  • 8/17/2019 REAM Guide Line

    1/120

     

    TRAFFIC MANAGEMENT DURING

    CONSTRUCTION

    - Interim Guide -

  • 8/17/2019 REAM Guide Line

    2/120

     

    ACKNOWLEDGEMENT

    This Interim Guide on Traffic Management During Construction was prepared as a team

    effort. Two teams were set up, namely the WRITE-UP TEAM and the REVIEW TEAM.

    The Write-Up team is made up of:

    1. 

    Ir. Mohamed Shafii Hj Mustafa - Mirage Consultancy

    2.  Abd Karim Mohamed - T & D Consult Sdn Bhd

    3.  Zahari Abd Aziz - T & D Consult Sdn Bhd

    4.  Yusof Ahmad - T & D Consult Sdn Bhd

    5.  Shafinas Saroji - JKR Malaysia (UKJ)

    6.  Mohd Hizam Hazli Bakri - T & D Consult Sdn Bhd

    7.  Siti Fairuz Hanim Hj Bahari - Mirage Consultancy

    The Review team is made up of:

    1.  Ir. Mohd Shahrom Mohd Saman - JKR Malaysia (UKJ)

    2.  Ir Suhaimi Hassan - Lembaga Lebuhraya Malaysia

    3.  Ir. Muhayadin Md Lip - Dewan Bandaraya Kuala Lumpur

    4.  Azmee Nin - PLUS Sdn Bhd

    5 M hd Y id M hd Y PROPEL

  • 8/17/2019 REAM Guide Line

    3/120

     

    FOREWORD

    This Interim Guide Traffic Management During Construction is to apply the current best

    practice in managing the safety of the travelling public through road-work sites throughout

    Malaysian.

    The prime focus is to review and upgrade the Arahan Teknik (Jalan) 2C/85 “Manual On

    Traffic Control Devices- Temporary Signs and Work Zones Control” which was published in

    1985.

    After the review, the team decided to propose the following changes to the practice of

    traffic management at construction work zones:

    i)  setting up a framework for the practice of designing to monitor and reporting

    of the site management

    ii) 

    introducing simplified traffic categories for easier referencesiii)  introducing changes to the “Sign Faces”, focusing more towards the use of

    symbols rather than words

    This document had been reviewed by a team of experts and practitioners and it had been

    presented in a Workshop at the Malaysian Road Conference in 2007. There were many

    comments made during the Workshop, and also through e-mails. The Team is thankful to all

    th l h h t k ti t k th i l bl t hi h h ll b

  • 8/17/2019 REAM Guide Line

    4/120

     

    TRAFFIC MANAGEMENT DURING CONSTRUCTION

    - An Interim Guide – 

    CONTENT

    1.0  THE NEED FOR TRAFFIC CONTROL AT WORK ZONES

    2.0 REQUIREMENTS OF TRAFFIC MANAGEMENT AT WORK ZONES

    3.0 STRATEGIES FOR EFFECTIVE IMPLEMENTATION OF TRAFFIC MANAGEMENT AT WORK

    ZONES

    4.0 PLANNING A TRAFFIC MANAGEMENT SCHEME

    5.0 DESIGNING A TRAFFIC MANAGEMENT SCHEME6.0 TYPICAL LAYOUTS OF THE TRAFFIC MANAGEMENT PLAN

    7.0 PLACEMENT AND REMOVAL OF TRAFFIC CONTROL DEVICES

    8.0  MAINTENANCE OF TRAFFIC CONTROL ZONES

    9.0 REPORTING & CHECKING

  • 8/17/2019 REAM Guide Line

    5/120

     

    CHAPTER 1

    THE NEED FOR TRAFFIC MANAGEMENT AT

    WORK ZONES 

  • 8/17/2019 REAM Guide Line

    6/120

     

    CHAPTER 1

    THE NEED FOR TRAFFIC MANAGEMENT AT WORK ZONES

    1.1 Background

    Whenever work is done on or near the roadway, drivers are faced with changing and

    unexpected traffic conditions. These changes may be hazardous for drivers, workers, and

    pedestrians unless protective measures are taken.

    Drivers may not be able to differentiate between the various types of construction sites and

    the unexpected dangers in the work zone areas. Hence, proper traffic control measures andsafety considerations are required for all types of work both on major long term projects or

    minor short duration.

    This Interim Guideline has been designed and written to explain the application of the

    standards to the various work situations. The Guidelines should be used by everyone who is

    involves with planning, designing, installing, maintaining, and inspecting traffic control at

    k it Th ill t ti b d f i k id d f f i

  • 8/17/2019 REAM Guide Line

    7/120

     

    1.2 Traffic Safety At Work Zones

    Traffic safety is a major issue at work zones. When the travelling path of the motorist isoccupied for work activity, conflict arises between the requirements of the construction

    workers and the desires of smooth un-interrupted traffic flow. Work sites create potential

    hazards because they:

    •  Confront the motorists with unexpected and often confusing situations;

    •  Create obstructions which the motorists have to avoid;

    •  Disrupt the motorist’s attention from the driving task; and 

    • 

    Expose the construction workers to move and often speeding traffic.

    Much had been said about the worsening problem of traffic safety at roadwork work zones.

    Numerous daily news reports of mishaps and fatalities had been published; however, not

    many studies have been conducted to understand the causes of these accidents. Studies on

    individual accident at work zones have been conducted mostly by the consultants at site but

    mostly for internal use only, not properly documented or recorded at a central agency such

    as JKR or the Police Traffic Department.

    In work zone accidents the following observations have been made:

    i) Most crashes occur within the Work Area.

    ii) The termination area had the least crashes.

    iii) Most accidents involved rear end collision, particularly in the Advance Warning Area.

    i ) I h T i i A h Sid S i h

  • 8/17/2019 REAM Guide Line

    8/120

     

    1.3 Identifying the Problem

    As mentioned in the previous section, it is apparently there is insufficient data collection tocarry out an in-depth study into road-works accidents. However, the general problems

    associated with local work zones are attributed to:

    •  Poor management of traffic flow.

    •  Inadequate Traffic Control Devices.

    •  In-appropriate signage.

    •  Lack of maintenance of signage and control devices.

    • 

    Speeding traffic.•  Lack of day time and night time safety auditing of the work zones.

    •  High incidence of traffic accidents.

    •  Removal of inappropriate signage outside working hours.

    These problems create inconvenience to the travelling public and causes concern to Road

    Authorities particularly increase in road accidents and fatalities. The Road Authorities had

    taken a serious stand on the problems of traffic safety at Work Zones. The first question was“why did these problems arise?" There are many reasons attributed to these, but the

    following reasons are the most common:

    •  Inadequate standards for traffic management

    •  Inadequate Traffic Management Plans

    •  Inadequate allocation for traffic management

    •  Poor method of construction

    P i l i f ffi h i i

  • 8/17/2019 REAM Guide Line

    9/120

     

    Additional statements to the Standard Specifications can be added to reinforce that

    the requirements of the specifications must be strictly implemented or possible

    litigation in the event of an accident.

    iii)  A major recent initiative by road authorities as to improve safety at work zones has

    been implement separate payments for traffic management within the contracts

    rather than as a general overhead cost or provisional sum. So, now there is a

    financial incentive to provide quality traffic management because contractors can

    price separately the traffic management components and treats it as a major

    element.

    iv)  With more funds available, the contractors can now provide improvement and safer

    construction practices and dedicate more resources to the implementation of the

    traffic management. Now, constructors have no excuse not to put into practice the

    requirements of the standards and specifications for the traffic management at work

    zones or they could face job suspension by the superintending authority and the

    possibility of litigation in the event of an accident under the Occupational Safety andHealth Act.

    v)  Lastly, there must be constant surveillance both day and night checks to ensure that

    the good design and practice of traffic management at work zones are adhered to.

    The Supervision Engineers must enforce the requirements of good traffic

    management practices and to ensure that the contractors comply with specifications

    d l l i

  • 8/17/2019 REAM Guide Line

    10/120

     

    CHAPTER 2

    REQUIREMENTS OF TRAFFIC

    MANAGEMENT AT WORK ZONES 

  • 8/17/2019 REAM Guide Line

    11/120

     

    CHAPTER 2

    REQUIREMENTS OF TRAFFIC MANAGEMENT

    AT WORK ZONES

    2.1 Purpose of Work Zone Traffic Management

    The purpose of work zone traffic management is to provide a safe work zone for workers

    and to provide safe passage for motorists, pedestrians, and workers through the road works

    site. An effective traffic management must incorporate the following key elements:

      warn motorists and pedestrians of road-works hazard ahead

      provide safe travel paths through the works area for the travelling

    public including pedestrians, at all times, day or night, and in all

    weather conditions

      provide a safe work zone for workers,

    2.2 Objective of Work Zone Traffic Management

  • 8/17/2019 REAM Guide Line

    12/120

     

    ii) Minor maintenance works

    -  shoulder repairs

    guardrail repair-  shoulder mowing

    -  pavement striping

    -  ditch cleaning

    iii) Major maintenance works

    -  pavement joint repair

    -  culvert repairs

    bridge repairsiv) Uti1ity operations

    v) Emergency situations such as vehicle breakdowns or road accidents

    2.4 The Principles of Work Zone Traffic Management

    The Principles of Work Zone Traffic Management includes;

    i) Make traffic safety an integral and high priority element of every project.

    -  Use geometries and traffic control devices that are comparable to

    those of normal highway situations.

