mine to mill optimization

Upload: a7me

Post on 14-Apr-2018

239 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Mine to Mill Optimization

    1/18

    Journal of Mining and Metallurgy, 38 (1-4) A (2002) 49-66.

    MINE TO MILL OPTIMISATION FOR CONVENTIONAL

    GRINDING CIRCUITS A SCOPING STUDY

    A. Jankovic and W. Valery,

    JKMRC, University of Queensland, Brisbane, Australia

    (Received 18 June 2002; accepted 6 October 2002)

    Abstract

    The scoping study a for a Mine to Mill optimisation program was carried out in

    a gold mine in Australia. The specific objective of this scoping study was to identify

    the problems and potential benefits for a Mine to Mill optimisation project.

    Available mining and milling data were collected during the visit and

    preliminary analysis was conducted to identify the potential benefits and best

    course of action during a Mine to Mill optimisation program. The main

    conclusions from the scoping study were:

    Preliminary blast fragmentation modelling confirms that finer ROM size

    distributions could be generated with significant reduction in the amount of

    oversize material.

    Assessment of crushing and milling operating strategies and preliminary

    simulations using JKMRC and Bond methodologies indicated possibility of 4-

    5% increase in milling throughput and better energy utilisation.

    Key words: Crushing, Milling, Mass balance, simulation, modeling.

  • 7/27/2019 Mine to Mill Optimization

    2/18

    A. Jankovic and W. Valery50

    1. Background

    As a general practice, blasting engineers design production blasts to

    achieve optimal shape and swell of the muckpiles and size of fragmentation

    primarily for increased shovel and truck productivity. This is in addition to

    ensuring that the same blasts produce minimum negative impact on dilution

    and on the integrity of adjacent pit walls and floors. It is however now

    recognized that blast results can be made to satisfy not only the digging,

    handling and grade control requirements but also crushing and milling

    requirements. This has been demonstrated to have a significant and positive

    impact on the overall economics of mining operations. However, to achievethis requires a disciplined implementation of the Mine to Mill concept.

    With respect to milling, the capacity and efficiency of comminution

    processes are strongly influenced by the ROM fragmentation distribution

    which in turn is influenced by the blasting [3, 6, 7, 9, 12, 14, 16].

    Throughput gains of 5-15% have been recorded and confirmed at

    operations with SAG mills such as Highland Valley Copper (Canada),

    Minera Alumbrera (Argentina) and Cadia (Newcrest Mining in Australia)

    through implementation of the Mine to Mill concepts. Current "Mine to

    Mill" trials being conducted at Escondida (Chile), Porgera (Placer Dome in

    Papua New Guinea), OK Tedi (BHP in Papua New Guinea), are indicating

    similar gains.

    Throughput gains and an increase in crusher availability should be

    achievable with the crushing and ball milling circuit (without SAG mills) if

    a disciplined Mine to Mill approach is introduced and properly managed.

    This involves modifications to current mining, crushing and milling

    practices without necessarily compromising some of the mining

    requirements such as productivity, good grade control and integrity of the

    intermediate and final walls.

    2. Crushing circuit survey

    In order to estimate performance and to model the crushing circuit, a

    detailed survey was carried out. Tonnages and power draw from the

    crushers were monitored and samples from different streams were collected

    for sizing. Measurement of the size distributions of the streams around the

    crusher circuit was also carried using the SPLIT image analysis system.

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    3/18

    Mine to mill optimisation for conventional... 51

    Images of the crusher circuit products were obtained using a video camera.

    Still camera pictures were taken of the grizzly oversize stockpile The video

    and still images were used for size distribution analysis using the SPLIT

    system. The oversize and primary crusher feed size distributions obtained

    from the SPLIT system were combined to estimate the ROM size

    distribution.

    3. Size analyses from the SPLIT system

    Using conventional methods to size coarse material such as ROM ore,

    muckpiles, primary crusher products, etc., is extremely difficult and costly.

    At the same time, accurate information about the ore fragmentation is

    essential for the Mine to Mill optimisation process. Image analysis

    techniques such as those used in the SPLIT system enable fragmentation to

    be estimated with reasonable accuracy and with relative ease [1, 16]. The

    size distribution of the grizzly oversize was estimated based on still

    photographs taken from the oversize stockpile. Video images were used to

    analyse the products from the crushing circuit.

