reduction of operator’s loading and unloading …...lean systems are used in industries on the...
TRANSCRIPT
http://www.iaeme.com/IJMET/index.asp 207 [email protected]
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 10, October 2017, pp. 207–216, Article ID: IJMET_08_10_025
Available online at http://www.iaeme.com/IJMET/issues.asp?JType=IJMET&VType=8&IType=10
ISSN Print: 0976-6340 and ISSN Online: 0976-6359
© IAEME Publication Scopus Indexed
REDUCTION OF OPERATOR’S LOADING AND
UNLOADING TIME USING LEAN SYSTEMS
FOR PRODUCTIVITY IMPROVEMENT
A. Gnanavelbabu
Department of Industrial Engineering, CEG Campus,
Anna University, Chennai, Tamilnadu, India
P. Arunagiri, G. Bharathiraja, V. Jayakumar and V. Velmurugan
Department of Mechanical Engineering, Saveetha School of Engineering,
Saveetha University, Chennai, Tamilnadu, India
ABSTRACT
The objective of this paper is to implement the concepts of lean production in
terms of waste elimination, in the matter of identification of waste time, factors
leading to it and eventually reduce\eliminate the same to provide guidance to the
industry. The research describes an approach to wait time waste of operator manual
loading and unloading time measurement. It is uniformly applied and creates results
that can be compared from one production line to another. The wait time waste
elimination method is a common approach for gathering and combining data to
support identification and elimination of time waste in the industrial lifecycle of a
product unit. The lean production system is to determine an efficient production
process through the removal of waste and to implement a flow. Wastes of various
types are seen in the manufacturing area. One among them is the time taken for
loading and unloading of work piece. Reduction in time waste will improve the each
production line and in an overall improvement in the number of components produced
per shift. Industrial data analysis has been carried out for calculating the current time
taken and improving the production process by setting the optimal time to get the
required output in terms of increase in the number of components produced per shift.
Keywords: Waiting time, Lean production, Optimised time, Allocated time, Actual
time.
Cite this Article: A. Gnanavelbabu, P. Arunagiri, G. Bharathiraja, V. Jayakumar and
V. Velmurugan, Reduction of Operator’s Loading and Unloading Time using Lean
Systems for Productivity Improvement, International Journal of Mechanical
Engineering and Technology 8(10), 2017, pp. 207–216.
http://www.iaeme.com/IJMET/issues.asp?JType=IJMET&VType=8&IType=10
Reduction of Operator’s Loading and Unloading Time using Lean Systems for Productivity
Improvement
http://www.iaeme.com/IJMET/index.asp 208 [email protected]
1. INTRODUCTION
Lean systems are used in industries on the basis of the requirement of the relevant lean tools
and techniques. Every firm uses specific lean tools to reduce the waste and increase the
number of components produced over a period of time. Roberto Panizzolo (1998) has worked
on lean production model by 27 excellent firms. Their study suggests that the implementation
of lean production principles and the perspective analysis shifted from operations
management to relationships management. Suggestions for future research have been
indicated through the empirical findings. Tu et al (2006) stated that the review of absorptive
capacity and develop the reliable instrument to measure the impact of organization. Fawaz
Abdulmalek & Jayant Rajgopal (2007) have made a study o the impact of lean principles
adopted in a large steel mill. The VSM tool was used to solve the problems in the firm.
Moreover a new simulation model has been developed for lead time and inventory reduction.
Richard Lindeke et al. (2009) state that the Temporal Think Tank (TTT) brings round all to
work as a team to develop their decision making skills to incubate new process or products
and after some time the individual are return to original position to implement the learned
procedure. Tarcisio Abreu Saurin & Cleber Fabricio Ferreira (2009) has made an assessment
of the impact of LPS (Lean Production System) on working conditions in a harvester
assembly line of an American-owned plant in Brazil. They have grouped the data collected as
work content, work organization, continuous improvement and health and safety. The
working conditions were fairly good and had improved after the introduction of LPS.