    -  Prepare a traffic management plan that is easily understood by all

    persons responsible for work zone traffic control.

  • 8/17/2019 REAM Guide Line

    13/120

     

    -  Analyze work zone accident records to guide officials in improving

    work zone operations.

    Remove traffic control devices immediately when they are no longerneeded.

    v) Give constant attention to roadside safety.

    -  Provide clear roadside recovery area as wide as practical.

    -  Use lightweight channelization devices, which will yield on impact.

    -  Provide appropriate barriers to protect workers and errant road users.

    Store construction equipment, materials and debris in a manner,which will minimize the opportunity for run-off-road vehicle impacts.

    -  Use latest technology / materials to provide advance information and

    enhanced visibility to all road users.

  • 8/17/2019 REAM Guide Line

    14/120

     

    CHAPTER 3

    STRATEGIES FOR EFFECTIVE

    IMPLEMENTATION OF TRAFFIC

  • 8/17/2019 REAM Guide Line

    15/120

    CHAPTER 3

    STRATEGIES FOR EFFECTIVE IMPLEMENTATION OF TRAFFIC MANAGEMENT

    AT WORK ZONES

    The Traffic Management at Work Zones in Malaysia requires thorough planning and design

    as to ensure a high and satisfactory level of safety is provided for all road users. A wellthought out Traffic Management Plan (TMP) will reduce the number and severity of

    accidents, slow down traffic and minimize public complaints.

    One of the major aims of this Interim Guide is to propose strategies for the effective

    implementation of managing traffic at work zones. The new strategies involve the following:

    i)  new definitions and categories of work zones designs (see Chapter 4 and 5);

    ii) 

    a framework for the design and implementation of the Traffic Management

    Plans;

    iii)  a framework for the checking and reporting on the execution of the Traffic

    Management Plans (TMPs) on site.

    The new strategies outline the procedures for planning, designing and implementing the

    traffic management schemes. It also outlines the roles, authorities and responsibilities of

  • 8/17/2019 REAM Guide Line

    16/120

     

    3.1.2 During the Pre-Construction Activities

    • 

    TMPs must be acceptable to the Local Authorities and Local Communities•  TMPs must be made known to the road users well in advance of any construction

    works

    •  TMPs must be made known to the JKR District and JKR State; particularly it may

    involve road/lane closure or major road diversion.

    3.1.3 During the Construction Activities

    •  These activities are to be carried out by the Contractor:

    o  Dissemination of Information on the proposed TMPs

    o  Ensure Proper and Adequate Enforcement from the local Enforcement Units

    o  Set up a formal Traffic Management Team, inclusive of Flagmen, Placement

    and Removal Crews and Maintenance Personnel's.

    o  Operate an Emergency Response Team

    Carry out Maintenance of the Scheme and the Deviceso  Ensure timely Placement and Removal

    o  Carry out timely cleaning of the control devices

    o  Inform the District Engineer of any road/lane closure and/or diversion

    3.1.4 Reporting

    • 

  • 8/17/2019 REAM Guide Line

    17/120

     

    3.2 During Pre-Construction Activities

    3.2.1 Proper Planning and Design

    Before any planning on Traffic Management Scheme (TMS) commences, the

    Contractor’s traffic engineer must visit the site for field check and to collect

    inventory of the existing facilities including existing structure, services and public

    facilities such as street lighting, traffic light, bus and taxi stop and road furniture’s

    that may require removal or relocation during the construction stage.

    In addition, the engineer should assess the existing road capacity, determine the

    existing travel and distributions pattern and identify potential problems that might

    arise due to temporary road diversions. The engineer should also carry out

    discussion with the local authorities on the effect of the construction works on the

    existing traffic patterns and the occurrence of any local festivities / activities /

    upgrading programs.

    3.3 During Construction Activities

    3.3.1 Dissemination of Information to Road Users

    Dissemination of information to the road users through mass media is encouraged.

  • 8/17/2019 REAM Guide Line

    18/120

     

    3.3.3 Supervision and Execution of Traffic Management Schemes

    To ensure a smooth construction sequence without compromising public road safetyfor pedestrians and other road users, the Contractor needs to set up two distinct

    teams, each with their unique roles and responsibilities. they are the Traffic

    Management Team and the Emergency Response Team as illustrated below.

    CONTRACTOR’s

    MANAGEMENT TEAM

    TRAFFIC

    MANAGEMENT

    OFFICER

    EMERGENCY RESPONSE

    TEAM

    ERT

    TRAFFIC

    MANAGEMENT TEAM

    TMT

  • 8/17/2019 REAM Guide Line

    19/120

     

    3.3.4 Traffic Management Team

    The role of the Traffic Management Team is to ensure that the traffic managementscheme is implemented in accordance with approved drawings. Their duties include

    proper installation, maintenance and cleaning of road safety equipments such as

    plastic barriers, safety cones, plastic hoardings, temporary warnings and directional

    signboards, arrow flashers, flashing ambers and etc, In addition, they will ensure that

    all lane closures and traffic diversions are implemented in compliance with all traffic

    management procedures as per the authority requirement.

    The team is also responsible to ensure the safety and smooth traffic flow through

    the period of road closure. The person in-charge of the traffic management team

    must regularly inspect the situation of traffic flow and update the road authorities on

    the prevailing traffic conditions. The team must be able to establish an effective line

    of communication for emergencies and changes in circumstances.

    There are occasions that necessary to reroute the traffic to opposite traffic lanes incontra flow for activities such as the launching of bridge beams, the construction of a

    bridge pier and at interchanges in the middle of existing roadways.

    Traffic management personnel should present at site during construction including

    weekends, public holidays, and under any weather conditions.

  • 8/17/2019 REAM Guide Line

    20/120

     

    3.4 Responsibilities

    3.4.1 Responsibilities of the S.O/P.D

    The duties of the S.O/P.D include the following:-

    •  Initiate/request for the appointment of a qualified Road Safety Auditor as soon

    as possible upon receipt of Letter of Award preferably within 1 month from

    receipt of LOA.

     

    Chair the commencement meeting and review any Stage 3 Compliance Audit.•  Chair the Stage 4 Audit meetings to discuss the Road Safety Auditor findings and

    make decisions based on the Auditor recommendations and response by the

    Contractor

    •  Evaluate the financial, contractual and legal issues arising from compliance/non

    compliance to Auditor recommendations based on advice from S.O/P.D

    representative and Road Safety Auditor

    3.4.2  Responsibilities of the S.O/P.D Representative

    The S.O/P.D representative is the engineer who is the supervisor appointed or

    employed by the Government to carry out supervision of the construction,

    maintenance or other works which require the use of a traffic management scheme.

    The S.O/P.D must follow the procedures;

  • 8/17/2019 REAM Guide Line

    21/120

    •  Inform major road users including truckers, public transport, Keretapi

    Tanah Melayu (KTM), Malaysia Airline System(MAS) Kargo, etc of any

    major disruptions to major Federal Roads due to construction works.

    3.4.3  Responsibilities of the Contractor

    The Contractor carrying out construction or maintenance operations on roads or

    bridges will take due care and diligence to minimize the risk of injury to road users or

    damage to their property as a result of such operations. Actions should be taken to

    warn the public of prevailing conditions and to guard, delineate, and, wherenecessary, to illuminate works which may pose a hazard to traffic. The contractor will

    take all necessary measures to minimize delays and detours which will

    inconvenience motorists.

    There is a legal requirement on the part of the Contractor to provide a safe working

    environment for its employees and the travelling public through the work site.

    The duties of the Contractor include:-

    •  Issue official letter of appointment to Road Safety Auditor

    •  Provide scope of Audit works

    •  Prepare TMP for all work zones and submit to SO/PD, Local Authority, PDRM

    and Road Safety Auditor

    •  Provide drawings, documents and reports to Road Safety Auditor

  • 8/17/2019 REAM Guide Line

    22/120

     

    ii.  To monitor that personnel under their control are employees of the

    Contractor and should at all times be courteous to the travelling public.

    Personnel should not allow themselves to be provoked by members of thepublic, by exercising restraint they will strengthen their position both then

    and at any subsequent enquiry or legal proceedings.

    iii.  To ensure that the traffic controllers assigned to direct traffic or personnel

    employed to place, maintain and remove signs and devices, are trained and

    fully aware of their duties and responsibilities.

    iv.  Able to act in accordance with the provisions and directives of, this guideline

    and all the appropriate acts.

    The Traffic Management Officer is to provide evidence to the SO that he has the

    necessary skills and qualification to perform his duties. The role of the Traffic

    Management Officer is to ensure a smooth construction sequence all throughout the

    construction period without compromising the safety of all road users includingpedestrians and bicyclists. The Traffic Safety Officer is to use his experience to

    anticipate possible traffic congestions and come out with appropriate mitigating

    measures.

    The duties of the Traffic Safety Officer include:

    i.  Designing the TMP’s 

  • 8/17/2019 REAM Guide Line

    23/120

     

    3.4.5  Responsibilities of the Road Safety Auditor

    The role of the Road Safety Auditor is to audit the TMP at the approach to and withinthe construction site. This includes the observation of the effectiveness of the TMP’s

    and the traffic control devices employed during the day and night. The duties of the

    Road Safety Auditor include:

    i.  Visiting the site (Preferably together with the Contractor and/or the

    Consultant)

    ii. 

