recent nysdot bridge failure ivestigations_ub presentation

83
7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 1/83 Bridge Failures - Lessons learned Recent NYSDOT Bridge Failure Investigations George A. Christian, P.E. Director, Office of Structures New York State Dept. of Transportation Bridge Engineering Course University at Buffalo March 29, 2010

Upload: albertofgv

Post on 03-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 1/83

Bridge Failures - Lessons learned

Recent NYSDOT Bridge Failure Investigations

George A. Christian, P.E.Director, Office of Structures

New York State Dept. of Transportation

Bridge Engineering Course

University at Buffalo

March 29, 2010

Page 2: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 2/83

2

I-787 - Dunn Memorial Bridge Interchange

Albany, NY

partial collapse at pier 11- August 2005

I-787 Ramp NB toSouth Mall

Expressway WB

(BIN 109299A)

Page 3: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 3/83

3

BIN 109299A

Page 4: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 4/83

4

Structure Layout (looking east)

Page 5: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 5/83

5

Overview of Failure

Page 6: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 6/83

6

High Rocker Bearings

Page 7: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 7/83

7

History of Misalignment of High

Rocker Bearings at Pier 11

1987Inspection

Temp. @ 45 °

1999Inspection

Temp. @ 70 °

Page 8: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 8/83

8

2003 Inspection – Span 12 East Bearing

Temp @ 45 F

Lifted 0.25 ft.(3 in.) - Eccentricity = 3.4 in.

Page 9: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 9/83

9

How did the bearings get misaligned?

Superstructure Displacements:• Survey of adjacent piers (w/ fixed bearings)

 – Pier 10 displaced north 1.6 inches.

 – Pier 12 displaced north 1.0 in (avg.) 1.7 inches oneast side.

• History of Pier 13 joint

 – Joints ‘reset’ (vertical) in 1990

 – Joint was closed in 1990

 – Closed in 1995 thru present

• Longitudinal forces due to braking, centrifugal force

Page 10: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 10/83

10

Condition of Rocker Bearings

• Susceptible to corrosion, debris when continuallytilted

• Corrosion, debris prevents rocking back towardvertical

 – Under rocker – Pin corrosion

• Contact surfaces flatten or “dish”

• Result: Bearings become resistant to horizontal 

movement, especially back toward being plumb .

Transfers longitudinal forces to substructure

Page 11: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 11/83

11

Corrosion &

Flattening

Page 12: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 12/83

12

Frozen Pins

Page 13: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 13/83

13

Rocker and Pintle Corrosion – Span 11

Bearing

Page 14: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 14/83

14

Pier 11

• Height: 82.3 feet

• 13.9’ x 6.44’ at

base

• 9’ x 4’ at top of 

stem

• Stem rebar: 46 -

# 8 bars

Page 15: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 15/83

15

Pier 11: Lack of Elastic Range

• Cracks 40 ft. upnorth face

• Rebounded51/2 in. when‘released’

• The pier failed

in flexure

Page 16: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 16/83

16

Comparison of Adjacent Piers

PIER

NO.

HGT. BASE REINFORCING STEEL

No.-Size Bars Area

BEARINGS

FIX OR EXP

9 67.47’ 131.4” x 71.2” 42 - # 8 33.18 Fix - Exp

10 72.79’ 132.6” x 72.6” 36 - #11 56.16 Fix

11 82.31’ 166.6” x 77.3” 46 - # 8 36.34 Exp - Exp

12 83.38’ 155.3” x 77.6” 42 – #11 65.52 Fix

13 84.75’ 156.4” x 84.2” 42 - #11 65.52 Exp - Exp

Page 17: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 17/83

17

Pier 11 Design Check

• Designed per 1965 AASHO code

• Meets strength req. for code assumptions

 – Allowable / Actual ratio = 0.98 =1.0 (OK)

• No provision for large flexural displacements

• Equivalent Column with 1% reinforcing.

Page 18: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 18/83

18

Results of Pier Analysis

• Limited elastic range - yields at 5.5” deflection

• Cracking at 2.5” deflection

• No capacity increase beyond cracking

Old Pier 11 (AC-12)

0

20

40

60

80

100

120

140

160

0 5 10 15 20

Longitudinal Pier Cap Displacement [in.]

