rehabilitation of road side drain from jattan wala chowk...

42
Rehabilitation of Road side Drain from Jattan Wala Chowk To Shahi Chowk, Peeran Wala Chowk To Shahi Chowk & Shahi Chowk to storm water channel No. 1 GM Abad

Upload: others

Post on 16-Sep-2019

9 views

Category:

Documents


0 download

TRANSCRIPT

Rehabilitation of Road side Drain from Jattan Wala Chowk To Shahi Chowk, Peeran Wala Chowk To

Shahi Chowk & Shahi Chowk to storm water channel No. 1 GM Abad

This Environmental and Social Management Plan (ESMP) is prepared

according to the World Bank Guidelines and Environmental and Social laws

of Government of Punjab (GoPb). It will be used to identify and mitigate the

environmental and social impacts that may emerge during implementation of

“Rehabilitation of Road side Drain from Jattan Wala Chowk

To Shahi Chowk, Peeran Wala Chowk To Shahi Chowk &

Shahi Chowk to storm water channel No. 1 GM Abad ”

being executed by WASA-FSD from the financial grant of PCGIP (EEPs)

awarded for the financial year 2015-16.This ESMP follows the social and

environmental appraisal and compliance as mentioned in the Environmental

and Social Management Framework (ESMF) of PCGIP.

TABLE OF CONTENTS

NTENTS

SECTION 1: INTRODUCTION .......................................................................................................................... 1

1.1. PUNJAB CITIES GOVERANCE IMPROVEMENT PROJECT (PCGIP) ................................................... 1

1.2. ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) ........................................ 1

1.3. ENVIRONMENTAL AND SOCIAL SCREENING OF SCHEMES ........................................................... 2

1.4. ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP) ..................................................... 2

SECTION 2: PROJECT DESCRIPTION ............................................................................................................... 4

2.1. AREA DESCRIPTION ....................................................................................................................... 4

2.2. LOCATION OF THE PROPOSED PROJECT ....................................................................................... 5

2.3. WORK ACTIVITIES .......................................................................................................................... 5

2.4. COST ESTIMATES ........................................................................................................................... 6

2.5. DURATION OF THE PROJECT ......................................................................................................... 6

2.6. PROVISION OF ALTERNATIVES ...................................................................................................... 6

SECTION 3: ENVIRONMENTAL BASELINE CONDITION OF FAISALABAD ....................................................... 7

3.1 CITY PROFILE ................................................................................................................................. 7

3.2 PHYSICAL ENVIRONMENT OF CITY ................................................................................................ 7

3.2.1 Air Quality ............................................................................................................................. 7

3.2.2 Dust ....................................................................................................................................... 8

3.2.3 Noise ..................................................................................................................................... 8

3.2.4 Soil Profile ............................................................................................................................. 9

3.2.5 WATER sources ..................................................................................................................... 9

3.3 BIOLOGICAL ENVIRONMENT OF CITY............................................................................................ 9

3.3.1. Parks and Gardens ................................................................................................................ 9

3.3.2. Flora & Fauna ........................................................................................................................ 9

3.4 SOCIAL ENVIRONMENT OF CITY .................................................................................................. 10

3.4.1. Demography ........................................................................................................................ 10

3.4.2. Institutes ............................................................................................................................. 10

3.4.3. Land Use .............................................................................................................................. 10

3.4.4. Economic Status .................................................................................................................. 11

3.4.5. Cultural Heritage ................................................................................................................. 11

SECTION 4: IMPACTS & MITIGATION MEASURES ....................................................................................... 12

Table 4.1 Environment & Social Management Plan ............................................................................... 12

Table 4.3: ENVIRONMENTAL MONITORING PLAN .................................................................................. 16

Table 4.4 ESMP IMPLEMENTATION COST ............................................................................................... 18

4.1. SITE HANDING OVER DOCUMENT .............................................................................................. 19

SECTION 5: SOCIAL ACCEPTABILITY AND PUBLIC CONSULTATION ............................................................. 20

5.1. GENERAL ..................................................................................................................................... 20

5.2. PUBLIC INFORMATION / CONSULTATION ................................................................................... 20

5.3. GRIEVANCE REDRESS MECHANISM ............................................................................................ 21

SECTION 6: CAPACITY BUILDING ................................................................................................................. 23

6.1. GENERAL ..................................................................................................................................... 23

6.2. CONTRACTOR’S TRAINING .......................................................................................................... 23

ANNEXURE A ........................................................................................................................................... 25

ANNEXURE B ........................................................................................................................................... 30

ANNEXURE C ........................................................................................................................................... 32

aNNEXURE D ........................................................................................................................................... 34

LIST OF ABBREVIATIONS

AHs Affected Households

APs Affected Persons

CDG City District Government

CDG-F City District Government, Faisalabad

DO District Officer

EIA Environmental Impact Assessment

ESMF Environmental and Social Management Framework

ESMP Environmental and Social Management Plan

ESSS Environmental and Social Safeguards Specialist

GRC Grievance Redress Committee

GRM Grievance Redress Mechanism

IEE Initial Environmental Examination

NEQS National Environment Quality Standards

PCGIP Punjab Cities Governance Improvement Project

PPEs Personal Protective Equipment’s

RAP Resettlement Action Plan

SAR Social Assessment Report

SOx Sulfur and its oxides

SSS Social Safeguard Specialist

WASA Water and Sanitation Agency

WB World Bank

WHO World Health Organization

Environment & Social Management Plan (ESMP)

The Urban Unit Page 1

1.1. PUNJAB CITIES GOVERANCE IMPROVEMENT PROJECT (PCGIP)

Government of the Punjab (GoP) with the financial assistance from World Bank (WB) is implementing

Punjab Cities Governance Improvement Project (PCGIP). The project is focused at strengthening of

systems and governance improvement for enhanced service delivery and being implemented in five large

cities (Rawalpindi, Lahore, Multan, Faisalabad and Gujranwala).

The project development objectives are to:

Support the Province of Punjab’s cities in strengthening systems for improved planning, resource

management, and accountability

Improve the capacity to respond promptly and effectively to Crisis or Emergency.

