report

34
PROJECT REPORT AT MARUTI SUZUKI INDIA LIMITED (MSIL), GURGAON Submitted by: SWATI GOYAL 655/MP/08 Under the guidance of: MR.MOHIT CHANDNA L12 ASSEMBLY ENGINEERING PRODUCTION ENGINEERING MARUTI SUZUKI INDIA LIMITED GURGAON

Upload: rishabh-bansal

Post on 19-Dec-2014

42 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Report

PROJECT  REPORT  

 

AT  

MARUTI  SUZUKI  INDIA  LIMITED  (MSIL),    

GURGAON  

Submitted  by:  

SWATI  GOYAL  

655/MP/08  

Under  the  guidance  of:  

MR.MOHIT  CHANDNA  

L-­‐12  

ASSEMBLY  ENGINEERING  

PRODUCTION  ENGINEERING  

MARUTI  SUZUKI  INDIA  LIMITED  

GURGAON  

 

Page 2: Report

CONTENTS  

 

S.NO.   PROJECT  TITLE  

1   Production  engineering  and  assembly  engineering  

2   Process  study  for  ritz  trim  

3   Study  of  door  loading  and  unloading  manipulators.  

4   Comparison  of  assembly  line  1  and  assembly  shop  3.  

5   MOST  study  for  trim  area  of  new  model.  

6   Palette  design  for  Module  docking  of  ritz.  

 

 

 

 

 

 

PROJECT-­‐1  

Process  study  for  trim  area  for  ritz  

Page 3: Report

Trim    area  for  Ritz  contains  3  parts  Trim-­‐1,Trim-­‐2,  Trim-­‐3.  In  this  region,  I  was  allotted  to  carry  out  a  detailed  study  of  the  area  which  includes  Part  No  of  the  product  assembled  in  that  area,  Part  Name  of  the  product  assembled,  Quantity,  Sequence  in  which  they  are  assembled,  Jigs/Equipments  required  to  carry  out  the  operation,  Tools  used  in  that  station,  Consumables  consumed.  

 

 

At  this  station  many  components  are  being  attached,  for  example  the  sunvisor  assembly  is  fitted  using  a  battery  gun.  

Also  rear  view  mirror  assembly  is  being  attached  at  the  same  station.  

 

 

 

 

Project-­‐2  

Study  of  door  manipulators  

Page 4: Report

Door  unloading  

Door  manipulators  were  required  for  a  new  model  being  introduced  at    assembly  shop  3.  Four    manipulators,  two  each  for  front  and  rear  doors  were  to  be  installed.  Feasibility  for  4  models  alto,  swift,  zen  estilo,yl8  had  to  be  checked.  I  was  involved  in  the  trials  of  these  manipulators.      

 

     

 

 

 

 

 

 

 

 

 

 

 

Sequence  of  operation  

1.  Select  the  appropriate  model  selector  switch  on  the  manipulator  as  per  the  required  vehicle  on  the  Trim  conveyor.  2.  Move  the  manipulator  to  vehicle  flowing  on  main  conveyor.  3.  Align  the  manipulator  with  the  front  door  &  side  sill  of  vehicle.    4.  Press  the  clamp  button  to  activate  the  door  clamp.  Then  the  manipulator  starts  moving  in  synchro  with  the  vehicle.  5.  Press  the  load  balance  button.  6.  Loosen  the  door  hinge  bolts  with  pneumatic  gun  &  keep  the  bolts  in  the  hardware  box.  7.  Take  the  manipulator  out  of  the  vehicle  towards  the  door  transfer  conveyor.  8.  Align  the  door  on  the  manipulator  with  the  resting  jig  of  door  carrier  on  the  transfer  conveyor.      9.  Clamp  the  door  with  the  clamping  jig  of  the  door  carrier.  10.  Press  the  load  release  button.  11.  Repeat  all  the  above  steps  for  rear  door.    

FL=0  

The  flow  direction  

Vehicle  

Trim    

B:  Run  rail  

A:  Handling  device  

Worker  

C:  Control  device  Unloaded  Door  

Rail  mount  

 3000  

Page 5: Report

All  the  movements  to  be  done  by  operator.  The  same  sequence  is  to  be  followed  for  both  sides  (LH  &  RH).  

Presently  alto  is  being  manufactured  at  the  assembly  shop.  Yl8  which  had  to  be  introduced  was  a  large  vehicle  as  compared  to  yv4  ,  so  certain  features  were  modified  in  the  new  manipulators  to  ease  workers  in  unloading  heavy  doors.  

 

Existing  manipulators  

 

Modification  content  in  the  unloading  device:    

A) Handling  device  for  Unloading  a) Handling  device  was  modified  in  order  to  unload  the  new  doors  from  the  

vehicle  moving  of  the  Trim  conveyor  &  loads  it  into  the  door  carrier  at  the  side.  (For  LH  &  RH)    

b) Arm  moved  in  all  X,  Y  &  Z  axes  after  the  modification.  Range  of  Horizontal  movement  (rotation)  &  vertical  movement  (up  /  down)  could  be    regulated  by  the  operator.  

c) Complete  checking  of  the  existing  unloading  handling  device  for  takt  time  of  50  sec.  

d) Complete  gripper  &  down  tube  assembly  was  replaced  with  a  new  one.  e) Extra  load  balance  settings  was    installed  as  per  the  model  compatibility    

Page 6: Report

f) Extra  pneumatic  elements  (cylinder/valves,  etc)  were  considered  as  per  the  model  compatibility.  

g) Equipment  Up  /  down  direction  during  air  balance  moved  smoothly  without  any  jerk.  

h) The  gripper  was  designed  to  cater  to  all  profiles  of  front  &  rear  door.  i)  ‘V  ‘shape  section  of  door  receiving  jig  was  installed  so  that  door  does  not  fall  

from  door  lower  surface.  j) To  install  door  clamp  so  that  Door  does  not  tumble  from  handling  device.  