   L   o   n   g   i   t  u   d   i   n   a   l   P

   i   e   r   C   a   p

   F   o   r   c   e   [   k   i   p   s   ]

f’c=9

210psi

Page 19: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 19/83

19

Forces Needed for Failure

• Thermal: limited by resistance of bearing

 – Up to 0.58 x Dead Load if sliding assumed: approx.

200 kip from Span 12 only

 – Limited range of movement

• Corrosion Build-up:

 – Develops horizontal component of vertical dead, live

load reactions

 – Larger range of movement

Page 20: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 20/83

20

Probable Failure Sequence

• Bearings tilted to north > 20 years ago

• Bearings begin to resist horizontal mov’t.

• Superstructure longitudinal displacements began tomove pier instead of Span 12 bearings

• Bearings resist movement moving back toward vertical – Increased southward tipping of Span 12 and 11 bearings

• Instability point reached – bearings tipped

• Forces (displacements) sustained to deflect pier 16 +

in. (bearings tipping and spans falling on tippedbearings)

Page 21: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 21/83

21

Page 22: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 22/83

22

Page 23: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 23/83

23

Page 24: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 24/83

24

Page 25: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 25/83

25

Page 26: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 26/83

26

Page 27: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 27/83

27

Page 28: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 28/83

28

Page 29: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 29/83

29

Page 30: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 30/83

30

Page 31: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 31/83

31

Page 32: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 32/83

32

Page 33: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 33/83

33

Underlying Cause of Failure

1. Rocker bearings becoming misaligned

2. Rocker bearing not functioning properly

3. Pier 11 was flexible in direction longitudinal

to the bridge

4. Pier 11 stem was “lightly” reinforced, and

not elastically ductile

• 1, 2 and 3 were required for failure to occur.

4 may have been required, but contributed 

to extent of failure

Page 34: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 34/83

34

Page 35: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 35/83

35

Page 36: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 36/83

36

Follow up actions

• Reviewed all high rocker bearings with low

inspection ratings (CR 3 or less)

• Inspected those overextended

• Preventive interim retrofits – bolsters

• Technical Advisory: INSP 05-001

Page 37: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 37/83

37

Follow up actions

• Bolsters installed as an extraordinary

precautionary measures on 10 bridges

• Alerted other owners of bridges not under

DOT’s inspection jurisdiction

• Corrective action:

 – Dunn Complex, bearing replacements

Page 38: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 38/83

Marcy Pedestrian Bridge CollapseOctober 2002

South Abutment

 North Abutment

Bracket

Field Splice

Span = 171 ft.

Page 39: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 39/83

Acknowledgements

• Sponsored by New York State DOT

• P.I.—Weidlinger Associates, Inc.

• Material testing and weld inspections by

ATLSS Research Engineering Center, Lehigh

University

Page 40: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 40/83

Outline

1. Collapsed Bridge

2. Review of Bridge Design

3. Analysis of Bridge Failure

4. Demolition

5. Laboratory Testing

6. Conclusions

7. Recommendations

8. NYSDOT Actions

9. Applications—Tub girders and beyond

Page 41: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 41/83

Tub Girder Cross Section

Intermediate

Diaphragm

 

14.0 ft (4.27 m)

   6 .   3

   f   t   (   1 .   9

   3  m

   )

4.3 ft (1.3 m)

Page 42: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 42/83

Collapsed Bridge

 North Abutment

South Abutment

Screed

Page 43: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 43/83

Collapsed Bridge

South Abutment

Exp. Bearing

Page 44: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 44/83

Collapsed Bridge

 North AbutmentFixed Bearing

Page 45: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 45/83

2. Review of Bridge Design

Objective: Evaluate the adequacy of the

bridge design

Page 46: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 46/83

2.1 Design Codes

• NYS Standard Specifications for Highway Bridges with

provisions in effect as of April 2000.

•  AASHTO Standard Specifications for Highway Bridges, 16th

Ed. LFD (1996) with 1997, 1998 & 1999 interim

• · AASHTO Subsection 10.51 Composite Box Girders (LFD) ….

“This section pertains to the design of … bridges of 

moderate length supported by two or more single cell composite box girders…..” 

Page 47: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 47/83

2.3 Finished Bridge

• Design assumption: Two I-girders

• Conclusions: The bridge, as designed, would have been

sufficient to resist its design loads if it had survived itsconstruction.