Krisztina Demeter & Zsolt Matyusz (2011) have focused on improvement of the inventory
turnover performance using lean systems. Firms that widely apply lean systems have high
inventory turnover than those that do not rely on lean systems. The data were analysed using
International Manufacturing Strategy Survey (IMSS). Kuhlang et al. (2011) have suggested a
methodical approach connecting the VSM and Method Time Measurement (MTM) and offers
new advantages to reduce the lead time and increase productivity. Arnout Pool et al. (2011)
affirm that the cyclic schedules fit in a lean improvement approach for the semi-process
industry. The cyclic schedules help to improve production quality and supply-chain
coordination and discrete event simulation. It is useful tool in facilitating a participative
design of a cyclic schedule. Noor Azlina et al. (2012) found a company that had implemented
green lean total quality information management have seen good financial outcomes in
Malaysian automotive industries. Stewart Robinson et al. (2012) have used discrete event
simulation and lean care approaches for the improvement of process and service delivery in
health care systems. Richard turner & Ju Ann Lane (2013) list the specific applications of the
concepts to support coordination of systems engineering activities with large scale system
acquisition, development and evolution. Sharma Neha et al. (2013) have studied application
of the lean systems leading to the continuous production process with a focus of the steel
industry. Sukhwinder Singh Jolly (2013) have reviewed the role of lean manufacturing
for various organization, lean manufacturing techniques and the benefits achieved through
lean systems. Matt & Rauch (2013) have analyzed the suitability of existing lean methods in
small size enterprises in Italy. Through a case study the difficulties in the implementation
stage and how to eradicate the same were discussed. Keitany & Riwo Abudho (2014) have
identified the impact of lean towards tools, quality, employee perceptions, and challenges.
Findings suggest that lean can improve using latest technology, customer involvement, reduce
resistance, challenges faced while adopting lean in Kenyan industries. Daryl Powell et al.
(2014) focus on the production line of main leaf spring. Analysis of the current map with the
experts and a future map is designed to propose a different way to reduce lead-time and to
increase productivity/ output. Michael Dwianto Nirwan & Wawan Dhewanto (2015) support
focus of lean startup methodology on agile testing and learning cycle for validating
A. Gnanavelbabu, P. Arunagiri, G. Bharathiraja, V. Jayakumar and V. Velmurugan
http://www.iaeme.com/IJMET/index.asp 209 [email protected]
hypotheses. The various barriers for implementation of lean in Indonesian environment and
the success rate of lean in United States environment has been discussed.
2. METHODOLOGY
The purpose of the methodology is to achieve the objective of the work. It is a guideline to
analyze wait time using the eight step Practical Problem Solving method. The step by step
process as elaborated below was used to find out the operators manual wait time reduction.
The 8 step problem-solving methodology was used for crank case cell in Greaves Cotton (P)
Ltd, Ranipet, India. The step by step process involved in the eight step PPS methodology is
listed below. xt into it.
A) Clarify the Problem
In the current situation, the number of components produced per shift was focused for the
entire sections crank case cell. The number of the components manufactured in ideal
condition was determined. There was a wide gap between the allocated time and actual time.
B) Break down the Problem
The process involved in the operators manual loading and unloading operation time was
carefully studied. Duration of inactivity or time wasted on unnecessary efforts was identified.
C) Set the Target
The current level of production was observed and production level considered ideal for the
optimal time was set. The aim of the target setting was to increase the output from current
level to targeted level.
D) Analyze the Root Cause
Fish bone diagram was used to identify the various causes for the reduction of loading and
unloading time during the production process as shown in Figure 1 below.
Figure 1 Fish bone diagram to find loading and unloading time
E) Develop Countermeasures
1. The operator’s loading and unloading time for each process was tabulated.
2. The total operator allocated and actual time for each level has been calculated.
3. Graphs were plotted between the number of operations Vs Operators Allocated time,
Actual time and optimized time of crank case cell.
4. The actual processing time per shift in crank case cell were calculated.
5. The optimized operators loading and unloading time per shift in crank case cell were
calculated.
Mapping the
current
production
process.
Calculate the
loading and
unloading time
for each
operation.
Calculate the
optimized time for
each loading and unloading
operation.
Setting the optimised
time for the loading and
unloading .
Increase the number
of components
produced per shift .
Reduction of
loading and
unloading time
during production
process
environment.
Reduction of Operator’s Loading and Unloading Time using Lean Systems for Productivity
Improvement
http://www.iaeme.com/IJMET/index.asp 210 [email protected]
F) Implementation of the Countermeasures
The various activities carried out in various sections were mapped. The section mapping gave
a clear idea of material movement from the first machine to the last machine till it was
converted into the finished product. The implementation of the reduction in operators loading
and unloading time was been carried out in the various sections. The results were monitored
and increase in the number of components per shift was calculated.