Clamping  of  the  door  was  such  that  door  could  be  clamped  by  jig  which  common  for  all  the  models  as  far  as  possible.    

k) Material  of  receiving  jig  &  door  clamp  was  Poly  Urethane  to  avoid  scratch  to  door.  

l) PU  material  of  door  clamp  had  notched  profile.    

 

 

 

 

 

 

 

m) Construction  was  done  considering  maintainability.    

 OPERATOR  CONTROLS      

                 Following  are  the  selector  Switches  in  door  unloading  

• CLAMP/  DECLAMP:    To  clamp  the  door  to  from  top  side  after  insertion  of  gripper  and  To  release  the  door  from  gripper.  

• HIGH/LOW:  High  for  balancing  of  manipulator  with  door  i.e.  component  and  Low  for  balancing  of  manipulator  without  door.  

• BRAKE  ON/OFF:  To  make  ON  and  OFF  brakes  of  swivel  movement  of  manipulator.  • Model  Selector  Switch:  This   is  a   two  position  selector   switch  &  required   for  balancing  of  door  

according  to  their  self  weight.    First  position  for  YV4  FR  &  YR9  FR  and  second  position  for  YG4  FR  /RR,YV4  RR  &  YR9  RR  

 

   

Receiving  jig  

Door  clamp  

Handle  

Door  

Mount  jig  for  inner  panel  

Mainframe  

Page 7: Report

Operation  sequence  using  operator  controls.  

• Position  lever  of  BRAKE  “ON/OFF”  selector  switch  at  “OFF”  to  make  brakes  off.  • Select  Model  selection  switch  according  to  front  door  model  to  be  handle  or  remove.  • Move  manipulator  from  parking  position  to  slat  conveyor.  

• Open  the  front  door  of  the  Vehicle.  • Locate  gripper   to   the   front  door  of  vehicle   i.e.   insert   “V”   jaw  of  gripper  below  bottom  side  of  

door.  • Select  lever  of  “CLAMP/DECLAMP”  selector  7switch  at  “CLAMP”  position  to  clamp  door.  • Remove  door  hinges  from  body  with  help  of  nut  runner  and  same  time  select  lever  of  “                HIGH/LOW”  selector  switch  at  “HIGH”  position  to  balance  manipulator  with  door.  • Separate  door  from  body  after  removing  both  hinges.  • Move  manipulator  along  with  the  gripper  &  door  towards  the  door  stacker  system.  • Place  &  locate  the  gripper  on  the  door  stacker  &  Select  lever  of  “CLAMP/DECLAMP”  selector  

                         switch  at  “DECLAMP”  position  to  declamp  door  from  gripper.    • Select   lever  of  “HIGH/LOW”  selector  switch  at  “LOW”  position  to  balance  manipulator  without  

door.  • Take  out  gripper  from  the  door  stacker  • Move  to  vehicle  conveyor  for  unloading  of  front  door.  • Select  Model  selection  switch  according  to  rear  door  model  to  be  handle  or  remove.  • pen  the  rear  door  Vehicle.  • Repeat  procedure  from  sr.  no-­‐  04  to  sr.  no  12  for  unloading  of  front  door.  • Continue  same  cycles  from  sr.  no.  -­‐  2  to  sr.  no.  -­‐  16  for  next  vehicles.    • Before  leaving  work,  park  manipulator  at  suitable  place  and  make  brake  lever  at  “ON”  position.  

   

 

 

 

 

 

 

LAYOUT  RAILS  

CARRIER  

Page 8: Report

   

 

     

 

 

Trial  report  

TRIM  LINE  

Page 9: Report

Trials  of  door  unloading  manipulators  were  carried  out  in  the  assembly  shop  itself.the  following  problems  occurred  

1. The  door  panel  face  butting  pad  required  modification  in  terms  of  spring  force  and  length,  which  was  changed  accordingly.  

 

2.  Problem  with  the  position  of  bottom  resting  rollers  for    alto  doors.  

3.  Tool  bin  was  replaced  with  removable  type.  

 

Face  butting  pad  

Bottom  rollers  

Page 10: Report

Door  loading  

Similar  to  door  unloading  manipulators,  door  loading  manipulators  were  also    required  for  the  new  model  being  introduced.  

Process  Flow  

・ The  door  sub  assembly  activity  of  all  the  models  was  to  be  done  offline.  ・ Doors  had  to  be  transferred  from  the  offline  sub  assembly  area  to  the  final  line  

stations  by  a  power  &  free  over  head  conveyor.  ・ The  doors  which  will  be  loaded  on  the  door  carriers  of  the  conveyor  will  be  

stopping  at  two  locations.  The  unloading  of  rear  &  front  doors  (LH  &  RH)  happen  in  these  locations.  

