renewable energy applications in residential … · renewable energy applications in residential...

179
RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES AND SMALL-SCALE DESALINATION PROCESSES A THESIS SUBMITTED TO THE GRADUATE DIVISION OF THE UNIVERSITY OF HAWAI‘I AT MĀNOA IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF MASTER OF SCIENCE IN MECHANICAL ENGINEERING DECEMBER 2012 By Tyler Thomas Phillips Thesis Committee: Weilin Qu, Chairperson David Garmire Reza Ghorbani

Upload: truongliem

Post on 13-Apr-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES

AND SMALL-SCALE DESALINATION PROCESSES

A THESIS SUBMITTED TO THE GRADUATE DIVISION OF THE UNIVERSITY OF HAWAI‘I AT MĀNOA IN PARTIAL FULFILLMENT OF

THE REQUIREMENTS FOR THE DEGREE OF

MASTER OF SCIENCE

IN

MECHANICAL ENGINEERING

DECEMBER 2012

By Tyler Thomas Phillips

Thesis Committee:

Weilin Qu, Chairperson David Garmire Reza Ghorbani

Page 2: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

©Copyright 2012

By

Tyler Thomas Phillips

All Rights Reserved

ii  

Page 3: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

ACKNOWLEDGEMENTS

There were many people who worked on the mechanical system since the beginning of engineering’s involvement on the Team Hawai‘i Solar Decathlon home. A special thanks needs to be made to Team Hawai‘i’s Project Manager David Cook, School of Architecture, who began the work and designed the initial mechanical system upon which the final design was based. The mechanical team was comprised of a group of Mechanical Engineering undergraduate students: Trevor Johnson, Kwok Hin Ko, Byron Blandchard, Huilin Xie, Chaoming Liang, Sonya Ling, and Angela Menghini. These students’ work was influential in the completion of the overall design. Huilin Xie did a tremendous job taking the lead on the Fire Protection system and worked closely with industry professionals from Thermal Engineering Corporation to complete a safe and effective fire suppression system design. Melvin Harano and Derick Kam from Thermal Eng. Corp (through collaboration with SFPE Hawai‘i) gave of lot of time and effort to help Huilin and the team complete this task.

Of course, without faculty support none of this would have been possible. The lead Mechanical Engineering faculty, Dr. Weilin Qu, formed the mechanical team after being approached by the Principal Investigator of Team Hawai‘i, David Rockwood from the School of Architecture. Dr. Qu’s constant guidance and support were pivotal in the design completion as well as the construction planning by finding industrial contacts for design assistance and product donations. Jim Moore, from Ferguson Hawaii, assisted not only in the design of the solar thermal system but also in offers of equipment procurement. Scott Inatsaka, from WSP Lincolne Scott, worked with the team to design the HVAC system to ensure code compliance and maximum efficiency. The plumbing system design was overseen by Norman Tada of Oahu Plumbing & Sheet Metal, Ltd, of the Sen Plex Corporation. The knowledge and experience of these industry professionals was essential for the mechanical team to complete all the systems, and their help is greatly appreciated.

The work on HDH desalination would have also not been possible without the constant guidance and support of Dr. Weilin Qu. The tremendous research and development work done by Riley McGivern on his HDH system with direct contact condensation, was the basis for this work. The resources and funding provided by the REIS program at UH Mānoa for this research is greatly appreciated and has allowed this work to be done.

iii  

Page 4: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

ABSTRACT:

The conservation and replenishing of our world’s energy and fresh water sources is of pivotal importance for the next generations. The global fossil-fuel reserves are dwindling as are the fresh water aquifers. The need for fresh water, however, may not be as apparent as the energy needs; especially in affluent countries where rising gasoline and electricity prices will be noticed by many, and where piped water supply is standard but bottled water is preferred by most. Even though this fresh water need may be unnoticed in the most developed countries the underground aquifers upon which they rely for bottled water production are depleting and going less restored each year. In reaction to the continual increasing of energy costs, the United States has experienced a surge of renewable energy research and has implemented requirements for the integration of many large-scale renewable energy generation methods all over the country. However, other much more impoverished countries have been utilizing small-scale renewable and sustainable sources of energy, food, and water for generations and the US could learn much from these “undeveloped” nations. There are many rural areas in developing countries where fresh water sources are lacking severely and there is high need for local water production with low energy and costs demands. There is also a potential for a range of classes within the developed countries to achieve sustainability through the use of small-scale renewable methods which can be adapted for any style of living. This work, therefore, is a comprisal of two projects which address the energy and fresh water needs that are facing our world today.

The first section of this work focuses on the effective integration of new and old sustainable methods of renewable energy generation into residential homes. This was done through a university wide project to design and build a net-zero home for the Department of Energy’s Solar Decathlon 2011 competition. An esthetically creative, highly efficient, net-zero home design will be presented which is coupled with the innovative sustainable food and oxygen production system known as aquaponics. This modern home not only provides its occupants will all energy needs through PV and solar thermal panels, but also with fresh produce and fish through the aquaponics system. The use of a thermal storage system with phase change materials is implemented to provide highly efficient home heating and cooling

The second section then focuses on the fresh water need, specifically of those rural areas of developing countries where conditions are dry and solar insolation is high. The high potential of these areas for solar energy generation through PV and solar thermal panels make them prime locations for the integration of solar desalination processes for fresh water production. A number of solar humidification dehumidification (HDH) desalination processes are presented and the optimal configurations identified for use in decentralized arid regions. A detailed analysis of the top modeling techniques used for the optimization of these processes is also described.

iv  

Page 5: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

TABLE OF CONTENTS  

 

ACKNOWLEDGEMENTS ................................................................................................................. iii 

ABSTRACT ..................................................................................................................................... iv 

LIST OF TABLES ............................................................................................................................ viii 

LIST OF FIGURES ........................................................................................................................... viii 

 

 

SECTION 1: U.S. DEPARTMENT OF ENERGY SOLAR DECATHLON 2011: TEAM HAWAII MECHANICAL SYSTEMS .............................................................................. 1 

CHAPTER 1 – INTRODUCTION TO SOLAR DECATHLON........................................................................... 2 

1.1 Background of Solar Decathlon .................................................................................................... 2 

1.2 Team Hawai‘i Objectives .............................................................................................................. 3 

1.3 General Competition Rules and Criteria ....................................................................................... 4 

1.3.1 Deliverables ........................................................................................................................... 5 

1.3.2 On‐Site Construction ............................................................................................................. 6 

1.3.3 Competition Days .................................................................................................................. 7 

1.3.4 On‐Site Disassembly .............................................................................................................. 9 

CHAPTER 2 – MECHANICAL SYSTEMS ................................................................................................... 10 

2.1 Fire Protection System ............................................................................................................... 10 

2.1.1 Fire Protection Requirements ............................................................................................. 10 

2.1.2 Fire Protection Design Plans ................................................................................................ 10 

2.1.3 Fire Protection Design Specifications .................................................................................. 12 

2.1.4 Fire Protection Construction and Disassembly ................................................................... 13 

2.2 Plumbing System ........................................................................................................................ 14 

2.2.1 Plumbing Requirements ...................................................................................................... 14 

2.2.2 Plumbing Design Plans ........................................................................................................ 15 

2.2.3 Plumbing Design Specifications ........................................................................................... 18 

2.2.4 Plumbing Construction and Disassembly ............................................................................ 18 

v  

Page 6: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

2.3 Heating, Ventilation, and Air Conditioning System .................................................................... 20 

2.3.1 Heating, Ventilation, and Air Conditioning (HVAC) Requirements ..................................... 20 

2.3.2 HVAC Design Plans .............................................................................................................. 20 

2.3.3 HVAC Design Specifications ................................................................................................. 22 

2.3.4 HVAC Construction and Disassembly .................................................................................. 23 

2.4 Solar Thermal System ................................................................................................................. 25 

2.4.1 Solar Thermal Requirements ............................................................................................... 25 

2.4.2 Solar Thermal Design Plans ................................................................................................. 25 

2.4.3 Solar Thermal Design Specifications ................................................................................... 27 

2.4.4 Solar Thermal Construction and Disassembly ..................................................................... 27 

CHAPTER 3 – RESULTS AND DISCUSSIONS ........................................................................................... 29 

3.1 Summary of Team Hawai‘i’s Solar Decathlon 2011 .................................................................... 29 

  

SECTION 2: REVIEW AND ANALYSIS OF HUMIDIFICATION DEHUMIDIFICATION DESALINATION PROCESSES WITH FOCUS ON DIRECT CONTACT CONDENSATION ............. 31 

CHAPTER 4 – INTRODUCTION TO WATER DESALINATION ................................................................... 32 

4.1 Background on Fresh Water Needs ............................................................................................ 32 

4.1.1 The Global Need .................................................................................................................. 33 

4.2 Background on Water Desalination ............................................................................................ 37 

4.2.1 Thermal (Phase‐Change) Processes .................................................................................... 38 

4.2.2 Membrane Processes .......................................................................................................... 42 

CHAPTER 5 – THE HUMIDIFICATION DEHUMIDIFICATION THERMAL DESALINATION PROCESS ......... 45 

5.1 Humidification Dehumidification (HDH) Process ....................................................................... 45 

5.1.1 HDH Classifications .............................................................................................................. 46 

5.1.2 Performance Parameters .................................................................................................... 49 

5.2 Literature Review of HDH Systems and Components ................................................................ 51 

5.2.1 Closed‐Air Open‐Water (CAOW) Systems ........................................................................... 51 

5.2.2 Closed‐Water Open‐Air (CWOA) Systems ........................................................................... 53 

5.2.3 Humidifier/Evaporator ........................................................................................................ 55 

5.2.4 Dehumidifier/Condenser ..................................................................................................... 57 

vi  

Page 7: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

5.2.5 Heat Exchangers .................................................................................................................. 59 

CHAPTER 6 – THE POTENTIAL OF HDH WITH DIRECT CONTACT CONDENSATION ............................... 61 

6.1 The Diffusion Driven Desalination (DDD) Process ...................................................................... 61 

6.2 Analysis Methods and Findings .................................................................................................. 62 

6.3 Summary of Analysis Methods and Findings .............................................................................. 77 

CHAPTER 7 – RESULTS AND DISCUSSIONS ........................................................................................... 80 

 

REFERENCES ................................................................................................................................ 83 

APPENDIX A: SOLAR DECATHLON WATER BUDGET .......................................................... ATTACHED 

APPENDIX B: MECHANICAL SPECIFICATIONS SHEETS ‐ DIVISION: 21, 22, 23, 28 ............... ATTACHED 

APPENDIX C: TEAM HAWAI‘I FULL DRAWING SET ............................................................ ATTACHED 

 

 

 

 

 

 

 

 

 

 

 

 

vii  

Page 8: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

viii  

LIST OF TABLES 

SECTION 2 – HDH DESALINATION 

Table 1: Disparities between rural and urban areas in water sources, 1990‐2010 [1]  ..................... 36 

Table 2: Top 10 desalinated water producing countries [2]  ........................................................... 38 

LIST OF FIGURES 

SECTION 1 – SOLAR DECATHLON 

Figure 1: Sheet F‐602/A1 showing the Fire Suppression Diagram with keynoting ............................ 11 

Figure 2: F‐901/A1 shows an isometric view of the fire suppression system ................................... 12 

Figure 3: F‐603/D1 showing fire sprinkler section detail of piping connected to rib ........................ 13 

Figure 4: A1/P‐602 Domestic water supply diagram with pipe sizes and annotations ...................... 16 

Figure 5: C4/P‐602 Sanitary waste and vent diagram with pipe sizing and annotations ................... 17 

Figure 6: A1/P‐901 Isometric view of domestic water supply piping and tanks ............................... 19 

Figure 7: A1/M‐101 showing HVAC equipment and distribution plan ............................................. 22 

Figure 8: A1/M‐102 showing spill containment plan for all systems of the house ........................... 24 

Figure 9: A1/M‐603 showing solar water diagram ......................................................................... 27 

Figure 10: A1/M‐902 showing solar water isometrics of solar water panels and tanks .................... 28 

SECTION 2 – HDH DESALINATION 

Figure 11: Drinking water coverage trends by developing regions, 1990‐2010 [1] ........................... 36 

Figure 12: Simple HDH diagram with solar collector ...................................................................... 46 

Figure 13: CAOW cycle diagram .................................................................................................... 48 

Figure 14: CWOA cycle diagram .................................................................................................... 48 

Figure 15: Flow diagram for innovative diffusion driven desalination process [13] .......................... 62 

Figure 16: Flow diagram for the DDD process [16] ......................................................................... 66 

Figure 17: Differential control volume for the direct contact condensation tower [16] ................... 66 

Figure 18: Schematic diagram of DDD experimental facility with twin condensation towers [17] .... 69 

Figure 19: Flow diagram procedure for computation of the counter‐current flow condenser [17] ... 70 

Figure 20: Flow diagram of Riley’s HDH system with direct contact condensation [14] ................... 71 

Figure 21: Control volume used for evaporator and condenser towers, showing the interactions between the liquid, gas/vapor, and solid packing material [18] ...................................................... 72 

Figure 22: Process flow diagram for solar diffusion driven desalination system [19] ....................... 75 

Page 9: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

SECTION 1:

U.S. DEPARTMENT OF ENERGY SOLAR DECATHLON 2011:

TEAM HAWAI‘I MECHANICAL ENGINEERING SYSTEMS

1  

Page 10: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

CHAPTER 1 - INTRODUCTION TO SOLAR DECATHLON

1.1 BACKGROUND OF SOLAR DECATHLON

The U.S. Department of Energy Solar Decathlon is an event that tests collegiate

teams from all over the world to design and build solar-powered net-zero homes which are

aesthetically and financially competitive as well as extremely energy-efficient. Not only are

teams judged on affordability, architecture, engineering, and over-all energy balance but also

on market appeal, communications, comfort zone, hot water, appliances, and even home

entertainment. The winner of the decathlon is the team that scores the highest over-all from

the judges based on the criteria described. The 2011 Solar Decathlon is the fifth decathlon

event held biennially since the first one held in 2002. The event has since expanded to 65

teams with 10,000 students over three competitions; Solar Decathlon Europe 2012, Solar

Decathlon China 2013, and the U.S. Department of Energy Solar Decathlon 2013. All Solar

Decathlon events have been open and free to the public and have encouraged visitors to tour

the homes and learn about energy conservation of all types in various booths around the

Solar Decathlon village.

The decathlon gives students the opportunity to display their hard work through the

houses and to interact with the other teams and industry professionals. This unique

experience prepares students to enter into the clean-energy workforce and gives them an

advantage in finding jobs by contact with industry throughout the project. The Solar

Decathlon event encourages young students to consider the repercussions of their energy

usage and the need for implementation of renewable resources and sustainable energy for

homes and industry. Through the nearly 17,000 collegiate participants who have competed

2  

Page 11: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

in decathlons so far, millions of spectators, ranging from family and friends of participants to

visitors and industry professionals, have been introduced to future smart homes capable of

saving money and, more importantly, energy for its occupants. Whether exposure to the

decathlon comes from word of mouth, being at a decathlon event, or through media, the

message is all the same; the youth of this generation is ready to make a change and is

showing the world how today.

1.2 TEAM HAWAI‘I OBJECTIVES

The challenge for the 2011 Solar Decathlon was to design and build a custom

modularized single family dwelling with net-zero (or better) energy usage to compete with

19 other collegiate teams from around the world in Washington D.C.. Team Hawai‘i

architects visualized an ergonomic tubular structure which the electrical and mechanical

engineering teams were tasked to design energy efficient systems within and around. The

mechanical systems were designed in conjunction with building codes and competition rules

and requirements in order to meet all the needs of the home’s occupants in the most energy

efficient way possible. These needs were determined by the Solar Decathlon judges and

demonstrate the average usage of appliances by a single family household of one to three.

Just as the shape of the house proposed by Team Hawai‘i goes outside the norm, the

mechanical equipment and techniques around the home also strayed away from the average

systems. Utilizing new concepts and materials was not only done to fit the shape of the

house but also to improve on the overall home efficiency and sustainability in the future.

The integration of aesthetics and functionality was a major challenge in this project and

pushed the engineers and architects to work very closely together, which yielded a highly

unique and strongly detailed design.

3  

Page 12: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

The mechanical systems of the 2011 Solar Decathlon Team Hawai‘i house are

comprised of four sub-systems: HVAC, Plumbing, Solar Thermal, and Fire Protection. The

heating, ventilation, and air conditioning (HVAC) system utilizes a heat-pump in conjunction

with a thermal mass pillow tank filled with water and phase change material (PCM). The

plumbing system consists of PEX flexible piping for hot and cold water delivery and recycles

grey water for use in the house’s aquaponics system. The solar thermal system has two solar

panels and two hot water tanks that can provide the house with all its hot water needs. The

fire protection system also uses PEX flexible piping in combination with copper tubing for

fire suppression through six ceiling mounted sprinkler heads.

1.3 GENERAL COMPETITION RULES AND CRITERIA

The Solar Decathlon event has a strict code of rules and regulations that need to be in

place so that the decathlon can run smoothly and fairly. Each team is required to assign

positions to its key members such as Project Manager, Health and Safety Officer, Electrical

Engineer, Mechanical Engineer, and etc. These officers must conduct themselves in a

responsible fashion and encourage other team members to follow the necessary rules.

Contact with the Solar Decathlon administration is also very important to ensure the correct

interpretation of the rules and requirements. Any discrepancies, no matter how small, could

lead to penalties or even rejection from the competition. From the very beginning of design,

all regulations, even those pertaining to site operations and construction, must be taken into

account to ensure that there will not be large issues later down the road. However, as in any

construction project, there of course will be problems and changes will occur up to the time

of competition.

4  

Page 13: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

For the mechanical teams the primary rules of importance are; Rule 4: Site

Operations, Rule 8: Energy, Rule 9: Liquids, and Rule 11: Contest Week. Within each Rule

there are many sub-rules, which must all be followed and/or clarified with Solar Decathlon

judges. The main contest criteria of concern for the mechanical teams are; Contest 3:

Engineering, Contest 6: Comfort Zone, Contest 7: Hot Water, Contest 8: Appliances, and

most importantly Contest 10: Energy Balance. Other contests, like Affordability, are taken

into account by the mechanical side but are not the primary focus.

1.3.1 Deliverables:

During the design process there are a number of deadlines for deliverables leading up

to the competition. These deliverables allow the competition coordinators and judges to

check over the plans of each team and ensure their cooperation with rules, regulations, and

building codes. If and when issues are found, the judges will relay these concerns to the team

and allow them time to fix and re-submit documentation. The primary set of drawings for

the house must be generated using the Autodesk Revit building information model (BIM).

The BIM shall also contain energy analysis models and a computer-animated walkthrough of

the home. The BIM will allow jury members to see a full view of each team’s project from

the small details of construction drawings, to an overview of assembly and disassembly, and

to the final artistic rendition of the home.

A project manual is also required and consists mostly of specification sheets, which

contain detailed product information on all the utilized materials and equipment. The

information found on the specification sheets are also integrated into the BIM, where all

materials and equipment are called out using keynoting according to the specification

numbers. Construction drawing sets are to be created using screen shots from the three-

5  

Page 14: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

dimensional BIM. Audiovisual presentations are required for architectural, sales, and

engineering sides of the project. These presentations combine images from the 3-D house in

BIM, audio information and descriptions of the sections, and artistic visualizations in order to

create a professional message for judges and spectators at the competition. A detailed energy

analysis description is also required in the project manual, which describes the methods used

to calculate the heat gain and loss from the house, usually by some computational modeling

systems. A detailed water budget, which accounts for all water needs during the course of

the competition, is also required for the project manual.

Along with the BIM, project manual, and presentations, a web-site and a video walk

through of the home must be created. The web-site is a means for the team to communicate

with the public, especially locally, about the project and to gain support and spread the word

about the Solar Decathlon contest. The video walkthrough should be available through the

web-site and can also be played during the competition for spectators and judges.

1.3.2 On-Site Construction:

The competition begins with seven days of stand-alone assembly of the solar homes.

Most of the seven days of assembly allow for 24 hour work, and during these long days there

are many important rules and deadlines that must be met in order to be prepared for the

beginning of the contests. This construction phase is also judged and by completing quickly,

teams allow themselves more time to test and prep home systems for contest days. Some of

the rules and regulations each team should consider are described in the following.

Each team is financially responsible for any damage that is caused to the site during

construction, contests, and disassembly. All equipment, such as forklifts, is required to move

along a grass protection product provided by event organizers. Also, truck-mounted cranes

6  

Page 15: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

or trailers need to stay on the gravel pathway. Ground penetration and impact on the grass

turf is of high concern for the event organizers and therefore restrictions and soil-bearing

pressure criteria must be followed for various footings around the homes. Generators are

allowed during assembly and disassembly days only and must meet National Park Services

noise regulations. All spills of any fluids from equipment and/or vehicles must be avoided

by use of secondary containment systems. During day five of assembly a water truck will

deliver a maximum of 1500 gallons to each home. A detailed water delivery plan is required

for each team to ensure safe and efficient delivery process. During assembly days no release

of water or other fluids is allowed from home into nearby storm drains. Lot conditions can

vary up to 18 vertical inches across the lot. Teams are allowed to send a representative to

scout the lot conditions during an organizer approved period and take measurements.

The solar envelope restrictions are another large consideration for the overall design

of the home including any roof mounted panels or equipment. Many other structural rules

and restrictions exists for the architectural design but are not mentioned in this report.

Overall, the main areas of concern for the mechanical teams are the turf impact of equipment

and tanks, the use of forklifts and cranes for moving and mounting equipment, and spill

containment especially during water delivery day.

1.3.3 Competition Days:

The seven days of house assembly are followed by nine days of competition during

which ten different contests occur and are graded by Solar Decathlon judges. The ten

contests are; Architecture, Market Appeal, Engineering, Communications, Affordability,

Comfort Zone, Hot Water, Appliances, Home Entertainment, and most importantly Energy

Balance. Each contest is graded on different specific criteria and results of the contests will

7  

Page 16: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

be posted at different times as they are finished. The architecture, market appeal,

communications, and affordability contests are partly judged on materials already received

by judges prior to competitions days and also on the presentation and demonstration of these

items during the first few competition days. For this reason these results are announced early

into the contest days. However, the engineering, comfort zone, hot water, appliances, home

entertainment, and energy balance contests, are based on readings and measurements taken

over all nine contest days. Therefore the results of these contests are not delivered until the

day following the last day of contests. The final two contests to be judged are Engineering

and Energy Balance; the results of these two important contests will determine the overall

decathlon winners.

The specific contest criteria for the engineering contest; functionality, efficiency,

innovation, reliability, and documentation, are meant to grade the overall engineering effort

of each team. The energy balance contest is based purely on the net electrical energy, which

is the total amount energy produced minus the total amount used, of each home for the

entirety of the contest days. If a team has a net electrical energy greater than or equal to 0

kWh, then the team receives full points. Reduced points are given from 0 to -50 kWh, and

no points are given for a net electrical energy less than or equal to -50 kWh. The specific

criteria of the comfort zone, hot water, and appliances contests are explained in Chapter 2 -

Mechanical Systems under requirements for HVAC, solar thermal, and plumbing sections,

respectively.

8  

Page 17: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

1.3.4 On-Site Disassembly:

The rules and regulations pertaining to the four disassembly days are very similar to

those imposed on the assembly days. One 12 hour day, followed by three 24 hour days will

be the total amount of time each team has to not only disassemble but re-pack and remove all

equipment and materials from the site. The goal for every team and the event organizers is to

try and leave the park in as good of condition as it was before the competition, in order to

show our appreciation to the park services and local community. Spill containment is a big

concern for disassembly as the water that was used by each home will need to be removed in

a similar method that it was delivered. This time, however, there is risk that the water is

contaminated, and therefore extra care must be taken to assure that no water or other fluids

spill and flow into local drainage. Again, for this reason, a detailed water removal plan must

be developed and drawn out by each team. The manner in which the homes are disassembled

is up to each team, however, since one goal of design is to demonstrate modular construction,

most teams will opt to disassemble in the same but opposite way that they assembled. Many

teams, regardless of placement in the decathlon results, will re-assemble their house for

display at the home university or another designated location.

9  

Page 18: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

CHAPTER 2 – MECHANICAL SYSTEMS

2.1 FIRE PROTECTION SYSTEM

2.1.1 Fire Protection Requirements:

Fire protection is the only system not tested directly by contest officials but is a very

important requirement for safety reasons. Just as any residential home must follow fire code,

so must all solar decathlon homes. Full coverage of the interior of the home is needed

through multiple ceiling mounted sprinkler heads and extinguishers need to be placed in

areas of high fire threat, such as the kitchen. Enough water must be available at all times for

the sprinkler system to fully run for seven minutes in the event of a fire, either during

competition hours or when empty at night. No contest points are awarded directly for fire

suppression and protection but without these the homes could not compete in the decathlon

events.

2.1.2 Fire Protection Design Plans:

The fire protection system was designed according to the International Residential

Code (IRC) standards in order to meet all the requirements of a new residential home, with

both fire alarm and suppression systems. Because the house does not have a traditional

ceiling, the fire suppression system was designed to fit within the shell structure and the

sprinkler heads mounted flush with the inner FRP skin. Smoke detectors and fire

extinguishers were placed according to IRC and can be seen on sheet F-101.

In order to design the fire suppression system the sprinkler heads must be placed in

very specific areas to provide maximum coverage and to conform to IRC. The slope of the

10  

Page 19: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

ceiling at the sprinkler head locations is greater than 1/3 but less than 2/3, and the heads are

sized accordingly. From the sprinkler specification sheet; the single sprinkler’s maximum

coverage needs to be 18” x18”, the minimum flow rate 19 gpm, and the minimum pressure

15 psi. According to IRC 2009 section P2904.4.2; two sprinklers run simultaneously for 7

minutes, and then the minimum water consumption is 266 gallons. Approximately 280

gallons of water are devoted to this fire suppression system and will be stored in a 300 gallon

tank in the under porch area. The sprinkler layout, piping, and tank are shown on sheet F-

102: Fire Suppression Plan, and sheet F-602: Fire Protection Diagrams (shown in Figure 1

below).

Figure 1:  Sheet F‐602/A1 showing the Fire Suppression Diagram with keynoting. 

The pressure needed for the fire suppression system is provided by a 3 hp centrifugal

pump. This pump was sized after performing a flow pressure simulation using a software

package developed by Thermal Engineering Corporation in Honolulu. The pump set up

along with valves and controls are drawn in Figure 1; the fire suppression diagram on F-602.

The fire sprinkler lines are PEX piping rated for fire suppression systems. These

pipes are flexible and can be routed through the curved shell structure of the house and will

11  

Page 20: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

penetrate through the shell in the under floor area. A three-dimensional representation of the

system is shown in a fire suppression isometric view on sheet F-901, and can be seen in

Figure 2 below. Excess PEX piping is fitted into the shell structure to accommodate for

multiple connections and disconnections for off-site assembly and disassembly. The

sprinkler heads are recessed into ceiling to incorporate into interior design and are depicted

on sheet F-603 Fire Sprinkler Detail. The fire protection schedules, sheet F-601, list the

specific materials needed with different details depending on the material. Other comparable

UL listed products could also be used to accomplish the same needs.

 

Figure 2:  F‐901/A1 shows an isometric view of the fire suppression system. 

2.1.3 Fire Protection Design Specifications:

The fire protection system is made up of PEX and copper piping and fittings, fire

sprinklers, a fire water storage tank, a fire pump, fire alarms, and fire extinguishers. Detailed

fire equipment information can be found in the project manual specification sheets Division

12  

Page 21: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

21: Fire Suppression. The fire equipment schedules, calling out all needed piping, fittings,

pumps, tanks, and sprinklers, can be found in the project plans on sheet F-601.

2.1.4 Fire Protection Construction and Disassembly:

Installation of the sprinkler heads will be done during the pre-construction stages of

the modules, and will be fitted flush to the ceiling FRP (fiber reinforced polymer) skin. The

flexible PEX piping will also be installed in each of the three individual modules containing

two sprinkler heads. These PEX lines will run from the bottom half of the shell into the

upper and are attached along one of the wooden ribs and placed below the joists that brace

the ribs together. Detailed plans of the PEX fire piping and sprinkler head placement inside

the shell are shown on sheet F-603: Fire Sprinkler Detail. Figure 3 below shows one of these

details from the drawing set; F-603/D1, which shows a cross-section detail of the sprinkler

heads and the PEX piping that runs along a rib and through joists.

Figure 3:  F‐603/D1 showing fire sprinkler section detail of piping connected to rib.

13  

Page 22: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Although the FRP skin is mostly translucent the PEX lines are clear and where

attached to the ribs will not be easily seen or noticed through the ceiling shell. Extra PEX

piping will be wound up in the top and bottom shells to be connected once the shells are

joined on-site. Once the shells are connected the final quick connections, provided by the

PEX piping, can be made through the length of the belly of the house. The flexible PEX will

be used to connect to a hard copper line coming from the fire pump, which is then connected

to the plastic fire water tank, holding at all times enough water for seven minutes of fire

suppression. The system will then be primed and tested in accordance with Solar Decathlon

rules and regulations.

