RELEASE ORDER APPLICATION SYSTEM REQUIREMENT SPECIFICATION
VERSION 1.6
Submitted to
Food Corporation of India FCI Head Quarters Barakhamba Road New Delhi
Copy to
National Informatics Centre. CGO Complex New Delhi
Submitted by
eCentric Solutions Pvt. Ltd N161-A, 2nd Floor, Saira Tower Yusuf Sarai, Green Park New Delhi – 110049 www.e-centricsolutions.com
Reference: Work Order No: W1460017 Project No: P131782MPND
2 2 J U N E 2 0 1 5
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
2
Disclaimer
This SRS includes data that shall not be disclosed outside the client and shall not be duplicated, used or disclosed in whole or in part for any purpose other than to evaluate this proposal. If, however, a contract is awarded to FCI as a result of, or in connection with, the submission of this data, FCI shall have the right to duplicate, use or disclose the data to the extent provided in the resulting contract. This restriction does not limit the FCI’s right to use the information contained in this data if it is obtained from another source or provided by client.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
3
TABLE OF CONTENTS
1. INTRODUCTION ................................................................................................................................................................. 9
1.1 ABOUT ECENTRIC ...................................................................................................................................................................... 9 1.2 ABOUT FOOD CORPORATION OF INDIA ........................................................................................................................................ 10 1.3 ABOUT NATIONAL INFORMATICS CENTRE ..................................................................................................................................... 11 1.4 ABOUT THE PROJECT ................................................................................................................................................................ 11 1.5 PURPOSE & SCOPE OF THE DOCUMENT........................................................................................................................................ 11 1.6 INTENDED AUDIENCE ................................................................................................................................................................ 12 1.7 STAKEHOLDERS ....................................................................................................................................................................... 12 1.8 REFERENCES ........................................................................................................................................................................... 12 1.9 DEFINITIONS, ACRONYMS AND ABBREVIATIONS ............................................................................................................................. 13
2. EXECUTIVE SUMMARY .................................................................................................................................................... 13
2.1 ABOUT RELEASE ORDER ............................................................................................................................................................ 14 2.2 EXISTING SYSTEM .................................................................................................................................................................... 15
2.2.1 Release Order Operations - Manual .......................................................................................................................... 15 2.2.2 External Applications – Runs Independently ............................................................................................................. 16 2.2.3 Weighbridges – Stand alone - Vender Specific – Different Makes & Models ............................................................ 16
2.3 PROPOSED SYSTEM .................................................................................................................................................................. 17 2.3.1 Objectives .................................................................................................................................................................. 18 2.3.2 Outcomes .................................................................................................................................................................. 18 2.3.3 Assumptions .............................................................................................................................................................. 19 2.3.4 Dependencies ............................................................................................................................................................ 19
3. REQUIREMENTS STUDY ................................................................................................................................................... 20
3.1 VISITED LOCATIONS .................................................................................................................................................................. 20 3.2 OBJECTIVE OF STUDY ................................................................................................................................................................ 23 3.3 UNDERSTANDING THE EXISTING SYSTEM ...................................................................................................................................... 24
3.3.1 Project Stakeholders with Roles & Responsibilities ................................................................................................... 24 3.3.2 Schemes .................................................................................................................................................................... 27 3.3.3 Release Order Steps .................................................................................................................................................. 32 3.3.4 Release Order Parameters ........................................................................................................................................ 34 3.3.5 External Applications................................................................................................................................................. 36
3.4 APPLICATION PROSPECTIVE ........................................................................................................................................................ 38 3.4.1 Release Order process steps ...................................................................................................................................... 38 3.4.2 Release Order Initiation ............................................................................................................................................ 39
3.4.2.1 Allocation Process .............................................................................................................................................................. 39 3.4.2.2 Indent Generation ............................................................................................................................................................. 43
3.4.3 Release Order Generation steps ................................................................................................................................ 44 3.4.4 Release Order Execution steps .................................................................................................................................. 46 3.4.5 Release Order Diversion Steps ................................................................................................................................... 47 3.4.6 Release Order Extension Steps .................................................................................................................................. 48 3.4.7 Release Order Reimbursement steps ........................................................................................................................ 50 3.4.8 Release Order Operations at Delhi ............................................................................................................................ 51
3.4.8.1 Bulk Parties ........................................................................................................................................................................ 51 3.4.8.2 Small Traders ..................................................................................................................................................................... 52 3.4.8.3 Kendriya Bhandar .............................................................................................................................................................. 53
4. PROPOSED BUSINESS SOLUTION ..................................................................................................................................... 54
4.1 RELEASE ORDER ARCHITECTURE ................................................................................................................................................. 54 4.2 FUNCTIONAL REQUIREMENTS ..................................................................................................................................................... 55
4.2.1 Workflow Engine ....................................................................................................................................................... 55
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
4
4.2.1.1 Allocation ........................................................................................................................................................................... 56 4.2.1.2 indent ................................................................................................................................................................................ 60 4.2.1.3 Release Order .................................................................................................................................................................... 67 4.2.1.4 Inflow ................................................................................................................................................................................. 71 4.2.1.5 Outflow .............................................................................................................................................................................. 78 4.2.1.6 Diversion ............................................................................................................................................................................ 85 4.2.1.7 Extension ........................................................................................................................................................................... 86 4.2.1.8 Stock Processing ................................................................................................................................................................ 90 4.2.1.9 NCDEX RO .......................................................................................................................................................................... 92 4.2.1.10 RO Reimbursement............................................................................................................................................................ 93
4.2.2 Data Exchange Engine ............................................................................................................................................... 94 4.2.3 Web Portal ................................................................................................................................................................ 95
4.2.3.1 Functional Requirements ................................................................................................................................................... 95 4.2.3.2 User Interface Requirements ............................................................................................................................................. 97 4.2.3.3 General Requirements ..................................................................................................................................................... 131
4.2.4 Database Requirements .......................................................................................................................................... 131 4.2.4.1 Determine the tables ....................................................................................................................................................... 131 4.2.4.2 Determine the fields you need in the tables ................................................................................................................... 132 4.2.4.3 Identify fields with unique values .................................................................................................................................... 132 4.2.4.4 Normalization .................................................................................................................................................................. 132 4.2.4.5 determine the relationships between tables ................................................................................................................... 133 4.2.4.6 Create Masters Data and Basic Data to Run the Application ........................................................................................... 133 4.2.4.7 Identify Sharing Fields ...................................................................................................................................................... 134 4.2.4.8 Backup & Maintenance .................................................................................................................................................... 134
4.3 BEHAVIORAL REQUIREMENTS – SYSTEM LEVEL ............................................................................................................................ 135 4.3.1 Use Case View ......................................................................................................................................................... 135
4.3.1.1 Release Order Process ..................................................................................................................................................... 135 4.3.1.2 Release Order Initiation ................................................................................................................................................... 136 4.3.1.3 Release Order Generation ............................................................................................................................................... 137 4.3.1.4 Release Order Execution .................................................................................................................................................. 138 4.3.1.5 Release Order Closing & Other Scenarios ........................................................................................................................ 139
5. NON FUNCTIONAL REQUIREMENTS ............................................................................................................................... 139
5.1 PERFORMANCE REQUIREMENTS................................................................................................................................................ 139 5.2 SAFETY AND SECURITY REQUIREMENTS ...................................................................................................................................... 140 5.3 SOFTWARE QUALITY ATTRIBUTES .............................................................................................................................................. 140
5.3.1 High Availability ...................................................................................................................................................... 140 5.3.1.1 Infrastructure Level – NIC ............................................................................................................................................... 140 5.3.1.2 Software level .................................................................................................................................................................. 140
5.3.2 Scalability ................................................................................................................................................................ 141 5.3.3 Interoperability ........................................................................................................................................................ 141 5.3.4 Usability .................................................................................................................................................................. 142 5.3.5 Extensibility ............................................................................................................................................................. 142 5.3.6 Maintainability ........................................................................................................................................................ 143 5.3.7 Uniformity of parameter ......................................................................................................................................... 143
5.4 USER GROUPS WITH ACCESS LEVELS .......................................................................................................................................... 145 5.5 APPLICATION ENVIRONMENT ................................................................................................................................................... 146
5.5.1 Client Environment .................................................................................................................................................. 146 5.5.1.1 Operating System ............................................................................................................................................................ 146 5.5.1.2 System Configuration ...................................................................................................................................................... 146 5.5.1.3 Supported Browsers ........................................................................................................................................................ 146
5.5.2 Development Environment ...................................................................................................................................... 146 5.5.2.1 Operating system ............................................................................................................................................................. 146 5.5.2.2 System Configuration ...................................................................................................................................................... 147 5.5.2.3 Software .......................................................................................................................................................................... 147
5.5.3 Deployment Environment........................................................................................................................................ 147 5.6 IMPLEMENTATION APPROACH .................................................................................................................................................. 148
5.6.1 Implementation Strategy ........................................................................................................................................ 148
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
5
5.6.2 Execution Plan ......................................................................................................................................................... 149 5.7 CAPACITY BUILDING & USER TRAINING ...................................................................................................................................... 149
6. APPENDIX A - DATA DICTIONARY .................................................................................................................................. 150
7. APPENDIX B - GROUP LOG ............................................................................................................................................. 151
8. APPENDIX C - REFERENCE DOCUMENTS & PHYSICAL COPIES ......................................................................................... 151
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
6
TABLE OF FIGURES (Flowcharts, Screens & Reports)
Figure 1: FCI Offices .......................................................................................................................................................................... 10 Figure 2: Roles & Responsibilities ..................................................................................................................................................... 24 Figure 3: RO Process Steps ................................................................................................................................................................ 39 Figure 4: Allocation Process - Welfare Schemes ............................................................................................................................... 41 Figure 5: Allocation Process - Commercial Schemes ........................................................................................................................ 43 Figure 6: Indent Generation .............................................................................................................................................................. 44 Figure 7: RO Generation Process ...................................................................................................................................................... 45 Figure 8: RO Execution Process ......................................................................................................................................................... 47 Figure 9: RO Diversion Process ......................................................................................................................................................... 48 Figure 10: RO Extension Steps .......................................................................................................................................................... 49 Figure 11: Bulk Parties ...................................................................................................................................................................... 51 Figure 12: Small Traders ................................................................................................................................................................... 52 Figure 13: Kendriya Bhandar ............................................................................................................................................................. 53 Figure 14: Architecture ..................................................................................................................................................................... 55 Figure 15: Login Page ........................................................................................................................................................................ 98 Figure 16: Dashboard ........................................................................................................................................................................ 98 Figure 17: State Wise Allocation Page .............................................................................................................................................. 99 Figure 18: Add New Revenue District Wise Allocation Page ........................................................................................................... 100 Figure 19: Update Revenue District Wise Allocation Page ............................................................................................................. 101 Figure 20: Generate Indent ............................................................................................................................................................. 102 Figure 21: Indent Approval ............................................................................................................................................................. 103 Figure 22: Make Payment ............................................................................................................................................................... 103 Figure 23: Make Offline Payment ................................................................................................................................................... 104 Figure 24: Pending for FAP Approval .............................................................................................................................................. 105 Figure 25: Approve Indent by Sales ................................................................................................................................................ 106 Figure 26: Release Order Creation .................................................................................................................................................. 107 Figure 27: Release Order Approval ................................................................................................................................................. 108 Figure 28: Gate Entry Token No ...................................................................................................................................................... 109 Figure 29: Inflow Token No ............................................................................................................................................................. 110 Figure 30: Weighbridge - Loaded Truck (Inflow) ............................................................................................................................. 111 Figure 31: Unit/Shed In-charge (Inflow) ......................................................................................................................................... 112 Figure 32: Generate Gate Pass (Exit) .............................................................................................................................................. 113 Figure 33: Empty Truck (Inflow) ...................................................................................................................................................... 114 Figure 34: Gate Exit (Inflow) ........................................................................................................................................................... 115 Figure 35: Empty Vehicle (Outflow) ................................................................................................................................................ 116 Figure 36: Generate Token ............................................................................................................................................................. 116 Figure 37: Gate Exit Loaded Truck .................................................................................................................................................. 117 Figure 38: Depot Manager Review & Approval .............................................................................................................................. 118 Figure 39: RO Diversion .................................................................................................................................................................. 119 Figure 40: RO Extension .................................................................................................................................................................. 120 Figure 41: NCDEX Release Order Digitization ................................................................................................................................. 121 Figure 42: NCDEX RO Approval ....................................................................................................................................................... 122 Figure 43: FAP Verification .............................................................................................................................................................. 123 Figure 44: Upgrade/Downgrade ..................................................................................................................................................... 124 Figure 45: Gain/Loss........................................................................................................................................................................ 124 Figure 46: Daily Deposit .................................................................................................................................................................. 125 Figure 47: FAP Approval .................................................................................................................................................................. 125 Figure 48: Gate Operator Inflow ..................................................................................................................................................... 125 Figure 49: Gate Operator Outflow .................................................................................................................................................. 126 Figure 50: Indent Approver ............................................................................................................................................................. 126 Figure 51: Area Sales Manager Report ........................................................................................................................................... 126 Figure 52: Indent Report ................................................................................................................................................................. 127
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
7
Figure 53: Release Order between Dates ....................................................................................................................................... 127 Figure 54: Release Order Approver................................................................................................................................................. 127 Figure 55: Release Order Creator ................................................................................................................................................... 128 Figure 56: Scheme Commodity Wise Issue ..................................................................................................................................... 128 Figure 57: Scheme Commodity Wise Issue Summary ..................................................................................................................... 129 Figure 58: Scheme Wise Issue ......................................................................................................................................................... 129 Figure 59: Issues off take ................................................................................................................................................................ 130 Figure 60: Statement of Issue ......................................................................................................................................................... 130 Figure 61: Use Case Release Order Process .................................................................................................................................... 135 Figure 62: Use Case Release Order Initiation .................................................................................................................................. 136 Figure 63: Use Case Release Order Generation .............................................................................................................................. 137 Figure 64: Use Case Release Order Execution ................................................................................................................................ 138 Figure 65: RO Closing & Other Scenarios ........................................................................................................................................ 139 Figure 66: Data Dictionary .............................................................................................................................................................. 150
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
8
Date Ver. No. Description Author Comments
01/07/2014 Ver. 1.0 Prepared based on Field Study
eCentric Team Initial Version shared with NIC for review and approval
21/07/2014 Ver. 1.1 Prepared based on Field Study
eCentric Team Edited by eCentric Team shared with NIC for review and approval
09/01/2015 Ver. 1.2 Based on discussion during development review
eCentric Team Edited by eCentric Team shared with NIC for review and approval
10/02/2015 Ver. 1.3 Based on discussion during development review
eCentric Team Edited by eCentric Team shared with FCI and NIC for review and approval
03/03/2015 Ver. 1.4 Based on discussion during development review
eCentric Team Edited by eCentric Team shared with FCI and NIC for review and approval
10/03/2015 Ver. 1.4 Based on discussion during development review
eCentric Team Reviewed and Approved by FCI
19/05/2015 Ver. 1.5 SRS Modification based on the review comments shared in the FAP meeting. Please refer the below section for details:
a) a) Section 4.2.1 for
Workflow engine
b) b) Section 4.2.3.2 for
Screens and Reports
eCentric Team Submit for final approval
19/06/2015 Ver. 1.6 SRS modification based on the following : 1) Feed Back received from Sales Team 2) Review Comments by IUG members during SRS finalization meetings dated 12th June 2015 & 16th June 2015
eCentric Team Submitted for sign off
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
9
1. INTRODUCTION
1.1 ABOUT ECENTRIC
eCentric Solutions Pvt. Ltd., (eCentric) part of Paradigm Group is one of the fastest growing Information Technology Company. Established in 2002, eCentric is a Total IT solution company with an enviable client list that includes Fortune 500, US Government and Indian Government Clients. eCentric has seen more than 100% growth in resources and revenues right from the first year of its operations. Our rich process development history and experience in partner engineering services position us to provide superior development, testing and support services to the client. We follow mature execution processes to ensure higher predictability, higher quality and lower risk. eCentric leverages its specialized resource pool and superior technology to deliver services with superior quality and economics. We adhere to the highest industry standards and adopt best practices and we are ISO-9001-2008, CMMI Level 5 accredited and Six Sigma compliant. eCentric provides services and solutions in every key area of information technology and management. The services and solutions are conceived and developed to provide a competitive edge to our Client's business. Our service range includes but not limited to:
Application Engineering
Application conversion / migration
Product Engineering
Product Implementation and deployment
Enterprise Content Management and Portals (ECMP)
GIS Consulting
Quality Assurance Testing
ITES / BPO Services
Web Site: www.e-centricsolutions.com
eCentric is an implementation agency responsible for executing automation of Release Order Process application for Food Corporation of India (FCI) through National Informatics Centre (NIC).
Contact Details
Sr. No. Particulars eCentric (Implementation Agency)
1. Name Abhishek Mishra
2. Phone +91 11 43332301
3 E-mail Address [email protected]
4 Mobile 91 9899763881
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
10
1.2 ABOUT FOOD CORPORATION OF INDIA The Food Corporation of India (FCI) was incorporated under the Food Corporation Act, 1964 with the function of undertaking purchase, storage, movement, transportation, distribution and sale of food grains on behalf of the Government of India (GOI). It is an agency under the administrative supervision and control of the Ministry of Consumer Affairs, Food and Public Distribution, Department of Food and Public Distribution (Ministry) which is responsible for implementation of the national food security system. FCI aims at fulfilling the following objectives:
providing price support operations through procurement for safeguarding the interests of the farmers
Making food grains available and accessible at reasonable price to weaker and vulnerable sections of society through Targeted Public Distribution System and other government schemes through efficient and cost effective movement, and distribution of food grains throughout the country
Maintaining satisfactory level of operational and buffer stocks of food grains to ensure national food security and to carry out price stabilization operations.
FCI Office
Figure 1: FCI Offices
FCI HQ
Zonal Offices - 5
Regional Offices - 24
District Offices - 170
FCI Depots – 2000 (Approx.)
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
11
1.3 ABOUT NATIONAL INFORMATICS CENTRE National Informatics Centre (NIC) of the Department of Electronics and Information Technology is providing network backbone and e-Governance support to Central Government, State Governments, UT Administrations, Districts and other Government bodies. It offers a wide range of ICT services including Nationwide Communication Network for decentralized planning, improvement in Government services and wider transparency of national and local Governments. NIC assists in implementing Information Technology Projects, in close collaboration with Central and State Governments, in the areas of (a) Centrally sponsored schemes and Central sector schemes, (b) State sector and State sponsored projects, and (c) District Administration sponsored projects. NIC endeavors to ensure that the latest technology in all areas of IT is available to its users. Specific to the Release Order application, National Informatics Centre (NIC) acts a nodal agency between the Food Corporation of India and the eCentric which can take care about the following activities
1. Overall project coordination, monitoring and supervision of the project. 2. Technical assistance to understand the External applications. 3. Deliverables validation and UAT. 4. To provide the infrastructure (both hardware and software licenses) help the agencies to test and deploy the
application in test and production environment. 5. To provide the technical assistance and complete the project as per the proposal and plan.
6. To help he Implementation agency in application Integration with External applications.
7. To Support the Implementation agency for application deployment and testing.
1.4 ABOUT THE PROJECT Release Order Application (RO) is an initiative by Food Corporation of India (FCI) intended to provide an integrated workflow system to perform the Release Order Operations online. The purpose of this application is to automate the existing Release Order Operations. It can exchange the information electronically with their stakeholders involved in the Release Order Operations including the State Agencies/Parties. It also expected to provide online reports to track and monitor the progress of Release Order Operations through online web portal.
1.5 PURPOSE & SCOPE OF THE DOCUMENT This document specifies the requirements for the proposed FCI Release Order Application (RO) in detail. The scope of this document includes the description of the existing system and functional interface requirements for the proposed system. It also talks about non functional requirements like security, performance, quality, training and other requirements as part of the Release Order Application. It helps the department to verify whether the functional requirements have been documented here completely, accurately and unambiguously to meet the Release Order Operations.
To help the department to check if proposed system functional needs are addressed completely and correctly.
To provide a foundation to implementation agency to design and develop the proposed System.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
12
To provide input into the design and development phase of the proposed Release Order application.
To describe what the proposed system will do.
1.6 INTENDED AUDIENCE The main intended audience for this document is the project stakeholders specially District offices of FCI (Food Corporation of India), Functional Heads, Depot officials involved in executing Release Orders, State Govt. Agencies & officials involved in Release Order operations and any other concerned officials. Implementation Agency Team (Project Manager, Data Architects, Application Architects and Technical Architects and Development Team) would also find the information in this document useful when they need to finalize the design, solution and develop the business logic to implement the Release Order Application. The requirement documented herein is technology-independent and this would help the project stakeholders to comprehend the requirements fairly easily from this document.
1.7 STAKEHOLDERS
Stakeholders are the individuals or groups who are participants of the Release Order operations and whose requirements need to be considered throughout the project. This section lists the Release Order application stakeholders for which System requirements are documented.
1. FCI Head Quarters 2. FCI Zonal Office 3. FCI Regional Office 4. FCI District Office 5. FCI Depot Office 6. State Agencies/Parties 7. NIC 8. Implementation Agency (eCentric)
1.8 REFERENCES System Requirement Document was prepared by Implementation Agency, M/s eCentric Solutions Pvt. Ltd based on a result of DPR Study, Field visits to FCI stakeholder offices and subsequent meetings/discussions with the NIC team and FCI User group. This section lists the references to previous documentation, correspondence that are helpful to come up with System Requirement Specification.
DPR document developed by NIC
Field Study at FCI stakeholder locations.
Discussions with Project stakeholder departments (FCI and NIC)
Field Survey & Feedback Reports
External Applications study with NIC and FCI officials
Review and Discussion meetings with NIC and FCI Officials
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
13
Physical Ledgers/Forms
1.9 DEFINITIONS, ACRONYMS AND ABBREVIATIONS
S.No. Abbreviation Description
1. AAY Antoyodya Anna Yojana
2. AFSO Assistant Food Supply Officer
3. AM Area Manager
4. AO Allocation Order
5. APL Above Poverty Line
6. BPL Below Poverty Line
7. CAF&PD Consumer Affairs, Food and Public Distribution
8. CWC Central Warehousing Corporation
9. DD Demand Draft
10. DFSO District Food Supply Officer
11. DM District Manager
12. DOF&PD Department of Food and Public Distribution
13. CSC State Civil Supply Corporation
14. F&S Food & Supply
15. FAP Financial Accounting Package
16. FCI Food Corporation of India
17. FPS Fair Price Shop
18. GOI Government of India
19. MDM Mid Day Meal
20. MSP Minimum Support Price
21. NIC National Informatics Centre
22. OMSS Open Market Sale Scheme
23. PDS Public Distribution System
24. RO Release Order
25. RTGS Real Time Gross Settlement
26. SGRY Sampoorna Grameen Rozgar Yojana
27. SWC State Warehousing Corporation
28. TPDS Targeted Public Distribution System
29. WCM Weigh Check Memo
2. EXECUTIVE SUMMARY Food Corporation of India (FCI) disburses commodity to State Agencies /Government Departments/nominated agencies / Wholesale Dealers / Fair Price Shops under various schemes based on guidelines provided by Ministry of Consumer Affairs, Food & Public Distribution. All these disbursals are based on the payments made by the respective Parties / Customers. On every payment by the Party, FCI District Office creates a document called ‘RELEASE ORDER’ – a document which authorizes the party / customer to receive commodity from the FCI depots designated by the FCI District Office.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
14
2.1 ABOUT RELEASE ORDER Release Order is an authorized document generated by Sales Department of FCI district office on the payment made by the respective State parties like State agencies and other private agencies. It facilitates the respective State Agencies /Parties to lift the commodity from FCI depots. The major activities involved in Release Order process are as follows.