    Fig. 1: An example of photograph of the oversize stockpile used for SPLIT

    system analysis

    Figure 1 shows an example of the photograph taken from the oversize

    stockpile. The SPLIT system sizing results obtained from several

    photographs are presented in Figure 2. It can be seen that the most of the

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    4/18

    A. Jankovic and W. Valery52

    oversize is in the 0.5 - 2 m size range. A significant proportion of the ore

    (up to 20%) is larger than 1.5 m.

    0

    20

    40

    60

    80

    100

    0 500 1000 1500 2000 2500

    Size (mm)

    C

    um%Pass

    image 1 image2 image 3 image 4

    image 5 image 6 image 7 average Fig. 2: SPLIT system analysis of the oversize stockpile

    0

    20

    40

    60

    80

    100

    1 10 100 1000

    Size (mm)

    Cum%

    Pass

    Fig. 3: SPLIT on-line results primary crusher product

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    5/18

    Mine to mill optimisation for conventional... 53

    Figure 3 presents the size distributions from the on-line SPLIT system

    analyses of the primary crusher product. A large envelope of the size

    distributions can be observed. This variability comes from the ROM

    material feed to the grizzly as well as the material flow pattern trough the

    grizzly feed chute.

    4. Crushing circuit mass balance

    In order to determine the throughputs of the secondary and tertiary

    crushers and to check the quality of the crushing circuit survey data, a massbalancing procedure was carried out. The mass balancing flowsheet

    constructed in JKSimMet is shown in Figure 4. A summary of the mass

    balancing results is presented in Table 1.

    Fig. 4: Mass balance flowsheet

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    6/18

    A. Jankovic and W. Valery54

    The total circuit SSQ (the sum of differences squared, between the

    experimental and mass balance data) was 275.3 i.e. 34.4 per stream which is

    considered as satisfactory for this survey considering the method of sample

    collection and the variability of the primary crusher feed.

    Table 1: Mass balance summary

    Throughput (t/h) P80 size (mm)Stream

    EXP MB EXP MB

    Primary crusher feed / 489.6 223.6 223.6

    Primary crusher product / 489.6 128.9 121.5

    Secondary crusher product / 644.6 40.1 44.8

    Tertiary crusher product / 445.7 13.7 13.2

    Screen O/S 1 / 644.6 99.4 105.6

    Screen O/S 2 / 445.7 21.5 21.1

    Screen feed 1550 1580 48.3 52.2

    Final crushing product 490 489.6 6.8 6.8

    Note: EXP = experimental; MB = mass balance

    5. Model fitting of the crushing circuit

    The grinding software simulator JKSimMet [11] was used for the circuit

    modelling and simulation. The throughputs obtained from the mass balance

    procedure and the experimental size distributions were used to fit the model

    parameters of the crushers and the screens. The primary crusher model was

    fitted separately using the feed size distribution obtained from the SPLIT

    system and the product size distribution obtained from the belt cut sample.

    The secondary and the tertiary crusher and screens model constants were

    fitted simultaneously. A summary of the model constants obtained from the

    fitting procedures is presented in Table 2.

    The predictions of the tertiary and secondary crusher power were in

    agreement with the survey information. This is important for the simulations

    of the crushing circuit under the different operating conditions.

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    7/18

    Mine to mill optimisation for conventional... 55

    Table 2: Summary of model fitting results

    Model constants K1 K2 K3 t10Primary crusher,

    CSS 120 mm

    129.9 249.4 2.3 7.6

    Secondary crusher,

    CSS 3538 mm

    31.8 76.6 2.3 16.0

    Tertiary crusher,

    CSS 12-15 mm

    12.0 17.2 2.3 30.8

    Screen d50cDeck 1, 38 mm aperture 7.0 28.7

    Deck 2, 11 mm aperture 6.5 9.6

    6. Blasting simulations

    During the crushing circuit survey the ROM ore was not monitored. An

    estimate of the ROM size distribution was obtained from the primary

    crusher feed and the grizzly oversize sizing (from the SPLIT system). Based

    on the primary crusher down time it was estimated that a maximum of 10%

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    1 10 100 1000 10000

    size (mm)