The objective of the PCGIP is to support Punjab’s large cities in strengthening institutional frameworks

and developing systems for improved urban planning, expenditure and accountability and to capacitate

these cities to improve delivery of municipal services in a medium to long term on a more sustainable

basis. The Project has a number of financial, social, economic and environmental benefits, including

institutional development, rehabilitation and improvement of municipal services, better quality of life and

employment generation. In addition a large number of secondary benefits are also likely to accrue in the

medium to long term such as institutional reforms at local level.

1.2. ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK (ESMF)

Environmental and Social Management Framework (ESMF) serves as a guiding document to address the

social and environmental issues during projects implementation covering following phases at: Planning

and design, Construction and rehabilitation, Operation and maintenance, Decommissioning and closure

phases.

Overall objectives of ESMF are to:

Ensure that schemes to be designed and implemented by the Government are environmentally sound

and socially acceptable

Ensure that all the schemes comply with the national regulatory and WB policy frameworks

Internalize and integrate the environmental and social management procedures and processes in the

routine projects/operations/service delivery of CDG’s and city entities

Screening will be the first step of the environmental and social management procedure. Each scheme

during its preparation stage will be screened with respect to environmental and social considerations. The

SECTION 1: INTRODUCTION

Environment & Social Management Plan (ESMP)

The Urban Unit Page 2

Safeguards Specialist will be responsible to carry out this screening. The screening criteria are presented

below.

1.3. ENVIRONMENTAL AND SOCIAL SCREENING OF SCHEMES

Environmental Categories: Depending on size, cost, location and the nature, scheme will have varying

impacts on city environment. The rigorousness of environmental assessment requires identifying and

mitigating the impacts, largely dependent upon the complexities of scheme. To facilitate effective

screening, schemes are categorized into three categories viz. E-1, E-2 and E-3.

(i) E-1 schemes are those wherein major environmental impacts are foreseen;

(ii) E-2 schemes are expected to have only moderate environmental impacts; and

(iii) E-3 schemes are the schemes with negligible environmental impacts and hence, these can be

termed as “environmentally benign”.

Since PCGIP funds are exclusive for operation and maintenance and rehabilitation schemes, schemes

falling under E-1 category shall not be funded.

Social Categories: Based on the number of households that may be affected by the scheme, i.e. Affected

Households (AHs) and magnitude of impacts, schemes are categorized as S-1, S-2 and S-3.

(i) S-1 schemes are those schemes that will impact more than 40 households, and are expected to

have significant negative social consequences;

(ii) S-2 schemes are those which will impact less than 40 households and are expected to have

significant social consequences affecting local inhabitants;

(iii) S-3 schemes are not expected to have any significant adverse social impacts;

Since PCGIP funds are exclusively allocated for operation and maintenance and rehabilitation schemes,

thus schemes falling under S-1 and S-2 categories shall not be funded through the project.

1.4. ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)

The type of environmental and social assessment requirements for each scheme will be determined

according to the following criteria:

Schemes having E-1 and S-1 categories: full EIA (or ESIA) will need to be conducted for each

individual scheme. In addition, a Resettlement Action Plan (RAP) will be prepared for each

scheme with S-1 category.

Schemes having E-2 and S-2 categories: Environmental and Social Management Plan (ESMP)

will be prepared for each individual scheme. In addition, an Abbreviated Resettlement Action

Plan will be prepared for each scheme with S-2 category.

Schemes having E-3 and S-3 categories: no further assessment is needed.

Environment & Social Management Plan (ESMP)

The Urban Unit Page 3

ESMPs preparation: For each scheme with E-2 category, ESMP will be prepared by the Environment

& Social Safeguards Specialist at the CDG level. The ESMP preparation will be an integral part of the

scheme preparation/appraisal process, and ESMP will be an integral part of the scheme documentation.

The ESMP will include details of the works to be carried out under the scheme, the site-specific

environmental and social information (baseline), and site-specific and scheme-specific mitigation

measures. The ESMPs will be reviewed and cleared by the DO (Environment) of the respective City.

ESMP Implementation: During the scheme implementation, the mitigation and monitoring measures

included in the ESMP will need to be implemented. The ESMP will be included in the bidding documents

(if the scheme is to be contracted out), and hence it will be included in the contractor’s scope of

work/services. Similarly, if the scheme is to be implemented by the concerned department itself, the

ESMP will be included in the scope of work/services. The ESMP cost will be included in the scheme

implementation cost. Environmental and social monitoring will also be carried out to ensure effective

implementation of the ESMP. First tier of monitoring will be conducted along with the monitoring of the

works being carried out under the scheme. At the second tier, the Safeguards Specialist will carry out spot

checks to ensure ESMP implementation. Checklists prepared on the basis of mitigation measures

proposed in the ESMP will be used for this purpose. Photographic record will also be maintained for this

purpose.

For each scheme with E-2 category 1as per ESMF document, ESMP prepared by the Environment &

Social Safeguard Specialist at the CDG level to ensure ESMF implementation at City level. The ESMP

preparation is an integral part of the scheme preparation/appraisal process, and ESMP will be an integral

part of the scheme contract documentation. The ESMP include details of the works to be carried out under

the scheme, the site-specific environmental and social information (baseline) and site-specific and

scheme-specific mitigation measures and ESMP cost estimation.

1E-2 schemes are expected to have only moderate environmental impacts;

Environment & Social Management Plan (ESMP)

The Urban Unit Page 4

2.1. AREA DESCRIPTION

The area where the scheme lies is mostly residential zone of Liaqat Chowk Faisalabad. Through

screening, this scheme lies in E-2 category; the Screening Form is attached as Annexure A, Checklist for

Environmental Management of E-2 Category Schemes is presented as Annexure B and Checklist for

drainage schemes is attached as Annexure C. the physical condition of the area is shown in Fig. 2.1 and

Fig. 2.2:

SECTION 2: PROJECT DESCRIPTION

Fig. 2.1 Pre-condition of eroded road & drain alignment

Environment & Social Management Plan (ESMP)

The Urban Unit Page 5

2.2. LOCATION OF THE PROPOSED PROJECT

The scheme is Repair / Improvement of roadside drain from Jattan wala chowk to Peeranwala chowk with

the total length of alignment. The linear location map of the scheme is given below

2.3. WORK ACTIVITIES

Following repair/improvement activities are involved during the execution of work.