    Auditing the TMP at the beginning of the construction to ensure workabilityand suitability throughout the duration of the construction period.

    iii.  Auditing the Work Zones during the Construction Phase. This is to be carried

    out every three months (Subject to request by S.O/P.D).

    iv.  Preparing the Road Safety Audit reports and sending them directly to all the

    relevant parties (JKR, Contractor and Consultant).

    v.  Presenting the findings of the Audit reports

    vi. 

    Providing best advice to the S.O/P.D for him to make well informed decisionsvii.  Providing advice to the S.O/P.D on matters related to traffic management

    plan during construction, as and when required.

  • 8/17/2019 REAM Guide Line

    24/120

     

    CHAPTER 4

    PLANNING TRAFFIC MANAGEMENT

    SCHEMES 

  • 8/17/2019 REAM Guide Line

    25/120

     

    CHAPTER 4

    PLANNING TRAFFIC MANAGEMENT SCHEMES

    The development of work zone traffic management begins with the planning process. This

    Section details the importance of the planning process and gives an overview of the steps in

    the process with emphasis is on the relationship between planning and design.

    4.1 The Planning Process

    The overall purpose of the planning process is to select the most appropriate traffic

    management strategy. “Work Zone Traffic Management Strategy” is the basic scheme of

    moving traffic through or around a construction, or maintenance activity. The type of work

    zone is the most significant element of the control strategy, which are also includes lengthof work zone, time of work, number of lanes, width of lanes, speed control method and

    right-of-way control method.

    The planning process involves seven steps:

    Step 1: Assemble Data- Describe the construction data base

  • 8/17/2019 REAM Guide Line

    26/120

     

    A flow chart of the process is as shown in Figure 4.1.

    Step 2

    Determine Traffic and

    Construction Duration Category

    Step 4

    Identify Feasible Work ZoneTypes

    Step 5

    Impact Analysis

    -  Environmental, Safety, Traffic flow and

    Step 1Assemble Data

    Step 3

    Determine Extent of Roadway

    Occupancy

  • 8/17/2019 REAM Guide Line

    27/120

     

    Step 1: Assemble Data

    The basic data required is a complete description of the work to be performed whichcovers a wide range of activities such as:

    i)  Construction of new roadside drainage which may have no direct disruption

    of traffic flow.

    ii)  Adding a new lane, reconstructing a highway ramp, or resurfacing a

    pavement can have extensive impact on traffic.

    iii) 

    Replacing a bridge or culvert which may involve roadway closure and detourswith very extensive disruption to traffic.

    The Degree of Impact will suggest the extent of the data required. Table 4.1

    summarizes some basic guidelines. The basic requirements are described in the top

    half of the table which will be sufficient for most projects the bottom half describes

    the requirement for detour routes or where additional information is required to

    appraise various options available.

    It is important that the designer of the Traffic Management Plans and his/her team

    to visit the site for field check and collate an inventory on the existing facilities

    including existing structures, services and public facilities such as street lighting,

    traffic light, bus and taxi stops and roadside furniture that may require removal

    during the construction stages.

  • 8/17/2019 REAM Guide Line

    28/120

     

    TABLE 4.1 – Suggested Data Base

    A. Basic Requirements

    Description of Construction Project

    -  Type of work

    Roadway encroachment should include the space required by the work activities andequipment, the safety buffer required for adequate work site protection and the physical

    space occupied by the barricades or other traffic control devices.

    -  Limits of work

    -  Tentative work sequence and schedule

    -  Estimated cost

    -  Construction category

    Traffic Data

    -  24 hour volume counts

    Roadway geometrics

    -  Speed data

    -  Description of potential detour routes

    B. Additional Information

    Roadway Data

    -  Right of way limitations

  • 8/17/2019 REAM Guide Line

    29/120

     

    Step 2: Select the Traffic and Construction Duration Categories

    For the purpose of standardization, ease of strategy identification and design, the

    Work Zone Types are divided into the following categories:

    TABLE 4.2: TRAFFIC CATEGORIES 

    ROAD CLASSIFICATION SPEED PROFILE SPEED

    URBANLow Speed < 60 km/hr

    High Speed > 60 km/hr

    RURALLow Speed < 70 km/hr

    High Speed > 70 km/hr

    EXPRESSWAYLow Speed < 90 km/hr

    High Speed > 90 km/hr

  • 8/17/2019 REAM Guide Line

    30/120

    iv)  The expected number of working days to complete the project.

    v)  The cross section of the road

    Each of the above factors is a function of the work zone strategy and has someflexibility such that traffic disruption can be minimised. As a guide, the number and

    size of lanes provided through the work zones should where possible be the same as

    the existing permission at the discretion of the SO. The Level of Service (LOS) during

    the construction period where possible, should be maintained.

    Step 4: Identify Feasible Work Zone Types

    Step 4 and Step 5 serve to identify possible work zone types such as:

    1.  Lane Constriction

    2.  Lane Closure

    3.  Shared Right of Way

    4.  Median crossover and contra flow

    5.  Detour

    6.  Temporary Bypass

    7. 

    Intermittent Closure

    8.  Use of Shoulder or Median

    Based on the extent of roadway occupancy, the cross-sectional characteristics (lane

    width, shoulder width, right of way, etc.) and considering the constraints imposed by

    regulations and policies, feasible work zone types can now be chosen. Typically, only

    a small number of work zone types will emerge as being feasible for a particular

  • 8/17/2019 REAM Guide Line

    31/120

     

    Step 6: Select Preferred Alternative Traffic Management Plan

    When all critical impacts are analysed, the most effective strategy will often has less

    impact on all measures.

    Step 7: Check for Mitigation Requirement

    Finally mitigation measures will be necessary for the preferred alternative to

    minimise impact caused by the construction works. This complete analysis should becarefully documented and used as input to the overall work zone traffic control

    process.

    4.2.1  Relationship Between Planning and Design

    Selecting the appropriate traffic management strategy that develop plans and specifications

    requires to implement the two distinctly activities.

    Although planning and design are different activities, a strong relationship exists between

    them. During the planning process when strategies are being defined, the traffic

    management plan for each strategy sketched. The cost of the traffic control is also a factor

    in the selection of the most cost effective traffic management strategy that meets the

    requirement of these guidelines and the relevant acts.

  • 8/17/2019 REAM Guide Line

    32/120

     

    CHAPTER 5

    DESIGNING A TRAFFIC MANAGEMENT

    SCHEME 

  • 8/17/2019 REAM Guide Line

    33/120

     

    CHAPTER 5

    DESIGNING A TRAFFIC MANAGEMENT SCHEME

    This Chapter discusses the design of Traffic Management Plans (TMPs) including the details

    of the plan, typical layout and adapting typical layout to actual site conditions.

    5.1 Traffic Management Plans (TMPs)

    The Traffic Management Plans show the placement and type of traffic control devices to be

    used in a work zone as well as details about the type of work zone to be used in each phase

    of the work. The Traffic Management Plan should be prepared and must be understood by

    all responsible personnel before the site is occupied. Any changes in the traffic management

    plan should be authorized by an official trained in safe traffic control practices. A formalTraffic Management Plan (TMP) is required with the plans, specifications, and estimates for

    all road projects.

    TMP's may range in scope from a very detailed plans designed for specific projects, to simply

    a reference to typical plans. The details of the TMP depend on the complexity of the project

    and on the amount of traffic interference introduced by the work activity.

  • 8/17/2019 REAM Guide Line

    34/120

     

    Areas that must be considered in detail include:

      Existing rules and restrictions on/within the construction area

     

    The location of work (on roadway, shoulders, or sidewalks)  The number of lanes required for the work activity,

      Hazards created by the work activity within the recovery area such as boulders,

    drains, pipe, headwalls, blunt ends of guardrail, and sign supports,

      Delays during the placement and removal (preferably during low traffic volume

    periods)

      Maximum length of work zone allowed by the road authority

     

    Special needs of local traffic

    Factors that should be considered in the TMP are shown in TABLE 5.1.

    TABLE 5.1: FACTORS IN DESIGN OF TRAFFIC MANAGEMENT PLANS

    Economic and community

    - commercial business districts,

    - residential locations,

    - recreation areas,

    - shopping centres,

    - railroad crossings,

  • 8/17/2019 REAM Guide Line

    35/120

     

    5.2 Traffic Control Zones

    The design of the traffic management scheme must follow the basic concept of a typicalwork zone. A typical work zone should have the following areas:

    -  ZONE A: Advance Warning Area

    -  ZONE B: Transition Area

    -  ZONE C: Buffer Area

    -  ZONE D: Work Area

    - ZONE E: Termination Area

    If no lane or shoulder closure is involved, the transition area will not be used.

    In this Chapter, each of the “Zone/Area” will be examin ed for one direction of travel. If the

    work activity affects more than one direction of travel, the same principles apply to traffic in

    all directions.

    FIGURE 5.1: illustrates the five parts of a traffic control zone to be discussed in this

    section.

  • 8/17/2019 REAM Guide Line

    36/120

     

    5.2.1  ZONE A: Advance Warning Area

    i) 

    An advance warning area is necessary for all traffic control zones becausedrivers need to be made aware that they are approaching the construction

    area. Before reaching the work area, drivers should be given enough time to

    alter their driving patterns. The advance warning area may vary from a series

    of signs starting 2 km in advance of the work area to a single sign or flashing

    lights on a vehicle

    ii) When the work area, including access to the work area, is entirely off theshoulder and the work does not interfere with traffic, an advance warning

    sign may not be needed. An advance warning sign should be used when any

    problems or conflicts with the flow of traffic may be anticipated.

    iii) The advance warning area, from the first sign to the start of the next area,

    should be long enough to give the motorists adequate time to respond to the

    changing conditions. For most operations, the advance warning distancerequirement for various road types are:

    a)  2 km to 1 km for expressways

    b)  500m for most rural roadways or open highways conditions

    c)  at least 250m for urban roadways.