    cum%pass

    current BIF, frag sim

    current volcanoclastic,

    frag sim10 m BIF, frag sim

    5m BIF, frag sim

    ROM JK, estimated

    Fig. 5: ROM size distribution: estimated from the survey data and

    simulated using blasting simulation software

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    8/18

    A. Jankovic and W. Valery56

    of the ROM is coarser than the grizzly size (600 mm). The calculated ROM

    size distribution is shown in Figure 6. The ROM ore size distribution was

    also simulated by using the JKMRC blast fragmentation model [4, 5, 6, 7,

    8]. It can be seen from Figure 5 that a coarser product was predicted by the

    blasting model simulation (labelled as current, frag sim) compared to the

    estimated one (labelled as ROM JK, estimated). It is important that

    agreement is good for particle sizes below 20 mm. The predicted ROM size

    distributions for the modified blast design (5 and 10 m B/F, frag sim) show

    significant increases in 20 mm material and only around 2% material

    coarser than 600 mm. With this type of material as ROM much lower

    crusher down time could be expected, as well as improved crushing circuitthroughput.

    7. Crushing simulations

    Simulations were carried out using the JKSimMet software to assess the

    effect of different ROM size distributions on the crushing circuit. The

    summary of the results is presented in Table 3.

    The response of the crushing circuit to the estimated ROM based on the

    SPLIT system measurements (see previous section) and the simulated ROM

    (see Figure 5, current BIF) was simulated initially. It can be seen from Table3 that simulations with the estimated ROM (ROM est) gave similar results

    to the mass balance results (see Table 1). This was expected as the model

    fitting was carried out using the mass balance data.

    As the results in Table 3 show, considerably more grizzly oversize

    material was obtained with the simulated ROM size distribution (ROM

    sim). The primary crusher feed and the final product throughput were

    therefore reduced. The secondary and tertiary crusher feed throughput was

    reduced by approximately 14 %, proportional to the reduction in primary

    crusher feed. The simulated final product feed size distributions were

    similar. The above simulation results suggest that the crushing circuit is

    mainly affected by the amount of coarse (+ 600 mm) and fine (-20 mm)

    material in ROM. It is relatively insensitive to the size distribution

    difference in the 600 + 20 mm fraction.

    Simulations were also carried out with the finer simulated ROM material

    (5m B/F, frag sim in Figure 5). The current circuit configuration (crusher

    CSS and screen sizes) was compared to a modified circuit designed to

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    9/18

    Mine to mill optimisation for conventional... 57

    produce a finer feed to the ball mill circuit. In the modified circuit the

    secondary crusher CSS was reduced to around 28 mm, the tertiary crusher

    CSS to around 10 mm, the top screen size to 30 mm and the bottom screen

    to 9 mm. These simulation results are presented in Table 4.

    Table 3: Crushing circuit simulation results with the estimated and

    simulated ROM ore

    Throughput (t/h) P80 size (mm)S t r e a m

    ROM est ROM sim ROM est ROM sim

    ROM 540 540 284.0 532

    Grizzly O/S 49.0 114 1627 905Primary crusher feed 489.6 426 223.6 352

    Primary crusher product 489.6 426 127 128

    Secondary crusher product 644.6 556 36.6 36.6

    Tertiary crusher product 445.7 379 10.7 10.6

    Screen O/S 1 644.6 556 114 116

    Screen O/S 2 445.7 379 24.3 24.6

    Screen feed 1580 1361 49.7 50.8Final crushing product 490 426 7.33 7.24

    Note: est = estimated; sim = simulated

    Table 4: Crushing circuit simulation with the finer ROM and modifiedcrusher gaps and screen sizes

    Throughput (t/h) P80 size (mm)