1. Department of Consumer Affairs, Food & Public Distribution (CA,F&PD). Government of India (GOI) receives
the food grain requirements from the State food departments to implement the welfare schemes.
2. Department of Consumer Affairs, Food & Public Distribution (CA,F&PD). Government of India (GOI) defines
policies/guidelines to allocate the food grains under various schemes for State agencies/parties on need
basis.
3. Department of Consumer Affairs, Food & Public Distribution (CA,F&PD). Government of India (GOI) allocate
commodities to the State under various schemes and send the State wise allocation orders with guidelines
to Food Corporation India and respective State/Central government agencies responsible for implementing
the scheme. Further, commodities allocated FCI Revenue District wise by respective State Govt.
4. State Agency/Party make payments to Food Corporation of India for allotted quantity based on the Central
issue prices (state wise, scheme wise, crop year & commodity) / issue price(OMSS & Commercial) as
decided by Govt. of India.
5. FCI receives payments along with requisition / indent from the State Agencies / Party / Customer – through
DD / NEFT / RTGS.
6. Payment Confirmation by FCI Account Section. Excess payments / Earnest Money Deposit / Sale Deposit by
the State Agencies/parties adjusted against the cost of the current Release Order.
7. FCI sales/commercial section assigns the depot based on stocks availability and Release Order is issued to
the Respective State Agencies/Parties.
8. State Agency/Party will lift the commodities from designated FCI Depots against Release Order.
9. Lifted food grains are weighed at the weighbridges.
10. Reconciliation of Release Orders against the Issues.
11. Closure of Release Order – after entire quantity is lifted by the party.
12. Diversion of Release Order – identification of alternate FCI depots in case of the initially identified depot
runs out of stock, at the request of State Govt. or any other operational/ natural exigencies.
13. Extension of Release Order – extension of the validity period.
14. Release Order Reimbursement - Calculate the Reimbursement amount against un-lifted quantity and
adjustment of payments.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
15
2.2 EXISTING SYSTEM The existing Release Order operations are completely manual at all the project stakeholder locations. The communications between stakeholders are through papers/documents/ledgers. Therefore, data/information exchange for Release Order business transaction and data sync with external applications take place manually. It results in re-entry of data into their internal/dependent systems and the increase in the dwell time for the Release Order operations. The existing applications FEAST, DCMS, IRRS, SIMS, FAP and other external applications used to handle the other functional areas and using in good extent in many of the FCI District offices and Depots, the stakeholders are unable to get the expected benefits due to the lack of holistic approach towards the automation and the disconnects resulted from the lack of common platform for data exchange. The existing IT infrastructure and environmental conditions at the depots are not meeting the requirements to use the existing applications. These problems are summarized below based on the Release Order functional process.
2.2.1 RELEASE ORDER OPERATIONS - MANUAL
1. Existing Release Order is not being generated in predefined standard format. Most of the FCI District Offices use
their customized format to generate the Release Order.
2. Format of release order differs for various schemes like PDS, MDM, Defense and OMSS (D) etc.
3. The project stakeholders are not adapting FCI prescribed formats/guidelines as part of Release Order operations
in all the locations.
4. Allocation demand submitted by district Food and Supply Corporation is not following a standard format. Each
agency follows their own format for generating allocation demand or indent. Indents may also cater allocation
against State driven PDS schemes. Although FCI can create Release Order only against schemes defined by GOI
like AAY, BPL, APL, MDM and Other Welfare and Non Welfare Schemes.
5. Existing release order process does not have any mechanism to identify discrepancy quantity mentioned in
allocation order and indent received from State agency. There is possibility of human error while generating
Release Order.
6. Delay in Release Order generation due to non-availability of online information to verify and validate the indent
details submitted by the State Agency/Party.
7. State agency/Party prepares Indent against an allocation order and sends it to FCI District office for issuing
Release Order but these agencies are not able to track the progress of their request.
8. The communication between State agency and Depot office to decide the schedule for lifting of commodity is
mostly informal, over telephone.
9. Release Order does not have any unique hologram to avoid any fudging.
10. Reconciliation of off-take v/s allocation on day to day basis is not possible due to non-availability of daily
transactions information online.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
16
11. Stakeholders still need to submit paper documents in many places (Depot/State Agency/Party) since either
existing applications are not accessible to the users due to non-availability of the infrastructure/manpower to
use the applications.
12. State agency/Party finds difficulty in getting day wise commodity lifting report from FCI depots.
13. State agency/Party sending hard copy of extension request to District office is unable to check the progress of
their request until final approval/ rejection happens.
14. The stakeholders are unable to track the Current Release Order Status during entire Release Order Workflow.
15. Existing manual operations are time consuming and error prone.
16. Release Order Parameters are entering repeatedly in different stages due to non-availability of digitized Release
Order details.
17. Due to lack of infrastructure and technical manpower at Depot, the FCI Depot officials are not using the online
applications.
18. Minimum IT infrastructure is available at most of the FCI owned depots, but depots managed/hired by FCI does
not have IT infrastructure to use the applications.
19. Reconciliation of off take data is difficult because data is spread across various physical registers.
20. There is no validation or verification mechanism to check whether lifted food grains from FCI Depot reached to
desired destination point or not.
2.2.2 EXTERNAL APPLICATIONS – RUNS INDEPENDENTLY
1. The existing DCMS, IRRS, FAP, FEAST, SIMS and Weighbridge applications are running independently and data
synchronization is not happening online.
2. Existing external applications are running independently and application users are repeatedly entering the same
parameters manually in the applications separately based on data available in physical papers.
3. IRRS application maintains depot wise closing balances of commodity on daily basis however does not provide
the commodity inflow and outflow data captured by weighbridge that are available with unit in charge in issue
register (or WCM/M-Form) against the Release Order.
4. There is no verification and validation check for the entered data since the applications are running
independently.
5. Most of the applications do not have a provision to capture the Release Order number (i.e. IRRS, and
Weighbridge).
6. Most of the external applications are not maintaining the up to date information due to lack of Infrastructure
and manpower at stakeholder premises.
7. Some of the Applications like FEAST and SIMS are developed only for the TPDS Schemes.
2.2.3 WEIGHBRIDGES – STAND ALONE - VENDER SPECIFIC – DIFFERENT MAKES & MODELS 1. FCI Depots uses different weighbridges makes and models developed by different vendors. The vendor supplies,
installs and maintain the software and hardware concerned with the weighbridge.
2. The weighbridges are pre-installed with device specific applications to generate weights.
3. Infrastructure of weighbridge (like power backup) is meant to support their weighbridge equipments only.
Further load of any electronic devices or power is not feasible on existing infrastructure.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
17
4. The computers used along with weighbridge are basic standard computers with minimal configuration which
may not support GUI intensive applications.
5. These computers are not exposed to internet to prevent virus and malicious software attacks.
6. Existing weighbridges uses the standalone applications and may not have the communication interfaces like
serial, USB ports etc. to capture parameters through external applications.
7. Weighbridges are either located inside or outside the Depots premises. Depots which do not have the
weighbridges within the premises, weighment is being done by private weighbridges.
8. Weighment details generated by weighbridges contain either two or five decimal places, i.e., either Kilo Grams
or Grams. Although FCI maintains issue/receipt quantity in grams but base unit of weighbridge is Kg and
tolerance level is (+/-)5 Kg.
9. Most of the FCI owned depots have electronic weighbridges installed. The status of the remaining depots is unknown.
10. All the Release Order execution steps are manual except the weighment details generated by weighbridge. 11. Except weighment parameters, all the other details like unit/shed number, bag type, numbers of bags,
commodity name are provided by unit in-charge.
12. Same parameters are repeatedly entered at different locations/places like Gate, weighbridge and at Unit/Shed.
13. Weighbridge software does not have a provision to capture the Release Order number.
14. Unit In-charge issues loose grains using beam scale.
15. Unit-in-charge uses 10% weighment method to weigh the food grains received in rail movement.
2.3 PROPOSED SYSTEM To overcome challenges in existing Release order operations Food Corporation of India, initiated the development of web based Release Order workflow automation system to perform the Release Order Operations. Release Order Application will provide a single window for the Food Corporation of India to perform the Release Order Operations online. It exchanges the information electronically across its stakeholders involved in the Release Order Operations supply Chain including the State Agencies/ Departments and Parties. It provides the external application interfaces to share the data in secure and efficient manner to perform the Release Order Operations as well as provides global visibility and access to the central Release Order database to all its stakeholders through web portal.
To develop a web enabled, work flow based application for Release Order with ability of linkages with DCMS, FEAST, DCMS, FAP and Weighbridge applications will enable a complete view of the inflow and outflow of the commodities and the stock position in the depot.
The application is built from scratch, and thus there is no initial foundation to build Release Order system upon. The proposed application will consist of development of backend solution and frontend applications. The backend will handle the storage of data pertaining to release order application and the frontend solution will allow the user to perform the Release Order operations remotely online. Following is the suggested approach to implement the Release Order application: 1. Online submission of Allocation Demand/Indent to be facilitated.
2. To develop commonly defined computerized work-flow for Release Order generation and execution process.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
18
3. Employing appropriate authentication mechanisms of the release order such digital signature, in addition to the
software based login security mechanisms.
4. Uniform format of Release order document irrespective of scheme.
5. Uniform format of peripheral documents such as Weight Check Memo, Issue Register Gate pass etc.,
6. Appropriate IT infrastructure may be provided for executing the proposed solution at all project stakeholder
premises including depots.
7. Integration of external application like IRRS, FAP and Weighbridge Software with Release Order is mandatory to
complete the entire workflow of the Release Order Solution.
8. The proposed system should allow the FCI district officers to enter NCDEX generated Release Order fields in
offline mode using the input forms.
9. Integration of Weighbridge data with the Release Order application works in either online or offline mode.
10. Proposed System can be used in web enabled devices like laptops/tablets/smart phones with large screen size to
perform the Release Order operations.
2.3.1 OBJECTIVES The objectives of the proposed Release Order application are as follows. 1. To eliminate the manual process and automate the current Release Order operations. 2. To strengthen the Release Order processes and procedures. 3. To maintain uniformity and consistency in Release Order process at all locations in the country. 4. To link the external applications with DCMS, IRRS, FAP, FEAST, SIMS and weighbridge data to maintain the
consistency and uniformity. 5. To track the Release Order operations online. 6. To speed up the Release Order operations. 7. To eliminate the leakages in current Release Order processes. 8. To reconcile the stock positions online at depot level by integrating with Weighbridge applications. 9. To maintain data consistency and uniformity by integrating the dependency applications with Release Order. 10. To assure the State Agency/Party that lifted the correct quantities against the Release Order. 11. To eliminate most of the paper work.
2.3.2 OUTCOMES
Uniform workflow solution for release order operations irrespective of the scheme and State Agencies/Parties
Tracking and monitoring Release Order operations progress online through portal.
Exact depot wise off-take stock positions made available online.
Reduced the Release Order operations time and cost due to automation of the processes.
Reduced administrative burden and service fulfillment time & costs
Increases the transparency, accountability and efficiency as part of System Implementation.
Reduced manual interaction of project stakeholders with and encourage ‘e’-interaction and more efficient
communication.
To link it to the PDS Supply chain.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
19
2.3.3 ASSUMPTIONS This section describes major assumptions that were made prior to or during the System 1. Release Order process steps are uniform across all FCI locations and adhere to FCI recommended guidelines. If
not, it is mandatory to follow FCI guidelines as part of Release Order operations. 2. External applications data like stock positions, designated depots etc., is accurate and up to date. 3. Existing external applications would be customized by the respective solution providers. 4. RO Application will define the protocol so that all the weighbridge system shall provide the necessary data and
linkages, based on standards as finalized by FCI (preferably by XML/CSV).
5. All the applications should maintain the uniform master tables and data exchange as per the codes instead of
the names.
6. FAP would follow existing payment validation and verification procedures.
7. All the financial transactions would be routed through FAP. Release Order application shall maintain only the
final status provided by FAP.
8. External applications are up and running 24/7 to maintain the live data sync.
9. All the project stakeholders have the appropriate infrastructure (hardware/software) to run the Release Order
application.
10. Infrastructure (system hardware and other connectivity devices) and software licenses to run the application can
be provided by the NIC.
11. Technical manpower is available to use the application at project stakeholder locations.
12. FCI would finalize and approve the required screens and reports for the proposed Release Order Application.
13. FCI would identify the pilot locations and provide the required infrastructure for POC Implementation.
14. NIC would provide the staging environment for POC study and testing.
15. FCI would provide the training officers details for capacity building.
16. Basic data and required masters to run the Release Order application would be provided by the Project
Stakeholders.
17. NIC would provide the support to linkage to existing e-Mail and SMS gateway systems with Release Order
application.
2.3.4 DEPENDENCIES 1. All the project stakeholders shall have the necessary infrastructure proposed by the Release Order application.
2. All the relevant data – master data , basic users data, static data, transactional data, etc., whatever needed by
the application, shall be provided by the concerned stake holders in a uniform standard format, within the
stipulated time, so that the work-flow processes functions uninterrupted.
3. FCI shall provide the necessary process details and the work-flows.
4. eCentric in consultation with NIC and FCI shall provide the format of the tabular parameters for the
graphical reports.
5. eCentric, need to take NIC & FCI’s approval over the portal screen design and input forms.
6. eCentric, in consultation with NIC and FCI shall freeze the requirements, in terms of input and output, and
formalize the same. Any change of requirement at a later stage of the development shall need a re-look on the
work-flow designed initially.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
20
7. For integration Release Order application with external applications such as DCMS, IRRS, FAP, FEAST & SIMS etc.
shall provide the necessary data and linkages provision to capturing the Release Order Number.
8. For weigh bridge linkage, all the weighbridge vendors shall provide the necessary data and linkages, based on
standards proposed by Release Order application.
9. NIC shall provide the required infrastructure and connectivity to deploy the application at NIC Data Centre.
10. FCI shall conduct the User Acceptance Testing (UAT) before submitting the same for security audit.
11. The application for the purpose of third party audit can be hosted at NIC’s server and undergo security audit by
FCI.
12. The issues arising out of the security audit shall be fixed by the eCentric.
13. Hosting of the web enabled work flow based Release Order Application, in its entirety, shall be subject to the
security audit clearance by NIC.
14. The security audited application shall be co-located at one of the NIC’s server.
3. REQUIREMENTS STUDY
3.1 VISITED LOCATIONS To understand the Release Order Operations and Requirements, NIC has already visited the various depots and district offices of FCI in the Year 2012 and prepared the Detailed Project Report. For this purpose NIC team has visited seven States in India and interacted with Project stakeholders for getting the understanding of the FCI Release Order Operations. Team has visited offices of State agencies and other stakeholders to understand the end to end flow of Release Order Operational Process. The study had focused especially on Release Order Operations pertaining to TPDS schemes. National Informatics Center (NIC) of India had visited following locations and done the field study and prepared the Detailed Project Report on Release Order Operations.
State District Office/Depots Officers Met
Delhi Commercial Section, FCI Regional Office Asst. General Manager
FCI District Sales Office, Mayapuri
Area Manager
Manager Sales
Manager Accounts
FCI Depot, Mayapuri Depot Manager
Depot in-Charge
Quality Manager
Weighbridge In-Charge
Haryana Commercial Section, FCI Regional Office Asst. General Manager
FCI District Office, Kurukshetra Area Manager
Manager Sales
Manager Accounts
FCI Pipli Depot, Kurukshetra Depot Manager
Depot in-Charge
Quality Manager
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
21
State District Office/Depots Officers Met
Weighbridge In-Charge
Punjab FCI Regional Office Commercial Section Assistant General Manager
FCI District Office, Ludhiana Area Manager
Manager – Commercial
Manager – Finance
FCI Depot, Machhiwara, Ludhiana Depot In charge
Quality Manager
District Office PUNGRAIN, Ludhiana District Manager
Assistant Food supply Officer
Account Officer
Food Inspector
District Office PUNSUP, Ludhiana Assistant Food supply Officer
Account Officer Food Inspector
Bihar FCI Regional Office, Patna Asst. General Manager
FCI District Office, Patna Area Manager
Manager Sales
Manager Accounts
FCI Godown Phulwari Sharif, Patna Depot Manager
Depot in-Charge
Quality Manager
Weighbridge In-Charge
Assam FCI District Office, Guwahati Area Manager
Manager Sales
Manager Accounts
FCI Depot Guwahati Depot Manager
Depot in-Charge
Quality Manager
Weighbridge In-Charge
Guwahati Wholesale Consumer Co-op Society Ltd., Guwahati
Assistant Supply Officer
Kerala FCI District Office, Valiathura Area Manager
Manager Sales
Manager Accounts
FCI Depot Office, Valiathura Depot Manager
Depot in-Charge
Quality Manager
Weighbridge In-Charge
Kerala State Civil Supplies Corporation, Chalai Depot
Depot In-Charge
Chhattisgarh FCI District Office, Raipur Area Manager
Manager Sales
Manager Accounts
FCI Depot Office, Raipur Depot Manager
Depot in-Charge
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
22
State District Office/Depots Officers Met
Quality Manager
Weighbridge In-Charge
Chhattisgarh State Civil Supplies District Supply Officer
The requirements study conducted by eCentric, which covers all the schemes (TPDS/Welfare/Commercial - OMSS) as part of Release Order Operations, was a supplementary study to firm up and fine tune the requirements and prepare a detailed specification for designing and developing the Release Order Application. In this purpose, In MARCH 2014, eCentric team has visited Delhi – Mayapuri , Kazipet, Sanatnagar, Taranaka and Charlapally locations to understand the FCI Release Order Operations, and usage of External applications like DCMS, IRRS, FAP, FEAST, and Weighbridge. At Kazipet location eCentric studied the WINGs application functionality.
State District Office/Depots Officers Met
Delhi Commercial Section, FCI Regional Office Asst. General Manager
FCI District Sales Office, Mayapuri
Area Manager
Manager Sales
Manager Accounts
FCI Depot, Mayapuri Depot Manager
Depot in-Charge
Quality Manager
Weighbridge In-Charge
Andhra Pradesh FCI District Office, Kazipet Area Manager
Manager Sales
Manager Accounts
FCI Depot, Kazipet Depot Manager
Depot in-Charge
WINGs Developer
Weighbridge In-Charge
FCI District Office, SanathNagar Area Manager
Manager Sales
Manager Accounts
FCI Depot, Sanath Nagar Depot Manager
Depot in-Charge
WINGs Developer
Weighbridge In-Charge
FCI District Office, Taranaka Area Manager
Manager Sales
Manager Accounts
FCI Depot, Charlapally Depot Manager
Depot in-Charge
Weighbridge In-Charge
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
23
3.2 OBJECTIVE OF STUDY The main objectives of the requirement study were
Understand the business processes of the stakeholders and to see any changes to the process or information
flow given in the Detailed Project Report by NIC.
To identify the document/information exchange requirements between the project stakeholders.
Find out the current IT infrastructure Release Order Application capabilities at FCI Depots/District offices and
other Stakeholders Locations.
To study the external applications usage at Project Stakeholders to come up with the best possible Integration
solution.
To study the inflow and outflow operations at weighbridge at unit/shed.
Identify the problems and shortcomings of the current system.
To take valuable feedback and suggestions from the project stakeholders as part of Release Order Operations
Automation.
The main activities involved as part of the field study are
Face-to-face meeting with the stakeholders to understand the business process pertaining to Release Order
Operations and validate the information flow against the flow in the DPR to see any major deviations.
Classify/categorize the document and the information exchanged between other stakeholders part of the
business cycle.
Collect the physical copies involved business transactions regards to Release Order.
Find out the current IT infrastructure Release Order Application capabilities and working environment at Project
Stakeholder locations.
Details of the field survey reports and physical documents collected from the field are included in the ANNEXURE-C section of this document.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
24
3.3 UNDERSTANDING THE EXISTING SYSTEM This section explains eCentric’s understanding about the existing system based on the Field Study.
3.3.1 PROJECT STAKEHOLDERS WITH ROLES & RESPONSIBILITIES
Department of
CS, F&PD
(GOI)
FCI (GOI)
Zonal office 1 Zonal Office 2 Zonal Office .. 5
Dept of CS, F&PD
(State - 2)
District Office 1 District Office 2 District Office .. N
Dept of CS, F&PD(State - 1)
Dept of CS, F&PD
(State ….. N)
Owned Depots 1---N Hired Depots 1...NCWCs 1 … N, SWCs 1 ----N
Regional Office 1 Regional Office 2 Regional Office ..N
District Office 1 District Office 2 District Office .. N
Stock Storage Points 1
Stock Storage Points 2
Stock Storage Points .. N
FPS 1 FPS 2 FPS ...N
Respective Central/State Govt.
Departments/ Agencies
FCI TPDS Schemes Other Welfare Schemes
Private Parties
OMMS & Others
Figure 2: Roles & Responsibilities
Release Order Operation
Department Users Roles and Responsibility
Release Order Initiation
Ministry of Consumer Affairs, Food and Public Distribution – GOI
Department Allocate of food grains for various Government schemes
Additional allocations on need basis
Allocations under OMSS and other schemes on need basis
FCI Department Issuing food grains under various schemes of the Govt. of India to the State Agencies/Parties
FCI Regional Office GM/AGM – Commercial Section
Receives State wise monthly allocations for the financial year from the Ministry
Send the district wise monthly allocation of food grains to FCI District offices.
FCI District Office Area Manager, To validate the payment made by
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
25
Release Order Operation
Department Users Roles and Responsibility
Manager, Commercial/Sales Section, Manager Accounts Section
State agency/Party against the requested food grains
To enter the Payment Details in the FAP
To issue the authorization letter to the Sales Section
To assign the active depot within the FCI District based on stocks availability
State Agency Department Heads To send the scheme wise monthly allocation requests to Regional office as per GOI allocation.
