report draft

65
1 ACKNOWLEDGEMENT It is with great pleasure and learning spirit that we bringing out this industrial training report. We use this opportunity to express our heartiest gratitude to the support and guidance offered to us from various sources during the courses and completion of the training. We would like to extend our sincere gratitude to Mrs. Sreeja Jacob, Head of the Department of Civil Engineering, for providing us the opportunity to undertake this industrial training. We are very much thankful to our guide Mr. Pramod S, Assistant Professor for sharing his wealthy knowledge. We would like to express our profound gratitude to Ms. Aysha Sharvana P, our beloved sister who had inspired and motivated us to undertake this industrial training. We convey our sincere gratitude to Mr. P Rameshan (The President, ULCCS), Mrs. Meena (Technical Engineer, Civil, ULCCS), Mr. Shanil V K, Mr. Jithin, Mr. Chanchal, Mr. Sandeep, Mr. Nirmal Kumar R, Mr. Jithesh, Mr. Miqdad N V, Mr. Akhil, Mr. Anuraj, Mr. Naveen (all Assistant Engineers, ULCCS), The Project officer at Govt. Cyber Park, Calicut, Mr. Viswanathan (Retd. Chief Engineer, PWD), Mr. Riyas (R E Wall Technician, Mukkam Kadavu Bridge) for providing us valuable advice and guidance during the training and also to all the staffs and labourers of ULCCS for the help and services they rendered. Above all, we owe our gratitude to the Almighty for showering abundant blessings upon us. And last but not the least we wish to thank our parents and our friends for helping us to complete our industrial training work successfully. MOHAMMED SAJEEM A

Upload: mohammed-sajeem-arabi

Post on 16-Apr-2017

427 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: report draft

1

ACKNOWLEDGEMENT

It is with great pleasure and learning spirit that we bringing out this industrial training

report. We use this opportunity to express our heartiest gratitude to the support and guidance

offered to us from various sources during the courses and completion of the training.

We would like to extend our sincere gratitude to Mrs. Sreeja Jacob, Head of the

Department of Civil Engineering, for providing us the opportunity to undertake this industrial

training.

We are very much thankful to our guide Mr. Pramod S, Assistant Professor for

sharing his wealthy knowledge.

We would like to express our profound gratitude to Ms. Aysha Sharvana P, our

beloved sister who had inspired and motivated us to undertake this industrial training.

We convey our sincere gratitude to Mr. P Rameshan (The President, ULCCS), Mrs.

Meena (Technical Engineer, Civil, ULCCS), Mr. Shanil V K, Mr. Jithin, Mr. Chanchal,

Mr. Sandeep, Mr. Nirmal Kumar R, Mr. Jithesh, Mr. Miqdad N V, Mr. Akhil, Mr.

Anuraj, Mr. Naveen (all Assistant Engineers, ULCCS), The Project officer at Govt. Cyber

Park, Calicut, Mr. Viswanathan (Retd. Chief Engineer, PWD), Mr. Riyas (R E Wall

Technician, Mukkam Kadavu Bridge) for providing us valuable advice and guidance during

the training and also to all the staffs and labourers of ULCCS for the help and services they

rendered.

Above all, we owe our gratitude to the Almighty for showering abundant blessings

upon us. And last but not the least we wish to thank our parents and our friends for helping us

to complete our industrial training work successfully.

MOHAMMED SAJEEM A

Page 2: report draft

2

ABSTRACT

The goal of the industrial training that we have undergone at Uralungal Labour

Contract Co-Operative Scociety (ULCCS Ltd.) was to gain a general idea about various

construction methods, techniques, materials and equipments used in differents construction

works which are on progress, around. The training provided us a first hand opportunity to

expeerience actual site works, its challenges and its thrills. As quality and teamwork are the

primary motives of the company, the training experinces were uniquely great.

Training works were conducted at various sites under ULCCS Ltd. and we could

study very much about different types of civil engineering works. Through this report, we

aim to present a brief outline about every works we were trained in.

We are not arguing that this is a complete description of the works; it’s just an outline

of the same.

Page 3: report draft

3

CONTENTS

1. INTRODUCTION

2. SWIMMING POOL WORK AT NADAKKAVU

2.1 LAND PREPARATION

2.2 CONSTRUCTION

2.3 FINISHINGS

2.4 WATER TREATMENT

3. PILE WORK FOR KERALA FEEDS

3.1 PROCEDURE

4. ROAD WORKS FOR GOVT. CYBERPARK, CALICUT

4.1 LAND DEVELOPMENT

4.2 FORMATION OF ROAD

4.3 DRAINAGE DETAILS

4.4 REINFORCED EARTH WALL

4.5 COMPOUND WALL

5. PILING WORK FOR EMS HOSPITAL

5.1 SOIL TEST DETAILS

5.2 LEVELLING

5.3 BORING

5.4 REINFORCEMENT

5.5 CONCRETING

5.7 PILE CAP

6. SWIMMING POOL WORK AT Pe-Co-C, PERINTHALMANNA

6.1 CONSTRUCTION

6.2 FINISHINGS

Page 4: report draft

4

7. CONSTRUCTION OF BRIDGE AT MUKKAMKADAVU

7.1 STRUCTURAL DETAILS OF BRIDGE

7.2 CONSTRUCTION OF RE WALL

8. ROAD WORK AT TIRUR

8.1 CONSTRUCTION OF PAVEMENT

8.2 CONSTRUCTION OF CROSS-DRAINAGE WORK

8.3 CONSTRUCTION OF RETAINING WALL

9. CONCLUSION

Page 5: report draft

5

LIST OF FIGURES

1. SWIMMING POOL CONSTRUCTIO, NADAKKAVU

2. SITE LAYOUT OF NADAKKAVU POOL

3. LATERAL DIMENSIONS OF POOL

4. STRUCTURAL DETAILS OF POOL

5. PEARL TILE

6. LIGHTING FITTINGS FOR POOL

7. SAND FILTERS OF POOL

8. PILING WORKS FOR KERALA FEEDS

9. SITE LAYOUT

10. LAYOUT OF PILES FOR SILOS TANK

11. BORING BY DMC METHOD

12. REINFORCEMENT UNITS FOR PILES

13. LAND DEVL. AND ROAD WORK AT CYBER PARK

14. EARTHWORK AT CYBERPARK

15. APPLYING GSB LAYER

16. TYPICAL ROAD SECTIONS

17. DRAIN/ COMM/ PLUM DUCTS

18. CATCH PIT VIEW

19. RE WALL

20. THE COMPOUND WALL

21. SECTION OF COMPOUND WALL

22. KEY PLAN OF BORE HOLES

23. BENTONITE MISING PIT

24. REINFORCEMENT DETAILS OF PILE

25. PCC LAYER OVER TWO PILE

26. AFTER CONSTRUCTION OF PILE

27. PILE CAP DETAILS

28. SWIMMING POOL 1 PE-CO-C

Page 6: report draft

6

29. SITE LAYPOT

30. SECTIONAL VIEW OF POOL 1

31. ARCHITECTURAL VIEW OF MUKKAM BRIDGE

32. SUPER STRUCTURE OF PIER

33. PILE AND PILE CAP

34. PILE REINFORCEMENT

35. PILE CAP REINFORCEMENT

36. ALIGNMENT OF PIER AND ABUTMENTS

37. PIERS OF CIRCULAR PORTION

38. FACIA PANELS

39. THE GEOGRID

40. STRENGTHENING AND WIDENING OF ROAD

41. WIDENING OF TIPPU ROAD

42. RED SOIL AS SUB GRADE

43. GSB LAYER APPLICATION

44. SECTIONALA VIEW OF BOX CULVERTS

45. PRE-CAST BOX CULVERT

46. PRE-CAST BOX CULVERT UNITS\

47. RR WALL SECTION

48. SIDE POST TIRUR

Page 7: report draft

7

LIST OF TABLES

1. BORING LOG OF HOLE 1

2. BORING LOG OF HOLE 2

3. BORING LOG OF HOLE 3

4. SELECTION OF VG PAVING BITUMEN

5. GUIDELINE FOR MODIFIED BITUMEN

Page 8: report draft

8

1. INTRODUCTION

Our team of four had seven days to complete the training, which we took as an

opportunity to get trained at seven different sites. We were trained by the ULCCS Ltd. at

their various construction sites where we could study briefly about different civil structures

like Swimming pools, Roads, Piles, Trusses, and Bridges etc.

The first day, we were at the construction of a swimming pool at Nadakkavu

A.U.P.School, Calicut. The project also includes the construction of associated lawn, bath &

dressing room building, Plant room for the water cleaning equipment’s, boundary walls etc.

About 90% of the work has been completed.

We were trained at a 10.106 Acre construction site of Kerala feeds at Thiruvangoor

on the second day, where piling works for Silos tank, truss work for finished goods go down

etc. were on progress. The total site is meant for 17 buildings and 10 silos tanks.

Our third day of training was at Govt. Cyber Park, Calicut. The ongoing 20.46 crore

worth project includes formation of road, Drains, Chamber, Footpath & Parapet wall,

Culverts & Retaining structure, Masonry wall and Chain link fencing. All these works were

at different stages at different chain ages of the road that spanned over a km.

We had a much more thorough training on the fourth day at the 1.266 Acre

construction site for E.M.S. Hospital at Perambra, where different stages of piling and

foundation for a 5 storied building were on progress. Over 82 of 100 piles were completed

and at some portions, rests of the foundation works were also simultaneously on progress.

Our training on the fifth day was at Perinthalmanna, where 2 swimming pools, A

cafeteria and Toilet rooms were under construction for The Pe-Co-C society. One of the

pools was for adults and the other for kids. Around 75% of the works for swimming pools

were completed and a indoor stadium was yet to be built.

Construction of the first Y-Shaped bridge of Kerala across Iruvanhippuzha on

Mukkam-Koodaranhi road was the project we were trained at, on the penultimate day. An

approach road supported by Reinforced earth wall was also a part of the project. The bridge

was to support a 11 m wide road.