Page 48: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 48/83

2.4 During Construction

Failure Modes:

• b/t of top flange;

Top flange buckling (betweenintermediate diaphragms)

• Global Torsional buckling

IntermediateDiaphragm

Top

Flange

Page 49: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 49/83

3. Analysis of Bridge Failure

Objective: To find and prove the cause of failure

Page 50: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 50/83

Metal Form

Angle

Bottom Flange

Bracket

(3' apart)

Form/Catwalk 

Tie-rod

(4' apart)

Web Concrete

Top Flange

Web

Hanger West

Operator 

Drum

C.L. Bridge

Engine

Screed

East

3.1 Deck Construction Facilities:

3 3 El i B i

Page 51: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 51/83

Top

Top Steel Plate

Bottom Steel Plate

Elastomer 

Steel

Plates

a). Expansion Bearing

Top Steel Plate

Bottom Steel Plate

 b). Fixed Bearing

Steel Pin

k ESk ES

k EC

X

Y

Z k BRG=k ES+k PIN

k FS

k EC

X

Y

Z

FD

 Nonlinear Spring

k PIN

3.3 Elastomeric Bearings

Page 52: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 52/83

0

10000

20000

30000

40000

50000

0 1 2 3 4 5 6 7 8 9 10

Deformation, mm

   F  o  r  c  e ,

   N

36 mm dia

Applied Force

SteelPlate

Force-Deformation CurveFixedBoundary

     9     4    m    m

3.4 Fixed Bearing Steel Pin Model

Page 53: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 53/83

End

Diaphragm

Top Flange

Top Flange

Web

Diaphragm

Strut

3.5 Global Model

Page 54: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 54/83

SW+DL (rebar, form, etc.)Concrete Screed

Steel girder 

North

 Abutment

-10.0

-9.0

-8.0

-7.0

-6.0

-5.0

-4.0

-3.0

-2.0

-1.0

0.0

0.0 10.0 20.0 30.0 40.0 50.0

Concrete Pour Length, m

   G   i   r   d   e   r   R   o   t   a

   t   i   o   n ,

   D   e   g   r   e   e

 As-built

 As-designed (ideal)

Y

Rotation

42'

105'

3.6 Analysis Results

Page 55: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 55/83

Middle Screw

Location

Edge Screw

Location3.7 Corrugated Metal Form

Form Thickness = 1.2 mm (3/64 in.)Top Flange

Page 56: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 56/83

F

Fixed Boundarya

Weak Form: a=1/2" (12 mm)

Fy = 40 ksi (275 MPa)

Strong Form: a=3/4" (20 mm)Fy = 45 ksi (310 MPa)

3.9 Form Connection Model

Page 57: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 57/83

Page 58: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 58/83

-10.0

-9.0

-8.0

-7.0

-6.0

-5.0

-4.0

-3.0-2.0

-1.0

0.0

0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0

Concrete Pour Length, m

   G   i  r   d  e  r

   R  o   t  a   t   i  o  n ,

   D  e  g  r  e  e

As-designed (ideal),

 No form

As-built

 No form

Strong form,

as-built

Weak 

form,

as-built

42' 82'95' 105'

Y

Rotation

3.11 Force-Rotation Curve

Page 59: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 59/83

4. Demolition

• Remove debris safely;

• Sample materials;

• Preserve evidence

Temp. Support

Cut Location

Objectives

Page 60: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 60/83

5. Laboratory Testing

• Verify Analysis Assumptions

• Check whether materials conform to contract specifications

Objectives:

Page 61: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 61/83

0

2000

4000

6000

8000

10000

12000

0 2.5 5 7.5 10 12.5 15 17.5 20 22.5 25

Lateral Deformation, mm

   F  o  r  c  e ,

   N

Force-Deformation Curve

of Form Connections

Strong Form Model

Weak Form Model

Lab Results

5.1 Form Connection Tests

Form connection test

Gage 12

Steel PL

Form

Screw

Page 62: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 62/83

0

2000

4000

6000

8000

10000

12000

0 2.5 5 7.5 10 12.5 15 17.5 20 22.5 25

Lateral Deformation, mm

   F  o  r  c  e ,

   N

Force-Deformation Curve

of Form Connections

Strong Form Model

Weak Form Model

Lab Results

5.1 Form Connection Tests

Form connection test

Gage 12

Steel PL

Form

Screw

Page 63: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 63/83

b. Bearing Model

Fixed Boundary

a. Damaged Fixed Bearing

5.2 Bearing Inspection

Page 64: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 64/83

6. Conclusions

• The bridge failed in a global torsional mode;