To release the payments to FCI District office for the allotted food grains
State Agency District Office/ Party
District Manager
To release the payment to FCI District office for the food allotted food grains
To assign authorized person to collect the Release Order and lift the commodities
Release Order Generation
FCI District Office Manager, Commercial/Sales Section
To generate the Release Order based on the request from the State Agency district officer/other parties
To send the Release Order to the assigned depot
State Agency District Office/ Party
Authorized person appointed by District Manager
To handover Indent Letter with payment details against the requested food grains in FCI District office
To Collect the Release order from the FCI District Office
Release Order Execution
FCI Regional Office Monitoring and Controlling of the overall Release Order operations of FCI district offices in the Region
FCI Depot Depot Manager, Depot In charge, Weigh bridge In charge
To assign the shed/block in the Depot and issue the delivery plan to State district office
To provide the Entry/Gate Pass to transport agency to lift the commodities against the Release Order
To issue the commodities against the Release Order to State Agency District Office/ Party
To weight the commodities at Weigh
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
26
Release Order Operation
Department Users Roles and Responsibility
bridge and 10% method
To entry the daily lifted quantities in Release Order as per Stock Issue/Dispatch Register
To update depot wise end of the day off take stock details in IRRS
State Agency District Office/Party
Authorized Representative/Transport Agency
Lifts the food grains against the Release Order based on the delivery plan issued by depot In-Charge through Transport Agency
Release Order Closing
FCI Depot Depot Manager, Depot In-Charge
Closes the Release Order once the State agency/party lifted all the commodities against the Release Order
To submit the Closed Release Order to FCI District Office
FCI District Office Manager, Commercial Section and Manager Accounts Section
To update the Release Order as closed in FAP and other applications
Release Order Extension
State Agency District Office/ Party
District Manager, State
Send Extension request with period along with reason against the Release Order to FCI District office
Receives the Approval or Rejection Letter from the FCI District Office
Payment of storage charges for the extension period (if applicable) by the State agency/party
To Lift the commodities within the extension period
FCI District Office Area Manager To send the extension request to FCI regional office
FCI Regional Office GM/AGM – Commercial Section
Approves/Rejects for the extension requests for first 15 days period
FCI Zonal Office GM/AGM – Commercial Section
Approves/Rejects for the extension requests beyond 15 days period
Release Order Cancellation
State Agency District Office/ Party
State Agency District Manager/ Party
Cancel Request send it to FCI District Office for un lifted quantity with reason
FCI District Office FCI Depot Office
Area Manager, Manager, Commercial Section and Manager Accounts Section Depot In-Charge
District office can cancel the Release Order by FCI District Office in two scenarios
a. The State agency/party is not lifted the quantity on time and extension request is rejected
b. Un availability of the Stocks in the
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
27
Release Order Operation
Department Users Roles and Responsibility
FCI designated Depots with in FCI district
Release Order Diversion
State Agency District Office/ Party
State Agency District Manager/ Party
Diversion Request from the State Agency due to stocks un availability
Lift the stocks from the newly allotted Depot as per the Release Order
FCI District Office Manager, Commercial Section
FCI District office can divert Release Order to another Depot
1. Within the FCI District Office 2. Out of FCI District Office
a. Amount can transferred internally to newly assigned District office by FCI District office
b. Cancel the Release Order
Release Order Reimbursement
State Agency District Office/ Party
State Agency District Manager/ Party
Reimbursement Request from the State Agency for un lifted quantity
FCI Depot/ District Office
Manager, Commercial Section and Manager Accounts Section
Cancel the Release Order
Reimburse the amount back to the State Agency/Party
3.3.2 SCHEMES Food Corporation India (FCI) releases food grains under various schemes to the State agencies/parties as per the guidelines given by the Department of CAF&PD. Following table explains the scheme wise allocation details with respective State agencies/parties responsible to lift the commodities. CA, F&PD department issues the allocation orders to food grains to following schemes
1. Welfare schemes 2. Commercial schemes
Following table explains the allocation and release of food grains with respect to State agencies/parties responsible to lift the commodities and is as follows. Scheme Name Frequency Purpose Orders issued to
Welfare Fixed Time intervals – Monthly/Quarterly/Half Yearly/Annual
To implement the subsidy Schemes by State Departments
Orders Issued to FCI head quarters and to State level scheme implementation departments
Welfare – Additional Need basis To serve the additional needs of the welfare schemes
Orders sent to the FCI head quarters and to State level scheme implementation
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
28
departments
Commercial Schemes - (OMSS (D) and others)
Need basis To release it to the third parties and private agencies to clear the excess stocks or to avoid the market fluctuations
Orders Issued to FCI head quarters to initiate the tendering process
Scheme Group Scheme Name Description
TPDS Schemes
AAY AAY A (Issues Against Pending Allotment of Previous Month)
APL Above Poverty Line (A-Issues Against Pending Allotment of Previous Month)
BPL Below Poverty Line Additional (A-Issues Against Pending Allotment of Previous Month)
Special Ad-hoc Allocation Special Ad-hoc Allocation
APL Additional(02-AUG-2010)
APL Additional (Allocation Date from 02-AUG-2010; changed from APL Additional vide FCI DO letter dated 11-JUL-2011)
BPL Additional (07-SEP-2010) BPL Additional
BPL Additional(06-JAN-2011) BPL Additional (Allocation Date from 06-JAN-2011 valid upto 30-JUN-2011)
BPL Additional(16-MAY-2011) BPL Additional (Allocation Date from 16-MAY-2011 valid upto 31-MAR-2012)
APL Additional(30-JUN-2011) APL Additional ((Allocation dated 30.06.2011 valid upto 31.03.2012) )
Allocation for 150 Districts(01-AUG-2011)
FCI letter no.1/7/2011-12/Sales dated 27 jul 2011;Additional monthly adhoc alloc under TPDS for 150 Poorest Districts in states of HP,UK,RJ,BR,JH,HR,JK,MR for the month of Aug to Oct 2011
Allocation for 174 Districts @ AAY rate (10-Oct-2011)
Allocation for 174 Poorest Districts for 1 year under AAY rate
Allocation for 174 Districts @ BPL rate (10-Oct-2011)
Allocation for 174 Poorest Districts for 1 year under BPL rate
APL Additional (12.03.2012) APL Additional (12.03.2012)
Additional Allocation for Poorest Districts @ BPL rate BPL Additional – Allocation date 07.05.2012
BPL Additional Allocation date 02.07.2012
BPL Additional Allocation date 02.07.2012 valid upto 31.03.2013
Additional Allocation for Poorest Districts @ AAY rate
Additional Allocation for Poorest Districts @ AAY rate’
APL Adhoc Additional (Allocation dated 22.05.2013)
APL Adhoc Additional (Allocation dated 22.05.2013)
NFSA National Food Security Act
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
29
BPL Additional (19.09.2013) BPL Additional (19.09.2013)
Other than NFSA Other than National Food Security Act, 2013 (NFSA)
BPL Addnl. Allocation Date 31.03.2014 BPL Addnl. Allocation Date 31.03.2014
APL Addnl. Allocation Date 31.03.2014 APL Addnl. Allocation Date 31.03.2014
BPL Addnl. Allocation Date 07.07.2014 BPL Addnl. Allocation Date 07.07.2014
APL Addnl. Allocation Date 07.07.2014 APL Addnl. Allocation Date 07.07.2014
APL Adnl. Allocation Date 09.04.2015 APL Adnl. Allocation Date 09.04.2015
BPL Adnl. Allocation Date 10.04.2015 BPL Adnl. Allocation Date 10.04.2015
OMSS (Domestic) Sale to State/UT Govt(Retail Sale)-From FCI OMSS(D)- (Agency Stock)
Sale to State/UT Govt(Retail Sale)-From State Agencies OMSS(D)- (Agency Stock)
Bulk Sale through Open Tender From FCI Depot NULL
Bulk Sale through Open Tender from State Agencies NULL
Small (Pvt) Traders upto 9 MT/Person/Depot/Day-From FCI Depot NULL
Small (Pvt) Traders upto 9 MT/Person/Depot/Day-From State Agencies NULL
Other Welfare Schemes (OWS) Annapurna
Annapurna A - (Issues against pending allotment of previous month)
Bhutan Bhutan
BSF / CRPF CRPF
ITBP ITBP
Defence Defence
EFP EFP
NPAG/SABLA NPAG A - (Issues against current financial years' allocation)
Relief Relief 1 - Flood
SC/ST/OBC HOSTEL SC/ST/OBC(HOSTELS) A - (Issues against current financial years' allocation)
Wheat Based Nutrition Programme WBNP A - (Issues against current financial years' allocation)
World Food Programme WFP 1 - (Domestic)
Welfare Inst. & Hostels Welfare Institute and Hostels A - (Issues against pending allotment of previous month)
UDS - Total UDS - Total
Indigent People Indigent People
Others Other Schemes
Mid Day Meal - Primary Standard MID DAY MEAL S(Primary Standard) A - (Issues against allotment of current month)
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
30
MSP 10 KG. MSP 10 KG.
Mid Day Meal - Upper Primary Standard
MID DAY MEAL S(Primary Upper) A - (Issues against allotment of current month)
NFFWP National Food for Work Programme A - (Issues against current financial years' allocation)
SGRY SGRY A - (Issues against current financial years' allocation)
Village Grain Bank Scheme Village Grain Bank Scheme A - (Issues against current annual plan)
Welfare Institutions Scheme - Addl. Allocation for CSR
Welfare Institutions Scheme - Addl. Allocation for CSR
Miscellaneous Sample for a Scheme Issue Samples for Schemes
Sale of Non-Issuable Stocks Tender Sale of Non-Issuable Stocks
Additional Allocation
Special Alloc.@ 8.45/11.45 per Kg.(06-JAN-2011) Special Allocation @ 8.45/11.45 per Kg.
Additional - @ Economic Cost Additional 1 - @ Economic Cost
Additional @ MSP Derived Rate Additional @ MSP
Additional @ Open Sale Rate Additional @ APL Rate Additional @ BPL Rate Additional @ Free of Cost Export Export Tender Sale (Sound)
excl. OMSS (D) Tender Sale(Sound) Excluding OMSS (Domestic)
Tender Sale - D category with TE opened for current date
Food Corporation India (FCI) maintains the food grain stocks at the depots and releases it to the State agencies/parties based on allocation guidelines given by the Department of CAF&PD. Following table explains the allocation and release of food grains with respect to State agencies/parties responsible to lift the commodities and is as follows. Active Schemes
Scheme Name Responsible Commodities Regular /Need basis
Lifting Duration
Payment made /Lifted Agency
TPDS (Targeted Public Distribution System) APL,BPL and AAY, NFSA & Other than NFSA Schemes
State Department of Consumer Affairs &Public Distribution
Rice & Wheat Regular Monthly 30 days or as per GOI order
District Office - CSC - Pre Payment
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
31
Scheme Name Responsible Commodities Regular /Need basis
Lifting Duration
Payment made /Lifted Agency
TPDS (Additional Allocations for APL,BPL and AAY, NFSA & Other than NFSA Schemes
State Department of Consumer Affairs &Public Distribution
Rice & Wheat Need basis
As per the GOI order
District Office - CSC - Pre Payment
MID-DAY-MEAL (National Program of Nutrition Support to Primary Education)
State Department of Consumer Affairs & Public Distribution
Rice & Wheat Regular Quarterly – 115 days
Department of School Education & Literacy- MoHRD – Credit Basis
Welfare Institutions and Hostels
State Department of Consumer Affairs & Public Distribution
Rice & Wheat Regular Monthly
Wheat/Rice Based Nutrition Program
Dept. of Child and Woman Development
Rice & Wheat Regular Quarterly – 115 days
Dept. of Child and Woman Development – Pre Payment
SC/ST/OBC Hostels & Welfare Institutions
State Department of Consumer Affairs & Public Distribution and
Rice & Wheat Regular Monthly - 50 Days or as per GOI order
Ministry of Social Justice & Empowerment – Pre Payment
Rajiv Gandhi Programme for Empowerment of Adolescent Girls- “AGPLM/NPAG/SABLA”
State run Women Welfare
Rice & Wheat Regular Quarterly – As per GOI Order
Defense Services State Defense Accounts Department
Rice & Wheat Regular Quarterly - 225 Days
State Defense Accounts Department - Pre booked stocks after prior inspection and quality check. Same stocks will be issued
Para Military Forces (CRPF/BSF/ITBP)
CRPF/BSF/ITBP Stations
Rice & Wheat Regular Monthly/Quarterly - 50 Days
CRPF/BSF/ITBP Stations
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
32
Scheme Name Responsible Commodities Regular /Need basis
Lifting Duration
Payment made /Lifted Agency
OMSS (D) - Open Market Sale Scheme – Retail Parties – Retail Traders Bulk Sale – Wholesalers
Private Agencies/Parties
Rice & Wheat Need basis
As per DO, FCI or Release Order
Sale it ether open market price or prices fixed as per bidding
Annapurna State Department of Consumer Affairs &Public Distribution
Rice & Wheat Regular Monthly - 50 Days or as per GOI Order
Discontinued/ Allotment Letter Not Received Schemes:
Scheme Name Responsible Commodities Regular /Need basis
Lifting Duration
Payment made /Lifted Agency
SGRY - Sampoorn Gramin Rozgar Yojna
State Department of Rural Development
Rice & Wheat Regular Monthly - 50 Days
District Project Director – Pre Payment
Emergency Feeding Program
Ministry of Social, Justice and Empowerment
Rice & Wheat Regular Monthly - 50 Days
Ministry of Social, Justice and Empowerment - Pre Payment
Village Grain Bank Scheme
Ministry of Tribal Affairs
Rice & Wheat Regular Monthly - 50 Days
Ministry of Tribal Affairs - Pre Payment
World Food Program
Exported to other Countries on need basis
Rice & Wheat On Need basis
To clear the Surplus Stocks
N/A
NFFWP - National Food for Work Program
State Department of Rural Development
Rice & Wheat Regular Monthly - 50 Days
District Project Director – Pre Payment
3.3.3 RELEASE ORDER STEPS
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
33
The following are the Release Order business processes details with suggested approach based on the Field Study at the Stakeholder premises is given in the tabular form below:
Process Steps Process Observation Suggested Approach Release Order Operations
All operations use manual process and managed through Registers and booklets. communication between stakeholders through physical forms and manual transfer
Release Order Initiation
Manual – Monthly once. Scheme wise Commodity Requests from the State Agency/ Department Payment is made to the FCI District Office based on CIP. Indent will be generated with bank and requested commodity Details
Monthly once and there is no online verification and validation of Central allocations against the Requested quantity.
The proposed application shall capture the monthly allocation parameters online (FEAST or proposed Central App)/offline along with Central Issue Price of the food grains. This can be made available to the State Agency/Party to generate the Indent. Alternatively the monthly allocation details created by the FCI Regional office shall be used to validate the allocations fed by the State Agency/Party during online Indent Submission.
Release Order Generation
Manual – Generated at FCI District Office by Sales Section based on Indent and Payment Confirmation Certificate from FCI Accounts Section.
Monthly once and can be generated on any day after the payment received and verified by FCI district Account section.
The proposed application shall verify the
confirmation of Payment
from FAP
stocks availability with IRRS
applications
and generate the Release
Order with the digital
signature
Release Order Execution
Manual – Entering the off take details daily at Depot by Depot In-Charge based on weighbridge Release Order Application Capturing weight and lifted quantity.
The current IRRS application captures daily end of the day depot wise inflow and outflow details. Off-take is captured against the individual Release Orders.
To capture the inflow and outflow stocks against individual the Release Order by integrating with weighbridge system for capturing the weighment data.
Release Order Closing Manual – Depot In charge closes the Release Order by crossing on the physical copy written between the two crossed lines as “Completed/Killed”.
Depot In-Charge closes the Release Order once the State agency lifted the entire quantity and send to District Office for Reconciliation.
The status can be updated in Release Order Application and same can be automatically reflected in all other dependent applications using external data sync interfaces.
Release Order Manual - Release Order is Manual Process. FCI Application should provide a
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
34
Process Steps Process Observation Suggested Approach
Diversion diverted to another Depot if un availability of stocks at assigned depot.
District officer write the newly assigned Depot Name in the existing Release Order
provision to assign the alternative depot within the FCI District and Release Order shall be updated accordingly.
Release Order Reimbursement
Manual - Reimbursement Amount for the un-lifted quantity will be calculated manually and Reimburse back to the State Agency/Party.
Manually calculating the amount and record the reimbursement amount in the FAP and Release Order is closed by the FCI District Officer.
System should automatically calculate un-lifted quantity and status shall be maintained. The Release Order shall be closed once RO receives the reimbursement payment confirmation from FAP.
Release Order Extension
Manual – To lift the quantity beyond the valid up to date.
Manual – 15 days – Approving authority is FCI Regional Office > 15 days – Approving authority is FCI Zonal Office > 30 - Ministry of F&PD
System shall facilitate the Regional/Zonal Office to approve/Reject the Release Order Extension Request through RO application.
3.3.4 RELEASE ORDER PARAMETERS
Release Order Parameters
Process Observation Suggested Approach
Generation Manual – Release Order will be generated Scheme & Commodity and allots designated depot based on the stocks availability and requested location by State Agency
Any date after Indent received.
Release Order should be generated within the time frame fixed by FCI.
Frequency Monthly - Release Order will be generated monthly once as per the Request
Monthly As per indent by State Govt.
Valid up to Date 7/14 Days – Time period to lift the commodities by State agency once the Release order is generated
7/14 Days in normal Scenario. In case of Extension - with in Extension period (Scheme Dependent)
The validity period should be calculated automatically by system as per the scheme.
Number of Copies 4 Copies 1. Original –to Depot 2. Duplicate – send it to State Agency/Party 3. Triplicate - to Depot – Back to District office 4. quadruplicate – Copy retained in the Booklet
4 Copies – Colors are not uniform at all the places
4 Copies with Digital Signature
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
35
Format Follows FCI Standard format with below details Release Order No. : Serial Number of the booklet Quantity Bank Payment Details Depot Details Daily Off-take Details
Booklet Running Sequence Number as a Releaser Order number
Unique Release Order format throughout the country.
Payment Mode RTGS Payment can made to FCI District Office account by State Agency on Monthly basis as per the Indent
RTGS/DD RTGS/DD
Crop Year FIFO Stocks will be allocated based on the FIFO based on the Age
Generally lift the stocks in FIFO. Sometimes it may relaxed due to surplus stored non open area/ alleyways due to lack of space in the block/unit
To lift the quantities based on the FIFO and Crop Year
Transport Agency Users Hired/Owned Transport Agency to lift the Commodities
Lift the commodities as per the Release Order based on Delivery Plan/Issue planning sheet
N/A
Weigh bridge Weighbridges of various makes and manual entry details provided by unit-in-charge and auto generated weighment data
Uses different makes and modals
Capturing of weighment data generated by Weighbridge software
Communication Phone/Mail/Physical Copy/Person
Phone/Person/Physical Copy
e-Mail/SMS
Stock Reconciliation at Depot
Manual – Daily Once Based on M-form Capturing of weighment data generated by Weighbridge software
Execution Based on physical copy Release Order Application Capturing the daily off-take as per Register/form
Execution process Status should be made available online
Closing Manual - After lifting the entire commodities for the respective Release Order
Only day wise lifted quantity is recorded
Should be updated in the Release Order as well as all other external applications automatically
Weigh bridge To capture the weighment data
Separate field to capture the Release Order Number is not available. Using some
Should provide the weighment details based on the Release Order number in the format specified by
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
36
other field for entering the Release Order number
Release Order application
3.3.5 EXTERNAL APPLICATIONS
External Applications Process Observation Suggested Approach
Weighbridge – Depot Release Order Application Capturing weighbridge data along with Release Order by entering in the other un used field
No online integration Weighbridge vendors should provide the Integration component to access the weighment data from weighbridge system
FAP – Used at District Office
On Need basis – Used by FCI District office Accounts Section to enter the Bank and payment details against the Release Order
Used by District office on need basis to Release Order Application Capturing the bank and payment details irrespective of the Release Order Verify the payment details through Online Bank Account
Release order application can provide the Indent data to FAP so that FAP shall take care necessary verification and validation and provide confirmation to Release Order application
IRRS On Need Basis – used by FCI District office/Depot to update the end of the day off-take stock positions
Manual Entry RO shall capture the inflow and outflow stocks against individual the Release Order by integrating with weighbridge system for capturing the weighment data and can be used by IRRS
DCMS On Need Basis – Not Using as part of assigning the Depot
Using on Need basis Release Order should Capture the designated depot data to create the Release Order
WINGs To automatic Depot Operations w.r.t. stock management
Automated all the stock management operations of the depot including the weighbridge Integration
To provide Release Order details to WINGs
NCDEX Release Order FCI is utilizing the NCDEX platform to generate Release Orders for issues against the OMSS(D)
It helps to generate the Release Order based on the bidding by the parties. All other Release Order Operations will done manually
Enter the required parameters into Release Order application to perform the next operations
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
37
Following external applications are used by Project Stakeholders to perform the Release Order operations. All the external applications are working independently.
Application Name
Description Used by Used in Purpose
DCMS - (Depot Code Management System)
DCMS maintains the repository of the FCI Depots. It facilitates the project stakeholders in adding new Depots and hiring/de-hiring of the Depots.
FCI District Office –Sales Section
Release Order Generation
To identify the active/designated depots available within the FCI District jurisdiction
IRRS - IISFM
Rapid Reporting
Services
IRRS application maintains the depot wise end-of-day stock positions along with daily inflow and outflow quantities of various food grains crop year wise.
FCI District Office –Sales Section
Release Order Generation
To know online stock positions in the designated/ alternate depots
FAP – Financial Accounting Package
Financial Accounting Package
(FAP) is being used to record
and maintain FCI’s financial
transactions.
FCI District Office –Accounts Section
To create the Release Order
To maintain uniform supplier/party details To receive the payment confirmation for deposited amount for Release Order Creation
FEAST - Food and Essential Commodities Assurance & Security Target
FEAST is used to monitor the supply chain of the PDS for the commodities lifted from FCI Depots
FCI District Office –Accounts Section FCI Depot In-Charge State Agency/Party Official
Release Order Initiation & Release Order Execution
To capture the allocation demand requests for TPDS schemes Stock Reconciliation at FCI Depot and State Agency Depot
SIMS – Stakeholder Identity Management System
SIMS holds the masters of State Agency stake holder’s details, who are involved in the PDS operations.
FCI District Office –Accounts Section FCI Depot In-Charge State Agency/Party Official
Release Order Generation
To get the State Agency details for TPDS schemes
Weighbridge Weigh bridges yield an automated and authenticated weighment data for the incoming and outgoing commodities at any given depot
FCI Depot In-Charge
Release Order Execution
To capture the commodity weighment data passing through weighbridge
NCDEX Release Order
To generate the Release Order online for OMSS schemes
FCI District Office –Accounts Section
Release Order Execution
To perform the Release Order Execution steps
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
38
3.4 APPLICATION PROSPECTIVE
Release Order is an authorized document generated by Sales Department of FCI district office on the payment made by the respective State parties like State agencies and other private agencies. It facilitates the respective State Agencies /Parties to lift the commodity from FCI depots.
3.4.1 RELEASE ORDER PROCESS STEPS
Release Order operations are broadly categorized into following 5 process steps based on the functionality.
1. Release Order Initiation
a. Scheme wise food grains allocation details.
b. Indent generation based on Central Issue Price
2. Release Order Generation
a. Designated depot assignment
3. Release Order Execution
a. update the lifted weights and quantities against the Release Order by integrating with
Weighbridge
4. Release Order Closing
a. Close the Release Order once the State Agency/Party lifted all the commodities against the
Release Order
5. Other Processes
a. Release Order Extension – Not lifted the commodities within the Release Order validity period
b. Release Order Diversion – Diverted to other Depot due to stocks unavailability
c. Reimbursement – Reimbursement of pending amount to State Agencies/Parties for un lifted
quantity.
d. Release Order Cancellation – Cancel the Release Order in case of not lifted the quantity in-time
and is not extended
6. To integrate the Release Order application with External Applications
a. DCMS
b. IRRS
c. FAP
d. FEAST
e. Weigh bridge
f. NCDEX Release Order Application
The consolidated process flow diagram is given below for Release Order operational steps
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
39
Prepares the District
wise food grain
requirements sheet
based on GOI
allocations
Prepare the district
wise indent letters
for each scheme
Send the indent to
the accounts
section for payment
Receives the Indent
letter with payment
details from the
State agency/party
District Office
FCI District Office Generate
4 Copies of the RO and
handover it to assigned
Depot and State Agency
District Officiall/ Party
FCI Depot In charge
generate the Issue
planning sheet and
handover it to State
Agency/party
State Agency/Party
Lifts the Commodity
Depot based on
Planning sheet using
Transport Agency
Allocated
Commodity
Lifted to
Truck
Weight the empty truck and
then loaded truck. Capture
the Weight and Quantity.