  • 8/17/2019 REAM Guide Line

    37/120

     

    5.2.2 ZONE B: Transition Area

    i) When work is performed within one or more travelled lanes, a lane closure(s)is required. In the transition area, traffic is channelized from the normal

    highway lanes to the path required to move traffic around the work area. The

    transition area includes the taper transition length.

    ii) The transition area should be clearly visible to drivers. The correct driving

    path should be clearly marked with channelizing devices and pavement

    markings. Existing pavement markings need to be removed and new

    markings placed when they conflict with the transition. Pavement marking

    arrows are useful in transition areas.

    iii) With moving operations, the transition area moves with the work area. A

    shadow vehicle may be used to warn and guide traffic into the proper lane.

    iv) A taper is a series of channelizing devices and pavement markings placed on

    an angle to move traffic out of its normal path. Four general types of tapers

    used in traffic control zones are:

    a) Lane closure tapers are those necessary for closing lanes of moving

    traffic (sometimes referred to as channelizing tapers)

    b) Two-way traffic tapers are those needed to control two-way traffic

    where traffic is required to alternately use a single lane (commonly

    used when flagman is present)

  • 8/17/2019 REAM Guide Line

    38/120

     

    vi) Two-Way Traffic Taper  

    a) The two-way traffic taper is used in advance of a work area that

    occupies part of a two-way road in such a way that the remainder ofthe road is used alternately by traffic in either direction. In this

    situation, the function of the taper is not to cause traffic to merge, but

    rather to resolve the potential head-on conflict. A short taper is used

    to cause traffic to slow down by giving the appearance of restricted

    alignment. Drivers then have time to decide whether to proceed

    cautiously past the workspace or to wait for opposing traffic clear. A

    flagman is usually employed to assign the right-of way in such

    situations.

    b) Two-way traffic tapers should be 15 to 30 meters long, with

    channelizing devices spaced a maximum of 3 to 6 meter respectively,

    to provide clear delineation of the taper.

    vii) Shoulder Closure Taper

    a) When an improved shoulder is closed on a high-speed roadway, it

    should be treated as a closure of a portion of the roadway, which the

    motorists may expect to use in an emergency. The work area on the

    shoulder should be preceded by a taper that may be shorter than for

    lane closures. One-half of the length from Table 5.4 is suggested as a

    maximum for shoulder closure’ tapers provided the shoulder is not

    used as a travel lane. If the shoulder is being used as a travel lane,

  • 8/17/2019 REAM Guide Line

    39/120

     

    5.2.3 ZONE C: Buffer Area

    i) The buffer zone is the open or unoccupied space between the transition andwork areas. With a moving operation, the buffer space is the space between

    the shadow vehicle, if one is used, and the work vehicle.

    ii)  The buffer space provides a margin of safety for both traffic and workers. If a

    driver does not see the advance warning or fails to negotiate the transition, a

    buffer space provides room to stop before the work area, It is important for

    the buffer space to be free of equipment, workers, materials, and workers’

    vehicles.

    iii)  Place channelizing devices along the edge of the buffer space. The suggested

    spacing in meters is equal to two times the spacing for lane closure taper.

    iv)  Situations may occur where opposing streams of traffic are transitioned so

    one lane of traffic uses a lane that is normally in the opposite direction. In

    these situations, a buffer space should be used to separate the two tapers for

    opposing directions of traffic as to avoid head-on collisions.

    5.2.4 ZONE D: Work Area

    i) The work area is that portion of the roadway, which contains the work

  • 8/17/2019 REAM Guide Line

    40/120

     

    iv) Guidelines

    a) Use traffic control devices to make the work area clearly visible totraffic.

    b) Place channelizing devices between the work area and the travelled

    way. Devices placed on a tangent (along the work area) to keep traffic

    out of a closed lane should be spaced in accordance with the extent

    and type of activity, the speed limit, vertical and horizontal alignment

    such that it is clearly visible that the lane is closed. For high speed

    roadways, the devices should be spaced 2 to 4 times the spacing for

    lane closure taper. For low-speed roadways, a closer spacing may be

    adopted.

    c) Provide a safe entrance and exit for work vehicles.

    d) Protect mobile and moving operations with adequate warning on the

    work and/or shadow vehicles.

    e) Flashing lights and flags should be considered on work vehicles

    exposed to traffic.

    5.2.5 ZONE E: Termination Area

    i) The termination area provides a short distance for traffic to clear the work

    area and to return to the normal traffic lanes. It extends from the

    downstream end of the work area to the “PEMBINAAN TAMAT” sign. A

  • 8/17/2019 REAM Guide Line

    41/120

     

    NOTE: Refer also to Figure 5. 4 for area distances and spacing of traffic control devices

    TABLE 5.3: FORMULAS FOR TAPER LENGTH 

    Posted Speed Formula

    70 km/h or under L= WS2 

    155

    70 km/h or over L= WS

    1.6

    Where L = taper length

    W = width of lane or offset

    S = posted speed, or off-peak 85 percentile speed

    Ref. ATJ 2C/85 - Temporary Signs and Work Zones Control

  • 8/17/2019 REAM Guide Line

    42/120

     

    TABLE 5.4: Taper Lengths for Lane Closures-Distance L

    * Base on 3.75-meter wide lane. This column is appropriate for lane widths less than

    3.75 meters

    Ref. ATJ 2C/85 - Temporary Signs and Work Zones Control  

    AREA DISTANCESPACING OF

    DEVICES

     ADVANCE WARNING AREA

    Expressways

    Rural Roadways or Open Highways

    Urban Roadways

    1-2 km

    350 m (min.)

    250 m (min.)

    min. 50 m apart

    min. 50 m apart

    min. 15 m apart

    TRANSITION AREA 

    Lane closure Taper

    2-way Traffic Taper

    As in Table 5.4

    15 - 30 m

    As in Table 5.4

    3 - 6 m apart

  • 8/17/2019 REAM Guide Line

    43/120

     

    CHAPTER 6

    TYPICAL LAYOUTS OF THE TRAFFIC

    MANAGEMENT PLAN 

  • 8/17/2019 REAM Guide Line

    44/120

     

    CHAPTER 6

    TYPICAL LAYOUTS OF THE TRAFFIC MANAGEMENT PLAN

    6.1  New Typical Layouts

    In this Interim Guide, a new set of Temporary Signs is being proposed. The main focus of the

    new proposal is the use of “symbols” rather than “words” in the sign faces. The new sign

    face proposals are as shown in APPENDIX A. The new temporary signs are also proposed to

    have different shapes for the “Expressway” categories and the “Urban and Rural”

    categories.

    For the purpose of standardization; ease of strategy identification; and design, it is proposedthat the Work Zone Types are divided into two, i.e.:

    i)  the Traffic Category  , and

    ii)  the Construction Duration Category  

  • 8/17/2019 REAM Guide Line

    45/120

      FIGURE 6.1: SIZES OF TRAFFIC ZONES

    URBAN

    Low Speed

    High Speed

    RURAL

    Low Speed

    High Speed

    EXPRESSWAYS

    Low Speed

    High Speed

    250m

    400m

    350m

    500m

    1000m

    2000m

    100m

    150m

    100m

    150m

    250m

    300m

    varies

    varies

    varies

    varies

    varies

    varies

    Note:

    1. Max length of work zone is 5km and the maximum area allowed for each excavation area is 200m.

    2. All barriers to be continuous

    ZONE A

    ADVANCE WARNING

    ZONE B

    TRANSITION

    ZONE C

    BUFFER

    ZONE E

    TERMINATE

    ZONE D

    WORK AREA

  • 8/17/2019 REAM Guide Line

    46/120

     

  • 8/17/2019 REAM Guide Line

    47/120

     

    6.1.2 The Construction Duration Category

    The Construction Duration category will determine the type of the Traffic Control Devices.

    These are illustrated in Table 6.2 and Figure 6.2.

    CONSTRUCTION DURATION CATEGORIES

    CLASSIFICATION DURATION

    Temporary Diversion

    # Flagmen are always required during

    temporary diversion works

    < 1 Day

  • 8/17/2019 REAM Guide Line

    48/120

      FIGURE 6.2: THE CHOICE OF TRAFFIC CONTROL DEVICES

    (Depending on the Construction Duration)

    ZONE A

    ADVANCE WARNING

    ZONE B

    TRANSITION

    ZONE C

    BUFFER

    ZONE E

    TERMINATE

    ZONE D

    WORK AREA

    TEMPORARY

    DIVERSION

    SHORT TERM

    LONG TERM

    Adv Sign – MUST

    The other signs are advantageous

    to have

    - Arrow Signs

    -Cones

    Adv Warning Signs - Apply the full

    set

    Adv Warning Signs – Apply the full

    set

    -Arrow Signs

    -Plastic NJBs

    -Arrow Signs

    -Plastic NJBs

    -Add. TCDs

    -Arrow Signs

    -Cones

    -Work Area, Speed Signs

    -Plastic NJBs

    -Delineators, Strings

    -Work Area, Speed Signs

    -Concrete, Plastic NJBs

    -Delineators, Strings

  • 8/17/2019 REAM Guide Line

    49/120

     

  • 8/17/2019 REAM Guide Line

    50/120

     

    6.2 Sign Arrangements

    It is the intention of the Interim Guide to standardize the application of the temporary signs

    in the work zones. This is to ensure drivers’ familiarize and compliance to the TMP proposal.