3. PROCESS MAPPING OF PRODUCTION AREA FOR CRANK CASE
CELL
Mapping the production process in Greaves cotton (P) Ltd for different sections of the
production system was done. The various areas in the production system are crank case cell
was first taken up and mapping was done mapped based on the various operations carried out
in this section and the movement of the material from machine 1 to machine 18 was carefully
studied. The movement of material is shown in Figure 2 below.
Figure 2 Process mapping of crank case cell
A) Operators Loading and Unloading Time MUDA Analysis in the Crank Case
Cell
For each set of machines from machine 1 to machine 16, the total allocated time, and actual
time were calculated and the optimized time was set to find the ideal output. The graphs were
plotted for the allocated, actual and the optimized manual operators loading and unloading
time for each operation as shown in the Figure 3 below.
Figure 3 Number of operation carried out Vs allocated time, actual time and optimized time for crank
case cell
Machine
2
Machine
1
Machine
4
Machine
3
Machine
5
Machine
6
Machine
7
Machine
8
Machine
9
Machine
10
Machine
11
Machine
12
Machine
13
Machine
14
Machine
16
Machine
15
Machine
17
Machine
18
A. Gnanavelbabu, P. Arunagiri, G. Bharathiraja, V. Jayakumar and V. Velmurugan
http://www.iaeme.com/IJMET/index.asp 211 [email protected]
B) Monitoring the Process and Results for Operator’s Allocated, Actual and
Optimized Time in Crank Case Cell
The time calculation has been carried out for allocated processing time per shift in crank cell.
The actual and optimized processing time can be calculated accordingly. The allocated time
for loading and unloading was 30 seconds. During the actual production, the time taken was
very much less when compared to the allocated time. The operators loading and unloading the
time taken was approximately 20 – 25 seconds. To achieve a optimum output, an optimized
time of 20 seconds was set for loading and unloading and output parameters were calculated
with reference to this time. The total time saved per shift was 39 minutes. The average time
for producing one component was 3 minutes and the number of components produced in the
optimized time was 161 per shift and 483 components per day. The current performance,
modified performance and the time were noted after re-modification of the system calculated
which indicated the improvement in the productivity. The simulated results using the Pro
model software also indicates that there is improvement in the number of components after
modifying the optimized operator manual loading and unloading time.
C) Simulation Carried out for Allocated Time Using Pro model Software in
Crank Case Cell
Single capacity locations are those that have the capacity for handling one job at a time.
Multi-capacity locations are those that involve handling more than one job at a time. Here, in
the case, taken up single capacity locations were the machines on the shop floor and multi-
capacity locations were the pallets, inspection deck, rack etc. The first set of machines include
a Vertical Machine Centre (VMC)1-VMC 8, a total of 8 machines and the second set included
VMC 9- VMC 16. The VMC was simulated as Lathe due to non-availability of options in the
Pro model software for all the simulated results.
Figure 4 Location utilization for allocated time in the crank case cell
For the first set of machines, the location utilization was 100% from start to end of the
schedule. For the second set, only 33% was utilized at the start of the operation. Starting hour
1, there was an increase in the utilization rate from 33% to 64%. This gradually decreased
during hour 2 to 54% and in hour 3 to 52 %.The utilization remained constant at hour 3 and
hour 4. At hour 5 there was an increase in utilization to 62% which was constant at hour 6
also. At the end of the operation at hour 7 the utilization decreased from 62 % to 56% which
ended the operation schedule as shown in Figure 4 above.
Reduction of Operator’s Loading and Unloading Time using Lean Systems for Productivity
Improvement
http://www.iaeme.com/IJMET/index.asp 212 [email protected]
Figure 5 Simulated results for allocated time in the crank case cell
Figure 5 above indicates the various factors that were considered by the software during
the simulation. First consideration of the entity states graph, indicated the current status of the
jobs under process. In other words, it can also be called as work in process status. As
mentioned earlier, the researcher has considered one type of job for crank case cell. Here,
product 1 was completed by 23%, of effort. Similarly, the total output from the system was
104 from type 1. The average time in the system was 3.81 hours for one product and average
was 0.88 hours for the specific operation. In multi-capacity location state the pallets for part
storage were considered. Here 100% utilization was seen for the pallets and emptiness is nil.
Figure 6 Machine utilization for allocated time in the crank case cell
The machines processing the jobs were under the single capacity location. The first set of
machines included VMC 1-VMC 8 utilized fully 100% during the 8-hour schedule. The
second set of machines included VMC 9-VMC 16 which utilized only 55% during the
operation and 45% of the machines remained idle as shown in Figure 6 above.