    S t r e a m Currentcircuit

    Modifiedcircuit

    Currentcircuit

    Modifiedcircuit

    ROM 540 450 307 307

    Grizzly O/S 18.1 15.1 753 753

    Primary crusher feed 522 435 292 292

    Primary crusher product 522 435 128 128

    Secondary crusher product 627 644 35.7 30.6

    Tertiary crusher product 482 434 10.6 9.57

    Screen O/S 1 627 644 120 110

    Screen O/S 2 482 434 24.9 18.9Screen feed 1631 1512 50 37.9

    Final crushing product 522 435 7.6 5.7

    Note: current current circuit; modified modified circuit

    It can be observed from Table 4 that with the finer ROM and current

    circuit configuration the circuit throughput could be increased to 522 t/h

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    10/18

    A. Jankovic and W. Valery58

    compared to the current 490 t/h. The amount of +600 mm material would be

    reduced significantly which would in turn significantly reduce the primary

    crusher down time. The secondary and tertiary crusher loads would remain

    similar to the current situation. The final crushing product would be slightly

    coarser. The overall positive effect of the finer ROM obtained by the

    changed blasting practices would be limited to the reduced primary crusher

    down time. Increase in the crushing circuit throughput (t/h) may not be

    relevant due to ball milling circuit constraints.

    On the other hand, with the modified crushing circuit (finer crushing), a

    significantly finer circuit product size could be obtained (P80=5.7 mm

    compared to current 7.2 mm). In this case the crusher circuit throughputwould be reduced to 435 t/h compared to current 490 t/h. The secondary and

    tertiary crusher loads would remain similar to the current situation. The

    reduced crushing circuit capacity may not have a detrimental effect on the

    whole process as it may be balanced by the increase in crushing circuit

    availability due to the reduction in primary crusher down time. With the

    finer feed, the milling circuit throughput could be increased.

    8. Milling simulations

    The milling circuit consist of the primary and the secondary ball mill as

    shown in Figure 6. Primary ball mill operates with large 71 mm ball size

    and the secondary ball mill uses 45 mm balls. The final milling circuit

    product 80% passing size is around 90 m. The model parameters for the

    ball mills and hydrocyclones were determined in a previous study and used

    for the Mine to Mill simulations in this study.

    Simulations of the milling circuit were carried out with the feed obtained

    from the finer ROM/finer crushing simulations in order to estimate the

    increase in throughput which might be obtained when milling this material.

    The results are compared with the current milling practice in Table 5.

    The simulation results presented in Table 5 suggest that an 4.8%increase in ball mill circuit throughput would be obtained with the finer

    milling circuit feed. It can therefore be concluded that the potential benefits

    from the finer blasting could be increased capacity of the milling circuit as

    well as increased availability of the crushing circuit.

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    11/18

    Mine to mill optimisation for conventional... 59

    Fig. 6: Milling circuit simulation flowsheet

    Table 5: Ball mill circuit simulations

    Feed Current Finer Current FinerNew Feed Secondary ball mill product

    Solids mass flow (t/h) 353 370 602 628

    % Solids 99 99 71 71

    P80 (mm) 7.5 5.7 0.246 0.250

    Primary ball mill product Secondary Cyclone Feed

    Solids mass flow (t/h) 639 646 955 998

    % Solids 78 78 60 60

    P80 (mm) 1.36 1.1 0.292 0.294

    Primary Cyclone Feed Secondary Cyclone U/F

    Solids mass flow (t/h) 639 646 602 629

    % Solids 68 68 73 74

    P80 (mm) 1.36 1.1 0.396 0.40

    Primary Cyclone U/F Secondary Cyclone O/F

    Slurry volume flow (m3/h) 286 276 353 370

    % Solids 80 80 45 45

    P80 (mm) 4.9 3.2 0.093 0.093

    Primary Cyclone O/F

    Solids mass flow (t/h) 353

    % Solids 61

    P80 (mm) 0.42

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    12/18

    A. Jankovic and W. Valery60

    9. Evaluation of possible mine to mill benefits using Bond

    methodology

    The efficiency of the crushing and grinding can be estimated using the

    Bond based methodology [2,13]. It was found in the crushing area that there

    are significant differences between the real plant data and the Bond

    calculations and therefore empirical corrections were introduced. The

    following modified Bond equation was proposed for crushing [10]:

    Wc =

    P

    AWi (

    10

    P

    -10

    F

    ) (1)

    where: Wc is energy consumed in crushing (kWh/t),

    Wi is Bond rod mill work index (kWh/t),

    P is sieve size passing 80% of the ore after crushing (m),

    F is sieve size passing 80% of the ore before crushing (m),

    A is a empirical coefficient, dependant on the ore and the crusher

    properties

    For the tumbling mills the correction factors[2,13] were introduced to

    calculate specific grinding energy:

    Wr = K7 K4 K3 Wi (10

    P1-

    P

    10) (2)

    where: Wr is energy consumed in milling (kWh/t),

    P1 is sieve size passing 80% of the mill product (m),

    P is sieve size passing 80% of the mill feed (m),

    K4 is correction factor if the ore feed size is coarser then the

    optimum size

    K7 is correction factor for the size reduction ratio in the ball mill

    K3 is correction factor for the mill diameter

    The correction factor K4 for the ore feed size is calculated as follows:

    K4 = [Rr+ (Wi - 7) (P P

    P

    0

    0

    )] / Rr (3)

    P0 = 16000 (Wi

    13)0.5 for rod mills (4)

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    13/18

    Mine to mill optimisation for conventional... 61

    P0 = 4000 (Wi

    13)0.5 for ball mills (5)

    Rr= P/P1 (6)

    where: Rr size reduction ratio

    P0 optimum mill feed size (m),

    P actual mill feed size (m),

    P1 mill product size (m),

    From equation (5) an optimum primary ball mill feed size (Wi=18.5kWh/t) is calculated, P0 =3.15 mm. The correction factor is therefore

    applied for the feed sizes P > 3.15 mm.

    The correction factor K7 for the size reduction ratio in the ball mill is

    calculated as follows:

    K7 =)35.12(R

    26.0)35.12(R

    r

    r

    +(7)

    where: Rr size reduction ratio in the ball mill

    The need to use size reduction factor would not occur often as this only

    applies when the size reduction ratio is less than 6.

    The correction factor K3 for the mill diameter is calculated as follow:

    K3 = ( ).

    20 2

    .44

    D= 2.0)

    5.0

    .442( = 0.87 (8)

    where: D mill diameter inside liners (m)

    10. Modelling methodology

    To create a Bond based energy-size reduction model of the crushing

    operation, results from the survey were used. The relevant informationextracted from the survey is presented in Table 6.

    The energy consumption for each crushing stage is calculated using two

    methods:

    1. the Bond formula assuming Wi=21 kWh/t and the product sizes

    presented in Table 6.

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    14/18

    A. Jankovic and W. Valery62

    2. using the actual crusher power draws (screening energy not included)

    and the plant throughput.

    Table 6: Crushing data

    crushing

    stage

    crusher

    type

    CSS Crusher

    power

    Throughput F80 P80

    (mm) (kW) (t/h) (mm) (mm)

    primary Jaw C140 110-120 70 500 450 125

    secondary HP500 35-38 350 500 125 25

    tertiary HP500 12-15 700 500 25 7

    Note: CSS - crusher close site setting

    The calculated energy consumption is presented is Table 7. It can be

    seen that differences exist between two methods. The Bond Formula

    overestimates the energy consumption for primary crushing two times,

    while the Bond calculations for the secondary and tertiary crushing were

    similar to the actual plant data.

    Table 7: Energy consumption for crushing (screening energy not included)

    Product

    80%passing

    size

    crushing

    energymethod 2

    cumulative

    crushingenergy

    method 2

    crushing

    energymethod 1

    cumulative

    crushingenergy

    method 1

    Crusher (mm) kWh/t kWh/t kWh/t kWh/t

    primary 125 0.14 0.14 0.28 0.28

    secondary 25 0.7 0.84 0.73 1.01

    tertiary 7 1.4 2.24 1.18 2.20

    The cumulative crushing energy calculated using the actual crusher

    power draws and the plant throughput (method 2) represents the real Sunrise

    dam ore crushing energy and it was used to estimate the coefficient A in

    equation (1). The estimated value was A = 100.