Transport Agency submit
the Gate Pass at Gate
RO Close once all
the food grains
lifted from the
Depot against RO
RO INITIATION STEPS
(Pre Process)
RO PROCESS STEPS
(Generation, Execution & Closing)
Extension Request
by State Agency
with No Days (15,30
or More
Approved
???NO (Rejected)
YES
Lift the Stock with in the
Extension period
No
No Stock
Certificate issue
by Depot
manager
District Office
diverts the RO to
another depot
based on Stocks
Availability
State Agency
Submits the
Reimbursement
Request
RO Closes and
release the pending
amount back to
State Agency/Party
State Agency/Party State Agency/Party
FCI District OfficeFCI District Office
FCI District OfficeFCI District Office
FCI Depot – Incharge/Stage Agency/PartyFCI Depot – Incharge/Stage Agency/PartyWeighbridge Incharge
Weighbridge InchargeFCI Depot
FCI Depot
FCI DepotFCI Depot
State Agency/PartyState Agency/Party
YES
FCI Regional / Zonal OfficeFCI Regional / Zonal Office
START
END
FCI District OfficeFCI District Office
FCI District OfficeFCI District Office
RO EXTENSION PROCESS
(RO Expires)
RO DIVERSION PROCESS
( stock Not Available )
RO REMERSEMENT PROCESS
(Un Lifted Quantity)
Account Section/Party
Transfer the amount to
FCI District Office either
through RTGS/DD
Verify and assigns
the Depot based on
the Stocks availability
Figure 3: RO Process Steps
3.4.2 RELEASE ORDER INITIATION The Release Order Initiation process includes the following steps:
3.4.2.1 ALLOCATION PROCESS
Department of Consumer Affairs, Food & Public Distribution (CA,F&PD) of Government of India (GOI) receives the
food grain requirements from the State food departments to implement the welfare schemes.
CA,F&PD department of GOI issues food grains allocation orders under various schemes as per the allocation
guidelines and policies.
The schemes are broadly classified into two types:
1. TPDS & other welfare schemes
2. Commercial schemes
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
40
Following are the steps involved in the allocation process based on the schemes:
a. TPDS & Welfare Schemes – Fixed time intervals
1. State Departments sends the scheme wise commodity requirements to the Consumer Affairs, Food &
Public Distribution (CA, F&PD) Department, GOI along with previous utilization/un-lifted quantity details
against previous allocations.
2. CA,F&PDS verify the requirements and allocates the commodities to the States, based on the guidelines
and issues the allocation order to the FCI head office and respective Central/State Departments.
3. FCI HQ sends Letters to the Respective Zonal/Regional offices to make sure the allotted quantities are
available in the designated FCI Depots.
4. A state food department segregates the State level allocations across revenue districts and sends the
same to FCI Regional office.
5. FCI regional office sends the revenue district-wise and scheme wise allocation of food grains details to
the FCI district office.
6. Area Manager of respective FCI District Office ensures that the food grain is available in the designated
depots for lifting by the State Food Dept. / Agencies.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
41
Allocation process – Welfare Schemes
FCI Head/Regional/
District Office
Consumer Affairs, Food
& Public Distribution,
GOI
Requesting Department
– State/ Central
Start
Prepare the scheme
wise food grain
requirements
Prepare the revenue
district wise allocations
and send it to FCI
Regional office
CA,,F&PD verifies the
requirements and allocate
the commodities to the
states with allocation
guidelines
END
Send the allocation Orders
to the FCI head office and
State Departments
FCI Head Office sends the
Letters to the FCI Zonal/
Regional Offices
Prepare the scheme
wise demand Requests
FCI District Area Manager
maintains the stocks at
designated depots as per
the allocations
FCI Regional Office
validate against GOI
allocations
FCI Regional Office sends
the allocation details to
FCI districts offices
Figure 4: Allocation Process - Welfare Schemes
b. Commercial Schemes - Open Market Sale Scheme – OMSS - On need basis To clear the surplus stocks, FCI releases food grains into open market via OMSS (D) scheme and sells it to the private agencies/parties based on the guidelines given by the Ministry of CA,F&PD to clear the surplus stocks from the Depots. This can be done at any time usually in following scenarios
1. To avoid the financial burden of storage and maintenance of food grains 2. To maintain the storage space for next procurement season 3. To stabilize the prices in the open market and inflation
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
42
Allocation Steps 1. Ministry of CA,F&PD decides the allocation of various commodities under OMSS scheme.
2. FCI Zonal/Regional office forms a committee to finalize the tender guidelines and eligibility criteria as
per the guidelines specified by CA,F&PD
a. Eligibility Criteria
b. Methodology
c. Payment Terms and Conditions
d. Minimum Quantity and Issue Prices etc.,
e. Empanelled State/private parties or all
3. Lifting priority
a. Stock kept in unscientific plinths
b. Stocks kept in CAP
c. Stocks kept in covered godowns
d. Non-rail head godowns
e. Godowns connected to railway goods shed (railheads).
4. Ministry of CA,F&PD publish tenders through online portal (NCDEX or any other portal)
5. Evaluate the submitted bids
6. Select the eligible parties
7. Assign the depots and Issue the allocation orders to the bidding parties
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
43
Allocation process – Commercial Schemes
FCI Head/Regional
Office
Consumer Affairs, Food
& Public Distribution
GOI
FCI District/Regional
Office
Send the allocation letters
to the FCI Head Quarter
Allot the quantities to sell
the commodities to the
private parties/agencies
by keeping the buffer
stocks of 3 months for
welfare schemes
END
Regional office select the
bidders by calling the
tenders
FCI Head Office sends the
allocation Orders and
guidelines to the FCI
Zonal/Regional Offices
Issue allocation letters to
successful bidders
Start
Prepare the surplus
Stocks availability
Submit to the Govt. of
India
Figure 5: Allocation Process - Commercial Schemes
3.4.2.2 INDENT GENERATION
1. State Agency/Party calculates the Deposit amount as per the central issue price for the allotted
commodities.
2. State Agency/Party makes the payment to FCI’s Bank Account through DD/RTGS/NEFT or any other financial
instrument recognized by FCI.
3. State Agency/Party prepares the indent letter with commodity (scheme name, required quantity etc.) and
payment (amount, bank, UTN number) details.
4. Submits indent to the FCI district office to initiate the Release Order Creation process.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
44
Indent Generation
State Agency/Party
Validate the demand vs
allocations
Submit the indent letter
to FCI District office for
issuing Release Order
Release Order
Generation
END
Deposit the amount to
FCI District office
account based for the
required /allotted
quantity
Prepare the Indent
Letter by providing
required commodities
with payment details
START
Figure 6: Indent Generation
3.4.3 RELEASE ORDER GENERATION STEPS Releaser Order generation process at FCI District Office consist of the following steps.
1. FCI district commercial section receives the Indent Letter along with payment or payment details from the
State Agency/Party.
2. FCI district commercial section send to accounts section for payment amount verification.
3. Accounts section verifies the deposit amount and enters the payment details in the FAP.
4. Accounts section sends the authorization letter to sales / commercial section.
5. Sales/ commercial section checks the stocks in the active depots using DCMS and IRRS respectively and
assigns the depot for stock lifting.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
45
6. FCI commercial section creates the Release Order and submits to FCI district’s area manager for approval.
7. FCI district’s Area manager approves the Release Order
8. FCI commercial section generates 4 copies of the Release Order and sends it to State Agency/Party and
Depot.
RO – Generation Process
FCI District Office
(Accounts Section)
FCI District Office
(Sales Section)State Agency/Party
Checks the Active
Depots and stocks
availability
Receives the Indent letter
from the State agency/
party and submit to the
department
Start
Sends the Indent Letter
with payment details to
the Account Section
RO Initiation
DCMS/IRRS
Verified OK?
Enter the payment
details to FAP.
Send authorization
;letter to Sales
Department
Yes
Release
Orde
Date
Quantityr
Release
Orde
Date
Quantityr
Release
Orde
Date
Quantityr
Release
Orde
Date
Quantityr
Retained in booklet
Send it to State Agency/Party
Send it to Depot to fill the daily lifted quantity
Send to Depot Return back to FCI District Office after closed
END
RO ExecutionCollects the Release
Order from FCI District
Office
Generate 4
Copies of Release
Order
FAP
Receives the Indent
Letter with payment and
commodity details
NoReject the Indent
and send back to
State Agency/Party
Verity the
payment Online through
Bank Portal
Figure 7: RO Generation Process
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
46
3.4.4 RELEASE ORDER EXECUTION STEPS Releaser Order Execution process includes following steps:
1. State Agency/Party visits the depot with Release Order.
2. Depot In-charge prepares the delivery plan and handover it to State agency/party.
3. Transport agency brings truck to the depot and produces the release order/delivery plan.
4. Gate in-charge issues the Inward gate pass to truck driver.
5. The truck driver positions the truck onto weighbridge.
6. Weighbridge software provides the weight of the empty truck.
7. Weighbridge Operator enter the following details:
a. Inward gate pass number
b. Truck number
c. Release Order number
8. Unit In-charge loads desired quantity onto truck and fills details in Weight Check Memo (WCM).
9. Truck driver positions his truck at weighbridge and shows WCM & initial inward receipt.
10. Weighbridge operator fills serial number and details of commodity, bag types, unit number, stack number,
provided by Unit-in-charge & weight of one bag into system. System also captures tare weight of truck and
calculates net weight of issued quantity. Revised receipt gets generated and given to truck driver.
11. Truck goes back to unit and shows weighbridge receipt.
12. Unit In-charge takes back extra loose grain or issues balance loose grain depending on excess or short of
issued quantity using beam scale.
13. Truck is again weighed and weighment slip is generated automatically by the weighbridge.
14. Once it is ensured that issued quantity is less than or equal to allocated quantity, details are entered into
WCM and M-form.
15. Unit In-charge generates four copies of gate pass and gives one copy to truck driver.
16. Truck driver deposits outward gate pass at exit gate.
Repeat the Steps 1 to 16 till all the assigned quantity against the Release Order is lifted.
17. The Daily Stocks Issue Register is updated for the stocks lifted against the Release Order
18. Weighbridge operator generates daily off take/ dispatch report against the Release Order and sends it to
depot manager.
19. Release Order gets killed/closed by Depot Manager once entire against the release order gets lifted.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
47
RO – Execution Process
State Agency/Party/
Transport Agency
FCI Depot
(Depot Incharge)Weighbridge In- charge
Transport Agency brings
the trucks to Depot Gate
and shows the RO and
Delivery plan
Weigh bridge operator
weighing the tare weight
of the empty truck
State Agency Official/
Party Collects the
Delivery plan from Depot
In-Charge and lift the
commodities accordingly
Prepares the Delivery
plan
Unit In-charge loads
the desired quantity
and fills the details in
the Weight Check
Memo
Weighbridge operator
fills truck and transport
agency details including
truck number into
weighbridge software
gives inward receipt to
Truck Driver
Start
State Agency Official/
Party visit the Depot with
Release Order Weighbridge operator fills
serial number and details
of commodity, bag
types & weight of one
bag to get the net weight
of the Commodity
1
3
4
Based on the weigh
bridge Receipt Unit In-
charge takes back extra
loose grain or issues
balance loose grain
depending on excess or
short of issued quantity.
5
Depot In-Charge
Accumulate daily off-
take quantity of the
Depot enter into IRRS
and enter the lifted
quantity against RO
6
8
RO Closing
Repeat the Steps 1 to 8 and lifted Quantity against RO will be
updated in the RO application either offline/ or by weighbridge
integration. Till all the quality lifted against the Release Order Yes No
Food grains are
not lifted with in
the Validity Period
RO
Extension
Stocks are not
available in
assigned Depot
RO
Diversion
No
END
END
RO
Generatio
n
IRRS
END
Gate In charge verifies
and permit the truck to
lift the commodities
2
7
Figure 8: RO Execution Process
3.4.5 RELEASE ORDER DIVERSION STEPS
Either in case of stock unavailability or in case such conditions where in stock can’t be lifted from designated depot, Commercial section of FCI District office diverts the Release Order to any feasible depot within same FCI district. In case Release Order needs to be diverted to any depot beyond the FCI district, Regional office authorizes the Release Order diversion to any depot of other district.
1. Depot Manager of the initially identified depot certifies that there is no stock to issue against the Release
Order.
2. FCI District Office diverts the Release Order to another depot within the same FCI District.
3. Party lifts commodity from the depot identified later.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
48
Release Order – Diversion Process
FCI District OfficeCSC District Office
Release Order
Diversion
Release Order
Closed
Release Order
Generation
Yes
FCI District office can
divert the Release Order
to another depot due to
unavailability of stocks in
the assigned depot
Same FCI
District
Start
FCI District office
divert the Release
Order to another
Depot based on
stocks availability
Release Order
Execution
New Release Order
is generated by the
newly assigned
District Office
Current Release Order
is closed and district
office will transfer the
amount to the newly
assigned District office
No
END
Figure 9: RO Diversion Process
3.4.6 RELEASE ORDER EXTENSION STEPS If Depot Manager receives requisition for lifting beyond the validity date (usually after 7 working days) of Release Order then concerned agency is denied for stock lifting. In such scenario, agency sends extension letter to FCI office. Following are the steps to execute Release Order extension request for TPDS and welfare Schemes:
1. Depot Manager receives Day wise requisition from State Agency / Party
2. FCI district office will extend the RO up to the validity period given by GOI.
3. After the expiry of validity period given by GOI, Regional Office can extend the RO up to 15 days and
thereafter, Zonal Office can extend it for another 15 days.
4. Ministry can extend the RO for no limit.
5. Extension request gets approved / rejected.
Following are the steps to execute Release Order extension request for OMSS (D) Scheme
1. Depot Manager receives Day wise requisition from State Agency / Party.
2. Extension Request as provided in the guidelines in vogue of OMSS (D).
3. Extension request is approved / rejected.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
49
Release Order – Extension Steps
CSC District Office FCI District OfficeFCI Regional/Zonal
Office
Release Order Execution Release Order
Execution
Yes
No
Approve
Reject
Approve
Release Order Execution
State Agency/Party requests for Release
Order extension to FCI District Office with
Reason for not lifting the food grains in time
Send the Request to FCI Regional for Release
Order Extension
Send it to Ministry for Approval
If Days is <= 7
END
Regional
Office Can Approve
or Reject
Release Order Reimbursement
Ministry Can
Approve/Reject
If Days is <= 15
Release Order Reimbursement
Start
Yes
No
District Office Can
Approve or Reject
Approve
Reject
Reject
Figure 10: RO Extension Steps
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
50
3.4.7 RELEASE ORDER REIMBURSEMENT STEPS
If Extension request of State Agency/Party is rejected by FCI office then State Agency submits reimbursement request to get the reimbursement against un-lifted quantity. State Agency may also submit reimbursement request if they are not willing to lift the commodity allocated to them.
In such scenario, following steps are recommended for executing the reimbursement request.
1. State Agency / Party submits reimbursement request.
2. Account Section receives reimbursement request.
3. Get off-take details against Release Order.
4. Calculate payment for remaining quantity.
5. Closing of Release Order.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
51
3.4.8 RELEASE ORDER OPERATIONS AT DELHI In Delhi, the Release Order Generation and Execution process is different from the other States. The stocks can be directly lifted to the Fair Price Shops and Single Release Order can be generated irrespective of the scheme and Commodity. Following are the operations steps involved for Release Order
3.4.8.1 BULK PARTIES
Figure 11: Bulk Parties
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
52
3.4.8.2 SMALL TRADERS
Figure 12: Small Traders
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
53
3.4.8.3 KENDRIYA BHANDAR
Figure 13: Kendriya Bhandar
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
54
4. PROPOSED BUSINESS SOLUTION This section presents high-level overview of the proposed System and the environment in which it will be used, the anticipated users of the software, known constraints, assumptions and dependencies.
4.1 RELEASE ORDER ARCHITECTURE The following are the key components which are proposed to be in-built the proposed Release Order Application.
1. Workflow engine - Core business component which includes the functionality to automate all the release
order operations from release order initiation to closing.
2. Centralized intelligent data exchange engine - Links the external applications. To develop the data communication interfaces between the Release Order Applications with external applications.
3. Web Portal - Online reporting and application dashboard which allows stakeholders to perform the Release Order tasks remotely. It allows the users to track and monitor the Release Order status online.
4. Centralized database - Data store for Release Order Application, to generate the reports online.
Following is the Release Order Application architecture with the Components.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
55
RO Database
Mail Server
SMS Server
DCMS/IRRS
FEAST/SIMS
Weighbridge
FAP
Allocation Indent Generation
RO Generation RO Execution RO Closing
RO Extension RO Diversion RO Reimbursement
WORLFLOW MODULE
DATA EXCHANGE MODULE
SMS Interfaces Mail Interfaces
DCMS Interfaces IRRS Interfaces FEAST Interfaces
FAP Interfaces
FCI District & Depot
Officers
FCI HQ/ Zonal/
Regional Officers
State Agencies /
Parties
WEB PORTAL
User Access
ManagementWorkflow Managment
Reporting
Engine
Security
Managment
Administration &
Configuration
HTTP
GU
I
I
NT
ER
FA
CE
S
DA
TA
E
XC
HA
NG
E
IN
TE
RF
AC
ES
CONNECTIVITY INTERFACES
CONNECTIVITY INTERFACES
ADO .NET
END USERSRELEASE ORDER APPLICATION EXTERNAL APPS
SMS
API
API
DB
Scripts
DB
Scripts
CSV
/XML
/Open Data
CSV
/XML
/Open
Data
Figure 14: Architecture
4.2 FUNCTIONAL REQUIREMENTS This section explains the module wise high level functional requirements of the proposed Release Order Application
4.2.1 WORKFLOW ENGINE The workflow engine module is responsible for implementing the business functionality to automate the Release Order operations from initiation stage to the Closing including the exceptional Release order processes like Release Order Extension, Diversion, Cancellation and Reimbursement based on Scheme and commodities. Following are the identified functional requirements to implement the Release Order Workflow Engine:
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
56
4.2.1.1 ALLOCATION
Department of Consumer Affairs, Food & Public Distribution (CA,F&PD). GOI allocates commodities to the State and State allocates to their revenue districts under various schemes and issues the allocation letters to Food Corporation India based on the prescribed guidelines and utilization along with unutilized allocation reports. FCI will releases the food grains to State agencies /parties under various schemes as per the allocation guidelines prescribed by Department of CA, F&PD. Release Order application should capture the scheme wise allocation details based on the allocation guidelines. Following are the functional requirements for the allocation process Requirement #1: Ability to add the scheme wise allocation details based on the central allocations for the new schemes.
o State wise
o Revenue District wise
To address this requirement RO application would offer a module called Allocation which further be divided in 2 sub module as follows 1. State allocation
2. Revenue District Allocation
State Allocation: Only authorized users having access State Wise or Revenue District Wise module would log in the application and add the scheme wise State or Revenue District wise allocation. In State Wise Allocation module, user would be provided with below details:
State
Allocation Duration (From and To)
GOI Allocation Order No.
GOI Order Date
Scheme Group
Scheme
Commodity Details
Commodity
Allocation Type
Quantity (MT up to 3 decimal places)
GOI Allocation Order Validity
Allocation letter for reference
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
57
User would key-in/select the appropriate values against aforementioned fields to create state Allocations. Business Rules and Validations: 1. Allocation would be done only for one state at a time
2. Allocation Duration (From and To) would be mandatory field for user. Allocation from date should be
less than or equal to Allocation To date.
3. GOI Order Date would be a mandatory field for user. GOI Order Date should be less than Allocation to
Date.
4. Scheme Group and Scheme Name would be a mandatory field. Based on the selection of “Scheme
Group”, scheme name dropdown should be populated with the appropriate values. Scheme Name
dropdown should only show those schemes which would be mapped to the respective Scheme groups
5. Multiple Commodity Details can be added in one State Allocation.
6. Commodity Name would be a mandatory field.
7. Allocation Type would also be a mandatory field having the values as: “Regular/Additional/ Ad hoc”.
8. GOI Allocation Order Validity date field would be mandatory and greater than GOI Order date
Revenue District Wise Allocation: In Revenue District Wise Allocation module, user would be provided with below details to fill:
State
GOI Allocation Orders Dated between (From and To)
GOI Allocation Order No.
Select State Allocation Year & Month
State Allocation Order No.
Allocation Order Date
Scheme Group
Select Scheme
Commodities Details
Revenue District**
Commodities
Total State Allocation
Payment Cutoff Date
Enter Allocation (MT up to 3 decimal places)
Allocation letter for reference
User would key-in/select the appropriate values against aforementioned fields to create revenue District allocations. ** Note: (1) One Revenue District is being served by more than One FCI District. VC is proposed against the same
example Durgapur and Burdwan in West Bengal Region.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
58
(2) Provisioning for sub division allocation.
Business Rules and Validations: 1. Allocation would be done for one state at a time
2. GOI Allocation orders Dated between (From and To) would be mandatory for user. GOI Allocation from
date should be less than or equal to GOI Allocation To date.
3. GOI Allocation Order No. field would populate only those orders falling between the GOI Allocation
orders from and To Date selected.
4. Based on the GOI Allocation order No. selection, Scheme group as well as scheme name dropdown
would only show the mapped appropriate values .
5. Special character would be restricted in Allocation Order No. except ‘/’ and ‘-‘.
6. Based on the GOI Order No., Commodity field would only show the mapped appropriate values
7. Revenue District field would be mandatory and populate the values based on State selected by the user
8. Allocation should also be done in multiple revenue districts.
9. The total Quantity should be less than or equal to the total Quantity of the state allocation
Requirement #2: Ability to update scheme wise allocation details based on the central allocations for the existing schemes.
o State wise
o Revenue District wise
Solution: State Wise Allocation: To update State Wise Allocation details, user would modify the below fields:
State
Allocation Duration (From and To)
GOI Allocation Order No.
GOI Order Date
Scheme Group
Scheme
Based on updating above fields, user would modify below commodity related details: Commodity Details
Commodity
Allocation Type
Quantity (MT up to 3 decimal places)
GOI Allocation Order Validity
Allocation letter for reference
Business Rules and Validations: 1. User can edit allocations and excess off take if any will be flagged in case allocation has been reduced.
2. Allocation Duration (From and To) would be mandatory field for user. Allocation from date should be
less than or equal to Allocation To date.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
59
3. GOI Order Date would be a mandatory field for user. GOI Order Date should be less than “Allocation To
Date”.
4. Scheme Group and Scheme Name would be a mandatory field. Based on the selection of “Scheme
Group”, scheme name dropdown should be populated with the appropriate values. Scheme Name
dropdown should only show those schemes which would be mapped to the respective Scheme groups
5. Multiple Commodity Details can be added in one State Allocation.
6. Commodity Name would be a mandatory field.
7. Allocation Type would also be a mandatory field having the values as: “Regular/Additional/ Ad hoc”.
8. GOI Allocation Order Validity date field would be mandatory and greater than GOI Order date.
Revenue District Wise Allocation: To update Revenue District wise Allocation details, user would modify the below fields:
State
GOI Allocation Orders Dated between (From and To)
GOI Allocation Order No.
Select State Allocation Year & Month
State Allocation Order No.
Allocation Order Date
Scheme Group
Select Scheme
Based on updating above fields, user would modify below commodity related details: Commodities Details
Revenue District
Commodities
Total State Allocation
Payment Cutoff Date
Enter Allocation (MT up to 3 decimal places)
Allocation letter for reference
Business Rules and Validations: 1. GOI Allocation orders Dated between (From and To) would be mandatory for user. GOI Allocation from
date should be less than or equal to GOI Allocation To date.
2. GOI Allocation Order No. field would populate only those orders falling between the GOI Allocation
orders from and To Date selected.
3. Based on the GOI Allocation order No. selection, Scheme group as well as scheme name dropdown
would only show the mapped appropriate values .
4. Special character would be restricted in Allocation Order No. except ‘/’ and ‘-‘.
5. Based on the GOI Order No., Commodity field would only show the mapped appropriate values.
6. Revenue District field would be mandatory and populate the values based on State selected by the user
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
60
7. Allocation should be segregated across the revenue districts.
8. The total Quantity should be less than or equal to the total Quantity of the state allocation.
Requirement 3#: Ability to send an e-Mail/SMS to concerned officers, once the allocation is digitized or captured from external applications.