2.2 PLUMBING SYSTEM

2.2.1 Plumbing Requirements:

The plumbing requirements for the solar house can be determined by each team

according their needs based upon the contests that use water. All local building plumbing

code requirements must be followed in order to create a home that can deliver water for

bathing, dish washing, clothes washing, fire suppression (in case of emergency), and also for

any other water features implemented by the teams. The rules also state that a toilet shall be

installed in the bathroom but will not be connected to plumbing and therefore will not be for

use. All sanitary waste water (grey water) will come from the shower drain, bathroom and

kitchen sinks, dishwasher, and clothes washer. A detailed water budget must be made in

order for each team to determine the total amount of water that will be used during the

competition. This water budget is based upon the amount of water used for each of the

measured contests. All water brought into the home prior to competition from the decathlon

14  

Page 23: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

provided water truck and then removed post competition must be accounted for in a detailed

water delivery and removal plan.

2.2.2 Plumbing Design Plans:

The plumbing system was designed following International Residential Code (IRC),

International Plumbing Code (IPC), and Uniform Plumbing Code (UPC). In order to

determine how much water would be consumed during the course of the competition, a water

budget was made. The budget details water usage from daily tasks such as showers, laundry,

dish washer, and cooking. It also must account for the water used for fire suppression (if

needed), and water needed for the thermal mass pillow tank. The maximum amount of

decathlon provided water for each team is 1500 gallons. Additional special water would be

brought in by the team for the aquaponics system to get it started. From the water budget the

water tanks were sized and configured in the under porch area, along with pumps, valves,

fittings and piping. The plumbing site plan, sheet P-101, shows the entire plumbing layout

for the house.

The domestic hot and cold water lines will be PEX piping because it can be rolled up

and stored in one module, then quickly and easily installed after module connection. All

horizontally installed PEX must be supported every 2.5 feet, in compliance with IRC

requirement from 2009 edition Table P2605.1 - Piping Support. The hot water supply PEX

piping is insulated to minimize heat loss and meet code requirements. Hot water is provided

from two lowboy solar thermal hot water storage tanks and connections are to copper piping.

Pressure for the domestic water supply is provided by a 1 hp centrifugal pump, and is

connected to a 500 gallon fresh water tank. The layout of the domestic supply plan can be

15  

Page 24: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

found on sheet P-102, and a more detailed riser diagram on sheet A1/P-602, which is also

shown in Figure 4 below.

Figure 4:  A1/P‐602 Domestic water supply diagram with pipe sizes and annotations. 

The sanitary waste and vent lines are assembled from PVC piping and are pre-

mounted into each module. All of the fixture sanitary drains are greater than or equal to 1-

1/4” to comply with IRC 2009 P2703.1, and drain into 2" branch lines leading to the main 2"

return line to the sanitary waste tank. The clothes washing machine drains into an 18 inch

high stand pipe to comply with IRC 2009 P2706.2 - Standpipes. The clothes washing

machine discharge goes through an air break to comply with IRC 2009 P2718.1 - Waste

Connection. The drainage fixture unit (DFU) value in the house is 7, and according to the

UPC, 2 inch gray water pipes can be used. Air admittance valves are used for low flow rate

fixtures (less than 18 gpm), and comply with IRC 2009 section P3114. These valves, along

16  

Page 25: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

with the rest of the sanitary system, are diagrammed on sheet C4/P-602 and shown in Figure

5 below. A site plan of the sanitary waste and vent system can also be found on sheet P-103.

Figure 5:  C4/P‐602 Sanitary waste and vent diagram with pipe sizing and annotations.

During the competition, once grey water begins to fill the sanitary tank, it will then be

pumped out and fed into the aquaponics system to be reused and recycled; this is

demonstrated in the landscape irrigation plan on sheet L-102. The plumbing schedules, sheet

P-601, list with details all the needed materials to complete the plumbing system to code.

Any comparable UL listed products could be used instead of the ones specifically listed in

schedules. Three-dimensional isometric views of the domestic supply and sanitary return are

shown on sheets P-901 and P-902, respectively. Along with the water budget, a water

delivery and removal plan is necessary for the competition in order to allow for coordinators

to schedule water deliveries to each house. The team’s water delivery and removal plan is

described and pictured on sheet O-201.

17  

Page 26: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

2.2.3 Plumbing Design Specifications:

The plumbing design utilizes PEX and copper piping and fittings, PVC piping and

fittings, valves and vents, a supply water pump, and fresh and grey water storage tanks.

Detailed plumbing equipment information can be found in the project manual specifications

sheets Division 22: Plumbing. The plumbing equipment schedules, which outline all the

piping, fittings, valves, pumps, fixtures, and tanks used in the system, is also shown in the

project plans on sheet P-601.

2.2.4 Plumbing Construction and Disassembly:

The installation of the plumbing systems will be mostly pre-fabricated into the needed

modules. The bathroom and kitchen, with fixtures and appliances, will be completely pre-

installed in their individual modules and connections made under the floor in the belly of the

home. Wound up sections of flexible PEX piping in the belly are used for both hot and cold

water connections from the solar hot water storage tank and fresh water tank, respectively.

Cold and hot lines run to most of the appliances and fixtures; clothes washer, dishwasher and

kitchen sink interconnected, bathroom sink, shower, and refrigerator has only cold water

connection. Copper fittings and piping will also be used for connections between hot water

tanks and pumps. All the domestic water supply connections can be seen in a 3-D isometric

view in Figure 6 (on next page) from sheet A1/P-901.

The sanitary return pipes are made of standard PVC and connect to drains in the

shower, bathroom sink, kitchen sink, clothes washer, and dishwasher. The toilet, although

installed, will not be connected to supply water lines nor sanitary return pipes, and will

therefore not be available for use. Connections of the PVC sanitary return system will be

done on-site using long sections brought together in the belly of the home. A ventilation pipe

18  

Page 27: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

will be pre-installed in the module with the bathroom and will penetrate the roof structure as

shown on sheet A-561 of the drawing set. A connection will also be made from the grey

water tank to feed into the aquaponics system as the grey water fills the tank. Water tanks

will not be pre-installed due to their large size and when placed on-site are raised up on

footings to reduce the ground impact. The fresh water tank, grey (waste) water tank, fresh

water pump, and hot water tanks are all located underneath the porch area, where they can be

blocked from view. Access to this under-porch area is required to be enough to allow

workers to fit safely. Priming and testing of the water systems will be done after day five of

assembly, when the water is delivered. Detailed water delivery and removal plans are found

in the site operations section on sheet O-201 of the full drawing set.

 

 

Figure 6:  A1/P‐901 Isometric view of domestic water supply piping and tanks.

 

19  

Page 28: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

2.3 HEATING, VENTILATION, and AIR CONDITIONING SYSTEM

2.3.1 Heating, Ventilation, and Air Conditioning (HVAC) Requirements:

The HVAC system requirements are based on the criteria of temperature and

humidity for the Comfort Zone contest. Temperature and humidity readings are taken from

various spots in the home and the thermal zone with most variation will be recorded and

time-averaged. The goal is to maintain an interior dry-bulb temperature between 71.0°F and

76.0°F, and an interior relative humidity below 60%. Each house’s thermal needs will of

course vary upon size, windows, building materials, and insulation. In order to determine the

thermal losses expected for the home design, a physical model is entered into a program.

Based on the sun path at the competition location and time, thermal exposure over a clear day

can be found and the average thermal gain of the home calculated. During the evening

thermal losses can be determined from exterior temperature and humidity estimations for the

area and by taking into account the insulation and windows used in the house.

During competition days the houses will be host to thousands of visitors, so during

this open public time temperature and humidity data is not taken. There are specific times

during each day when the comfort zone contest will occur. The times of the testing can be

utilized by the teams to optimize their cooling and heating potentials during those particular

hours. For this reason highly sophisticated HVAC systems can be used to accurately monitor

and control the temperature and humidity of different zones in the house. The HVAC system

and controls should be functional, efficient, innovative, reliable, and well documented.

2.3.2 HVAC Design Plans:

The HVAC system was designed in accordance to International Residential Code

(IRC), American Society of Heating, Refrigerating and Air-Conditioning Engineers

20  

Page 29: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

(ASHRAE), and American Society for Testing and Materials (ASTM) standards. In order to

determine the amount of heating and cooling needed to maintain the required temperature

and humidity range, according to the Solar Decathlon rules, a thermal analysis of the house

was conducted using Autodesk Ecotect and ACCA Manual J and D load calculations. The

programs were run considering the size and shape of the home and that the home would be in

Washington D.C. during the time of the competition in late September. Using the standard

weather of the location at this time it was possible to get a fairly accurate depiction of the

conditions that the house would experience and the heating and cooling loads necessary to

remain within the required ranges. From these loads the size of the heat-pump could be

found and then sizing for thermal mass, ducting, and diffusers calculated.

The HVAC system implements a water-source heat-pump drawing from a thermal

mass which acts as a geothermal source. The thermal mass contains water and phase change

material (PCM) which creates a lower and upper bound temperature range that optimizes the

performance of the heat pump. During cooling mode in the day time, heat is taken from the

interior and dumped into the thermal mass. During heating mode at night, warmer water

(requiring less heating) is now available in the thermal mass tank to be pumped through the

heat-pump. This balance helps to reduce home energy needs as well as heat loss from the

system. The thermal mass water and PCM is held in an insulated pillow/bladder tank. The

phase change materials are inside of tiny balls, which are contained in one meter long tubes

with a five centimeter diameter. Approximately 450 of these self-stacking tubes will be

placed into the pillow tank through a fill opening and is then filled with water.

HVAC air distribution uses rectangular ducting with a 1-inch layer of insulation to

prevent heat transfer between the air in ducts and the under-floor environment. Flexible hose

21  

Page 30: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

duct is used for fresh air intake and also for dehumidifier connection. The dehumidifier is

placed in parallel to the rest of the distribution system so that if heat pump is not running the

dehumidifier can still run and dehumidify the air going into the house. This method reduces

energy consumption for days when heating and cooling may not be needed. Bathroom

ventilation is provided by a fan under the lavatory, and takes air out of west bulkhead

through a flexible hose duct. Six floor diffusers distribute conditioned air into the home up

the north wall and six others, along the south wall, intake low stagnant air to be recycled

back through the heat-pump. A plan view of the home from sheet A1/M-101, seen below in

Figure 7, shows all the under-floor mechanical equipment and air distributions.

Figure 7:  A1/M‐101 showing HVAC equipment and distribution plan.

2.3.3 HVAC Design Specifications:

The HVAC system is comprised of a heat pump, dehumidifier, metal ducting and

junctions, hose ducts, floor diffusers, thermal mass pillow tank, copper piping and fittings,

and a thermal mass water pump. Detailed HVAC equipment information can be found in the

project manual specification sheets Division 23: HVAC. The HVAC equipment schedules,

22  

Page 31: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

which outline all the ducting, piping, fittings, pumps, tanks, and other equipment used in the

system, is also shown in the project plans on sheet M-601.

2.3.4 HVAC Construction and Disassembly:

Pre-installation is done for the main supply and return ducts, branch ducts, and floor

diffusers into each module of the house. A bathroom air-ventilation fan is also pre-installed

in the bathroom module; however, a vent hose must be connected on-site and will exit out the

west bulkhead. All other mechanical equipment and materials are shipped separately and

installed on-site. Once the top and bottom modules are in place, cover is provided for

installers and the under-floor equipment, such as the heat-pump, pillow tank, and

dehumidifier can be installed. The connections between main supply ducts can also be made

once the modules have been joined together. Additional ducting is installed connecting the

heat-pump to supply and return air ducts, as well as to the dehumidifier and vent hose. The

vent hose will exit out the east bulkhead. Copper piping connections and fittings are then

made between the heat-pump, thermal fluid recirculating pump, and pillow tank. The PCM

tubes are placed into the pillow tank and will self-stack with some help from installers.

On water delivery day, the pillow tank can be filled with water which is pumped out

of the water tanks through a 1.5 inch rubber hose. The two water tanks are filled by the

water delivery truck prior to filling of the pillow tank. A 0.6 hp submersible pump is used to

pump the water from the water tanks into the pillow tank. This is all completed between the

two water deliveries; the first will deliver 1000 gallons and about 800 gallons of that will be

pumped into the pillow tank with the PCM tubes. The second water delivery will supply the

house with an additional 500 gallons of fresh water. During disassembly, on water removal

day, the submersible pump is used to drain the pillow tank back into the water tanks to

23  

Page 32: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

prepare for water removal and is also used to assist in draining the aquaponics tanks. The

rest of the equipment is removed as it was installed, and pre-installed equipment is kept in

the modules. Because spills are eminent during disassembly and assembly days, a spill

containment plan (sheet A1/M-102) is required for each team and can be seen below in

Figure 8.

Figure 8:  A1/M‐102 showing spill containment plan for all systems of the house.

The spill containment plan shows all the systems which could contain any fluid at

some time during the competition; and therefore shows all plumbing and water tanks, HVAC

heat-pump and pillow tank, fire suppression lines and tank, solar thermal hot water tanks and

panels (not shown), and also the connections to aquaponics system tanks.

24  

Page 33: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

2.4 SOLAR THERAL SYSTEM

2.4.1 Solar Thermal Requirements:

Solar thermal needs are based upon the hot water and appliance contests criteria. The

bulk of the hot water needs will come from the hot water contest which attempts to replicate

the bathing needs of a single family home. Up to three hot water draws from the shower,

with shower head removed, can be made each day by judges and will be performed at

different times throughout the competition. Each draw must provide at least 15 gallons of

hot water within a ten minute time in order to qualify for points. Full points are given if the

average water temperature meets or exceeds 110°F and no points are received for an average

temperature lower than 100°F. Based on the number of water draws and estimating average

water usage per contest, the total hot water needs can be calculated for the competition. This

water will come from the fresh water supply delivered to each home just prior to competition

start, and must be accounted for in the water budget. From the hot water volume needs for

the most possible water draws on one day, the maximum daily hot water production value is

found and used to size a solar water heating system. The number of solar hot water panels

required and the angles they are mounted is determined based on the location and solar zone

and the daily hot water production needs.

2.4.2 Solar Thermal Design Plans:

The solar thermal water heating system was designed with IRC, ASHRAE, and

ASTM standards in mind. In order to determine the system size needed for the house the

water budget was used to calculate the maximum amount of hot water that could be drawn in

two consecutive competition days. Although the home would be built in Hawaii and is

designed for tropical climates, the HVAC and solar thermal systems need to be able to

25  

Page 34: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

perform for competition in Washington D.C. weather conditions for the end of September.

Because of this fact, the solar thermal system is over-sized for the Hawaii solar zone but is

correct for the Washington D.C. zone. When in Hawaii, one of the three panels can be

disconnected so that the system will not overheat.

Solar water heating for the house is provided by three superstructure mounted solar

thermal flat-plate collectors. Copper piping runs from the collectors, down the side of the

structure, and into the solar thermal storage tanks. The first tank is simply for storage while

the second, connected in series, is a solar thermal storage tank fitted with a backup heating

element. In the event that the collectors are unable to provide sufficient water heating, the

backup heater can make up the difference. A mixing valve is connected after the second tank

and takes hot water from solar storage and mixes it with cold water drawn from the fresh

water tank. The mixing valve is set to provide the house with water at 120 degrees

Fahrenheit in order to meet hot water requirements for dishwasher and for showers. The

storage tanks will reach temperatures upwards of 180 degrees Fahrenheit depending on sun

exposure and water usage. Blow-off valves are needed on each of the three panels and on hot

water tanks in the event that temperatures exceed safe limits. The flow of the water through

the solar thermal system can be seen in the solar water diagram on sheet M-603; also shown

in Figure 9 on next page.

26  

Page 35: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Figure 9:  A1/M‐603 showing solar water diagram.

2.4.3 Solar Thermal Design Specifications:

The solar thermal system consists of three solar thermal panels, two hot water tanks, a

solar thermal pump and controls, PEX and copper piping and fittings, three-way temperature

control mixing valve, and other valves. Detailed solar thermal equipment information can be

found in the project manual specifications sheets in Division 22: Plumbing and also Division

23: HVAC. The solar thermal equipment schedules are found in the teams full drawing set

on sheets M-601 and P-601.

2.4.4 Solar Thermal Construction and Disassembly:

Most of the construction of the solar thermal system must be done by professionals as

the copper piping has to be soldered well. The system must be able to handle temperatures

exceeding 180°F, and therefore many safety precautions are implemented to avoid

overheating. Blow-off valves are connected to each panel to alleviate pressure and steam to

27  

Page 36: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

cool the system. The solar thermal panels will be installed using a crane and will be

connected via junctions on the super-structure framing atop the home. Special care is taken

to ensure that the angles of the panels are not only correct but that they smoothly mesh with

the PV panels and super-structure louvers. A three-dimensional isometric view of the solar

water panels, copper piping, and hot water storage tanks can be found on sheet A1/M-902,

and also in Figure 10 below.

Figure 10:  A1/M‐902 showing solar water isometrics of solar water panels and tanks.

Sections of copper piping, pre-soldered locally, will then be soldered and connected

between the panels and the hot water storage tanks. The storage tanks need to be placed on a

platform in order to distribute the weight evenly over the ground and reduce damage. The

mixing valve and temperature sensors are installed and connected to the controls. The pump

is installed after the first storage tank with check and ball valves, and flow monitoring

controls and sensors are connected. Once water is delivered to the water tanks, the solar

thermal system can be primed and tested. During disassembly all water must be drained

from the system prior to dismantling. The same care taken in installation will be taken in the

disassembly process.

28  

Page 37: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

CHAPTER 3 – RESULTS AND DISCUSSIONS

3.1 SUMMARY OF TEAM HAWAI‘I’S SOLAR DECATHLON 2011

Combining aesthetics with functionality was the design goal of Team Hawai‘i’s Solar

Decathlon home and through the integrated efforts of architecture, mechanical and electrical

engineering students this goal was accomplished. With the strict code guidelines pertaining

to all sectors of the build, it was essential to meet these while maintaining the clean look of

the home. For the mechanical team it was very important to ensure proper design with

plumbing and HVAC ducting in order to increase efficiencies as well as to meet all code

requirements. The final design not only met code but also fit neatly in the under floor area of

the home, where components such as the heat-pump unit could still be accessed for repair.

The rest of the tanks and pumps are also efficiently and cleanly placed under the porch and

are hidden from sight. Even the copper piping running from the solar thermal panels run

under the superstructure and are not easily seen.

Keeping our mechanical equipment hidden, however, was not the main focus of the

team. Efficiency and innovative design were the driving forces that brought about many

unique systems like the internalized geothermal heat-pump application. Being the only team

implementing a very new and expensive building technology like phase change materials was

challenging but also very rewarding. Through this research it was found that there are very

high possible efficiency gains and energy savings with PCM in the thermal mass. Trying

new applications and pushing the envelope of what is normal in residential homes is the point

of the Solar Decathlon competition and Team Hawai‘i’s home design accomplished this task

on many different levels.

29  

Page 38: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Unfortunately, the ultimate goal of building the Team Hawai‘i solar home was not

reached due to financial constraints. As the construction phase kept being pushed back

because of issues in structural design, the student based construction team from the

community college deemed that building the home under shortened deadline would not be

realistic given their experience level and limited fabrication equipment. The team leaders

decided to contract a few local companies to assist in finalizing designs and beginning the

complex fabrication of the home’s steel rib structure. However, final estimates began to

come in from the contractors and yielded numbers far above the team’s original construction

projections. Because much of the funding for building was coming from the University and

Colleges, the decision on whether to proceed with the project was ultimately up to a board

deans, the University Chancellor, and the Principle Investigator; David Rockwood of the

School of Architecture. David has been involved with the project from the beginning and he

very reluctantly agreed with the other professors and deans that the project would not be

completed on-time, nor on-budget, and therefore Team Hawai‘i would officially withdrawal

from the Solar Decathlon 2011 competition in the summer of 2011.

With hopes to compete in Solar Decathlon 2013, Team Hawai‘i’s members continued

final designs through completion and each group submitted and presented within their own

colleges and departments. Although Team Hawai‘i was unable to physically put the uniquely

efficient design to the test, the whole process was a huge learning experience for everyone

involved and it brought together colleges that wouldn’t normally work together on such a

large university wide project.

30  

Page 39: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

SECTION 2:

REVIEW AND ANALYSIS OF HUMIDIFICATION DEHUMIDIFICATION

DESALINATION PROCESSES WITH FOCUS ON DIRECT CONTACT

CONDENSATION

(Gerindtec Company’s solar powered desalination unit using MEH technology in India, September 2010)

31  

Page 40: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

CHAPTER 4 - INTRODUCTION TO WATER

DESALINATION

4.1 BACKGROUND ON FRESH WATER NEEDS

The need for fresh water is a growing concern for many people in countries all over

the world and especially those in isolated communities. The conservation and replenishing

of the world’s fresh water sources is of pivotal importance for the next generations.

However, in places where rain fall is scarce, simple conservation will not provide relief. The

use of desalination processes to create fresh water from saline water sources, such as

seawater or brackish water, is dramatically growing in certain countries, especially in gulf

areas. The primary large-scale desalination facilities in the world use the reverse osmosis

(RO) process or the multiple stage flash (MSF) distillation process. These processes are

ideal for coupling with power plants to utilize waste heat or quick electricity to aid in the

reduction of the desalination energy costs and demands.

The major need for fresh water exists in developing countries where large-scale plants

like this are few and far between. The use of small-scale decentralized solar powered

desalination systems is much more realistic for areas where water need is high, money is low,

and solar insolation is high. The humidification dehumidification (HDH) desalination

process coupled with PV energy generation and solar thermal water heating has been a focus

of study in recent years for these decentralized applications. The optimization of the many

different types of HDH desalination processes has been explored by many researchers from

all over the globe in order to validate their effectiveness. In order to optimize these current

HDH systems, various computer models have been used to analyze these systems and then

32  

Page 41: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

compare with experimental results to determine the parameters which have the greatest effect

on the performance and production rates. The effectiveness of these different models will be

explored and compared to determine which are the most suitable to obtain accurate fresh

water production rates. Based upon the several process methods the most common

optimization findings will be identified and discussed. The most viable systems and methods

will be found and verified from multiple sources. These top systems, modeling methods,

optimization parameters, and flow processes will be consolidated to present the most

productive and efficient HDH desalination process that can be further developed.

4.1.1 The Global Need:

The rain cycle is a naturally occurring process of fresh water production from saline

sources and through it rivers, lakes, and underground aquifers can be replenished.

Unfortunately there are many locations in the world where this natural fresh water generation

process does not occur on a regular basis and will sometimes not occur for years at a time.

This rain cycle, however, can be replicated through a method known as the humidification

dehumidification process of thermal desalination. This simple process was first mimicked by

the introduction of the solar still which can be dated back to the fourth century before Christ,

when sailors used it to desalinated seawater on long voyages. Since then a great deal of

advancement has been made in technology and therefore much more effective desalination

processes have been implemented for large-scale water desalting for use in industrial

applications as well as for providing nearby communities with a potable water source. In

recent history the true need for fresh water has become increasingly apparent, especially in

developing countries where population growth and drought have devastated the land and the

people. This growing need is the basis for this research and the goal is to show the potential

33  

Page 42: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

of solar powered HDH desalination processes in developing regions for use as a manageable

constant water source for the people around the area. The seemingly unquenchable global

need for fresh water is described in detail by the Progress on Drinking water and Sanitation

2012 Update; compiled by UNICEF and the World Health Organization (WHO) [1]. The

findings of this progress update are outlined in the following.

UN-Water Report for 2012 -

Every two years, UNICEF and the World Health Organization (WHO), compiles a

report describing the global status of water supply and sanitation development and also on

the progress made towards the related targets from the Millennium Development Goals

(MDG). Their primary MDG interest is Target 7c - reducing by half the proportion of people

without sustainable access to safe drinking water and basic sanitation between 1990 and 2015

[1]. This WHO/UNICEF program, known as the Joint Monitoring Program (JMP) for Water

Supply and Sanitation, collects data sets based upon information gathered from household

surveys and censuses to report on the advancement of water supply and sanitation for every

country in the world. Although accurate monitoring may not be available in all countries, the

JMP has continually produced reliable data to keep the world informed on these most

important figures. The estimates provided in the new 2012 report present the status as of the

end of 2010. This 2012 report bears very exciting news that the MDG drinking water target

was successful as of 2010, which is five years ahead of the target goal of 2015 [1]. These

improvements for developing regions can be seen in Figure 11, which also shows all

developing regions compared with the whole world. The MDG sanitation target,

unfortunately, will most likely remain unreached as of 2015 [1].

34  

Page 43: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

There are huge disparities in the numbers between rural and urban areas and the

overall percentages, which show “success” for water supply improvement goals, do not

accurately portray the truth in the many developing countries. These disparities are of great

concern and much of the 2012 JMP report focuses on this issue. Countries in sub-Saharan

Africa and Oceania are the most affected by these rural-urban disparities and are a primary

focus for efforts to drastically increase coverage as well as promote global monitoring of

drinking water quality and sanitation progress [1]. These disparities between rural and urban

areas can be seen in Table 1, on the next page. The disparities aside, there has been much

improvement world-wide with over 2 billion people receiving access to some form of

improved water source and 1.8 billion gaining access to improved sanitation facilities

between 1990 and 2010 [1]. Many of the countries that showed the most improvement were

also facing large population growth, making these gains even more impressive, although the

rapid growth can also reduce the value of some of these numbers.

Tragically, there are still over 780 million people without access to improved

drinking water sources and a staggering 2.5 billion lack improved sanitation [1]. If these

trends continue, estimates for 2015 show 605 million still lacking improved drinking water

sources and 2.4 billion without improved sanitation [1]. Since improvement in water supply

and sanitation go hand in hand, for the most part, the efforts of both are in connection but yet

the numbers seem to show great leaps for water supply and much less so for sanitation. This

may be due to discrepancies in data sets and census information; which shows the importance

of improved monitoring systems in order to know where the most need for each region exists.

For these reasons UNICEF and WHO are attempting to develop new water, sanitation and

hygiene goals, targets and indicators for beyond 2015 [1]. These new indicators and methods

35  

Page 44: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

of monitoring could potentially report not only on the availability of fresh water sources and

sanitation facilities but on the safety, quality, reliability, and sustainability of these sources

and facilities [1].

 

Figure 11: Drinking water coverage trends by developing regions, 1990‐2010 [1].  Table 1: Disparities between rural and urban areas in water sources, 1990‐2010 [1].  

36  

Page 45: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

4.2 BACKGROUND ON WATER DESALINATION

Desalination methods can be categorized into two process types; thermal and

membrane processes. Thermal, or phase-change, processes use heat to bring a saline water

source to the point of evaporation, after which the pure water vapor is condensed and

collected to produce fresh water. Membrane processes use a semi-permeable membrane to

separate concentrates from fresh water by either applying an external pressure with use of

pumps or by using an electric current to move salt ions through an ion exchange membrane.

Both thermal and membrane process types need some source of energy to produce fresh

water and that energy generally will come from the burning of fossil-fuels; whether it be

through direct heating or through the use of electricity. In order to alleviate these energy

needs waste heat can be utilized from power plants or other sources; also renewable sources,

such as solar or geothermal, can easily be harnessed for this purpose. When renewable

sources or waste heat are used for desalination the result is much cheaper production costs,

making desalination much more viable for use in potable water production.

The history of desalination methods and processes as well as the most current

technologies are described in some detail in the following sections. The thermal processes

are outlined first; beginning with the simple solar still, moving on to the largest producing

thermal process today of multi-stage flash distillation (MSF), then multiple effect distillation

(MED), and finally the thermal and mechanical vapor compression (T/MVC). The many

different systems and configurations of the humidification dehumidification thermal process

will be described in the next chapter. After the thermal processes, the membrane processes

are described; beginning with the world’s largest producer of reverse osmosis (RO), then the

37  

Page 46: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

electrical current based process of electrodialysis reversal (EDR), a brief about nanofiltration

(NF), and finally some other ion membrane processes and their applications.

The global breakdown of the current percentages for desalinated water production is;

RO with a majority of 53%, MSF following at 25%, MED generating 8%, ED with 3%, and

the all others representing the remaining 11% [2]. These desalination methods are used all

over the world and yet nearly 75% of the total desalinated water production occurs in only 10

top countries [2]. The four largest producers; the Kingdom of Saudi Arabia (KSA), the

United Arab Emirates (UAE), the United States of America (USA), and Spain, together

represent over 50% of the global production [2]. The majority of this production comes from

the use of RO and MSF process plants. The total capacity output per day of the top 10

countries and their corresponding share of the global production are shown below in Table 2.

Table 2: Top 10 desalinated water producing countries [2]. 

4.2.1 Thermal (Phase-Change) Processes:

Solar Still-

The use of solar energy to naturally produce fresh water from a saline source by

means of the humidification dehumidification process can be dated back to Greek sailors in

the fourth century BC, using seawater to get drinking water on voyages. However, the first

38  

Page 47: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

published work on solar desalination was in 1551 by Arab alchemists [3]. The first solar still

was designed and built by Carlos Wilson, a Swedish engineer in Chile in 1872. During

WWII a plastic inflatable still was developed by Telkes for use by the US Navy and Air

Force in emergency life rafts [4]. The basic solar still is a very simple design in which a

single basin still is used to hold salt water and is covered by some clear covering, usually

plastic or glass, which allows sunlight to pass through. The solar rays heat the salt water to

evaporation, this water vapor can then condense on the cool glass or plastic covering. The

condensed fresh water then travels by gravity to a collection area. This process is very

simple but usually has an efficiency of below 45% due to the inherent heat losses from the

glass or plastic. This energy loss is from the latent heat of condensation transferred from the

condensing water through the glass or plastic and lost to the ambient air.