    It is recommended that a uniform arrangement of signs be adopted throughout the work

    area. The proposed arrangement of signs is in Figure 6.3.

    The detailed signing of each zone is as follows:

    ZONE A: ADVANCE WARNING AREA (the example given here is for the Rural High Speed Traffic Category)

    See Figure 6.4.

    Sign 1 – Identification Sign

    -  This sign gives an advance warning to the motorists of a work area ahead.

    It should also identify the Road Authority responsible for the work. This isusually a “worded” sign. 

    -  This sign should be installed 500m from Transition Area in the case of the

    Rural High Speed Traffic Category.

    Sign 2 – Information Sign

  • 8/17/2019 REAM Guide Line

    51/120

     

    Sign 5 – Speed Sign

    This is the Speed sign indicating the second “step-down” speed for themotorists.

    -  This sign should be installed 100m from Transition Area in the case of the

    Rural High Speed Traffic Category.

  • 8/17/2019 REAM Guide Line

    52/120

     

    USE

    1st

     Sign- Identification Sign

    2nd

     Sign- Info Sign

    3rd

     Sign- Speed Sign

    4th

     Sign- Info Sign

    5th

     Sign- Speed Sign

    USE

    ARROW SIGNS

    ZONE A

    ADVANCE WARNING

    ZONE B

    TRANSITION

    ZONE C

    BUFFER

    ZONE E

    TERMINATE

    ZONE D

    WORK AREA

    USE

    ARROW

    SIGNS

    USE

    WORK AREA SIGNS

    And

    SPEED SIGNS

    USE

    WARNING

    SIGN

    FIGURE 6.3: SIGN ARRANGEMENTS 

  • 8/17/2019 REAM Guide Line

    53/120

     

    FIGURE 6.4: SIGN ARRANGEMENTS FOR ADVANCE WARNING AREA 

    1st

     Sign- Identification Sign

    2nd

     Sign- Info Sign

    3

    rd

     Sign- Speed Sign4th

     Sign- Info Sign

    5th

     Sign- Speed Sign

     ARROW SIGN at the start of Transition Area to be

     placed on high post

    ZONE A

    ADVANCE WARNING

  • 8/17/2019 REAM Guide Line

    54/120

     

  • 8/17/2019 REAM Guide Line

    55/120

     

    ZONE B: TRANSITION AREA (See Figure 6.5).

    Sign 6 –  Arrow Sign

    -  This is the Arrow Sign at the start of the Transition Area.

    -  This sign should be installed at the beginning of the Transition Area. It is

    advisable to install all the Arrow Signs on high posts.

    Signs 7 & 8 –  Arrow Signs

    -  The Arrow Signs are repeated for Sign 7 and Sign 8.

    -  Sign 7 is placed at the middle of the Transition Area.

    -  Sign 8 is placed at the end of the Transition Area.

    * The number of “Arrow Signs” in the Transition Area can be more if the conditions at

    the site demand it.

    ZONE D: WORK AREA (See Figure 6.6). 

    Sign 9 – Speed Sign

    Thi i th S d Si i f i th t i t th f d t d i

  • 8/17/2019 REAM Guide Line

    56/120

     

    ZONE E: TERMINATION AREA

    Sign 13 – “PEMBINAAN; TAMAT” 

    Install 30m after the downstream taper

    Figure 6.7 gives an overall sign arrangement layout for the typical Rural High Speed

    Traffic Category work zone.

  • 8/17/2019 REAM Guide Line

    57/120

    FIGURE 6.5: SIGN ARRANGEMENTS FOR TRANSITION AREA 

    ARROW SIGNs at the Transition Area

    - To be placed on high post

    - The numbers of Arrow signs can be

    increase if needed

    ZONE B

    TRANSITION

  • 8/17/2019 REAM Guide Line

    58/120

    ALL SIGNS at the Work Area

    - To be placed on high post

    - Number of signs should be increased if

    the Work Area is long.

    FIGURE 6.6: SIGN ARRANGEMENTS FOR WORK AREA 

    ZONE C

    BUFFER 

    ZONE E

    TERMINATE

    ZONE D

    WORK AREA

     

    FIGURE 6.7: OVERALL SIGN ARRANGEMENTS FOR RURAL HIGH SPEED 

  • 8/17/2019 REAM Guide Line

    59/120

    ZONE A

    ADVANCE WARNING

    ZONE B

    TRANSITION

    ZONE C

    BUFFER

    ZONE E

    TERMINATE

    ZONE D

    WORK AREA

    500m 150m 100m L 100m

    100m 100m 100m 100

     

    100

     

     

  • 8/17/2019 REAM Guide Line

    60/120

  • 8/17/2019 REAM Guide Line

    61/120

     

    6.3 Modification of Typical Layouts

    Each work zone is different, with variables such as speed, volume, location of work,pedestrians, and intersections changing the needs for each zone. The goal of work zone

    traffic control is safety, and the key factor in effective traffic control in work zones is

    application of proper judgements.

    Plans contained in the Guide are called “typical applications.” In this respect, they represent

    the layouts for the general situations found in the field. When unusual conditions are found,

    the typical layouts must be adapted to the particular roadway and worksite configuration.Furthermore, these typical layouts are minimum requirements. When needed, either

    additional device may be used to supplement the layout, or the sign spacing and taper

    lengths can be increased to give drivers additional response time or shortened for low-speed

    situations. When difficult situations or unusually hazardous conditions are encountered, a

    higher-type treatment than that shown as typical may be required.

    The types of modifications that may be desirable or needed include the following:

    i) Additional devices

    -  additional signs (but care must be taken not to “oversign” especially in the

    advance warning and transition areas of the work zone)

    -  flashing arrow panels

    -  more channelizing devices

  • 8/17/2019 REAM Guide Line

    62/120

     

    The following points should be considered when designing a TMP for a specific field

    condition:

    i) 

    Drivers may not perceive or understand one or more of the devices placed inthe traffic control zone. Therefore, some extra signs or devices may be

    required to improve safety for motorists and workers, however, be aware of

    the possibility of over signing.

    ii) Consideration must be given to the risks involved if the motorist does not get

    the required information. The level of protection used and the delivery of the

    message should be proportional to the level of hazard. More emphaticmessages and a higher level of protection are needed for high hazard

    situations.

    iii) Where possible, a recovery space (buffer zone) should be provided.

    iv) Devices must be evaluated on an overall system basis to determine if the

    safety objectives for the travelling public and workers in the work zone areachieved.

    6.4 Classification of Typical Layouts

    The classification of typical plans is difficult because of many different parameters that must

  • 8/17/2019 REAM Guide Line

    63/120

     

    v) Closure configuration

    -  shoulder closed

    -  lane or lanes closed

    shoulder used as travel lane-  roadway closed

    -  crossover and/or contra flow

    -  on-site detour (bypass)

    -  off-site detour

    When making modifications to the typical solutions it is best to establish a set of plans,

    which covers the range of conditions commonly found rather than a plan for every possiblecombination of parameter values.

    6.5 Considerations to Modifying the Typical Layouts

    Each traffic control zone is different, with variables such as speed, volume, location of work,

    pedestrians and intersections changing the needs for each zone. The primary goal of trafficcontrol zone is safety, and the key factor in ensuring the control zone works is the

    application of sound judgment principles. The examples in this chapter are guides showing

    how best to apply the standards.

    The typical applications include use of various traffic control methods, although they do not

    include a specific layout for every conceivable work situation. Typical applications may be

  • 8/17/2019 REAM Guide Line

    64/120

     

    ii)  Work On Or Over Shoulder Or Parking Lane

    i)  No encroachment in the travelled lane means there is little or no direct

    interference with traffic. When shoulder is occupied or closed, the motoristshould be warned and the workers should be protected. In most cases a

    single warning sign is adequate. When a sealed or constructed shoulder is

    closed on a high-speed roadway, it should be treated as a closure of a portion

    of the road system because the motorist expects to be able to use this area in

    the event of an emergency. The approach to the work area on the shoulder

    should be closed off by a taper of channelizing devices.

    ii)  Minor encroachment in the travelled lane means when work on the shoulder

    or takes up part of a lane, traffic volumes, type of traffic (buses, trucks and

    cars), speed, and capacity should be analyzed to determine whether the

    affected lane be closed. For high-speed traffic conditions, a full lane closure

    should be considered or narrowing of the traffic lanes.

    iii)  Work On Two-Lane Roadway

    i)  When one lane is closed on a two-lane, two-way road and the remaining lane

    is used by traffic travelling in both directions, the short two-way traffic taper

    of 15 meters minimum is used to slow traffic as it approaches the work space.