Solution: To address the above requirement, e-Mail/SMS facility would be integrated with Release order application and e-mails/SMS would be shared to related authorities on any action.
4.2.1.2 INDENT
Indent letter would be generated by the State agency/party which includes the scheme, commodity and payment details. FCI District office would verify the payments details and send indent to competent authority for approval. Once indent approved by competent authority the Release Order Creation process would start. Below are the functional requirements for the Indent generation process.
1) Create New Indent
2) Approve Indent
3) Make Payment
4) Sales Approve
Requirement 1#: Application should have ability to create a new indent.
Solution: In Create New Indent module, user will be provided with below details to fill so that Indent Creation activity can be performed.
FCI District
Revenue District **
Allocation Year/Month
Name of State Agency Party
State Government Allocation Order Number
State Govt. Allocation Order Date
Payment Cut-off Date
GOI Allocation Order Number
Scheme Details
Central Scheme Name
Commodity
Total Allocation Quantity (MT)
Available Quantity (Qtl.Kg gms)
Quantity (Qtl.Kg gms)
CIP/Issue Price (Rs./Qtl.Kg gms)
Cost of Food Grains
Tax / VAT / Other Charges
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
61
Tax Name
Tax Rate
Tax (Rs.)
Cess (Rs.)
Total (Rs.)
Deduction Details
Deduction Details
Amount
** Note: (1) One Revenue District is being served by more than One FCI District. VC is proposed against the same,
example Durgapur and Burdwan in West Bengal Region.
(2) Provisioning for sub division allocation.
Business Rules and Validations:
1. FCI District and Revenue District would be populated automatically for which logged in user is
authorized.
2. User would select Allocation Month and Year. “State Government Allocation Order Number”
would be populated based on selected Month and Year.
3. User would select “State Government Allocation Order Number” and “State Govt. Allocation
Order Date”. Based on the selection against both the fields, “GOI Allocation Order Number”
should be populated accordingly.
4. After performing step from 1 to 3 user would provide Payment Cut-off Date which should be
greater than or equal to today’s date. This input is mandatory for user.
5. User would provide Commodity details. One Indent should capture only one commodity.
6. Quantity should be entered less than or equal to Available Quantity. Available Quantity will refer
to quantity for which Indent is pending.
Quantity Available for Indenting/Off take = Total Allocation – Total Quantity Indented
7. CIP/Issue price will be populated from CIP/Rate master database as per selected commodity.
8. Cost of Food Grains would be calculated by the system.
Cost of Food Grains = (Quantity * CIP/issue price) + Applicable Taxes
9. User can add multiple Tax / VAT/ Other Charges for the currently added commodity. Based upon
the Tax Name selection “Tax Rate” and “Tax” will be calculated
Total Tax= Tax + Cess
10. Multiple Deductions can be added for the current commodity.
Indent Amount= Cost of Food Grains + Tax Cost – Deductions (if any)
11. Multiple indents can be created against a revenue district allocation.
Requirement 2#: Application should have ability to approve or reject the current indent details by Indent Approver.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
62
Solution: To address the above requirement user would be provided with below details to fill so that Indent Approve/Reject activity can be performed. Authorize user will be log in the Application and will select Indent Approve module, where user will provide Date From and Date To as input and user will see details of Indent between given date range which are created for that Revenue District for which user (Approver) is authorized to approve. User will see below details in Awaiting Approval (which are waiting for approval) and Approved (which are approved by user) section.
Awaiting Approval
S.No.
Indent Number
Allocation No.
Indent Submission Date
Indent Status
Approved
S.No.
Indent Number
Allocation No.
Indent Submission Date
Indent Status
By selecting “View/Approve” option of any row item displayed in Awaiting Approval list user will move Indent Approve/Reject module.
o Indent Approve/Reject: In Indent Approve Reject module user will be provided with below details to
view and fill required input details so that Indent Approve/Reject activity can be performed.
Indent No.
Indent Submission Date
FCI District
Revenue District
Allocation Year & Month
Name of State Agency / Party
State Govt. Allocation Order Date
State Government Allocation Order Number
GOI Allocation Order Number
Payment Cut-off date
Schemes Indented By State Agency / Party
Central Scheme Name
Commodity
Quantity
CIP/Rate(Rs./Qtl.Kg gms)
Cost of Food Grains
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
63
Business Rules and Validation:
1. User will get indent of that Revenue District for which he/she is authorized.
2. All the details of indent which will appear to approver are only which are captured at the of
Indent creation.
3. User has to enter Approved Remarks or Reject Remarks for the Indent.
4. Approved Indent will be appearing for payment.
5. User will get a message as status of action.
Requirement 3#: Application should allow the user to provide the payment details. Application should consider the previous balance amounts if any, while generating the current payment details of the current month.
Solution: To address the above requirement user will be provided with below modules by using user can capture payment details.
o Make Payment
o Payment Type
o Make Offline Payment
o Make Payment: In Make Payment module user will be provided with below details of Indent to view
List of Approved Indents
S.No.
Indent Date
Indent No.
Indent Approval Date
State Allocation Order Number
State Allocation Order Date
Amount To Be Paid
Amount Paid
Payment Cut-off Date
User will select Pay Now option against any listed items to process the payment and user will see indent details and pending indent amount of last month to be paid.
Payment Type: In Payment Type module user will be provided with below details to view. Un-utilized Payments details are pending Indent Amount of last month
State Agency Party Name
Indent No.
Indent Date
Indent Approved Date
State Allocation Order No.
State Allocation Order Date
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
64
Indent Amount (INR)
Amount Paid Till Date
Partial Payment Details for Indent No.
S.No.
Payment Mode
Authorization of Cash
Bank Name
Branch
IFSC Code
Payment Date
Transaction / Ref. No.
Amount Paid
FAP Receipt
Un-utilized Payments
S.No.
Description
Amount
User will see Offline and Online Payment options. If user will select Online user will move to Payment page of Bank website. If user will select Offline user will move Make Offline Payment page.
Make Offline Payment: In Make Offline Payment module user will be provided with below details
State Agency Party Name
Indent No.
Indent Date
Indent Approved Date
State Allocation Order No.
State Allocation Order Date
Indent Amount (INR)
Amount Paid Till Date
Payment Details
Payment Mode
Bank Name
Payment Date
Branch Name
Payment Instrument No.
IFSC Code
Amount Paid
Upload Payment Proof
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
65
Business Rules and Validations:
1. Upload Payment Proof is mandatory for every payment.
2. Payment Date should be equal or less than today’s date.
3. When we select “Payment Mode” as DD, Cheque, Bank Challan, NEFT, RTGS the bank details,
Amount and Payment Instrument No. are mandatory.
4. When we select “Payment Mode” as Cash the Details of Authorization of Cash and Amount are
mandatory.
5. User will make payment Online/Offline, payment details will be updated in FAP Application
against selected Indent Details. It will happen though a service.
Requirement 4#: Application should allow the FAP user to verify the payment details which in-turn is verified from the FAP Application. After verifying the payment made by the State agency/party gives the confirmation for proceeding with the indent generation process. Solution: To address the above requirement user will be provided with FAP Approval module by using FAP user can verify payment details.
o FAP Approval: In FAP Approval module user will be provided with below details to which user need to
verify.
List of Pending FAP Approvals
S.No.
Indent Date
Indent No.
Indent Approval Date
State Allocation Order Number
State Allocation Order Date
State / Party Name
Amount Paid
Document Number
Receipt Number
Remarks
View Payment Receipt
User will select “Request FAP Approval” option against any pending item from list and user will move on Payment Verification page. FAP Approve / Reject: Before approval FAP user has to enter receipt No. and document No. from FAP module to RO module in the relevant fields in FAP Approval screen. In this screen, FAP user will be provided with the following fields
Approve / Reject Option
Document Number
Receipt Number
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
66
Approved / Reject Remarks
Upload FAP Receipt
Business Rules and Validations:
1. FAP User can upload Receipt in PDF Format.
2. FAP user will verify and approve the payment details. In case payment is not available then FAP user
has option to reject the indent with rejection remarks.
Requirement 5#: Sales division can approve or reject the current indent details vis-à-vis the amount deposited and the quantity indented.
Solution: To address the above requirement user will be provided with “Approve Indent by Sales section”, here users will Approve or Reject Indent details.
o Approve Indent By Sales: In “Approve Indent By Sales” section user will be provided with below details
from Approval or Rejection. User will get two list Awaiting Approval (which are waiting for approval) and
Approved (which are approved by user) section. Here user will get From To Date option, by providing
date range user will get indent details held under given date range as below:
Awaiting Approval
S.No.
Indent Number
Allocation No.
Indent Submission Date
Indent Status (FAP Approved/Rejected)
Approved
S.No.
Indent Number
Allocation No.
Indent Submission Date
Indent Status (Sales Approved/Rejected)
User will see above details of indents which are approved or waiting for approval by Sales Manager. When user will select “View/Approve” option user will move on Indent Approval/Rejection module.
Indent Approve Reject: In Indent Approve Reject module user will be provided with below details
Indent No.
Indent Submission Date
FCI District
Revenue District
Allocation Year & Month
Name of State Agency / Party
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
67
State Govt. Allocation Order Date
State Government Allocation Order Number
GOI Allocation Order Number
Payment Cut-off date
Schemes Indented By State Agency / Party
Central Scheme Name
Commodity
Quantity
CIP/Rate(Rs./Qtl.Kg gms)
Cost of Food Grains
Schemes Indented By Sales Manager
Total State Allocation Quantity (Qtl.Kg gms.)
Indented Quantity (Qtl.Kg gms.)
Total Amount
Paid Amount
Entitled Quantity (Qtl.Kg gms.)
Approved Quantity (Qtl.Kg gms.)
Business Rules and Validation: 1. Approved Quantity should be less than or equal to Entitled Quantity.
2. User can approve partial indent on the basis of Total and Paid Amount.
Requirement 7#: Ability to send an e-Mail/SMS to concerned officers once the allocation is digitized or captured from external applications.
Solution: To address the above requirement e-Mail/SMS would facility would be integrated with Release order application and e-mails/SMS would be shared to related authorities on any action.
4.2.1.3 RELEASE ORDER
Release Order generation talks about the steps involved in creation of the Release Order based on the Indent received from the State agency/party. Following are the functional requirements for the Release Order generation process. Requirement 1#: Ability to add the commodity details based on the State agencies /parties indented commodity details for the new schemes.
o Create New Release Order
o Approve Release Order
To address the above requirement “Create New Release Order”, “Approve Release Order” modules would be provided to the user. Those users having permission to access Create New Release Order or
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
68
“Approve Release Order” modules would log in the application with valid credential and Create New Release Order or Approve Release Order. User would be provided with below details
o Create New Release Order: In Create New Release Order module user will be provided with below
details
Commercial/Sales Approved Indent No.
View Stock Position
Select Commodity
Select Depot
FCI Depot for Offtake
Release Order No.
Release Order Date
GOI Allocation Order No. & Date
Allocation Month & Year
State Agency/ Party
Issued to Revenue District
FCI District
Schemes Indented By State Agency / Party Details
Central Scheme Name
Commodity
Indented Qty (Qtl.Kg gms)
Sales Officer Approved Qty(Qtl.Kg gms)
CIP/Rate(Rs./Qtl.Kg gms)
Indenter Cost Of Food Grains
Release Order Commodity Details
Central Scheme Name
Commodity Name
Available Indenter Qty(Qtl.Kg gms.)
CIP/Rate(Rs./Qtl.Kg gms)
Issued Qty(Qtl.Kg gms.)
Amount
Business Rules and Validation:
1. User will get select option to FAP Approved Indent No., FCI Depot for Off take. On the basis of selected
Commercial/Sales Approved Indent No., FCI Depot for Off take - Release Order No. auto generates.
2. GOI Allocation Order No. & Date, Allocation Month & Year, State Agency/ Party, Issued to Revenue
District, FCI District will be populated on the basis of selected FAP Approved Indent No.
3. Release Order date will be today’s date.
4. Schemes Indented By State Agency / Party details will be populated on the basis of selected
Commercial/Sales Approved Indent No..
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
69
5. Based on the stock availability user will create the Release Order. User will check stock position by
clicking on “View Stock Position” hyperlink.
6. Only one commodity/scheme can be added in one Release Order.
7. Quantity of Release Order can’t be more than approved Indented Quantity.
8. Multiple “Release Orders” can be created against one approved Indented Quantity. After creating one
Release Order, when user will create another Release Order against same Indent, Release order can be
issued for remaining quantity only.
Available Quantity for Release Order against Indent Number = (Total Indented Quantity against
Indent Number – Release Order Allotted Quantity against that Indent Number)
Commodity Cost = (CIP/Issue Price * Issued Quantity)
Total Release Order Cost = (Commodity Cost + Applicable Tax/Vat/Others Charges - Deductions)
Requirement 2#: Ability to approve or reject the current Release Order details by User.
o Manage Release Order
o Release Order Approve Reject
o Release Order Manage: In Manage Release Order module user will be provided with below details
Awaiting Approval
Release Order No.
Release Order Submission Date
Indent No.
Indent Submission Date
FAP Approval Date
Approved
Release Order No.
Release Order Submission Date
Indent No.
Indent Submission Date
FAP Approval Date
Business Rules and Validation:
1. User able to generate the physical copy of the Release Order with Digital Signature which is mandatory.
o Release Order Approve Reject: In this module user will be provided with below details. This form will
appear when we click on View/Approve button in Release Order Manage page.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
70
FCI District Office - Release Order Verification and Approval
FAP Approved Indent No.
State Allocation Month & Year
GOI Allocation Order No. & Date
FCI Depot for Offtake
FCI District
Release Order Date
Release Order No.
Issued to Revenue District
State Agency/ Party
Schemes Indented By State Agency / Party Details
Central Scheme Name
Commodity
Indented Qty (Qtl.Kg gms)
Sales Officer Approved Qty(Qtl.Kg gms)
CIP/Rate(Rs./Qtl.Kg gms)
Indenter Cost Of Food Grains
Release Order Commodity Details
Commodity Name
Central Scheme Name
CIP/Rate(Rs./Qtl.Kg gms)
Issued Qty(Qtl.Kg gms.)
Amount
Release Order Cost Details
S.No.
Commodity Name
Central Scheme Name
CIP/Rate(Rs./Qtl.Kg gms)
Issued Qty(Qtl.Kg gms.)
Amount
Business Rules and Validation: 1. User has to select validity date for the Release Order.
2. Release Order Validity date will be greater than to Today date and should not be more than lifting
duration.
3. User has to upload the Digital Signature at the time of Release Order Approval.
4. User has to enter Approval Remarks or Rejection Remarks for the Release Order.
Requirement 3#: Ability to use the existing common master data to populate the values. To address the above requirement, below masters data would be provided to the user.
State
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
71
FCI District (mapped with corresponding Revenue District)
Revenue District (mapped with corresponding FCI District)
State Agency/Party
Commodity
Commodity Category
CIP/Issue Price (State wise)
Tax (State wise)
Bank
Bank Branch
Requirement 4#: Ability to send an e-Mail/SMS to concerned officers once the Release Order is digitized or captured from external applications.
To address the above mentioned requirement, e-Mail/SMS would facility would be integrated with Release order application and e-mails/SMS would be shared to related authorities on any action.
4.2.1.4 INFLOW The Food Corporation of India purchases food grains from producers during both the seasons, directly or through the agency of co-operatives or purchasing agents, and from millers under various arrangements of procurement determined by different State Governments. FCI undertakes the procurement of food grains on behalf of Government of India and State Governments where it has been entrusted with this responsibility either as a sole agency or jointly with other public procurement agencies. Following are the functional requirements for the Inflow process:
Requirement 1#: Application should have ability to add the commodities as per vehicle challan by Gate Entry Operator.
o Gate Entry - Loaded Truck
o Generate Token Number
o Gate Exit – Empty Truck
Gate Entry – Loaded Truck: In Gate Entry – Loaded Truck module, user will be provided with below details
Vehicle Challan No.
Vehicle Challan Date
Vehicle No.
Driving License No.
Driver Name & Mobile No.
Source of Inflow
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
72
Entry Date & Time
Loading Date at Source
Consigner
Consignee
Commodity Details as Per Vehicle Challan
Commodity Name
No. of Bags
Bag Type (BT/SBT/PP)
Quantity (Qtl.Kg gms.)
Business Rules and Validation:
1. Vehicle Challan Date should be less than or equal to today’s date.
2. Entry Date should be current date.
3. Loading Date at Source should be less than or equal to today’s date.
4. Single Commodity details will be allowed.
Generate Token Number: In “Generate Token Number” section, user would be able to generate the physical copy of token number.
Vehicle Challan No.
Vehicle Challan Date
Vehicle No.
Driving License No.
Driver Name & Mobile No.
Source of Inflow
Entry Date & Time
Loading Date at Source
Consigner
Consignee
Commodity Details as Per Vehicle Challan
Commodity Name
No. of Bags
Bag Type (BT/SBT/PP)
Quantity (Qtl.Kg gms.)
Business Rules: 1. Token Number to be printed must be a valid token number.
Gate Exit – Empty Truck: In Gate Exit Empty Truck user will be provided with below details
Vehicle Challan No.
Vehicle Challan Date
Vehicle No.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
73
Destination Depot Name
Driver Name & Mobile No.
Driving License No.
Entry Date & Time
Source of Inflow
Loading Date at Source
Consigner
Consignee
Loaded Weight of Truck
Weighment Date
Tare Weight of Truck
Weighment Time
Remarks
Commodity Unloaded
Commodity
Crop Year
Bag Type (BT/SBT/PP)
Issuable?
Category
Specification
Type of Labour
Quantity (Qtl.Kg gms.)
Gang No.
Labours Used
Type of Operation
Storage Type
Unit No.
Stack No.
No. of Bags Unloaded
S No.
Commodity
Bag Type (BT/SBT/PP)
As Per Vehicle Challan
Bags
Quantity (Qtl.Kg gms.)
As Per Unit Shed
Bags
Quantity (Qtl.Kg gms.)
Tare Weight Of Bags (Qtl.Kg gms.)
Gross Weight Of Commodity (Qtl.Kg. gms)
Net Weight Of Commodity (Qtl.Kg gms.)
Exit Details
Exit Date & Time
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
74
Business Rules and Validation:
1. Token Number to be printed must be a valid token number.
2. Exit date should be current date.
3. All the weighment details should come from the Open xml data format.
Requirement 2#: Application should have ability to get the weighment details by Weighbridge Operator.
o Weighbridge Room - Loaded Truck
o Weighbridge Room – Empty Truck
Weighbridge Room - Loaded Truck: In Weighbridge Room - Loaded Truck module, user would perform weighment of the loaded truck which was entered into the weighbridge room.
Vehicle Challan No.
Vehicle Challan Date
Vehicle No.
Destination Depot name
Driver Name & Mobile No.
Driving License No.
Entry Date & Time
Source of Inflow
Loading Date at Source
Consigner
Consignee
Commodity Details as Per Vehicle Challan
Commodity Name
No. of Bags
Bag Type (BT/SBT/PP)
Quantity (Qtl.Kg gms.)
Loaded Truck Weight
Weighbridge Identification No.
Weighbridge Room - Empty Truck: In Weighbridge Room - Empty Truck module, user would perform weighment of the empty truck which was entered into the weighbridge room.
Vehicle Challan No.
Vehicle Challan Date
Vehicle No.
Destination Depot name
Driver Name & Mobile No.
Driving License No.
Entry Date & Time
Source of Inflow
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
75
Loading Date at Source
Consigner
Weight of the Commodity as per 10% Weighment Rule
Loaded Vehicle Weight as Per Weighbridge
Consignee
Commodity Details as Per Vehicle Challan
S No.
Commodity Name
No. of Bags
Bag Type (BT/SBT/PP)
Quantity (Qtl.Kg gms.)
Commodity Unloaded
Commodity
Crop Year
Bag Type (BT/SBT/PP)
Issuable/Non Issuable
Category
Specification
Type of Labour
Quantity (Qtl.Kg gms.)
Gang No.
Labours Used
Type of Operation
Storage Type
Unit No.
Stack No.
No. of Bags Unloaded
Weighment Details
Loaded Weight of Truck
Tare Weight of Truck
Date & Time
Remarks
S. No.
Commodity
Bag Type (BT/SBT/PP)
As Per Vehicle Challan
Bags
Quantity (Qtl.Kg gms.)
As Per Unit/Shed
Bags
Quantity (Qtl.Kg gms.)
Tare Weight Of Bags (Qtl.Kg gms.)
Gross Weight Of Commodity (Qtl.Kg. gms)
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
76
Net Weight Of Commodity (Qtl.Kg gms.)
Business Rules and Validations:
1. Token Number to be printed must be a valid token number.
2. Date should be current date.
3. Time should be current time.
4. Tare Weight of Truck should be less than the Loaded Weight of Truck
5. Values of “Gross Weight of Commodity” and “Net Weight of Commodity” are display based
upon the values of “Loaded Weight of Truck” and “Tare Weight of Truck”.
6. All the weighment details should come from the Open xml data format. Where ever
weighbridges do not have a capability to exchange data in open data format, the weighment
details shall be manually fed at weighbridge/gate..
7. In case of Rail Siding Depot, internal movement/rail movement, truck shall be tare weight every
time.
Requirement 3#: Application should have ability to add the commodities as per unit/shed by Unit/Shed In charge.
o Unit / Shed
Unit / Shed: In Unit / Shed module, user will be provided with below details
Vehicle Challan No.
Vehicle Challan Date
Vehicle No.
Destination Depot name
Driver Name & Mobile No.
Driving License No.
Entry Date & Time
Source of Inflow
Loading Date at Source
Consigner
Consignee
Loaded Vehicle Weight as Per Weighbridge
Weight of the Commodity as per 10% Weighment Rule.
Commodity Details as Per Vehicle Challan
S. No.
Commodity Name
No. of Bags
Bag Type (BT/SBT/PP)
Quantity (Qtl.Kg gms.)
Commodity Unloaded
Commodity
Crop Year
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
77
Bag Type (BT/SBT/PP)
Issuable/Non Issuable
Category
Specification
Type of Labour
Quantity (Qtl.Kg gms.)
Gang No.
Labors Used
No. of Bags Unloaded
Type of Operation
Storage Type
Unit No.
Stack No.
Business Rules and Validations:
1. Token Number to be printed must be a valid token number.
2. Unit Shed Bag Type should be same as of vehicle challan Bag Type.
Requirement 4#: Application should have ability to add the commodity received as per Rail Movement by Depot manager
o Rail Movement - Inflow
Rail Movement - Inflow: In Rail Movement - Inflow module, user will be provided with below details
Rail Details
Special No.
Special Dispatch Depot / Station
Special Dispatch Date
Special Arrival Depot / Station
Special Arrival Date & Time
Special Release Date & Time
Commodity Received
Unit No.
Stack No.
Commodity
Crop Year
Bag Type (BT/SBT/PP)
Issuable/Non Issuable
Category
Specification
Type of Labour
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
78
Quantity (Qtl.Kg gms.)
Gang No.
Labours Used
Type of Operation
No. of Bags Loaded
Weighment Mode
Business Rules and Validations:
1. Special Indent Date should be less than or equal to today’s date.
2. Special Dispatch/Release Date should be greater than or equal to today’s date.
Requirement 5#: Ability to use the existing common master data to populate the values. To address the above requirement, below masters would be provided to the user.