Page 9: report draft

9

The first phase of Strengthening, Widening and Extension of Tippu Sultan road as a

part of Vallarpadam - Kozhikode west coast corridor at Tirur, for Roads and Bridges

Development Corporation of Kerala Ltd. (RBDCK), was our final work for training. The 4.5

km work worth 17.75 crore includes the drainage works also. Precast box culvert used here is

the first of its kind, to be used in the Malabar region.

Page 10: report draft

10

2. SWIMMING POOL WORK AT NADAKKAVU

In the present world the standard for the construction of pools is growing popularity

of swimming and other water activities for sport, fitness, therapy or relaxation has led to the

increased use of swimming pools. Pool constructed should provide facilities that are safe,

hygienic and comfortable for bathers. But in India the construction of swimming pool is

limited to a small scale. The construction of swimming pool at Nadakkavu, Calicut was a

new challenge for District sports council. The land for the construction is provided by A.U.P

School East Nadakkavu and the total cost 1.5 crore was a fund of MLA. The swimming pool

having rectangular shape with 4 tracks and capacity of 4.5 lake liters of water. The total

project includes the construction of swimming pool and adjacent building having facilities for

plant room, office, bathroom, open shower, cafeteria and separate dressing room for both

boys and girls. The estimated duration for total construction was 7 months and is scheduled to

open Oct.15th 2013.

A number of civil structures and their construction details were familiar for us, but the

details in making of a swimming pool were really new and thrilling. We were trained under

the guidance of Mr. Shanil V K, on Sep.27th 2013. About 90% of the work has been

completed by then. The site lay out is shown in Fig.2.2

Fig.2.1 Swimming Pool Construction at Nadakkavu.

Page 11: report draft

11

2.1 LAND PREPARATION

The shape of the pool was rectangular having size of 25 m X 12.5 m, and the depth

varied from 1.2 m to 1.7 m from one end to another as shown in fig.2.2 Once the inside

dimensions of the pool are marked out along with the excavation lines, which are 0.5m larger

all the way around, to allow for the thickness of the walls and layers, setting out and digging

started.

Fig.2.3 Lateral dimensions of swimming pool, Nadakkavu

2.1.1 Excavation

A mechanical excavator J.C.B Earth mover was used to excavate the whole

pool. It took almost three days to complete the process. The excavated soil was used

for garden to form a bank, filling in lower area of ground and back filling of

swimming pool side wall. Excess soil was then transported from site by means of

Lorries; obviously the removal of soil from site also extends the time taken to dig the

pool. If the subsoil is gravel, shale or good draining rocky strata, the layer of quarry

muck is not necessary and the concrete floor can be laid direct onto the subsoil. In our

training site the total excavated material was red cohesive soil and no hard strata were

found during the excavation process.

Page 12: report draft

12

2.2 CONSTRUCTION

Fig.2.4 Structural details of swimming pool, Nadakkavu

2.2.1 Quarry muck layer

Before the application of quarry muck layer the soil at the bottom of the pool

was well compacted to required depth, so that the soil must possess an optimum

moisture content that produces the maximum density under proctor test. In our project

hand tampers were used for the compaction process. Good compaction of a cohesive

soil reduces permeability and increases shear strength and the stability of the

structure. Above the well compacted soil a layer of quarry muck of depth 40 cm was

provided throughout the bottom of the pool for making the ground stiff and hard for

the further construction.

2.2.2 Reinforcement

The most common cause of cracking in concrete pools is the inadequacy of the

reinforcement used, while it 8 mm steel mesh is sufficient for pools of 1.2 m in depth

with good foundations, it is not adequate for deeper pools. Therefore, 10 mm mild

steel bars were used throughout, these bars can be easily bent to conform with the

shape of the pool and were spaced at 230mm intervals, crossed with bars also at 230

Page 13: report draft

13

mm intervals, making 230 mm squares. The crossing top reinforcement was wired

with galvanized wire to the base reinforcement to keep it correctly spaced, this

reinforcement fabrication has to be raised from the floor by 50mm and this was done

with steel chairs. These chairs support the fabrication prior to concreting, and can be

obtained from steel stockholders.

Note: The pipe work from the main drains should be positioned before fixing the

Reinforcement for the pool floor.

2.2.3 Location Of Main Drain and Inlet Pipe work

The main drain was then placed in the middle of the deep end floor ensuring

that the top 40 mm will be above the finished concrete slab in order to allow for the

rendering and the finishing. 4 nos. of 3” dia. drain pipe and 20 nos. of 2” dia. inlet

pipe are used for the fast working of pool. Run the pipe from the main drain through

the concrete floor slab to outside the proposed pool walls, and then brings the pipe up

to the top of the pool. The end of this pipe should then be sealed to prevent any debris

falling into the pipe work during construction.

2.2.4 Concreting

Before starting the reinforcement work for RCC, a layer of 20 cm depth PCC

of 1:4:8 were provided for a getting a hard level surface. The main drain positioned

and all the reinforcing fabricated, the floor is now ready for concreting. It is always

best to carry out all the concreting on the same day, as these results in the strongest

floor, if this is not possible it should be done on successive days. It is always

advisable to use ready mix concrete as the proportions and mixing are always

constant. The concrete used for this particular pool was the grade of M35. The depth

RCC was kept 25.5 cm for both pool walls and base. When moving the concrete into

the pool it was important that it goes well under the reinforcement, at this stage plenty

of labor needs to be available to help with the leveling and vibrating.

Page 14: report draft

14

2.2.5 Water Proof Layer

The water proofing of swimming pool was one of the major construction

challenge of pool making at Nadakkavu. And it was the essential layer that was

unavoidable. The inside of the pool shell must have to be rendered with a waterproof

render incorporating “Sealocrete”, “Vandex”. In our site a special multi-coat render

work, “Sika” was used for water proofing. Once applied, the sika admixture reacts

with moisture by expanding into jelly-like substance, blocking all the voids and leaves

the surface with an impregnable seal.

2.2.6 Plastering

Before the beginning of tiling the entire pool should be plastered above the

water proof sika layer. All the bottom corners should be rounded in150 mm curve. A

suitable cement mortar and calculated amount of amount of cement grout were used

for the plastering.

2.2.7 Tile Work

Tile work was the final finish provided at the upper surface of swimming pool.

Variety color of tiles and mosaics were available in market. In our site sky blue

colored “Pearl” brand tiles are used for final finish. The tile used was slip-resistant

and have a surface which is not conducive to slipping under contact of bare feet. It

was designated by the manufacturer as suitable for walking surfaces in wet areas or

for use in pool areas, and coved at the wall juncture for ease of cleaning.

Fig.2.5 Pearl Tile

Page 15: report draft

15

2.3 FINISHINGS

2.3.1 Underwater Light

An underwater light certainly transforms a pool during the late evening. One

light is sufficient for pools up to 8.5m x 4.3m but the larger pools do benefit from the

use of two lights. In our site 10 nos. of lightings are provided, when deciding the

position of a pool light, one should always install the light on the side of the pool

nearest the house or the sitting area; in this position the pool will be lit up without

seeing the light itself. Therefore, the best position for the light, if it complies with the

previous rule, is in the center of one of the long walls. When positioning the

underwater light make sure it is installed 875 mm down from the underside of the

pool coping as in the event of bulb failure the light unit can then be lifted out of the

water and changed above water level. The typical light fitting is shown in fig.2.4. The

conduit from the light is then attached to the niche with a waterproof joint which

should then lead out through the back wall up to the deck box fitted at paving level.

The niche should be thoroughly concreted with reinforcement and tied into the pool

walls.

Fig.2.6 Light Fittings for Swimming Pool

2.3.2 Balancing Tank and Channel

The swimming pool constructing in our site is over flowing type. Hence

suitable channels are provided around the swimming pool edge to collect the over

flowing water. This water is then transported to the balancing tank adjacent to the

Page 16: report draft

16

swimming pool. The balancing tank should be located below the ground level to

balance the water level inside the pool.

2.3.3 Steps

Total four number of stainless steel ladder are provided for the swimming

pool, one ladder at each corner is located.

2.3.4 Backfilling

There is usually only a small gap of 150mm to backfill and this is done using

gravel, scalping, soil or rejects. The backfilling is done in layers of 300mm and

continues to just below the piping connections, it is then thoroughly consolidated. All

piping should be laid on a bed of sand and then also covered with sand in order to

prevent damage before the backfilling is completed.

2.3.5 Paving

The paving around the pool should be practicable as well as aesthetically

pleasing. Paving should be laid where possible with a fall away from the pool so that

dirt or dust on the paving does not enter the pool after rain; it needs to be non-slip, as

smooth slippery surfaces can be very dangerous. For indoor pools Drain easy is a

simple method of removing splash water enabling the pool surround to be kept dry, if

it is being used, it is installed immediately behind the pool coping before the paving.

2.3.6 Plant Room

The pool equipment needs to be sited in a shed or outhouse, preferably the

building needs to be located as close to the pool as possible and must have an

electrical supply. The plant room and office building for the pool operator was located

about 9 m away from the pool edge at Nadakkavu project. It is detailed in site plane.

It also possesses adequate size to contain the pool pump, sand filter and cleaning

system. etc.

Page 17: report draft

17

2.4 WATER TREATMENT

A plant room was constructed attached to the office building. This contains water

treatment equipment’s, sand filters, pH measuring apparatus, drain and inlet pipe control

valves, 2 pumps of 3 HP pumping capacity.

2.4.1 Filtration

Filters are the heart of the pool water treatment and the filter system should

normally be operated continuously. In our site total 8 hr. filtration was required per

day for the complete filtration of pool water and almost 3000 liters of waste water is

estimated to be generated per day. This filtration is carried out by 2 sand filters

(ASTRA POOL, BERLIN), which were located inside the plant room. Filters should

be maintained in a good condition by frequent backwashing and regular inspection.

Conventional sand filters need backwashing at least once a week and much more

frequently in a busy pool. High rate and pre-coat filters require frequent, sometimes

daily backwashing as specified in the manufacturer's guidance.

Fig.2.7 Sand Filters For Swimming Pool, Nadakkavu.

Page 18: report draft

18

3. PILE WORK FOR KERALA FEEDS

A 10.106 acre construction site of Kerala Cattle feeds at Thiruvangoor was our

training site on Sept.9th.2013 under the guidance of Mr. Jithin and Mr. Chanchal. The

construction at the site was boring for 300 piles. Almost 80 piles were casted by then and

making of silos tank above the pile and pile cape were started. The total site is meant for 17

buildings and 10 silos tanks. The layout of the site is given Fig.3.2.

