r r i-95 safety improvements at route 3 · i-95 safety improvements at route 3 city of...
TRANSCRIPT
Response to Request for Proposals
I-95 SAFETY IMPROVEMENTS AT ROUTE 3City of Fredericksburg, Virginia
State Project No.: 0095-111-278Federal Project No.: OC-095-2(535)Contract ID Nmber: C00107715DB91
LETTER OF SUBMITTAL
Submit ted by:
in ASSociAtion With:
ORIGINAL
ATTACHMENT 4.0.1.1 I-95 Safety Improvements at Route 3
LETTER OF SUBMITTAL CHECKLIST AND CONTENTS
1 of 2
Offerors shall furnish a copy of this Letter of Submittal Checklist, with the page references added, with the Letter of Submittal.
Letter of Submittal Component Form (if any) RFP Part 1 Cross Reference
Page Reference
Letter of Submittal Checklist and Contents Attachment 4.0.1.1 Section 4.0.1.1 N/A
Acknowledgement of RFP, Revisions, and/or Addenda Attachment 3.4 (Form C-78-RFP) Sections 3.4; 4.0.1.1 N/A
Letter of Submittal NA Sections 4.1
Letter of Submittal on Offeror’s letterhead NA Section 4.1.1 1
Offeror’s full legal name and address NA Section 4.1.1 1
Authorized representative’s original signature NA Section 4.1.1 1
Declaration of intent NA Section 4.1.2 1
120 day declaration NA Section 4.1.3 1
Point of Contact information NA Section 4.1.4 1
Principal Officer information NA Section 4.1.5 1
Offeror’s Corporate Structure NA Section 4.1.6 1
Full Legal Name of Lead Contractor, Lead Designer, and QAM NA Section 4.1.7 1
Offeror’s VDOT prequalification information NA Section 4.1.8 1
DBE statement confirming Offeror is committed to achieving the required DBE goal NA Section 4.1.9 1
Final Completion Date NA Section 4.1.10 1
ATTACHMENT 4.0.1.1 I-95 Safety Improvements at Route 3
LETTER OF SUBMITTAL CHECKLIST AND CONTENTS
2 of 2
Letter of Submittal Component Form (if any) RFP Part 1 Cross Reference
Page Reference
Attachments to the Letter of Submittal NA Section 4.2
Affiliated and/ or Subsidiary Companies Attachment 4.2.1 Section 4.2.1 2-3
Certification Regarding Debarment Forms Attachment 4.2.2(a)
Attachment 4.2.2(b) Section 4.2.2 4-6
Offeror’s VDOT prequalification information NA Section 4.2.3 7
Evidence of obtaining bonding NA Section 4.2.4 8-10
Full size copies of DPOR licenses and SCC registrations NA Section 4.2.5 12-19
SCC registration information - businesses Attachment 4.2.5 Section 4.2.5.1 11
DPOR registration information - businesses Attachment 4.2.5 Section 4.2.5.2 11
Lead Contractor Work History Form Attachment 4.2.6(a) Section 4.2.6 20-22
Lead Designer Work History Form Attachment 4.2.6(b) Section 4.2.6 23-25
Conceptual Roadway Plans NA Section 4.2.7 26-35
4.1 - Letter of Submittal
4.1 - Letter of Submittal
4.2 - Attachments To The Letter Of Submittal
4.2 - Attachments To The Letter Of Subm
ittal
4.2.1 - Affiliated and/or Subsidiary Com
panies
4.2.1 - Affiliated and/or Subsidiary Companies
ATTACHMENT 4.2.1 State Project No. 0095-111-278
Affiliated and Subsidiary Companies of the Offeror
2
Offerors shall complete the table and include the addresses of affiliates or subsidiary companies as applicable. By completing this table, Offerors certify that all affiliated and subsidiary companies of the Offeror are listed.
The Offeror does not have any affiliated or subsidiary companies. X Affiliated and/ or subsidiary companies of the Offeror are listed below.