Many variations of the solar still have been made over time to reduce these losses;

one of the most effective utilizes multiple effects to take advantage of the latent heat of

condensation and reuse this energy to preheat the water through different stages [5,6].

Because of this heat recovery the set up yielded a substantial 80% increase in the gain output

ratio (GOR: the ratio of the energy consumed to the energy input) compared with a regular

single stage still [5,6]. Although this setup produced a high GOR as well as higher fresh

water production quantities these values were only achieved with a constant hot water supply

at 90°C. If the system were to actually operate at this high temperature for a long period then

the scale formation would cause issues and maintenance would be difficult. Also, the low

heat and mass transfer coefficients in this unit would require operation at these fairly high

temperatures to be productive and evaporation and condensation surfaces would need to be

made of expensive metals. For these reasons the solar still, even with multiple stages

39  

Page 48: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

providing regenerative heating, is extremely limited in production and efficiency and because

of this many other processes have been researched and developed.

Multi-Stage Flash Distillation (MSF) -

The multi-stage flash distillation process currently is used in nearly 90% of all

commercial thermal desalination plants and, as noted above, represents nearly 30% of the

world desalinated water production. MSF plants in general produce around 100,000 m3/day

of desalinated water but on the extreme side can have rates nearing 1,000,000 m3/day [7].

The reason for this is because the MSF process is highly efficient on a large capacity and

especially when in connection with a power plant for use of waste heat. The MSF process

works by allowing a saline water source to enter an evacuated chamber which suddenly drops

the pressure (flashes) to produce water vapor. This flashing process is repeated through

multiple champers with successively decreasing pressures and increasing temperatures.

Once through all the flashing stages the water vapor is condensed by using the cool source

water, thus preheating and conserving heat. The MSF process requires an external steam

supply around 100°C, which would ideally come from waste heat from a power plant. The

limiting factors for this system are determined by scaling formation at the peak temperatures.

Multiple Effect Distillation (MED) -

The process of multiple effect distillation is similar to MSF in that it utilizes multiple

chambers to increase the water vapor concentration and provide regenerative heating.

However, MED relies mainly on heating to achieve evaporation, as opposed to flashing or

drastically dropping pressure in MSF. The MED process is made up of cascading chambers

in series within which the pressure is reduced for each stage and the steam produced in each

previous stage used to heat the saline solution in the next stage. The more stages the more

40  

Page 49: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

effective these systems can be but costs limit the number of stages that is realistic. MED is

second to MSF as a commercially used process for fresh water production. The MED

process is generally operated at fairly low temperatures, usually below 70°C, which helps to

reduce the build of scale formation. The largest MED plant in the world began operation in

April 2009 and is located in Jubail, Saudi Arabia. This large-scale plant is capable of

producing above 800,000 m3/day of desalinated water [8].

Thermal or Mechanical Vapor Compression (T/MVC) -

The distillation process of vapor compression employs compressed super-heated

water vapor to heat the saline water source to the point of evaporation. The compression of

the vapor for heating can be produced by either a thermal or mechanical method. This

compressed vapor has much higher temperatures and pressures and is able to heat the original

saline feed water source very quickly. The thermal compression method takes steam from an

external source which comes from an ejector system, and makes it possible to recycle vapor

produced from the distillation process. The mechanical compression method can be

accomplished through a compression turbine and can be done at normal atmospheric

pressures or within a vacuum. When using the vacuum approach the distillation process is

more efficient but costs to generate the vacuum can be high. In both MVC and TVC the

condensation of the water vapor is done by heat exchanging condenser and because of the

high temperatures allows this regenerative heating to create more vapor. The vapor

compression method is very effective in heat regeneration but because of the high energy

demands needed to produce compressed vapor, the costs associated can be also be high.

Since VC is not as capable at producing effectively on a large-scale it is generally

used for smaller scale production. Australia used to depend on VC for nearly 18% of its

41  

Page 50: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

water production from desalination in 2002; however, since then RO process plants have

taken over and drastically reduced the number of VC process plants [8].

4.2.2 Membrane Processes:

Reverse Osmosis (RO) -

Reverse osmosis large-scale industrial plants account for nearly 80% of all membrane

process fresh water production in the world and 59% of the world production. The largest

RO plant in operation to date is the Ashkelon plant in Israel, which is capable of producing

330,000 m3/day of desalinated water [9]. The use of this process for large-scale water

production is only in competition with the MSF process. The RO process is a membrane

filtration method which can remove large ions and molecules from a solvent solution by

applying an external pressure to reverse the natural flow of the solvent. This natural flow of

the solvent from an area of low solute concentration to an area of high concentration is the

normal osmosis process. This flow across a membrane to equalize the solute concentrations

is what causes osmotic pressure. Thus, by inducing an external pressure and forcing the

reverse flow of the solvent across the membrane, the solute can remain on the pressurized

side while the pure solvent is allowed to pass through to the other side. This reversal of the

natural osmotic process flow is therefore called reverse osmosis. Standard membrane

filtration uses a straining mechanism by particle sizes and is mostly dependent on the

membrane construction, while RO uses a diffusive mechanism and is mostly dependent on

pressure and solute concentration. The pressure at which the reverse osmosis can be

productive is directly proportional to the solute concentration, and therefore this pressure and

concentration must be optimized to maximize production rates. For these reasons, RO is

42  

Page 51: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

ideal for use in drinking water purification from saline sources, such as seawater, to remove

salt ions and other concentrates from the pure water molecules.

Electrodialysis Reversal (EDR) -

Electrodialysis reversal, or EDR, is a desalination process which has been

commercially used since 1960 and, like RO, is a membrane process driven by electricity to

separate ions from the pure water molecules. Unlike RO, the EDR process implements an

electric current which is sent through the solvent solution to cause the movement of the

dissolved salt ions through the membrane. The membrane used for EDR is also different

from RO and is made of stacked layers alternating between cationic and anionic ion

exchange membranes. The direction of the ion flow through these membranes is changed by

reversing the polarity of the applied electric current. Although EDR can be used to

desalinate water for drinking purposes, the production values are generally low and better for

small-scale as opposed to large-scale RO plants.

Nanofiltration (NF) -

The method of nanofiltration is a membrane process which operates in much the same

way as reverse osmosis. The membrane developed for nanofiltration has pore sizes smaller

than those in RO and also use pressure to create flow across the membrane. The pressure

needed to create this flow is much less than that for RO and as a result the process can use

considerably less energy. The NF process is subject to fouling and scaling just as in other

desalination processes but can be more costly to the system efficiency since the filter pore

sizes are much smaller. For this reason, nanofiltration is generally used to process water with

lower total dissolved solid levels, such as surface water or groundwater. NF is being more

commercially employed in food processing for demineralization and disinfection. Although

43  

Page 52: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

NF has potential in desalination, currently the process has not shown promise as a large-scale

producer nor as efficient for small-scale applications. NF does show much potential as a

further filtration process, in conjunction with another desalination method (such as RO), to

soften and remove organic matter.

Other Desalination Processes -

Some other processes, such as the ion-exchange and the gas hydrate process, are

extremely effective at removing salt ions as well as any others from a solution. These

processes tend to be much more expensive on a large-scale and are designed more for the

removal of almost all dissolved solids. With purity levels around less than ten parts per

million (< 10 ppm), these processes far exceed the requirements for desalination for potable

water and would also remove many of the necessary nutrients found in water. Therefore,

these processes tend to be needed for applications where high purity is required such as in

hydrometallurgical, metals finishing, chemical and petrochemical, pharmaceutical, industrial

water, semiconductors, power engineering, and the nuclear industry.

44  

Page 53: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

CHAPTER 5 – THE HUMIDIFICATION

DEHUMIDIFICATION THERMAL DESALINATION

PROCESS

5.1 HUMIDIFICATION DEHUMIDIFICATION (HDH) PROCESS

The humidification dehumidification thermal process is one of the more simple

desalination methods and is based on the rain cycle. The HDH process works in much the

same way that rain is created from seawater in the natural water cycle; seawater (or saline

source) is heated by solar rays to the point of evaporation and then the water vapor is cooled

and condenses as pure water. A HDH plant simply concentrates and expedites this natural

water cycle through the use of solar thermal water heating panels, pumps, and the separation

of humidification and dehumidification into separate thermally insulated chambers. In

general, a HDH system is comprised of a humidification (evaporation) chamber, a

dehumidification (condensation) chamber, solar thermal panels, piping and pumps, and air

heaters and fans (if applicable). Many different variations of the HDH process have been

developed to maximize efficiency and production rates as well as reduce costs. The multiple

stage humidification process is a common adaptation of the general HDH system in which

multiple stages of humidification are used to maximize the water vapor content before

moving to dehumidification chamber. This allows for increases in fresh water production in

the condensation tower but the more stages used in a system the higher the costs will be. A

simple diagram of an HDH system can be seen on the next page in Figure 12.

45  

Page 54: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Figure 12: Simple HDH diagram with solar collector. 

5.1.1 HDH Classifications:

The HDH process can be classified into a multitude of configurations based upon

cycle, heating type, and energy usage method. There are two cycle configurations; the

Closed-Water Open-Air cycle (CWOA) and the Closed-Air Open-Water cycle (CAOW). As

the name would indicated, the CWOA cycle (in general), has a closed loop for the water flow

from the cool saline source through the condensation piping, where it is pre-heated collecting

the latent heat of condensation. This regenerative heating is followed by solar heating

through the panels. The heated saline water is then pumped into the humidification chamber,

where it meets air flowing in counter-current. The excess saline water not evaporated then

flows down to be added back to the saline feed and then around the loop again. The open air

flow through this cycle begins as relatively cool dry air is blown upward through the

46  

Page 55: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

humidification chamber where it meets the warm saline source and ideally reaches a relative

humidity of 100%. Once the saturated air leaves the evaporator it will enter the

dehumidification chamber where it will come into contact with the cool condensation piping

and form fresh water droplets. These droplets flow down and are collected into a fresh water

tank.

The CAOW cycle (in general) works in an opposite way; a closed air loop is first

heated by thermal collectors and flows up through the evaporator mixing with the saline feed

water and becoming humidified, then down through the condenser where it is dehumidified.

Since not all of the water vapor can condense the air retains some moisture and is sent back

through the heater and over the cycles will continue to rise in relative humidity eventually

ensuring that fully saturated air will always enter the condenser. The open water flow in this

cycle enters at the condenser where it is pre-heated through latent heat and flows down

through the evaporation chamber and is allowed to leave the cycle as the concentration of

saline in this water is now greater. For the most part, many of the systems seen in practice

try to find some way to capture the latent heat from the water that does not evaporate in the

humidification chamber and also to not waste water. Each cycle incorporates brine outflows

from the humidification chamber. Diagrams of the general CAOW and CWOA cycles can

be seen on the next page in Figures 13 and 14, respectively.

47  

Page 56: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

48  

            Figure 13: CAOW cycle diagram.                     Figure 14: CWOA cycle diagram.   

There are two types of heating that can be used in these cycles; air and water heating.

Both heating methods can be powered by solar energy and integrate panels of some sort. For

CAOW cycle configurations, the heating form of choice is generally air heating; however

both heating types are commonly employed to increase performance. When water heating is

used in this cycle the excess heat from the water not evaporated in the humidifier can be

transferred to new entering saline water through heat exchangers. Heating the water only in a

closed air loop would not be productive and is not seen in the literature. For the CWOA

cycle configurations, water heating is obviously always used and air heating is not because of

the inherent losses associated with heating air in an open loop because excess heat cannot be

easily exchanged as with water. In general water heating is much more efficient than air; at

times having a heat transfer coefficient 100 times greater.

The final classification is the type of energy consumed to power equipment and to

heat the water and/or air. The type of energy used depends mainly on the location of the

system. The goal is always to utilize as many renewable sources as possible without having

to rely on fossil-fuels. In most areas solar energy is available both to power pumps, through

Page 57: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

PV panels, and to heat water and/or air, through solar thermal panels. Geothermal energy

can be implemented when in a location where this renewable source can be found and readily

exploited without environmental impact or extreme costs. Standard forms of energy such as

electricity from the grid or from generators burning fossil-fuels are also always available, but

would do not provide reduction in energy usage nor conservation.

5.1.2 Performance Parameters:

In order to analyze the performance of these HDH systems various parameters have

been designated to accurately compare the many different configurations that have been

developed. The ones described and used in this paper are the gained output ratio (GOR), the

specific water production, the recovery ratio (RR), and the humidifier efficiency. There are

of course other efficiencies having to do directly with specific components; such as solar

thermal water panels, solar air panels, pumps, and ext. These maybe mentioned but will not

be the focus as they are unique to different systems, experimental set-ups, locations, and

other factors. The four primary performance parameters are described below.

Gained Output Ratio (GOR) -

The GOR is defined by the ratio of the latent heat of evaporation of the distillate to

the total heat input which, in the case of HDH, is absorbed by the solar collectors that are

used. The GOR is used by other desalination processes as well, such as RO and MSF, to

describe their efficiencies of water production to the amount of energy used. These large-

scale processes tend to have a GOR of around 8. It is important, however, to remember that

in general large RO or MSF plants require much larger amounts of energy, which generally

does not and cannot come from renewable sources.

49  

Page 58: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Specific Water Production -

This parameter measures the amount of desalinated water produced per the total solar

collector area per day. This value gives an idea of the effectiveness of the system to take

advantage of the solar energy that is captured for the production of fresh water. Since much

of the costs associated with HDH systems comes from the solar collectors, the specific water

production is a not only a good indicator of energy efficiency but cost effectiveness as well.

Solar thermal air panels can account for up to 45% of the total costs for systems with air

heating [10]. Solar thermal water panels cost less but still account for around 30% of the

total costs for systems with water heating [11].

Recovery Ratio (RR) -

The recovery ratio for a system is the ratio of the amount of fresh water produced per

the saline or brackish feed water. This ratio is generally fairly low for HDH processes when

compared with large-scale production processes like RO or MSF. Although because of this

low value there is much less brine output and thus less concern for scaling occurring inside

the system. RO and MSF plants require complex brine pre-treatment processing and disposal

methods, while these are not needed for HDH systems. When the saline source water is re-

circulated the RR can be higher but this will also increase the saline concentration of the feed

and therefore increase brine blow down and then may require some pre-processing.

Humidifier Efficiency -

The efficiency of the humidifier can be evaluated using the following equation:

η = (ωout - ωin )/(ωout,sat - ωin ) ,

where ωout is the outlet absolute humidity, ωin is the inlet absolute humidity, and ωout,sat is the

outlet absolute humidity at saturation. When the efficiency of the humidifier reaches unity

50  

Page 59: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

this means that the outlet absolute humidity is at the saturation point. This is the primary

goal of the humidification chamber because when there is saturated air entering the

condensation tower it always for maximum fresh water production. In general, this

parameter is used in systems where the humidification chamber uses packing material which

is wetted by spray from the top of the chamber.

5.2 LITERATURE REVIEW OF HDH SYSTEMS and COMPONENTS

The following is a brief overview of the findings from various different

configurations of HDH systems which have been developed, built, modeled, tested, and/or

studied by others in recent desalination literature. The systems are grouped into CAOW

systems and CWOA systems, and then divided by heating type. The different designs used

for the humidification and dehumidification chambers are also described and compared in

some detail. The common heat exchanger types and methods used to provide heating and

also help reduce heat losses are explained and contrasted as well.

5.2.1 Closed-Air Open-Water (CAOW) Systems:

For systems which used essentially CAOW cycles both types of heating, water and

air, can be made effective and in some cases both were made functional. The setups that

used water heating only all were able to obtain maximum GOR and specific water production

performance values which corresponded directly to an optimal water mass flux. In some

cases this was done experimentally and others through modeling, but many were able

compare both results and find consistent relations between them. The flow rate of the saline

source through solar collectors also has a large effect on the heat transfer performance

experienced. The movement of the air through these systems was also varied; in general the

51  

Page 60: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

flow rate of the air did not have a dramatic effect on any of the performance parameters. A

GOR value of between 1 and 5 was found for most systems [12]. The high end values were

generally obtained by means of the recovery of the latent heat of condensation through pre-

heating. In one case, a new process called multiple effect humidification (MEH) was

presented which was able to achieve the largest GOR value of 5 [11]. The MEH

configuration implements a continuous temperature stratification method where vapor from

the evaporator is directly extracted at certain elevations along the chamber and injected into

the condenser at the same level [11]. This process allows for a small temperature difference

between the humidifier and dehumidifier which allows for higher heat recovery. The high

recovery of the latent heat means a lower energy demand and therefore a greater GOR value.

The MEH method also experienced higher values for specific water production and also

recovery ratio. Another method applied to this MEH process that produced larger GOR

values was the integration of thermal storage tanks. Thermal storage tanks can be used

primarily to reduce the start-up energy and time demand. By storing excess heat in tanks it

can be used at a later time when heating needs increase; for example when the suns intensity

drops due to cloud cover or time of day. Also with enough thermal storage 24-hour

operation can become feasible and more cost effective [11].

For those using a CAOW cycle with air heating only the temperature of the air was a

large factor in the absolute humidity which could be achieved through the evaporator. When

air temperatures where insufficient the low absolute humidity outlet drastically reduced the

water production from the condenser. This led to a low values for the humidifier efficiency.

Multiple stage systems were developed by some to raise the humidity values. This was

accomplished by having multiple stages of air heating and also humidifying in separate

52  

Page 61: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

chambers. The multiple humidification and heating steps produced increases in the absolute

humidity before entering the condenser, increasing total humidifier efficiencies, and boosted

fresh water production. Since the increase in production came only with additional air

heating panels, the specific water production values did not change much. Also, because of

the increased costs from multiple humidification chambers and additional solar thermal air

panels did not validate the production increases. The GOR values for most of these systems

were also low due to the much lower heat transfer coefficient associated with air heating.

Heat losses from the warm air to the incoming cool saline water source in the evaporator

were also experienced for most because this heat cannot be as easily recovered through heat

exchangers, as with water heating cycles.

For those systems where water and air heating were combined the advantages seen

were not extraordinary and costs generally outweighed the benefits. The overall findings for

systems using the CAOW cycle were that water heating is best with a maximum production

water flow rate being obtained for most. The use of the MEH process can greatly increase

the recovery of latent heat, decreasing energy demands for water heating and increasing the

GOR value. Rises in both specific water production and recovery ratio could also be seen in

the MEH systems. Overall, in order to produce higher values for all performance parameters

the primary goal is to increase the amount of heat recovery and regeneration from the water

source. This can be done through many means, but the best methods are the simplest which

also can decrease the cost per fresh water production.

5.2.2 Closed-Water Open-Air (CWOA) Systems:

For those systems seen that used the CWOA cycle all utilized water heating and none

air heating due to the inherent losses associated with heating air in an open cycle. Most of

53  

Page 62: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

the systems found that the higher the temperature of the water entering the humidifier the

greater the fresh water production. This did not always mean an increase in the specific

water production as this value is dependent on the amount of solar panels needed to provide

this heat to the water. One issue that all noticed with this CWOA cycle was that if the

recycled saline water, not evaporated in the humidifier, is not cooled enough before its

reentry into the condenser then it would be too warm to allow for maximum condensation of

fresh water from the warm humid air. To reduce the temperature of the re-feed saline water,

heat exchangers were introduced by some and found increased performance of the condenser

but by removing this heat, additional heating is required before entry to the humidifier. This

would defeat the purpose and advantage of using a closed water loop.

Unlike the CAOW cycle, both optimal air and water flow rates were found by most to

yield the best performance of the specific systems at a set water temperature. This means

that much more adjustment is necessary for this cycle in order to optimize and since water

temperatures in a real world application would vary throughout the day; it would require the

use of monitoring devices and automatic adjustment controls. The controls and monitoring

needed would dramatically increase the total system costs and would not validate the

increase in performance values. Some were able to achieve these optimal conditions and

maintain them, but this was only accomplished under ideal laboratory conditions. Through

the use of highly efficient humidifiers and optimization controls and monitoring, these

idealize laboratory systems were able to achieve higher water production values than CAOW

systems. This process, however, is very hard to maintain and not only requires the use of

advanced equipment but also constant monitoring by skilled operators. Although it is

exciting to see high production rates like these, it is unrealistic to develop a system like this

54  

Page 63: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

for a remote region where qualified operators could not be available on-site. Also, high costs

and real world conditions would drastically reduce the potential of systems such as these.

5.2.3 Humidifier/Evaporator:

Humidification chamber design is imperative to the performance of the overall

system as it is the first step of the process and without the achievement of high humidifier

efficiency then water production as well as reduction of energy usage cannot be obtained.

The primary needs for successful humidification are heat and surface area. The inlet water

and/or air temperature into the humidifier has a drastic effect of the performance; without

high enough temperatures evaporation cannot occur. The contact surface area between the

entering dry air and water must also be maximized in order to increase the effectiveness of

the evaporation process. Although there are various ways to achieve evaporation, the most

commonly used and accepted method is the integration of spray towers with a packed bed

concept. Spray nozzles at the top of the humidification tower provide direct water to air

contact and a nice distribution of the feed water throughout the chamber. In combination

with a packed tower, the spray nozzles cover the packing material with water droplets,

providing maximum contact area between the water and air.

The greatest difference between humidifiers is the type of packing material that can

be implemented to increase this contact area. Many different mediums can provide the

needed distribution of water droplets, ranging from the simple and natural to the very

complex and manufactured. Some of the packing materials seen in the literature were;

fleeces, cottons, wood materials, plants, plastics, honeycomb paper, corrugated cellulose

material, and canvas. When looking purely at surface area, the best packing comes from

manufactured grid patterns that are generally made from a plastic to reduce heat transfer

55  

Page 64: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

increase longevity. Other more natural materials would not last long, might degrade

releasing particulate into the water, and could also absorb heat. Those materials that would

absorb the water may be good for saturation but over time would degrade and require

replacement, costing time and money.

As opposed to spray nozzles, a trickle effect has been used by some to saturate a

vertical medium, or packing. A bubble method was also seen, working in the opposite way

of a spray tower, where the chamber is filled with feed water and then the air was injected at

the bottom creating small bubbles. As the bubble rise through the saline water the air inside

becomes saturated and upon reaching the surface of the water, releases and merges into

humidified air, which can then proceed to the condenser. This method depends highly on

bubble formation, size, and interaction and is highly unpredictable.

The spray nozzle tower with packing material being the optimal design choice, the

next goal is to maximize the absolute humidity of the air leaving the humidification chamber.

This humidity increase can come from varying the height of the tower, the type of spray

nozzles, the flow rate of the spray, distribution of the spray, and the density of packing

material. These features can be varied through various means and are specific to the systems

in which they reside. The MEH method takes optimization to another level, taking

evaporated vapor from the humidifier at varying heights and injecting into the condenser at

corresponding heights to ensure consistent temperature stratification between the two towers.

As mentioned earlier, this method is highly effective as it increases heat recovery which

increases the GOR and specific water production values. However, the complexity of this

design increases overall costs and maintenance needs.

56  

Page 65: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

5.2.4 Dehumidifier/Condenser:

The design of the dehumidification chamber is something that varies drastically from

each system as there are many different methods to accomplish the task of condensing the

humidified air coming from the evaporator. One of the primary goals of condensation is to

create the greatest temperature differential between the warm humid air and the cooling

medium upon which the fresh water molecules can condense. For HDH systems the cooling

is generally provided by incoming feed water in order to preheat the feed water source before

further heating and entrance to the humidifier. Therefore, the cooler the original feed water

source, the better the condensation rate. The temperature of the humid air depends on the

water and/or air temperature entering the humidifier. As with the humidification tower, the

contact area between the humid air and the cooling medium is the other huge factor in the

performance of the condenser, along with the temperature differential. The most common

method used is indirect contact condensation upon heat exchangers in the form of conductive

piping through which the cool feed water can flow and preheat. Heat exchanger designs can

be enhanced using piping with connected fin arrays to maximize the contact surface area. In

these heat exchanger condenser types the kind of metal used is of great importance as heat

transfer characteristics vary greatly. Also, especially with simple piping coil designs, the

flow rate of the feed water needs to be adjusted in order to maximize heat transfer properties

and also ensure that the cooling fluid doesn’t gain too much heat inside the condenser,

reducing the needed temperature differential. These indirect contact heat exchanger type

dehumidification towers are ideal for the recovery of the latent heat of condensation, which is

captured by the cooling feed water and preheated.

57  

Page 66: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

In recent years the method of direct contact, as opposed to indirect contact methods,

has been integrated in condensation towers. The goals of this method are still the same;

increase the temperature differential and increase the contact area. However, the means by

which the condensation occurs is much different. Direct contact dehumidification towers

work and look very similar to the spray nozzle packed bed humidification tower, except for

instead of spraying heated saline water they spray cool fresh water. The cool fresh water

usually comes from the fresh water production tank after it has been cooled through an

indirect heat exchanger by the entering cool feed water; thus also accomplishing preheating

and recovering some of the latent heat of condensation. The cool fresh water is sprayed into

the condensation tower from the top and is distributed throughout the tower on the packing

material. The same plastic grid packing material as in the humidifier can be used for this as

well. Once the warm humid air from the humidifier comes into contact with the cool water

droplets and packing material the water vapor condenses. The use of this packing material

greatly increases the surface area to volume ratio and hence increases the heat and mass

transfer between the air and water in both the condensation and evaporation towers.

Although the packing material increases these values, much of latent heat of condensation is

lost to the air. The recovery of this latent heat of condensation in the condenser is more

effective through the use indirect contact condensation methods; where the humid air is

separate from the cooling fluid and heat transfer can occur across the conductive metal heat

exchanger. The use of an additional heat exchanger can recover some of this lost latent heat

and is described further in the following section.

58  

Page 67: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

5.2.5 Heat Exchangers:

Heat exchangers are a pivotal part of the HDH process as they are nearly involved in

every aspect of the process. There are two types of heat exchangers; those that incorporate

direct contact between the two mediums and those that use indirect contact. The two primary

locations in the HDH process where heat exchangers are needed are in the solar panels

heating the water and/or air prior to entry to the humidifier, and in the dehumidification

chamber. Air heating is accomplished through the use of solar thermal air panels which use

the direct contact method. The heating of the saline feed water can either be achieved

through direct contact with specialized solar thermal panels made to withstand salt content,

or through an indirect contact approach. This indirect approach begins with the direct

contact heating of fresh water in regular solar thermal panels which is then sent through an

indirect contact heat exchanger with the saline feed water flowing through the other side.

The advantages to using direct heating with specialized panels is that there are less

heat losses through piping and an additional exchanger, and also less equipment and costs.

However, since salt water thermal panels need to be made of non-corrosive metals they are

much more costly and also as the salt concentration increases, the thermal conductivity of the

saline source decreases. Also, overtime even the specialized panels and piping can

experience scale build up and require cleaning as to not decrease heating efficiencies. When

the indirect method is used there are fewer issues with scaling, specialized panel costs, and

also the direct heat transfer to the fresh water is much more effective than to the salt water.

The additional heat exchanger needed to make the indirect method possible also creates

additional costs and heat losses. As can be seen, there are many trade-offs between using

indirect or direct methods for the primary water heating of the saline source. Either method

59  

Page 68: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

can be effective but most choices are made based upon the different type of systems to which

they are being adapted.

The type of heat exchanger used inside the condensation chamber depends entirely on

the method of condensation that has been chosen. This was described in some detail in the

dehumidifier/condenser section. Direct contact exchangers use spray towers and indirect

contact exchangers use piping in connection with fin arrays to produce the fresh water

condensate. As with the primary heating of the saline feed water, if the direct method is

chosen, then an additional indirect heat exchanger must be used at a later point to recovery

heat. In this case, the addition indirect heat exchanger takes warm fresh water from

production and cools it with the original cold feed water, preheating it prior to primary

heating.

60  

Page 69: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

CHAPTER 6 – THE POTENTIAL OF HDH WITH DIRECT

CONTACT CONDENSATION

6.1 THE DIFFUSION DRIVEN DESALINATION (DDD) PROCESS

As was mentioned in the review of current HDH systems, the use of direct contact

condensation has been more popular and James Klausner, along with his researchers at the

University of Florida, have done much work using this condensation method and have coined

their process as Diffusion Driven Desalination (DDD) [13]. Other than the use of the direct

contact condensation method in the dehumidification chamber, as opposed to general indirect

film condensation, there are no large differences between DDD and other HDH processes.

For ease of explanation, DDD will be used to describe any HDH process that uses direct

contact condensation and not just the ones developed at the University of Florida (UF).

Generally speaking, the DDD process operates a CAOW cycle configuration with water

heating, but can also incorporate air heating. As mentioned in the Dehumidifier/Condenser

and Heat Exchanger sections, there are two sources of water flow through the towers; the

saline feed water through the humidifier and re-circulated cooled fresh water. This means

that there are actually two separate semi-closed water loops used in DDD systems. Also as

previous described, there is a choice of direct and indirect heating of the saline feed water

source, and if the indirect method is used then there would be a third water loop for fresh

water heating. The DDD process takes all of the most effective HDH components and

methods in combination to make a highly efficient and productive HDH process. A flow

diagram of the proposed “Innovative Diffusion Driven Desalination Process” is shown in

61  

Page 70: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Figure 15 below [13]. The primary focus of this chapter will be on DDD units like this, the

many variations developed by those at UF, and others.

Figure 15: Flow diagram for innovative diffusion driven desalination process [13]. 