Fig.3.1 Piling Work for Kerala Feeds, Thiruvangoor

A total of 120 piles were to be constructed for the foundation of 10 silos tank. Each

tank require a foundation resting on a pile cap connecting 10 piles in a circle and 2 pillars

outside it. The layout of piles is as shown in fig.3.3. The piles are of diameter 700mm for

which M30 Grade reinforced concrete is used. Each piles are required to carry a load of 112

tonnes. The piles are end bearing type, which rest on hard rock strata underground. At this

site, the hard rock was found at 10-13m depth. If no rock was found, friction piles might be

required. A pile cap was built, connecting a set of piles for a tank, over which 18 pedestals

were also built. The silos tank will be placed over these pedestals.

Page 19: report draft

19

Fig.3.3 Layout of Piles for Silos Tanks

IS: 2911 (part I Sec.2) – Indian Standard Code of practice for Design and

Construction of pile Foundations: Part I concrete piles, Section 2 – Bored Cast –in Situ piles

was referred in conjunction with other specifications during the entire design, construction

and installation work.

3.1 PROCEDURE

3.1.1 Test on soil

Standard penetration test was conducted earlier on the soil and the report was

provided by the consultants. The report showed that the N value was greater than 50

for depths greater than 10-13, on an average. This lead to a conclusion that bores for

piles has to be bored up to these depths plus around 10cm through the underlying

strata. The soil profile here indicated higher presence of red, clayey and sandy soils.

3.1.2 Levelling

Whole of the loads from tanks were to be transferred to the foundation area,

uniformly. For this the foundation had to be straight and level. This was achieved by

ensuring that the pile caps are all, in a same level. Levelling was done for assuring

that this requirement is met perfectly, using dumpy levels. Cutting and back filling

operations were then done, according to the requirement.

Page 20: report draft

20

3.1.3 Boring

Fig.3.4 Boring by DMC Method

As concluded from the standard penetration test, the piles are expected to be

10-13 meters long and that deep, boring was to be done. Boring was done by Direct

Mud Circulation (DMC) method. It was earlier ensured that the soil is capable of

safely withstanding the whole mechanical arrangements required for this method of

boring. In soft soils, a permanent liner has to be provided so as to withstand any

scouring of side walls. Even though the soil here wasn’t that soft, a permanent liner,

made of 6mm thick M.S. Sheets were provided. It was also ensured that the rigs had

the capacity of boring up to the required depth.

As the first step of boring, pile positions were marked according to the

drawings, with maximum precision possible. IS: 2911(part 1 /Sec.2) was referred for

permissible deviations. Then the boring rig was installed at such a position that the

chisel is ready to bore at the exact location of the pile to be cast. At this site, 4 rigs

were used, which are all run with petroleum fuels. A rig include an electric motor that

initiates work, three long pillars that can be set like a tripod, A pulley connected to the

motor via cable that can be released of load by means of a lever, A sharp edged chisel

Page 21: report draft

21

of high weight and required diameter etc. The chisel is like a thick metallic hollow

pipe that tapers out towards the bottom so that it can be connected to extra-long pipes

at the back, which are to be joined on boring deeper. The connecting pipes are also

hollow so that mud can be pumped through these pipes using an electric motor that

takes mud from a flushing chamber, nearby.

When the mechanical operations begin, the chisel is first lifted up and then

fallen down. This work is repeated by the chisel as bore starts developing at the pile

point. To make the soil soft, some water was initially poured. This water gets mixed

with the dugout soil and forms mud. The mud formed was taken through channels, to

the flushing chamber. The flushing chamber has two sections- one for the incoming

mud and the other for mud, mixed with Bentonite. The Bentonite is clay like mineral

that is extensively found in the Kuchh areas of Gujarat and Rajastan. Properties of

bentonite used was according to IS: 2911 (part 1/Sec.2). Bentonite is available in bags

at cheap rate. It’s like liquid in dynamic state and high viscous fluid in static state.

This property helps in preventing the actual soft soil walls of the bores from scouring

and falling in. This mud is circulated through the chisel to the bore and back to the

flush chamber through channel and hence called Direct Mud Circulation method.

When about half a meter of boring was done, a 6mm thick hollow metallic

cylindrical sheet was inserted so as to keep the bore diameter uniform. After each 2m

of boring, mud samples coming out from the bores were collected and tested. The

completion of boring can be understood when hard sounds are heard on hitting of

chisel on to the hard rock. The mud coming out of bore also indicates an approximate

depth of the bore. As a test if the boring has reached the hard strata, the depth of

further boring during a period of 1hour is noted. If it falls to be under 5-10 cm, hard

strata can be inferred and boring can be stopped. Some amount of pure water was then

pumped through the chisel so as to clean the bore and make it ready for the

installation of reinforcement and placing of concrete.

Page 22: report draft

22

3.1.4 Placing reinforcement

Fig.3.5 Reinforcement Units for Piles

By this time, the reinforcements as per designs were prepared aside. 20mm

diameter longitudinal bars along with lateral ties at designed spacing and other

specifications according to Relevant parts of IS: 2911 (part 1/Sec.2), were used. In

case of usage of two segments of reinforcement in the same place, they were lap

jointed by welding. As long as possible, lateral joints were avoided. Small circular

cement mortar elements called rollers were tied on to the outer parts of reinforcement

bars, which ensured required spacing from bore walls. They also facilitated smooth

and easy movement of reinforcement unit, on inserting it to the bore. The same rig as

that of the boring unit along with human support were used to place the

reinforcements correctly, which was done with extreme care.

3.1.5 Placing of concrete.

As the design, M30 Grade concrete had to be placed. The required amount of

concrete and its components were calculated before placing was started. The required

amount of concrete was prepared at the site in a mechanical mixer, on demand. The

mixed portion of concrete was poured very soon, concerned of the early setting of

concrete. For placing, Tromie pipe system was used. This system consists of hollow

metallic pipes of small diameter and considerable lengths, which could be connected

Page 23: report draft

23

back to back using screw arrangements. It also contains a funnel of the same bottom

diameter as that of the pipes. The funnel had a key at its mouth. The pipes were

joined back to back and to one end, the funnel was connected. It was then inserted

into the bore using boring rigs, along with human effort. The tremie is so placed that

there is always a 30cm clear between bottom of it and end of the bore hole.

In such a position, the concrete mixer was placed very near to funnel so that

mixed concrete can be directly poured into the tremie. Initially, the mouth of the

funnel was closed using its key arrangement. Then, mixed concrete was filled in the

funnel. Then the key was suddenly opened and the concrete had fallen into the bore

through the tremie pipes, which resulted in the replacement of the mud at the bottom

of hole, by the incoming concrete. As the pouring procedure was repeated 2 or 3

times, the mud which was at the bottom of hole started rising and the mud at top

started overflowing out. Then, the tremie system was uplifted by some amount and

the pipe at the top was removed. Also, the tremie was moved up and down slightly for

helping compaction. During this procedure, it was mathematically ensured that the

pipe was still way inside the placed concrete, by around a meter so that no mud or air

gets inside the placed concrete.

On repeating this procedure, finally, the mud that was at the bottom of hole

came out, indicating that the hole is filled by concrete. The procedure was repeated

for better safety, until fresh concrete evolved out. As soon as the placing of concrete

was completed, the tremie was taken out and cleaned well.

3.1.6 Pile cap

The piles were constructed to the designed level of top of pile cap so that the

bottom portions of the pile would very strong. The top portion- around 1m, as

calculated- was then chipped off without affecting its reinforcements. Reinforcements

for the pile cap were placed over the piles, which results in strong intermingled

reinforcements. Pile caps of 1m depth were built over them on which pedestals were

constructed as a foundation for the tanks.

Page 24: report draft

24

4. ROAD WORKS FOR

GOVT. CYBERPARK, CALICUT

Cyber Park, a Government of Kerala organization planned in the lines of Techno Park

at Trivandrum and Info Park at Kochi to build, operate and manage IT park for the promotion

and development of investment in IT and ITES industries in Malabar region of Kerala has

been registered under the Societies Act 1860 on 28-01-09. The Cyberpark is expanding its

projects around 28 hectares of land in Nellikkode and Pantheerankavu village, Calicut. The

Govt. Expenditure towards the land acquisition for Cyberpark is estimated to be around 430

million INR and another 2.50 billion INR over the next two year for providing necessary

infrastructure and construction of buildings.

Fig.4.1 Land Development and Road works for Govt. Cyber Park, Calicut.

The road constructed at cyber park were a BMBC type Flexible road had a total coat

of 20.46 crore for road, drainage, and Reinforced Earth Wall etc. We were trained at this

project site on Sept. 30th 2013, with the help of Mr. Sandeep and The Project officer at Govt.

Cyber Park, Calicut, Mr. Viswanathan (Retd. Chief Engineer, PWD). The detailed

construction details which we gained from the project are explained below.

Page 25: report draft

25

4.1 LAND DEVELOPMENT

Fig.4.2 Earthwork at Cyberpark, Calicut.

There were some schedules and guideline was taken by the authorities for the total

construction of the project. The site chosen for the Cyberpark were a hill top and it was

covered with dense vegetation. Hence for the further construction the land were had to be

developed. The small jungles were cleared first and the uprooting of trees up to 30 cm depth

was done. This rubbish is shifted to a distance of 150 m outside the periphery of the proposed

area.

Earth work for all the soil except hard rock was done by means of Earthmovers. This

excavated soil is then transported to a distance within 5 km in Lorries. The levelling of

underlying soil is done after that. The depressions on the land are filled by using some of the

excavated soil. The soil consolidated with rollers and made a 15 cm layer. And watered and

ramming were done.