A. Gnanavelbabu, P. Arunagiri, G. Bharathiraja, V. Jayakumar and V. Velmurugan
http://www.iaeme.com/IJMET/index.asp 213 [email protected]
D) Simulation Carried out for Actual Time Using Promodel Software in Crank
Case Cell
Here in the case, single capacity locations were the machines on the shop floor and multi-
capacity locations were the pallets, inspection deck, rack etc. The first set of machines
included VMC 1-VMC 8, of 8 machines in all were there in the first set. The second set
included VMC 9- VMC 16 as shown in Figure 7 below.
Figure 7 Location utilization for actual time in the crank case cell
For the first set of machines, the location utilization was 100% from start to end for the
schedule. For the second set, at only 31% was utilized at the start of the operation. From hour
1 there was an increase in the utilization rate from 31% to 64%. This gradually decreased
during hour 2 to 58% and in hour 3 to 56 %.The utilization remained constant at hour 3 and
hour 4. At hour 5, there was an increase in utilization to 58% and the utilization for hour 6
was 64%. This remains constant at hour 7 also.
Figure 8 Simulated results for actual time in the crank case cell
Reduction of Operator’s Loading and Unloading Time using Lean Systems for Productivity
Improvement
http://www.iaeme.com/IJMET/index.asp 214 [email protected]
Figure 8 indicates the various factors that were considered by the software during the
simulation. To start with, consideration of the entity states graph, indicates the current status
of the jobs being processed. In other words, it can also be called as work in process status. As
mentioned earlier, it was considered as one type of job for crank case cell. Presently Product 1
is completed by 23%, similarly, the total number of product from the system were 112
products for type 1. The average time in the system was 4.01 hours for one product and the
average time of operation was 0.87 hours. In the multi-capacity location state, the pallets for
part storage were considered. Here 100% utilization was seen for the pallets and emptiness is
nil.
Figure 9 Machine utilization for actual time in the crank case cell
The machines processing the jobs come under the single capacity location. The first set of
machines included VMC1-VMC 8 which was utilized 100% during 8-hour schedule as shown
in Figure 9 above. The second set of machines included VMC 9-VMC 16 which was utilized
only at 55 % during the operation. 45% of the machines remained idle. The Pro model
software simulated results indicated an increase in the number of components. Both the
calculated and simulated results show positive with the outputs
E) Standardize and Share Success
Various steps were taken over a period of time for monitoring the operator manual loading
and unloading time. Material movements were carefully monitored. Man and material
movement considered unnecessary were avoided by setting the optimized time for the loading
and unloading. The setting of the optimized time periodically increased the daily output. The
output from the crank case cell showed a marginal change per shift.
4. CONCLUSIONS
Today lean faces a major challenge for implementation in industries. But many industrial
organizations have started adopting various techniques for ensuring productivity improvement
and to stay in the market. Process mapping has been done for the crank case cell and
individual process mapping has been done for all the above sections. The problem was solved
using the 8 step PPS methodology. In crank case cell , the number of output per shift before
optimization was 148 whereas the number of output per shift after optimization was 161
components per shift. The number of components increased from 444 to 483 components in
crank case cell. The output increase in the crank case cell was found. The types of lean waste
analyzed were waiting time reduction, motion, transportation and over processing. The lean
tools used are concepts of Process mapping, 8 step problem-solving methodologies,
A. Gnanavelbabu, P. Arunagiri, G. Bharathiraja, V. Jayakumar and V. Velmurugan
http://www.iaeme.com/IJMET/index.asp 215 [email protected]
elimination of waste, Set up time reduction. Here increase in the output in the industrial data
analysis results after setting the optimized loading and unloading time increases the number of
components per shift. The results indicate that there is impact of lean systems for the
productivity improvement in automobile industries.
REFERENCES
[1] Arnout Pool, Jacob Wijngaard & Durk-Jourkevan der Zee 2011, Lean planning in the
semi-process industry a case study, International Journal of Production Economics, vol.
131, pp. 194-203.
[2] Daryl Powell, Erlend Alfnes, Jan Ola Strandhagen & Heidi Dreyer 2014, The concurrent
application of lean production and ERP: Towards an ERP-based lean implementation
process, Computers in Industry, vol. 64, pp. 324–335.
[3] David Van Losonci, Krisztina Demeter & Istvan Jenei 2011, Factors influencing
employee perceptions in lean transformations, International Journal Production
Economics, vol. 131, pp. 30–43.
