rec mechanism v1

Upload: bijayabc

Post on 05-Apr-2018

226 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 REC Mechanism v1

    1/18

    REC Mechanism in Indiafor Solar Power Development

    16th March 2012

  • 8/2/2019 REC Mechanism v1

    2/18

    Background Renewable Energy being costlier than conventional energy, support

    required from state and central government and state utilities in terms ofpreferential tariffs, capital subsidy and other fiscal benefits to facilitate RE

    development

    Renewable power potential in India limited to a few states. Challenges to

    enforce Renewable Purchase Obligation to the states where there islimited or no RE potential

    REC mechanism launched in Dec 2010 to address this anomaly and

    provide a mechanism to facilitate imposition of uniform RPOs across

    states

    REC mechanism devised to enable uniform imposition ofRPOs across states

  • 8/2/2019 REC Mechanism v1

    3/18

    REC Mechanism - Basics

    Under REC mechanism, RE power generated from the plant has two

    componentso Power (Black Component) To be sold to state Discom at non-

    preferential tariff (not exceeding APPC) or through merchant route

    o REC (Green Component) To be sold on power exchange (IEXand PXIL). Floor and Forbearance prices defined for trading to limit

    risks of RE developers and lenders

    Obligated Entities (State Discoms or Captive and Open AccessConsumers) can meet their RPOs through

    o Direct purchase of RE (Green) power OR

    o Purchase of RECs

    o Setting-up their own RE Capacity

  • 8/2/2019 REC Mechanism v1

    4/18

    REC Mechanism - Basics

    National Load Dispatch Center (NLDC) is the nodal agency forregistration of projects and issuance of RECs

    SERCs mandated to nominate a nodal agency for RECs in the state (20

    states already nominated the nodal agency till date)

    Project developer required to get the project accredited through the state

    agency

    The process for accreditation and registration made simple and web

    enabled to facilitate fast development of projects under the mechanism

    REC mechanism was an instant hit. Within 15 months oflaunch 418 RE projects with aggregate capacity of 2478 MW

    got accredited under REC

  • 8/2/2019 REC Mechanism v1

    5/18

    REC Pricing Framework As per CERCs REC regulation 2010, CERC would determine Floor and

    Forbearance price for RECs within which the RECs would be traded inexchanges

    CERC framed the methodology for calculation of Solar REC floor and

    forbearance price :

    o Solar REC Floor Price: Minimum Viable cost of solar power(covering O&M, interest and debt repayment) Minimum APPC

    (Average Power Purchase Cost)

    o Forbearance Price: Solar PV Tariff (As per CERC Regulations)

    Minimum APPC

    The price range for solar REC was determined as Rs 9.3 13.4/kwh for

    the period FY 13-FY17

    REC pricing methodology ensures commensurate returns todevelopers and protects lenders from market uncertainties

  • 8/2/2019 REC Mechanism v1

    6/18

    RECs The Price Advantage

    While preferential tariff PPA for a solar developer is possible only betweenRs 7 8/kwh as per the latest bidding trends, REC mechanism would fetch

    anywhere between Rs 9 -11/kwh on a levelized basis for the 25 year project

    life even if we assume that RECs clear at floor price

    Returns under REC mechanism will be higher For next five

    years window & thereafter too

  • 8/2/2019 REC Mechanism v1

    7/18

    REC Price Advantage Key Drivers

    REC price range is already set for next five years giving excess revenue to

    developer for initial years

    The power sale price at APPC is expected to increase every year due to

    increasing cost of conventional power and high marginal cost of power in the

    grid

    REC Floor and forbearance Price are determined based on CERC norms. In adecreasing capital cost scenario, the capital cost used to determine the REC

    price would lag and hence will be less than the actual costs at the time of

    installation of plant.

    The REC price window would be set for at least 5 years in advance. In a

    decreasing capital cost scenario, this will cause REC price to be higher than

    preferential tariff especially during later part of five year window (As is currently

    the case)

  • 8/2/2019 REC Mechanism v1

    8/18

    The Opportunity As per JNNSM, the National Tariff Policy would mandate SERCs to fix minimum

    solar power purchase of 3% by year 2022. This translates into installed solarcapacity of over 34000 MW as per CEA estimates (18th EPS)

    The capacities to be developed under JNNSM and state policies would not be

    sufficient to satisfy RPO requirements

    Captive power users and Open Access consumers would be another major

    segment for solar REC purchase, as they would find it unviable to purchase

    solar power

    Attractive Solar REC price coupled with the escalating revenue from power sale

    provide returns commensurate to risk for the investors. Lenders and project

    developers would find themselves more and more comfortable with REC

    mechanism in coming years

    Significant solar capacity will be developed under RECmechanism in coming years

  • 8/2/2019 REC Mechanism v1

    9/18

    Challenges & Risks

    Though the mechanism looks very interesting and has witnessed highinterest from non-solar RE developers, the response of solar developers

    has not been encouraging

    The major reason for this lukewarm response is the challenge in achievingdebt funding for REC based projects.