6.2 ANALYSIS METHODS AND FINDINGS:

The optimization and analysis of the HDH process coupled with direct contact

condensation, and alike DDD systems, can lead to the increased potential for the HDH

technique to be a viable and productive method of desalination on a small-scale for

decentralized locations and island communities all over the world. Providing a renewable,

efficient, reliable, and cost effective form of fresh water production for those people that

need it most is the primary objective for small-scale desalination processes such as these.

Many different analysis techniques have been used by researchers to identify the key

enhancement operating parameters of various direct contact condensation HDH designs. The

62  

Page 71: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

majority of work performed on these systems has come from the University of Florida

research on their DDD process. Additional analysis of HDH with direct contact

condensation comes from work at the University of Hawaii at Manoa done by this author’s

predecessor and colleague Riley McGivern [14]. Riley was able to developed a simple

system which could be adaptable for small-scale renewable production in remote

communities and islands. Another collaborative work of engineers at the Beihang University

in China and the Technical University of Munich Germany presented a novel integration of

small spherical phase change material (PCM) elements as packing material in the direct

contact condenser [15]. The different optimization and analysis methods used by these

researchers, as well as an overview of their systems, are presented in the following.

To begin; the introduction of the DDD process in the Journal of Energy Resources

Technology initially presented it as a process with large-scale desalination production

potentials, capable of reducing cost values below that of RO and MSF [13]. The flow

diagram of the process introduced in this paper can be seen in Figure 15 on the previous

page. The system shown consumes waste heat from a power plant to provide the main feed

water heating and has two additional indirect heat exchangers; one water chiller for the fresh

water condensate and a regenerative heater. The water chiller uses the salt water source

drawn from a lower depth, giving cooler temperatures, to cool the exiting warm fresh water

production before it is sprayed into the direct contact condenser tower. The regenerative

heater attempts to capture the latent heat of condensation from the warm fresh water

production and transfer it to salt water drawn from the (less cool) surface water, before it

enters the primary heater. This process maybe effective given ideal location and salt water

source conditions but the use of two indirect heat exchangers, as opposed to one, could also

63  

Page 72: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

reduce the amount of heat recovered. The system shown also uses a closed-air loop driven

by a forced draft blower. The primary focus of the paper was a thermodynamic cycle

analysis in order to determine the performance bounds of their DDD process [13]. This

analysis was based on the rate of entropy generation per air flow rate in the humidification

chamber (or diffusion tower) which must be positive; and also upon the enthalpy of the brine

leaving the diffusion tower [13]. This exergy analysis was similar to many others seen in

literature from other HDH processes mentioned in the review. The conclusions yielded, as

others did, that with a higher inlet saline feed water temperature corresponding to an ideal air

to feed water mass flow ratio, there will be a minimum energy consumption rate [13]. They

also found that increasing the humidifier inlet water temperature increases the fresh water

production efficiency [13]. Based upon these results the authors were able to conclude that

the advantage to the DDD process is low exergy usage when driven by waste heat, with

satisfactory performance from inlet water temperatures as low as 50°C [13]. They went on

further to express the potential for inexpensive large-scale production.

The second major step for the UF team on their DDD process came through the

development of a detailed heat and mass transfer analysis to model the dynamic performance

of the cycle; this time based upon the flow diagram shown in Figure 16 [16]. This flow

diagram differs from the one original presented by Klausner and company in Figure 15. The

main differences being the flow of the fresh water production through the cooling heat

exchanger in connection with the flow of the saline feed water. The flow diagram also shows

an open-air loop where the air leaving the condenser is just exhausted as opposed to re-

circulated; this was done for ease of modeling of the system. The physical model developed

was based on a two-fluid film model with one-dimensional conservation equations for mass

64  

Page 73: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

and energy applied to a differential control volume, which can be seen in Figure 17 [16].

The control volume shown is just for the counter-current direct contact condenser, although

the model was created using both the humidifier and condenser. The model attempts to

describe the temperature of the water and air/vapor mixture as well as the humidity along the

heights of the towers from inlet of feed water to exit of fresh water. Three primary gradient

equations were developed for both the humidifier and condenser, however, since the direct

contact condensation is the focus, only these equations are shown in Eq. 1, 2, and 3,

respectively. Equation 1 describes the gradient of the temperature of the liquid water, TL,

along the height, z, of the condensation tower; where G is the air mass flux and L is the water

mass flux. Similarly, Equation 2 describes the gradient of the temperature of the air/vapor

mixture, Ta, along the height, z, of the condensation tower. Equation 3 describes the gradient

of the humidity ratio, ω, along the height, z, or the condensation tower; where Psat(Ta) is the

water saturation pressure corresponding to the local air temperature and is calculated using

an empirical representation of the saturation line [16].

65  

Page 74: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Figure 16: Flow diagram for the DDD process [16]. 

Figure 17: Differential control volume for the direct contact condensation tower [16]. 

(1)

66  

(2) (3)

Page 75: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

In order to evaluate the heat and mass transfer coefficients associated with both the

evaporator and condenser processes, modified Onda’s correlations were used. Through the

use of Onda’s relations, the mathematical model can be solved using an iterative guess and

check procedure along the height of both the humidification and dehumidification towers.

The primary goal of the model was to show the dynamic performance of the system through

a parametric study. The optimal heights of both towers could be obtained based on the air to

feed water mass flow ratio. Also, the exit air and fresh water temperatures could be found

based on air mass flux, as well as the fresh water production efficiency. An energy analysis

based only on the energy required to power pumps and blowers, assuming primary heating

from power plant waste heat, was also described and the variation of the energy consumption

rate with the air to feed water mass flow ratio found. This energy analysis yielded a prime

consumption rate of 0.0022 kWh/kgfw; which can be re-written as 2.2 kWh/m3 of fresh water

[16]. This energy consumption rate would be competitive with RO, MSF, and MED, but

since the energy usage is based only upon electrical needs for pumps and blowers, it is

unrealistic to compare. This work showed the potential for improvement of the DDD system

based on a heat and mass transfer analysis.

A further adaptation of the work done in the paper described above on the DDD

system was conducted showing the correspondence of the modeling outputs with that of an

experimental setup. The focus of this work was on the experimental setup’s use of twin

condensation towers; one with co-current flow and the twin receiving the counter-current

flow [17]. A schematic diagram of the DDD experimental facility with twin condensation

towers can be seen in Figure 18. The goal of this work was to include the co-current flow

condenser tower into the model and to compare both condenser tower computational data

67  

Page 76: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

with that of the experimental findings. The addition of the co-current flow required another

differential control volume with opposite flow directions; therefore a new set of three

gradient equations were used as well. The liquid and air/vapor temperature gradients

remained unchanged, but the humidity ratio gradient was just the negative version of that for

the counter-current flow [17]. The flow diagram for the iterative computation procedure

used for the modeling of the counter-current flow through the condenser is shown in Figure

19. The procedure uses a guess and check approach with fourth order Runge-Kutta iterative

process to find all the corresponding values at the next step up in the z direction of the tower.

This procedure is very similar to that for the co-current flow (with same inputs), but for this

one the iterations will begin at the top of the packed bed and work down, instead of starting

at the bottom for the counter-current flow.

After running the model and experiments with both the co-current and counter-

current flow condensers separately, the authors found that there was good correlation

between the two for both flow patterns. However, both results showed that the effectiveness

of the co-current flow condensation tower was dramatically degraded in comparison with the

counter-current flow for the same air mass flow ratio and inlet conditions; the difference in

the effectiveness being approximately 15% [17]. This reduction in performance was

investigated through the use of high-speed cameras to capture the formation and shape of the

liquid film upon the packing material [17]. The cameras showed that the wetting of the

polyethylene packing ring structures has a high likelihood of forming liquid bridges which

can block the air flow [17]. However, as mentioned in other works, the use of this plastic

packing material is ideal for surface area maximization and works well in the evaporator and

is also cheap and easy to replace [17]. Because of the formation of these liquid bridges the

68  

Page 77: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

use of a counter-current flow is necessary to better disrupt and break these bridges, which is

why the co-current flow probably lost so much effectiveness. The authors suggested the

further investigation of these liquid bridge formations in connection with packing diameters

and wettability.

Figure 18: Schematic diagram of the DDD experimental facility with twin condensation towers [17].  

69  

Page 78: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Figure 19: Flow diagram procedure for computation of the counter‐current flow condenser [17]. 

A similar work to the ones just described was developed by Riley McGivern in his

HDH system with direct contact condensation [14]. When comparing the flow diagrams of

Riley’s system in Figure 20 on the next page, to that of the flow diagram used for modeling

(with only counter-current flow) by Klausner and company, they are very nearly the same

except for Riley’s use of a closed-air loop and also solar thermal energy for water heating.

However, it should be noted that Riley’s experimental set up also used an open-air loop as

did Klausner’s. Riley was also able to show the peak performance characteristics of his

system through the use of the two-fluid flow model for a packed bed through the application

of mass and energy conservation to differential control volumes for the evaporator and

condenser towers. Through this he was able to describe the changing liquid, air/vapor

70  

Page 79: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

temperature, and humidity ratio gradients along the height of the towers. Riley’s results

showed the changing exit water temperatures for the evaporator and condenser plotted versus

the varying air volume flux, while keeping the water mass flux constant [14]. Good

agreement was found between the model and the experimental results. Riley noted that the

implementation of solar thermal panels for heating would be possible based on the modeling

and experimental results [14].

Figure 20: Flow diagram of Riley’s HDH system with direct contact condensation [14]. 

In order to take the analysis of the DDD system to the next level, Klausner and

company turned their focus to the further development of their heat and mass transfer

analysis into a transient one. One-dimensional conservation equations were again used to

derive the necessary, now no longer steady-state, equations. Through the application of

conservation of mass and energy to the liquid phase and the air/vapor mixture side of the

control volume shown in Figure 21; two first order partial differential equations (PDEs) in

time and space are found to describe the temperature of the liquid and air/vapor mixture [18].

71  

Page 80: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

The gradient of the humidity ratio to the height, z, is found in a similar manner as the steady-

state case. An additional equation describing the differential of the temperature of the

packing material with respect to time is also generated through the conservation of energy on

the packed bed [18]. This set of four equations is used to solve a transient model from an

explicit finite difference method with a uniform grid size defined for the evaporator and

condenser mesh [18]. The set of equations used for the condenser; with the humidity ratio

gradient to height, z, and then the temperature of the liquid, the air/vapor mixture, and the

packing material with respect to time and are shown in Equations 4, 5, 6, and 7, respectively.

Closure relations are required along with the use of Onda’s correlations for the heat and mass

coefficients on the liquid and gas side are used to complete the solution. The results yielded

good correlations between the model and experimental for the water and air temperatures, but

the humidity ratio values experienced a maximum deviation around 20% [18].

Figure 21: Control volume used for evaporator and condenser towers, showing the interactions 

between the liquid, gas/vapor, and solid packing material [18]. 

72  

Page 81: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

(4)

There are many applications for the transient modeling of the DDD process through

parametric studies to optimize operating conditions for varying water and/or air temperature

inputs [18]. Klausner, along with his team, decided to generate another paper which would

explore these applications focusing on that of coupling the DDD system with solar thermal

water heating [19]. This obvious combination has been explored in the HDH literature by

many others; however, Klausner and company were the first to publish about the transient

modeling of this specific process. With this most recent work, they have also become some

of the first to publish on the potential of the solar thermal panel integration. Although

Riley’s work did focus on the integration of the HDH cycle with direct contact condensation

with solar thermal heating, his model was used the steady-state conditions and therefore

could not input expected temperatures providing from a regular day of solar thermal heating.

In this work, “Solar diffusion driven desalination for decentralized water production”,

Klausner and corresponding author Alnaimat were able to show the expected production

values and energy consumption given the average solar thermal inputs for a clear day in

Jacksonville, Florida in the month of June [19]. They performed their analysis with a

73  

Page 82: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

specified number of solar thermal panels operating at set efficiencies. The solar array could

be varied for any system and location to provide the needed amount of thermal energy to

provide the optimal inlet feed water temperatures. This DDD process requires the use of

thermal and electrical energy, to heat the water and power pumps/blowers, respectively.

Therefore, a new electric specific energy consumption equation was also developed for this

application, which now takes into account the power needed for pumping through the solar

thermal panels and the major losses expected [19]. One of the primary findings boasted by

this work was the advantages of containing the latent heat of condensation within the system,

and not removing it through cooling as was done in the steady-state operation of their DDD

system in earlier works [19]. This idea is not novel and this recirculation and regeneration of

the latent heat of condensation has been achieved by many, including Riley and can be seen

in his system process in Figure 20. Also, it is notable, that when comparing this flow

diagram of Riley’s to the one used for the solar DDD process, shown in Figure 22, they are

very similar. The primary differences in these processes are the solar DDD’s employment of

multiple saline water tanks and the location of the fresh water cooling heat exchanger. The

location of the heat exchanger can have a drastic effect on the recovery of this latent heat and

will be discussed further in the following comparisons section.

There are many parameters which can be varied to analyze the system using this

transient model but the focus of this work was on the optimum operating mode. They

concluded that the best mode would be to use a delayed operating mode in which thermal

heat could be generated through the panels and stored prior to system startup [19]. They also

found through the parametric study that the air mass flux is a very important parameter and

this was also noticed by Riley is his work [19,14]. When using eight thermal panels for a

74  

Page 83: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

normal day in Florida, they found a maximum daily water production rate of 6.3 L/m2 of

collectors and an average specific energy consumption of 3.6 kWh/m3 of fresh water

produced [19]. From these findings Klausner and Alnaimat concluded that the solar DDD

system has high potential for small-scale fresh water production in decentralized areas [19].

Figure 22: Process flow diagram for solar diffusion driven desalination system [19]. 

Finally, there is one more performance analysis completed on an HDH process with

direct contact condensation which developed the novel idea of integrating phase change

materials (PCM) for the packing material. This work also performed a transient heat and

mass transfer analysis of their process using a different mathematic model than that executed

at UF by Klausner. This collaborative work between engineers at Beihang University in

China and the Technical University of Munich Germany [15] used a model that was

developed by an early work conducted in Brazil in 1999 [20] on possible fixed bed models

for pcm and sensible heat storage. In this early work by Ismail and company [20], many

75  

Page 84: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

different possible models were developed and shown; the one chosen for use by the

Germany/China team [15] was the continuous solid phase model. Through the application of

this continuous solid phase model in comparison with experimental findings they attempted

to find the effectiveness of small spherical PCM elements on the performance of the packed

bed condenser. The numerical solution of their one-dimensional model, which is made up of

a set of second-order parabolic PDEs, was done using MATLAB’s partial differential

equations solver called “pdepe” function [15]. After inputting the set of equations and

boundary conditions the “pdepe” solver is able to show the temporal and spatial evolutions of

temperature and vapor concentration fields of all the fluid and solid phases throughout the

towers [15].

The comparison of the numerical findings and the experimental was done in a

parametric analysis which investigated a number of parameters similar to those of other HDH

analysis but focused on the effects of the PCM thermal properties. The conclusions showed

that although in the initial startup of the system the PCM helped increase performance, when

steady-state operation was reached the thermal properties of the PCM actually decreased the

condenser effectiveness [15]. They also concluded, as did many others, that the air mass

flow ratio is of crucial importance on the system performance [15]. The authors proposed

that an investigation into a different packing material with high thermal conductivity, smaller

size, and lower cost than PCM could yield much better results as the PCM had poor thermal

conductivity at steady-state and very high costs [15].

76  

Page 85: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

6.3 SUMMARY OF ANALYSIS METHODS AND FINDINGS

There are many different approaches explored and presented above that all yielded

some important results for the potential of the HDH process with direct contact condensation

(or DDD process). Even though analysis methods varied drastically in complexity; from that

of a fairly simple exergy analysis to show operation bounds, to a highly involved transient

model with second-order PDEs to perform an accurate parametric study, they all provided

similar findings. Throughout these analysis methods the consistent findings were that the air

mass flux (or air mass flow ratio used by some) was the most important operating parameter.

Each system, however, was unique in what this optimum air mass flux would be to maximize

fresh water production and reduce energy consumption. Many other parameters were studied

and were optimized for each system and it is interesting to note that even though some

analyses were more complex the parametric optimizations were very similar.

The most interesting findings for this author came from looking at the differences in

the process setups and especially the many different iterations of the UF coined DDD

process, and comparing these with that of Riley McGivern’s system. Klausner and company

began with an exergy analysis and presented the DDD process as a lower cost large-scale

process with potential when coupled with power plants and using their waste heat, which

could rival RO, MSF, and MED [13]. These assertions were self-confirmed with a detailed

heat and mass transfer analysis of the steady-state operation through a parametric study and

energy analysis of a slightly varied DDD flow process (eliminating additional heat

exchangers). From this analysis Klausner presented a highly ambitions energy consumption

rate of 2.2 kWh/m3 fresh water, which as noted earlier, was only based on the electric energy

needed for pumps and blowers [16]. Klausner’s next work focused on the comparison of the

77  

Page 86: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

computer model with an experimental setup with a primary focus on the twin condensation

towers with co-current and counter-current flow. The primary findings from this work was

that the co-current flow condensation tower was ineffective and that through camera footage

the formation of liquid bridges on the packing material [17]. It can be inferred that the co-

current flow didn’t provide enough force to break these liquid bridges on the packing

material and therefore the condensation performance was drastically diminished. In the

transient analysis of the DDD process, the model showed good relation with experimental

results with temperature of the liquid and air, but the humidity ratio values were off by 20%

[18]. When comparing their set of equations with that of the ones performed in the PCM

condenser analysis with the continuous solid phase model, the equations were much simpler

and were not second-order parabolic PDEs. It can be concluded that to get good humidity

ratio or vapor concentration (as used in PCM analysis) relations, then the continuous solid

phase model should be used for any further transient investigations.

Finally, when looking at the flow diagram for the solar DDD system and comparing

with the diagram of Riley’s system, the location of the cooling heat exchanger for the fresh

water is different. In the solar DDD system; the fresh water production from the condenser is

dumped into a fresh water tank, fresh water is then drawn out by the pump and directed

through the heat exchanger where it is cooled by the entering saline feed water heading to the

saline feed water tanks. This flow process allows for the warm fresh water condensate

directly out of the condenser to mix and lose heat in the tank. The heat left in the fresh water

is transferred to the saline feed water which is also dumped into one of two tanks, again

allowing heat losses by mixing and through the tank. The little regenerative heating that

occurred at the heat exchanger is now lost and the saline feed water enters the solar collector

78  

Page 87: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

without being preheated effectively. Now, for Riley’s flow process; condensate from the

dehumidification tower is pumped directly to the heat exchanger allowing optimal heat

transfer to the saline feed water. The saline feed water is pumped directly from the saline

reservoir through the heat exchanger to be preheated right before it enters the solar seawater

heater. Although the DDD system proposed multiple “innovative” techniques, such as twin

condensers and the recovery and reuse of the latent heat of condensation, in the end these

methods were not very effective. The co-current tower was shown through experimental and

model results to highly degrade the condensation production [17]. Then, through a simple

flow process analysis, the heat recovery was shown to be less effective and when compared

with another flow diagram proved less energy efficient.

79  

Page 88: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

CHAPTER 7 – RESULTS AND DISCUSSIONS

Through this comparison and review of the many currently functional HDH process

configurations and modeling techniques the most effective systems have been identified and

analyzed in detail. Of the possible HDH cycle configurations, in general, the most effective

is the closed-air open-water cycle coupled with solar thermal water heating. The most

efficient humidification chamber design was found to use polyethylene packing material to

maximize surface area and spray nozzles to effectively cover this packed bed with the saline

feed water. This evaporation technique was found by most to be enhanced by adjusting the

air mass flux at a set water mass flux in order to provide the maximum humidity ratio at the

exit of humidifier. With a saturated air/vapor mixture entering the dehumidification

chamber, the goal now shifts to providing the greatest temperature differential between the

warm humid air and the cooling fluid, and also as with the humidifier to maximize the

surface area to volume ratio. In order to accomplish both of these goals in the condensation

tower design, the best method is direct contact condensation. Although the recovery of the

latent heat of condensation is better with indirect contact condensation heat exchangers, the

direct contact method increases the heat and mass transfer effectiveness through both

temperature differential and surface area. Therefore, the optimal condenser design will be

very similar to the evaporator and will have spray nozzles with a packed bed of polyethylene

grid rings. The spray for the condenser will use fresh water from production which has first

been cooled by entering saline feed water through an indirect heat exchanger. This heat

exchanger allows for both the recovery of some of the latent heat of condensation from the

warm condensate and also the preheating of the saline feed water. As was noted in the

comparison of the DDD processes, the placement of this heat exchanger in the flow process

80  

Page 89: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

is very important to the effectiveness of this heat recovery and regeneration. The most

effective placement is shown by Riley’s work in Figure 20.

The recovery and reuse of heat in the HDH process is of utmost importance to the

increased performance of the system. Thus the method and type of solar heating used is very

important. Both indirect and direct heat transfer methods can be used to provide the solar

thermal heating of the saline feed water source. Each method has its advantages and

disadvantages as described in detail in the heat exchanger section. In order to determine

which would be most effective, additional studies need to be performed on the efficiency of

new specialized seawater solar thermal panels and the longevity of such units analyzed for

scaling formation. There would be losses for both methods and therefore either could

potentially provide similar results over the long term.

Another important area of heat loss is in the water tanks, and one possible method to

reduce these heat losses would be the implementation of thermal storage tanks integrated

with phase change materials (PCM). The use of PCM was seen in a direct contact

condensation tower and its effectiveness at startup was productive, but during steady-state it

did not provide any increase in production. The further exploration of this PCM inside the

thermal storage tanks could increase the amount of heat retained, especially over a period of

time, such as the night. As the MEH system showed, the integration of regular thermal

storage methods allowed for the system to be run through the night and increase production

rates. Through the integration of PCM, these thermal storage tanks would be able to store

more energy at night and release it during the day time hours, potentially increasing

productivity even further.

81  

Page 90: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Finally, additional work on the material and grid design of the packing material rings

could yield an optimal packed bed which would not experience the same liquid bridging that

occurred for the DDD processes. Both of the works that performed transient analyses for the

DDD system and the PCM system, concluded that the packing material needed to be

improved with increased thermal conductivity and an optimal grid spacing. Of these

transient analyses, the one for the PCM system using the continuous solid phase model was

more successful in producing good relation for not only the liquid and air/vapor temperatures

but also for the humidity ratio or vapor concentration. Therefore, this continuous solid phase

model, as first described by Ismail [20], would be the best choice for any further transient

analyses of the HDH process with direct contact condensation. One potential future work

could then be conducted with the use of both direct and indirect methods of saline water solar

thermal heating using the continuous solid phase model while testing polyethylene packing

grids of varying spacing.

82  

Page 91: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

REFERENCES

[1] UNICEF and World Health Organization, Progress on Drinking water and Sanitation: 2012 Update. UN-Water Reports, 2012.

[2] ESCWA (Economic and Social Commission for Western Asia), Role of Desalination in Addressing Water Scarcity 2009. 2009 November, http://www.escwa.un.org/information/publications/edit/upload/sdpd-09-4.pdf.

[3] M.A.S. Malik, G.N. Tiwari, A. Kumar and M.S. Sodha, Solar Distillation, Pergamon, 1982.

[4] M. Telkes, Solar distiller for life rafts, US Office of Science, R&D Report No. 5225, P.B.21120, 1945.

[5] F. Graeter, M. Duerrbeck and J. Rheinlaender, Multi effect still for hybrid solar/fossil desalination of sea and brackish water. Desalination, 138 (2001) 111-119.

[6] J. Rheinlaender and F. Graeter, Technologies for desalination of typically 10 m3 of water per day. Desalination, 139 (2001) 393-397.

[7] F.F. Alshareff, Investment opportunities in the desalination sector of the Kingdom of Saudi Arabia resulting from privatization and restructuring. Saudi Water and Power Forum, Jeddah, (2008) 1-4.

[8] R. Clayton, A Review of Current Knowledge: Desalination for Water Supply. Foundation for Water Research, (2011) FR/R0013.

[9] Sauvet-Goichon, B., Ashkelon Desalination Plant - A Successful Challenge. Desalination 203, (2007) 75-81.

[10] E. Chafik. A new type of seawater desalination plant using solar energy. Desalination, 156 (2003) 333-348.

[11] H. Muller Holst, Solar thermal desalination using the multiple effect humidification (MEH) method. Solar Desalination for the 21st Century, (2007) 215-225.

[12] G.P. Narayan, M.H. Sharqawy, E.K. Summers, J.H. Lienhard, S.M. Zubair, M.A. Antar, The potential or solar-driven humidification-dehumidification desalination for small-scale decentralized water production. Renewable and Sustainable Energy Reviews, 14 (2010) 1187-1201.

83  

Page 92: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

84  

[13] J.F. Klausner, Y. Li, M. Darwish, R. Mei, Innovative Diffusion Driven Desalination Process. ASME Journal of Energy Resources Technology, 126 (2004) 219-225.

[14] R.S. McGivern, Humidification-Dehumidification Seawater Desalination System Driven by Solar Energy. A Thesis for Master of Science in Mechanical Engineering, University of Hawaii at Manoa, August 2010.

[15] T. Hu, A.H. Hassabou, M. Spinnler, W. Polifke, Performance analysis and optimization of direct contact condensation in a PCM fixed bed regenerator. Desalination, 280 (2011) 232-243.

[16] Y. Li, J.F. Klausner, R. Mei, Performance characteristics of the diffusion driven desalination process. Desalination, 196 (2006) 188–209.

[17] Y. Li, J.F. Klausner, R. Mei, J. Knight, Direct contact condensation in packed beds. International Journal of Heat Mass Transfer, 49 (2006) 4751–4761.

[18] F. Alnaimat, J.F. Klausner, R. Mei, Transient analysis of direct contact evaporation and condensation within packed beds. International Journal of Heat Mass Transfer, 54 (2011) 3381–3393.

[19] F. Alnaimat, J.F. Klausner, Solar diffusion driven desalination for decentralized water production. Desalination, 289 (2012) 35-44.

[20] K.A.R. Ismail, R. Staginsky Jr., A parametric study on possible fixed bed models for pcm and sensible heat storage. Applied Thermal Engineering, 19 (1999) 757-78 

Page 93: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

APPENDIX A: WATER BUDGET

Function Gal Events Notes

Hot Water Draws 240 15 16 Will Draw from Fresh Water Tank

Water Vaporization 3 0.75 4 Will Draw from Fresh Water Tank

Dishwasher 10 2 5 Will Draw from Fresh Water Tank

Clothes Washer 160 20 8 Will Draw from Fresh Water Tank

Solar Thermal Tanks 80* Tank Capacity (*Will draw from Fresh Water to Provide Hot Water)

Fire Suppression Tank 266 280 Minimum 266 gallons needed for Fire Suppression

Thermal Storage Tank 770 770 Thermal Storage Water Fill

Fresh Water Tank 450 Initial Fresh Water Tank Fill

Aquaponics 50* 500**

*50 gallons Team Provided for Irrigation. **Capacity of system after

grey water recovery.

Safety Factor 50 N/A

Totals: 1499 1500

Water Required: ~1500 Gallons

CalculationsWater Use

(Gallons)

Water Storage

(Gal)

Page 94: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

APPENDIX B: MECHANICAL SPECIFICATIONS SHEETS

DIVISION 21: FIRE SUPPRESSION

- SECTION 21 09 00: Instrumentation and control for fire-suppression systems - SECTION 21 13 00: Fire-suppression sprinkler systems - SECTION 21 24 16: Dry-chemical fire-extinguisher equipment - SECTION 21 31 13: Electric-Drive, Centrifugal fire pumps - SECTION 21 41 23: Ground suction storage tanks for fire-suppression water

DIVISION 22: PLUMBING

- SECTION 22 11 16: Domestic water piping - SECTION 22 11 23.26: Close-coupled, horizontally mounted, in-line centrifugal

domestic-water pumps - SECTION 22 12 19: Facility ground-mounted, potable-water storage tanks - SECTION 22 13 16: Sanitary waste and vent piping - SECTION 22 13 19.36: Air-admittance valves - SECTION 22 13 53: Facility septic tanks - SECTION 22 33 30.23: Residential, collector-to-tank, solar-electric domestic water

heaters - SECTION 22 41 00: Residential plumbing fixtures

DIVISION 23: HEATING, VENTILATION, AND AIR CONDITIONING

- SECTION 23 09 23: Direct-digital control system for HVAC - SECTION 23 21 13.43: Thermal mass-loop heat-pump piping - SECTION 23 21 23.13: In-line centrifugal hydronic pumps - SECTION 23 30 00: HVAC air distribution - SECTION 23 56 13.13: Heating solar flat-plate collectors - SECTION 23 71 13.23: Pressurized-water thermal storage tanks - SECTION 23 71 13.26: Phase change material for thermal mass - SECTION 23 81 46: Water-source unitary heat pumps - SECTION 23 84 16: Dehumidifiers

DIVISION 28: ELECTRONIC SAFETY AND SECURITY

- SECTION 28 31 46: Smoke detection sensors

Page 95: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 1

CENTRIFUGAL FIRE PUMPS 21 31 00 - 1

DIVISION 21: FIRE SUPPRESSION

SECTION 21 09 00

INSTRUMENTATION AND CONTROL FOR FIRE-SUPPRESSION SYSTEMS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Jockey Pump Controller.

B. Related Requirements

1. Fire-Suppression Sprinkler Systems (Section 21 13 00).

2. Electric-Drive, Centrifugal Fire Pumps (Section 21 31 13).

3. Ground Suction Storage Tanks for Fire-Suppression Water (Section 21 41 23).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. NFPA – National Fire Protection Association.