Construction of Road Side Drain 2'x4.5'

Construction of Culverts

Construction of Road Side Drain 3'x4.5'

Construction of Culverts

Construction of Road Side Drain 4'x5'

Construction of Culverts

Dismantling of road metalling (1x285x7.75x1) +(315*8.75*1)+(173x9.75x1)

Provision for restoration of road metalling (1x285x7.75x1) +(315*8.75*1)+(173x9.75x1)

Provision for shifting of services

Fig. 2.3 Linear Location map of the scheme

Environment & Social Management Plan (ESMP)

The Urban Unit Page 6

2.4. COST ESTIMATES

Total cost of the scheme: 27.383 million/- PKR (including ESMP cost)

ESMP implementation cost: 420,000/- PKR (Break-up of this cost described in Table 4.4)

2.5. DURATION OF THE PROJECT

Duration of the Project: 03 months

Labors involved: 25-30

2.6. PROVISION OF ALTERNATIVES

As the proposed project is limited to repair/ improvement of road under limited traffic load (mostly light

weight), there is no need for alternatives for this project. Due to proposed project activity, entry/ exit

problem may not occur for the residents as road width is enough for traffic/pedestrians movement. The

impact is temporary and minor in nature. The mitigation measure should be adopted to reduce the impact.

Environment & Social Management Plan (ESMP)

The Urban Unit Page 7

3.1 CITY PROFILE

The Faisalabad district lies from 30-35 to 31-47 0 N latitude and 72-01 to 73 – 400 E longitudes. It is

bounded in the North by Gujranwala and Sheikhupura Districts, in the East by Sheikhupura and Sahiwal

districts, in the south by Sahiwal and Toba Tek Singh districts and in the West by Jhang district.

Faisalabad district has an area of 5,856 sq km and a population of 65,00,000 souls. The climate of the

district touches two extremes. The maximum temperature in summer reaches up to 50 oC or 122 oF and in

winter it may fall below the freezing point. The maximum and minimum temperature in winter is 21oC

and 6oC respectively.

3.2 PHYSICAL ENVIRONMENT OF CITY

3.2.1 AIR QUALITY

The degradation of air quality in all the large cities is a major environmental concern these days. Air

pollution levels in urban centers have either crossed safe limits given in the NEQS or have reached the

threshold values. About 60 to 70 % of the deterioration in the air quality is due to the vehicular emissions.

The parameters which have proved to be the major threat are particulate matter and concentration of

oxides of nitrogen that are relatively higher in all the large cities of Punjab. The PM2.5 has shown an

estimated increase of more than 60 % since last 3 years. Further the present road infrastructure cannot

cater the need of growing automobiles flow resulting in the mounting concentrations of NOx and SO2.

There is dire need to adopt strict measures to obviate this issue, which is not only a hazard for the

environment but also to the health and quality of life of the people.

The ambient air quality data for Faisalabad is presented in the Table 3.2.1.

SECTION 3: ENVIRONMENTAL BASELINE CONDITION OF FAISALABAD

Environment & Social Management Plan (ESMP)

The Urban Unit Page 8

Table 3.2.1: Air Quality Data of Faisalabad2

City Air Quality Parameters

Ozone (μg/m3) SO2 (μg/m3) CO (μg/m3) NOx (μg/m3) PM2.5(μg/m

3)

Faisalabad 32.8 72.8 2.5 164.4 252.3

NEQS - 80.0 5.0 40.0 40.0

3.2.2 DUST

The roadside dust is one of the most important contributors towards overall atmospheric pollution. This

problem becomes even more significant when we consider it in relation to the poorly maintained roads

loaded with ever increasing motor vehicle traffic especially in urban areas. This result in many adverse

effects especially to the respiratory health of the persons exposed to this dust either because of their

residence or occupation in these areas (Zafar, 20073). During the construction phase of this scheme,

roadside dust can be generated. It can be mitigated by water sprinkling with water bowsers.

3.2.3 NOISE

Noise4 is generally used as an unwanted sound, or sound which produces unpleasant effects and

discomfort on the ears. Noise is considered as environmental pollution, even though it is thought to have

less damage on humans than water, air or land pollution. Generally, problems caused by noise pollution

include stress, hearing loss, sleep disruption etc. During the construction phase of this scheme, noise can

be generated from machinery used in road construction. Mitigation measures have been suggested in

mitigation table 4.1& 4.3 in order to reduce its effects upon human beings.

The general mitigation measures to control noise are:

Control of the noise at source.

Control of the noise in the area of impact (receiver position).

Control of the noise at some convenient intermediate location (i.e. along the transmission path)

between the source and impacted receive.

2Sources: City brief of Faisalabad, the Urban Unit (2010); Punjab Development Statistics – 2011, Bureau of Statistics,

Government of the Punjab, Lahore, December 2010; Official website of City District Government, Faisalabad

(http://faisalabad.gov.pk/statistics.aspx?task=geo accessed on 14 April 2012). 3Zafar et al., (2007).Effects of airborne dust on lung function of the exposed subjects. Pak Journal of Physiology; 3(1).

4 Source:http://www.tshwane.gov.za/Services/EnvironmentalManagement/Noise%20Management%20Documents/ NoiseAppendixD.pdf

Environment & Social Management Plan (ESMP)

The Urban Unit Page 9

3.2.4 SOIL PROFILE

The soil of Faisalabad comprises of alluvial deposits 5 having calcareous characteristics. The soil is

generally fertile. Soil profile of scheme area is also fertile. There will be no impact on soil profile of

scheme area as scope of work limited to the repairing of existing metal road surface. No impact on soil

envisaged as no excavation or deep ditching activities are under scope of work of this scheme.

3.2.5 WATER SOURCES6

River Chenab flows about 30 km in the North West while river Ravi meanders about 40 km off the city in

the south east. Lower Chenab canal is the main source of irrigation water, which meets the requirements

of 80% of cultivated land. There is no prominent water channel lies under the scheme. Ground water used

by local community for drinking purposes. There is no prominent water channel lies under the scheme.

Ground water used by local community for drinking purposes.

3.3 BIOLOGICAL ENVIRONMENT OF CITY

3.3.1. PARKS AND GARDENS

There are many important parks and gardens in Faisalabad. It

includes Bagh-e-Jinah Park (Company Park), Fun Land, Sindbad,

Amusement Park Faisalabad, Gatwala Forest Park Faisalabad,

Butt Water Land, Aqua land water park, D-Ground Central Park,

Pahare ground, Madina Welfare Society Park etc.