    Alternatively a one-way traffic control may be affected by the following

    means:

  • 8/17/2019 REAM Guide Line

    65/120

     

    ii)  Do not decrease safety by using fewer devices simply because the operation

    will change its location frequently. Flaggers may be used but caution must be

    taken so they are not exposed to unnecessary hazards. Portable light weight

    devices should be used and moved periodically to keep them near to thework area.

    v)  Moving Operations

    i)  Moving operations are work activities where workers and equipment move

    along the road without stopping, usually at slow speeds, the advance warning

    area moves with the work area and traffic should be directed to pass safely.Parking may be prohibited and work should be scheduled during off peak

    hours. For some moving operations, such as street sweeping, if volumes are

    light and sight distances are good, a well marked and signed vehicle may

    suffice. If volumes and/or speeds are higher, a shadow or backup vehicle

    equipped as a sign truck should follow the work vehicle. Where feasible,

    warning signs should be placed along the road and periodically moved as the

    work in progress. In addition to improve visibility and worker safety, vehiclesmay be equipped with flags, flashing vehicle lights, and large signs.

    vi)  Short-Term Utility Operations

  • 8/17/2019 REAM Guide Line

    66/120

     

    (c)  Maintain access - to business, industrial and residential areas. Even if the

    road closed to vehicles, pedestrian access and walkways should be

    provided.

    6.7  Pedestrians

    i)  When there is pedestrian traffic in the area, specific walkways need to be

    provided. If nearby buildings are being demolished or built, covered walkways

    may be needed. Do not force pedestrians to walk through the work area or

    into travelled lanes. If a sidewalk closed, provide a temporary walkwayaround the work area or direct the pedestrians to an alternate protected

    route.

    ii) The following situations normally warrant walkways in the TMPs at:

    a)  sidewalks cross the work zone,

    b) 

    designated school route crosses the work zone,

    c)  significant pedestrian activity or evidence of such activity exists (i.e. a

    worn path), and

    d)  existing land use generates pedestrian activity. (such as bus stops,

    factories, places of worship, night market, etc.)

     

  • 8/17/2019 REAM Guide Line

    67/120

    h) Signs and traffic control devices should not be a physical hazard to

    pedestrians.

    i) Signs located near or adjacent to a sidewalk should have a 2.5mclearance.

     j)  Where construction activities involve sidewalks on both sides of the

    street, work should be staged so that both sidewalks are not out of

    service at the same time. In the event when sidewalks on both sides of

    the street must be closed, pedestrians should be guided around the

    construction site.

    k)  Retro reflectorized traffic control devices are of little value to pedestrians.

    Warning lights should be used to delineate the pedestrian’s pathway and

    to mark any hazards.

    l)  Where possible, the scheduling for the construction of the overhead

    pedestrian bridge should be brought in to the beginning of the program tominimise probability of accidents involving pedestrians crossing multi lane

    roads.

    6.8 Bicycles

     

  • 8/17/2019 REAM Guide Line

    68/120

    ii) The access to the exit ramp should be clearly marked and outlined with

    channelizing devices. For long-term projects existing markings should be

    removed and new ones placed. As the work area changes, the access may be

    modified.

    6.11 Intersections

    i) Use advance-warning signs, devices and markings as appropriate on all

    crossroads. The effect of the work upon signal operation should be

    considered such as signal phasing for adequate capacity and for maintainingor adjusting detectors in the pavement.

    6.12 Detours

    i) Detour signing is usually handled by an authorized traffic engineer because it

    is considered a traffic routing item. Detour signs are used to direct trafficonto the alternative roadway. When the detour is long, install “Arrow”

    symbol signs to periodically remind and reassure drivers that they are still on

    a detour.

    ii) When an entire roadway is closed, a detour should be provided and traffic

    should be warned of the closure well in advance.

  • 8/17/2019 REAM Guide Line

    69/120

     

    CHAPTER 7

    PLACEMENT AND REMOVAL OF TRAFFIC

    CONTROL DEVICES 

     

  • 8/17/2019 REAM Guide Line

    70/120

    CHAPTER 7

    PLACEMENT AND REMOVAL OF TRAFFIC CONTROL DEVICES

    This Chapter discusses the important aspects of the process of placing and removal of traffic

    control devices in work zones including preparation, the order of device placement, the

    treatment of existing signs, and the use of “shadow” or protection vehicles.

    7.1 Preparation for Placement Process 

    The placement, modification, and removal of traffic control devices for road construction

    and maintenance operations can be enhanced by adequate preparations. This is particularly

    important because of the hazard associated with these activities. The installation and

    removal of worksite traffic control devices create situations that are often far more

    hazardous than the operation of the completed zone. These hazards are often greater than

    those during the work activity because:

    i)  Workers placing advanced warning and channelizing devices must be in the

    roadway at points of high conflict without the full protection of the devices

    being placed.

    ii) Th l t ti tit t t d it ti f th

     

  • 8/17/2019 REAM Guide Line

    71/120

    Coordination prior to the Placement of the traffic controls at a site greatly improves the

    safety and efficiency of the installation. The coordination includes the following

    considerations:

    i) 

    Advance publicityii)  Selection of the day and time-of-day for the installation

    iii)  Analysis of traffic volumes

    iv)  Selection of crew work hours

    v)  Consideration of emergency requirements in case of utility breakdown, road

    accidents, etc.

    7.1.3 Inventory and Storage

    All traffic devices required for the placement and maintenance of the zone should be on-

    hand and in good condition. Also, special equipment, trailers, and trucks should all be

    operating properly and safely.

    Devices maintained in inventory need to be formally organized to assure that all items are

    actually in stock and can be rapidly retrieved. Traffic control devices need to be storedproperly to avoid marring, and all devices need to be kept clean.

    All mechanical and electrical elements and equipment require routine maintenance to

    assure that they will function properly. Devices should be inspected carefully when they are

    returned to inventory. All devices found to be non-standard or in poor condition should be

    replaced, modified, or repaired. Equipment for the roadway worksites must be in good

     

  • 8/17/2019 REAM Guide Line

    72/120

    7.2 Placement

    7.2.1 Placement Sequence

    Devices are installed in the direction that traffic moves that is, moving “downstream”. The

    first device placed is the first advance warning sign. The installation then proceeds with the

    i) Advance warning zone

    ii)  Transition zone

    iii)  Buffer zone,

    iv)  Work zone, and

    v) 

    Termination zone.

    If traffic in both directions will be affected, such as with work in the centre lanes, the devices

    can be placed in both directions at the same time, starting at each end farthest from the

    work area. Alternately one direction can be installed before the other.

    When one direction of traffic will be directed into opposing traffic lanes, the signs, devices,

    and pavement markings for the opposing traffic should be placed first.   It is essential tochannelize opposing traffic out of its lane before moving the oncoming traffic into the lane.

    When all signs and devices are placed for opposing traffic, the devices for the oncoming

    direction can then be set up.

    When signs or channelizing devices are to be installed and removed several times during the

    work operation, a spot should be painted where each device is located. This way the

     

    h h d d “b k ” “ h d ” “ ” h l h ld b d h

  • 8/17/2019 REAM Guide Line

    73/120

    On high-speed roads, a “backup,” “shadow,” or “protection,” vehicle should be used. This

    vehicle should first  be positioned on the shoulder some 30 meters or more behind the

    device truck when the first signs are placed. The shadow vehicle uses special lights or a

    flashing arrow panel to warn traffic. When the crew needs to work on the roadway, theshadow vehicle is moved into the travelled lane. Truck mounted attenuators are desirable

    for these vehicles.

    7.2.3 Placing Channelizing Devices

    When closing a lane, tapers are laid out in a straight line starting at the shoulder. Each

    channelizing device is then placed in sequence moving downstream. When placed by hand,  the devices should be moved out from  the shoulder with the worker looking toward traffic

    as he moves into the lane to place the device. When channelizing tapers are installed, each

    device is placed 30cm further into the lane that being closed.

    7.2.4 Lateral Position

    For some closures, traffic doesn’t have to be excluded from the entire width of the lane toestablish a safe workspace. Under these circumstances, the work area channelizing devices

    should be placed a few meters back from the lane line as to:

    i) Reduce the chances of the devices being hit, and

    ii) Provide increased lateral clearance, thereby increasing capacity.

     

    Wh ll i i l h li ti d i th l d Th t ti hi l

  • 8/17/2019 REAM Guide Line

    74/120

    When all signs are in place, channelization devices are then placed. The protection vehicle

    gradually encroaches upon the exterior lane as the workers install the taper in front of the

    protection vehicle. Finally, the protection vehicle is positioned in the closed lane while the

    work zone channelization is placed.

    7.2.8 Interior Or Center Lane Closures

    When work is necessary on an interior or center lane, the recommended procedure is to

    also close the adjacent exterior lane to avoid an “island” closure. In locations where, due to

    volumes or geometrics traffic, it must be carried around both sides of an interior lane work

    space, the preferred procedure is to first close an exterior lane upstream from the workspace, particularly for high-speed conditions. Next, interior lane traffic is channelized into

    the previously closed exterior lane.

    Warning signs are placed on both sides of the approach warning area. The exterior lane is

    then closed as described above to create an “empty” work space. 

    To continue the setup, the protection vehicle moves carefully into the closed exterior laneand workers complete the exterior lane channelization and closing taper. The protection

    vehicle then moves to the downstream end of the closed exterior lane and blocks the

    adjacent center lane. The taper which moves traffic from the interior lane to the previously

    closed exterior lane is placed, and worksite channelization is established on both sides of the

    closed centre lane.

     

    7 4 S i l E i t d T h i

  • 8/17/2019 REAM Guide Line

    75/120

    7.4 Special Equipment and Techniques

    Some Maintenance Agencies may have special equipment to facilitate and expedite the

    placement process, such as, trucks with racks in which signs are loaded in the reversesequence to that needed; that is, the last sign put on is the first one to be taken off.