3. UL – Underwriters Laboratories Inc.

1.01 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Jockey Pump Controller.

1.02 QUALITY ASSURANCE

A. Certificates

1. UL certification of Jockey Pump Controller.

2. Compliance with IRC Section P2904 or NFPA 13D.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Firetrol® (or other manufacturer with similar product meeting all codes and requirements)

(www.firetrol.com).

Page 96: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 2

CENTRIFUGAL FIRE PUMPS 21 31 00 - 2

2.02 CONTROLLERS

A. Firetrol® FTA500 Jockey Pump Controllers.

1. For use with Fire-Suppression system to regulate pump and control system pressure.

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed and tested to Manufacturer’s requirements and IRC code.

END OF SECTION

Page 97: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 3

CENTRIFUGAL FIRE PUMPS 21 31 00 - 3

SECTION 21 13 00

FIRE-SUPPRESSION SPRINKLER SYSTEMS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Fire Sprinklers.

2. Fire Sprinkler Piping.

3. Valves and Fittings.

4. Mounting Brackets.

B. Products Installed But Not Furnished Under This Section

1. Fire Pump.

2. Fire Water Storage Tank.

C. Related Requirements

1. Instrumentation and Control for Fire-Suppression Systems (Section 21 09 00).

2. Electric-Drive, Centrifugal Fire Pumps (Section 21 31 13).

3. Ground Suction Storage Tanks for Fire-Suppression Water (Section 21 41 23).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. NFPA – National Fire Protection Association.

3. UL – Underwriters Laboratories Inc.

4. ASTM – American Society for Testing and Materials

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for all products included in section.

B. Shop Drawings

1. Submit shop drawings of Fire-Suppression System.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC Section P2904 or NFPA 13D.

1.05 WARRANTY

A. Manufacturer’s Warranty

Page 98: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 4

CENTRIFUGAL FIRE PUMPS 21 31 00 - 4

1. Fire Sprinklers: Products manufactured by Tyco® Fire Suppression & Building Products (TFSBP)

are warranted solely to the original Buyer for ten (10) years against defects in material and

workmanship when paid for and properly installed and maintained under normal use and

service. This warranty will expire ten (10) years from date of shipment by TFSBP. No warranty is

given for products or components manufactured by companies not affiliated by ownership with

TFSBP or for products and components which have been subject to misuse, improper

installation, corrosion, or which have not been installed, maintained, modified or repaired in ac-

cordance with applicable Standards of the National Fire Protection Association, and/or the

standards of any authorities having jurisdiction. Materials found by TFSBP to be defective shall

be either repaired or replaced, at TFSBP’s sole option. TFSBP neither assumes, nor authorizes

any person to assume for it, any other obligation in connection with the sale of products or parts

of products. TFSBP shall not be responsible for sprinkler system design errors or inaccurate or

incomplete information supplied by Buyer or Buyer’s representatives.

2. Fire Sprinkler Piping and Accessories: Shall cover the repair or replacement of properly installed

tubing and fittings proven defective as well as incidental damages. Warranty period for PEX

tubing and subsequent system shall be 25 year non-prorated warranty against failure due to

defect in material or workmanship, beginning with the date of installation. It is the installer’s

responsibility to avoid mixing fittings manufactured by others as it will reduce the owner’s

warranty.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Sprinklers Heads: Tyco (www.tyco-fire.com).

B. Fire Sprinkler Piping: Uponor® PEX piping (www.uponor-usa.com).

C. Valves and Fittings: Uponor® PEX valves and fittings (www.uponor-usa.com).

D. Mounting Brackets: Uponor® PEX mounting (www.uponor-usa.com).

2.02 SPRINKLER HEADS

A. The TYCO RAPID RESPONSE Series LFII Residential Domed-Plate Concealed Pendent 4.9 K-Factor

Sprinklers (TY2234) are decorative, fast response, frangible bulb sprinklers designed for use in

residential occupancies such as homes, apartments, dormitories, and hotels. The Cover

Plate/Retainer Assembly conceals the sprinkler operating components above the ceiling. The domed

profile of the cover plate provides aesthetically appealing sprinkler design with lower flow rates than

can be achieved by lower profile cover plates. The separable two-piece design of the Cover Plate

and Support Cup Assemblies allows installation of the sprinklers and pressure testing of the fire

protection system prior to the installation of the ceiling or application of a finish coating.

B. The Series LFII Residential Domed- Plate Concealed Pendent Sprinklers (TY2234) are shipped with a

Dispos-able Protective Cap. The Protective Cap is temporarily removed for installation, and it must

be replaced to protect the sprinkler while the ceiling is being installed or finished. The tip of the

Protective Cap can also be used to mark the center of the ceiling hole into plaster board or ceiling

tiles by gently pushing the ceiling product against the Protective Cap. When ceiling installation is

complete, the Protective Cap must be removed and the Cover Plate Assembly installed. The

Protective Cap must be removed to ensure proper performance of the sprinklers.

2.03 FIRE SPRINKLER PIPING

Page 99: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 5

CENTRIFUGAL FIRE PUMPS 21 31 00 - 5

A. Uponor® PEX piping certified for use in Fire Protection systems

1. Cross-linked polyethylene (PEX) manufactured by the Silane method.

2. Non-barrier type.

a. Shall have a pressure and temperature rating of 160 PSI at 73°F, 100 PSI at 180°F and 80 PSI

at 200°F.

b. Tubing shall have a minimum of 6 months UV protection.

3. Manufactured in accordance with ASTM F876 and ASTM F877 and tested for compliance by an

independent third-party agency.

2.04 VALVES AND FITTINGS

A. Fittings shall be manufactured by Uponor® PEX, identified by the letters “Q” or “Z” and

Manufactured in accordance with ASTM F1807 or ASTM F2159 and/or comply with ASTM F877

system standard as identified on the fitting.

B. Valves shall be of the plastic or metal type, meeting the requirements of ASTM F877, identified as

such with the appropriate mark on the product.

2.05 MOUNTING BRACKETS

A. Mounting brackets provided by Uponor® PEX, in compliance with ASTM requirements.

PART 3 – EXECUTION

3.01 INSTALLATION

A. All Uponor® PEX products provided in this section should be installed to manufacturer’s

specifications and to IRC and NFPA code requirements.

END OF SECTION

Page 100: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 6

CENTRIFUGAL FIRE PUMPS 21 31 00 - 6

SECTION 21 24 16

DRY-CHEMICAL FIRE-EXTINGUISHER EQUIPMENT

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Dry Powder Fire Extinguisher.

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. NFPA – National Fire Protection Association.

3. UL – Underwriters Laboratories Inc.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Fire Extinguisher.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC Section P2904 or NFPA 13D.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. First Alert® (or other manufacturer with similar product meeting all codes and requirements).

2.02 FIRE EXTINGUISHERs

A. (2 ct) First Alert® Model FE3A40GR Rechargeable Heavy Duty Dry Powder Fire Extinguishers.

1. For use in case of controlled fire where one could safely use to extinguish.

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed in locations in house where required by IRC and NFPA.

Page 101: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 7

CENTRIFUGAL FIRE PUMPS 21 31 00 - 7

END OF SECTION

Page 102: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 8

CENTRIFUGAL FIRE PUMPS 21 31 00 - 8

SECTION 21 31 13

ELECTRIC-DRIVE, CENTRIFUGAL FIRE PUMPS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Electric-Drive, Centrifugal Fire Pump.

B. Related Requirements

1. Fire-Suppression Sprinkler Systems (Section 21 13 00).

2. Instrumentation and Control for Fire-Suppression Systems (Section 21 09 00).

3. Ground Suction Storage Tanks for Fire-Suppression Water (Section 21 41 23).

1.02 REFERENCES

1. Reference Standards

1. IRC – International Residential Code.

2. NFPA – National Fire Protection Association.

3. UL – Underwriters Laboratories Inc.

4. ISO – International Standards Organization.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Fire Pump.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC Section P2904 or NFPA 13D.

1.05 WARRANTY

A. Manufacturer’s Warranty

1. Products manufactured by GRUNDFOS® PUMPS CORPORATION (Grundfos®) are warranted to

the original user only to be free of defects in material and workmanship for a period of 24

months from date of installation, but not more than 30 months from date of manufacture.

Grundfos® liability under this warranty shall be limited to repairing or replacing at Grundfos®

option, without charge, F.O.B. Grundfos® factory or authorized service station, any product of

Grundfos® manufacture. Grundfos® will not be liable for any costs of removal, installation,

transportation, or any other charges which may arise in connection with a warranty claim.

Products which are sold but not manufactured by Grundfos are subject to the warranty provided

by the manufacturer of said products and not by Grundfos® warranty. Grundfos® will not be

liable for damage or wear to products caused by abnormal operating conditions, accident,

Page 103: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 9

CENTRIFUGAL FIRE PUMPS 21 31 00 - 9

abuse, misuse, unauthorized alteration or repair, or if the product was not installed in

accordance with Grundfos® printed installation and operating instructions.

2. The warranty period shall be a non-prorated period of 24 months from date of installation, not

to exceed 30 months from date of manufacture. Warranty shall cover pump, motor and add-on

modules as complete unit.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Grundfos® (or other manufacturer with similar product meeting all codes and requirements).

(www.grundfos.com)

2.02 ELECTRIC-DRIVE, CENTRIFUGAL FIRE PUMP

A. Grundfos® CR 5-8 Centrifugal Pump with standard cast iron and 304 stainless steel construction.

1. For use with Fire-Suppression System to regulate and provide water pressure to Fire Sprinkler

Heads.

2. The pumps shall have the following features:

a. The pump housing shall have a stainless steel neck ring to minimize recirculation and

increase pump efficiency.

b. The impellers shall be laser welded stainless to obtain maximum efficiency. Composite

material shall not be acceptable. The impellers shall be secured to the shaft with a neck ring

and a nut.

c. The suction and discharge flanges shall be tapped and drilled to allow gauge installation on

the pump.

d. The pumps shall have radial tungsten carbide sleeve bearings for extended life. Metal

impregnated carbon radial bearings shall not be acceptable.

e. Pump Construction:

1) Pump housing Cast Iron

2) Impellers, rotor can, rotor cladding 304 Stainless Steel

3) Shaft 316 Stainless Steel

4) Bearings Tungsten Carbide

5) Axial thrust bearing Carbon MY106

6) Shaft journals/ inner bearings Silicon Carbide

7) O-rings EPDM

8) Bearing plate 304 Stainless Steel

PART 3 - EXECUTION

3.01 INSTALLATION

A. The pump shaft shall be installed horizontally or vertically per manufacturer’s recommendations.

The system shall be vented out from a higher location form the pump. The required inlet pressure

by the pump shall be available at the pump inlet.

B. Pump location: The pump should be located in a dry, well-ventilated area which is not subject to

freezing or extreme variation in temperature. Care must be taken to ensure the pump is mounted at

least 6 inches (150 mm) clear of any obstruction or hot surfaces. The motor requires an adequate air

Page 104: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 10

CENTRIFUGAL FIRE PUMPS 21 31 00 - 10

supply to prevent overheating and adequate vertical space to remove the motor for repair. For open

systems requiring suction lift the pump should be located as close to the water source as possible to

reduce piping losses.

C. Foundation: Concrete or similar foundation material should be used to provide a secure, stable

mounting base for the pump. See table of bolt hole center line dimensions for the various pump

types. Secure the pump to the foundation using all four bolts and shim pump base to assure the

pump is vertical and all four pads on the base are properly supported (uneven surfaces can result in

pump base breakage when mounting bolts are tightened). The pump can be installed vertically or

horizontally. Ensure that an adequate supply of cool air reaches the motor cooling fan. The motor

must never fall below the horizontal plane. Arrows on the pump base show the direction of flow of

liquid through the pump. To minimize possible noise from the pump, it is advisable to fit expansion

joints on either side of the pump and anti-vibration mountings between the foundation and the

pump.

Note: Care should be taken to ensure that the vent plug is located in the uppermost position.

Isolating valves should be fitted either side of the pump to avoid draining the system if the pump

needs to be cleaned, repaired or replaced.

3.02 TESTING

A. The pumps shall be factory performance and hydrostatic tested as a complete unit prior to

shipment. The testing shall be done in accordance with ISO 9906 Annex A. No test certificate is

required.

END OF SECTION

Page 105: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 1

PLUMBING FIXTURES 22 40 00 - 1

SECTION 21 41 23

GROUND SUCTION STORAGE TANKS FOR FIRE-SUPPRESSION WATER

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. 300 Gallon Fire-Suppression Water Storage Tank.

B. Related Requirements

1. Fire-Suppression Sprinkler Systems (Section 21 13 00).

2. Electric-Drive, Centrifugal Fire Pumps (Section 21 31 13).

3. Instrumentation and Control for Fire-Suppression Systems (Section 21 09 00).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. NFPA – National Fire Protection Association.

3. UL – Underwriters Laboratories Inc.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Fire-Suppression Water Storage Tank.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC Section P2904 or NFPA 13D.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Go To Tanks (or other manufacturer with similar product meeting all codes and requirements).

(www.gototanks.com/300RT-CRM.aspx)

2.02 PLASTIC STORAGE TANK

A. Go To Tanks 300RT-CRM Rectangular Utility Tank.

1. For use with Fire-Suppression system to store Fire-Suppression water.

Page 106: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 2

PLUMBING FIXTURES 22 40 00 - 2

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed on pallets to distribute weight evenly over ground surface.

END OF SECTION

END OF DIVISION 21

Page 107: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 3

PLUMBING FIXTURES 22 40 00 - 3

DIVISION 22: PLUMBING

SECTION 22 11 16

DOMESTIC WATER PIPING

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Hot and Cold Water Piping.

2. Valves and Fittings.

3. Mounting brackets.

B. Related Requirements

1. Close-Coupled, Horizontally Mounted, In-Line Centrifugal Domestic-Water Pumps

(Section 22 11 23.26).

2. Facility Ground-Mounted, Potable-Water Storage Tanks (Section 22 12 19).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. IPC – International Plumbing Code.

3. UL – Underwriters Laboratories Inc.

4. UPC – Uniform Plumbing Code.

5. ASTM – American Society for Testing and Materials.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for all products included in section.

B. Shop Drawings

1. Submit shop drawings of Domestic Water Supply System.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC, IPC, and UPC.

1.05 WARRANTY

A. Manufacturer’s Warranty

1. Hot and Cold Water Piping and Accessories: Shall cover the repair or replacement of properly

installed tubing and fittings proven defective as well as incidental damages. Warranty period for

Page 108: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 4

PLUMBING FIXTURES 22 40 00 - 4

PEX tubing and subsequent system shall be 25 year non-prorated warranty against failure due to

defect in material or workmanship, beginning with the date of installation. It is the installer’s

responsibility to avoid mixing fittings manufactured by others as it will reduce the owner’s

warranty.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Hot and Cold Water Piping: Uponor® PEX piping (www.uponor-usa.com).

B. Valves and Fittings: Uponor® PEX valves and fittings (www.uponor-usa.com).

C. Mounting Brackets: Uponor® PEX mounting (www.uponor-usa.com).

2.02 HOT AND COLD WATER PIPING

A. Uponor® PEX piping certified for use in Fire Protection systems

1. Cross-linked polyethylene (PEX) manufactured by the Silane method.

2. Non-barrier type.

a. Shall have a pressure and temperature rating of 160 PSI at 73°F, 100 PSI at 180°F and 80 PSI

at 200°F.

b. Tubing shall have a minimum of 6 months UV protection.

3. Manufactured in accordance with ASTM F876 and ASTM F877 and tested for compliance by an

independent third-party agency.

2.03 VALVES AND FITTINGS

A. Fittings shall be manufactured by Uponor® PEX, identified by the letters “Q” or “Z” and

Manufactured in accordance with ASTM F1807 or ASTM F2159 and/or comply with ASTM F877

system standard as identified on the fitting.

B. Valves shall be of the plastic or metal type, meeting the requirements of ASTM F877, identified as

such with the appropriate mark on the product.

2.04 MOUNTING BRACKETS

A. Mounting brackets provided by Uponor® PEX, in compliance with ASTM requirements.

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed per Manufacturer’s requirements and IRC, IPC, UPC compliance.

END OF SECTION

Page 109: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 5

PLUMBING FIXTURES 22 40 00 - 5

SECTION 22 11 23.26

CLOSE-COUPLED, HORIZONTALLY MOUNTED, IN-LINE CENTRIFUGAL DOMESTIC-WATER PUMPS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Domestic Fresh Water Pump.

B. Related Requirements

1. Domestic Water Piping (Section 22 11 16).

2. Facility Ground-Mounted, Potable-Water Storage Tanks (Section 22 12 19).

1.02 REFERENCES

A. Abbreviations and Acronyms

1. POM: Polyoximetylen

2. NR-rubber: Natural Rubber

3. PPO: Polyphenylene Oxides

4. NBR-rubber: Nitrile-Butadiene Rubber

B. Reference Standards

1. IRC – International Residential Code.

2. IPC – International Plumbing Code.

3. UL – Underwriters Laboratories Inc.

4. UPC – Uniform Plumbing Code.

5. ASTM – American Society for Testing and Materials.

6. ISO – International Standards Organization.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Domestic Fresh Water Pump.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC, IPC, and UPC.

1.05 WARRANTY

A. Manufacturer’s Warranty

1. Products manufactured by GRUNDFOS® PUMPS CORPORATION (Grundfos®) are warranted to

the original user only to be free of defects in material and workmanship for a period of 24

months from date of installation, but not more than 30 months from date of manufacture.

Grundfos® liability under this warranty shall be limited to repairing or replacing at Grundfos®

Page 110: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 6

PLUMBING FIXTURES 22 40 00 - 6

option, without charge, F.O.B. Grundfos® factory or authorized service station, any product of

Grundfos® manufacture. Grundfos® will not be liable for any costs of removal, installation,

transportation, or any other charges which may arise in connection with a warranty claim.

Products which are sold but not manufactured by Grundfos are subject to the warranty provided

by the manufacturer of said products and not by Grundfos® warranty. Grundfos® will not be

liable for damage or wear to products caused by abnormal operating conditions, accident,

abuse, misuse, unauthorized alteration or repair, or if the product was not installed in

accordance with Grundfos® printed installation and operating instructions.

2. The warranty period shall be a non-prorated period of 24 months from date of installation, not

to exceed 30 months from date of manufacture. Warranty shall cover pump, motor and add-on

modules as complete unit.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Grundfos® (or other manufacturer with similar product meeting all codes and requirements).

(www.grundfos.com)

2.02 DOMESTIC FRESH WATER PUMP

A. Grundfos® MQ 3-45 Self-Priming Multistage Centrifugal Pump.

1. For use with Domestic Water Supply System to regulate and provide water pressure to fixtures.

2. The MQ is a complete, all-in-one unit, incorporating pump, motor, diaphragm tank, pressure and

flow sensor, controller and check valve. The controller ensures that the pump starts

automatically when water is consumed and stops automatically when the consumption ceases.

In addition, the controller protects the pump in case of faults.

B. Material Specifications as follows:

Page 111: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 7

PLUMBING FIXTURES 22 40 00 - 7

PART 3 - EXECUTION

3.01 INSTALLATION

A. The pump shaft shall be installed horizontally per manufacturer’s recommendations. The terminal

box shall be located as per manufacturer’s recommendations. The system shall be vented out from

a higher location form the pump. The required inlet pressure by the pump shall be available at the

pump inlet.

B. Pump location: The pump should be located in a dry, well-ventilated area which is not subject to

freezing or extreme variation in temperature. Due to its compact design, the pump does not take up

much space and is easy to install. No space around the pump is required.

C. Self-priming pump: As it is self-priming, the MQ is able to pump water from a level below the pump.

Provided it is filled with water, the pump is able to lift water from a depth of 26 ft (8 m) in less than

5 minutes. This facilitates installation and startup of the pump and provides more reliable water

supply in installations where there is a risk of dry running and leakages in suction hose or pipes.

3.02 TESTING

A. The pumps shall be factory performance and hydrostatic tested as a complete unit prior to

shipment. The testing shall be done in accordance with ISO 9906 Annex A. No test certificate is

required

END OF SECTION

Page 112: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 8

PLUMBING FIXTURES 22 40 00 - 8

SECTION 22 12 19

FACILITY GROUND-MOUNTED, POTABLE-WATER STORAGE TANKS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. 500 Gallon Potable-Water Storage Tank.

B. Related Requirements

1. Domestic Water Piping (Section 22 11 16).

2. Facility Ground-Mounted, Potable-Water Storage Tanks (Section 22 12 19).

3. Close-Coupled, Horizontally Mounted, In-Line Centrifugal Domestic-Water Pumps

(Section 22 11 23.26).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. IPC – International Plumbing Code.

3. UL – Underwriters Laboratories Inc.

4. UPC – Uniform Plumbing Code.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Potable-Water Storage Tank.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC, IPC, and UPC.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Go To Tanks (or other manufacturer with similar product meeting all codes and requirements).

(www.gototanks.com/500RT.aspx)

2.02 POTABLE-WATER STORAGE TANK

A. Go To Tanks 500RT-CRM Rectangular Utility Tank.

Page 113: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 9

PLUMBING FIXTURES 22 40 00 - 9

1. For use with Domestic Water Supply System to store fresh water.

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed on pallets to distribute weight evenly over ground surface.

END OF SECTION

Page 114: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 10

PLUMBING FIXTURES 22 40 00 - 10

SECTION 22 13 16

SANITARY WASTE AND VENT PIPING

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Sanitary Piping.

2. Vent Piping.

3. Valves and Fittings.

4. Mounting Brackets.

B. Related Requirements

1. Air-Admittance Valves (Section 22 13 19.36).

2. Facility Septic Tanks (Section 22 13 53).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. IPC – International Plumbing Code.

3. UL – Underwriters Laboratories Inc.

4. UPC – Uniform Plumbing Code.

5. ASTM – American Society for Testing and Materials.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for all products included in section.

B. Shop Drawings

1. Submit shop drawings of Sanitary and Venting System.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC, IPC, and UPC.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Any providers with products meeting builder’s needs and ASTM standards, as well as compliant with

IRC, IPC, and UPC.

Page 115: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 11

PLUMBING FIXTURES 22 40 00 - 11

2.02 SANITARY PIPING

A. PVC piping meeting ASTM standard.

1. For use with Sanitary and Venting System to drain water from fixtures into Sanitary-Water

Storage Tank.

2.03 VENT PIPING

A. PVC piping meeting ASTM standard.

1. For use with Sanitary and Venting System to allow air to escape through the roof of the building

and prevent drainage problems.

2.04 VALVES AND FITTINGS

A. PVC fittings and valves meeting ASTM standard.

1. For use with Sanitary and Venting System to connect piping and adjust flow conditions.

2.05 MOUNTING BRACKETS

A. PVC mounting brackets meeting ASTM standard.

2. For use with Sanitary and Venting System to hang piping.

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed per requirements of IRC, IPC, and UPC.

END OF SECTION

Page 116: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 12

PLUMBING FIXTURES 22 40 00 - 12

SECTION 22 13 19.36

AIR-ADMITTANCE VALVES

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Air-Admittance Valves.

B. Related Requirements

1. Sanitary Waste and Vent Piping (Section 22 13 16).

2. Facility Septic Tanks (Section 22 13 53).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. IPC – International Plumbing Code.

3. UL – Underwriters Laboratories Inc.

4. UPC – Uniform Plumbing Code.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Air-Admittance Valves.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC Section P3114, IPC, and UPC.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Any providers with products meeting builder’s needs and ASTM standards, as well as compliant with

IRC, IPC, and UPC.

2.02 AIR-ADMITTANCE VALVES

A. Individual Air admittance valves (AAVs).

1. AAV’s are pressure-activated, one-way mechanical vents. For use with Sanitary and Venting

System provide venting to low flow fixtures to eliminate the need for conventional pipe venting

and roof penetrations for these fixtures. Regular Venting still required for high flow fixtures.

Page 117: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 13

PLUMBING FIXTURES 22 40 00 - 13

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed per requirements of IRC, IPC, and UPC.

END OF SECTION

Page 118: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 14

PLUMBING FIXTURES 22 40 00 - 14

SECTION 22 13 53

FACILITY SEPTIC TANKS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. 500 Gallon Sanitary-Water Storage Tank.

B. Related Requirements

1. Sanitary Waste and Vent Piping (Section 22 13 16).

2. Air-Admittance Valves (Section 22 13 19.36).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. IPC – International Plumbing Code.

3. UL – Underwriters Laboratories Inc.

4. UPC – Uniform Plumbing Code.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Sanitary -Water Storage Tank.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC, IPC, and UPC.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Go To Tanks (or other manufacturer with similar product meeting all codes and requirements).

(www.gototanks.com/500RT.aspx)

2.02 SANITARY -WATER STORAGE TANK

A. Go To Tanks 500RT-CRM Rectangular Utility Tank.

1. For use with Sanitary and Venting System to store grey/used water.

Page 119: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 15

PLUMBING FIXTURES 22 40 00 - 15

PART 3 – EXECUTION

3.01 INSTALLATION

C. To be installed on pallets to distribute weight evenly over ground surface.

END OF SECTION

Page 120: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 16

PLUMBING FIXTURES 22 40 00 - 16

SECTION 22 33 30.23

RESIDENTIAL, COLLECTOR-TO-TANK, SOLAR-ELECTRIC DOMESTIC WATER HEATERS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Solar Hot Water Storage Tank with Backup Heating.

2. Solar Hot Water Storage Tank.

3. Solar Hot Water Circulating Pump.

4. Solar Hot Water Piping, Fittings, and Valves.

B. Related Requirements

1. Domestic Water Piping (Section 22 11 16).

2. Heating Solar Flat-Plate Collectors (Section 23 56 13.13).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. IPC – International Plumbing Code.

3. UL – Underwriters Laboratories Inc.

4. UPC – Uniform Plumbing Code.

5. ASTM – American Society for Testing and Materials.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for all products included in section.

B. Shop Drawings

1. Submit shop drawings of Solar Hot Water System.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC, IPC, and UPC.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Solar Hot Water Storage Tank with Backup Heating: Rheem Marathon® Thermal Storage Tanks.

(www.marathonheaters.com)

Page 121: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 17

PLUMBING FIXTURES 22 40 00 - 17

B. Solar Hot Water Storage Tank: Rheem Marathon® Thermal Storage Tanks.

(www.marathonheaters.com)

C. Solar Hot Water Circulating Pump: Grunfos® UP 15-18SU LC Circulating Pump.

(www.grundfos.com)

D. Solar Hot Water Piping, Fittings, and Valves: Any provider with code compliant products.

2.02 SOLAR HOT WATER STORAGE TANK WITH BACKUP HEATING

A. 40 Gallon Rheem Marathon® Thermal Storage Tank with Backup Heating Element.

1. For use with Solar Hot Water System to store hot water and provide backup heating when solar

thermal gains are not enough.

2.03 SOLAR HOT WATER STORAGE TANK

A. 40 Gallon Rheem Marathon® Thermal Storage Tank.

1. For use with Solar Hot Water System to store hot water.

2.04 SOLAR HOT WATER CIRCULATING PUMP

A. Grunfos® UP 15-18SU LC Circulating Pump.

1. For use with Solar Hot Water System to circulate water through Solar Thermal Collector Panels

and into storage tanks.

2.05 SOLAR HOT WATER PIPING, FITTINGS, AND VALVES

A. Copper piping with insulation per ASTM standards and IRC.

B. Copper pipe fittings meeting ASTM standards and IRC.

C. Copper pipe valves meeting ASTM standards and IRC.

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed per Manufacturer’s requirements and IRC, IPC, UPC compliance.

END OF SECTION

Page 122: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 18

PLUMBING FIXTURES 22 40 00 - 18

SECTION 22 41 00

RESIDENTIAL PLUMBING FIXTURES

PART 1 – GENERAL

1.01 SUMMARY

A. Section includes

1. Kitchen Sink, Faucet, and Strainer.

2. Bathroom Sink, Faucet, and Drain.

3. Handshower Kit, Drain, Stack Valve, and Stack Valve Trim.

4. Water Closet.

B. Related Requirements

1. Domestic Water Piping (Section 22 11 16).

2. Sanitary Waste and Vent Piping (Section 22 13 16).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. IPC – International Plumbing Code.

3. UL – Underwriters Laboratories Inc.

4. UPC – Uniform Plumbing Code.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for all products included in section.

B. Shop Drawings

1. Submit shop drawings of detail connections of plumbing to fixtures.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC, IPC, and UPC.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Kohler Kitchen & Bath

2.02 KITCHEN SINK, FAUCET, AND STRAINER

Page 123: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 19

PLUMBING FIXTURES 22 40 00 - 19

A. Kohler K7507 Faucet:

(http://www.us.kohler.com/onlinecatalog/detail.jsp?from=thumb&frm=null&module=Kitchen+Sink

+Faucets&item=15108502&prod_num=7507&section=1&category=4&resultPage=0).

B. Kohler K3331 Sink:

(http://www.us.kohler.com/onlinecatalog/detail.jsp?from=thumb&frm=null&module=Kitchen+Sinks

&item=242302&prod_num=3331&section=1&category=5&resultPage=0-1315060530).

C. Kohler K8801 Duo Sink Strainer:

(http://www.us.kohler.com/onlinecatalog/detail.jsp?item=468302&section=1&category=7&subcate

gory=41&retail=false).