・ The  operator  will  select  the  appropriate  model  selector  switch  on  the  manipulator  as  per  the  required  vehicle  on  the  Final  conveyor.  

・ Once  the  carriers  stop,  operator  with  loading  device  will  approach  the  carriers,  which  are  in  stationary  condition  as  they  are  stopped  by  positive  stoppers  .Then  the  operator  maneuvers  the  handling  device  to  align  with  respect  to  the  carrier.  At  this  moment  the  bottom  roller  of  the  handling  device  would  position  itself  below  that  of  door  carrier.  

・ Then  the  operator  unclamps  the  assembled  door  from  the  carrier.  ・ The  operator  aligns  the  handling  device  &  actuates  the  clamping  mechanism  

on  the  handling  device.  The  rollers  provided  on  the  lower  most  part  of  handling  device  lift  up  &  touch  the  lower  surface  of  the  door  profile.  At  the  same  time  the  door  gets  clamped  by  downward  force  applied  by  the  door  clamp.    

・ The  operator  will  press  the  load  balance  button/toggle  switch.  ・ Once  the  door  gets  clamped  onto  the  manipulator,  the  operator  takes  the  

handling  device  away  from  the  carrier  &  moves  to  the  vehicle  moving  on  the  slat  conveyor.  The  operator  also  acknowledges  work  over  switch  of  sub  assembly  conveyor  so  that  the  empty  carrier  returns  back.  

・ After  operator  reaches  near  the  vehicle  on  slat  conveyor  he  aligns  the  handling  device  to  clamp  the  loading  device  on  to  the  side  sill  of  the  vehicle.  Then  handling  device  gets  clamped  onto  the  side  sill  of  the  front/rear  door  &  then  loading  device  moves  in  synchronization  with  the  main  conveyor  speed.  The  operator  sits  on  the  front/rear  seat  &  hinges  the  door  to  the  vehicle.  This  has  to  happen  under  following  constraints:  

・                    a)  The  open  stopper  angle  for  Front  &  rear  doors  are  to  be  adhered  as  specifications.    

・                  b)  Door  loading  angles  for  doors  also  to  be  adhered  as  per  specification    ・ The  operator  presses  the  load  release  button/toggle  switch  ・ The  operator  de-­‐clamps  the  handling  device  &  removes  it  away  from  the  

vehicle  zone  ・ This  complete  work  cycle  is  to  be  repeated  for  every  door  loading  operation.  ・ The  same  sequence  is  to  be  followed  for  both  sides  (LH  &  RH)  for  Front  &  Rear.    

Page 11: Report

 

   

Modification  content  in  the  loading  device:    

A) Handling  device  for  loading  a) Handling  device  was  modified  in  order  to  unload  the  new  doors  from  the  door  

carrier  at  the  side  (LH  &  RH)  &  load  it  into  the  vehicle  moving  of  the  Final  conveyor.    

b) Arm  moved  in  all  X,  Y  &  Z  axes  after  the  modification.  Range  of  Horizontal  movement  (rotation)  &  vertical  movement  (up  /  down)  can  be  regulated  by  the  operator.  

c) Complete  checking  of  the  existing  loading  handling  device  for  takt  time  of  50  sec.  

d) Complete  gripper  &  down  tube  assembly  was  replaced  with  a  new  one.    

e) Extra  load  balance  settings  were  installed  as  per  the  model  compatibility    f) Extra  pneumatic  elements  (cylinder/valves,  etc)  were  considered  as  per  the  

model  compatibility    g) Equipment  Up  /  down  direction  during  air  balance  moved  smoothly  without  

any  jerk.  h) The  gripper  was  designed  to  cater  to  all  profiles  of  front  &  rear  door.  i) The  rollers  provided  on  the  handling  device  on  which  the  door  rests  should  

had  “V”  sections  to  avoid  door  falling  from  the  trolley.  The  rollers  easily  rotated  about  their  axis.    

j) Door  clamp  was  installed  such  that  door  did  not  tumble  from  handling  device.  Clamping  of  the  door  was  such  that  door  could  be  clamped  by  jig  which  common  for  all  the  models  as  far  as  possible.    

k) Middle  locating  jig  was  self  adjusting  by  using  spring  type  adjusting  mechanism.  

l) Rollers,  face  of  the  door  clamp  which  will  be  mating  with  door  glass  panel,  jigs  used  for  locating  about  the  side  sill  &  synchronizing  the  handling  device  had  Poly  Urethane  surface  to  prevent  scratches  &  dents  on  the  vehicle.  

m) The  design  of  the  locating  jig  considered  both  the  open  stopper  angle  &  door  loading  angle.  

Page 12: Report

n) Height  adjustment  was  incorporated  in  the  handling  device  to  cope  up  any  requirement  while  loading  the  door.  

o) Synchronization  of  the  device  while  fitment  of  door  on  the  body  to  be  achieved  by  installing  mechanism  to  be  clamped  with  side  sill  of  the  moving  vehicle.  

p) PU  material  of  door  clamp  had  notched  profile.  q) The  actuation  of  pneumatic  device  was  not  jerky.  r) There  was  a  pressure  regulator  switch  installed  in  the  device  so  that  the  door  

clamping  force  could  be  varied.  s) Air  outlets  were  installed  on  the  gripper  at  two  points  for  air  tool.  t) There  should  be  model  selection  switch  to  activate  corresponding  door  

loading  angle.  u) Operating  handle  position  was  ergonomically  OK.  v) Aligning  jig  was  provided  to  locate  the  gripper  with  respect  to  door  carrier  

during  door  picking  operation.  w) Construction  was  done  considering  maintainability.    