    Debt funding remains the biggest challenge for solardevelopment under REC

  • 8/2/2019 REC Mechanism v1

    10/18

    REC Perceived Risks

  • 8/2/2019 REC Mechanism v1

    11/18

    REC Price Variability

    Argument: REC prices are determined only till FY 17. Considering the

    decreasing cost of solar power, the prices may fall significantly post FY 17

    Mitigation Justification:

    True that solar REC price after 2017 would reduce substantially. Our analysis

    predicts a floor price range of Rs 4-5/kwh for the solar REC during FY 18-22.

    Post 2022, even if the grid parity is achieved, there would be some value (Rs 1

    3/kwh) that a solar REC will fetch

    Despite price variability, the financial viability for the project is not at risk as

    both equity payback and the debt servicing can be achieved during the initial

    10 years only

    Upcoming amendment in REC regulations (CERC) will introducevintage multiplier concept. Under this, the developer setting up

    solar project earlier will get a higher multiple of RECs/kwh ofgeneration. This would further mitigate REC price variability risks

  • 8/2/2019 REC Mechanism v1

    12/18

    REC Marketability (1/3)Argument: Whether state regulatory commissions would specify increasingtrajectory of solar RPOs as per the JNNSM?

    Mitigation Justification:

    Most of the SERCs (31 states and UTs) have already specified the REC and

    RPO regulations in their states and 21 states and UTs have specified solar

    RPOs in excess of 0.25% for FY 2011-12

    Cabinet has already approved amendment in National Tariff Policy mandating

    SERCs to impose solar RPO starting from FY 13 and a target of 3% by FY 2022

    Crisil Infrastructure Advisory conducted study on impact of RPOson utilities financial health. The study is now complete and is in

    public domain. Impact not found significant

  • 8/2/2019 REC Mechanism v1

    13/18

    Argument: Obligated entities would prefer buying solar power and not RECs. Anentity could buy solar power @ Rs 8/kwh or bundled solar power @ Rs 5/kwh.Buying solar RECs (@ min 9.3 Rs/kwh) would be the last resort for the obligatedentities

    Mitigation Justification:

    The upcoming solar generation capacity in the country is not sufficient to fulfill

    RPOs of obligated entities. Most utilities would need to buy RECs to fulfill their

    obligations

    Open access and captive consumers would find it unviable to procure solar or

    bundled solar power. It would be prudent for them to buy RECs, even if costlier

    There will be a large demand for solar RECs even if solarpower remains a cheaper option

    REC Marketability (2/3)

  • 8/2/2019 REC Mechanism v1

    14/18

    Argument: Whether SERCs would be able to enforce the RPO compliance targets

    on obligated entities?

    Mitigation Justification:SERCs have specified following consequences in caseof default:

    Obligated entity will deposit an amount based on RPO shortfall and REC

    forbearance price with the state agency. The state agency will buy RECs onbehalf of defaulting entities

    Noncompliance to RPO obligations will be considered as default of Electricity

    Act and action would be taken u/s 142. Fining the head of the defaulting

    company.. Panel provisions to be confirmed

    Monetary penalties will not be allowed to pass through in ARR

    The way non solar RECs are getting traded in the market and theprices are hovering near forbearance price, instills confidencethat obligated entities expect strong enforcement against non-

    fulfillment of RPOs

    REC Marketability (3/3)

  • 8/2/2019 REC Mechanism v1

    15/18

    Long Term Tie up for Power SaleArgument:

    Most of the states signing PPA under REC mechanism are not signing on long-

    term

    The solar developer may not be able to achieve expected escalation in the

    power price for the project life

    Mitigation Justification:

    The state utilities always need day power and would not relinquish PPA at

    Average Purchase Price

    The power produced from solar project being day power, enjoys better

    marketability and higher price in power markets. Also power can be predicted

    and scheduled with greater accuracy and hence can compete in the Power

    market with conventional power

    Solar power is competitive in market. Dependence on statePPA is minimal

  • 8/2/2019 REC Mechanism v1

    16/18

    REC Shelf life

    Argument:

    RECs are currently valid for only 1 year. This will increase selling pressure on REdevelopers

    Mitigation Justification:

    CERC is considering to increase the shelf life in the upcoming amendment of RECregulations

  • 8/2/2019 REC Mechanism v1

    17/18

    Key investment drivers in REC

    While it is not possible for an RE developer under a long term preferential tariff

    PPA to migrate to REC mechanism; there is no such restriction on an REC

    based power generator to migrate to preferential tariff mechanism at any point in

    time. Hence, an REC based generator may optimize its risk return tradeoff at

    any time after taking advantage of the initial five year tariff advantage

    After FY16 , the project choose to move to PPA route or APPC & REC route

    based on the pricing available

    Higher REC prices in the initial years support a project pay-back in 5-6 years

    only

    Solar project under REC can anytime participate in biddingand migrate to preferential tariff PPA

  • 8/2/2019 REC Mechanism v1

    18/18

    thankyou