Depot
Revenue District
Commodity
Bag Type (BT/SBT/PP)
Crop Year
Issuable
Category
Specification
Type of Operation
Storage Type
Weighment Mode
4.2.1.5 OUTFLOW FCI release the food grains to State agencies / parties under various schemes as per the allocation guidelines prescribed by Department of CA, F&PD. Release Order application should capture the commodity loaded and commodity unloaded details for a particular Release order/ Dispatch order Number. Following are the functional requirements
Requirement 1#: Application should have ability to add the commodities as per Release order/Dispatch No. by Gate Entry Operator.
o Gate Entry - Empty Truck
o Generate Token Number
o Gate Exit – Loaded Truck/ Empty Truck (in case of exceptions)
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
79
Gate Entry – Empty Truck: In Gate Entry – Empty Truck module, user will be provided with below details
Vehicle No.
Driving License No.
Driver Name & Mobile No.
Entry Time
Release Order/Dispatch No.
Entry Date
Consigner
Consignee
Business Rules and Validations:
1. Entry Date and time should be current.
2. Details will be populated based on Release order No. selection.
3. Dispatch No. should be entered if Release order not selected.
4. In case Dispatch No. , Rail movement or Internal Transfer should be selected.
5. In case Rail Movement Consignee will become free text to enter.
6. In case Internal Transfer Depot name should be selected.
Generate Token Number: In “Generate Token Number” section user would be able to print physical copy of the following details and token number.
Vehicle No.
Driving License No.
Driver Name & Mobile No.
Release Order/Dispatch No.
Entry Date and Time
Consigner
Consignee
Business Rules and Validations:
1. A valid token number is one as long as the truck is within the Depot premises.
2. Token Number to be printed must be a valid token number.
Gate Exit – Loaded Truck: In Gate Exit Loaded Truck user will be provided with below details
Vehicle No.
Release Order/Dispatch No.
Driver Name & Mobile No.
Driving License No.
Entry Date and Time
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
80
Consigner
Consignee
Tare Weight of Vehicle
Weighbridge Identification No.
Commodity Loaded
Unit No.
Stack No.
Commodity
Bag Type (BT/SBT/PP)
Crop year
Issuable
Category
Specification
Type of Labour
Gang No.
Labour Used
Type of Operation
No. of Bags
Quantity
Commodity Unloaded
Commodity
Crop Year
Bag Type (BT/SBT/PP)
Issuable/Non Issuable
Category
Specification
Quantity (Qtl.Kg gms.)
Added /Taken back Loose Grains
No. of Bags Unloaded
Business Rules and Validations:
1. Token Number to be printed must be a valid token number.
2. A valid token number is one as long as the truck is within the Depot premises.
3. Truck Number will be fed in running order without space.
4. Gate pass shall be prepared/generated by Unit/Shed In-charge.
5. Exit date should be current date and time.
6. Exit Gate Pass No. should be validated with generated Gate Pass No..
7. All the weighment details should come from the Open xml data format. Where ever
weighbridges do not have a capability to exchange data in open data format, the weighment
details shall be manually fed at weighbridge/gate.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
81
Requirement 2#: Application should have ability to get the weighment details by Weighbridge Operator.
o Weighbridge Room - Empty Truck
o Weighbridge Room – Loaded Truck
Weighbridge Room - Empty Truck: In Weighbridge Room - Empty Truck module user will be done weighment of the empty truck which was entered into the weighbridge room.
Vehicle No.
Destination Depot name
Driver Name & Mobile No.
Driving License No.
Entry Date
Entry Time
Consigner
Consignee
Release Order /Dispatch No.
Tare weight of vehicle
Weighbridge Identification No.
Business Rules and Validations:
1. Token Number to be printed must be a valid token number.
2. A valid token number is one as long as the truck is within the Depot premises.
3. All the weighment details should come from the Open xml data format. Where ever
weighbridges do not have a capability to exchange data in open data format, the weighment
details shall be manually fed at weighbridge/gate.
Weighbridge Room - Loaded Truck: In Weighbridge Room - Loaded Truck module user will be done weighment of the loaded truck which was entered into the weighbridge room.
Vehicle No.
Destination Depot name
Driver Name & Mobile No.
Driving License No.
Entry Date and Time
Source of Inflow
Loading Date at Source
Consigner
Consignee
Commodity Loaded
Unit No.
Stack No.
Commodity
Bag Type (BT/SBT/PP)
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
82
Crop year
Issuable
Category
Specification
Type of Labour
Gang No.
Labour Used
Type of Operation
No of Bags
Quantity
Commodity Unloaded
Commodity
Crop Year
Bag Type (BT/SBT/PP)
Issuable/Non Issuable
Category
Specification
Quantity (Qtl.Kg gms.)
Added /Taken back Loose Grains
No. of Bags Unloaded
Requirement 3#: Application should have ability to add details of the commodity (No. of bag, specification etc.) as per unit shed by Unit Shed In charge.
o Unit / Shed
o Generate Exit Gate Pass
Unit / Shed: In Unit / Shed module, user will be provided with below details
Vehicle Challan No.
Vehicle Challan Date
Vehicle No.
Destination Depot name
Driver Name & Mobile No.
Driving License No.
Entry Date and Time
Consigner
Consignee
Loaded Vehicle Weight as Per Weighbridge
Weight of the Commodity as per 10% Weighment Rule.
Commodity Loaded
Unit No.
Stack No.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
83
Commodity
Bag Type (BT/SBT/PP)
Crop year
Issuable
Category
Specification
Type of Labour
Gang No
Labour Used
Type of Operation
No. of Bags
Quantity
Commodity Loaded
Commodity
Crop Year
Bag Type (BT/SBT/PP)
Issuable/ Non Issuable
Category
Specification
Quantity (Qtl.Kg gms.)
Added /Taken back Loose Grains
No. of Bags Loaded
Business Rules and Validation:
1. Token Number to be printed must be a valid token number.
2. A valid token number is one as long as the truck is within the Depot premises.
3. Duplicate Commodity details will not be added.
Generate Gate Exit Pass: In Generate Gate Exit Pass module, user would be able to generate the physical copy of the commodity details, commodity loaded details, token number and gate exit pass.
Vehicle No.
Destination Depot name
Driver Name & Mobile No.
Driving License No.
Entry Date and Time
Consigner
Consignee
Tare weight of Vehicle
Weighbridge Instrument No.
Commodity Details
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
84
S No.
Unit No.
Stack No.
Commodity Name
No. of Bags
Quantity (Qtl.Kg gms.)
Commodity Unloaded (Loose Grains Loaded/Taken back)
S No
Commodity
Bag Type (BT/SBT/PP)
Quantity (Qtl.Kg gms.)
No. of Bags loaded
Business Rules and Validations:
1. Token Number to be printed must be a valid token number.
2. Truck Number will be fed in running order without space.
3. Gate pass shall be prepared/generated by Unit/Shed In-charge.
Requirement 4#: Application should have ability to take action on Release Order/Dispatch Order in case of exigencies like Initiation of RO Diversion, Closing of RO, Re-weighment etc..
o Depot Manager - Outflow
Depot Manager - Outflow: In Depot manager - outflow module, user will be provided with below details
Review pending details grid
Token No.
Release Order No.
Release Order Date
Entry Date Time
Amount
Business Rules and Validations:
1. The list of Release Orders against which action has already been taken shall not be available to
the depot manager.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
85
4.2.1.6 DIVERSION In case of stock unavailability or where stock can’t be lifted from designated depot, Commercial section of FCI District office diverts the Release Order to any feasible depot within same FCI district. In case Release Order needs to be diverted to any depot beyond the FCI district, Regional office authorizes the Release Order diversion to any depot of other district. User would be provided with below sub- modules under Diversion:
o Manage RO diversion
Below are the functional requirements for Manage RO Diversion:
Requirement 1#: Ability to view the Diverted Release Orders along with associated FAP receipt Solution: Under Manage RO Diversion, user would be able to view the below details related to diverted Release orders:
S.No.
RO No.
RO Creation Date
RO Approval Date
RO Validity Date
State Agency/Party
RO Quantity (Qtl.kg gms)
Quantity Lifted (Qtl.kg gms)
Unlifted Quantity (Qtl.kg gms)
Amount
FAP Receipt: Clicking on “FAP receipt” button, user would be able to view the FAP receipt of
the corresponding diverted release order
Business Rule and Validation: 1. In case of release order validity expiry, same release order should not be shown under Release order list Requirement 2#: Ability to divert a release order Solution: To address the above requirement, user would perform below operation:
Selecting the values from “RO Diversion Type” field
Entering IOG No.
Entering Remarks
Post entering the above details, user would be able to start the process of release order diversion.
In “Manage RO Diversion”, the user would also be provided with options saying “Awaiting Approval” as well as “Approved”.
a. Awaiting Approval: User would be able to find list of awaiting RO diverted list for his/her approval.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
86
b. Approved: User would be able to see all the approved RO by him/her.
Note: User would also be able to see the release order details by clicking “View Release Order Details”.
Business Rules and Validation:
1. IOG No. field should be populated only when RO Diversion Type is selected as “Diversion within
FCI District” and “Diversion to another FCI district outside region”
o Create New Release Order
In Create New Release Order, user can view all approved diverted RO list in dropdown where he/she can create new release order (RO No. will same) against Diverted RO and RO will be assigned to new FCI depot for off take. Requirement 1#: Ability to assign a new FCI depot for off take against a commodity Solution: To address this requirement, system would provide depot dropdown for commodity off-take Business Rules and Validation: 1. Quantity should not be greater than the Balance Quantity against that diverted RO
4.2.1.7 EXTENSION State agency/party shall request for extension, if the State agency/party fails to lift the commodity in the validity period of Release Order. Extension module has below sub modules:
o Manage RO Extension
o Extend RO
o View RO
Following are the functional requirements of the Release Order extension process. Requirement 1#: Ability to extend the validity date of expired Release Order by indenter, Approve or Reject the RO Extension request by Area Manager or General Manager. Solution: To address the above requirement, “Manage RO Extension”, “Extend RO” and “View RO” modules would be provided to the user. Those users having permission to access Manage RO Extension, Extend RO and View RO module would log in the application and request for extension and approve or reject that request. User would be provided with below details
o Manage RO Extension: In Manage RO Extension module user will be provided with below details
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
87
Release Order List
S. No.
RO No.
RO Creation Date
RO Approval Date
RO Validity Date
RO Quantity (Qtl.kg gms)
Quantity Lifted (Qtl.kg gms)
Unlifted Quantity (Qtl.kg gms)
Deposited Amount
RO Extension Status and Authority
RO Extension Validity date
Awaiting Approval
S. No.
RO No.
RO Creation Date
RO Approval Date
RO Validity Date
State Agency / Party
RO Quantity (Qtl.kg gms)
Quantity Lifted (Qtl.kg gms)
Unlifted Quantity (Qtl.kg gms)
Deposited Amount
Extension Request Date
Approved
S. No.
RO No.
RO Creation Date
RO Approval Date
RO Validity Date
State Agency / Party
Deposited Amount
Extend RO Approval Date and Authority
RO Extension Validity date
o Extend RO: In Extend RO module user will be provided with below details
Release Order Details
FAP Approved Indent No.
State Allocation Month & Year
FCI District
FCI Depot for Off-take
Release Order No.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
88
Release Order Date
State Agency/ Party
Issued to Revenue District
Release Order Validity
RO Quantity
Quantity Lifted
Unlifted Quantity
Schemes Indented By State Agency / Party Details
Central Scheme Name
Commodity
Quantity
CIP/Rate(Rs./Qtl.Kg gms)
Cost Of Food Grains
Release Order Commodity
S.No.
Commodity Name
Central Scheme Name
CIP/Rate(Rs./Qtl.Kg gms)
Quantity (Qtl.Kg gms.)
Amount
Deduction Based on Indent Submitted by State Agency / Party
S.No.
Deduction Details
Amount
Release Order Cost
S.No.
Commodity Name
Central Scheme Name
CIP/Rate(Rs./Qtl.Kg gms)
Quantity (Qtl.Kg gms.)
Amount
Release Order Extension
No. of days
Remarks
Business Rules and Validation: For PDS/OWS 1. FCI Area Manager will not have power to extend the RO.
2. GM (Region) can extend the RO up to first 15 days including processing period. 2. ED (Zone) can extend the RO up to next 15 days (16th to 30th Day) including processing period.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
89
3. Ministry can extend the RO after the 30th day for no limit. 4. Remarks should be entered by the designated officers for not lifting the commodity by extended time.
For OMSS 1. Will be governed as per MTF.
o View RO: In Extend RO module user will be provided with below details
Release Order Details
FAP Approved Indent No.
State Allocation Month & Year
FCI District
FCI Depot for Off-take
Release Order No.
Release Order Date
State Agency/ Party
Issued to Revenue District
Release Order Validity
RO Quantity
Quantity Lifted
Unlifted Quantity
Schemes Indented By State Agency / Party Details
Central Scheme Name
Commodity
Quantity
CIP/Rate(Rs./Qtl.Kg gms)
Cost Of Food Grains
Release Order Commodity
S.No.
Commodity Name
Central Scheme Name
CIP/Rate(Rs./Qtl.Kg gms)
Quantity (Qtl.Kg gms.)
Amount
Deduction Based on Indent Submitted by State Agency / Party
S.No.
Deduction Details
Amount
Release Order Cost
S.No.
Commodity Name
Central Scheme Name
CIP/Rate(Rs./Qtl.Kg gms)
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
90
Quantity (Qtl.Kg gms.)
Amount
Release Order Extension
Release Order Validity Date
RO Extension Requested Days
Action(Approve/Reject)
RO Extension Validity Date
Remarks
Business Rules and Validation:
1. Ability to select Action(Approve/Reject),
2. Validity will be defined as per MTF.
Requirement 2#: Ability to send an e-Mail/SMS to concerned officers once the Release Order is digitized or captured from external applications. Solution: To address the above requirement e-Mail/SMS would facility would be integrated with Release order application and e-mails/SMS would be shared to related authorities on any action.
4.2.1.8 STOCK PROCESSING
Unit Shed In charge shall Upgrade/Downgrade of the commodities. Following are the functional requirements for the Upgrade/Downgrade or Gain/Loss process
Requirement 1#: Ability to Upgrade/Downgrade of the commodities by Unit Shed Incharge.
o Upgrade/Downgrade
o Gain/Loss
To address the above requirement “Upgrade/Downgrade” and “Gain/Loss” modules would be provided to the user. Those users having permission to access Upgrade/Downgrade and Gain/Loss module would log in the application with valid credential and Upgrade/Downgrade or Gain/Loss of the commodities. User would be provided with below details
Upgrade/Downgrade: In Upgrade/Downgrade module of Stock Processes user will be provided with below details
Upgrade/Downgrade – Adding
Storage Type
Unit No.
Stack No.
Commodity
Crop Year
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
91
Bag Type (BT/SBT/PP)
No. of Bags
Issuable?
Category
Specification
Quantity
Business Rules and Validation:
1. Ability to select Storage Type, Unit No., Stack No., Commodity, Crop Year, Bag Type
Issuable?, Category, Specification.
2. Ability to enter No. of Bags, Quantity.
Upgrade/Downgrade – Editing
Storage Type
Unit No.
Stack No.
Commodity
Crop Year
Bag Type (BT/SBT/PP)
No. of Bags
Issuable?
Category
Specification
Quantity
Business Rules and Validations: 1. Ability to select Storage Type, Unit No., Stack No., select Bag Type Issuable?, Category, Specification.
Gain/Loss: In Gain/Loss module of Stock Processes user will be provided with below details
Gain/Loss – Adding
Storage Type
Unit No.
Stack No.
Gain / Loss Type
Commodity
Crop Year
Bag Type (BT/SBT/PP)
Category
Specification
Issuable?
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
92
No. of Bags
Quantity
Business Rules and Validations:
1. Ability to select Storage Type, Unit No., Stack No., Commodity, Crop Year, Bag Type, Category,
Specification, Issuable?.
2. Ability to enter No. of Bags, Quantity.
Gain/Loss – Editing
Storage Type
Unit No.
Stack No.
Gain / Loss Type
Commodity
Crop Year
Bag Type (BT/SBT/PP)
Category
Specification
Issuable?
No. of Bags
Quantity
Business Rules and Validations:
1. Ability to select Storage Type, Unit No., Stack No., Bag Type, Category, Specification, Issuable?.
4.2.1.9 NCDEX RO NCDEX RO is used to create a release order against the tendered commodity (OMMS (D)). Requirement #1:
Create NCDEX RO: concern user can see this option and create a new NCDEX for particular party, FCI dist and FCI depot for off take. Scheme group will be the OMMS (D) only. And capture payment details also.
NCDEX Release Order No.
NCDEX Release Order Date
FCI District
FCI Depot for Off-take
Release Order No.
NCDEX RO Validity Date
State Agency / Party
Scheme Group
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
93
Scheme Name
Commodity Name
Rate(Rs./Qtl)
Quantity (Qtl.Kg gms.)
Amount
Payment Mode
Payment Date
Payment Instrument No.
Amount paid
Bank Name
Branch Name
IFSC Code
Upload NCDEX RO
Business Rule and Validations:
1. Release Order No. : Combination of NCDEX/RO/FCI depot Code/Running No. Ex :
NCDEX/RO/NG19002/00003
2. Only OMSS scheme group is available for NCDEX RO.
3. Digital signature will be mandatory for NCDEX RO.
4. No Payment verification from FAP Application is required as RO is already generated.
Requirement #2:
After creating the NCDEX RO, The same release order will appear for approval to the concern user. He will either approve or reject with approval/Rejection remarks.
NCDEX RO No.
NCDEX RO Creation Date
NCDEX RO Validity Date
RO No.
Party Name
Amount
After viewing particular record: user can approve as well as reject
4.2.1.10 RO REIMBURSEMENT All the balance quantity or amount paid by state agency or party for which commodity has not been lifted can go for reimbursement the amount of the balance or whole quantity. Quarterly report of such expenditure will be presented in the FCI Board. Business Rule and Validation:
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
94
1. Payment has to verify from FAP and lifted quantity against the payment has to verify from the RO
application.
2. During reimbursement amount should not be excess from the amount of balance quantity.
3. After successful reimbursement of a release order the same has to close by district officer.
4.2.2 DATA EXCHANGE ENGINE Data Exchange engine is responsible for implementing the business functionality to transfer the information between the proposed Release Order application with other external applications to perform the Release Order operations. It allows maintaining the data consistency and uniformity between all the applications. Data exchange engine module talks about linking the external applications with Release Order application. Following are requirements to implement the data exchange module.
1. To identify the data exchange parameters.
2. Data exchange bi-directional/uni-directional.
3. Data exchange approaches
a. Backend database scripts
b. XML web services
c. simple flat/CSV file
d. Any other open data format
4. Database Sync Requirements
a. Time period
b. online/offline
c. Communication technology
Release Order application shall be linked with existing external applications to perform the Release Order operations workflow.
1. FAP - Financial Accounting Package – For creation of invoices in FAP. Data will be consumed by FAP
application through XML web services in consultation with FAP/FAP vendor (which is maintaining the FAP
Application) after finalization of Release Order Application SRS.
2. FEAST – Food and Essential Commodities Assurance & Security Target – To handle the State level allocation
details for the TPDS schemes
3. SIMS – Stakeholder Inventory Management System – To get the State agency officers details for TPDS
schemes.
4. DCMS – Depot Code Management System - To find the active depots in the FCI District.
5. IRRS - IISFM Rapid Reporting Services – To get the depot wise stock positions details.
6. Integration with Weighbridge - to handle the inflow and outflow stocks management in Depot.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
95
4.2.3 WEB PORTAL The development of web portal for Release Order Application means creating a website in which the management of all Release Order operations could be done online. This portal is designed using industry standard .Net technologies with MS SQL Server as a backend database. Web Portal, is an online reporting with executive dashboard application which allows stakeholders to perform the Release Order tasks. It allows the users to track and monitor the Release Order status online. It includes following components
1. GUI Screens to perform the Release Order Operations online
2. Executive Dashboard for overall portal administration and configuration
User Management.
Schemes based State/Revenue District wise allocations.
Depot/FCI District/Revenue District/State/Zone/Country wise Stock Positions.
Status of the Release Orders and off take against the Release Orders.
Schemes details along with CIP and validity period etc.,
3. Online Reports to track and view the Release Order Operations.
Allocation – State, Revenue and FCI District-wise.
Indent Generation Reports Release Order Generation Reports.
Release Order Progress Reports.
Online stock lifting Status Reports against the Release Orders.
Release Order Exceptional Reports – (Diversion, Extension and Reimbursement Reports).
Daily Release Order Deposit.
Scheme Commodity wise Issues.
Release Orders between Dates.
Scheme & Commodity wise Issues Summary.
Scheme wise Issues.
Single RO Scheme wise Issues Commodity wise.
Statement of Issue Date wise.
4.2.3.1 FUNCTIONAL REQUIREMENTS
1. Web Portal shall be built on a multi-tiered, distributed architecture, including object-oriented design, event-
driven programming design, and transaction-based processing.
2. Ability to create, edit and view different user groups. A user group is assigned privileges of reading, writing
application resources, e.g. user management screen, information entry screen etc.
3. Ability to create a new system user in an already created group and then to edit and view the user
information.
4. Allows administrators to easily manage users and groups through a GUI interface.
5. Ability to provide login and logout facility to multiple concurrent users (this will be a multi user application).
6. Ability to authenticate and provide confined view to the user as per permitted privileges.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
96
7. Single-Sign On (SSO) facility
8. Customized view based on the user access levels.
9. Support Unicode compatibility.
10. The proposed system should provide relevant prompts to available commands or actions on every screen.
11. The system should have Instructions for receiving help and for quitting from the system should appear on
every screen.
12. The portal will be compatible with the hardware and software used for this purpose.
13. The system will facilitate the administrator to use pre-defied access levels to assign format of reports at
different levels.
14. The system should have the ability auto populate the relevant parameters of any given parameter once it’s
fed or selected in the form. For Eg. If Release Order Number is generated which is used in a form then all the
related fields on the form, which already persist in the database, should populate automatically.
15. The system must have the ability to generate a unique Release Order number automatically.
16. The system should generate the following physical documents in PDF format and store it in the backend
system and be accessible/ download/print the same on need basis.
a. Indent Letter
b. Release Order generation document in PDF format
c. Release Order closing document with daily lifted depot and quantity details
d. Release Order cancelled document
e. Release Order diversion document
f. Release Order Reimbursement Document
g. Delivery/Issue Planning Sheet
h. Weight Check Memo and M-form
i. Inward Gate Pass
j. outward Gate pass
17. This system must have the ability to determine the current process of the Release Order
18. The system must have the ability to generate separate views based on the User Roles and access rights. The
type of web pages displayed will depend upon the access rights given to them. The System should directly
launch the required page.
19. The system must have the ability to perform analysis reports based on the history data and should perform
and make predictions in advance accordingly.
20. The system must have the ability to automate information regarding inbound and outbound trucks and the
quantities that they are carrying.
21. The system must have the ability to update stocks on daily basis.
22. The system must have the ability to maintain record of the transactions pertaining to Release Order based
on the Quantity lifted.
23. The system must have the ability to provide the reports based on the Scheme wise and commodity wise
based on the State Agency/Party.
24. The system must have the ability provide required information to the State Agencies and Parties.
25. The system must have ability to generate notifications against delay in the Release order operations.
26. The system must have the ability to maintain audit trail and keep track of each other’s activities and actions
being performed within the system.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
97
27. The system must be able to provide search the database according to the search as per the criteria specified
by the user.
28. The system must have the ability to generate progress reports statements for the selected period (i.e Daily,
Weekly, Monthly and Yearly etc).