 

 

 

 

 

 

 

 

 

 

 

 

OPERATOR  CONTROLS  

1.  Door  clamp:  This  lever  is  used  for  clamp  &  unclamp,  if  we  press  the  lever,  the  door  holder  clamp  move  down.  

2.  Body  clamp  on/off  :  to  clamp  the  manipulator  to  the  side  sill  of  the  car  ody  and  unclamp.  

Receiving  jig  

Door  clamp  

Handle  

Door  

Mount  jig  for  inner  panel  

Mainframe  

Page 13: Report

3.  HIGH/LOW:  High  for  balancing  of  manipulator  with  door   i.e.  component  and  Low  for  balancing  of  manipulator  without  door.  4.  BRAKE  ON/OFF:  To  make  ON  and  OFF  brakes  of  swivel  movement  of  manipulator.  5.   Model   Selector   Switch:   This   is   two   position   selector   switch   &   required   for  balancing  of  door  according  to  their  self  weight.    First  position  for  YV4  FR  &  YR9  FR  and  second  position  for  YG4  FR  /RR,  YV4  RR  &  YR9  RR.    6.  Angle  adjustment:  to  activate  door  loading  angle  for  alto  and  yl8    7.  Horizontal  movement  switches:  to  activate  movement  in  horizontal  direction.      8.  System  up/down  switch:  to  move  the  complete  setup  in  upper  or  lower  direction.                  Trial  report.  

   Yl8  front    

1. Top  clamp  position  was  changed.    

   

2. Problems  with  face  pad  shape  and  spring  force.  

3. Angle  setting  was  modified.  

4. Middle  carrier  mount  was  shifted  by  20  mm.  

Alto  front  

1. TL  butting  roller  fouled  with  instrument  panel.  The  bracket  was  then  modified  to  make  it  straight.  

Top  plate  clamp  

Page 14: Report

 

2. Gun  and  torque  wrench  fowling  with  TL  roller  bracket.  

Yl8  rear  

1. TL  roller  position  was  not  OK.  The  bracket  was  modified.  

 

2. Door  trim  interfering  with  TL  roller  bracket.  

3. Door  loading  angle  was  set  to  1  degree  42  minutes.  

YG  4  rear  

1. Interference  between  side  sill  butting  pad  mounting  plate  and  seat  rear.  

2. Difficulty  in  removal  of  manipulator  after  door  docking.  

TL  butting  roller.  

Fowling  of  door  trim.  

Page 15: Report

   

3. TL  position  mismatch.    Door  was  up  by  30-­‐35  mm.  mounting  of  body  clamp  was  changed  to  fit  exactly.  

 

                                           PROJECT-­‐3  

Mismatch  

Page 16: Report

             Comparing  assembly  line  1  and  line  3  

Assembly-­‐1  trim                                                                                                                  Assembly-­‐3  trim  

Door  is  not  removed  at  the  first  station.  Completely  assembly  of  car  takes  place  with  doors  attached.    

Door  manipulators  with  highly  advanced  features  such  as  horizontal  slide  and  angle  adjusters.  High  weight  handling  capacity  designed  for  heavier  models.  

Door  assembly  is  simultaneous.    

Door  assembly  is  separate  at  some  other  conveyor.  

There  is  a  gum  spraying  manipulator  for  the  roof  lining  of  car  and  omni.    

Roof  lining  is  supplied  by  the  vendor  and  applied  with  the  help  of  clips.  

i/p  subassembly  is  manual.  No  conveyors  are  involved.  Also  the  i/p  main  frame  is  fitted  before  directly  on  the  car  and  not  in  the  ip  sub  assembly  I/P  inserted  through  the  windshield  space.    Lock  set  Steering  component  and  heater  and  ac  unit  fitment  after  ip  fitment  Also  the  sub-­‐assembly  is  in  pieces  at  different  stations.  

Newly  installed  i/p  subassembly(u  shaped  layout),  with  larger  stations  to  accommodate    the  original  tact  time.  

No  primers  and  cemedine  for  windshield  and  other  glasses.  Only  weather  strip  is  used.  

Glass  manipulators  for  various  functions.  One  cleans  the  glass,  one  applies  the  primer  and  the  third  1  applies  cemedine.  Then  one  manipulator  inverts  the  glass,  to  aid  in  picking  and  placing  the  glass.  They  are  provided  with  vacuum  handles  too.  

No  manipulators  for  assistance  in  glass  fitment.  Everything  is  manual.  

 

The  assembly  shop  also  comprises  of  some  gravity  conveyors  for  transport  of  parts  from  one  station  to  another.  

Process  sequence  is  different,  head  lamps  are  not  fitted  in  the  trim  line.  

 

Head  lamps  fitted  in  the  trim  line  itself.  

I  D  plate  machine  is  manually  operated.    

ID  plate  automatic,  directly  connected  with  the  vehicle  tracking  system.  

Page 17: Report

       

Door  unloading  manipulators                                                                                                                newly  installed  i-­‐p  subassembly.  