Page 26: report draft

26

4.2 FORMATION OF ROAD

The road work at Cyberpark Calicut were a BMBC Flexible pavement having

following layers from bottom to top, Sub Base, Wet Mix Macadam, Wearing Coarse,

Bituminous Macadam, Bituminous Concrete. The detailed specification of each layer is

explained below. Typical Road section is shown in fig. 4.4

4.2.1 GSB (Granular Sub Base)

The construction of granular sub base is done by providing close graded

materials (metal size: 53 - 9.5 mm = 0.64 m3, 9.5 – 2.36 mm = 0.25 m3 and 2.36 mm

= 0.38 m3). The mixing operation were done in a mechanical mix plant at OMC,

carried to site and spread in uniform layer with motor grader on prepared surface and

compacted with vibratory power roller to activate desired density. The GSB layer

provided in 20 cm thickness for whole road.

Fig.4.3 Applying GSB Layer using Aggregate Grader

4.2.2 WMM (Wet Mix Macadam)

Providing, laying and spreading and compacting graded stone aggregate

(metal size : 45 – 22.4 mm = 0.396 m3, 22.4 – 2.36 mm = 0.52 m3 and 2.36 mm - 75µ

= 0.396 m3) to wet mix macadam specifications including premixing the material with

Page 27: report draft

27

water at required OMC in the mechanical mix plant and carried the mixed material by

tipper to site, laid in uniform layer. Paved on well prepared sub-base and compacted

with vibratory roller to achieve desired density and thickness 25 cm.

4.2.3 WC (Wearing Course)

Providing and laying surface dressing as wearing course in single coat using

crushed stone aggregate of size 19 mm at 0.015m3 /m2 on a layer of bituminous binder

at 1.20 kg/ m2 laid on prepared surface and rolling with 8-10 tonne smooth wheeled

steel roller. The wearing Coarse thickness were 15 mm. Providing and applying tack

coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.02 kg

per sqm on the prepared bituminous/granular surface cleaned with mechanical broom.

4.2.4 BM (Bituminous Macadam)

Providing and laying bituminous macadam of 50 mm thick with 100-120 TPH hot

mix plant producing an average out of 75 tonnes per hour using crushed aggregate

of40 mm nominal size 1.42 m3 premixed with bituminous binder over a previously

prepared surface with paver finisher to the required grade, level and alignment and

rolled to achieve the desired compaction. Providing and applying tack coat with

bitumen emulsion using emulsion pressure distributor at the rate of 0.30 kg per sqm

on the prepared bituminous/granular surface cleaned with mechanical broom.

4.2.5 BC (Bituminous Concrete)

Providing and laying bituminous concrete of 25 mm thick with 100-120 TPH batch

type hot mix plant producing an avg. output of 75 tonnes per hour using crushed

aggregate of size 19mm nominal size 1.46 m3 and filler 2 % of weight of aggregate,

premixed with bituminous binder at 5.4 to 5.6 per cent of mix and filler, transporting

the hot mix to work site, laying with a hydrostatic paver finisher with sensor control

to the required grade, level and alignment, rolling with smooth wheeled, vibratory and

tandem rollers to achieve the desired compaction.

Page 28: report draft

28

4.3 DRAINAGE DETAILS

In hilly areas, the drainage of rain water is faster and it discharges into nearby

depressions. The need for an efficient drainage system can, therefore, be hardly over

emphasized. The essential components of drainage system are: water collection catch pit at

roadside; connection of the catch pits to open/underground drains; and discharge of these

drains into an outfall. Since the rain water does not require any kind of treatment, so

generally the water is disposed of in any nearby nallah/river etc.

4.3.1 Drain/Com./Plum Duct

After the earth work were done for the drainage construction a layer of PCC is

provided on the proposed drainage line. The structural details are shown in fig. For

both drain duct and communication duct of length 60 cm a PCC layer of 1:5:10 0f 10

cm thick is provide and for plumbing duct of 75 cm a PCC of 1:4:8 of 10 cm thick is

provided. The three ducts were covered with RCC slabs of M20 grade. The covering

was only provided discontinuously for the later insertion of cables and pipes. Typical

view is shown in fig.4.5.

Fig.4.5 Drainage, Communication and Plumbing Duct, Cyberpark

Page 29: report draft

29

4.3.2 Catch pit

Fig.4.6 Catch pit Drainage Cyberpark, Calicut.

Water collection in the catch pits, usually covered by horizontal/vertical

gratings, is hampered as these gratings get covered with dead leaves/ rubbish. These

catch pits, which temporarily store the surplus water themselves get choked over time,

as dust/dirt/debris get deposited and choke their outlets to drains. The periodic

cleaning of these collection chambers is essential. There is a need to design and install

catch pits keeping in view the maximum rainfall intensity, duration of rainfall, the

expected surface run off and the capacity of the outlet of the catch pit so that the catch

pits do not overflow during high intensity rains. The location of catch pits should be

decided judiciously so as to permit future development and widening of road without

disturbing the storm water collection system. The design details of the catch pit are

shown in fig.4.7.

Page 30: report draft

30

4.4 REINFORCED EARTH WALL

Reinforced Earth is a composite material formed by the association of a frictional soil

and reinforcement strips. In concept, it is like reinforcing concrete; that is, it is an economical

means of improving the mechanical properties of a basic material, earth, by reinforcing that

material with another, steel. Concrete facing panels are used at the face of the reinforced

volume to prevent erosion of the backfill and to provide an attractive, finished appearance.

Fig.4.7 the RE Wall Constructed at Cyberpark, Calicut

Reinforced soil wall installation is the combination of quite a few simple procedures

like casting, curing, stacking, transporting of facia panel, excavation, earth filling layer,

compaction, facia panel erection and alignment, fixing of soil reinforcement (geogrid),

casting of coping/ barrier etc.

Page 31: report draft

31

4.4.1 Panel Casting

Precast concrete panel is one of the biggest advantages of this system as it

save lot of construction hassles along with time and money. Use of especially

designed/fabricated molds is required for this job as aesthetic and dimension of this

panel play an important role in overall performance of the reinforced soil wall.

Different size of panels is being used depending up on the geometry/ profile of the

structure, majority of panels is standard 1.5 x 1.5. Casting of precast panel involves

following activities.

Infrastructure set – up i.e. casting yard/ store/ batching plant/ laboratory etc.

Casting of panels i.e. molds fixing, placing accessories, concrete pouring etc.

Curing

Stacking and transportation.

4.4.2 Panel Erection

The ultimate manifestation of a reinforced soil structure depends largely on

the care taken in erecting and positioning facing elements. For this reason, particular

attention must be paid to the erection of facing elements and to the backfill placement.

In the installation of reinforced soil facia panel and the activities related to

construction of reinforced soil wall. The following major activities are involved.

Setting up the site. i.e. Excavation, Foundation treatment, Levelling pad etc.

Erection of facia panel i.e. placing and alignment

Earth Work i.e. filling and compaction of reinforced soil, retained soil and

filter media.

Reinforcement i.e. placing of geogrid and tightening

Installation of pavement fixture i.e. friction slab, crash barrier, railing, drain

etc.

Page 32: report draft

32

4.5 COMPOUND WALL

Fig.4.8 The Compound wall of Cyberpark, Calicut.

A well erected masonry boundary wall had provided throughout the periphery of the

Cyber Park. The standard specifications for the construction of the wall are following.

Excavation in ordinary rock and depositing on bank with initial lead up to 50m and

lift up to 1.5m including breaking clods, watering, ramming, sectioning of spoil bank,

stacking serviceable material for measurements and disposal of unserviceable material as

directed, filling back the sides of RR Masonry. Cement concrete were casted 1:4:8 using

40mm broken stone. Random Rubble masonry in cement mortar 1:6 for foundation and

basement of boundary wall. Laterite masonry using neatly dressed stones of size 35x20x20 in

CM 1:6 for bounder wall. For fixing angles and completing coping cement concrete 1:2:4

(M 15) using 20mm broken stones are used. Above this MS Angle iron for fencing post are

provided. Typical c/s of the masonry boundary wall has shown in fig.4.10.

Page 33: report draft

33

5. PILING WORKS FOR E.M.S. HOSPITAL

Construction works of the proposed 12crore worth E.M.S. Hospital at a 1.266 Acre

site at Perambra was the fourth concern of our training works, which we did on 01/03/2013,

with the help of site Engineer Mr.Nirmal. The works on progress at this site was mainly that

of piling. 100 piles had to be constructed at this site for transferring load from a 5 storied

building, uniformly over the ground, where hard strata was found at about 9-13 m depth, on

an average. Of the total 100 piles, about 82 were completed of work and 2 were on progress.

The piles were all of diameter 600, 700 or 900mm. Pile cap and superstructure works have

been started over some completed piles. Direct mud circulation method was used here for

piling, for which 2 rigs were employed.

5.1 SOIL TEST DETAILS

As the primary step, Standard Penetration Test (SPT) was conducted on the soil, so as

to obtain the soil profile and strength details. For this, 3 known points were selected at the

site, where bore holes were made, from which soil samples at different depths were collected

for testing. The locations of the bore holes were as shown in fig. 5.1. The test details which

include the soil profile and N values at different depths are shown in table. 5.1, 5.2 & 5.3.

Fig.5.1 Key Plan on Location of Bore Holes

Page 34: report draft

34

Table.5.1 Boring Log of Hole 1

Table.5.2 Boring Log of Hole 2

Page 35: report draft

35

Table.5.3 Boring Log of Hole 3

5.1.1 Recommendations

From the soil test details as presented in the above figures, it was inferred that

there’s no uniformity in soil profiles at different locations. Even though in BH2

medium hard laterite, which is capable of supporting the foundation of the proposed

structure, was available, it was missing at other locations. Since the proposed

structure was a 4 storeyed one with a possibility of additional floor later and since

hard and strong stratum was missing at other locations other than BH2, Shallow

foundation was not recommended for the structure. Piles resting on hard strata, which

were available at 9-13 m below, were recommended for foundation.

5.2 LEVELLING

Whole of the loads from the building were to be transferred to the foundation area

uniformly. For this the foundation had to be straight and level. This was achieved by ensuring

that the pile caps were all in the same level. The area was levelled using dumpy levels and it

was assured that this requirement is met perfectly. Cutting and back filling operations were

then done, according to the requirement.