Environmental sensitive areas are more prone towards human

disturbance. For this scheme, no wetland, estuarine, river, protected area and cultural heritage sites lie

within scope of work of scheme area and no significant environmental impacts has been envisaged,

however mitigation measures have been recommended against less significant environmental concerns.

This scheme is environmentally sound & sustainable.

3.3.2. FLORA & FAUNA

Preservation of biodiversity is of global concern, but the causes of loss and their solutions are very often

local in scale. Road development continues to be a major player in the overall reduction of biodiversity,

5Sources: City brief of Rawalpindi, The Urban Unit (2010); Punjab Development Statistics – 2011, Bureau of Statistics,

Government of the Punjab, Lahore, December 2010 6 Source: http://en.wikipedia.org/wiki/Lai_Nullah and http://en.wikipedia.org/wiki/Khanpur_Dam (accessed on March, 2014)

For this scheme, no wetland,

estuarine, river, protected area

and cultural heritage sites lie

within scope of work of

scheme area and no significant

environmental impacts has

been envisaged.

Environment & Social Management Plan (ESMP)

The Urban Unit Page 10

and proper planning at the project level can go a long way in limiting the loss, while still serving the

transport need. No wild animal/endangered species is found in the area except pet animals. No flora &

fauna will be affected due to project construction activities.

3.4 SOCIAL ENVIRONMENT OF CITY

3.4.1. DEMOGRAPHY7

Demography of Faisalabad city is shown in the Fig. 3.4.1.

Fig. 3.4.1: Demography of Faisalabad City

3.4.2. INSTITUTES

There is one major educational institute Govt. Girls Higher Secondary School in the project vicinity.

However, no infrastructural damage can be anticipated as per scope of work under this scheme.

Improvement of road side drain required to ensure drainage of rain water.

3.4.3. LAND USE

Major land use of the area is residential cum commercial. No land use patterns will be affected due to

project activities as scope of work is restricted to repair/improvement of existing road side drain.

7 Source: Standard Demographic population groups based on DHIS

Demography

Total Population(7310691)

Total Area

(5856 Km2)

Annual growth

(2.5 1%)

Population density

1248.41 persons per

Km2

Environment & Social Management Plan (ESMP)

The Urban Unit Page 11

3.4.4. ECONOMIC STATUS

The economic status of local population is middle class. People mostly are businessman and private or

servants etc.

3.4.5. CULTURAL HERITAGE

There is not any documented or known site of archeological, historical, cultural or religious significance

at or in the immediate vicinity of the proposed site. By its nature, the Project will not have any adverse

impacts on existing archeological sites, shrines, and religious sites in the surrounding areas.

Environment & Social Management Plan (ESMP)

The Urban Unit Page 12

This section deals with the identification of potential negative impacts and addresses the mitigation measures of the proposed scheme and is shown in

the Table 4.1 while Environmental Analysis, Environmental Monitoring Plan and ESMP implementation cost is given in the Table 4.2, Table 4.3 and

Table 4.4 respectively.

TABLE 4.1 ENVIRONMENT & SOCIAL MANAGEMENT PLAN

Activities Potential Impacts Mitigation Measures Implementing Authority Monitoring

Responsibility

A. REPAIR/CONSTRUCTION PHASE

Excavation activities

during the scheme

execution

a) Environmental Impacts:

Repair/Improvement work

might lead to the deterioration

of ground water quality if

deep ditch required.

Slugged material deposition

can block the pipeline and

manholes which can be

overflowed.

b) Social Impacts:

Conflicts might arise due to

piling of debris material and

blockage of project route.

Analysis of surface water/ground

water to check quality of water in

case of any contamination

recommended by ESMF

Committee.

Desilted material should be

immediately disposed off at

designated CDGF/WASA waste

collection points or reused for

depression areas. No debris

material is to be thrown into water

channel.

Deep ditching more than 5/ as per

scope of work should be shared

with ESSS to analyze the

situation.

PPE’s should be provided to

workforce as per nature of their

Contractor

ESMF

Committee

SECTION 4: IMPACTS & MITIGATION MEASURES

Environment & Social Management Plan (ESMP)

The Urban Unit Page 13

job.

First Aid facility should be

provided to workforce.

Safety signs should be displayed.

Complaints regarding stockpiling

of slugged or desillted material

should be immediately addressed

and complaints can be lodged on

WASA Helpline 1334 in this

context.

Emergency contact numbers for

complaints redressal should be

displayed at project site.

In case of social issue regarding

any conflict; complaints should be

addressed on WASA Helpline

1334 in this context.

Dismantling of road

pavement.

a) Environmental Issue:

Generation of solid waste.

Safety concerns may arise for

nearby community and labor.

Dust generation.

Noise generation.

b) Social Issues:

Blockage of passage for traffic

and pedestrians.

Dismantled material should be

immediately disposed off at

designated CDGF/WASA waste

collection sites or reused for

depression areas.

Cordon off the working area to

ensure safety of nearby

community.

PPE’s should be provided to

workforce as per nature of their

job.

Water sprinkling will be carried

out to mitigate dust.

Alternative routes for traffic and

pedestrians will be provided

where possible.

Contractor

ESMF

Committee

Construction of

roadside drain

a) Environmental Issue:

Safety issues for nearby

Cordon off the working area to

ensure safety of nearby Contractor

ESMF

Committee

Environment & Social Management Plan (ESMP)

The Urban Unit Page 14

community and labor.

If additional land acquired;

compensation should be paid

to affetes.

Smell can be raised; if drain

stays uncovered.

Seepage into ground water

b) Social Issues:

Blockage of passage for

pedestrians and traffic if

precast slabs framed onsite.

community.

Alternative routes for traffic and

pedestrians will be provided

where possible.

Concrete filling of base and

plaster of walls of drain to reduce

impact of seepage.

Drain will be covered with slabs

to reduce impact of piling of solid

waste by local community.

Construction of

Culverts

Environmental Impact:

Blockages of water drainage

will cause water to get

stagnant which can become

breeding place for mosquitoes.

Cross drainage will be ensured to

connect existing infrastructure for

smooth water flow.

Base work & walls of culverts

will be concrete filling to avoid

seepage.