 

 

 

Glass  manipulators.  

Page 18: Report

 

Assembly-­‐1  Chassis                                                                                                                              Assembly-­‐3  chassis  

Weight  fitment  on  the  underbody  system  using  manipulators.  Tool  trolleys  for  aiding  fitment.  

 

No  weight  fitments  in  newly  modeled  cars.  

No  sub  assembly  for  front  disc  brakes.    

Brakes  and  suspensions  for  the  front  tyres  assembled  in  a  subassembly.  Transported  to  the  right  side  by  underground  gravity  conveyors.  

Chain  lifts  for  rear  axle  lifting  and  subassembly.  Rear  axle  carriers  for  lifting  and  fitting.  The  rear  axle  subassembly  conveyor  is  semi  automated.  The  empty  conveyor  is  manually  pushed  back.  

New  rear  axle  conveyer  to  carry  the  rear  axle  along  the  line  and  support  the  operator  .rear  axle  lifter  from  NKC  India-­‐  one  main  lifter  and  one  compression  lifter  to  stimulate  the  condition  of  compressed  spring  .rear  axle  sub  assembly  is  fully  automatic  with  limit  switches  strategically  placed  to  work  without  help  from  the  operator  

Fuel  tank  fitment  manual.   fuel  tank  lifter  provided  to  reduce  operator  fatigue-­‐  fully  automatic  and  works  in  accordance  with  the  moving  conveyor.  

Engines  come  from  an  overhead  conveyor  after  being  tested  at  some  other  spot  in  the  shop.  Small  engine  subassembly  after  that,  moved  on  a  gravity  conveyor.  

advanced  engine  assembly  based  on  friction  conveyor  mechanism  .the  car  is  high  enough  and  the  operators  work  on  two  levels-­‐  underneath  the  car  and  beside  the  car-­‐  so  no  operator  fatigue  is  seen  .  engine  subassembly  and  testing  along  side  the  main  conveyor  and  engine  loaded  using  a  high  tech  merry  go  round  type  engine  docking  system  by  DAIFUKU  that  has  4  dollies  that  carry  the  engines  along  with  the  car  and  the  engine  docking  is  done  at  2  levels  -­‐  ground  level  and  the  over  head  level  

wheel  nut  tightning  is  using  hand  held  guns  and  hence  as  per  the  tact  time  only  4  nut  wheels  can  be  managed    

wheel  nut  fasteners  by  ATLAS  COCO,  employed  that  automatically  align  and  tighten  the  wheel  nuts-­‐  variable  number  of  nuts  can  be  tightened  depending  upon  the  type  of  car  -­‐  interchangeable  4  and  5  nut  fastener  

in  chasis  line  the  car  is  not  so  high  -­‐  so  the  operator  has  to  duck  down  to  fight  a  component  underneath  the  car-­‐  this  leads  to  operator  fatigue  

 

     

Page 19: Report

 Wheel  fastening  machine  used  in  assembly-­‐3  

 

Fuel  tank  lifter    

 rear  axle  lifter  

Page 20: Report

 

 

       Assembly  line  1  final  line                                                                                                Assembly  shop-­‐3  final  line    

All  seats  lifted  and  fitted  manually  without  the  use  of  manipulators.  The  seats  reach  the  station  in  the  vendor  trolleys  and  from  there  the  operator  picks  them  up  and  takes  them  to  the  car      

Specially  designed  seat  transporter  is  used  which  is  one  of  the  most  advanced  systems  used  in  the  assembly  shop  and  is  very  effective  in  providing  the  seats  at  the  correct  station.  Further  seat  loading  manipulator  is  used  that  decreases  operator  fatigue  and  helps  in  proper  picking  and  placement  of  the  seat  

Various  fluids  are  filled  in  using  a  system  that  lacks  accuracy  and  if  a  change  has  to  be  made-­‐  it  can  be  done  only  through  PLC  and  not  directly  using  GOT  (graphical  operation  terminal)  

Coolant  fuels  are  filled  using  much  more  advanced  system  that  gives  accurate  measure  and  can  be  changed  on  the  line  using  the  GOT  

Doors  are  assembled  on  the  line  itself  and  hence  no  door  loading  takes  place  

Doors  are  assembled  in  a  separate  sub  assembly  and  are  brought  to  the  final  line  using  a  chain  conveyor  that  has  a  new  improved  logic.  The  door  sub  assembly  helps  in  decreasing  the  tact  time  and  also  helps  in  making  the  fitment  of  bigger  parts  such  as  seats/ip  etc.  

 Brake  oil  leakage  checking  machine  which  presses  brake  pedal  and  checks  for  leaks.  

The  original  design  is  fool  proof,  therefore  requires  no  such  checking.  

  The  shop  consists  of  a  few  lower  pits  on  the  sides  to  help  them  in  inspecting  some  components.  

 

 

Seat  conveyors  

Page 21: Report

PROJECT-­‐4  

Most  Study  for  Trim  Area  of  New  Model  

MOST®    WORK  MEASUREMENT  TECHNIQUE  

WORK  MEASUREMENT:    

Work  measurement  has  an  important  place  in  productivity  improvement  since  the  early  part  of  twentieth  century.  The  philosophy  has  been  the  same  through  the  decades.  Productivity  can  be  maximised  only  when  there  exists  a  standard  method  of  accomplishing  a  task  and  the  time  to  perform  a  task  according  to  a  standard  method    can  be  measured.  