2.03 BATHROOM SINK, FAUCET, AND DRAIN

A. Kohler k7507 Faucet:

(http://www.us.kohler.com/onlinecatalog/detail.jsp?from=thumb&frm=null&module=Kitchen+Sink

+Faucets&item=15108502&prod_num=7507&section=1&category=4&resultPage=0).

B. Kohler Vox Vessel Lavatory:

(http://www.us.kohler.com/onlinecatalog/detail.jsp?from=thumb&frm=&module=Lavatories&item

=15184302&prod_num=14800&section=2&category=16&resultPage=0-1420926875).

C. Kohler K-7124-A-cp Pop-up :

(http://www.us.kohler.com/onlinecatalog/detail.jsp?item=11987102&retail=false).

2.04 HANDSHOWER KIT, DRAIN, STACK VALVE, AND STACK VALVE TRIM

A. Kohler K8487 Hand shower:

(http://www.us.kohler.com/onlinecatalog/detail.jsp?from=thumb&frm=&module=Handshower+Acc

essories&item=13645102&prod_num=8487&section=2&category=12&resultPage=0-1846098269).

B. Kohler K-9132 Drain:

(http://www.us.kohler.com/onlinecatalog/detail.jsp?item=473002&retail=false).

C. Kohler K-T14489-4-cp Trim:

(http://search.us.kohler.com/?q=Purist%AE+stacked+valve+trim&x=6&y=7).

D. Kohler Stack Valve:

(http://search.us.kohler.com/?q=MasterShower%AE+thermostatic+valve+with+integrated+volume+

control+&x=21&y=6).

2.05 WATER CLOSET

A. Kohler K-3492-0 Toilet: (http://search.us.kohler.com/?q=hatbox).

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed per Manufacturer’s requirements and IRC, IPC, UPC compliance.

END OF SECTION

END OF DIVISION 22

Page 124: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 20

PLUMBING FIXTURES 22 40 00 - 20

DIVISION 23: HEATING, VENTILATING,

AND AIR-CONDITIONING (HVAC)

SECTION 23 09 23

DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. HVAC Controller Unit.

B. Related Requirements

1. In-Line Centrifugal Hydronic Pumps (Section 23 21 23.13).

2. HVAC Air Distribution (Section 23 30 00).

3. Water-Source Unitary Heat Pumps (Section 23 81 46).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. ASHRAE – American Society of Heating, Refrigerating and Air-Conditioning Engineers.

3. UL – Underwriters Laboratories Inc.

4. AHRI – Air-Conditioning, Heating and Refrigeration Institute.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for HVAC Controller.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. AHRI certification.

3. Compliance with IRC and ASHRAE standards.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Johnson Controls® (or other manufacturer with similar product meeting all codes and

requirements). (www.johnsoncontrols.com)

Page 125: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 21

PLUMBING FIXTURES 22 40 00 - 21

2.02 HVAC CONTROLLERS

A. Johnson Controls® RJ Series Controls - Premier Microprocessor.

1. For use with HVAC System to regulate Thermal Mass Pump and Heat Pump fan in order to

achieve desired indoor air conditions.

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed and tested to Manufacturers requirements and IRC and ASHRAE standards.

END OF SECTION

Page 126: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 22

PLUMBING FIXTURES 22 40 00 - 22

SECTION 23 21 13.43

THERMAL MASS-LOOP HEAT-PUMP PIPING

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Thermal Mass-Loop Heat-Pump Piping.

B. Related Requirements

1. In-Line Centrifugal Hydronic Pumps (Section 23 21 23.13).

2. HVAC Air Distribution (Section 23 30 00).

3. Water-Source Unitary Heat Pumps (Section 23 81 46).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. ASHRAE – American Society of Heating, Refrigerating and Air-Conditioning Engineers.

3. UL – Underwriters Laboratories Inc.

4. ASTM – American Society for Testing and Materials.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Thermal Mass-Loop Heat-Pump Piping.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC and ASHRAE standards.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Any provider with products meeting system requirements and IRC.

2.02 THERMAL MASS-LOOP HEAT-PUMP PIPING

A. Copper Piping with insulation meeting ASTM standards and Heat-Pump Manufacturer’s

requirements.

1. For use with HVAC System to transport Thermal Mass fluid to and from the Heat-Pump unit.

Page 127: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 23

PLUMBING FIXTURES 22 40 00 - 23

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed and tested to Manufacturer’s requirements and IRC and ASHRAE standards.

B. Thermal Mass Water Piping: Piping is usually designed as ‘reverse return’ to equalize flow paths

through each unit. A short flexible pressure rated hose is used to make connection to the fixed

building piping system. This hose is typically stainless steel braid and includes a swivel fitting on one

end for easy removal and is flexible to help isolate the unit for quieter operation. Isolation valves for

servicing, y-strainers for filtering and memory-stop flow valve or a balancing valve can be provided

for consistent water flow through the unit. All unit source water connections are fittings that accept

a male pipe thread (MPT). Insert the connectors by hand, and then tighten the fitting with a wrench

to provide a leak proof joint. The open and closed loop piping system should include

pressure/temperature ports for serviceability. The proper water flow must be provided to each unit

whenever the unit operates. To assure proper flow, use pressure/temperature ports to determine

the flow rate. These ports should be located at the supply and return water connections on the unit.

The proper flow rate cannot be accurately set without measuring the water pressure drop through

the refrigerant-to-water heat exchanger. Limit hose length to 10 feet per connection. Check

carefully for water leaks.

END OF SECTION

Page 128: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 24

PLUMBING FIXTURES 22 40 00 - 24

SECTION 23 21 23.13

IN-LINE CENTRIFUGAL HYDRONIC PUMPS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Thermal Mass Booster Pump.

B. Related Requirements

1. Thermal Mass-Loop Heat-Pump Piping (Section 23 21 13.43).

2. HVAC Air Distribution (Section 23 30 00).

3. Water-Source Unitary Heat Pumps (Section 23 81 46).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. ASHRAE – American Society of Heating, Refrigerating and Air-Conditioning Engineers.

3. UL – Underwriters Laboratories Inc.

4. ISO – International Standards Organization.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Thermal Mass Booster Pump.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC and ASHRAE standards.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Dayton® (or other manufacturer with similar product meeting all codes and requirements).

(www.grainger.com)

2.02 THERMAL MASS BOOSTER PUMP

A. Dayton® Multistage Booster Pumps.

1. For use with HVAC System to pump Thermal Mass fluid to and from the Heat-Pump unit.

Page 129: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 25

PLUMBING FIXTURES 22 40 00 - 25

2. The Multistage Booster Pump increases pressure from city mains, or can pump water from

cisterns and private ponds to ensure the proper operation of filtration equipment. Each pump

stage has a 304 stainless steel radial bearing, Noryl® impeller, and Delrin® diffuser. All are rated

for continuous duty.

3. Cast-Iron housings feature cast-iron suction and discharge housings and mechanical seat with

stainless steel, Buna N, and carbon/silicon carbide parts.

PART 3 – EXECUTION

3.01 INSTALLATION

A. The pump shaft shall be installed horizontally per manufacturer’s recommendations. The system

shall be vented out from a higher location form the pump. The required inlet pressure by the pump

shall be available at the pump inlet.

B. Pump location: The pump should be located in a dry, well-ventilated area which is not subject to

freezing or extreme variation in temperature.

C. Pump Priming: Self-priming to 10 ft. when pump housing and suction housing are filled; must

maintain 1.5 gpm flow to pump for proper seal and pump housing lubrication. If liquid temperature

is above 60°F, pumps require inlet pressure of 10 psi.

D. Electronic Pump Protectors: An electronic pump protector can be used to monitor water flow and

automatically shut down the motor when flow drops below 1.0 gpm; protect pumps against damage

caused by dry run or dead head conditions. The motor will turn back on to boost system pressure

when flow goes back above that level.

3.02 TESTING

A. The pumps shall be factory performance and hydrostatic tested as a complete unit prior to

shipment. The testing shall be done in accordance with ISO 9906 Annex A. No test certificate is

required.

END OF SECTION

Page 130: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 26

PLUMBING FIXTURES 22 40 00 - 26

SECTION 23 30 00

HVAC AIR DISTRIBUTION

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Metal Ducts.

2. Volume-Control Dampers.

3. Backdraft Dampers.

4. Flexible Duct Collars.

5. Flexible Hose Ducts.

6. Floor Diffusers.

7. Duct Insulation Liners.

8. Bathroom Ventilation Fan.

B. Related Requirements

1. Thermal Mass-Loop Heat-Pump Piping (Section 23 21 13.43).

2. In-Line Centrifugal Hydronic Pumps (Section 23 21 23.13).

3. Water-Source Unitary Heat Pumps (Section 23 81 46).

4. Dehumidifiers (Section 23 84 16).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. ASHRAE – American Society of Heating, Refrigerating and Air-Conditioning Engineers.

3. UL – Underwriters Laboratories Inc.

4. ASTM – American Society for Testing and Materials.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for all products included in section.

B. Shop Drawings

1. Submit shop drawings of HVAC System Diagram.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC and ASHRAE standards.

PART 2 – PRODUCTS

Page 131: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 27

PLUMBING FIXTURES 22 40 00 - 27

2.01 MANUFACTURERS

A. Metal Ducts: To be manufactured by builder.

B. Volume-Control Dampers: Any provider meeting IRC and ASHRAE standards.

C. Backdraft Dampers: Any provider meeting IRC and ASHRAE standards.

D. Flexible Duct Collars: Any provider meeting IRC and ASHRAE standards.

E. Flexible Hose Ducts: Any provider meeting IRC and ASHRAE standards.

F. Floor Diffusers: Any provider meeting IRC and ASHRAE standards.

G. Duct Insulation Liners: Any provider meeting IRC and ASHRAE standards.

H. Bathroom Ventilation Fan: Panasonic®(www.panasonic.com).

2.02 METAL DUCTS

A. Ducts to be manufactured by builder to meet system requirements and IRC and ASHRAE standards.

1. Ducts to be secured by mounting brackets approved for application.

2. Ducts will be constructed of sheet metal meeting ASTM requirements.

2.03 VOLUME-CONTROL DAMPERS

A. Volume-Control Dampers will be installed into ducting for HVAC System balancing and adjustment.

2.04 BACKDRAFT DAMPERS

A. Backdraft Dampers to be installed in ducts to prevent flow of air in the wrong direction.

2.05 FLEXIBLE DUCT COLLARS

A. Flexible Duct Collars to be installed at supply and return duct connections to Heat-Pump in order to

prevent noise and vibration.

2.06 FLEXIBLE HOSE DUCTS

A. Flexible Hose Ducts will be used in place of metal ducting when applicable.

2.07 FLOOR DIFFUSERS

A. Floor Diffusers will be installed for both supply and return venting into and out of conditioned

spaces inside house.

2.08 DUCT INSULATION LINERS

A. Duct Insulation Liners will be used on both supply and return ducts with a minimum of 1 inch

thickness, complying with IRC and ASHRAE standards. Duct liners are used to insulate and prevent

heat transfer to conditioned air in ducts.

2.09 BATHROOM VENTILATION FAN

A. Panasonic® WhisperGreen-LiteTM

Ventilation Fan.

1. For use in Bathroom to provide ventilation.

Page 132: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 28

PLUMBING FIXTURES 22 40 00 - 28

2. Ventilating fan shall be Low Noise ceiling mount type rated for continuous run. Fan shall be

ENERGY STAR rated and certified by the Home Ventilating Institute (HVI). Fan shall include

energy efficient compact fluorescent lighting. Evaluated by Underwriters Laboratories and

conform to both UL and cUL safety standards.

3. Motor/Blower:

a. Enclosed DC brushless motor technology rated for continuous run.

b. Power Rating shall be 120 volts and 60 Hz.

c. Fan shall be UL listed for tub/shower enclosure when used with a GFCI branch circuit wiring

and use in insulated ceiling (TYPE I.C.).

d. Motor equipped with thermal cut-off fuse control.

e. Removable with permanently lubricated plug–in motor.

4. Housing:

a. Rust proof paint, galvanized steel body.

b. Detachable 4" diameter duct adapter.

c. Built in backdraft damper.

d. Double hanger bar system allowing for ideal positioning.

5. Grille:

a. Attractive design using PP material.

b. Attaches directly to housing with torsion springs.

6. Light:

a. One 32-watt electronic ballast compact fluorescent lamps included.

b. One 4-watt, night-light included.

PART 3 – EXECUTION

3.01 INSTALLATION

A. Ductwork:

1. Ensure return air grilles will not allow line of site noise to transfer to adjacent space. Use a

sound barrier or some other material to isolate the grille from the unit. A supply grille, boot and

short piece of flex duct pointed away from the unit can greatly attenuate equipment noise.

2. Use a canvas isolation duct connector at the supply and return duct connection of the unit.

3. Internally line the discharge and return duct within the first 4-8 feet of unit with acoustic

insulation. Install an internally lined ‘L’ shaped return duct elbow at return grille. Face the elbow

away from adjacent units.

4. Always install at least one 90° elbow in the discharge duct to eliminate line of sight noise

transmission of the blower.

5. Use turning vanes at all elbows and tees to reduce turbulence.

6. Limit supply duct velocities to less than 1000 fpm

7. Design and install ductwork as stiff as possible

8. Allow 3 duct diameters both up and down stream of the unit before any fittings or transitions

are installed.

9. Use duct sealant on all duct joints.

10. Install a short (2-4’) of flex duct on all branch ducts just prior to discharge boot or diffuser to

reduce vibration and duct sound prior to delivery in the room.

11. Locate the branch duct balancing damper as far away from the diffuser as possible.

12. In ceiling plenum systems, install an internally lined ‘L’ shaped return duct elbow at unit. Face

the elbow away from adjacent units (horizontal).

Page 133: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 29

PLUMBING FIXTURES 22 40 00 - 29

3.02 TESTING

B. Testing and balancing of HVAC System to be done in accordance with ASHRAE standards and meet

Manufacturer requirements of the Heat-Pump unit.

END OF SECTION

Page 134: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 30

PLUMBING FIXTURES 22 40 00 - 30

SECTION 23 56 13.13

HEATING SOLAR FLAT-PLATE COLLECTORS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Solar Hot Water Flat-Plate Collectors.

B. Related Requirements

1. Domestic Water Piping (Section 22 11 16).

2. Residential, Collector-to-Tank, Solar-Electric Domestic Water Heaters (Section 22 33 30.23).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. IPC – International Plumbing Code.

3. UL – Underwriters Laboratories Inc.

4. UPC – Uniform Plumbing Code.

5. ASTM – American Society for Testing and Materials.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Solar Hot Water Flat-Plate Collectors.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC, ASTM, and ASHRAE standards.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. SunEarth® Inc. (or other manufacturer with similar product meeting all codes and requirements).

(www.sunearthinc.com)

2.02 SOLAR HOT WATER FLAT-PLATE COLLECTORS

A. SunEarth® Empire Series Glazed Flat Plate Solar Collectors.

Page 135: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 31

PLUMBING FIXTURES 22 40 00 - 31

1. Three (3) Empire EP21 Panels will be installed in conjunction with Solar Hot Water System to

provide thermal energy to water as it passes through panel setup and then returns to Solar Hot

Water Storage Tanks.

PART 3 – EXECUTION

3.01 INSTALLATION

A. System shall be installed following Solar Thermal System sizing and mounting standards. Follow

Manufacturer’s requirements as well as following IRC, IPC, and UPC standards.

3.02 TESTING

A. System testing shall be performed to Manufacturer’s requirements.

END OF SECTION

Page 136: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 32

PLUMBING FIXTURES 22 40 00 - 32

SECTION 23 71 13.23

PRESSURIZED-WATER THERMAL STORAGE TANKS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Thermal Mass Pillow Tank.

2. Thermal Mass Fill Hose.

B. Related Requirements

1. Thermal Mass-Loop Heat-Pump Piping (Section 23 21 13.43).

2. In-Line Centrifugal Hydronic Pumps (Section 23 21 23.13).

3. Water-Source Unitary Heat Pumps (Section 23 81 46).

4. Phase Change Material for Thermal Mass (23 71 13.26).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. ASHRAE – American Society of Heating, Refrigerating and Air-Conditioning Engineers.

3. UL – Underwriters Laboratories Inc.

4. ASTM – American Society for Testing and Materials.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Thermal Mass Pillow Tank and Thermal Mass Fill

Hose.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC, ASTM, ASHRAE standards.

1.05 WARRANTY

A. Manufacturer’s Warranty

1. The Original Rainwater Pillow®: Rainwater Collection Solutions, Inc., warrants that for 5 years

from the date of purchase that The Original Rainwater Pillow will be free from defects in

materials. This warranty extends to the initial purchaser of The Original Rainwater Pillow, and is

valid for the 5 years from the date of purchase. If within 5 years from the date of purchase, the

product shall prove to be defective in the materials used, it shall be repaired or replaced at

Rainwater Collection Solutions, Inc., option. The original receipt of purchase is required to

Page 137: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 33

PLUMBING FIXTURES 22 40 00 - 33

determine warranty eligibility. No warranty implied or express is given by Rainwater Collection

Solutions, Inc., related to the installation of The Original Rainwater Pillow. This includes any

leaks that result from the connection of pipes, pumps, or other devises necessary to the

operation of The Original Rainwater Pillow. The Original Rainwater Pillow is not warranted

against: acts of God, abuse, tampering, freezing, alteration in design, overfilling, storage of

liquids (other than rainwater), and problems associated with the lack of filter maintenance. The

Original Rainwater Pillow may not be used for the transportation of liquids, and the warranty

does not extend to such uses.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Thermal Mass Pillow Tank: Rainwater Collection Solutions, Inc. (or other manufacturer with similar

product meeting all codes and requirements). (www.rainwaterpillow.com).

B. Thermal Mass Fill Hose: Abbott Rubber Company, Inc. (or other manufacture with similar product).

(www.abbottrubber.com).

2.02 THERMAL MASS PILLOW TANK

A. The Original Rainwater Pillow® Tank (1500 Gallon).

1. For use with HVAC System to store Phase Change Material along with water creating a Thermal

Mass fluid, which will be circulated through Pillow Tank.

2. The Original Rainwater Pillow is manufactured for long term water storage usage. The Pillows

are made from first grade materials and all are provided with a certificate of fitness upon

request. The Material is a reinforced polymer alloy (polyester scrim coated on both sides with a

PVC polymer). The same heavy duty industrial strength fabric commonly used by the military

and fire departments.

3. Ultra violet radiation inhibitors are incorporated in the manufacturing process of the polymers

to provide excellent ultra violet radiation resistance.

4. Fabric weight 6.5 oz sq yard. Total weight 30 oz sq yard

5. Its abrasion resistance is > 2,000 cycles. This means that an independent ASTM lab has

determined that every square inch of the Original Rainwater Pillow can withstand friction more

than 2,000 times before it begins to abrade. The breaking strength of our material is 550 lbs per

inch, which means a one-inch strip of it can hold 550 lbs. Tear 80 lbs. Adhesion 35 lbs/inch.

6. Seams are radio frequency welded, which means that we use electromagnetic energy to heat

and bond materials together under pressure, ensuring strong, leak-proof seams. Each pillow is

pressure tested before shipping. It is severe-weather tolerant, able to sustain extreme

temperatures, ranging from -30 to +160 Fahrenheit. Easily repairable with heat or cold bonding.

7. The Original Rainwater Pillow is exceedingly durable and shows excellent resistance to ruptures,

abrasions and leaks. It has also been shown to be impervious to rodents in 30 years of

experience using these pillows in crawlspaces, under decks, in yards and a wide variety of other

spaces that rodents tend to like, our manufacturer has never seen any rodent damage.

2.03 THERMAL MASS FILL HOSE

A. Abbott All Weather Water Suction Hose.

1. For use in filling up Thermal Mass Pillow Tank with needed water (1000 Gallons).

Page 138: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 34

PLUMBING FIXTURES 22 40 00 - 34

2. All weather low temperature suction and discharge hose. Lightweight and flexible. Ideal for

septic handling, construction, waste removal and industrial fluid handling.

3. Made from 100% EPDM tube reinforced with a green polyethylene helix. Abrasion resistant

cover.

PART 3 – EXECUTION

3.01 INSTALLATION

A. Pillow Tank should be placed on flat area that will be able to drain system. Supports can be used but

are not needed as the Pillow is naturally very strong. When connecting pumps and piping be sure to

make strong connections and use a leak guard.

B. Thermal Mass Fill Hose to be used to fill up Thermal Mass Pillow Tank with water. The hose will be

temporarily connected to Potable-Water Storage Tank while it is being filled, and Thermal Mass will

be filled concurrently. Once filling of Pillow Tank is complete, hose with be shut off and

disconnected from Potable-Water Storage Tank and then this will be topped off.

C. For Installation of Phase Change Material, see Section 23 71 13.26.

3.02 TESTING

A. Testing of the Thermal Mass Pillow Tank with installed Phase Change Material shall be done prior to

installation of the system to check performance of Thermal Mass.

END OF SECTION

Page 139: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 35

PLUMBING FIXTURES 22 40 00 - 35

SECTION 23 71 13.26

PHASE CHANGE MATERIAL FOR THERMAL MASS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Phase Change Material for Thermal Mass.

B. Related Requirements

1. Thermal Mass-Loop Heat-Pump Piping (Section 23 21 13.43).

2. In-Line Centrifugal Hydronic Pumps (Section 23 21 23.13).

3. Water-Source Unitary Heat Pumps (Section 23 81 46).

4. Pressurized-Water Thermal Storage Tanks (23 71 13.23).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. ASHRAE – American Society of Heating, Refrigerating and Air-Conditioning Engineers.

3. UL – Underwriters Laboratories Inc.

4. ASTM – American Society for Testing and Materials.

5. MSDS – Material Safety Data Sheets.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Phase Change Material for Thermal Mass.

2. MSDS for Phase Change Material to be submitted as well.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. Compliance with IRC, ASTM, and ASHRAE standards.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. PCM Products Ltd. (or other manufacturer with similar product meeting all codes and

requirements). (www.pcmproducts.net/home.htm)

2.02 PHASE CHANGE MATERIAL FOR THERMAL MASS

Page 140: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 36

PLUMBING FIXTURES 22 40 00 - 36

A. TubeICE® containers of PCM products.

1. For use in Thermal Mass Pillow Tank to provide a temperature range that the Thermal Mass will

stay within. This will increase productivity of Heat-Pump unit while replicating a Geothermal

Heat-Pump application.

2. These containers operate on a similar principle to the FlatICE® containers, and are supplied as

fully sealed PCM-filled HDPE tubes. The tubular design enables them to be stacked effectively in

both rectangular and cylindrical tanks with minimal void space. Once installed, a series of ridges

around the circumference of the tube mean that air or water can pass freely between the

containers allowing excellent heat exchange properties.

3. TubeICE® set at an upper and lower Phase Change Temperature shall be used to keep Thermal

Mass at most efficient operating temperatures as possible to reduce needed cooling or heating

energy from Heat-Pump unit. Approximately 300 gallons of PCM shall be used, which is about

450 TubeICE® units.

PART 3 – EXECUTION

3.01 INSTALLATION

A. TubeICE® shall be inserted into Pillow Tank prior to filling the rest of the tank with water. Once all

TubeICE® is installed the Pillow Tank can then be attached to Thermal Mass Fill Hose and filled with

approximately 1000 gallons of water.

3.02 TESTING

A. Testing of the Thermal Mass Pillow Tank with installed Phase Change Material shall be done prior to

installation of the system to check performance of Thermal Mass.

END OF SECTION

Page 141: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 37

PLUMBING FIXTURES 22 40 00 - 37

SECTION 23 81 46

WATER-SOURCE UNITARY HEAT PUMPS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Water-Source Heat Pump.

B. Related Requirements

1. In-Line Centrifugal Hydronic Pumps (Section 23 21 23.13).

2. HVAC Air Distribution (Section 23 30 00).

3. Direct-Digital Control System for HVAC (Section 23 09 23).

4. Thermal Mass-Loop Heat-Pump Piping (Section 23 21 13.43).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. ASHRAE – American Society of Heating, Refrigerating and Air-Conditioning Engineers.

3. UL – Underwriters Laboratories Inc.

4. AHRI – Air-Conditioning, Heating and Refrigeration Institute.

5. ISO – International Standards Organization.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Water-Source Heat Pump.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. AHRI certification.

3. Compliance with IRC and ASHRAE standards.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Johnson Controls® (or other manufacturer with similar product meeting all codes and

requirements). (www.johnsoncontrols.com)

2.02 Water-Source Heat Pump

A. Johnson Controls® RJ Series Geothermal/Water Source Heat Pump RJS-H015-ER.

Page 142: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 38

PLUMBING FIXTURES 22 40 00 - 38

1. For use with HVAC System to provide heating and cooling to conditioned space inside house, by

means of Thermal Mass acting as Geothermal source.

2. Equipment shall be completely assembled, piped and internally wired. Capacities and

characteristics as listed in the schedule and the specifications that follow. The reverse cycle

heating/cooling units shall be either suspended type with horizontal air inlet and discharge or

floor mounted type with horizontal air inlet and vertical upflow/down flow or rear air discharge.

Units shall be AHRI/ISO 13256-1 certified and listed by a nationally recognized safety-testing

laboratory or agency, such as ETL Testing Laboratory. Each unit shall be computer run tested at

the factory with conditioned water and operation verified to catalog data. Each unit shall be

mounted on a pallet and shipped in a corrugated box or stretch-wrapped. The units shall be

designed to operate with entering liquid temperature between 20°F and 120°F [-6.7°C and

48.9°C].

3. Refrigerant Circuit: All units shall utilize the non-ozone depleting and low global warming

potential refrigerant R410A. All units shall contain a sealed refrigerant circuit including a

hermetic motor-compressor, bidirectional thermostatic expansion valve, finned tube air-to

refrigerant heat exchanger, reversing valve, coaxial tube water-to refrigerant heat exchanger,

optional hot water generator coil, and service ports. Compressors shall be high-efficiency single

speed rotary or scroll, or dual capacity scroll type designed for heat pump duty and mounted on

vibration isolators. The compressor shall be double isolation mounted using selected durometer

grommets to provide vibration free compressor mounting. The compressor mounting bracket

shall be acoustically deadened galvanized steel to prevent vibration transmission to the cabinet.

Compressor motors shall be three-phase or single-phase PSC with overload protection. The air

coil shall be sized for low face velocity and constructed of lanced aluminum fins bonded to rifled

copper tubes in a staggered pattern not less than three rows deep for enhanced performance.

4. Blower Motor and Assembly: The blower shall be a direct drive centrifugal type with a

dynamically balanced wheel. The housing and wheel shall be designed for quiet low outlet

velocity operation. The blower housing shall be removable from the unit without disconnecting

the supply air ductwork for servicing of the blower motor. The blower motor shall be a variable-

speed ECM2 type. The ECM2 blower motor shall be soft starting, shall maintain constant CFM

over its operating static range, and shall provide 12 CFM settings. The blower motor shall be

isolated from the housing by rubber grommets. The motor shall be permanently lubricated and

have thermostatic overload protection. ECM2 motors shall be long-life ball bearing type.

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed and tested to Manufacturers requirements and IRC and ASHRAE standards.

B. Unit Location: Locate the unit in an indoor area that allows for easy removal of the filter and access

panels. Location should have enough space for service personnel to perform maintenance or repair.

Provide sufficient room to make water, electrical and duct connection(s). If the unit is located in a

confined space, such as a closet, provisions must be made for return air to freely enter the space by

means of a louvered door, etc. Any access panel screws that would be difficult to remove after the

unit is installed should be removed prior to setting the unit. On horizontal units, allow adequate

room below the unit for a condensate drain trap and do not locate the unit above supply piping.

Care should be taken when units are located in unconditioned spaces to prevent damage from

frozen water lines and excessive heat that could damage electrical components.

Page 143: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 39

PLUMBING FIXTURES 22 40 00 - 39

C. Condensate Drain: On vertical units, the internal condensate drain assembly consists of a drain tube

which is connected to the drain pan, a 3/4 in. or 1 in. copper female adapter and a flexible

connecting hose. On vertical units, a condensate hose is inside all cabinets as a trapping loop;

therefore, an external trap is not necessary. On horizontal units, a PVC stub is provided for

condensate drain piping connection. An external trap is required (see below). If a vent is necessary,

an open stand pipe may be applied to a tee in the field-installed condensate piping. In order to work

properly, the vent must be after the trap and away from the unit.

D. Sound Performance: The RJ Series is third party sound rated in accordance with AHRI 260.

1. Recommendations for Noise Reduction for Horizontal Unit Location:

a. Specify equipment with quietest sound power ratings

b. Do not locate units above areas with a required NC 40 or less

c. Space WSHP at least 10 ft (3m) apart to avoid noise summing of multiple units in a space.

d. Maximize the height of the unit above the ceiling (horizontal).

e. Suspend unit with isolation grommets that are appropriately rated to reduce vibrations

(horizontal).

3.02 TESTING

A. The system shall follow performance standard AHRI/ASHRAE/ISO 13256-1. After performing testing

values can be compared to performance data found in Engineering Guide.

END OF SECTION

Page 144: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 40

PLUMBING FIXTURES 22 40 00 - 40

SECTION 23 84 16

DEHUMIDIFIERS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Dehumidifier.

A. Related Requirements

1. HVAC Air Distribution (Section 23 30 00).

2. Direct-Digital Control System for HVAC (Section 23 09 23).

3. Water-Source Unitary Heat Pumps (Section 23 81 46).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. ASHRAE – American Society of Heating, Refrigerating and Air-Conditioning Engineers.

