEC Promag Consultancy Pvt. Ltd.

    SignatureReviewed and Approved by

    AEC Promag SM

  • 8/11/2019 Report Formats

    15/15

    Name of Work:

    Employer:

    LOI No.:

    Contractor:

    YESKAY PROMAG CONSULTANCY PVT LTDACCIDENT REPORT

    REPORT DATE

    PRO

    JECT

    Project

    Start Date

    Project Completion

    ACCIDE

    NTDETAILS

    DESCRIPTION

    Nature of Injury:

    Cut/Fracture/ Loss of limb/ Burns/ others (specify)

    Description of Accident:

    Cause of Accident:

    Fall from height/ Fall of material / Electrification / Fire/ others

    Preventive Measures Taken:

    Contractor:

    Date of Accident

    Nature of Accident:

    First aid/ Temporary disability/ Permanent disability/ Fatal (specify)

    Name of the Injured:

    Age Sex

    Designation

    Location of Accident:

    Signature

    Date

    Project Manager

    Eye Witness

    1.

    Signature

    Date

    Contractor

    Site Engineer

    Signature

    Date

    REMARKS

    Signature

    Date

    Signature

    Date

    Signature

    Date

    Project Manager2.

    PMC Team

    SafetyEngineer