Relationship with Offeror (Affiliate or Subsidiary) Full Legal Name Address
Affiliate Atkinson Construction 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Atkinson Contractors, LP 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Shirley Design/Build, LLC 8435 Backlick Road, Lorton, Virginia 22079
Affiliate SCC Infrastructure 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Clark Construction Group, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Clark Civil Construction, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Clark Concrete Contractors, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Clark Construction International, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Clark Construction, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Clark Design/Build, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Clark Facility Services, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Clark Foundations, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Clark Global Technologies, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
ATTACHMENT 4.2.1 State Project No. 0095-111-278
Affiliated and Subsidiary Companies of the Offeror
3
Relationship with Offeror (Affiliate or Subsidiary) Full Legal Name Address
Affiliate Clark Strategic Operations Group, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Clark Real Estate Advisors, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Clark/Balfour Beatty NCE, A Joint Venture 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Edgemoor Real Estate Services, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Innovative Infrastructure, LLC 8435 Backlick Road, Lorton, Virginia 22079
Affiliate Loudoun County Transportation Networks, LLC 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Metro Earthworks, 8435 Backlick Road, Lorton, Virginia 22079
Affiliate Route 28 Corridor Improvements, LLC 8435 Backlick Road, Lorton, Virginia 22079
Affiliate Shirley Pentagon Constructors,, LLC 8435 Backlick Road, Lorton, Virginia 22079
Affiliate Shirley/Clark Loudoun Infrastructure, LLC 8435 Backlick Road, Lorton, Virginia 22079
Affiliate Charlottesville Bypass Constructors, A Joint Venture 8435 Backlick Road, Lorton, Virginia 22079
Affiliate Capital Rail Constructors, a JV 7500 Old Georgetown Road, Bethesda, MD 20814
Affiliate Maryland Transit Connectors 7500 Old Georgetown Road, Bethesda, MD 20814
4.2.2 - Debarment Form
s
4.2.2 - Debarment Forms
4
5
6
4.2.3 - Prequalification Certificate
4.2.3 - Prequalification Certificate
7
4.2.4 - Surety Letter4.2.4 - Surety Letter
8
9
10
4.2.5 - SCC Registrations/DPOR Licenses
4.2.5 - SCC Registrations/DPOR Licenses
ATTACHMENT 4.2.5 State Project No. 0095-111-278
SCC and DPOR Information
11
Offerors shall complete the table and include the required state registration and licensure information. By completing this table, Offerors certify that their team complies with the requirements set forth in Section 4.2.5 and that all businesses listed are active and in good standing.
SCC & DPOR INFORMATION FOR BUSINESSES (RFP Sections 4.2.5.1 and 4.2.5.2)
Business Name
SCC Information (4.2.5.1) DPOR Information (4.2.5.2)
SCC Number
SCC Type of Corporation
SCC Status
DPOR Registered Address
DPOR Registration
Type DPOR Registration
Number DPOR Expiration
Date
Shirley Contracting Company, LLC S082038-3 Limited
Liability Co. Active 8435 Backlick Road Lorton, Va. 22079
Class A Contractor 2705071652 October 31, 2018
Dewberry Consultants LLC S044733-6 Limited
Liability Co Active 8401 Arlington Blvd. Fairfax, Va. 22031
Business Entity 0407003966 December 31, 2017
Quinn Consulting Services, Inc. 0492551-7 Corporation Active
14160 Newbrook Drive Suite 220
Chantilly, Va. 20151
Business Entity 0407003733 December 31, 2017
12
13
14
15
16
17
18
19
4.2.6 - Work History Form
s
4.2.6 - Work History Forms
ATTACHMENT 4.2.6(a)
LEAD CONTRACTOR - WORK HISTORY FORM
(LIMIT 1 PAGE PER PROJECT)
I - 95 SAFE T Y I MP ROVE M E NT S AT R OUT E 3 CI T Y O F FRE DE RI C KSB U R G, VI RGI NI A
A DE SI GN- B UI LD PR OJE CT
a. Project Name & Location b. Name of the prime designconsulting firm responsiblefor the overall projectdesign.
c. Contact information of the Client or Owner andtheir Project Manager who can verify Firm’sresponsibilities.
d. ContractCompletionDate(Original)
e. ContractCompletionDate (Actualor Estimated)
f. Contract Value (in thousands) g. Dollar Value of Work Performedby the Firm identified as the LeadContractor for this procurement.(inthousands)
Original Contract Value
Final or Estimated Contract Value
Name: Route 50 Widening
Location: Fairfax and Loudoun Counties,
Virginia
Name: Dewberry Consultants LLC
Name of Client/Owner: Virginia Department of
Transportation
Project Manager: Susan Shaw, PE Phone: 703-259-1995
Email: [email protected]
12/2014
12/2015*
*Difference Due toOwner added scope
$67,830
$77,337*
*Difference Due toOwner added scope
$77,337
h. Narrative describing the Work Performed by the Firm identified as the Lead Contractor for this procurement. If the Offeror chooses to submit work completed by an affiliated or subsidiary company of the Lead Contractor, identify the full legal name of the affiliate or subsidiaryand the role they will have on this Project, so the relevancy of that work can be considered accordingly. The Work History Form shall include only one singular project. Projects with multiple phases, segments, elements, and/or contracts shall not be considered a single project. If aproject listed includes multiple phases, segments, elements, and/or contracts, the SOQ may be rendered non-responsive. In any case, only the first phase, segment, element, and/or contract listed will be evaluated.