Contractor ESMF

Committee

Shifting of Services

No environmental impacts

envisaged. Electric towers will be shifted as

per requirement in coordination

with WAPDA.

Contractor ESMF

Committee

B. GENERAL SOCIAL ISSUES

Scheme will produce positive impacts for the local communities by generating jobs and providing good state of art infrastructure. However, following

social issues envisaged.

Social Issues Potential Prospective Mitigation Measures Implementing Authority Monitoring

Responsibility

Information disclosure

to public

Grievance recording needs to

be triggered

Public consultation carried out to

communicate with local residents

to share project activities to be

undertaken.

Copy of approved ESMP should

be available with the Contractor

onsite.

Contractor ESMF

Committee

Environment & Social Management Plan (ESMP)

The Urban Unit Page 15

Obstruction to

accessibility Disturbance may cause in

pedestrian and vehicular

movement.

Alternate route should be provided

to local residents.

Debris construction waste should

be disposed off immediately.

Contractor ESMF

Committee

Vehicle Movement

Road congestion may arise if

not properly managed.

Alternate route should be provided

to local residents. Safety signage

should be displayed at appropriate

places.

Project activities shared with local

residents so that they schedule

their vehicle movements.

Contractor ESMF

Committee

Economic losses

Blockage of passages,

No land acquisition carried out in

this scheme.

No damage to public structure

envisaged.

Contractor ESMF

Committee

Damage to public

structures

Contractor should ensure no

damage to public structures.

In case of any complaint; residents

can call on helpline number of

WASA-F displayed on scheme

board.

Contractor will have to

compensate in case of any damage

to public structures.

Contractor ESMF

Committee

Safety Issues

Accidents might be occur if

construction zone doesn’t

cordoned off properly.

Contractor should ensure safety

measures at project site. Display

of safety boards, provision of

PPE’s to workforce is ensured. Contractor

ESMF

Committee

Environment & Social Management Plan (ESMP)

The Urban Unit Page 16

TABLE 4.3: ENVIRONMENTAL MONITORING PLAN

Sr. #

Identified

Environmental

& Social issues

Mitigation Measure Monitoring

Site

Monitoring

Frequency

Reporting

Frequency Responsibility

1. Noise Use of machineries & equipments having less

noise.

Provision for personal protective equipment

(PPE’s), ear muffs/ear plugs to workers.

Noise level testing should be executed by

Contractor.

Scheme Site Once before

the start of

the project

and once

during

construction

phase of

scheme

Once after the

completion of

the project.

ESMF Committee

2. Dust Provision for personal protective equipment

(PPE’s), Mask

Sprinkling of water and removal of excess

matter/construction debris from the site as soon

as possible

Scheme Site Once before

the start of

the project

and once

during

construction

phase of

scheme

Once after the

completion of the

project.

ESMF Committee

3. Air Quality Ambient air quality will be analyzed through

Environment Lab.

Scheme Site Once before

the start of

the project

and once

during

construction

phase of

scheme

Once after the

completion of the

project.

ESMF Committee

4. Waste

management Immediately transport the accumulated

construction waste to a site identified by the

implementing CDG****/WASA other

concerned authority

Scheme Site Twice during

construction

phase

Once after the

completion of the

project.

ESMF Committee

5. Provision of

first aid in case

of any

emergency

First aid will be provided immediately to save

the life of affectees.

Ambulance will be called up to shift the

affectees to the nearest medical facility.

Scheme Site Twice during

construction

phase

Once after

completion of

project.

ESMF Committee

Environment & Social Management Plan (ESMP)

The Urban Unit Page 17

6. Health, Safety

and

Environmental

needs

The Contractor should ensure provision of

appropriate housing, water supply, and sanitation

facilities to construction labor.

Adequate safety precautions such as helmets,

safety shoes, gloves, etc. should be provided to

the labor

Scheme Site Twice during

construction

phase

Once after

completion of

project.

ESMF Committee

7. Public

Consultation Local residents in the project area will be

informed about the project details, project

schedule and GRM

Scheme Site Three times

(pre, during

and post

construction

phase)

Once after

completion of

project.

ESMF Committee

8. Vehicle

Movement Provision of alternative routes

Indicators/signboards regarding alternate routes

should be provided at proper distance

In case of any complaint, focal person of GRC

may contact and his contact details will be

provided at project site.

Scheme Site Twice during

construction.

In case of any

complaint

emergency

visit may be

arranged

Once after

completion of

project.

ESMF Committee

9. Obstruction in

Public access Provision of alternative routes

Construction should start from middle of the

road and later on from either right or left side

Scheme Site Twice during

construction.

Once after

completion of

project.

ESMF Committee

10. Economic losses Loss of land

Damage to structures

Damage to plants

negative impacts on livelihood in form of

blockage of passage for shopkeepers as well as

vendors (Mobile/permanent)

This scheme will not cause any economic loss of

structure, land and livelihood.

Scheme Site Once during

construction

Once after

completion of

project.

ESMF Committee

11. Privacy Issues Workers would be trained to address privacy

issues and ethically behaved.

Scheme site Once during

construction

Once after

completion of

project.

ESMF Committee

Environment & Social Management Plan (ESMP)

The Urban Unit Page 18

TABLE 4.4 ESMP IMPLEMENTATION COST

Scheme: Repair/Improvement of roadside drain from Jattan wala chowk to Peeran wala chowk G.M Abad.

Sr.No

Item Quantity Cost/Item (Rs)*

Total Cost

Remarks

A. Personnel Protective Equipments (PPEs)

1) Dust Masks 300 10 3,000

2) Safety Shoes (Pair) 30 1200 36,000

3) Gloves (Pair) 30 500 15,000 Long gloves should be provided to workforce.

4) Safety Helmets 30 500 15,000

5) Ear Plugs 100 35 3,500

6) Reflective Safety Vest 35 500 17,500 Orange in color for labors & green for supervisors

7) First Aid Box 03 2200 6,600 Bandage, Suniplast, Spirit Swab, Pyodine, Flagyl, Scissor, Buscopan, Panadol, Tab Adalet, Disperine etc.

Sub-Total 96,600

B. Environmental Analysis

1) Drinking Water Quality Analysis

02 22000 44,000 Samples should be collected from community. Lump Sum Cost for testing.