3. UL – Underwriters Laboratories Inc.

4. AHRI – Air-Conditioning, Heating and Refrigeration Institute.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Dehumidifier.

1.04 QUALITY ASSURANCE

A. Certificates

1. UL certification.

2. AHRI certification.

3. Compliance with IRC and ASHRAE standards.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. Therma-Stor® LLC. (or other manufacturer with similar product meeting all codes and

requirements). (www.thermastor.com).

2.02 DEHUMIDIFIER

A. Ultra-AireTM

65H Ventilating Dehumidifier.

1. For use in parallel with HVAC Air Distribution System in order to dehumidifier conditioned air

further, or to dehumidify while Heat Pump is not running.

Page 145: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 41

PLUMBING FIXTURES 22 40 00 - 41

2. The Ultra-AireTM

65H uses a refrigeration system similar to an air conditioner’s to remove heat

and moisture from incoming air, and add heat to the air that is discharged. Hot, high pressure

refrigerant gas is routed from the compressor to the condenser coil. The refrigerant is cooled

and condensed by giving up its heat to the air that is about to be discharged from the unit. The

refrigerant liquid then passes through a strainer and capillary tubing which causes the

refrigerant pressure and temperature to drop. It next enters the evaporator coil where it

absorbs heat from the incoming air and evaporates. The evaporator operates in a flooded

condition, which means that all the evaporator tubes contain liquid refrigerant during normal

operation. A flooded evaporator should maintain nearly constant pressure and temperature

across the entire coil, from inlet to outlet. The mixture of gas and liquid refrigerant enter the

accumulator after leaving the evaporator coil. The accumulator prevents any liquid refrigerant

from reaching the compressor. The compressor evacuates the cool refrigerant gas from the

accumulator and compresses it to a high pressure and temperature.

3. Refrigerant Charging: If the refrigerant charge is lost due to service or a leak, a new charge must

be accurately weighed in. If any of the old charge is left in the system, it must be recovered

before weighing in the new charge. Refer to the unit nameplate for the correct charge weight

and refrigerant type.

4. Compressor/Capacitor Replacement: This compressor is equipped with a two terminal external

overload and a run capacitor, but no start capacitor or relay.

5. Electric Ventilation Damper: The damper will open when the ventilation is called for, allowing

fresh air into the structure through the fresh air inlet duct. The electric ventilation damper will

remain closed when the ventilation is not activated in order to prevent over-ventilating the

structure when the unit is dehumidifying or recirculating the indoor air. The electric ventilation

damper operates on 24 Vac from the control circuit. DO NOT connect high voltage to the

damper motor or damage to the motor will result. DO NOT force the blade of the damper by

hand or damage to the damper motor may result. The damper opens in one direction only. The

damper rotates very slowly, allow sufficient time for the damper to cycle. The damper will take

approximately one minute to cycle from closed to open or from open to closed.

PART 3 – EXECUTION

3.01 INSTALLATION

A. Prior to installation of the Ultra-AireTM

65H, the following checklist should be reviewed. The Ultra-

AireTM

65H can be installed in a variety of locations to meet the owner’s needs, and be integrated

with existing forced air systems or existing ductwork if desired. The location choice is contingent on

a variety of requirements not limited to: ease of service, controls access, drainage, filtration, power,

fresh-air ventilation (optional), water damage prevention, and current regulatory codes (ASHRAE,

fire, etc). Please address all of these issues before you select the location of the device.

B. Power Accessibility: Unit should be located in an area where the cord’s length (8') should easily

reach a 110-120 VAC electrical outlet with a minimum of a 15 A circuit capacity.

C. Space: Location should have enough clearance to handle the unit’s overall dimensions as well as the

necessary return/supply ductwork to the unit.

D. Support Structure and Suspension: Place the Ultra-AireTM

65H on supports to raise the base of the

unit. Do not place the Ultra-AireTM

65H directly on structural building members without vibration

absorbers or unwanted noise may result. The Ultra-AireTM

65H may be suspended with a hang kit

(4028111) or a suitable alternative from structural members, as long as the suspending assembly

supports the Ultra-AireTM

65H’s base in its entirety. Do not hang the Ultra-AireTM

65H from the

Page 146: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 42

PLUMBING FIXTURES 22 40 00 - 42

cabinet. Remember to place a drain pan under the unit if it is suspended above a finished area or

above an area where water leakage could cause damage.

E. Electrical Requirements: The Ultra-AireTM

65H plugs into a common grounded 115VAC outlet. The

device draws 5.5 Amps under normal operating conditions. If used in an area which may become

wet, a ground fault interrupter (GFI) protected circuit is recommended. Please, consult local

electrical codes for any further information. Therma-Stor® LLC offers a family of control devices for

use with the Ultra-AireTM

65H. The controls are to be located remotely from the unit and located in

the space to be conditioned. The controls are low voltage (24 volt) and should be connected to the

Ultra-AireTM

65H with low voltage wire (thermostat or other appropriate).

F. Supply Air: A short piece of flexible ducting on all Ultra-AireTM

65H duct connections is

recommended to reduce noise and vibration transmitted to rigid ductwork in the structure. Ducting

the Ultra-AireTM

65H as mentioned requires consideration of the following points. Duct Sizing: For

total duct lengths up to 25', use a minimum 8" diameter round or equivalent rectangular. For longer

lengths, use a minimum 10" diameter or equivalent. Grills or diffusers on the duct ends must not

excessively restrict airflow. Connecting to existing HVAC systems: An optional 8" check backdraft

damper is available from the factory to prevent reverse air flow through the Ultra-AireTM

65H. If the

Ultra-AireTM

65H is ducted to the supply of an air handler, the check damper should be placed in the

Ultra-AireTM

65H supply duct.

G. Noise Abatement: A length of 10 feet or more of flex ducting on the outlet of the Ultra-AireTM

65H

will reduce air noise from the fan. A length of flexible ducting on all Ultra-AireTM

65H duct

connections is recommended to reduce noise transmitted to rigid ductwork in the structure.

3.02 TESTING

A. The system should be tested to check performance standards and checked with data from

Installation Guide. Troubleshooting section can be used in the case of problems, any further issues

can be taken up with technical support.

3.03 MAINTENANCE

A. High Efficiency Air Filter: The Ultra-Aire 65H is equipped with a MERV 11 media filter. This filter

should be checked every three months. Operating the unit with a dirty filter will reduce

dehumidifier capacity and efficiency and may cause the compressor to cycle off and on

unnecessarily on the defrost control. DO NOT operate the unit without a filter or with a less

effective filter. Operating the unit without a filter or with a less effective filter may cause internal

damage to the unit and invalidate the product warranty.

END OF SECTION

END OF DIVISION 23

Page 147: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 43

PLUMBING FIXTURES 22 40 00 - 43

DIVISION 28: ELECTRONIC SAFETY AND SECURITY

SECTION 28 31 46

SMOKE DETECTION SENSORS

PART 1 – GENERAL

1.01 SUMMARY

A. Section Includes

1. Smoke Alarms.

A. Related Requirements

1. Fire-Suppression Sprinkler Systems (Section 21 13 00).

2. Electric-Drive, Centrifugal Fire Pumps (Section 21 31 13).

3. Ground Suction Storage Tanks for Fire-Suppression Water (Section 21 41 23).

1.02 REFERENCES

A. Reference Standards

1. IRC – International Residential Code.

2. NFPA – National Fire Protection Association.

3. UL – Underwriters Laboratories Inc.

1.03 SUBMITTALS

A. Product Data

1. Submit product sheets and specifications for Smoke Alarms.

1.04 QUALITY ASSURANCE

B. Certificates

1. UL certification of Jockey Pump Controller.

2. Compliance with IRC Section P2904 or NFPA 13D.

PART 2 – PRODUCTS

2.01 MANUFACTURERS

A. First Alert® (or other manufacturer with similar product meeting all codes and

requirements) (www.firstalert.com).

Page 148: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

Published

Page -- 44

PLUMBING FIXTURES 22 40 00 - 44

2.02 SMOKE ALARMS

A. (2 ct) First Alert® SA-9120-BCN Hardwired Smoke Alarm with Battery (9V) Backup .

1. For use in house to detect smoke and warn those inside of fire and/or smoke.

PART 3 – EXECUTION

3.01 INSTALLATION

A. To be installed and tested to Manufacturer’s requirements and IRC Fire code.

END OF SECTION

Page 149: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

APPENDIX C: TEAM HAWAII FULL DRAWING SET

Page 150: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

LOT NUMBER:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY / NREL2011 SOLAR DECATHLON

WWW.SOLARDECATHLON.GOV

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

TEAM NAME:

ADDRESS:

CONTACT:

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

306

UNIVERSITY OF HAWAII(TEAM HAWAII)

[email protected]

Page 151: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

11:

49:1

6 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

G-001

TABLE OF CONTENTS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

11:

49:1

6 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

G-001

TABLE OF CONTENTS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

SHEET LISTSHT NO SHEET NAME

E-103 LIGHTING DETAILSE-104 PV ROOF PLANE-106 RAMP LIGHTING PLANE-201 ELECTRICAL EQUIPMENT ELEVATIONSE-601 PV ONE-LINE DIAGRAME-603 THREE-LINE DIAGRAME-604 PANEL SCHEDULESE-605 ELECTRICAL SCHEDULES

T-001 TELECOMMUNICATIONS SYMBOLS AND NOTEST-101 TELECOMMUNICATIONS WIRING PLANT-602 DATA WIRING DIAGRAM

O-100 ARRIVAL STAGING PLANO-101 ARRIVAL SHELL ASSEMBLY SEQUENCE PLANSO-102 SUPERSTRUCTURE ASSEMBLY SEQUENCE PLANO-103 RAMP ASSEMBLY SEQUENCE PLANO-201 WATER DELIVERY AND REMOVAL PLANO-602 TRUCK LOADING DIAGRAM

SHEET LISTSHT NO SHEET NAME

A-101 SITE PLANA-110 FIRST FLOOR PLANA-111 RAMP DECK PLANA-112 ROOF PLANA-121 FIRST FLOOR REFLECTED CEILING PLANA-211 ELEVATIONSA-212 ELEVATIONSA-213 INTERIOR ELEVATIONSA-301 BUILDING SECTIONSA-302 BUILDING SECTIONSA-313 WALL SECTIONS AT WEST AND EAST ENDA-314 WALL PLAN AT WEST AND EAST ENDA-320 FLOOR SECTIONS AND DETAILSA-321 FLOOR SECTIONS AND DETAILSA-322 ROOF SECTIONSA-401 LARGE SCALE PLANSA-501 PLAN DETAILSA-511 SECTION DETAILSA-531 WINDOW AND DOOR DETAILSA-541 WINDOW AND DOOR DETAILSA-561 ROOF DETAILSA-701 TYPICAL DETAILS

F-001 FIRE PROTECTION NOTES AND SYMBOLSF-101 FIRE DETECTION AND ALARM PLANF-102 FIRE SUPPRESSION PLANF-601 FIRE PROTECTION SCHEDULESF-602 FIRE PROTECTION DIAGRAMSF-603 FIRE SPRINKLER DETAILF-901 FIRE SUPPRESSION ISOMETRICS

P-001 PLUMBING SYMBOLS AND NOTESP-101 PLUMBING SITE PLANP-102 DOMESTIC SUPPLY PLANP-103 DOMESTIC SANITARY RETURN PLANP-601 PLUMBING SCHEDULESP-602 PLUMBING DIAGRAMSP-901 DOMESTIC SUPPLY ISOMETRICSP-902 SANITARY WASTE AND VENT ISOMETRICS

M-001 MECHANICAL SYMBOLS AND NOTESM-101 HVAC EQUIPMENT AND DISTRIBUTION PLANM-102 SPILL CONTAINMENT PLANM-103 CONTAINER LOCATIONS PLANM-104 MECHANICAL GROUND CONTACT PLANM-201 MECHANICAL ELEVATIONSM-601 MECHANICAL SCHEDULESM-602 HVAC DIAGRAMSM-603 SOLAR WATER DIAGRAMSM-901 HVAC ISOMETRICSM-902 SOLAR WATER ISOMETRICS

E-001 ELECTRICAL SYMBOLS AND NOTESE-101 ELECTRICAL DISTRIBUTION PLANE-102 LIGHTING PLAN

SHEET LISTSHT NO SHEET NAME

G-000 COVER SHEETG-001 TABLE OF CONTENTSG-101 FINISHED SQUARE FOOTAGE COMPLIANCE PLANG-102 EGRESS PLANG-103 ADA TOUR ROUTE COMPLIANCE PLANG-201 SOLAR ENVELOPE COMPLIANCE ELEVATIONSG-202 SOLAR ENVELOPE COMPLIANCE ELEVATIONSG-602 EXTERIOR SHADING STUDIES

C-100 SITE LOCATION MAPC-101 GROUND CONTACT PLANC-104 SITE ELEVATIONSC-105 SITE ELEVATIONS

L-001 LANDSCAPE NOTES AND SYMBOLSL-101 LANDSCAPE SITE PLANL-102 LANDSCAPE IRRIGATION PLANL-201 LANDSCAPE ELEVATIONSL-601 LANDSCAPING DETAILSL-602 LANDSCAPING PLUMBING DIAGRAM

S-001 STRUCTURAL NOTES AND SYMBOLSS-100 FOUNDATION PLANS-101 FOUNDATION ELEVATIONS-102 FIRST FLOOR FRAMING PLANS-103 ROOF FRAMING PLANS-104 DECK FRAMING PLANS-105 RAMP DECK ELEVATIONSS-201 FRAMING ELEVATIONSS-301 FRAMING SECTIONSS-500 ENLARGE STRUCTURAL PLANS-501 ENLARGE STRUCTURAL SECTIONS-511 SECTION DETAILSS-521 RAMP AND DECK DETAILSS-522 RAMP AND DECK DETAILSS-523 RAMP AND DECK DETAILSS-524 RAMP AND DECK DETAILSS-525 RAMP AND DECK DETAILSS-526 RAMP AND DECK DETAILSS-527 RAMP AND DECK DETAILSS-535 FOUNDATION DETAILSS-536 FOUNDATION DETAILSS-537 FOUNDATION DETAILSS-538 FOUNDATION DETAILSS-539 FOUNDATION DETAILSS-540 FOUNDATION DETAILSS-541 FOUNDATION DETAILSS-542 FOUNDATION DETAILSS-543 FOUNDATION DETAILSS-544 FOUNDATION DETAILSS-550 SHELL FRAMING DETAILSS-645 SUPERSTRUCTURE DETAILSS-646 SUPERSTRUCTURE DETAILSS-801 TYPICAL DETAILSS-901 FRAMING ISOMETRICSS-903 MODULE DIAGRAM

MARK DATE DESCRIPTIONMARK DATE DESCRIPTION

Page 152: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

FIRE PROTECTION NOTES1. THE FIRE SUPPRESSION SYSTEM WAS DESIGNED ACCORDING TO

INTERNATIONAL RESIDENTIAL CODE STANDARDS.2. THE SLOPE OF CEILING IS GREATER THAN 1/3 BUT LESS THAN 2/3.

FROM THE SPRINKLER SPECIFICATION SHEET, THE SINGLESPRINKLER’S MAXIMUM COVERAGE AREA IS SELECTED TO 18” X 18”,AND THEN THE MINIMUM FLOW RATE IS 19GPM AND MINIMUMPRESSURE IS 15PSI. ACCORDING TO IRC2009 SECTION P2904.4.2,TWO SPRINKLERS RUN SIMULTANEOUSLY FOR 7 MINUTES, AND THENTHE MINIMUM WATER CONSUMPTION IS 266 GALLONS. APPROXIMATELY280 GALLONS OF WATER WILL BE DEVOTED TO THIS FIRESUPPRESSION SYSTEM AND WILL BE STORED IN A 300 GALLON TANKIN THE UNDER PORCH AREA.

3. THE PRESSURE NEEDED FOR FIRE SUPPRESSION WILL BE PROVIDEDBY A 3 HP CENTRIFUGAL PUMP. THIS PUMP WAS SIZED AFTERPERFORMING A FLOW PRESSURE SIMULATION BY THERMALENGINEERING CORPORATION.

4. THE FIRE SPRINKLER LINES ARE PEX PIPING RATED FOR FIRESUPPRESSION SYSTEMS. THESE PIPES ARE FLEXIBLE ARE ABLE TOBE ROUTED THROUGH THE SHELL STRUCTURE OF THE HOUSE. THEYWILL PENETRATE THE SHELL IN THE UNDERFLOOR AREA. EXCESSPEX PIPING WILL BE FITTED INTO THE SHELL STRUCTURE TOACCOMMODATE FOR MULTIPLE CONNECTIONS AND DISCONNECTIONSFOR OFF-SITE ASSEMBLY AND DISASSEMBLY.

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

15:0

6 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

F-001

FIRE PROTECTIONNOTES AND SYMBOLS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

DESCRIPTIONABBRV.SYMBOL

BREAK LINE

FIRE PROTECTION LEGEND

CHECK VALVE

SPRINKLER HEAD - PENDANT

SMOKE DETECTOR

CV

FLOW DIRECTION ARROW

PUMP

GATE VALVE

UNION

SD

SHP

GV

P

U

SD

MARK DATE DESCRIPTION

DV DRAIN VALVE

Page 153: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

SD

SD

28 31 46

28 31 46

21 24 16

21 24 16

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

15:0

9 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

F-101

FIRE DETECTION ANDALARM PLAN

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

3/8" = 1'-0"A1 FIRE DETECTION AND ALARM PLAN0 4' 6'2'

REFERENCE KEYNOTES21 24 16 DRY-CHEMICAL FIRE-EXTINGUISHER

EQUIPMENT28 31 46 SMOKE DETECTION SENSORS

SHEET KEYNOTES

GENERAL SHEET NOTES

Page 154: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

21 41 23

21 31 13

21 13 00

14

15

D1F-603

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

15:1

3 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

F-102

FIRE SUPPRESSIONPLAN

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

REFERENCE KEYNOTES21 13 00 FIRE-SUPPRESSION SPRINKLER SYSTEMS21 31 13 ELECTRIC-DRIVE, CENTRIFUGAL FIRE

PUMPS21 41 23 GROUND SUCTION STORAGE TANKS FOR

FIRE-SUPPRESSION WATER

SHEET KEYNOTES14 DUAL CONNECTION CONCEALED SPRINKLER

HEAD15 SINGLE CONNECTION CONCEALED

SPRINKLER HEAD

GENERAL SHEET NOTES

MARK DATE DESCRIPTION

3/8" = 1'-0"A1 FIRE SUPPRESSION PLAN0 4' 6'2'

Page 155: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

FIRE PROTECTION EQUIPMENT SCHEDULE

DESCRIPTION MANUFACTURER

V PHHZ

MODEL

GRUNDFOS CR 5-8

MAX FLOW RATE

GPM

POWER

HP

CURRENTAMPS

RATED VOLTAGE

16012019.03FIRE WATER PUMP

DIMENSIONSINCH

33 H X 8-5/8 D

TYCO LFII TY2234FIRE SPRINKLER HEADS(6 CT) 13 [EA] __ ______ 3-5/16 D

[3/4 CONNECTION]__

FIRE PROTECTION PIPING SCHEDULE

DESCRIPTION MATERIAL LENGTH

PEX PIPE NONEFIRE SUPPRESSION SHELLBRANCH SUPPLIES

FIRE SUPPRESSION MAIN LINE AND PUMP CONNECTION

~60 FEET

~50 FEET

INSULATION

45

SIZEDIAMETER INCH

1

1-1/4

FIRE PROTECTION FITTING SCHEDULE

FAMILY MATERIAL COUNT

EPFIRE SUPPRESSION SUPPLY

EP

4

4

COPPERTYPE K

6

CONNECTION SIZESDIAMETER INCH

1-1/4 X 1 X 3/4

1-1/4 X 1-1/4

TYPE

REDUCINGTEE

COUPLING

ELBOW

EP

TEE

ELBOW

EP

1-1/4 X 1-1/4

1 X 3/4

1-1/4 X 1-1/4 X 1-1/4

2

1

FIRST ALERT FE3A40GRFIRE EXTINGUISHER __ __ ______ 4.6 D x 16.0 H__

COPPER TYPE K

FIRE PROTECTION VALVE SCHEDULE

FAMILY TYPE COUNT

CHECK VALVEFIRE SUPPRESSION SUPPLY

GATE VALVEFIRE SUPPRESSION SUPPLY

1

2

CONNECTION SIZEDIAMETER INCH

1-1/4

1-1/4

FIRE PROTECTION TANK SCHEDULE

DESCRIPTION MATERIAL VOLUMEGALLONS

MEDIUM-DENSITYPOLYETHYLENE

FIRE SUPPRESSIONWATER STORAGE TANK 300

DIMENSIONS INCH

40 W X 58 L X 29 H

NONE

FIRE SUPPRESSIONPUMP CONNECTION

FIRE SUPPRESSION SUPPLY

FIRE SUPPRESSION SUPPLY

FIRE SUPPRESSION SUPPLY

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

15:1

5 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

F-601

FIRE PROTECTIONSCHEDULES

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

Page 156: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

21 41 23

21 31 13

14

15

22

23

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

15:1

6 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

F-602

FIRE PROTECTIONDIAGRAMS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

REFERENCE KEYNOTES21 31 13 ELECTRIC-DRIVE, CENTRIFUGAL FIRE

PUMPS21 41 23 GROUND SUCTION STORAGE TANKS FOR

FIRE-SUPPRESSION WATER

SHEET KEYNOTES14 DUAL CONNECTION CONCEALED SPRINKLER

HEAD15 SINGLE CONNECTION CONCEALED

SPRINKLER HEAD22 DIAPHRAGM PRESSURE TANK23 SENSOR WIRE FOR PUMP TO DIAPHRAGM

TANK

GENERAL SHEET NOTES

NTSA1 FIRE SUPPRESSION DIAGRAM

MARK DATE DESCRIPTION

Page 157: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

FIRST FLOOR4'-5"

F-603A1

F-603A4

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

15:2

3 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

F-603

FIRE SPRINKLERDETAIL

306

Checker

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

1/2" = 1'-0"D1 FIRE SPRINKLER SECTION DETAIL

3" = 1'-0"A1 SINGLE CONNECTION FIRE SPRINKLER DETAIL 3" = 1'-0"A4 DUAL CONNECTION FIRE SPRINKLER DETAIL

REFERENCE KEYNOTES

SHEET KEYNOTES

GENERAL SHEET NOTES1. THE PLACEMENT AND FLOW RATES OF THE

FIRE SPRINKLER HEADS WERE DETERMINEDBASED ON THE SPECIFICATIONS FROM TYCO.

2. FOR SLOPED CEILING GREATER THAN 4-INCHRISE UP TO MAXIMUM 8-INCH RISE FOR 12-INCHRUN.

3. THESE HEADS ARE CAPABLE OF MAXIMUMCOVERAGE AREA OF 18 X 18 (FEET), WITH A 19GPM MINIMUM FLOW RATE.

0 6" 1'3" 0 6" 1'3"

0 1' 2' 4'

Page 158: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

15:3

8 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

F-901

FIRE SUPPRESSIONISOMETRICS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

A1 FIRE SUPPRESSION ISOMETRIC0 4' 6'2'

Page 159: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

DESCRIPTIONABBRV.SYMBOL

CLEANOUT

AAV

CHECK VALVE

TRAP

PLUMBING LEGEND

FIXTURE CONNECTION

FLOOR DRAIN

FIXTURE DRAIN

BV

FLOOR PENETRATION

PUMP

GATE VALVE

AIR ADMITTANCE VALVE

BALL VALVE

SHOWER

VENT ROOF

CV

CO

FXC

FXD

FLD

FLP

GV

P

SHR

TRP

VTR

PLUMBING NOTES1. PLUMBING SYSTEMS WERE DESIGNED FOLLOWING INTERNATIONAL

RESIDENTIAL CODE, INTERNATIONAL PLUMBING CODE, AND UNIFORMPLUMBING CODE.

2. DOMESTIC HOT AND COLD WATER LINES WILL BE PEX PIPING IN ORDERTO ALLOW FOR EASE OF INSTALLATION. HORIZONTAL PEX PIPES WILL BESUPPORTED FOR EVERY 2.5 FT, COMPLYING TO 2.67 FT REQUIREMENTFROM IRC2009 TABLE P2605.1 - PIPING SUPPORT. HOT WATER SUPPLYLINE WILL BE USED INSULATED PEX PIPE TO MINIMIZE THE HEAT LOSS.PRESSURE FOR THE DOMESTIC WATER SUPPLY WILL BE PROVIDED BY A1 HP CENTRIFUGAL PUMP, AND WILL BE CONNECTED TO THE 500 GALLONFRESH WATER TANK.

3. SANITARY WASTE AND VENT LINES WILL BE PVC PIPING. THE FIXTURESANITARY DRAINS ARE GREATER OR EQUAL THAN 1-1/4” TO COMPLY WITHIRC2009 P2703.1, AND WILL DRAIN INTO 2" BRANCH LINES LEADING TO THEMAIN 2" RETURN LINE TO SANITARY WASTE TANK. THE CLOTHES WASHINGMACHINE WILL DRAIN INTO AN 18 INCH HIGH STAND PIPE TO COMPLY WITHIRC2009 P2706.2 - STANDPIPES. THE CLOTHES WASHING MACHINEDISCHARGE WILL BE THROUGH AN AIR BREAK TO COMPLY WITH IRC2009P2718.1 - WASTE CONNECTION. THE DRAINAGE FIXTURE UNIT VALUE(D.F.U.) IN OUR HOUSE IS 7, AND ACCORDING TO UNIFORM PLUMBINGCODE, 2 INCH GRAY WATER PIPES CAN BE USED. AIR ADMITTANCEVALVES ARE USED FOR LOW FLOW RATE FIXTURES (LESS THAN 18GPM),AND COMPLY WITH IRC2009 SECTION P3114.