29. The system must have the ability to generate progressive reports.
30. The system must have the ability to capture the transactional data for weighbridge from Weighbridge
software.
31. The system must have the ability to print the physical document through portal.
32. The system must have the ability to send print out report in pre-defined format.
33. The system must have the ability to enter, update the information of parties / State Agencies details on
need basis.
34. The system shall utilize the already available information either from Release Order or access it from the
external applications.
4.2.3.2 USER INTERFACE REQUIREMENTS The users from different stakeholders also can access the Release Order Portal online using any web browser. Only the registered users can access the portal based on the access rights and user credentials. The proposed Portal should meet global standards in best practices, design and functionality. The portal should comply with the following standards
Guidelines for Indian Government websites MDDS – Demographic Metadata and data standards Localization standards W3C standards level 2 The portal should be accessible and operational from web enabled devices like Laptops, tablets and smart
phones etc.
Connectivity Requirements to access the application
• To access the Release Order portal, internet connectivity will be needed at both server side as well as client side.
• Communication between the systems is mandatory for data exchange between the Release Order applications and the external applications and vice versa.
• SMS Gateway Server Along with this, the application should have the connectivity to the portal will interact with the SMS Gateway server to push SMS to different stakeholders
• Email servers to send the automated emails generated from the system to various stakeholders of the system.
• Connectivity to the external applications
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
98
Below are the user interfaces for Release Order application:
Figure 15: Login Page
Figure 16: Dashboard
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
99
Figure 17: State Wise Allocation Page
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
100
Figure 18: Add New Revenue District Wise Allocation Page
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
101
Figure 19: Update Revenue District Wise Allocation Page
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
102
Figure 20: Generate Indent
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
103
Figure 21: Indent Approval
Figure 22: Make Payment
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
104
Figure 23: Make Offline Payment
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
105
Figure 24: Pending for FAP Approval
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
106
Figure 25: Approve Indent by Sales
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
107
Figure 26: Release Order Creation
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
108
Figure 27: Release Order Approval
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
109
Figure 28: Gate Entry Token No.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
110
Figure 29: Inflow Token No.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
111
Figure 30: Weighbridge - Loaded Truck (Inflow)
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
112
Figure 31: Unit/Shed In-charge (Inflow)
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
113
Figure 32: Generate Gate Pass (Exit)
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
114
Figure 33: Empty Truck (Inflow)
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
115
Figure 34: Gate Exit (Inflow)
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
116
Figure 35: Empty Vehicle (Outflow)
Figure 36: Generate Token
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
117
Figure 37: Gate Exit Loaded Truck
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
118
Figure 38: Depot Manager Review & Approval
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
119
Figure 39: RO Diversion
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
120
Figure 40: RO Extension
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
121
Figure 41: NCDEX Release Order Digitization
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
122
Figure 42: NCDEX RO Approval
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
123
Figure 43: FAP Verification
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
124
Figure 44: Upgrade/Downgrade
Figure 45: Gain/Loss
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
125
Below are the Reports:
Figure 46: Daily Deposit
Figure 47: FAP Approval
Figure 48: Gate Operator Inflow
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
126
Figure 49: Gate Operator Outflow
Figure 50: Indent Approver
Figure 51: Area Sales Manager Report
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
127
Figure 52: Indent Report
Figure 53: Release Order between Dates
Figure 54: Release Order Approver
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
128
Figure 55: Release Order Creator
Figure 56: Scheme Commodity Wise Issue
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
129
Figure 57: Scheme Commodity Wise Issue Summary
Figure 58: Scheme Wise Issue
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
130
Figure 59: Issues off take
Figure 60: Statement of Issue
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
131
4.2.3.3 GENERAL REQUIREMENTS This section talks about the general (non functional) requirements for the proposed Release Order application.
1. User Rights and Security Management
Control all the authorized users with their assigned rights and only authorized users can login to the
portal and perform the tasks that the administrator of the portal has allowed from menu-level up to the
button level (add, edit, delete, print, post and view etc.)
Authentication of a user to a secure Web site via the Secure Sockets Layer (SSL) protocol with 128 bits
encryption technique.
Access level of each user shall be defined at the time of creating the user.
2. Performance
Background processes, reporting, data loading, data integrity checking, data backup operations etc
should not take a toll on the performance of the system.
System should perform optimally during normal and peak workloads.
The system must be designed for less than 1% downtime at normal load.
3. Operations, Backup and Recovery
Mechanisms and techniques to must be devised to guard against unintentional loss of data. If necessary,
full data recovery must be made possible as and when required.
4. The system should have an emergency / contingency plan during failures.
5. Online Monitoring and Logging
For the purpose of trouble shooting and performance analysis, authorized members activity log
mechanism must be incorporated in the system.
The system must be able to identify and reveal which individual has modified, added or deleted any data
within any part of the system. This feature generates a comprehensive log of all actions under taken by
various users. This trail ensures all information in the system is secure and can be used for accountability
and proper monitoring of the system.
4.2.4 DATABASE REQUIREMENTS
A Release Order database is responsible for storing the data pertaining to release order application. Release Order application uses the MS SQL as a backend system
Following are the identified requirements to create the Database for Release Order Application
4.2.4.1 DETERMINE THE TABLES
Following are the proposed design guidelines to generate the tables for the Release Order application.
Table should not contain duplicate information, and information should not be duplicated between tables (e.g. Store the user details name, in only one table and can be accessed from other tables based on user id key).
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
132
When each piece of information is stored in only one table, application shall update it in one place. This is more efficient, and also eliminates the possibility of duplicate entries that contain different information.
Design tables without redundant data. Choose appropriate data types for fields. It saves not only space in database and also handles the data
validation checks. Create indexes for fields you sort, join, or set criteria for faster retrieval.
4.2.4.2 DETERMINE THE FIELDS YOU NEED IN THE TABLES
Once the tables are identified the fields required can be determined. When sketching out the fields for each table, keep following tips in mind:
Relate each field directly to the table. Determine the data types and sizes for the identified fields. Don't include derived or calculated data (data that is the result of an expression). Include only the specific information you need.
4.2.4.3 IDENTIFY FIELDS WITH UNIQUE VALUES
There are three kinds of primary keys that can be defined:
AutoNumber primary keys - An AutoNumber field can be set to automatically enter a sequential number as each record is added to the table. Designating such a field as the primary key for a table is the simplest way to create a primary key.
Single-field primary keys - If you have a field that contains unique and not null values such as unique serial numbers or part numbers, you can designate that field as the primary key. The primary key field should not allow the NULL values.
Multiple-field primary keys - In situations where you can't guarantee the uniqueness of any single field, you may be able to designate two or more fields as the primary key. The most common situation where this arises is in the table used to relate two other tables in a many-to-many relationship
4.2.4.4 NORMALIZATION
Normalization is a complex process with many specific rules and different levels intensity. In its full definition, normalization is the process of discarding repeating groups, minimizing redundancy. In simple terms, the rules for normalization can be summed up in a single phrase: "Each attribute (column) must be a fact about the key, the whole key, and nothing but the key." Said another way, each table should describe only one type of entity (such as a release order, commodity, or scheme). Some normalization benefits are:
Data integrity (because there is no redundant, neglected data). Optimized queries (because normalized tables produce rapid, efficient joins). Faster index creation and sorting (because the tables have fewer columns). Faster UPDATE performance (because there are fewer indexes per table). Improved concurrency resolution (because table locks will affect less data).
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
133
4.2.4.5 DETERMINE THE RELATIONSHIPS BETWEEN TABLES
Once the tables and primary key fields are identified, the related information can place together in meaningful ways.
To do this, define relationships between tables. Relationship is an association between common fields (columns) in two tables. A relationship works by matching data in key fields. In most cases, these matching fields are the primary key from one table, which provides a unique identifier for each record, and a foreign key in the other table.
Relationships between tables are grouped into 4 groups:
o One-to-one (1:1) - each record in Table A can have only one matching record in Table B, and each record in Table B can have only one matching record in Table A. This type of relationship is not common and it is very rarely used in database systems, but it can be very useful way to link two tables together. The information related in this way could be in one table. However, you might use a one-to-one relationship to divide a table with many fields in order to isolate part of a table for security reasons, or to store information that applies only to a subset of the main table, or for efficient use of space. A one-to-one relationship is created if both of the related fields are primary keys or have unique indexes.
o One-to-many (1:M) - is the most common type of relationship and it is used to relate one record in a table with many records in another table. In a one-to-many relationship, a record (parent) in Table A can have many matching records (children) in Table B, but a record (child) in Table B has only one matching record (parent) in Table A. This kind of relationship is created if only one of the related fields is a primary key or has a unique index.
o Many-to-one (M:1) - is used to relate many records in a table with only one (single) record in another table. It is often called the lookup table relationship. Normally, this kind of relationship is not based on a primary key field in either table. Although in theory this relationship is one-to-one, it is known as many-to-one because it does not use a primary key field for the link, and many records from the primary table link to a single record in another table.
o Many-to-many (M:M) - is used to relate many records in a table with many records in another table. A record (parent) in Table A can have many matching records (children) in Table B, and a record (child) in Table B can have many matching records (parents) in Table A. It is the hardest relationship to understand and it is not correct. By breaking it into two one-to-many relationships and creating a new (junction/link) table to stand between the two existing tables (e.g. whose primary key may consist of two fields - the foreign keys from both tables A and B) will enable correct and appropriate relationship setting. A many-to-many relationship is really two one-to-many relationships with a junction/link table.
4.2.4.6 CREATE MASTERS DATA AND BASIC DATA TO RUN THE APPLICATION
Develop the scripts to have the basic data to run the application like (users, schemes, party names, commodities etc) which can be done initially for test environment and can be replicate it to production environment.
Master Data
o Allocation Masters
o Scheme Masters
o Commodity Masters
o FCI District vs Revenue District Mapping Masters
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
134
o Location wise Project Stakeholder Masters
Head Office
Zonal
Regional/State
FCI District
Depot
User Data
Transactional Data
4.2.4.7 IDENTIFY SHARING FIELDS
To check the external application schema including the tables fields and relationships
Identify the data exchange fields and formats
Design the scheme accordingly
4.2.4.8 BACKUP & MAINTENANCE
The application should take the backups to avoid the loss of the data in case of system failure
1. Data backup – daily – full/Incremental
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
135
4.3 BEHAVIORAL REQUIREMENTS – SYSTEM LEVEL
4.3.1 USE CASE VIEW
4.3.1.1 RELEASE ORDER PROCESS
ACTORS RELEASE ORDER PROCESS STEPS
Ministry CA&PDS
GOI
FCI Regional Office
FCI District Office
FCI Depot Office
FCI Zonal Office
Allocation
State Agencies/
Parties
Indent Generation
Payment Confirmation Depot Assignment
Release Order Creation
Delivery Plan Weighment
Commodity Issue Commodity Lifting
Request Approve/Reject
Request Reimbursement
Request Approve/Reject
30 Days
RO Initiation
RO Generation
RO Execution
RO Extension
RO Reimbursement
RO Diversion
Kill RO
RO Closing
> 30 Days
15 Days
Close RO
Figure 61: Use Case Release Order Process
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
136
4.3.1.2 RELEASE ORDER INITIATION
ACTORS ACTORSRELEASE ORDER INITIATION
Add state level Allocation Details along with Issue
Price based allocation orders and guidelines
Update the existing State Level Allocation Details
along with Issue Price according to new new
guidelines given by CA,PDS, GOI
Cancel the schemes/allocations if GOI cancel the
scheme/allocations
STATE LEVEL ALLOCATIONS
Add Revenue district wise allocations based on the
details provided by state agencies/parties
Update the existing Revenue District level allocations
with Issue Price according to new guidelines given by
CA,PDS, GOI
Cancel the schemes/allocations if GOI cancel the
scheme/allocations
Generate the Indent with Scheme and
Commodity along with Bank Details
Approve by FCI Accounts section
Make the payment in bank and enter the
Payment Details
Prepare the allocation requirements based on
the demand and map it to actual GOI
allocations
Select the party enter the payment details
into FAP
Validate the payment Details with the Bank
online and Approve and Email/SMS Sent to
the Respective Parties
Validate Actual allocations with Requested
Allocations
Approve
Approve
INDENT GENERATION
INDENT APPROVAL
REVENDUE DISTRICT WISE
ALLOCATIONS
Approved
Indent
Indent
Generation
E Mail
SMS
Reject
Reject
FAP Online
Ministry CA&PDS
GOI / FCI
Regional Office
FCI Regional Office
State Agency /
Party
FCI District Office
Sales Section
FCI District Office
Accounts Section
Verify
Figure 62: Use Case Release Order Initiation
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
137
4.3.1.3 RELEASE ORDER GENERATION
ACTORS ACTORSRELEASE ORDER GENERATION
Selects the Designated Depot using DCMS
Assigned the Depot based
on Stocks Availability using IRRS
Generate the Release Order
RELEASE ORDER CREATION
Check the Party, Payment and Commodity Details
Approve the Release Order
Digitally Signed Release Order
Yes
Yes
RELASE ORDER APPROVAL
DCMS
IRRS
FCI Sales Section
FCI District
Area Manager
Retrieve Depot
Details ( DB Scripts)
Retrieve Stocks
Details – DB Scripts
FCI Depot
State Agency / Party
FCI Depot
FCI District Office
Sales Section
Digitally Singed Release
Order is Generated
Reject
Update RO
(DB Scripts)
E Mail
SMS
Email to OfficersSMS to
Officers
Figure 63: Use Case Release Order Generation
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
138
4.3.1.4 RELEASE ORDER EXECUTION
ACTORS ACTORSRELEASE ORDER EXECUTION
Generate the Delivery
Plan Sheet
Generate the Inward
Gate Pass
Capture the Truck Tare
Weight from Weigh
bridge
IRRS
Depot Manager
Weighbridge In-Charge
Step 1
Step3 Step 8
FCI Depot
State Agency / Party
FCI Depot
FCI District Office
Sales Section
Updated RO with Lifted
Quantity
Update Stocks
(DB Scripts)
E MailSMS
Email to Officers SMS to Officers
Gate Incharge
Inward
Gate Pass
Delivery
Plan Sheet
Weighbridge
Software
CSV/Serial
Connectivity
Inward Weight
Receipt
Step 2
Unit Incharge
Step 4
Assign and Validate the
Lifted quantity
Capture the Gross
Weight of Truck
Step 6
Step 5 CSV/Serial
Connectivity
Check the lifted Weight
Vs loaded weight on the
Truck
Step 7
Step 8 - Gain/Loss
Quantity Can be adjusted
Continue the RO Execution Steps 1 to Step 9 till all the
quantity against Release Order is lifted
FEAST
Update Stocks
(DB Scripts)
Freeze the lifted Quantity
Aggregate lifted Stocks
On Daily basis
Step 9
Weight Check
Memo
Outward
Gate Pass
Figure 64: Use Case Release Order Execution
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
139
4.3.1.5 RELEASE ORDER CLOSING & OTHER SCENARIOS
ACTORS ACTORSRELEASE ORDER EXECUTION
Generate the Delivery
Plan Sheet
Generate the Inward
Gate Pass
Capture the Truck Tare
Weight from Weigh
bridge
IRRS
Depot Manager
Weighbridge In-Charge
Step 1
Step3 Step 8
FCI Depot
State Agency / Party
FCI Depot
FCI District Office
Sales Section
Updated RO with Lifted
Quantity
Update Stocks
(DB Scripts)
E MailSMS
Email to Officers SMS to Officers
Gate Incharge
Inward
Gate Pass
Delivery
Plan Sheet
Weighbridge
Software
CSV/Serial
Connectivity
Inward Weight
Receipt
Step 2
Unit Incharge
Step 4
Assign and Validate the
Lifted quantity
Capture the Gross
Weight of Truck
Step 6
Step 5 CSV/Serial
Connectivity
Check the lifted Weight
Vs loaded weight on the
Truck
Step 7
Step 8 - Gain/Loss
Quantity Can be adjusted
Continue the RO Execution Steps 1 to Step 9 till all the
quantity against Release Order is lifted
FEAST
Update Stocks
(DB Scripts)
Freeze the lifted Quantity
Aggregate lifted Stocks
On Daily basis
Step 9
Weight Check
Memo
Outward
Gate Pass
Figure 65: RO Closing & Other Scenarios
5. NON FUNCTIONAL REQUIREMENTS This section talks about the non functional requirements of the proposed release order application.
5.1 PERFORMANCE REQUIREMENTS Performance is defined as the responsiveness. Release Order Application should manage the user load and response time. The response time for average network connectivity speed should be as follows:
90% of the responses for static web pages should be within 2 seconds. 5-10 second: For user operation on data (for e.g. sorting of data in a column) or (5 to 50 records per page up
to max of 100,000 records) 10-20 second: For user awaiting response from the system upon executing a transaction (for e.g. a
query/update). 1 minute – Unacceptable response time
It would be the key challenge is that its interact with the external applications to perform the Release Order Operations The proposed solution should take care of the application level performance requirement by do the data
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
140
sync like caching technique. The size of pages should be such that even on low bandwidth internet connections response time should be satisfactory. Following are few guiding principles but not limited to that Releaser Order Application should adhere in order to achieve high performance
Most of the application level logging should be disabled in production code. (Only Critical level logs are maintained in the production environment to improve the performance). In test environment keep all the logs.
Code should be optimized in the performance testing phase before deploying in production environment.
5.2 SAFETY AND SECURITY REQUIREMENTS In order to maintain the highest levels of security and privacy of the data, the following requirements to be considered:
Application and data access strictly as per the user/group/role based access controls and password
protection.
Maintain the access controls based on the user levels.
Password security at operating System level and application level.
Access control and rights and authorization levels.
Provision for digitally sign Release Order to ensure security.
Protection against virus threats, Intruders, Trojans and other security threats.
5.3 SOFTWARE QUALITY ATTRIBUTES
5.3.1 HIGH AVAILABILITY High availability refers to a system or component that is continuously operational for a desirably long length of time.
5.3.1.1 INFRASTRUCTURE LEVEL – NIC To achieve the high availability of following components are to be ensured.
Network elements such as routers, gateways etc. firewalls load balancers/dispatchers
5.3.1.2 SOFTWARE LEVEL Following are proposed guidelines to achieve the high availability of the Release Order application
All file names should be relative Do not hardcode IP addresses Do not bind anything with 'local host' Minimize amount of data saved in 'http session object' Do not use static variables Do not perform write operations on external files
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
141
5.3.2 SCALABILITY Scalability is the ability of a system, network, or process, to handle growing amount of load in a Release Order Application Following measures of scalability to be consider while developing the proposed Release Order application. Administrative scalability: Number of stakeholder organizations may increase in future Functional scalability: New functionality may be needed to be added Geographic scalability: Extended it to more depots or offices may be added in future Load scalability: Number of users may increase To address the scalability challenge, the modular design will be adopted. Proposed architecture will use Service Oriented Architecture (SOA). Interactions among the various services and integration with the existing application will be achieved using XML open standards. T The proposed solution should adhere to following are few principles in order to achieve scalability
• Make software and layout design highly modular.
• The solution should be developed using layered architecture with components spread across different
architectural layers.
• Make the client component as thin as possible to serve the end user requests in faster and efficient manner.
• In the data layer, to serve the data requests in parallel, multiple instances of database must be deployed.
Based on the load and other parameters, done can plan the clustering of underlying data sources.
• The data archival and purging based on the requirement will also improve the scalability of the application.
5.3.3 INTEROPERABILITY Interoperability is the ability of diverse systems and organizations to work together (interoperate). Interoperability is a property of a product or system, whose interfaces are completely understood, to work with other products or systems, present or future, without any restricted access or implementation. The interfaces of Release Order application should be properly exposed to make it interoperable. The proposed architecture of Release Order Application is built around the web services standard and adopts open data exchange standards for interacting with various applications to address the interoperability requirement. Interoperability also means the ability of software to work on different browsers adhering to standards.
• The Release Order Application should follow standard technologies and techniques, data models and
interfaces.
• Meta data and application standards must be taken into account from the inception of the Release
Order Application.
• Vendor-specific extensions to the standard Web technologies (XHTML, HTML, JavaScript) and plug-ins
should be avoided.
• Distributed search of site may use page-level Meta tags, a site map and/or site search tool.
• External interfaces transactions should be logged.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
142
• use Web services to integrate with existing applications
• The application should work with most common Operating systems, web browsers, and access devices
like computers, laptops and mobiles.
5.3.4 USABILITY Usability is a quality attribute that assesses how easy user interfaces are to use. The proposed application should be easy to use. Usability is defined by following quality components:
• Learnability - How easy is it for users to accomplish basic tasks the first time they encounter the design?
• Efficiency - Once users have learned the design, how quickly can they perform tasks?
• Memorability -When users return to the design after a period of not using it, how easily can they
reestablish proficiency?
• Errors - How many errors do users make, how severe are these errors, and how easily can they recover
from the errors?
• Satisfaction- Make the application more modular
• Use relative font size so that a user can easily change overall font size from the browser interface.
• Release Order Application should function even with simple JavaScript and CSS.
• Navigability –The user should be able to perform operations without having to navigate through
multiple pages/links – No operation should require more than 4 to 5 clicks.
• Familiarity – The system’s interfaces and navigations should be based on other systems that the users
are familiar with.
Administration – The system should not require any administration tasks at the user level. Interfaces
should be available for administration/setup operations.
Help - The system should provide online help to the end users.
Standards Adherence – The system should adhere to commonly accepted standards of web-design
(such as acceptable size of web pages, small style sheets etc)
5.3.5 EXTENSIBILITY Extensibility refers the ability to add new functionality without requiring major changes to the existing code. Release Order Application should be extensible in the sense that new features can be easily added or plugged-in without any significant changes to the existing system.
• Release Order Application should be extensible to adopt following changes with minimal or no changes
to existing code.
• Providing new workflows.
• Providing new functionality or feature or service.
Following are few guiding principles to be followed but not limited to that Release Order Application should adhere in order to achieve extensibility–
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
143
• Solution must be developed using Layered architecture
• Solution must follow Object oriented methodology, which inherits extensibility
• User defined attributes
• Business rules
• Configurable parameters
5.3.6 MAINTAINABILITY Software maintenance is the modification of a software product after delivery to correct faults, to improve performance or other attributes. Proposed solution should adhere to the following guidelines for realizing Maintainability
• Software Code must be modular and well documented.
• Avoid Complex Coding: Very complex “spaghetti code” is quite difficult to maintain safely. Hence it should
be avoided.
• Early planning: anticipating what and how programs might be modified at a later stage.
• Modular design: defining subsets and simplifying functionality (i.e., one module performs only one function).
• Object-oriented design: encapsulating both methods and data structures to achieve a higher level of
independence.
• Uniform conventions: facilitating error detection and debugging.
• Naming conventions: providing understandable codes.
o Use of Coding standards, comments, and style enhancing readability of the program.
o Use of Documentation standards
o Use Common tool sets
o Configuration Management
o Proper versioning of the software to be maintained.
• All the artifacts related to the software such as code, SRS, User Manual etc. should be well documented and
self-explanatory for any programmer to understand. Detailed documentation shall be available at each stage
for easy comprehensions of the application system.
• All documents shall be prepared as per the defined documentation standards.
• Backup and recovery policy should be in place for databases. The system administrator shall take regular
back up of the database.