2) Waste Water Quality Analysis

01 30,000 30,000 Sample should be collected from Channel # 01 Lump Sum Cost for testing.

Sub-Total 74,000

C. Others

1) Pole Hanging Waste Bins 10 9000 90,000

2) Warning Tape Roll 20 500 10,000

3) Safety Cones (Large Size) 20 1200 24,000 Safety cones with reflective tapes.

4) Traffic Management Plan (Traffic Direction & Safety Boards)

08 4000 32,000

5) Water Sprinkling During Executio

n

100,000 100,000 Lump Sum Cost

Sub-Total 256,000

Total 426,600

Note: Items A-2, 3, 4, 6, 7 & C-3, 4 are returnable to WASA Store after completion of project.

Environment & Social Management Plan (ESMP)

The Urban Unit Page 19

4.1. SITE HANDING OVER DOCUMENT

SCHEME TITLE:

Repair / Improvement of roadside drain from Jattan wala chowk to Peeran wala chowk. Faisalabad

CDG:

WASA, Faisalabad.

REFERENCE: (Work Award Letter #)

CONTRACTOR:

The site required for the execution / implementation of above mentioned scheme, as per plans, profiles,

lines, grades and specifications is being handed over to ------------------------------------------------------------

for mobilizing at site. The site being handed over for the construction activities is owned / acquired /

purchased by the implementing body and there is no claim pending for compensation as per

Environmental and Social Management Framework (ESMF) of the GoPunjab, approved by the Steering

Committee. The site is clear of all encumbrances and all entitlements and payments have been delivered to

the affected persons/party if any. You are expected to mobilize at site to start the construction activities,

with-in the stipulated time mentioned in your contract agreement for this sub-scheme.

Environment and Social Management Plan of the scheme is attached with bidding document and it is

obligatory for contractor to implement the mitigation measures proposed in Environment and Social

Management Plan (given at page number 12 of ESMP). Guidelines for contractor are also attached and it is

obligatory for contractor to implement these guidelines otherwise penalty will be imposed subject to

violation. It may lead to cancellation of contract.

Contractor is liable to engage services of Environment Scientist during construction activities for ESMP

implementation in its true spirit. Contractor Environment Scientist will be guided by Environment and

Social Safeguards Specialist, City Program Unit, PCGIP.

Handed Over by Taken Over by

In-charge Implementing Entity Contractor’s Authorized Representative

---------------------------------------- -----------------------------------------------------

Firm’s Name:

Address:

Environment & Social Management Plan (ESMP)

The Urban Unit Page 20

It is in great benefit that timely and broad-based stakeholder involvement is an essential element for an

effective environmental and social assessment, as it is linked with Project Planning, appraisal and

development in general. Public involvement during Environmental Social Assessment has a tendency to

improve project design environmental soundness and social acceptability.

5.1. GENERAL

This section describes the outcomes of the public consultation sessions held with community of the

proposed project area that can be affected by the project. The objectives of this process were to:

1. Share information with stakeholders on the rehabilitation of the proposed project and expected

impacts on the physical, biological and socio-economic environment of the project;

2. Understand stakeholder’s concerns regarding various aspects of the project and the likely impacts

of construction related activities and operation of the project;

3. Understand the perceptions, assessment of social impacts and concerns of the affected people/

communities of the proposed project;

4. Provide an opportunity to the public regarding their valuable suggestions in a positive manner; and

5. Reduce the chances of conflict through the early identification of controversial issues, and consult

them to find acceptable solutions.

5.2. PUBLIC INFORMATION / CONSULTATION

For public information/ consultation, visits were made in the proposed project areas on October 30, 2015 to

acknowledge their concerns regarding project activities. Representative samples were taken during

consultation process. Methodology selected for selection of residents was random sampling from Laiqat

chowk in project vicinity. Figure 5.2 shows pictorial record of public consultation.

SECTION 5: SOCIAL ACCEPTABILITY AND PUBLIC CONSULTATION

Environment & Social Management Plan (ESMP)

The Urban Unit Page 21

The public consultation forms are attached as Annexure D. The minutes of this consultation is described

below:

Record of Public information/ Consultation

Subject: Meeting with residents of Liaqat chowk regarding project consultation and collection of

baseline data

Date: October 30, 2015 Time: 11:00 a.m–2:15 p.m

Venue: Liaqat Chowk Team

Involved: SDO (Roads)

Sub-Engineer Inspector,

Environment Representative,

Faisalabad)

E&SSS CPU Faisalabad

Monitoring & Evaluation

Specialist CPU Faisalabad

Participants: Residents of the proposed project area

Sr. # Discussion

1

Firstly, project was briefed out by DDO Road Faisalabad to local residents. ESSS

briefed the expected environmental issues and get their concerns

2

All people showed positive feedback towards repair of roads. Mostly, people stated that

it’s a great step of CDG-F from the funding of World Bank that our roads are going to

be repaired. We have no objection over this scheme in fact this project will generate

jobs for local labors and will help in improving infrastructure of this area.

3

At the end all participants filled the Public Consultation form and gave their valuable

remarks on it.

4

Public meeting was ended with vote of thanks and public showed positive attitude

towards project to be executed at the earliest.

5.3. GRIEVANCE REDRESS MECHANISM

In order to receive and facilitate the resolution of affected people concerns, compliments, and grievance

about the project’s environmental and social performance an Environmental Grievance Redress Mechanism

(GRM) has already been established. The GRM will address affected people’s concerns and complaints

proactively and promptly, using an understandable and transparent process that is gender responsive,

culturally appropriate and readily accessible to all segments of the affected people at no costs and without

retribution.

It will comprise the Contractor’s, CDG Environmental & Social Safeguards Focal Persons and

Environmental & Social Safeguards Specialist CPU-Faisalabad. The purpose of GRM is to address the

Environment & Social Management Plan (ESMP)

The Urban Unit Page 22

project related grievance of the affected parties. In case of any complaint, focal person of GRC may contact

and his contact details will be provided at project site.

Any complaints which will not be resolved in Zonal/regional offices level will be put up before GRC. The

responsibilities of GRC are as follow:

The GRC shall review, consider and resolve grievances related to environmental and social issues

during execution of scheme

Nominated person from CDG would serve as focal person

Environment & Social Management Plan (ESMP)

The Urban Unit Page 23

6.1. GENERAL

A comprehensive program will be followed to strengthen the technical and institutional capacities of the

executing agency (CDG-F), contractors, and laborers. Training program will be scheduled after approval of

ESMP from EPD. Labors will be trained before and during the execution of the project.