    The energy consumption for the Sunrise dam ore crushing + primary ball

    milling can be estimated using the following Bond based model:

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    15/18

    Mine to mill optimisation for conventional... 63

    Wcr = Wc + Wr (9)

    Wcr =0.5P

    100Wi (

    10

    P-

    10

    F) + 0.87 {[Rr+ (Wi -7) (

    P P

    P

    0

    0

    )] / Rr}

    ()35.12(R

    26.0)35.12(R

    r

    r

    +) Wi (

    10

    P1-

    P

    10)

    It should be emphasized that correction factors are applied in the model

    only if the criteria given by Bond are met [2, 13]. The model predictions of

    the energy consumption for the crushing and primary ball milling for the

    different crushing product and primary ball mill product sizes are presented

    in Figure 7.

    Figure 7 shows that the energy consumption decreases with decreasing

    the crushing product size, i.e. ball mill feed size. The model predicts that the

    decrease in ball milling energy consumption would outweigh the increase in

    energy consumption from finer crushing. This trend is dominated by the

    correction factor for ball mill feed size (K4). The optimum feed size for the

    primary ball mill is 3.15 mm and (K4) increases significantly for the coarser

    feed. The model predicts that the energy consumption could be reduced by4% if the crusher product size is reduced from the current 7 mm to 6 mm.

    10

    11

    12

    13

    14

    15

    16

    17

    18

    4 6 8 10 12 14

    crushing product size P (mm)

    s

    pecificenergy(kWh/t)

    P1 =0.8mm

    P1=0.6mm

    P1=0.4 mm

    P1=0.3mmactual kWh/t

    actual crushing product

    predicted kWh/t

    Fig. 7: Total energy consumption for crushing and primary ball milling

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    16/18

    A. Jankovic and W. Valery64

    It can be seen from Figure 7, that the model predicts higher energy

    consumption (14.6 kwh/t) than the actual plant (13.7 kWh/t) for the product

    size P1 = 0.4 mm. This is mainly due to over-prediction of the crushing

    power. It suggest that a better model for crushing is required.

    The predicted primary ball mill kWh/t is close to the actual. The primary

    ball mill operating work index was calculated based on the survey data

    Wi0 = 29.35 kWh/t. The corrected Bond index was calculated based on the

    laboratory Bond test index Wi = 18.5 kWh/t and appropriate correction

    factors (K4 , K3), Wic = 27.8 kWh/t. Comparing the operating work index

    and the corrected Bond index, 94.7% efficiency of the primary ball mill

    circuit can be calculated. It suggest that the primary ball performs close toits Bond best for the given conditions.

    In summary, using the developed model based on the Bond calculations,

    analysis of the crushing primary ball milling circuit was carried out to

    determine the potential benefits of a mine to mill optimisation and optimum

    crushing product size. It was found that the comminution circuit power

    consumption decreases as crushing product size decreases. By reducing the

    crusher product 80% passing size (P) from 7 mm to 6 mm, the power

    consumption may be reduced by around 4%. This gains are in line with

    those indicated by JKMRC methodology and simulations presented in the

    previous section of this report. Note that the above calculations do not

    include screening power and capacity. Separate calculations are required to

    estimate the cost benefits from finer crushing which would include

    increased operational and maintenance costs.

    11. Conclusions

    The scoping study simulations indicated that the predicted finer ROM

    size distribution could result in primary crusher throughput increase to 522

    t/h compared to the current 490 t/h. The amount of +600 mm material would

    be reduced significantly which would in turn significantly reduce theprimary crusher down time. The secondary and tertiary crusher loads would

    remain similar to the current situation. The final crushing product would be

    slightly coarser. The overall positive effect of the finer ROM obtained by

    the changed blasting practices would be limited to the reduced primary

    crusher down time. Increase in the crushing circuit throughput (t/h) is not

    relevant due to ball milling circuit constraints.

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    17/18

    Mine to mill optimisation for conventional... 65

    On the other hand, with a modified crushing circuit (finer crushing), a

    significantly finer circuit product size could be obtained (P80=5.7 mm

    compared to current 7.2 mm). Simulations indicate that in this case the

    crusher circuit throughput would be reduced to 435 t/h compared to current

    490 t/h. The secondary and tertiary crusher loads would remain similar to

    the current situation. The reduced crushing circuit capacity would not have a

    detrimental effect on the whole process as it would be balanced by the

    increase in crushing circuit availability due to the reduction in primary

    crusher down time.