Page 36: report draft

36

5.3 BORING

As concluded from the standard penetration test, the piles were expected to be 10-13

metres long and that deep, boring was done. Boring was done by Direct Mud Circulation

(DMC) method. It was earlier ensured that the soil is capable of safely withstanding the

whole mechanical arrangements required for this method of boring. In soft soils, a permanent

liner has to be provided so as to withstand any scouring of side walls. Even though the soil

here wasn’t that soft, a permanent liner, made of 6mm thick M.S.Sheets were provided. It

was also ensured that the rigs had the capacity of boring up to the required depth.

As the first step of boring, pile positions were marked according to the drawings, with

maximum precision possible. IS: 2911(part 1/Sec.2) was referred for permissible deviations.

Then the boring rig was installed at such a position that the chisel is ready to bore at the exact

location of the pile to be cast. At this site, 2 rigs were used, which were all run with

petroleum fuels. A rig include an electric motor that initiates work, three long pillars that can

be set like a tripod, A pulley connected to the motor via cable that can be released of load by

means of a lever, A sharp edged chisel of high weight and required diameter etc. The chisel

is like a thick metallic hollow pipe that tapers out towards the bottom so that it can be

connected to extra-long pipes at the back, which are to be joined on boring deeper. The

connecting pipes are also hollow so that mud can be pumped through these pipes using an

electric motor that take mud from a flushing chamber, nearby.

When the mechanical operations began, the chisel was first lifted up and then fallen

down. This work was repeated by the chisel as bore started to develop at the pile point. To

make the soil soft, some water was initially poured. This water got mixed with the dugout soil

and mud was formed. The mud formed was taken through channels, to the flushing chamber.

The flushing chamber has two sections- one for the incoming mud and the other for mud,

mixed with Bentonite. The Bentonite is clay like mineral that is extensively found in the

Kuchh areas of Gujarat and Rajastan. Properties of bentonite used was according to IS: 2911

(part 1/Sec.2). Bentonite is available in bags at cheap rate. It’s like liquid in dynamic state

and high viscous fluid in static state. This property helps in preventing the actual soft soil

walls of the bores from scouring and falling in. This mud was circulated through the chisel to

Page 37: report draft

37

The bore and back to the flush chamber through channel and hence called Direct Mud

Circulation method.

Fig.5.2 Bentonite Mixing Pit, EMS Hospital Construction, Perambra

When about half a metre of boring was done, a 6mm thick hollow metallic cylindrical

sheet was inserted so as to keep the bore diameter uniform. After each 2m of boring, mud

samples coming out from the bores were collected and tested. The completion of boring can

be understood when hard sounds are heard on hitting of chisel on to the hard rock. The mud

coming out of bore also indicates an approximate depth of the bore. As a test if the boring has

reached the hard strata, the depth of further boring during a period of 1hour is noted. If it falls

to be under 5-10 cm, hard strata can be inferred and boring can be stopped. Some amount of

pure water was then pumped through the chisel so as to clean the bore and make it ready for

the installation of reinforcement and placing of concrete.

5.4 REINFORCEMENT

By this time, the reinforcements as per designs were prepared aside. 20mm diameter

longitudinal bars along with lateral ties at designed spacing and other specifications

according to Relevant parts of IS: 2911 (part 1/Sec.2), were used. In case of usage of two

segments of reinforcement in the same place, they were lap jointed by welding. Care was

taken to avoid lateral joins at same levels. As long as possible, lateral joints were avoided.

Page 38: report draft

38

Small circular cement mortar elements called rollers were tied on to the outer parts of

reinforcement bars, which ensured required spacing from bore walls. They also facilitated

smooth and easy movement of reinforcement unit, on inserting it to the bore. The same rig as

that of the boring unit along with human support were used to place the reinforcements

correctly, which was done with extreme care. The reinforcement details of different piles are

shown in fig 5.3.

5.5 CONCRETING

As the design, M35 Grade concrete had to be placed. The required amount of concrete

and its components were calculated before placing was started.

The required amount of cement and thereby that of concrete was calculated as follows:

(For this case, a pile of diameter 900mm & depth 12.64m was considered.)

Volume of 1 pile = pr2h

= 3.14 *0 .452 *12.64

= 8.03 m3 of concrete per pile

Amount of cement per m3 of M35 concrete = 400 kg

No. Of bags = 400kg / 50kg

=8 bags of cement per m3 of M35 concrete

No. of bags of cement for 1 pile = 8.03m3 * 8 bags/m3

= 64.29 bags of cement per pile

The required amount of concrete was prepared at the site in a mechanical mixer, on

demand. The mixed portion of concrete was poured very soon, concerned of the early setting

of concrete. For placing, tremie pipe system was used. This system consists of hollow

metallic pipes of small diameter and considerable lengths, which could be connected back to

back using screw arrangements. It also contains a funnel of the same bottom diameter as that

of the pipes. The funnel had a key at its mouth. The pipes were joined back to back and to

one end, the funnel was connected. It was then inserted into the bore using boring rigs, along

Page 39: report draft

39

with human effort. The tremie is so placed that there is always a 30cm clear between bottom

of it and end of the bore hole.

In such a position, the concrete mixer was placed very near to funnel so that mixed

concrete can be directly poured into the tremie. Initially, the mouth of the funnel was closed

using its key arrangement. Then, mixed concrete was filled in the funnel. Then the key was

suddenly opened and the concrete had fallen into the bore through the tremie pipes, which

resulted in the replacement of the mud at the bottom of hole, by the incoming concrete. As

the pouring procedure was repeated 2 or 3 times, the mud which was at the bottom of hole

started rising and the mud at top started overflowing out.

Then, the tremie system was uplifted by some amount and the pipe at the top was

removed. Also, the tremie was moved up and down slightly for helping compaction. During

this procedure, it was mathematically ensured that the pipe was still way inside the placed

concrete, by around a metre so that no mud or air gets inside the placed concrete.

The mathematical procedure was as follows:

Ht. of pile with 1 bag of cement = 12.64 m / 64.29 bags

= 0.19 m rise of pile / bag

Ht. to be completed before removal of 1st pipe = 0.3 (Bottom clearance) +1 (Dipped

Length of tremie) + 0.8 (Length of top pipe)

= 2.3m of pile

Corresponding no. of bags of cement = 2.3m / 0.19m

= 12 bags of cement

i.e., after placing concrete corresponding to 12 bags of cement, the top most tremie piece

of 0.80m length can removed. Then the rest tremie system will be immersed in the

concrete by 1m length. This length can be considered for compaction.

The rest of the pipes were all 1.35m depth. So, each pipe could be removed after

addition of additional concrete, corresponding to (1.35/.19 =) 7-8 cement bags.

On proceeding, finally, the mud that was at the bottom of hole came out, indicating

that the hole is filled by concrete. The procedure was repeated for better safety, until fresh

concrete evolved out. As soon as the placing of concrete was completed, the tremie was taken

out and cleaned well.

Page 40: report draft

40

5.6 PILE CAP

Fig.5.4 PCC Layer over two piles.

The piles were constructed to the designed level of top of pile cap so that the bottom

portions of the pile would very strong. The top portion- around 1m, as calculated- was then

chipped off without affecting its reinforcements. Before casting Pile cap a combined PCC

layer of 100 mm thick is provided as shown in fig.5.3, on the top of two piles for providing a

hard levelled base surface for the pile cap construction. Reinforcements for the pile cap were

placed over the piles, which results in strong intermingled reinforcements. Pile caps of 1m

depth were built over them, over which the super structure was to be built. The reinforcement

details of 600 mm pile are shown in fig.5.6.

Fig.5.5 After construction of pile cap.

Page 41: report draft

41

6. SWIMMING POOL WORK AT Pe-Co-C,

PERINTHALMANNA

The Pe-Co-C (Perinthalmanna Co-operative Health and Recreation Centre) will be a

multi-sports facility that provides its users with various services. A first class fitness Centre,

two swimming pools both for adults and kids, life style center, indoor stadium etc. are

included in the construction of the Pe-Co-C. It is the first sports facility in Perinthalmanna

where families of all age groups have the options to expand their activities. The Pe-Co-C is

located on a hill top just 4 km away from Perinthalmanna town. The total cost estimated is 20

crore. It is supposed to be the best south Indian multipurpose indoor stadium, modern aquatic

club, sports village, courts of a range of events. These apart 3-star accommodations would

also be on offer.

The structural construction of restaurant, bath room, swimming pool 1 and 2 was

almost finished yet some finishing works has to be completed. After the completion of this,

the work for indoor stadium was planned to start. Our training date at this site was, Oct 3rd

2013, under the guidance of Mr. Jithesh. The site layout is shown in fig.6.2

Fig. 6.1 swimming pool 1 construction at Pe-Co-C

Page 42: report draft

42

6.1 CONSTRUCTION

The swimming pools constructing at Pe-Co-C is having rectangular shape of

dimension 25.60 m X 13.60 m for adult pool, and for kids pool its limited to 12.60 m X 6.60

m. The main difference in construction of this swimming pool from the pool at Nadakkavu

was, this swimming pool constructed above the original ground level, whereas at nadakkavu

a trench with pool dimension is excavated below the ground surface. Here after the full

construction of pool the ground level of four sides are to be elevated up to the pool’s top level

by backfilling. Due to the structural and load considerations this swimming pool has to

provide additional beams and columns.

The following aspects were taken into account during the load calculations process;

pool filling, alternating thermal loads, internal stress of the concrete pool shell with regard to

the reduction of shrinkage cracks, water pressure, support of other structural components

during construction, and loads resulting from normal operation of the pool.

6.1.1 Beams and Columns

Large amount of water pressure and weight of pool users are to be subjected

on the pool surface at normal operation condition. Due to design considerations and

for maximum safety 20 cm thick beams and columns are provided and slab of 20cm

thick was provided.10 mm mild steels are used for beam construction and they are

arranged with a spacing of 20 cm c/c. 10 mm mild steels are used for column

construction and they are arranged with a spacing of 15 cm c/c. The double mesh

method was used for slabs to withstand the water pressure. Stirrups of 8 mm thick

were provided for both beams and columns and are arranged with a spacing of 18 cm

c/c.