• Stay-in-place forms greatly delayed thecollapse, but were not strong enough toprevent it;

• Progressive failure of form connections thatinitiated the failure sequence

• The bridge would have buckled even if thetwo deck haunches were identical

Page 65: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 65/83

7. Recommendations

• Clarify applicable codes;

• Add a new code provision that requires full 

length lateral bracing to be installed between

top flanges unless proven unnecessary by 

analysis

Page 66: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 66/83

8. NYSDOT Actions

• Reviewed similar ongoing projects in NYS.

• Required bracing systems for similar bridges in

NYS—(NYSDOT “Blue Page”)

• Sought recommendations from AASHTO

regarding code revisions.

Page 67: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 67/83

AASHTO LRFD Specs. – 3rd Edition (2004)

• Art. 6.11: Provisions for single or multipleclosed-box or tub girders

• Art. 6.7.5: Lateral Bracing

 – 6.7.5.3: Top lateral bracing shall be provided between flanges of individual tub sections. The

need for a full-length system shall be

investigated…

 – If a full length lateral bracing system is not  provided, the local stability of the top flanges and 

global stability of the individual tub sections shall 

be investigated for the assumed construction

sequence

Page 68: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 68/83

Centroid @ +36.3” Shear Ctr. @ -36.0” 

Izz = 36 in^4Iyy = 205,817 in^4

Centroid @ +37.3” Shear Ctr. @ -12.2” 

Izz = 114,870 in^4Iyy = 212,572 in^4

1/16” Top Plate

Lateral Torsional Stability of Open-tub girders

Page 69: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 69/83

Application to I-Girder Bridges

Page 70: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 70/83

Application to I-Girder Bridges

Page 71: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 71/83

Twin I-Girders: No bottom lateral bracing

Iyy = 15,470 in^4 Izz = 472 in^4

Page 72: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 72/83

Centroid @ +19.96” 

Shear Ctr. @ -19.06” 

Izz = 472 in^4Iyy = 296,426 in^4

Twin I-Girders: With bottom lateral bracing

Page 73: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 73/83

LTB with Non-linear Plate Model

0.0

0.5

1.0

1.5

2.0

2.5

0.0 20.0 40.0 60.0 80.0

Transverse Displacement at Midspan [in.]

   D  e  a   d

   L  o  a   d

   F  a  c

   t  o  r

Twin I-Girders: With bottom lateral bracing

6

Page 74: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 74/83

LTB with Non-linear Plate ModelNo Lateral Bracing

0.0

0.5

1.0

1.5

2.0

0.0 20.0 40.0 60.0 80.0 100.0

Transverse Displacement at Midspan [in.]

   D  e  a   d

   L  o  a   d

   F  a  c   t  o  r

11

Twin I-Girders: No bottom lateral bracing

Page 75: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 75/83

Page 76: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 76/83

Page 77: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 77/83

Page 78: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 78/83

Page 79: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 79/83

Twin I-Girder Behavior--summary

• More stable than open tub girder.

• Lateral or lateral-torsional behavior (vs. global torsional)

• Bottom lateral system effective for lateral resistance

• Consider top and bottom laterals for long, narrow spans

• No “spec-ready” equations for checking global behavior

(Single Tubs or Twin-I systems)

l h b d f l

Page 80: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 80/83

Dealing with a bridge failure

• Expect your inspection program to come underscrutiny

• Expect safety of other bridges to be questioned

• Expect requests for data on failed bridge and otherbridges

• Establish point of contact for all media questions.

• Make “public” info. Easily available –

l h b d f l

Page 81: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 81/83

Dealing with a bridge failure

• Work with your lawyers, (but do not expect them toalways have the same priorities).

• Establish protections for privileged material, e.g.

ongoing investigations.

O

Page 82: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 82/83

The Paradox of Failure

“When it comes to bridge

design, collapse is a most 

reliable teacher.” 

Henry Petroski

“Success Through Failure; The

Paradox of Design”

One Final Lesson

Q i ?

Page 83: Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

7/28/2019 Recent NYSDOT Bridge Failure Ivestigations_UB Presentation

http://slidepdf.com/reader/full/recent-nysdot-bridge-failure-ivestigationsub-presentation 83/83

Questions?