There  are  many  reasons  for  wanting  to  know  the  amount  of  time  a  particular  task  should  take  to  accomplish.   It  may  simply  be   for   reasons  of  curiosity.  But   realistically   it   is   for  any  of   three  reasons:   to  accomplish   planning,   determine   performance,   and   establish   costs.   Knowing   the   time   to  manufacture  and  assemble  various  parts  and/  or  components,  a  manager  could:    

Determine  the  total  labour  cost  of  the  product.  

Determine  the  number  of  production  workers  needed.  

Determine  the  number  of  machines  needed  

Determine  the  amount  of  and  delivery  times  for  material.  

Determine  the  overall  production  schedule.  

Determine  the  feasibility  of  entering  into  production  of  the  product.  

Set  production  goals.  

Follow  up  on  production:  Have  goals  been  achieved?  

Check  individual  or  departmental  efficiency.  

Know  the  actual  costs  of  production.  

Pay  by  results.  

 

CONCEPT  OF  ‘MOST’  WORK  MEASUREMENT  TECHNIQUE  :-­‐  

MOST   refers   to   Maynard   Operation   Sequence   Technique.It   is   a   system   to   measure   work;  

therefore   it   concentrates  on   the  movement  of  objects.   It  was  noticed   that   the  movements  of  objects  

Page 22: Report

follow  certain  consistently   repeating  patterns,   such  as   reach,  grasp,  move,  position  the  object,  etc.  To  

move  an  object  a   standard   sequence  of  events  occurs.  Consequently,   the  basic  pattern  of  an  object’s  

movement  is  described  by  a  universal  sequence  model  instead  of  random,  detailed  basic  motions.  

In  general,  objects  can  be  moved  in  only  two  ways;  either  they  are  picked  up  and  moved  freely  

through  space,  or  they  are  moved  while  maintaining  contact  with  another  surface.  For  example,  a  box  

can  be  picked  up  and  carried  from  one  end  of  a  workbench  to  another  or  it  can  be  pushed  across  the  top  

of  the  workbench.  

For   each   type   of   move,   a   different   sequence   of   events   occurs;   therefore,   a   separate   MOST  

activity   sequence   model   applies.   However,   the   use   of   tools   is   analysed   through   a   separate   activity  

sequence  model.  

Consequently,   three  MOST   activity   sequences   are   needed   for   describing  manual  work,   plus   a  

fourth  for  measuring  the  movements  of  objects  with  manual  cranes  :  

• The  General  Move  Sequence  (for  the  spatial  movement  of  an  object  freely  through  air).  

• The  Controlled  Move  Sequence  (for  the  movement  of  an  object  when   it  remains   in  contact  with  a  

surface  or  is  attached  to  another  object  during  the  movement  or  has  restriction  in  its  movement).  

• The  Tool  Use  Sequence  (for  the  usage  of  common  hand  tools).  

TIME  UNITS  :-­‐  

The  Time  Units  used  in  MOST  are  based  on  hours  and  parts  of  hours  called  Time  Measurement  

Units  (TMU).  The  following  conversion  table  is  provided  for  calculating  standard  times:    

           1  T.M.U=  1/28  OF  A  SECOND                      =  0.036      SEC  

=  0.0006  MIN  

=0.00001HOUR  

The  time  value  in  TMU  for  each  sequence  model  is  calculated  by  adding  the  index  numbers  and  

multiplying   the   sum   by   10.   It   is   then   converted   to   hours,  mins.   or   secs.   Total   time   for   the   complete  

MOST   analysis   is   arrived   at   by   adding   the   computed   sequence   times.   All   time   values   established   by  

MOST   reflect   the   activity   of   an   average   skilled   operator  working   at   an   average   performance   level   or  

normal  pace.  This  time  represents  pure  work  content  at  100%  performance  level.  

Page 23: Report

WHY  USE  MOST  FOR  MPS:-­‐  

It  is  faster  than  other  work    measurement  techniques.  

Easy  to  learn  and  understand,  it  is  workman-­‐friendly.  

It  can  be  applied  directly  from  memory.  

It  has  a  controlled  accuracy.  

Rating  factor  is  not  required.  

It  reduces  paper  work.    

The  time  can  be  calculated  in  advance.  

It  is  method  sensitive,  so  non-­‐value  added  activities  can  be  easily  detected.  

It  can  establish  work-­‐measurement  independently.  

It  is  consistent,  therefore,  more  acceptable  to  management,  engineers,  supervisors  and  workmen  

alike.  

It  is  universal  in  application.  

The  staff  required  is  less  than  other  methods  and  hence  economical.  

Thus,  MOST  will  help  you  to  reduce  costs  and  improve  productivity.  

 MOST  SYSTEMS  FAMILY  :-­‐                                                            

• Basic  MOST  -­‐  General  Operations  

• Mini    MOST  -­‐  Repetitive  Operations  

• Maxi    MOST  -­‐  Non  -­‐  Repetitive  Operation  

 

A.  Mini  MOST  :-­‐  

At   the   lowest   level,  Mini  MOST   provides   the  most   detailed   and   precise  methods   analysis.   In  

general,  this  level  of  detail  and  precision  is  required  to  analyze  any  operation  likely  to  be  repeated  more  

than  1500  times  per  week.  An  operation  in  this  category  may  range  from  2  to  10  seconds.  It  was  devised  

to   measure   highly   repetitive   and   short   cycle   operations.   There   are   only   sequence   models   i.e.   the  

General  and  the  Controlled  Move.  In  contrast  to  Basic  MOST,  the  index  value  total  for  a  sequence  model  

is  multiplied  by  1  and  converted  to  minutes  or  seconds.    