    The simulation results using JKMRC methodology suggest that an 4.8%

    increase in ball mill circuit throughput (370 t/h vs. current 353 t/h) would beobtained with the finer milling circuit feed from the modified crushing

    circuit. Therefore, the potential benefits from the finer blasting are increased

    capacity of the milling circuit and increased availability of the crushing

    circuit.

    A similar increase in throughput and better energy utilisation was

    predicted using Bond based calculations.

    References

    1. Y.Atasoy, I.Brunton, F.Tapia-Vergara and S. S.Kanchibotla, 1998,

    Implementation of Split to Estimate the Size Distribution of Rocks in Mining

    and Milling Operations, Proc. of Mine to Mill Conference, AusIMM, Brisbane.

    2. F.C.Bond, , 1985. Testing and Calculations. SME Mineral Processing

    Handbook , Norman L. Weiss, Editor in Chief.

    3. B.Bulow, P.Smallbone and P.Walker, 1998, , Blasting for reduced process

    plant costs at Argyle Diamond Mine, Proc. of Mine to Mill Conference,

    AusIMM, Brisbane.

    4. C.Grundstrom, S.S. Kanchibotla, A.Jankovic and D.Thornton, (2001) Blast

    Fragmentation for Maximising the Sag Mill Throughput at Porgera Gold Mine

    Proceedings of the Twenty-Seventh Annual Conference on Explosives and

    Blasting Technique, Orlando, USA5. JKMRC, 1995. The assessment and control of coal damage and loss, ACARP

    Project Report C3017, JKMRC.

    6. S.S.Kanchibotla, S.Morrell, W.Valery and P.OLoughlin , 1998, Exploring the

    effect of blast design on throughput at KCGM, Proc. of Mine to Mill

    Conference, AusIMM, Brisbane

    J. Min. Met. 38 (1 4) A (2002)

  • 7/27/2019 Mine to Mill Optimization

    18/18

    A. Jankovic and W. Valery66

    7. S.S.Kanchibotla, W.Valery and S.Morrell, (1998), Modelling fines in blast

    fragmentation and its impact on crushing and grinding, Proc. Explo-99 Conf.

    Kalgoorlie, Nov (in press).

    8. S.S.Kanchibotla, 1994. Models for assessing the blasting performance of

    explosives. Ph.D Thesis, University of Queensland (JKMRC).

    9. M.Lam, A. Jankovic, W.Valery, S.S.Kanchibotla, (2001) Increasing SAG Mill

    Circuit Throughput at Porgera Gold Mine by Optimising Blast Fragmentation.

    SAG2001 - SAG mill circuit. International Conference on Autogenous and

    Semiautogenous Grinding Technology, 1, p., Vancouver, Canada

    10. N.Magdalinovic et al., 1990. Mathematical Model for Determination of an

    Optimal Crusher Product size. Aufbereitungs-Technik 31, No 5.

    11. R.Morrison and W.Valery, (1999) JKTech software for process design and

    optimisation. IRR Crushing and Grinding Conference, Perth, WA 29-31

    March.

    12. K.Nielsen, (1998), Economic optimisation of the blasting-crushing-

    comminution process in a low-grade iron ore (Taconite) operation, Proc. Mine

    to Mill Conf., Brisbane.

    13. C.A.Rowland, Grinding Calculations Related to the Application of large Rod

    and Ball Mills. Allis-Chalmers Publication 22P4704.

    14. R.Simkus, and A.Dance, 1998, Tracking Hardness and Size: Measuring and

    Monitoring ROM Ore Properties at Highland Valley Copper, Proc. of Mine to

    Mill Conference, AusIMM, Brisbane

    15. W.Valery et al., (2001) Mine to mill optimisation and case studies presented atVI Southern Hemisphere Conference on Minerals Technology in Rio de

    Janeiro, Brazil, 27-30 May.

    16. W.Valery, T.Kojovic, F.Tapia-Vergara and S.Morrell, (1999) Optimisation of

    blasting and sag mill feed size by application of online size analysis. IRR

    Crushing and Grinding Conference, Perth, WA 29-31 March.

    J. Min. Met. 38 (1 4) A (2002)