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

50:0

2 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

P-001

PLUMBING SYMBOLSAND NOTES

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

Page 160: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

22 13 53

22 12 19

22 11 23.26

22 35 23.16

22 33 30.23

22 11 16

22 13 16

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

50:0

6 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

P-101

PLUMBING SITE PLAN

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

3/8" = 1'-0"A1 PLUMBING SITE PLAN

REFERENCE KEYNOTES22 11 16 DOMESTIC WATER PIPING22 11 23.26 CLOSE-COUPLED, HORIZONTALLY

MOUNTED, IN-LINE CENTRIFUGALDOMESTIC-WATER PUMPS

22 12 19 FACILITY GROUND-MOUNTED, POTABLEWATER STORAGE TANKS

22 13 16 SANITARY WASTE AND VENT PIPING22 13 53 FACILITY SEPTIC TANKS22 33 30.23 RESIDENTIAL, COLLECTOR-TO-TANK,

SOLAR-ELECTRIC DOMESTIC WATERHEATERS

22 35 23.16 CIRCULATING, STORAGE DOMESTIC WATERHEAT EXCHANGERS

SHEET KEYNOTES

GENERAL SHEET NOTES

0 4' 6'2'

1. WC WILL NOT BE CONNECTED TO WATER SUPPLYAND SANITARY LINES DURING COMPETITION.

Page 161: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

22 12 19

22 11 23.26

22 11 16

22 33 30.23

16

17

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

50:1

1 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

P-102

DOMESTIC SUPPLYPLAN

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

3/8" = 1'-0"A1 DOMESTIC SUPPLY PLAN

REFERENCE KEYNOTES22 11 16 DOMESTIC WATER PIPING22 11 23.26 CLOSE-COUPLED, HORIZONTALLY

MOUNTED, IN-LINE CENTRIFUGALDOMESTIC-WATER PUMPS

22 12 19 FACILITY GROUND-MOUNTED, POTABLEWATER STORAGE TANKS

22 33 30.23 RESIDENTIAL, COLLECTOR-TO-TANK,SOLAR-ELECTRIC DOMESTIC WATERHEATERS

SHEET KEYNOTES16 PEX INSULATED HOT WATER LINE17 PEX COLD WATER LINE

GENERAL SHEET NOTES

0 4' 6'2'

1. WC WILL NOT BE CONNECTED TO WATER SUPPLYAND SANITARY LINES DURING COMPETITION.

Page 162: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

22 13 53

22 11 16

22 13 19.36

22 13 19.36

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

50:1

5 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

P-103

DOMESTIC SANITARYRETURN PLAN

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

3/8" = 1'-0"A1 SANITARY WASTE AND VENT PLAN

REFERENCE KEYNOTES22 11 16 DOMESTIC WATER PIPING22 13 19.36 AIR-ADMITTANCE VALVES22 13 53 FACILITY SEPTIC TANKS

SHEET KEYNOTES

GENERAL SHEET NOTES

0 4' 6'2'

1. WC WILL NOT BE CONNECTED TO WATER SUPPLYAND SANITARY LINES DURING COMPETITION.

Page 163: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

PLUMBING EQUIPMENT SCHEDULE

DESCRIPTION MANUFACTURER

V PHHZ

MODEL

GRUNDFOS MQ 3-45

MAX FLOW RATE

GPM

POWER

HP

CURRENTAMPS

RATED VOLTAGE

16012010.01FRESH WATER PUMP

DIMENSIONSINCH

12.74H X 22.44L X 8.58W

GRUNDFOS UP15-18 BUC 7SOLAR RECIRCULATING PUMP 16 1/25 1601200.74

PLUMBING PIPING SCHEDULE

DESCRIPTION MATERIAL LENGTH

PEX PIPE NONEDOMESTIC COLD WATER

PEX PIPEDOMESTIC HOT WATER

~60 FEET

~60 FEET

INSULATION

1 INCH LAYER

19

PVCSANITARY RETURN ~50 FEET NONE

PVCSANITARY VENT ~30 FEET NONE

SIZEDIAMETER INCH

3/4 & 1/2

1-1/2 & 2

1-1/2 & 2

3/4 & 1/2

PLUMBING FITTING SCHEDULE

FAMILY MATERIAL COUNT

EPDOMESTIC WATER

EPDOMESTIC WATER

4

4

PVC

DOMESTIC WATER 6

PVCSANITARY WASTE AND VENT 3

CONNECTION SIZESDIAMETER INCH

3/4 X 3/4 X 1/2

1-1/2 X 1-1/2 X 1-1/2

3/4 & 3/4

TYPE

REDUCINGTEE

COUPLING

ELBOW

TEE

DOMESTIC WATER

PVCSANITARY WASTE AND VENT 52 X 1-1/2 X 2TEE

PVCSANITARY WASTE AND VENT 32CLEANOUT

PVC/CHROMESANITARY WASTE AND VENT 41-1/2P-TRAP

EP

TEE

SANITARY WASTE AND VENT TEE

EP

2 X 2 X 2

3/4 X 1/2

3/4 X 3/4 X 3/4

2

1

BRADFORD WHITE M-1-40L6DS**SOLAR STORAGE TANKW/ BACKUP HEAING __ __ 160240 31-1/4 H X 22 D

[40 GAL]16.0

COPPER TYPE KSOLAR HOT WATER ~25 FEET 1 INCH LAYER1 & 1/2

COPPERSOLAR HOT WATER 31 X 1 X 1/2REDUCINGTEE

COPPERSOLAR HOT WATER 101 X 1COUPLING

COPPERSOLAR HOT WATER 71 X 1/2ELBOW

PLUMBING VALVE SCHEDULE

FAMILY TYPE COUNT

BALL VALVEDOMESTIC COLD WATER

CHECK VALVEDOMESTIC COLD WATER

1

1

GATE VALVEDOMESTIC COLD WATER 2

BALL VALVESOLAR HOT WATER 6

CONNECTION SIZEDIAMETER INCH

3/4

3/4

1 & 1/2

3/4

CHECK VALVESOLAR HOT WATER 21 & 1/2

DRAINSOLAR HOT WATER 21

PRESSURE RELIEFVALVE

SOLAR HOT WATER 11MIXING VALVE

SOLAR HOT WATER 11

TEMPERATURE &PRESSURE RELIEF

VALVESOLAR HOT WATER 21

AIR-ADMITTANCEVALVESANITARY VENT 21-1/2

PLUMBING TANK SCHEDULE

DESCRIPTION MATERIAL VOLUMEGALLONS

MEDIUM-DENSITYPOLYETHYLENE

FRESH WATERSTORAGE TANK

SANITARY WATERSTORAGE TANK

500

500

STEEL CASSINGW/ VITRAGLAS LINING

SOLAR HOT WATERSTORAGE TANK 40

DIMENSIONS INCH

48 W X 92 L X 29 H

MEDIUM-DENSITYPOLYETHYLENE 48 W X 92 L X 29 H

PLUMBING FIXTURES SCHEDULE

DESCRIPTION MANUFACTURER COLOR/FINISH

KOHLERKITCHEN SINK

KITCHEN SINKFAUCET

__

POLISHED CHROME

KITCHEN SINKSTRAINER

MODEL

PURIST KITCHEN FAUCET7507-CP

DUO STRAINER8801-CP

UNDERTONE KITCHEN SINK3331-NA

BATHROOM SINK WHITE

BATHROOM SINKFAUCET

VOX VESSEL LAVATORY14800-0

KOHLER

KOHLER

KOHLER

KOHLER PURIST KITCHEN FAUCET7507-CP

POLISHED CHROME

POLISHED CHROME

KOHLERBATHROOM SINKDRAIN

SHOWER POLISHED CHROME

SHOWER DRAIN

PURIST LOW FLOWHANDSHOWER

978-CP

SHOWER DRAIN9135-CP

LAVATORY DRAIN7124-A-CP

SHOWER VALVE __

WATER CLOSET

STACKED VALVE 680-KS-NA

KOHLER

KOHLER

KOHLER

KOHLER PURIST HATBOX TOILET3492-0

POLISHED CHROME

WHITE

POLISHED CHROME

DELTA-T CONTROLSHELIODYNE INC. DLTA 000-002SOLAR THERMAL

SYSTEM CONTROLLER __ __ 1601204.45

5-1/4 H X 7-3/4 L X 3-3/4 W

31-1/4 H X 22 D

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

50:1

7 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

P-601

PLUMBING SCHEDULES

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

Page 164: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

3/4"

3/4"

1/2"

1/2"

1/2"

1/2"1/2"

1/2"

1/2"3/4"

16

17

24

25

1.5"

1.5"

2"

2"

1.5"

2"

1.5"2"

2"

1.5"

26

27

22 13 19.36

22 13 19.36

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

50:1

8 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

P-602

PLUMBING DIAGRAMS

306

Checker

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

NTSA1 DOMESTIC SUPPLY DIAGRAM

REFERENCE KEYNOTES22 13 19.36 AIR-ADMITTANCE VALVES

SHEET KEYNOTES16 PEX INSULATED HOT WATER LINE17 PEX COLD WATER LINE24 COLD WATER SUPPLY TO SOLAR WATER

SYSTEM25 HOT WATER SUPPLY FROM SOLAR WATER

SYSTEM26 SANITARY WATER RETURN TO SANITARY

WATER TANK27 SANITARY VENTING TO ROOF

GENERAL SHEET NOTES

NTSC4 SANITARY WASTE & VENT DIAGRAM

MARK DATE DESCRIPTION

Page 165: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

50:3

3 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

P-901

DOMESTIC SUPPLYISOMETRICS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

A1 DOMESTIC SUPPLY ISOMETRIC

Page 166: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

50:4

5 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

P-902

SANITARY WASTE ANDVENT ISOMETRICS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

A1 SANITARY WASTE AND VENT ISOMETRIC

Page 167: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

DESCRIPTIONABBRV.SYMBOL

BREAK LINE

BALL VALVE

PUMP

MECHANICAL LEGEND

CHECK VALVE

DUCT TRANSITION

CONDENSATE DRAIN

BDD

FLOW DIRECTION ARROW

MIXING VALVE

GATE VALVE

AIR FLOW DIRECTION ARROW

BACK DRAFT DAMPER

PRESSURE RELIEF VALVE

BV

CV

CD

DT

GV

MV

PRV

P

UNION

TEMPERATURE & PRESSURE RELIEF VALVETPRV

VCD

VOLUME CONTROL DAMPERVCD

MECHANICAL NOTES1. MECHANICAL AND HVAC SYSTEMS SHALL BE INSTALLED PER

MANUFACTURER'S SPECIFICATIONS AND INTERNATIONAL RESIDENTIALCODE.

2. THE HVAC SYSTEM IMPLEMENTS A WATER-SOURCE HEAT PUMP DRAWINGFROM A THERMAL MASS WHICH ACTS AS A GEOTHERMAL SOURCE. THETHERMAL MASS CONTAINS PHASE CHANGE MATERIAL WHICH WILL CREATEA LOWER AND UPPER BOUND TEMPERATURE RANGE THAT WILL OPTIMIZETHE PERFORMANCE OF THE HEAT PUMP. DURING COOLING MODE, HEAT WILLBE DUMPED INTO THERMAL MASS, WHILE DURING HEATING MODE COOLERWATER WILL BE PUMPED BACK INTO THERMAL MASS TANK. THIS BALANCEWILL HELP TO REDUCE ENERGY NEEDS AND REDUCE HEAT LOSS FROMSYSTEM.

3. THE THERMAL MASS WILL BE CONTAINED BY AN INSULATEDPILLOW/BLADDER TANK. THE PILLOW TANK WILL HOLD THE PHASE CHANGEMATERIAL WHICH IS CONTAINED IN LONG TUBES. APPROXIMATELY 450 OFTHESE TUBES SHALL BY PLACED INTO THE PILLOW TANK THROUGH FILLOPENING. THE TUBES WILL SELF-STACK INSIDE THE PILLOW TANK, WITHSOME ASSISTANCE. ONCE ALL PHASE CHANGE MATERIAL TUBES (TUBEICE)ARE IN PLACE, THE PILLOW TANK WILL BE FILLED WITH WATER.

4. THE PILLOW TANK WILL BE FILLED WITH WATER PUMP OUT OF THE WATERTANKS THROUGH A 1.5 INCH RUBBER HOSE. A 0.6 HP SUBMERSIBLE PUMPWILL BE USED TO PUMP THE WATER FROM THE WATER TANKS INTO THEPILLOW TANK. THIS PUMP WILL ALSO BE USED TO DRAIN THE PILLOW TANKBACK INTO THE WATER TANKS FOR WATER REMOVAL.

5. HVAC AIR DISTRIBUTION SHALL USE STANDARD RECTANGULAR DUCTINGWITH 1 INCH INSULATION LAYER. FLEXIBLE HOSE DUCT WILL BE USED FORFRESH AIR INTAKE AND ALSO FOR DEHUMIDIFIER CONNECTION. THEDEHUMIDIFIER IS PLACED IN PARALLEL TO THE REST OF THE DISTRIBUTIONSYSTEM SO THAT IF HEAT PUMP IS NOT RUNNING THE DEHUMIDIFIER COULDSTILL RUN AND DEHUMIDIFY AIR INTO HOUSE. THIS WILL REDUCE ENERGYCONSUMPTION FOR DAYS WHEN HEATING AND COOLING ARE NOT NEEDED.BATHROOM VENTILATION WILL BE PROVIDED BY A FAN UNDER THELAVATORY, AND WILL TAKE AIR OUT OF WEST BULKHEAD.

6. INSTALLATION OF MAIN SUPPLY AND RETURN DUCTS, BRANCH DUCT, ANDFLOOR DIFFUSERS WILL BE PRE-INSTALLED PER MODULE OF THE HOUSE.CONNECTIONS BETWEEN MAIN DUCTS WILL BE MADE AFTER MODULES AREPLACED TOGETHER. ALL OTHER MECHANICA EQUIPMENT WILL BE SHIPPEDSEPARATELY AND INSTALLED ONSITE.

7. SOLAR WATER HEATING WILL BE PROVIDED BY SUPERSTRUCTUREMOUNTED SOLAR THERMAL FLAT-PLATE COLLECTORS. PIPING WILL BE RUNFROM COLLECTORS INTO A SOLAR THERMAL STORAGE TANK, CONNECTEDTO A SECOND SOLAR THERMAL STORAGE TANK FITTED WITH A BACKUPHEATING ELEMENT. IN THE EVENT THAT THE COLLECTORS DON'T PROVIDESUFFICIENT WATER HEATING, THE BACKUP HEATER WILL MAKE UP THEDIFFERENCE. A MIXING VALVE WILL TAKE WATER FROM SOLAR STORAGETANKS AND MIX WITH COLD WATER FROM FRESH WATER TANK.

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

43:0

9 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

M-001

MECHANICAL SYMBOLSAND NOTES

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

Page 168: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

23 81 46

23 84 16

23 21 13.4323 21 23.13

23 71 13.23

23 38 18

11

10

23 37 13.13

13

12

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

43:1

2 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

M-101

HVAC EQUIPMENT ANDDISTRIBUTION PLAN

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

3/8" = 1'-0"A1 HVAC PLAN

REFERENCE KEYNOTES23 21 13.43 THERMAL MASS LOOP HEAT-PUMP PIPING23 21 23.13 IN-LINE CENTRIFUGAL HYDRONIC PUMPS23 37 13.13 FLOOR DIFFUSER23 38 18 ROOM EXHAUST FAN23 71 13.23 PRESSURIZED-WATER THERMAL STORAGE

TANKS23 81 46 WATER-SOURCE UNITARY HEAT PUMPS23 84 16 DEHUMIDIFIERS

SHEET KEYNOTES10 FRESH AIR INTAKE11 BATHROOM VENTILATION EXHAUST12 AIR SUPPLY MAIN DUCT13 AIR RETURN MAIN DUCT

GENERAL SHEET NOTES

MARK DATE DESCRIPTION

0 4' 6'2'

Page 169: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

22 12 1922 33 30.23

22 13 53

21 41 23

22 11 23.26

22 11 16

23 81 46

23 71 13.23

23 21 23.13

23 21 13.43

21 31 13

18

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

43:2

1 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

M-102

SPILL CONTAINMENTPLAN

306

Checker

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

3/8" = 1'-0"A1 SPILL CONTAINMENT PLAN

REFERENCE KEYNOTES21 31 13 ELECTRIC-DRIVE, CENTRIFUGAL FIRE

PUMPS21 41 23 GROUND SUCTION STORAGE TANKS FOR

FIRE-SUPPRESSION WATER22 11 16 DOMESTIC WATER PIPING22 11 23.26 CLOSE-COUPLED, HORIZONTALLY

MOUNTED, IN-LINE CENTRIFUGALDOMESTIC-WATER PUMPS

22 12 19 FACILITY GROUND-MOUNTED, POTABLEWATER STORAGE TANKS

22 13 53 FACILITY SEPTIC TANKS22 33 30.23 RESIDENTIAL, COLLECTOR-TO-TANK,

SOLAR-ELECTRIC DOMESTIC WATERHEATERS

23 21 13.43 THERMAL MASS LOOP HEAT-PUMP PIPING23 21 23.13 IN-LINE CENTRIFUGAL HYDRONIC PUMPS23 71 13.23 PRESSURIZED-WATER THERMAL STORAGE

TANKS23 81 46 WATER-SOURCE UNITARY HEAT PUMPS

SHEET KEYNOTES18 AQUAPONICS TANKS

GENERAL SHEET NOTES

0 4' 6'2'

Page 170: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

23 71 13.23

21 41 23

22 33 30.23 22 12 19

22 13 53

18

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

43:2

8 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

M-103

CONTAINERLOCATIONS PLAN

306

Checker

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

3/8" = 1'-0"A1 CONTAINER LOCATIONS PLAN

REFERENCE KEYNOTES21 41 23 GROUND SUCTION STORAGE TANKS FOR

FIRE-SUPPRESSION WATER22 12 19 FACILITY GROUND-MOUNTED, POTABLE

WATER STORAGE TANKS22 13 53 FACILITY SEPTIC TANKS22 33 30.23 RESIDENTIAL, COLLECTOR-TO-TANK,

SOLAR-ELECTRIC DOMESTIC WATERHEATERS

23 71 13.23 PRESSURIZED-WATER THERMAL STORAGETANKS

SHEET KEYNOTES18 AQUAPONICS TANKS

GENERAL SHEET NOTES

0 4' 6'2'

Page 171: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

22 13 53

22 12 19

21 41 23

22 33 30.23

E

F

G

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

43:3

2 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

M-104

MECHANICAL GROUNDCONTACT PLAN

306

Checker

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

3/8" = 1'-0"A1 MECHANICAL GROUND CONTACT PLAN

REFERENCE KEYNOTES21 41 23 GROUND SUCTION STORAGE TANKS FOR

FIRE-SUPPRESSION WATER22 12 19 FACILITY GROUND-MOUNTED, POTABLE

WATER STORAGE TANKS22 13 53 FACILITY SEPTIC TANKS22 33 30.23 RESIDENTIAL, COLLECTOR-TO-TANK,

SOLAR-ELECTRIC DOMESTIC WATERHEATERS

SHEET KEYNOTESE TYPICAL WATER TANK FOOTINGF TYPICAL FIRE TANK FOOTINGG HOT WATER TANKS FOOTING

GENERAL SHEET NOTES1. ALL MECHANICAL EQUIPMENT LOCATED IN THE

UNDER-PORCH AREA WILL BE ELEVATED 3-1/2 INCHOFF THE GROUND ON STANDS.

2. THESE STANDS WILL HAVE FOOTINGS AS SHOWNWITH PRESSURES INDICATED IN MECHANICALFOOTING SCHEDULE.

MECHANICAL FOOTING SCHEDULE

FOOTING TYPE QUANTITY SIZE DIA AREA (SF) TOTAL FILLED LOAD PER TANK (LBS)

E (WATER TANKS)

F (FIRE TANK)

G (HOT WATER TANKS)

8

4

1

1'

10"

N/A

0.7854

0.5454

0.8194

4,360

2,615

454 (2 CT)

1,387.8

1,198.6

1,108.1

FOOTING PRESSURE (PSF)

0 4' 6'2'

Page 172: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

FIRST FLOOR4'-5"

SOLAR ENVELOPE18'-0"

GRADE LEVEL0"

2 3 4 5 6 7 8 9 10 111

FIRST FLOOR4'-5"

SOLAR ENVELOPE18'-0"

GRADE LEVEL0"

D BF AE C

FIRST FLOOR4'-5"

SOLAR ENVELOPE18'-0"

GRADE LEVEL0"

DB FA EC

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

43:5

4 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

M-201

MECHANICALELEVATIONS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

REFERENCE KEYNOTES

SHEET KEYNOTES

GENERAL SHEET NOTES

MARK DATE DESCRIPTION

1/4" = 1'-0"A1 SOUTH MECHANICAL

1/4" = 1'-0"C4 EAST MECHANICAL 1/4" = 1'-0"C1 WEST MECHANICAL ELEVATION

0 2' 4' 8' 0 2' 4' 8'

0 2' 4' 8'

Page 173: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

WATER COOLED AIR CONDITIONING EQUIPMENT SCHEDULE

DESCRIPTION MANUFACTURER

V PHHZ

MODEL

COMPRESSOR (1 EACH)

JOHNSON CONTROLS RJSH015ER000C

FLOW RATE

GPM CFM

COOLINGEWT 86°F

CAPACITY EERBTUH BTUH/W

HEATINGEWT 68°F

CAPACITYCOP

BTUH

PSC FAN MOTOR

HP [W] FLAFACTORY CHARGE

R410A, OZ [KG] RLA LRA

RATED VOLTAGE TOTAL UNIT

FLA

MIN CIRC

AMP

MAX FUSE

HACR

1511.810.216023029.06.238 [1.08]1/6 [134] 4.05.318,50015.914,4005004.0WATER-SOURCE HEAT PUMP

HVAC EQUIPMENT SCHEDULE

DESCRIPTION MANUFACTURER

V PHHZ

MODEL

THERMA-STOR LLC ULTRA-AIRE 65H

FLOW RATE

GPM CFM

POWER

HP WATTS

CURRENTAMPS

RATED VOLTAGE

1601205.50680500DEHUMIDIFIER

DIMENSIONSINCH

21 W X 12 H X 12 D

GRUNDFOS UP15-18 BUC 7THERMAL MASS CIRCULATING PUMP 0 - 16 1/25 160120 5-1/4 H X 7-3/4 L X 3-3/4 W0.74

PANASONICWHISPERGREEN LITE

VENTILATION FANFV-08VKML3

BATHROOM VENTILATION FAN 80 14.9 160120 11.5H x 14.17W x 16.73D0.12

HVAC DUCT AND PIPING SCHEDULE

DESCRIPTION MATERIAL LENGTH

FABRICATED SHEET METAL 1 INCH LAYERRECTANGULAR METAL DUCT

COPPER TYPE K1 INCH THERMAL MASS PIPE

~100 FEET

~30 FEET

INSULATION

1 INCH LAYER

SOLAR THERMAL EQUIPMENT SCHEDULE

DESCRIPTION MANUFACTURER MODEL

HELIODYNE 26,199 (19,742)HEATING SOLARFLAT-PLATE COLLECTORS GOBI 406

DAILY INSOLATION BTU500 ZONE (400 ZONE) PANEL COATING PANEL SIZE

(INCH)

BLACK PAINT 47.56 X 81.56

JOHNSON CONTROLSRJ SERIES CONTROLS

PREMIERMICROPROCESSOR

HVAC CONTROLS 160120_________

__

__

__

__

__ __

__

__

__

__

__

RAINWATER COLLECTIONSOLUTIONS, INC

1200 GALLONPILLOW TANKTHERMAL MASS PILLOW TANK ______ 15' L X 8' W X 2' H

[FEET]____ __ __ __

PCM PRODUCTS LTD TUBEICEENAPSULATED PCMPHASE CHANGE MATERIAL __________ __ __ __ 1000 MM LENTH

50 MM DIAMETER

MECHANICAL VALVE SCHEDULE

FAMILY TYPE COUNT

VOLUME-CONTROLDAMPERHVAC AIR DISTRIBUTION

BACK DRAFTDAMPERHVAC AIR DISTRIBUTION

12

2

GATE VALVETHERMAL MASS LOOP 4

BALL VALVETHERMAL MASS LOOP 2

CONNECTION SIZEDIAMETER INCH

6

1

1

7.5

CHECK VALVETHERMAL MASS LOOP 21

CONDENSATEDRAINHVAC EQUIPMENT 21

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

43:5

6 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

M-601

MECHANICALSCHEDULES

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

Page 174: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

23 84 16

23 81 46

23 71 13.23

23 71 13.26

23 21 23.13

23 21 13.43

23 38 18

10

11

23 33 13.13

23 37 13.13

23 32 36

12

13

23 33 13.13

23 33 13.23

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

43:5

7 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

M-602

HVAC DIAGRAMS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

REFERENCE KEYNOTES23 21 13.43 THERMAL MASS LOOP HEAT-PUMP PIPING23 21 23.13 IN-LINE CENTRIFUGAL HYDRONIC PUMPS23 32 36 AIR-DISTRIBUTION FLOOR PLENUMS23 33 13.13 VOLUME-CONTROL DAMPERS23 33 13.23 BACKDRAFT DAMPERS23 37 13.13 FLOOR DIFFUSER23 38 18 ROOM EXHAUST FAN23 71 13.23 PRESSURIZED-WATER THERMAL STORAGE

TANKS23 71 13.26 PHASE CHANGE MATERIAL FOR THERMAL

STORAGE23 81 46 WATER-SOURCE UNITARY HEAT PUMPS23 84 16 DEHUMIDIFIERS

SHEET KEYNOTES10 FRESH AIR INTAKE11 BATHROOM VENTILATION EXHAUST12 AIR SUPPLY MAIN DUCT13 AIR RETURN MAIN DUCT

GENERAL SHEET NOTES

NTSA1 HVAC DIAGRAM

MARK DATE DESCRIPTION

Page 175: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

22 33 30.23

22 35 23.16

23 56 13.13

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

43:5

8 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

M-603

SOLAR WATERDIAGRAMS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

REFERENCE KEYNOTES22 33 30.23 RESIDENTIAL, COLLECTOR-TO-TANK,

SOLAR-ELECTRIC DOMESTIC WATERHEATERS

22 35 23.16 CIRCULATING, STORAGE DOMESTIC WATERHEAT EXCHANGERS

23 56 13.13 HEATING SOLAR FLAT-PLATE COLLECTORS

SHEET KEYNOTES

GENERAL SHEET NOTES

NTSA1 SOLAR WATER DIAGRAM

MARK DATE DESCRIPTION

Page 176: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

44:1

4 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

M-901

HVAC ISOMETRICS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

A1 HVAC ISOMETRIC

MARK DATE DESCRIPTION

Page 177: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

44:2

2 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

M-902

SOLAR WATERISOMETRICS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

A1 SOLAR WATER ISOMETRIC

Page 178: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

13:4

9 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

A-561

ROOF DETAILS

306

CHECKER

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

REFERENCE KEYNOTES

SHEET KEYNOTES

GENERAL SHEET NOTES

MARK DATE DESCRIPTION

1" = 1'-0"E1 ROOF PLUMBING VENT PENETRATION0 2' 3'1'

Page 179: RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL … · RENEWABLE ENERGY APPLICATIONS IN RESIDENTIAL HOMES ... The work on HDH desalination would have also ... Flow diagram of Riley’s

22 13 53

22 12 19

21 41 23

23 71 13.23

18

WATER DELIVERY AND REMOVAL SCHEDULE1. ON DAY 5 OF COMPETITION WATER WILL BE DELIVERED TO SITE. TRUCK WILL ARRIVE ON DECATHLON WAY. HOSE WILL BE

UNLOADED AND BROUGHT TO SIDE OF PORCH.2. THE PORCH ACCESS DOORS WILL BE OPENED AND THE HOSE WILL BE RUN UNDER PORCH AREA TO BE INSERTED INTO

THE FRESH WATER STORAGE TANK. PRIOR TO DELIVERY A CONNECTION BETWEEN THE FRESH WATER TANK ANDSANITARY TANK WILL BE MADE. AS THE FRESH WATER TANK IS FILLED, WATER WILL ALSO FLOW INTO THE SANITARY WATERTANK VIA THE CONNECTION. BOTH TANKS WILL BE FILLED WITH APPROXIMATELY 500 GALLONS EACH, FOR A TOTAL INITIALDELIVERY OF 1000 GALLONS.

3. AFTER INITIAL DELIVERY WATER WILL BE DISTRIBUTED FROM FRESH AND SANITARY WATER TANKS INTO THE THERMALMASS PILLOW TANK AND FIRE TANK. THIS WILL BE DONE USING A SANITARY SUBMERSIBLE PUMP AND HOSE. THIS PROCESSWILL EMPTY BOTH FRESH AND SANITARY WATER TANKS.

4. WATER TRUCK WILL RETURN FOR "TOP OFF" OF FRESH WATER TANK. THIS WILL TAKE THE REMAINING 500 GALLONS OFALLOTTED WATER DELIVERY BUDGET. AT THIS POINT THE CONNECTION BETWEEN THE SANITARY AND FRESH WATERTANKS WILL HAVE BEEN REMOVED, AND CONNECTION POINTS PLUGGED. IT WILL REMAIN THIS WAY DURING COMPETITION.

5. ON WATER REMOVAL DAY THE WATER TRUCK WILL ARRIVE ON DECATHLON WAY. HOSE WILL BE UNLOADED ANDBROUGHT TO SIDE OF PORCH.

6. PRIOR TO WATER REMOVAL WATER WILL BE DRAINED FROM THERMAL MASS PILLOW TANK AND FIRE TANK BACK INTOFRESH AND SANITARY WATER TANKS. THIS WILL BE DONE USING A SANITARY SUBMERSIBLE PUMP AND HOSE. THISPROCESS WILL FILL BOTH FRESH AND SANITARY WATER TANKS.

7. THE PORCH ACCESS DOORS WILL BE OPENED AND THE HOSE WILL BE RUN UNDER PORCH AREA TO BE INSERTED INTOTHE FRESH WATER STORAGE TANK. PRIOR TO REMOVAL THE CONNECTION BETWEEN THE FRESH WATER TANK ANDSANITARY TANK WILL BE MADE. AS THE FRESH WATER TANK IS DRAINED, WATER WILL ALSO DRAIN FROM THE SANITARYWATER TANK VIA THE CONNECTION. BOTH TANKS WILL BE DRAINED OF APPROXIMATELY 500 GALLONS EACH, FOR A TOTALINITIAL REMOVAL OF 1000 GALLONS.

8. AFTER INITIAL REMOVAL THE WATER NOW CONTAINED IN THE AQUAPONICS TANKS WILL BE DRAINED AND PUMPED BACKINTO SANITARY WATER TANK, WITH CONNECTION BETWEEN FRESH AND SANITARY TANKS STILL IN PLACE. THE WATERTRUCK WILL RETURN AFTER SERVICING OTHER HOUSES TO REMOVE APPROXIMATELY 500 GALLONS OF REMAININGWATER.

FIRST FLOOR4'-5"

GRADE LEVEL0"

1'-4

3/4

"

1 2 3 4 5 6 7

A

B

C

D

E

1 2 3 4 5 6 7

A

B

C

D

E

SHEET TITLE

LOT NUMBER:

DRAWN BY:

CHECKED BY:

COPYRIGHT:

CLIENT

U.S. DEPARTMENT OF ENERGY

SOLAR DECATHLON 2011

WWW.SOLARDECATHLON.GOV

TEAM NAME:

ADDRESS:

CONTACT:

ARCHITECTURE:

CONSULTANTS

ENGINEERS:

LANDSCAPING:

CODE CONSULTANTS:

UNIVERSITY OF HAWAI'ISCHOOL OF ARCHITECTURE

UNIVERSITY OF HAWAI'I

5/3/

2011

10:

49:5

6 AM

UNIVERSITY OF HAWAI'I AT MĀNOA2410 CAMPUS ROADHONOLULU, HI 96822

O-201

WATER DELIVERY ANDREMOVAL PLAN

306

Checker

UNIVERSITY OF HAWAII (TEAM HAWAII)

[email protected]

MARK DATE DESCRIPTION

1/4" = 1'-0"A1 WATER DELIVERY AND REMOVAL PLAN

REFERENCE KEYNOTES21 41 23 GROUND SUCTION STORAGE TANKS FOR

FIRE-SUPPRESSION WATER22 12 19 FACILITY GROUND-MOUNTED, POTABLE

WATER STORAGE TANKS22 13 53 FACILITY SEPTIC TANKS23 71 13.23 PRESSURIZED-WATER THERMAL STORAGE

TANKS

SHEET KEYNOTES18 AQUAPONICS TANKS

GENERAL SHEET NOTES

3/8" = 1'-0"D1 WATER DELIVERY AND REMOVAL SECTION DETAIL

0 2' 4' 8'

0 4' 6'2'