[4] Fawaz A Abdulmalek & Jayant Rajgopal 2007, Analysing the benefits of lean
manufacturing and value stream mapping via simulation: A process sector case study,
International Journal of Production Economics, vol. 107, pp. 223–236.
[5] Keitany, P & Riwo Abudho 2014, Effects of lean production on organisational
performance A case study of flour producing company in kenya, European Journal of
Logistics Purchasing and Supply Chain Management, vol. 2, no. 2, pp. 1-14.
[6] Krisztina Demeter & Zsolt Matyusz 2011, The impact of lean practices on inventory
turnover’, International Journal of Production Economics, vol. 133, pp. 154–163.
[7] Kuhlang P, Edtmayr T & Sihn, W 2011, Methodical approach to increase productivity and
reduce lead time in assembly and production-logistic processes’ CIRP Journal of
Manufacturing Science and Technology, vol. 4, pp. 24–32.
[8] Matt, DT & Rauch, E 2013, Implementation of Lean production in small sized enterprises,
Procedia CIRP, vol. 12, pp. 420-425.
[9] Michael Dwianto Nirwan & Wawan Dhewanto 2015, Barriers in implementing the lean
startup methodology in Indonesia – case study of B2B start up, Procedia social and
behavioral sciences, vol. 169, pp. 23-30.
[10] Noor Azlina, Mohd.Salleh, Salmiah Kasolang & Ahmed Jaffar 2012, Green lean total
quality information management in Malaysian automotive companies, Procedia
Engineering, vol. 41, pp. 1708-1713.
[11] Richard R Lindeke, David A Wyrick & Hongyi Chen 2009, Creating change and driving
innovation in highly automated and lean organisations: The Temporal Think Tank,
Robotics and Computer Integrated Manufacturing, vol. 25, pp. 879-887.
[12] Roberto Panizzolo 1998, Applying the lessons learned from 27 lean manufacturers. The
relevance of relationships management, International Journal of Production Economics,
vol. 55, pp. 223-240.
[13] Sharma Neha, Matharou Gurupreet Singh, Kaur Simran & Gupta Pramod, Lean
manufacturing tool and techniques in process industry, International Journal of Scientific
Research and Reviews, vol. 2, no. 1, pp. 54-63.
[14] Stewart Robinson, Zoe J Radnor, Nicola Burgess & Claire Worthington 2012, Simlean:
Utilising simulation in the implementation of lean health care’, European Journal of
Operation Research, vol. 219, pp. 188-197.
[15] Sukhwinder singh jolly 2013, A review on lean manufacturing: A feasible solution to
industrial objectives, International Journal of Engineering and Management Research, vol.
3, no. 2, pp. 13-16.
Reduction of Operator’s Loading and Unloading Time using Lean Systems for Productivity
Improvement
http://www.iaeme.com/IJMET/index.asp 216 [email protected]
[16] Tarcisio Abreu Saurin & Cleber Fabricio Ferreira 2009, The impacts of lean production
on working conditions: A case study of a harvester assembly line in Brazil, International
Journal of Industrial Ergonomics, vol. 39, pp. 403–412.
[17] Tu, Q, Vonderembse, MA, Ragunathan, TS. & Sharkey, TW 2006, Absorptive capacity:
Enhancing the assimilation of time-based manufacturing practices Journal of Operations
Management, vol. 24, no. 5, pp. 692–710.
[18] Singh M.P., Ramphool Meena and Avinash Panwar, A Survey on the Adoption of Lean
Practices in Indian Manufacturing Sector, International Journal of Industrial Engineering
Research and Development, 7(2), 2016, pp. 52–62.
[19] Shahryar Sorooshian and Tan Ai Fen, Applicability of Manufacturing Lean Tools in
Service Operations, International Journal of Mechanical Engineering and Technology
(IJMET), Volume 8, Issue 7, July 2017, pp. 53-60
[20] M.Indira and M. Venkata Jyothsna, An Approach to Effective Construction Management
Based on Lean Construction Techniques, International Journal of Civil Engineering and
Technology (IJCIET) Volume 8, Issue 4, April 2017, pp. 1954-1959
[21] Hari Supriyanto and Diesta Iva Maftuhah, A Lean Six-Sigma Manufacturing Process Case
Study, International Journal of Mechanical Engineering and Technology (IJMET) Volume
8, Issue 7, July 2017, pp. 498-509