  Area  of  application  :  Light  press  shop  operations.,  manufacturing  of  PCB’s,  etc.  

B. Basic  MOST  :-­‐  

Page 24: Report

At   the   intermediate   level,   operations   that   are   likely   to   be   performed  more   than   150   but   less  

than  1500  times  per  week  should  be  analyzed  with  Basic  MOST.  An  operation  in  this  category  may  range  

from   a   few   seconds   to   10   minutes   in   length.   The   method   descriptions   that   result   from   Basic   MOST  

analysis  are  sufficiently  detailed  for  use  as  operator  descriptions.  Areas  of  application:  General  manual  

work.  

Basic  MOST    WORK    MEASUREMENT  TECHNIQUE  

ACTIVITY                                                                                    SEQUENCE  MODEL   SUB  –  ACTIVITIES  

GENERAL  MOVE   A  B  G  A  B  P  A   A-­‐ACTION  DISTANCE  

    B  –  BODY  MOTION  

    G  –  GAIN  CONTROL  

    P  –  PLACEMENT  

CONTROLLED    

MOVE  

A  B  G  M  X  I  A   M  –  MOVE  CONTROL  

  X  –  PROCESS  TIME  

    I  –  ALIGNMENT  

TOOL  USE   ABGABP  _  A  B  P  A   F  –  FASTEN  

    L  –  LOOSEN  

    C  –  CUT  

    S  –  SURFACE  TREAT  

    M  –  MEASURE  

    R  –  RECORD  

    T  –  THINK  

Sequence  models  comprising  the  Basic  MOST  technique.  

Page 25: Report

 

C.  Maxi  MOST  :-­‐  

At   the  highest   level,  Maxi  MOST   is  used   to  analyse  operations   that  are   likely   to  be  performed  

fewer  than  150  times  per  week.  An  operation  in  this  category  may  be  just  less  than  2  minutes  to  more  

than  several  hours  in  length.  Maxi  MOST  index  ranges  accommodate  the  wide  cycle  to  cycle  variations  

that  are  typical  in  such  work  such  as  set-­‐ups  or  heavy  assembly.    

Even   at   this   level,   the   method   descriptions   resulting   from  Maxi   MOST   are   very   practical   for  

instructional  purposes.  Maxi  MOST  uses   the  same   index  values  as  Basic  and  Mini  MOST.  However   the  

multiplier  here  is  100  instead  of  10  as  in  Basic  MOST  and  then  converted  as  required.  

Areas  of  application:  Maintenance  work,  ship  building,  rail  car  fabrication  etc.  

 

VERSATILITY  OF  MOST  :-­‐  

Because  MOST  is  a  universal  technique  with  applicability  to  any  kind  of  manual  work  situations  

for   which   the  method   can   be   described   explicitly,   it   can   be   used   in   both   traditional   and   ‘new’   work  

measurement   areas.   So   far,   MOST   has   been   used   most   extensively   in   the   metal   working   industry.  

Standards   based   on   MOST   are   now   in   use   for   the   manufacturing   of   products   and   components   in  

electronics,   automotive,   power   generating   and   packaging   as   well   as   ship   building   and   other   heavy  

industries.  

MOST  has  also  been  tested  and  found  ideally  suited  for  work  measurement  in  other  industries  

such  as  furniture  and  food,  and  for  non-­‐manufacturing  work  such  as  clerical  and  maintenance.  

 

BASIC  ‘  MOST’  SEQUENCE  MODELS:-­‐  

I. General  Move:  is  applicable  when  objects  are  moved  manually  from  one  location  to  another,  freely  

through  the  air.  To  consider  the  various  ways  in  which  a  General  Move  can  occur,  the  activity  sequence  

is  made  up  of  four  sub-­‐activities      

A  -­‐  Action  distance  

B  -­‐    Body  motion  

Page 26: Report

G  -­‐  Gain  control  

P  -­‐    Placement  

A  fully  indexed  General  Move  Sequence,  for  example,  might  appear  as  follows:  -­‐  

             A6                B6            G1          A3            B3            P3          A3  

Where:  A6    =  Walk  three  to  four  steps  to  object  location.  

B6    =  Bend  and  rise.  

G1    =  Gain  control  of  one  light  object.  

A1  =  Walk  one  to  two  steps  to  object  destination.  

B0    =  Partial  Bending  (50%  occ.).  

P3    =  Place  and  adjust  object.  

A3    =  Return  back.  

This  example  could,  for  instance  represent  the  following  activity:  Walk  3  steps  to  pick  up  a  box  

from  floor  level,  walk  two  steps  and  place  the  box  on  the  rack.  