6.1.2 Concrete Slab

After the beam and column construction the slabs of pool dimension were

casted. In concrete construction of our site, a form was typically created using

plywood in the desired shape of the pool. The pool floor was poured first and the

walls are constructed on top of the floor, around a steel reinforcing web. The cavities

in the forms are filled with a high density concrete specifically designed and mixed

for pool construction. For our project M35 cast in-situ mix concrete were used. A

Page 43: report draft

43

vibrating tool was utilized to fill any cavities and honeycomb voids and to make sure

that the steel reinforcing is completely encapsulated. Once the forms are removed and

the concrete is allowed to cure for a specified length of time, the pool can be tiled or

finished using another method.

6.2 FINISHINGS

The finishing work for swimming pools at Pe-Co-C is not yet started, but it was

scheduled to start after the work of restaurant. But some of the design and construction

features for final finish of swimming pool are planned at Pe-Co-C are given below.

6.2.1 Tile Selection

Tile and stone in swimming pools, fountains, spas, and water features is a very

appealing way to provide beauty and functionality. There are many types of tile and

stone in the world, but not all of them are suitable or functional in a submerged

installation. Choosing a tile or stone that is suitable for submerged applications is

critical to the long-term performance of the installation. Generally speaking, tile or

stone used in submerged installations must have a low absorption rate, a high

coefficient of friction, be freeze/thaw resistant (in cool climates), resistant to moisture

expansion, and chemical resistant.

6.2.2 Plumbing

Water in a swimming pool needs to circulate through a filtering system to

remove dirt and debris, and to evenly distribute the pool chemicals. For in ground

pools, fountains and water features most of the plumbing for the pool drains, pump

system and filters have to be installed prior to the pouring or spraying of the concrete.

The main drains are usually located in the lowest point of the pool, so the entire

contents of the pool will flow to the drains. The drain is tied into the pump system for

easy draining or fast circulation of the water in the pool.

6.2.3 Lights and Electrical

Like the plumbing, the lighting and electrical installation must be done prior to

the concreting. In our training site, swimming pool was constructed with underwater

lights. Five light fittings are provided on both long sides of the pool. These lights are

Page 44: report draft

44

essentially used so swimmers can see what they are doing at night and, to a lesser

extent, for aesthetic appeal. An incandescent light is sealed into a watertight fixture

which is located in a niche in the pool shell. The electric wire runs into the fixture

through a special seal which is designed to keep water away from the electrical

elements. Fiber optics is becoming more and more popular in pools because they do

not have to be embedded within the pool structure. Electrical work done in pools

before this time may be of sub-standard quality. Modern light fixtures are designed to

last for decades; however, poor water chemistry can weaken or degrade the fixture,

gasket and fasteners which hold it together. Failure to inspect these fixtures and

replace as necessary could result in costly damage to pool users or property.

6.2.4 Water Treatment

The presentation of a generally clean and tidy swimming pool is one reason

for following an appropriate cleaning programmed. However, good hygiene is also

most important to minimize the presence of harmful bacteria and other substances

which might pollute the water. Following are the major facilities planned in Pe-Co-C

for water treatment and disinfection.

The pool water disinfected with chlorine, bromine or by an ultraviolet light plus

hydrogen peroxide system.

The pH, total alkalinity, pool water turnover rate and cyanuric acid concentration

maintained.

The pool is to have a filtration system that provides a continuous circulation of

the pool water through the filter.

All water in the pool must pass through the filter as often as necessary to ensure

that the water is maintained in a clean and clear condition and in any event a

volume equivalent to the total volume of the pool at least.

Once in every six hours the swimming pool must be fitted with automatic dosing

and monitoring equipment that continuously analyses and controls the pH and

disinfectant levels in the pool water within the ranges.

The pool water clarity will be maintained as specified Standard.

Page 45: report draft

45

7. CONSTRUCTION OF BRIDGE

AT MUKKAMKADAVU

The long time wait of the civic society around the Mukkam region of Kozhikkode

district had ended up in the design of a complicated T- shaped bridge across the

Iruvanhippuzha River, near Mukkam. The special shaped bridge is first of its kind in Kerala,

which made it easier for the residents of Koodaranhi and Kodiyathoor regions to connect with

the Mukkam side, without being much affected by the higher rising flood at the region.

Designed by N.M.Salim associates and constructed by ULCCS Ltd., the bridge also is to have

a magnificent appearance. It provides a 11m roadway including footpaths, for the public.

Under the guidance of Mr. Miqdad N V and Mr. Akhil, This Bridge at Mukkamkadavu was

our industrial training site on Oct.4th 2013.

7.1 Architectural view of Mukkamkadavu Bridge

Approach roads supported by Reinforced earth wall were also a part of the project.

Due to their steep gradient the RE wall formation is only provided only for two shores. The

RE wall details were described by Mr. Riyas. The main structural portions of this particular T

Bridge was three arms and a central circle.

Page 46: report draft

46

7.1 STRUCTURAL DETAILS OF BRIDGE

7.1.1 Basic Components of Bridge

The component of the bridge is broadly grouped into

Foundation

Substructure

Superstructure

The foundation is different type viz., open foundation, well foundation, raft

foundation and pile foundation. The Mukkamkadavu Bridge was provided with pile

foundation. The substructure is the portion of the bridge structure such as pier and

abutments above the foundation unit and supporting the superstructure. It shall also

include returns and wing walls but exclude bearings. Superstructure is the portion of

bridge structure above the substructure level viz., deck slab/beam, hand rail, foot path

etc.

7.1.2 Standard definition

Clearance: Is the shortest distance between the boundaries at a specified

position of a bridge.

Free Board: Free board at any point is the difference between the highest

flood level after allowing for afflux if any, and the formation level of road

embankment on the approaches or top level of guide bunds at that point. Free

Board for high-level bridge shall in no case be less than 600 mm.

Linear Water way: is the width of waterway between the extreme edges of

water surface at the highest flood level measured at right angles to the

abutment faces.

Effective Linear Water way: is the total width of the waterway of the bridge

at HFL minus the effective width of obstruction.

Afflux: The rise in flood level of the river immediately on the upstream of the

bridge as a result of obstruction to the natural flow caused by the construction

of bridge and its approaches.

Page 47: report draft

47

Scour Depth: In natural stream, the scouring action of the current is not

uniform all along the bed width particularly at the bends and also round

obstructions to the flow eg. The piers of bridges there is deeper scour than

normal. The assessment of the scour depth is relevant for the design of bridge

foundations and protective works. Whenever possible such assessment should

be based on data made available from actual sounding taken at the proposed

bridge site or in its vicinity. Such soundings are being taken during

immediately after a flood before the scour holes have had time to silt up

appreciably. Necessary allowance shall be made in the observed scour depth

for increased depth for various reasons.

Vertical clearance: Adequate vertical clearance shall be provided in case of

all high level bridges which is usually the height from the designed HFL with

afflux to the lowest point of the bridge superstructure.

7.1.3 Components of Bridge

Fig.7.2 Super structures of Bridge pier

Page 48: report draft

48

7.1.3.1 Piles and Pile cap

The piles and pile caps constructed for this bridge were cast-insitu type.

Boring for the piles was done by Direct Mud Circulation (DMC) method. It was

ensured that the soil is capable of safely withstanding the whole mechanical

arrangements required for this method of boring. In soft soils, a permanent liner has to

be provided so as to withstand any scouring of side walls. Even though the soil here

wasn’t that soft, a permanent liner, made of 6mm thick M.S.Sheets were provided. It

was also ensured that the rigs had the capacity of boring up to the required depth.

Piling were done up to the hard strata and 50 cm more is digged to it. The average pile

depth in the site was 15 m. Total 4 piles were provided as foundation for each pier and

abutments, and each four piles were connected with a 1.5 m thick pile cap. The piles

and pile capes were casted in M35 grade concrete with OPC of 43 grades. The setting

time of concrete is having very importance in the bridge pile construction so a special

type admixture called Visconcrete were used while patching and casting, and it will

helps in controlling the setting time of concrete. The diameter of the piles for the

circle portion was of 1m and for the other parts were 0.9 m. The pile and pile cap

details were shown in fig.7.4 and 7.5.

Fig.7.3 Pile and Pile cap under Pier

Page 49: report draft

49

7.1.3.2 Piers and Abutments

Fig.7.6 Alignment of Piers and Abutments

A total of ten numbers of piers were constructed for the whole bridge. And

three numbers of abutments were located at three ends of bridge. The layout of piers

and were shown in Fig.7.6. The piers and abutments are cast in situ RCC M35 grade

concrete. The concrete was pumped to the mould by using machines, for the fast

construction. The piers and abutments were having 1.5 m diameter. The length of

each pier and abutment were different at due to the terrain undulations. The pier

length was large for the circular portion while it was small for piers near to shore area.

The cement used for the concrete preparation was OPC of 43 grades.

Fig.7.7 Piers of circular portion of bridge

Page 50: report draft

50

7.2 CONSTRUCTION OF RE WALL

Reinforced Earth is a composite material formed by the association of a frictional soil

and reinforcement strips. In concept, it is like reinforcing concrete; that is, it is an economical

means of improving the mechanical properties of a basic material, earth, by reinforcing that

material with another, steel. Stresses produced within the soil mass are resisted by the strips.

The stresses are transferred to the strips by friction. A Reinforced Earth structure constructed

using this material is shown as the “reinforced volume” in figure 1 below. Concrete facing

panels are used at the face of the reinforced volume to prevent erosion of the backfill and to

provide an attractive, finished appearance. The reinforced earth wall construction was one of

the main features of Mukkam Kadavu Bridge. The RE walls were provided at the starting of

arm1 and arm 2, for arm 3 the RR masonry is provided. The major parts of a RE wall

construction is, facia panels, geogrids and soil for backfilling. The RE wall panel of single

unit had about 980 kg of weight, and a face area of 2.1 m2.

7.2.1 Facia Panel

Fig.7.8 Facia Panels arranged for initial setting

Placing of mould in casting area should be on a leveled and well-compacted

surface. A layer of Brick bat/ GSB (100mm) and cement concrete (75mm0 shall cover

the entire casting and curing area. Proper drainage arrangement shall be made to avoid

stagnation of water at any location; arrangement can be made to collect drain water

Page 51: report draft

51

and its reuse for the curing purpose. Mould shall be placed at a higher level for the

ease of work, Base plate of mould shall be evenly supported on a leveled firm

concrete base.