    Special traffic control vehicles should be available for traffic control zone placement,

    maintenance and removal. These vehicles should be employed for:

    i)  Carry devices to worksites.

    ii)  Facilitate handling.

    iii) 

    Help to organize and protect signs and devices.iv)  Emergency situations.

    Special features of these traffic control vehicles may include;

    i)  Appropriate colour (orange),

    ii)  Flashing/rotating lights or beacons,

    iii) 

    Flashing arrow panels,iv)  Changeable message signs,

    v)  Sign racks,

    vi)  Cone chutes,

    vii)  Power lift tailgates,

    viii)  Worker platform and protective railing,

    ix)  Crash cushions on shadow vehicles, and

  • 8/17/2019 REAM Guide Line

    76/120

     

    CHAPTER 8

    MAINTENANCE OF TRAFFIC CONTROL

    ZONES 

     

    CHAPTER 8

  • 8/17/2019 REAM Guide Line

    77/120

    CHAPTER 8

    MAINTENANCE OF TRAFFIC CONTROL ZONES

    Traffic control zones should be maintained so that they remain as effective as when first

    installed. Documentation of maintenance and inspections is necessary in the event of

    lawsuits resulting from accidents or other grievances suffered by an injured citizen. ThisChapter will explain the types of inspections and maintenance required and methods to

    document inspections and actions taken.

    8.1 Inspection and Maintenance Program

    Once the traffic control zone is established, it is important that it continues to functioneffectively. The traffic control devices must be maintained as it was installed or modified to

    ensure the motorists are not misled with unnecessary changes to the work zone shape and

    sizes.

    Maintenance is needed to service the equipment and make corrections required by any

    combination of the following factors:

     

    8 1 1 Elements of an Inspection Program

  • 8/17/2019 REAM Guide Line

    78/120

    8.1.1 Elements of an Inspection Program

    A comprehensive inspection and maintenance program should include the following

    elements.i)  A formalized plan

    ii)  Defined inspection procedures

    iii)  A form to record the findings of the field inspection

    iv)  A repair program

    v)  An adequate inventory of devices for emergency replacements or repairs

    vi)  Day and night review of the marking of the travel path through the work

    zonevii)  Procedures to assure that specified repairs are made

    viii)  Formal documentation of inspections and repairs

    ix)  Identification of possible causes of accidents and skid marks

    The inspector will need to make decisions during the inspection. He must exercise

     judgement in establishing appropriate practices. As deficiencies are observed, the following

    choices are available:i)  Make on-the-spot corrections

    ii)  Call for emergency repairs (radio or phone)

    iii)  Instruct the work crew to make routine repairs during the next work day

    iv)  Schedule deferrable corrective actions, such as sign cleaning

    A key element of the program is the procedure that ensures that the required maintenance

     

    8.2.2 Frequency

  • 8/17/2019 REAM Guide Line

    79/120

    8.2.2 Frequency

    To determine the frequency of inspections, the following factors must be considered.

    i) 

    Project size and durationii)  Degree of liability

    iii)  Severity of hazards

    iv)  Frequency at which damage is occurring

    v)  Number of deficiencies observed during previous inspections.

    vi)  Traffic volumes and speed.

    Traffic controls left in place overnight should he inspected during hours of darkness at thesame frequency as during the daylight hours. Inspections should also be carried out during

    adverse weather conditions to ensure safety requirements are met and adequate road

    drainage is maintained during the construction period.

    8.2.3  Documentation

    Documentation is an essential part of the traffic control maintenance function. It isnecessary for good planning and for project accounting. Documentation serves to:

    i)  Ensure the integrity of the project traffic control; and

    ii)  Provide a means of

      identifying the maintenance needed,

    providing a tool for getting maintenance started,

     

    Good record keeping procedures suggest that the time and location of the installation and

  • 8/17/2019 REAM Guide Line

    80/120

    Good record keeping procedures suggest that the time and location of the installation and

    removal of traffic control devices be noted. Although this record keeping can be time

    consuming for a moving maintenance operation, significant traffic control actions taken by

    the field crew should be recorded. These records should include:

    i)  Starting and ending time of work

    ii)  Location of work,

    iii)  Names of personnel,

    iv)  Type of equipment used, and

    v)  Any changes in temporary or permanent regulatory devices

    Major projects will require more detailed record keeping since they may involve greater

    amounts of funds from the contract BQ, and longer distances and times of physical exposure

    with resulting potential danger to the worksite employees and the motoring public.

    Several methods of recording traffic controls are available. These include:

    i) 

    Photographs either keyed to a diary or containing a brief description of  Date

      time,

      Location with GPS co-ordinates if possible.

      direction, and

      photographer’s name. 

     

    Each agency should have general checklist for different types of operations and conditions.

  • 8/17/2019 REAM Guide Line

    81/120

    g y g yp p

    These can be modified to meet the requirements of an individual worksite. Inspection sheets

    should be developed for major projects from the general checklists and schedule guidelines.

    For typical worksites, standard inspection sheets can be prepared and used.

    8.3 Training And Equipment Needs

    8.3.1  Training

    Several elements should be considered in preparing for and performing traffic control zoneinspections and maintenance. Personnel designated to perform these tasks must

    understand the general traffic control process, have a deep appreciation for safety, and be

    trained in device maintenance procedures. Training should include:

    ii)  Proper cleaning methods for the various types of equipment and

    reflective materials.

    iii) 

    Maintenance techniques for mechanical and electrical equipment,iv)  Proper placement and ballasting of traffic control devices

    v)  Methods to check sign reflectivity,

    vi)  Knowledge of the hazard potential of various types of situations

    vii)  Solutions that may be used to solve various problems.

    viii)  Situations requiring special technical assistance, (such as hazardous

    materials)and procedure to be followed in securing such assistance, and

     

    iii)  Tools and hardware for on the spot repairs

  • 8/17/2019 REAM Guide Line

    82/120

    ) p p

      Hammers

      Screwdrivers

     

    pliers and wrenches (crescent)  wrecking bar

      Shovel

      saw

      nails, nuts, bolts and washers

      tape measure

      Knife

    iv)  Spare parts and materials

      Batteries

      Bulbs

      Fuel

      Sandbags

      Posts

     

    Hardware

      wire and rope

      pavement marking tape

      reflective tape

      washing materials

  • 8/17/2019 REAM Guide Line

    83/120

     

    CHAPTER 9

    REPORTING & CHECKING 

     

    CHAPTER 9

  • 8/17/2019 REAM Guide Line

    84/120

    CHAPTER 9

    REPORTING & CHECKING

    To ensure proper adherence to the standards and specifications and also to ensure

    adequate implementation, there must be constant reporting and checking carried out at the

    work zones.Based on the scope of activities required, the documents and reporting requirements are as

    follows:

    i) Traffic Management Plans (TMP)

    Traffic Management Plans are required for all Work Zones of the project. Each work

    zone will have a specific TMP with a specific reference number to it. These TMPs shall

    have reference numbers  and it needs to be displayed   for easy access during theinspection and audit visits. Whenever there is a change of traffic management on the

    site, these must be reflected in the TMPs being displayed.

    The TMPs will have to be approved by the Supervising Engineers. A copy of the

    agreed TMP shall be forwarded to the S.O. for final approval and acceptance.

    However it is a requirement that any major TMP shall also be audited by Road Safety

     

  • 8/17/2019 REAM Guide Line

    85/120

    APPENDIX A

    TEMPORARY SIGNS

     

    APPENDIX A

  • 8/17/2019 REAM Guide Line

    86/120

    APPENDIX A

    TEMPORARY SIGNS

    1. GENERAL NOTES ON TEMPORARY SIGNS

    Temporary operations, such as maintenance operations or short construction

    activities, represent unusual roadway conditions and warrant special attention. If the

    temporary operations require measures different from those normally use, the

    existing permanent traffic signs shall be removed or covered and superseded by the

    appropriate temporary sign. In other words, temporary signs are used to notify road

    users of specific hazards, which may be encountered when temporary operations are

    underway.

    Temporary signs shall be placed in positions where they are most effective and

    placement must therefore take into consideration road geometry. The signs shall be

    so placed that road users will have adequate time for response. As a general rule,

    signs shall be located on the left-hand side of the highway. For additional safety

    duplicate signs may be placed on both sides of the carriageway. Within a

    construction or maintenance zone, however, it is often necessary to erect signs on

     

    2 Si f

  • 8/17/2019 REAM Guide Line

    87/120

    2.1  Temporary Signs for Expressways

    The temporary signs for use on the expressways shall have a HEXAGONAL shape sign

    as follows:

    2.2  Temporary Signs for Other Roads

  • 8/17/2019 REAM Guide Line

    88/120

  • 8/17/2019 REAM Guide Line

    89/120

  • 8/17/2019 REAM Guide Line

    90/120

  • 8/17/2019 REAM Guide Line

    91/120

  • 8/17/2019 REAM Guide Line

    92/120

  • 8/17/2019 REAM Guide Line

    93/120

  • 8/17/2019 REAM Guide Line

    94/120

  • 8/17/2019 REAM Guide Line

    95/120

  • 8/17/2019 REAM Guide Line

    96/120

    TS. 17 TYPICAL STRING DELINEATORS

    A form of delineation, particularly useful along rural areas without

    street light

    COLOUR

  • 8/17/2019 REAM Guide Line

    97/120

  • 8/17/2019 REAM Guide Line

    98/120

  • 8/17/2019 REAM Guide Line

    99/120

     

  • 8/17/2019 REAM Guide Line

    100/120

    APPENDIX B

    TYPICAL LAYOUTS FOR TRAFFIC

    MANAGEMENT PLANS

     

  • 8/17/2019 REAM Guide Line

    101/120

    NO. SPEED PROFILE

    ROAD CLASSIFICATION

    Urban Rural Expressway

    1. Low Speed < 60km/j < 70km/j < 90km/j

    2. High Speed > 60km/j > 70km/j > 90km/j

    TRAFFIC CATEGORY

     

    TRAFFIC CATEGORY & WORK ZONES CONTROL

  • 8/17/2019 REAM Guide Line

    102/120

    NO.