• Configurable parameters
5.3.7 UNIFORMITY OF PARAMETER
To develop a web enabled, work flow based application for Release Order with appropriate linkages with DCMS, FEAST, DCMS, FAP and Weighbridge applications which will enable to have a complete view of the inflow and outflow of the commodities and the stock position in the depot , we have to define some protocols. Existing external applications are running independently and application users are repeatedly entering the
same parameters manually in the applications separately based on data available in physical papers. There are
several ways for applications to exchange data with other applications. We will select any one among CSV, XML
or open format to exchange data. Hence, there is no validation and verification checks for the entered data
since the applications are running independently RO Application will maintain Uniformity of Parameters.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
144
Data maintained by external application are different type and format. Standards should be developed to insure
compatibility between applications developed by different vendors, and to allow for reasonable success in
transferring data. The RO Application will produce standards that deal with data communications. The standards
bring uniformity to data communications.
Data standardization is the first step to ensure that your data is able to be shared across the enterprise. This
establishes trustworthy data for use by other applications in the organization. Ideally, such standardization
should be performed during data entry. If, for some reason this is not possible, a comprehensive back end
process is necessary to eliminate any inconsistencies in the data.
For instance: when application will communicate through the FAP application then user has to go for XML data
exchange which is platform and software independent. XML data exchange reduces the over head on the
application due to its nature. Both the vendors will agree on a particular format of the XML to interchange the
data and get the desired result set.
Another example we take of as data exchange between FIST and RO application as WSDL format. WSDL is used
to HTTP protocol to communicate between client and server. WSDL format is widely preferred and can be
generated by the WCF service. WCF service has it on features and more ever is platform and language
independent.
Data exchange will take place in the application based on client and server and request and response based. A
client is going to send the request and getting response from server. The request can be a form of Entity and
response will be in form of Entity so that we can have same data contract between client and server.
In case of weighbridge communication we are going to provide the WCF server to get weighment details. WCF
service will expose by the client and consume by the application to get the weighment details.
Data contract will help to make data standardization by using the provision of SOA (Service oriented
architecture)
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
145
5.4 USER GROUPS WITH ACCESS LEVELS
The Application users are classified into four levels based on Roles and Responsibilities.
Group Description Access Rights
Administrator - Technical Support Team
Administer and Configure the software
The administrator has full control over the system. He is
responsible for creating groups /users, giving them access
rights, modifying groups / users, creating, editing, and
deleting workflows and archival to CD or Storage Disks.
Full control (Read, delete, view and write privileges) of
each interface.
Report Generation
Database Backup
Change Tracking
User Management
ACRs/Inquiry Reports
Level - 2 FCI Zonal/Regional Officers /District Area Manager
Higher officials of FCI Department
User management for Level 3 and 4 Groups within
Judiciary
Application Progress Monitoring and Review
Verify/ Approval/Reject the Requests
Digitally sign the approval Records
State Agency/Party User management for Level 3 and 4 Groups within
Judiciary
Allocation and Indent Generation Reports
Release Order Progress monitoring and Tracking
To generate the Extension/Diversion/Reimbursement
Requests
Level - 3 FCI/ State Agency District Level Officers
FCI District Officer – Sales
User management for Level 4 Group within Judiciary
Report generating facilities
Release Order Operations configuration
Read Write privileges to a few exceptional interfaces to
handle the Release Order
Diversion/Reimbursement/Cancellation /Extension
Requests
Release Order Creation Operations
Release Order Execution monitoring
FCI District Officer – Accounts
User management for Level 4 Group within Judiciary
Indent Verification and Approval
Release Order Progress monitoring and tracking Reports
FCI Depot Manager Release Order Execution Reports
Release Order Execution Step Configuration
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
146
Group Description Access Rights
State Agency/ Party Officer
To track and monitor the Release Order Execution Reports
Verify/Approve/Reject the Requests
Level – 4 Operators
Data Entry Operators
Read/write (as per the group/security policy) for all
Interfaces.
Access to the input forms to enter the required Data
5.5 APPLICATION ENVIRONMENT
5.5.1 CLIENT ENVIRONMENT Release Order client is a web application and runs on any standard browser, so the various details about the operating environment is unimportant and hidden from the end user. End users can use the application from a modern internet browser such as Firefox, Chrome, and Internet Explorer. However, it’s recommending to have a following environment for better visibility and navigation flow and to meet the proposed SLAs.
5.5.1.1 OPERATING SYSTEM
Any Standard Operation System like Windows, Linux or Unix Flavor
5.5.1.2 SYSTEM CONFIGURATION
1. Intel based Pentium IV workstations
2. RAM: 2GB or More
3. HDD: 50 GB or More
4. Accessories
a. Keyboard, Monitor and Mouse
b. Printer – (Optional for printing the Documents & Reports )
5.5.1.3 SUPPORTED BROWSERS Any standard browser is supports but it’s recommended to have following browsers for better look and fell and navigation flow
1. Internet Explorer 10.0 or up to the existing higher version as on deployment date
2. Google Chrome 17.0 or higher
3. Mozilla Firefox 30.0 or higher
5.5.2 DEVELOPMENT ENVIRONMENT
5.5.2.1 OPERATING SYSTEM
Operating System: Windows 7 or above
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
147
5.5.2.2 SYSTEM CONFIGURATION
1. Intel dual core with 2.02 GHz
2. RAM: 4GB or More
3. HDD: 300 GB or More
4. Accessories
a. Keyboard, Monitor and Mouse
5.5.2.3 SOFTWARE
Front end : ASP.net, html, JavaScript, CSS
Back end Database : MS SQL 2008
Technology used : Visual studio 2008 or Above
Language used : c sharp (c#).
Version Control: VSS
5.5.3 DEPLOYMENT ENVIRONMENT Following is the system configuration to deploy the Release Order application in production environment System Configuration
1. Intel Multi-core processor or better Quad-core processor
2. RAM: 16 GB or More
a. 4 GB available for IIS server installation and initial usage, plus room for perpetual growth
b. 5 GB available for web server installation, plus room for perpetual growth
c. 5 GB available for SQL Server installation and initial usage, plus room for perpetual growth
d. 2 GB buffer for Operation System processes
3. HDD: 1 TB or More
a. 500 GB for Database
b. 200 GB IIS Server
c. 300 GB for OS and others
4. Accessories
a. Keyboard, Monitor and Mouse
Software Operating system: Windows 2008 Server or Above
Back end Database: MS SQL 2008
Web Server: IIS 7.0 or Above.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
148
5.6 IMPLEMENTATION APPROACH
This section provides the project Release Order application implementation approach by the eCentric to execute the project
5.6.1 IMPLEMENTATION STRATEGY
System Analysis o Study of Existing Release Order Operations/Reverse Engineering o Study the External applications that use the proposed Release Order Application. o Study the existing infrastructure and communication mechanism. o Perform Gap Analysis
Prepare the System Regiment Specification Document o Review and Sign-off
Prepare the Design Document
Application Development o Develop application prototype o Implement the Solution at Pilot Location o Customize the Application o Design Finalization - based on the pilot study outcomes the solution would be designed and the
proper documentation is to be drafted for the proposed solution. o Sign-off the Design document
Roll out o Create integration and system test plan and test cases o Implement the application functionality o Application Components Integration o Hardware Components Integration o System Integration includes both hardware and software components integration o Create integration and system test plan and test cases
Unit & Integration Testing o Execute the test cases and fix the bugs o Unit Testing o Integration Testing
User Acceptance Test o Deploy the application at UAT o Execute the UAT Test Cases o Fix the bugs
Application Deployment o Setup the application environment o Deploy the application
System Demonstration and Application Training o The installed application would be demonstrated to the FCI officials and take the feedback and
training would be conducted
Enhancements based on the suggestions o Customize the application based on the suggestion from the FCI officials if needful.
System Maintenance and Support o Make sure that system perform the operations round the clock without fail.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
149
5.6.2 EXECUTION PLAN
S.No. Phase Activity M1
M2
M3
M4
M5
M6
M7
M8
M9
M 10
M 11
M 12
1 I SRS including linkage with Weighbridge & Other Applications, data standardization
2 II System Design, Database Design & Test Plan
3 III Application Development and integration with existing applications & Test cases
4 IV Application Testing along with linkage with existing applications, Test reports
5 V Security Audit & Application Deployment
6 VI Training and Roll Out
7 VII Implementation Support, Feature enhancements, Application maintenance and handing over of application
5.7 CAPACITY BUILDING & USER TRAINING Following User Manuals and Guides for system personnel and end users would be provided in both hard copies and electronic form based on the user levels System Administrators and System users
Administration guide for configuring and managing the Release Order application Administration guide for web application.
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
150
6. APPENDIX A - DATA DICTIONARY
Figure 66: Data Dictionary
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
151
7. APPENDIX B - GROUP LOG
Third User Group Review meeting held on 15/07/2014 at FCI Head Quarters to discuss on FAP integration.
Second User Group Review meeting at FCI Head Quarters on 01/07/2014 on Release Order processes.
First User Group Review meeting at FCI Head Quarters on 05/06/2014 on Release Order Processes.
Field Study at FCI stakeholder locations.
Discussions with Project stakeholder departments (FCI and NIC)
Field Survey & Feedback Reports
External Applications study with NIC and FCI officials
Physical Ledgers/Forms
8. APPENDIX C - REFERENCE DOCUMENTS & PHYSICAL COPIES
S.No Description of the Document Document Name
1. DPR Document (Refer to SRS Version 1.5) DPR
2. Field Visit Reports (Refer to SRS Version 1.5) FCI Mayapuri Survey
3. Release Order Operations Study & Discussion Points (Refer to SRS Version 1.5)
RO Operations Discussion
4. FAP Integration & Discussion Points (Refer to SRS Version 1.5)
FAP Study Report
5. Weighbridge Study, Integration Solution and Discussion Points (Refer to SRS Version 1.5)
Weighbridge Integration
6. Release Order Physical Documents (Refer to SRS Version 1.5) Sample
7. Release Order Physical Documents (Refer to SRS Version 1.5) RO Printed
8. Modification History History
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
152
Modification History
S.No. Page
No.
(if
any
in
Ver.
1.5)
Initial Text (as in SRS Version 1.5) Page
No.
(if
any
in
Ver.
1.6)
Revised text (as in SRS Version
1.6)
Remarks
1 14 Further, commodities allocated FCI Revenue District wise.
14 Further, commodities allocated FCI Revenue District wise by respective State Govt.
Sales
division’s
feedback
2 14 State Agency/Party make payments to Food Corporation of India for allotted quantity based on the Central issue prices.
14 State Agency/Party make payments to Food Corporation of India for allotted quantity based on the Central issue prices (state wise, scheme wise, crop year & commodity) / issue price(OMSS & Commercial) as decided by Govt. of India.
Sales
division’s
feedback
3 14 Diversion of Release Order – identification of alternate FCI depots in case of the initially identified depot runs out of stock.
14 Diversion of Release Order – identification of alternate FCI depots in case of the initially identified depot runs out of stock, at the request of State Govt. or any other operational/ natural exigencies.
Sales
division’s
feedback
4 14 Point no. 4 was
State Agency/Party make payments
to Food Corporation of India for
allotted quantity based on the
Central issue prices.
14 Now point no. 4 is
State Agency/Party make
payments to Food Corporation
of India for allotted quantity
based on the Central issue
prices (state wise, scheme wise,
crop year & commodity) / issue
price(OMSS & Commercial) as
decided by Govt. of India.
Based on
MOM
5 14 Point no. 12 was
Diversion of Release Order – identification of alternate FCI depots in case of the initially identified depot runs out of stock.
14 Now point no. 12 is
Diversion of Release Order –
identification of alternate FCI
depots in case of the initially
identified depot runs out of
stock, at the request of State
Govt. or any other operational/
natural exigencies.
Based on
MOM
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
153
6 15 Existing Release Order is not being generated in predefined standard format. Most of the States uses their customized format to generate the Release Order.
15 Existing Release Order is not being generated in predefined standard format. Most of the FCI District Offices use their customized format to generate the Release Order.
Sales
division’s
feedback
7 19 Point no. 4 was
All the weighbridge vendors shall provide the necessary data and linkages, based on standards as finalized by FCI (preferably by XML/CSV).
19 Now point no. 4 is
RO Application will define the protocol so that all weighbridge system shall provide the necessary data and linkages, based on standards as finalized by FCI (preferably by XML/CSV).
Based on
MOM
8 19 Point no. 7 was
All the financial transactions including (payments verification and taxes and penalties etc.,) would be taken care in FAP. Release Order application shall maintain only the final status provided by FAP.
19 Now point no. 7 is
All the financial transactions would be routed through FAP. Release Order application shall maintain only the final status provided by FAP.
Based on
MOM
9 28 28 Scheme Table has been taken from DISFM.
Sales
division’s
feedback
10 29-30 Monthly - 50 Days 30 Monthly - 30 days or as per GOI order
Sales
division’s
feedback
11 29-30 Need Basis – Generally 50 days or as per the Govt, Order
31 As per the GOI order. Sales
division’s
feedback
12 29-30 Monthly/Quarterly - 50 Days
31 Quarterly – 115 days Sales
division’s
feedback
13 29-30 Monthly – 50 Days Except in Year Closing months
31 Quarterly – 115 days Sales
division’s
feedback
14 29-30 Monthly - 50 Days 31 Monthly - 50 days or as per GOI order
Sales
division’s
feedback
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
154
15 29-30 Quarterly 31 Quarterly – as per GOI order Sales
division’s
feedback
16 29-30 31 AGPLM/NPAG/SABLA Is one row as SABALA only.
Sales
division’s
feedback
17 29-30 To clear the surplus stocks 32 As per DO, FCI or Release Order Sales
division’s
feedback
18 29-30 32 Annapurna Scheme is added as active Scheme
Sales
division’s
feedback
19 33 Monthly once between specific time interval
34 As per indent by State Govt. Sales
division’s
feedback
20 46 FCI district officer will extend the RO up to 7 days
48 FCI district office will extend the RO up to the validity period given by GOI.
Sales
division’s
feedback
21 46 Regional Office can extend the RO up to 15 days
48 After the expiry of validity period given by GOI, Regional Office can extend the RO up to 15 days and thereafter, Zonal Office can extend it for another 15 days.
Sales
division’s
feedback
22 46 Ministry and Headquarters can extend the RO for no limit
48 Ministry can extend the RO for no limit
Sales
division’s
feedback
23 46 Extension Request for 7 working days by District Area Manager excess storage amount can be deposited within 2 days.
48 Extension Request as provided in the guidelines in vogue of OMSS (D).
Sales
division’s
feedback
24 46 Point no. 4 is deleted Extension Request for 15 working days can be done by the Regional Office.
Sales
division’s
feedback
25 57 Point no. 1 was
User can edit only those allocations
for which revenue district
allocation has not been happened.
58 Now point no. 1 is
User can edit allocations and excess off take if any will be flagged in case allocation has been reduced.
Based on
MOM
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
155
26 57 Point no. 2 was deleted
Allocation would be done only for one state at a time.
Based on
MOM
27 58 Point no. 1 was deleted. Those revenue district allocation can be modified for which indent has not been created.
Based on
MOM
28 58 Point no. 2 was deleted
Allocation would be done for one state at a time
Based on
MOM
29 58 Point no. 7 was Allocation should also be done in multiple revenue districts.
60 Now point no. 7 is
Allocation should be segregated
across the revenue districts.
Based on
MOM
30 CPI/Rate CPI/Issue Price Based on
MOM
31 59 Point no. 6 Formula of Quantity was Available Quantity= Total Allocation – Total Quantity of Generated Indent
61 Now point no. 6 Formula of Quantity is
Quantity Available for
Indenting/Off take = Total
Allocation – Total Quantity
Indented
Based on
MOM
32 59 Point no. 6 Formula of Cost was Cost of Food Grains = Quantity * CIP/Rate
61 Now point no. 6 Formula of Cost is
Cost of Food Grains = (Quantity
* CIP/issue price) + Applicable
Taxes
Based on
MOM
33 60 Point no. 10 Formula of Indent Amount was Indent Amount= Cost of Food Grains + Tax Cost – Deductions Cost
61 Now Point no. 10 Formula of Indent Amount is
Indent Amount= Cost of Food Grains + Tax Cost – Deductions (if any)
Based on
MOM
34 63 Details of “FAP Approve / Reject” section was In FAP Approve / Reject module user will be provided with below details
65 Details of “FAP Approve / Reject” section is Before approval FAP user has to enter receipt No. and document No. from FAP module to RO module in the relevant fields in FAP Approval screen. In this screen, FAP user will be provided with the following fields
Based on
MOM
35 64 Point no. 1 was deleted Document number and Receipt
Based on
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
156
Number details will be fetch from FAP Application. It will be happened through a service.
MOM
36 64 Point no. 2 was User can upload Receipt in PDF Format.
66 Now point no. 2 is FAP User can upload Receipt in PDF Format.
Based on
MOM
37 64 Point no. 3 was If user will get payment details from FAP Application user will approve payment else user will reject payment.
66 Now point no. 3 is FAP user will verify and approve the payment details. In case payment is not available then FAP user has option to reject the indent with rejection remarks.
Based on
MOM
39 64 Requirement #5 was Application should have ability to ability to approve or reject the current indent details by Area Sales Manager.
66 Now Requirement #5 is Sales division can approve or reject the current indent details vis-à-vis the amount deposited and the quantity indented.
Based on
MOM
40 64 Indent Status 66 Indent Status (FAP Approved/Rejected)
Based on
MOM
41 66 FAP Approved Indent No. 68 Commercial/Sales Approved Indent No.
Based on
MOM
42 66 Point No. 3 was Release Order date will be less or equal to Today date.
68 Now Point no. 3 is Release Order date will be Today’s date.
Based on
MOM
43 67 FAP Approved Indent No. 68 Commercial/Sales Approved Indent No.
Based on
MOM
44 67 Point no. 5 & 6 is merged.
69 Based on
MOM
45 67 Point no. 7 was Only one commodity can be added in one Release Order.
69 Now point no. 7 is as 6 Only one commodity/scheme can be added in one Release Order.
Based on
MOM
46 67 Point no. 8 was Issued quantity of Release Order can’t be more than Available Indenter Quantity.
69 Now point no. 8 is as 7 Quantity of Release Order can’t be more than approved Indented Quantity.
Based on
MOM
47 67 Point no 9 was Multiple “Release Orders” can be created against one Indent if Indenter Quantity available. After creating one Release Order, when user will create another Revenue Release Order against same Indent,
69 Now point no. 9 is as 8 Multiple “Release Orders” can be created against one approved Indented Quantity. After creating one Release Order, when user will create another Release Order against
Based on
MOM
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
157
user can allocate remaining quantity only.
same Indent, Release order can be issued for remaining quantity only.
48 67 Commodity Amount = (CIP/Rate * Issued Quantity)
69 Commodity Cost = (CIP/Issue Price * Issued Quantity)
Based on
MOM
49 67 Total Release Order Cost = (Commodity Amount + Tax/Vat/Others Charges - Deductions)
69 Total Release Order Cost = (Commodity Cost + Applicable Tax/Vat/Others Charges - Deductions)
Based on
MOM
50 68 Point no. 1 was User able to generate the physical copy of the Release Order with Digital Signature in Approved tab.
69 Now point no. is User able to generate the physical copy of the Release Order with Digital Signature which is mandatory.
Based on
MOM
51 68 Point no. 2 was Release Order Validity date will be greater than to Today date
70 Now point no. 2 is Release Order Validity date will be greater than to Today date and should not be more than lifting duration.
Based on
MOM
52 68 Point no. 4 is deleted. Digital Signature will be in .JPG Format only.
Based on
MOM
53 Inflow Gate Entry - Empty Truck
Gate Entry - Loaded Truck
Based on
MOM
54 70 Point no. 4 was Duplicate Commodity details will not be added again.
72 Single Commodity details will be allowed.
Based on
MOM
55 72 Point no. 3 is deleted Exit Gate Pass No. should be validated with generated Gate Pass No.
Based on
MOM
56 76 Point added In case of Rail Siding Depot, internal movement/rail movement, truck shall be tare weight every time.
Based on
MOM
57 75 Generate Gate Exit Pass section is deleted.
Based on
MOM
58 Special Order Date Is deleted.
Based on
MOM
59 Special Arrival Date Special Arrival Date & Time
Based on
MOM
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
158
60 Special Release Date Special Release Date & Time Based on
MOM
61 77 Special Order Date should be less than or equal to today’s date.
78 Special Indent Date should be less than or equal to today’s date.
Based on
MOM
62 77 Special Dispatch Date should be greater than or equal to today’s date.
78 Special Dispatch/Release Date should be greater than or equal to today’s date.
Based on
MOM
63 77 Point no. 3 is deleted Duplicate Commodity Received details will not be added again.
Based on
MOM
64 78 Gate Exit – Empty Truck 78 Gate Exit – Loaded Truck/ Empty Truck (in case of exceptions)
Based on
MOM
65 78 Depot Id 78 Depot Name Based on
MOM
66 Entry Date should be current date. Entry Date and time should be current.
Based on
MOM
67 78 Generate physical copy 79 print physical copy Based on
MOM
68 Entry Date Entry Date and Time Based on
MOM
69 79 New point added A valid token number is one as long as the truck is within the Depot premises.
Based on
MOM
70 Token Number must be a valid token number.
Token Number to be printed must be a valid token number
Based on
MOM
71 In Inflow Gate Exit – Empty Truck
Now Gate Exit – Loaded Truck
Based on
MOM
72 Weighbridge Serial No. Weighbridge Identification No. Based on
MOM
73 80 80 New point added A valid token number is one as long as the truck is within the Depot premises
Based on
MOM
74 80 80 New Point added Truck Number will be fed in running order without space.
Based on
MOM
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
159
75 All the weighment details should come from the Open xml data format.
80 All the weighment details should come from the Open xml data format. Where ever weighbridges do not have a capability to exchange data in open data format, the weighment details shall be manually fed at weighbridge/gate.
Based on
MOM
76 Issuable? Issuable/Non Issuable Based on
MOM
77 Bag Type Bag Type (BT/SBT/PP) Based on
MOM
78 In Out Flow Commodity Unloaded
Commodity Loaded
Based on
MOM
79 82 Point no. 3 was Duplicate Commodity Unloaded details will not be added.
83 Now Point no. 3 is Duplicate Commodity details will not be added.
Based on
MOM
80 83 Commodity Unloaded 83 Commodity Loaded Based on
MOM
81 83 No. of Bags Unloaded 83 No. of Bags Loaded Based on
MOM
82 84 New point added Truck Number will be fed in running order without space
Based on
MOM
83 84 New point added Gate pass shall be prepared/ generated by Unit/Shed In-charge.
Based on
MOM
84 83 Application should have ability to add the commodity received by Depot manager.
84 Application should have ability to take action on Release Order/Dispatch Order in case of exigencies like Initiation of RO Diversion, Closing of RO, Re-weighment etc..
Based on
MOM
85 83 Release Order No should disappear after taking action by depot manager from the grid.
84 The list of Release Orders against which action has already been taken shall not be available to the depot manager.
Based on
MOM
86 86 RO Amount 87 Deposited Amount Based on
MOM
87 86 RO Extension Status 87 RO Extension Status and Authority
Based on
System Requirement Specification Ver 1.6
©2015 Food Corporation of India, Govt. of India. All rights reserved.
160
MOM
88 86 Extend RO Approval Date 87 Extend RO Approval Date and Authority
Based on
MOM
89 88 88 For PDS/OWS and OMSS business rule is added
Based on
MOM
90 89 Point no. 2 & 3 is deleted. Based on
MOM
91 89 Point no. 4 was RO Extension Validity Date will be greater than to Today date.
90 Now point no. 4 is Validity will be defined as per MTF
Based on
MOM
92 89 Upgrade/Downgrade or gain/loss 90 Upgrade/Downgrade Based on
MOM
93 92 93 New point is added Digital signature will be mandatory for NCDEX RO.
Based on
MOM
94 92 93 New point is added No Payment verification from FAP Application is required as RO is already generated.
Based on
MOM