The concrete received from the batching plant were tested for field test, ideal

slump of concrete (considering a batch of 6 m3) is 30-40 mm, and in no case it shall

exceed to 60 mm. Mould was poured with concrete in 1-2 layers. Each layer were

compacted with a needle vibrator of 40 mm, additional tamping may be provided to

release entrapped air.M35 grade concrete were used for the making of facia panels.

De-molding of panel can be started after 4-5 hrs of casting depending up on

the ambient temperature/ humidity, amount of plasticizer etc. Remolding shall

carefully be watched to avoid any damage to corners of panel. If any crack is

appeared at the rear surface due to de-molding, shutter should be re-fixed

immediately, as crakes have a tendency to open up during which will result in

permanent rejection.

After panel casting, curing shall start as soon as possible. At the time when

panels are in casting area it shall be covered with canvas or plastic sheet, Hessia cloth

was recommended.

Panel can be lifted from the casting bed after 15-20 hrs.of casting, at the time of

lifting concrete should have attained at least 33% of its characteristics strength. The

panels shall be lifted from four points. The panels require minimum 14 days curing

before they can be erected at site. Curing time shifting of panels should be avoided.

Panel can be dispatched to site as soon as the curing period of panels is over.

A close coordination is required between site and casting yard to ensure that panels

are shifted to site are as per the erection program. Transportation can be made through

low bed trailer/ tipper/ truck etc. stability of individual panels must be ensuring before

sending any lot. First row of panels shall be stacked over the wooden sleepers and rest

of the rows to be placed over the wooden cube of 120x120x120. Not more than five

no. Of panel shall be put in one stack.

Page 52: report draft

52

7.2.2 Geogrid

There are mainly three type of geogrids are commonly available 80 kN, 60

kN, 40 kN. The first type geogrids were used at the bottom of RE wall, the geogrid

reinforcement is to be placed as per design and length of the project. The length of

reinforcement of geogrid to be laid can be ensure by snapping a line parallel to the

facia at a distance of reinforcement length from the back face of the facia panel. The

geogrid reinforcement should be laid perpendicular to the panel facia and wrapped

around the connector bars which are passed through the tie rods. The adjacent geogrid

should be placed butting each other.

7.9 The Geogrid used at Mukkamkadavu Bridge for RE wall formation.

Geogrid reinforcement should be properly tensioned and care should be taken

to ensure that there is no slack in reinforcement before placing of fill. If required the

geogrid can be nailed to the compacted fill prior to placement of succeeding layer of

fill material. The fill material placed over the geogrid should be spread in the

direction parallel to the facia panel. It should be ensured that no heavy machinery/

vehicle is allowed to move directly over the geogrid. The bed prepared to receive the

geogrid reinforcement should be properly leveled and have an even surface. The use

of cut pieces along the length is not permitted.

Page 53: report draft

53

8. ROAD WORK AT TIRUR

The construction work on coastal corridor linking vallarpadam with kozhikode is

started on March 2013. The corridor is expected to bring about tremendous development to

the coastal belt. The total project estimated to cost 2000 crore. It would lift the coastal area

between Kochi and Kozhikode to new level of development. The industrial, commercial, and

tourism development of Ernakulam, Thrissur, Malappuram and Kozhikkode district will

depend a great deal on the new corridor passing through the coast.

The first phase of the project “Strengthening, Widening and Extension of Tippu

Sulthan road” was our training site on Oct.5th 2013, under the guidance of Mr. Anuraj and

Mr. Naveen. The 4.5 km length road work had a total estimated cost of 17.75 crore, work

begun on March 21st 2013 and were planned to complete in one year.

Fig.8.1 Strengthening, Widening and Extension of Tippu Sultan Road, Tirur

Page 54: report draft

54

Road Construction activity in India has undergone significant changes over the last

one decade owing to the huge investments made and due to the adoption of state‐of‐the‐art

construction technology and design principles. Various types of bituminous binders and

several stabilizers are now available. The bituminous paving mixes as specified in MORTH

“Specifications for Road and Bridge Works”, Fourth Revision, 200128 are commonly used in

India. Some of these mixes have evolved since 1960s, an era when the present day hot mix

asphalt plants were not common and mixes were produced with small portable mixing plants

with limited aggregate heating, blending and mixing capabilities. The proliferation of

bituminous paving mixes as specified in the MORTH publication basically manifest the

constraints of non-availability of modern hot-mix plant besides likely cost reduction of lean

bituminous mixes.

It is well known that roads are generally constructed in embankment which comes in

the way of natural flow of storm water (from existing drainage channels). As, such flow

cannot be obstructed and some kind of cross drainage works are required to be provided to

allow water to pass across the embankment. There are numbers of cross drainage works are

practiced in India in pavement works, but box culverts are not common in those. One of the

interesting fact for us to work at Tirur was the use of box culverts as cross drainage, and it

were first time in Malabar region.

Box culvert has many advantages compared to other drainage works. The box is

structurally strong, stable and safe and easy to construct. The main advantage is, it can be

placed at any elevation within the embankment with varying cushion which is not possible

for other type of culverts. It does not require separate elaborate foundation and can be placed

on soft soil by providing suitable base slab projection to reduce base pressure within the safe

bearing capacity of foundation soil.

The design specifications for the flexible road, Tippu Sulthan were based on the

current Indian Roads Congress Specifications and recommended codes of practice, and

ministry of Roads Transport and highways as per IRC specifications.

Page 55: report draft

55

8.1 CONSTRUCTION OF PAVEMENT

Structural strength is the primary purpose of most bituminous mixes except those used

in very thin surfacing. The objective is to disperse appropriately the dynamic and static

effects of traffic wheel loads to the underlying pavement layers such as bituminous/crushed

stone base course. For low volume roads only a granular base and a bituminous wearing

course may suffice based on structural requirements. Normally, lower layers of base courses

including those of bituminous base courses (as provided in developed countries) should have

desired stiffness characteristics to act as good foundation, which should be effective in

dispersing the traffic loads to the lower layers. The top layers of bituminous binder courses

should have adequate stiffness to resist rutting coupled with the flexibility to be effective in

re-bounding. The flexibility characteristics should, therefore, increase when going from

bottom to upwards layer. The Tippu Sulthan road was a BMBC, Flexible road. The road

constructed were possessed the following layers, from bottom to top, sub grade, sub base, wet

mix macadam layer, dense grade bituminous macadam, bituminous concrete, bituminous

macadam. The details of development of these structural layers are explained below.

Strengthening, Widening and Extension of the Tippu sulthan road were done

simultaneously. The existing road had a width of 10 m, additional width of 5 m were

widened. For this purpose a suitable trench of required depth and 5 m width was excavated

along the side of existing road. At the location of bus bay the 5 m width is scaled in to 7-8 m

for the future construction of bus stops. After the trench formation the bottom surface soil

inside the trench was loosened, watered and compacted for about 15 cm depth. The

compaction was done by roller.

Fig.8.2 Widening of Tippu Sulthan road, Tirur

Page 56: report draft

56

8.1.1 Subgrade

Because of the presents of Arabian Sea at near, the natural earth surface at

Tirur was covered by sand, and no soil is found out during the widening and

excavation process. Due to this reason a layer of soil sub grade had provided for more

strength and stability. Hence a 30 cm layer of red sandy soil is applied in two layers,

with a 20 cm maximum layer thickness.

Fig.8.3 Red soil layer as Sub grade, Tippu Sultan Road

8.1.2 GSB (Granular Sub Base)

Fig.8.4 Applying GSB Layer over Subgrade, Tirur

Page 57: report draft

57

Sub bases serve a variety of purposes, including reducing the stress applied to

the sub grade and providing drainage for the pavement structure. The granular sub

base acts as a load-bearing layer, and strengthens the pavement structure directly

below the pavement surface, providing drainage for the pavement structure on the

lowest layer of the pavement system. However, it is critical to note that the sub base

layer will not compensate for a weak sub grade. Sub grades with a CBR of at least 10

should provide adequate support for the sub base.

As the granular sub base provides both bearing strength and drainage for the

pavement structure, proper size, grading, shape, and durability are important attributes

to the overall performance of the pavement structure. Granular sub base aggregates

consist of durable particles of crushed stone or gravel capable of withstanding the

effects of handling, spreading, and compacting without generation of deleterious

fines.

The GSB layer provided for Tippu Sulthan road had a thickness of 30 cm after

compaction, and this thickness is applied in 2 layers of GSB, the maximum layer

thickness were limited to 20 cm. The spreading and compaction of GSB were carried

out by Aggregate grader and Road rollers.

8.1.3 WMM (Wet Mix Macadam)

Wet mix macadam construction is an improvement over the conventional

water bound macadam providing speedy and more durable construction. It differs

from the water bound macadam in that graded aggregates and granular materials are

mixed with predetermined quantity of water in accordance with the specifications to

form dense mass which is spread and wiled to approved lines, grades and cross-

section to serve as pavement courses.

The thickness of single compacted wet mix macadam layer was limited to 15

cm. And a WMM layer of thickness 25 cm is provided for the 5 m wide road.

After construction of the top WMM layer immediate sealing with bituminous

surfacing is done at site.

Page 58: report draft

58

8.1.4 DBM (Dense Graded Bituminous Macadam)

The dense graded bituminous macadam was applied on the top of WMM, with

a thickness of 15 cm after compaction of road rollers. At Tirur, This was applied in 2

layer thickness of single layer were fixed to be 7.5 cm.

The bitumen for DBM shall comply with the Indian Standard Specifications

for viscosity graded bitumen, IS: 73 modified bitumen complying with IS: 15462 or

as otherwise specified in the Contract. Guideline for selection of viscosity graded

bitumen and modified bitumen is in table 7.1 and table 7.2 respectively. The use of

modified bitumen is recommended for very heavy traffic roads in very hot climate.

Table 8.1 Guideline for selection of viscosity graded (VG) Paving bitumen’s

Based on Climatic Conditions.