6.2. CONTRACTOR’S TRAINING

In order to comply with the anticipated environment and social attributes as described in ESMPs of the

PCGIP funded schemes of CDG-F, meetings will be held with the contractors of CDG-F to ensure the

socially acceptable and environmentally sustainable situation during execution of the schemes.

The Contractor will also be briefed about procedures and methods for complying with these general

environmental and social management conditions, and any specific conditions specified in an ESMP; a

description of specific mitigation measures that will be implemented in order to minimize adverse impacts;

a description of all planned monitoring activities.

Trainings for contractors will be organized when the bidding process will be completed. It will be suggested

to develop inventory at project site to address potential impacts during construction. Contractors shall be

bound for environmental and social compliance otherwise cost will be deducted as per break-down of

environmental mitigation cost (item wise) in ESMPs.

SECTION 6: CAPACITY BUILDING

Environment & Social Management Plan (ESMP)

The Urban Unit Page 24

Contractors shall also provide safety equipments i.e., PPEs, safe drinking water, first aid boxes etc. to the

workforce as per nature of their jobs. By ensuring all these mitigation measures; not only their company

profile shall boost up but also enable them to qualify and win the future projects. It will also be briefed that

the contractors having environmental and social safeguards expert in their company will be preferred during

evaluation.

Contractors have to comply with the following responsibilities:

Observation of timings and make a schedule that the surrounding community

should not affect from noise pollution, air emissions and disturbances in their

routine work and avoid use of heavy machinery in day hours.

Usage of machinery/equipments producing negligible/low noise.

Ensure health, safety and protective measures including safety equipment,

safe drinking water, first aid boxes etc. to the workforce as per nature of their

jobs.

Water sprinkling to avoid air pollution.

Indicate alternate routes and provide indicators on suitable places during

work timings.

Local labor should be preferred to work.

Child labor is strictly prohibited as per labor law. All labor should be more

than 14 year of age individually.

Information should be provided to the surrounding populations before pre-

construction and privacy of women should not be disturbed.

Proper disposal of wastes and garbage.

Health, safety and protective measures for the labor.

Notice board of emergency numbers should be placed on proper place

Environment & Social Management Plan (ESMP)

The Urban Unit Page 25

S-3

ANNEXURE A

ENVIRONMNETAL AND SOCIAL SCREENING FORM

1. Name of Scheme: R/I of roadside drain from Jattanwala chowk to Peeran wala chowk

2. Location of Scheme: G.M Abad, Faisalabad

3. Duration of Scheme: 04 Months

4. Name of Executing Agency: WASA, Faisalabad

5. Estimated No. of Labor involved: 25-30

6. Social Category

7. Environmental Category

A. SOCIAL ASSESSMENT

SECTION 1: BACKGROUND INFORMATION:

a. Nature of Area:

i. Residential ii. Commercial iii. Industrial

iv. Agricultural v. Residential cum Commercial

vi. Any other

b. Demography

i. Number of households in project area: 150

ii. Estimated number of persons/house: 06

iii. Estimated total population: 900

iv. Number of shops in the area: 05

v. Number of offices in the area: 00

vi. Number of mobile vendors seen in the area: 02

c. Public infrastructure present in the proposed area :

i. Shops ii. Banks iii. Shopping Plaza

iv. Offices v. Industrial areas

d. Civic facilities in the surrounding of proposed area?

i. School/college/university, (if yes)

1) Name: Govt. Girls Higher Secondary School, GM Abad

2) Public/Private-

3) Timing: 08 am- 2 pm

ii. Hospital/Dispensary/clinic (if yes)- No

1) Name:

2) Public/Private

E-2

Environment & Social Management Plan (ESMP)

The Urban Unit Page 26

3) Timing

e. Presence of Cultural/Archeological/Religious Sites

1) Mosque (if yes)

a. No. of mosques

b. Name of mosques

2) Church (if yes)

a. No. of church

b. Name of church (if yes)

3) Temples (if yes)

a. No. of temples

b. Name of temples

4) Forts- (No)

5) Tombs-

6) Graveyard- (No)

i) Muslims/ non-Muslims

f. No. of vendors/hawkers in the project area-

i) Permanent Hawkers (No)

a. If yes, then how many permanent hawkers _____

b. Timings of their coming ______

c. Nature of their business _______

ii) Mobile Hawkers

a. If yes, then how many mobile hawkers: 02

b. Timings of their coming: No specific timing

c. Nature of their business: Fruit, Vegetable etc

SECTION 2: SCREENING FOR POTENTIAL IMPACTS

a. Land Acquisition (No land will be acquired during scheme execution )

1. Total land / property needed to be permanently acquired (in kanals):

a. Ownership of the proposed land / property to be acquired (N/A)

b. Current use of proposed land / property to be acquired (N/A)

2. Will any land be acquired on a temporary basis for any purpose such as for storage of materials and

equipment?

a. Ownership of the proposed land / property to be acquired (N/A)

b. Current use of proposed land / property to be acquired (N/A)

.

vii. Nature of impacts on households: (Specify for how many days per type of loss and

for how many households)

a. Temporary loss of assets (green belt, sheds, footsteps etc.)

b. Temporary restriction of mobility

No

Yes

Environment & Social Management Plan (ESMP)

The Urban Unit Page 27

c. Temporary land acquisition for storage of machinery/equipment

viii. Total Number of affected households (if any): Not anticipated as pre scope of work

a. Public Service Facility in the scheme proposed area:

i. Electric Poles ii. Telephone cables iii. Telephone lines

iv. Gas pipelines v. Tube wells vi. Disposal station

vi. Water supply lines vii. Railway tracks xi. Sewerage/drains

b. Is there any identified impact on public utilities due to project activities?

No public utility would be affected as they are not existed within the project vicinity

c. Is there any identified impact on public infrastructure due to project activities?

No public utility existed within the project vicinity

Identify for how many days and for how many households per day

1. Can any of the impacts be mitigated without compensation?

(i) Restriction of mobility (Yes/No)

Describe how: Temporary restriction in mobility during road construction or dismantling can

be anticipated.