    TRAFFIC CATEGORY WORK ZONES

    CONTROL DRAWING

    REFERENCEROAD CLASSIFICATION SPEED PROFILE SPEED

    1. Urban

    Low Speed < 60km/l Figure 1

    High Speed > 60km/j Figure 2

    2. Rural

    Low Speed < 70km/j Figure 3

    High Speed > 70km/j Figure 4

    3. Expressway

    Low Speed < 90km/j Figure 5

    High Speed > 90km/j Figure 6

     

  • 8/17/2019 REAM Guide Line

    103/120

     

  • 8/17/2019 REAM Guide Line

    104/120

     

  • 8/17/2019 REAM Guide Line

    105/120

     

  • 8/17/2019 REAM Guide Line

    106/120

     

  • 8/17/2019 REAM Guide Line

    107/120

     

  • 8/17/2019 REAM Guide Line

    108/120

     

  • 8/17/2019 REAM Guide Line

    109/120

  • 8/17/2019 REAM Guide Line

    110/120

     

    APPENDIX C

    ROAD SAFETY AUDITING OF THETRAFFIC MANAGEMENT AT

    WORK ZONES

     

    ROAD SAFETY AUDITING OF THE TRAFFIC MANAGEMENT AT WORK ZONES

    (TMP)

  • 8/17/2019 REAM Guide Line

    111/120

    (TMP)

    1.0 Introduction

    In an effort to spur the economic growth of the country, the Federal Government has

    embarked on a massive program to provide new construction contracts especially in the

    road sector. Many projects, worth billions of ringgit had been identified and currently beingdesigned and implemented.

    Jabatan Kerja Raya Malaysia (JKR), being the implementation agency for the Federal

    Government, is very concerned about the effect of the construction activities to the

    possibility of increased accident occurrences at the construction work sites.

    As a mitigation effort, JKR has introduced the following steps in the road constructionprojects:

    i) Preparation of Traffic Management Plans (TMP) during the Design and Construction

    Phases

    ii) Cost of management and provision of Traffic Management at construction sites to be

     

    3.0 Reports

    The following reports must be prepared for the Audit work:

  • 8/17/2019 REAM Guide Line

    112/120

    The following reports must be prepared for the Audit work:

    i) Traffic Management Plans (TMP)

    Traffic Management Plans are required for all Work Zones of the project. Each work

    zone will have a specific TMP with a specific reference number to it. These TMPs are

    to be displayed   for easy access during the inspections and audit visits. Whenever

    there is a change of traffic control on the site, these must be reflected in the TMPs

    being displayed.

    The TMPs will have to be approved by the Supervising Engineers and endorsed by

    the Superintending Officer . The displayed copy must have these approval and

    endorsement.

    ii) Traffic Management Safety Reports (TMSR) 

    The Traffic Management Safety Reports are essential documents in the execution of

    the project. These reports are to be prepared by the Traffic Safety Officer and shall

    include the following:

      TMPs prepared and enforced on the ground

    TMPs for the ne t three months’ ork

    FLOWCHART FOR TRAFFIC MANAGEMENT AUDIT 

    Traffic Management Plans (TMP)

  • 8/17/2019 REAM Guide Line

    113/120

    Contractor prepare TMP for all work zones

    of the project

    Traffic Management Safety Reports (TMSR)

    Traffic Mgmt Officer prepare TMSR thatincludes:

    a)  TMPs prepared & enforced on the ground

    b)  TMPs for the next three months work

    c) 

    Estimated duration of each TMP (Expected

    placement & removal dates)

    d)  Accident occurrences and analyses

    Submit report to S.O/P.D and Road SafetyAuditor. Extend copy to HOPT (first week of the

    third months)

    Work Zone Audit

    Road Safety Auditor to carry out audit on

    a) 

    TMSR submitted

    b)  Traffic management at work zones

    (every 3 months/as per nos. agreed)

    - Road Safety Auditor to prepare audit

    report (within 2 weeks after receiving

    TMSR) and submit to S.O/P.D. Extend copy

    to HOPT

    RSA STAGE 4 (PART 1) PROCESS 

    COMMENCEMENT MEETING (*) 

    - Called & chaired by Road Branch Director

    - Scope of audit given to Road Safety Auditor

  • 8/17/2019 REAM Guide Line

    114/120

    Scope of audit given to Road Safety Auditor

    CONSTRUCTION & TRAFFIC

    MANAGEMENT DRAWING 

    - S.O / P.D submit drawing to Road Safety Auditor.

    VERIFICATION AUDIT

    STAGE 4 (PART 1)

    -  Road Safety Auditor prepared RSA Stage 4 (Part 1)

    report & send to S.O / P.D and Contractor. Extend

    copy to HOPT

    RESPONSE REPORT

    -Contractor prepares response report

    and submits to Road Safety Auditor.

    Extend copy to S.O / P.D and HOPT

    RSA STAGE 4 Pt 2

    COMPLETION MEETING

    - Called & chaired by HOPT

    - Road Safety Auditor to present findings

    - Designer present response

    - Decisions are made & minute

    RSA STAGE 4 (PART 2) PROCESS 

    DIRECTIVE TO DO RSA-  S.O / P.D instruct Road Safety Auditor to do

    RSA Stage 4 (Part 2)

  • 8/17/2019 REAM Guide Line

    115/120

    Required Corrective Action

    RSA Stage 4 (Part 2)

    ROAD SAFETY AUDIT

    -  Road Safety Auditor prepared RSA Stage 4 (Part 2)

    report & send to S.O / P.D and Contractor. Extend

    copy to HOPT

    RESPONSE REPORT

    - Contractor prepares response

    report and submits to Road SafetyAuditor. Extend copy to S.O / P.D and

    CORRECTIVE ACTION

    - By Contractor

    RSA STAGE 2

    COMPLETION MEETING

    - Called &chaired by S.O / P.D

    - Road Safety Auditor to present findings

    - Contractor present response

    - Decisions are made & recorded

    RSA STAGE 4 (PART 3) PROCESS 

    DIRECTIVE TO DO RSA

    STAGE 4 (PART 3)

    - S.O / P.D instruct Road Safety Auditor

    to do RSA Stage 4 (Part 3)

  • 8/17/2019 REAM Guide Line

    116/120

    Required Corrective Action

    ROAD SAFETY AUDIT

    -  Road Safety Auditor prepared RSA Stage 4 (Part 3)

    report & send to S.O / P.D and Contractor. Extend

    copy to HOPT

    RESPONSE REPORT

    - Contractor prepares response reportand submits to Road Safety Auditor.

    Extend copy to S.O / P.D and HOPT

    RSA STAGE 4 (PART 3)

    COMPLETION MEETING

    - Called &chaired by S.O / P.D

    - Road Safety Auditor to present findings

    - Contractor present response

    - Decisions are made & recorded 

    CORRECTIVE ACTION

    - By Contractor

  • 8/17/2019 REAM Guide Line

    117/120

     

    APPENDIX D

    FORMAT FOR TRAFFIC

    MANAGEMENT SAFETY REPORT

    (TMSR)

     

    FORMAT FOR TRAFFIC MANAGEMENT SAFETY REPORT (TMSR)

  • 8/17/2019 REAM Guide Line

    118/120

    1.0 

    Introduction

     objective of the report

     objective of the Traffic Management Plans

     objective of the TMSR report

     photos of the site

     schedule of the TMSR reports for the project

    2.0 

    Background of Project

     Project details

     Traffic data

     Strip map

     Construction Program

     The importance of the road

     The conditions of the road and surrounding area

    3.0 Project Contractor’s Site Organisation

     Organization chart of the project

     TMT and ERT organization

     List the tasks and responsibilities of each member of the TMT and ERT

     

    7.0 Emergency Response Plan (ERP) and Emergency Response Team (ERT)

     Emergency Response Plan (ERP)

    o Give detail of the plan and show “alternative route”

  • 8/17/2019 REAM Guide Line

    119/120

    o  Give detail of the plan and show alternative route  

     

    Emergency Response Team (ERT)

    o  Give detail of the organization chart and “Line of Communication” 

    8.0 Records of Public Complaints

     Provide records of public complaints through hotline, letters, newspapers, etc

    9.0 Damage to Vehicles

     

    Provide records and photos of vehicles experiencing problems within the work zones

    10.0  Accident Analyses

     Provide records of Accidents within Work Zones during the last 3 months

    o  Give detail of dates, time, collision diagram, location, damages. Show photos.

     Provide records of Accidents within the Project Work Zones from the start of project.

    o  Give detail of dates, time, collision diagram, location, damages. Show photos.

    11.0  Evaluation

     Evaluate the effectiveness of the TMPs during the last 3 months

     Highlight main issues for the next 3 months

     Propose steps to upgrade the situations

    Alert JKR on the iss es hich are sensiti e and propose mitigations

     

  • 8/17/2019 REAM Guide Line

    120/120