Highest Daily Mean Air Temperature, oc

Lowest Daily Mean

Air Temperature, oc

Less than 20 oc 20 to 30 oc More than 30 oc

More than -10 oc VG-10 VG-20 VG30

-10 oc or lower VG-10 VG-10 VG-20

Table 8.2 Selection Guideline for Grade of Modified Bitumen

Lowest Daily Mean Highest Daily Mean Air Temperature, oc

Air Temperature, oc Less than 20 oc 20 to 30 oc More than 30 oc

Grade Of Modified Bitumen

More than -10 oc PMB/NRMB 120

CRMB 50

PMB/NRMB 70

CRMB 55

PMB/NRMB 40

CRMB 60

-10 oc or lower PMB/NRMB 40

CRMB 50

PMB/NRMB 120

CRMB 55

PMB/NRMB 70

CRMB 50

PMB = Polymer modified bitumen

NRMB = Natural rubber modified bitumen

CRMB = Crumb rubber modified bitumen

Page 59: report draft

59

The dense flexible macadam (DBM) is specified for use as a base course

and/or binder course. The Coarse aggregate used for DMB were consist of clean

crushed rock, crushed gravel or other hard material retained on 2.36 mm sieve. For

the existing road the DBM of 7.5 cm thick is applied, at this level the newly

constructed road as well as the existing road where been in same level.

8.1.5 BM (Bituminous Macadam)

Bituminous Macadam (BM) is an open graded, permeable, and recipe type

mix produced without any quality control on its volumetric or strength (stability). The

primary problem with the BM mix is that being very open graded, it is highly

permeable and therefore will trap moisture or water. BM and SDBC were developed

several years ago, when conventional hot mix plants were not common. At that time,

hot mixing was done in small portable plants or concrete mixers in which much fine

aggregate could not be used due to limitations of the available heating and mixing

equipment. Now, good hot mix plants are normally available.

For Bituminous Macadam, the bitumen content for premix should be 3 to 3.5

per cent by weight of total mix except otherwise directed. The composition of

Bituminous Macadam should conform to IRC Specifications. The manufacturing and

rolling temperature limited to 155-170 oc. In our training site BM is applied with a

average thickness of 10 cm.

8.1.6 BC (Bituminous Concrete)

Above the 15 m wide road a BC layer of 4 cm thick is provided, because

bituminous macadam is a highly permeable mix and promotes rutting. Use of

Bituminous Macadam a very popular mix at present may be deleted and substituted

with DBM because it is finally cost effective and better performing. Similarly, use of

Semi-dense Bituminous Concrete is also not considered to be allowed in the

specifications. It suffers from “pessimum” voids, which have potential to trap water

resulting in moisture damage. It should be substituted by Bituminous Concrete as it is

better performing and cost effective. It is estimated that after finishing the complete

road work the height of the road may rise 19 cm from the initial road level.

Page 60: report draft

60

8.2 CONSTRUCTION OF CROSS DRAINAGE WORKS

It is essential that adequate provision is made for road drainage to ensure that a road

pavement performs satisfactorily. The main functions of a road drainage system are:

To prevent flooding of the road and ponding on the road surface

To protect the bearing capacity of the pavement and the sub grade material

To avoid the erosion of side slopes

Road surface drainage is done by kerbs and gullies are commonly used in urban areas

and in rural embankment conditions. Surface water flows over the pavement to a kerb at the

edge of the road and is collected in gullies which are connected to longitudinal carrier drains

set within the road verge. The carrier drain may be a sealed pipe for the collection of surface

water only (separate system), or a perforated or open jointed pipe may be used in order to

convey both surface water and subsoil water to the outfall (combined system). For the

removal of rain water from the road surface a camber of 2.5 cm vertical to every 1m

horizontal is provide for Tippu Sulthan Road. If this collected water has to be transferred

from one side of the road to another, suitable cross drainage work has to be provided.

8.2.1 Pre-cast Box Culverts

In the construction of new roads it is frequently necessary to culvert existing

watercourses passing across the line of the roadway. The most common materials

used for new culverts include concrete pipes, concrete box sections, and corrugated

steel pipes and arches. Materials used for older culverts include brick, masonry and

cast iron. At our training site Pre-cast Box culverts units were used. Total of 12

culverts were needs to provide for the t 4.5 km road, two of them were for convey

cables and 10 Nos. for drainage. The cable duct had inside size of 0.75m X 0.75m and

for the drainage 1m x 1m standard boxes were used. For the complete crossing of a

single culvert, about 16 pre-cast units of box culverts were required.

Page 61: report draft

61

Fig.8.6 Pre-cast Box Culvert Construction, Tippu Sulthan Road, Tirur.

Pre-cast construction means that traffic may use the installation immediately

after placing and backfilling whereas in-situ construction will require a period for

curing prior to stripping forms ready for use. Due to their ability to tolerate heavy

wheel loads even with no overfill in place, precast box culverts are superior to most

alternative systems which require compacted overfill in place before loading is

applied.

Fig.8.7 Pre-cast Box Culvert Units Tippu Sulthan Road, Tirur.

Page 62: report draft

62

Box culverts are normally designed for the standard highway vehicle loads or

railway load requirements bridge design code, as appropriate for the application.

However they can also be used in many non-standard applications and can be

designed to carry loads well in excess of normal highway loading. It is important to

note that construction considerations on site may require that heavy equipment must

travel over box culverts before soil cover is placed. This can result in loading

conditions more severe than those expected in service.

8.2.1.1 Design and Detailing

Box culverts are generally designed and detailed in accordance with the Box

Culvert Association Standard Specification which covers materials, manufacturing

tolerances, external loading design and detailing standards. Box culverts carrying

highway loading or railway loading are designed to current standards and

specification as stipulated by the client. For the construction of Tippu Sulthan road the

concrete used for the construction of each single units of box culverts was RCC of

grade M35 in 1:1.5:2.79 mix ratio. 1m x 1m box culverts had a weight near to 2.5

tonnes. The reinforcement details of the culvert have shown in fig.

8.2.1.2 Surface loading and Fill depth

Loading applied at the ground surface and weight of fill material produce a

combination of vertical and horizontal forces on the box culvert. Surface loading may

be specified as a standard loading type, equivalent uniform loading or individual

wheel loads. The critical load on a culvert can occur at minimum or maximum fill.

Each enquiry for a culvert should state the minimum and maximum fill depth and the

amount or type of surface loading. It is recommended that the minimum fill depth

should be not less than 200mm or one fifteenth of the internal width of the culvert if

this is greater.

8.2.1.3 Bedding, Laying and Backfilling

Excavation can be kept to a minimum with only nominal working space

required on each side of the box culvert. When working in trenches the normal

Page 63: report draft

63

requirements for health and safety must always be observed. The base of the trench

should be uniformly prepared before laying a 200mm bedding of compacted granular

material over the full width of the trench. A surface blinding of the fine material will

assist levelling. Local packing’s are subject to settlement and should not be used. As

an alternative to granular bedding a concrete blinding layer is sometimes preferred to

protect the formation or to allow a faster rate of laying the culverts. A layer of

unreinforced concrete approximately 75mm thick on a trench bottom which has been

well prepared to provide a uniform support is generally sufficient. . In our training site

before placing these culvert units a layer 20 cm, PCC of grade M15 were provided for

making a leveled hard bed surface. A culvert line is usually laid directly on the

bedding starting from the downstream end with the sockets facing upstream, to

receive the next culvert. The trench should be backfilled as soon as possible after the

culvert has been laid and it should be filled evenly on each side of the trench.

Backfilling should continue in 200mm compacted layers to reach the required depth

of cover.

8.2.1.4 Jointing

The boxes were constructed with an inward edge grip of 10 cm for the

interlocking of one box to another. The culvert sections generally have rebated joints

and can be laid open, or sealed using pre formed strips and/or pointing materials.

Reference should be made to the jointing material manufacturer’s specification and

recommendation for use of the product. A system using preformed strip within the

joint is most commonly used. When the strip is bitumen based the joint faces should

be cleaned, primed and allowed to dry. The strip is then applied to the internal corner

of the socket just before the culvert is laid in the trench. Joints are closed to a nominal

gap by pulling against previously laid culverts with an applied load of approximately

one tonne per metre of strip plus about half of the weight of the culvert unit to

overcome base friction, less if the unit is suspended from the crane whilst jointing.

Heat may be required to soften the strip when working at low temperature. When the

box culvert is of sufficient size for access, it can be pointed internally with an

elastomeric or bitumen based material using a suitable primer. At Tirur while

construction the joints are bonded with “Nitrobond PC40”-Fosroc-epoxy. Not all

methods of jointing, however, should be expected to be completely watertight.

Page 64: report draft

64

8.3 CONSTRUCTION OF RETAINING WALL

The retaining walls are structures designed to restrain soil to unnatural slopes. They

are used to bound soils between two different elevations often in areas of terrain possessing

undesirable slopes or in areas where the landscape needs to be shaped severely and

engineered for more specific purpose like hillside farming or roadway overpasses. At our

training site the terrain were not been in proper level at all portions, due to these undulations

and slopes, a Random Rubble Retaining wall had provided at these portions of the road. The

details of the same is shown in fig.8.8 the specification for this particular RR Retaining wall

are as follows.

Weep holes using 50 mm dia. PVC pipe to be provided at one per sq.m. The entry

point of weep holes to be covered with nylon mesh tied with nylon rope to avoid entry

of silt.

One bond stone shall be provided for every 0.50 sqm. of the area of wall surface of

the random rubble and dry rubble.

All bond stones shall be marked suitably with paint, bond stones running right

through the thickness of the walls shall be provided in walls up to 60 cm thickness.

For wall thickness above 60 cm a set of two or more bond stones overlapping each

other by at least 15 cm shall be provided in a line from face of the wall to the bake.

Where bond stones of suitable length are not available precast cement concrete block

of 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm normal size)

of cross section not less than 400 sq.cm and length equal to the thickness of wall shall

be used in lie of bond.

Expansion joints to be provided at every 25 m.

Page 65: report draft

65

9. CONCLUSION

The Industrial training we had undergone at various construction sites gave us

awareness about the details of construction. The study of various proposed civil structures

like buildings, roads, bridges, swimming pools etc. were done. Different stages of

constructions, modern technologies and materials used etc. were observed. Structural design,

architectural design safety measures, electrical and plumbing works etc. were noteworthy.

The aesthetics and structural design were the best.