(ii) Impact on health (Yes/No)

Describe how:

(iii) Impact on property and items e.g. crops? (No)

Describe how:

SECTION 3: MITIGATION MEASURES

2. For impacts that cannot be mitigated, compensation needs to be provided:

(i) Temporary land acquisition

(ii) Loss of livelihoods

(iii) Loss of business income

(iv) Other

If this is required, a household level checklist will be filled to assess compensation

level.

(No such impact envisaged)

No

No

No

Environment & Social Management Plan (ESMP)

28

Table: Summary of Compensation (N/A)

Sr # Name of Affected

Households/

shopkeepers/hawkers/

any other

Address Contact Number Nature of

affect

Nature of

compensation

No. of

Days/hours

to be

affected

Compensation

Rate (Rs.)

Amount

Total Amount Rs.

Environment & Social Management Plan (ESMP)

The Urban Unit Page 29

B. ENVIRONMENTAL ASSESSMENT

a. Environmental assets of the proposed scheme area (No)

b. Forest

c. Wetlands

d. National Park

e. Farm House

f. Fish hatchery

g. Botanical garden

(No environmental sensitive area (b-c) lies within project vicinity)

2 = Minor Negative Impacts are considered as likely to have minimal or no adverse Environmental impacts

1 = Moderate Negative Impacts are defined as Less significant adverse impacts that may be easily prevented or mitigated

-1 = Major Negative Impacts are defined as significant, or irreversible adverse impacts

-2 = This category serves no impacts from projects

Scheme

1 2 3 4 5 6 7 8 9 10 11 12

Surface

and

Ground

Water

Quality

Water

Logging

Air

Quality

Noise

Solid

Waste

Destructi

on of

Habitat /

Vegetati

on

Disturba

nce to

Other

Services

Urban

Cong

estion

Urban

Aesthet

ics

Public

Health

&

Safety

Smell

&

Smok

e

Fire

Hazar

ds

2 -2 1 1 2 -2 2 -2 -2 1 -2 -2

Environment & Social Management Plan (ESMP)

The Urban Unit Page 30

ANNEXURE B

CHECKLIST FOR ENVIRONMENTAL MANAGEMENT OF E-2 CATEGORY SCHEMES

Environmental Assesment

Yes

No

If Yes, Specify Details

Environmental

Management

Measures

1. Will the scheme involve any of the

following changes in land use

classification?

No changes in Land

use patterns as

existing drain will be

repaired/rehabilitated

i. Conversion of recognized

environmentally / historically /

culturally sensitive land to any

other use.

ii. Conversion of open / recreational

areas to commercial / industrial

residential use.

iii. Conversion of residential /

industrial areas to industrial /

commercial use.

iv. Restoration of cultural heritage.

Any other. (please specify)

2. Will the scheme create risk of

contamination of ground/surface or

drinking water?

i) Effluents or leachate

ii) Due to leakages Leakage should be

properly mitigated

with engineering

solution.

iii) Any other? (please specify)

3. Will the scheme increase or decrease the

following?

i) Depth of GW table.

ii) Flow / quantity in water bodies.

4. Will the scheme have any possibility of

water spillage or water stagnation?

5. Will the scheme cause any air pollution? During road construction it

may lead to cause air

pollution and reduce road

side visibility.

Water sprinkling

should be

regularized. Ambient

air quality testing

should be carried out

for air quality

assessment before

and during scheme

execution.

Environment & Social Management Plan (ESMP)

The Urban Unit Page 31

6. Will the scheme cause noise pollution? It might create nuisance for

locals due to working of

unmaintained machinery.

Good machinery

should be used to

reduce its impact.

7. Will the scheme generate solid waste? Solid waste can be

generated during

construction phase

Piling of solid waste

should be prohibited

& dispose off at

designated disposal

point of

CDGF/WASA.

8. Will the scheme result in cutting of trees? No trees were found

to be affected in

that area

9. Will the scheme damage or disturb other

service lines?

i) Water supply lines

ii) Electric cables

iii) Roads

iv) Telephone cables

v) Any other (please specify)

10. Will the scheme cause any health hazard?

11. Will the scheme create smell and / or

smoke?

12. Will the scheme cause any effect on flora

and fauna?

No biological

diversity found in

that area to be

affected

13. Will land be acquired temporarily for

storage of machienry/equipments and

other contruction material

14. .Will land be acquired for the building of

the road itself

The roadside drain is

only improved.

Environment & Social Management Plan (ESMP)

The Urban Unit Page 32

ANNEXURE C

CHECKLIST FOR DRAINAGE

Description Status Notes

What is the mode of drainage in the area?

i. Open drain System

Road side drain will be repaired

under scope of work. It will help

in avoiding stagnation of water

during rains. ii. Closed Drain System

iii. Septic Tanks

Are the sewerage / drainage facilities available in the

scheme area ?

i. Sewerage system Sewerage network is available

in the vicinity of scheme but

meeting the demand.

ii. Open drains

iii. Disposed in street

Are the sewerage/ drainage facilities available in the

scheme area?

If not how the impact of stagnant waste water will be

mitigated?

Does the drainage network need

i. Replacement of out-lived infrastructure

ii. Repair of existing drains

Existing roadside drain will be

repaired through this scheme.

Is the laboratory analysis of the water source attached?

Water quality analysis will be

carried out as per desire of

ESMF committee.

Is there any impact of scheme on the ground water?

Is there any pumping station available?

When will drainage and/or sewerage improvements be

made to this area?

i) Next year

ii) Within five years

iii) No Plan

Public Consultation Forms

The Urban Unit Page 33

Is there any impact of scheme on the ground water?

No impact envisaged as no deep

ditching or excavation will be

carried out under scope of work.

Is the scheme operationally sustainable? Scheme is operationally

sustainable as it will avoid

stagnation of storm water

during rain and will sustain

road structure.

Ongoing monitoring for checking the drinking water

quality

i. Twice a year

ii. Thrice a year

Drinking water quality

analysis carried out where any

issue raised.

iii. Regular basis

Public Consultation Forms

The Urban Unit Page 34

ANNEXURE D

Public Consultation Forms

Public Consultation Forms

The Urban Unit Page 35

Public Consultation Forms

The Urban Unit Page 36

Public Consultation Forms

The Urban Unit Page 37