Page 27: Report

GENERAL MOVE SEQUENCE MODEL: ILLUSTRATION

AB PBAGA

A: ACTIONDISTANCETO OBJECT

B: BODYMOTION

G: GAINCONTROLOF OBJECT

A: ACTIONDISTANCE TODESTINATION

A A: ACTIONDISTANCE

B: BODYMOTION

P:PLACEOBJECT

General  

Move  is  by  far  the  most  frequently  used  of  the  three  sequence  models.  Roughly  50%  of  all  manual  work  

occurs  as  a  General  Move,  with  the  percentage  running  higher  for  assembly  and  material  handling  and  

lower  for  machine  shop  operations.  

 

II. Controlled  Move  :    

This  sequence  is  used  to  cover  such  activities  as  operating  a  lever  or  crank,  activating  a  button  or  

switch,   or   simply   sliding   an  object   over   a   surface.   In   addition   to   the  A,  B   and  G  parameters   from   the  

General   Move   Sequence,   the   sequence   model   for   a   controlled   move   contains   the   following   sub-­‐

activities:    

                                               M                                                    X                                                    I  

                       Move  controlled              Process  time                        Align  

 The  sequence  model  for  this  activity  might  be  indexed  as  follows:    

                 A3        B0          G1          M1        X10        I1        A3  

Where:    A1  =  Walk  one  to  two  steps  upto  the  machine.  

B0    =  No  Body  motion.  

UnknownField Code Changed

Page 28: Report

G1    =  Gain  control  of  the  button.  

M1    =  Press  the  switch  button.  

X10  =  Process  time  of  approximately  3.5  seconds.  

I0        =  Eye  Alignment.    

A0      =  Return  back.

CONTROLLED MOVESEQUENCE MODEL:

ILLUSTRATION

AB IXMGA

A: ACTIONDISTANCETO OBJECT

X:PROCESSTIME

G: GAINCONTROLOF OBJECT

M: PRESSBUTTON TOSTART M/C

A A: ACTIONDISTANCE

B: BODYMOTION

I: EYEALIGNMENT

 

 

III. Tool  Use  :-­‐    This  sequence  model  covers  the  use  of  hand  tools  for  such  activities  as  fastening  or   loosening,  

cutting,  cleaning,  gauging,  and  recording.  Also,  certain  activities  requiring  the  use  of  the  brain  for  mental  

processes  can  be  classified  as  Tool  Use,  for  e.g.  reading  and  thinking.    

As   indicated   above   the   Tool   Use   Sequence   Model   is   a   combination   of   General   Move   and  

Controlled  Move  activities.   It  was  developed  as  a  part  of   the  BASIC  MOST  Systems,  merely   to  simplify  

the  analysis  of  activities  related  to  the  use  of  hand  tools.  

The  use  of  a  wrench,  for  example,  can  be  described  by  the  following  sequence  :  

         A1  B0    G1    A1    B0    P3      F10        A1  B0    P1    A0                              

Where:    A1    =  Reach  to  wrench.  

UnknownField Code Changed

Page 29: Report

B0    =  No  body  motion.  

G1    =  Get  hold  of  wrench.  

A1    =  Move  wrench  to  fastener  a  distance  within  reach.  

B0    =  No  body  motion.      

P3    =  Place  wrench  on  fastener.  

F10  =  Tighten  fastener  with  wrench.  

A1    =  Move  wrench  a  distance  within  reach.  

B0    =  No  body  motion.  

P1    =  Lay  wrench  aside.  

A0    =  No  return.

TOOL USE SEQUENCE MODEL

A B G A B P T A B P A

T TOOL USE PARAMETER

 

I  was  asked  to  formulate  the  MOST  for  new  model  for  the  trim  region  by  comparing  it  with  MOST  for  an  

existing   similar   model.   Since   the   new   model   was   not   in   existence,   so   I   studied   the   videos   for   mass  

production   trials   and   then   I   could   formulate   it   as   required.   A   sample   MOST   sheet   is   attached   for  

reference.  

UnknownField Code Changed

Page 30: Report
Page 31: Report

PROJECT-­‐5  

Checking  Feasibility  and  Palette  Design  for  Ritz  Module  Docking  

Jig  design  for  module  docking  of  Ritz  chassis.  It  was  proposed  that  almost  all  the  components  that  were  fitted  in  the  chassis  line  namely  rear  axle,  front  and  rear  suspension,  engine,  fuel  tank,  exhaust  pipe.  I  was  asked  to  check  the  feasibility  of  such  a  project.  I  visited  the  existing  chassis  line  for  Ritz  and  checked  for  any  nuts  or  screws  which  could  not  be  fitted  if  the  complete  setup  would  be  mounted  simultaneously.  

1. It  was  observed  that  there  would  be  difficulty  in  mounting  of  two  clamps  for  hand  brake  pipe  mounting  after  fixing  the  fuel  tank.  The  solution  to  this  was  change  in  the  mounting  position  of  those  clamps.  

2. Another  problem  was  the  mounting  of  brake  pipes  on  a  clamp  already  mounted  on  the  car  body.  The  process  sequence  was  changed  to  combat  this  error.  

 

Under  side  of  Ritz  for  which  pallets  were  to  be  designed.  

Page 32: Report

 

Components  fitted  in  the  chassis  line  

Engine  

Exhaust  pipe  

Fuel  tank  

Rear  suspension.  

rear  axle  

Page 33: Report

 

 

 

 

 

Front  disc  brake  

 

Mount  for  front  disc  brake  

 

muffler  

Mount  for  muffler  

Page 34: Report