PROJECT NARRATIVE:
In March 2011, Shirley Contracting Company, LLC (Shirley) was awarded the Route 50 Widening Design-Build Project (the Project) by the Virginia Department of Transportation (VDOT). The $77 million project included the reconstruction and widening of Route 50 from 4 to 6-lanes for 3.7-miles from Poland Road (Route 742) to Sully Road (Route 28). One major feature of the Project included right-of-way and temporary/permanent easement acquisitions on 68 properties along the corridor. There were numerous utilities in conflict that had to be relocated. These included overhead/underground power (15,000'), overhead/underground communications (50,000'), gas line relocations (4,000'), sanitary line relocations (1100') and waterline relocations (17,000'). Another important feature was the construction of eight new traffic signals which needed to be maintained during all phases of traffic. In addition, the new roadway construction included two new bridges over Cub Run, a new 10' wide shared use path for each side of the roadway, a new retaining wall (400'), two new box culverts (485'), all new roadway pavement, new storm pipe (31,000'), and storm structures (300 each). The Project required the management of several challenging issues. One of the largest issues was the coordination of utility relocations and right-of-way acquisition in a linear transportation corridor where the majority of the widening resulted in direct utility conflicts. The Team overcame this challenge by closely coordinating the Transportation Management Plan with the right-of-way and utility relocation priorities to ensure that adequate float was provided to third party controlled utility relocations without compromising the aggressive schedule. A key element was creating a sequence that optimized the amount of ultimate roadway that could be constructed concurrent with the acquisition of right-of-way, permits, and the relocation of the utilities. The Team accomplished this by reversing the original RFP sequence of construction and utilizing the median. Additionally, detours were constructed that allowed for the start of reconstruction of the existing pavement within the existing right-of-way. This sequence allowed the right-of-way acquisition and utility relocation phases to run parallel with the early phases of construction and decrease the risk of utility delays that would ultimately impact the final completion date.
PROJECT SCOPE: • 3.7 Miles of Roadway Widening from 4 to 6-Lanes• Extensive coordination and relocation of facilities owned by 15 different utility companies• Acquisition of environmental permits• Improvements to eight signalized intersections• Four new storm water management facilities• Widening and reconstruction of the existing bridges over Cub Run• Right-of-way acquisitions of 68 parcels including one relocation• Contractor administered quality assurance and quality control• Coordination of public involvement• Coordination of waterline relocations with Fairfax Water Authority & Loudoun Water
SHIRLEY'S ROLE:
As the Design-Builder and Lead Contractor, Shirley was responsible for management and oversight of all aspects of construction, including design and engineering, right-of-way acquisitions, permitting, coordination of utility relocations, public outreach before and during the project, overall Project administration and construction management, and Quality Assurance and Quality Control. All construction work was performed on a heavily traveled roadway with over 60,000 vehicles per day passing through the Project. Lane restrictions were coordinated by Shirley with VDOT to allow for public notifications of impacts to traffic. Shirley was the primary point of contact with the Owner in public relations and getting notices out to traveling motorists, businesses, home-owners and local politicians. Shirley was also responsible for creating and monitoring the schedule throughout design and construction.
VERIFIABLE EVIDENCE OF GOOD PERFORMANCE: 1. This aggressively scheduled project was completed on time, without claims, and with
change orders that consisted primarily of owner-directed modifications to add projectscope.
2. The success of this Project was largely due to significant innovations to Maintenanceof Traffic (MOT) during design and construction. During the design process, a sequenceof construction was planned that utilized the median for the first phase of construction sothat work could be done in existing VDOT right-of-way which allowed constructionactivities to be completed simultaneously with the acquisition of right-of-way. During thelater phases of the Project, the sequence of roadway construction was modified to runparallel with the order at which the right-of-way properties were being acquired and theutility relocations being completed. This improved the flow of the schedule and allowedthe project to be completed on-time.
3. Shirley developed work schedules and activity plans to minimize disruptions andimpacts to the public. One example was the reconstruction of an existing intersection inone weekend instead of taking weeks of daily lane closures. This was accomplished byShirley mobilizing extra crews over the weekend and working around the clock in orderto have the intersection rebuilt in one weekend. This required coordination betweenShirley and VDOT to develop an MOT plan and sequence of work for the weekendoperations, as well as public notifications that were sent to the media and local politicians.This approach proved so successful that it was used on several other intersections.
4. Shirley worked closely with local Supervisors, Delegates, and local fire and rescue, tosend out public notifications for any major work activities or shifts in traffic patterns onthe Project. An email distribution list was also developed from the preconstruction"pardon our dust" meetings and quarterly local town hall meetings which were also usedfor public notifications. The local town hall meetings were used as a way to keep thelocal homeowners and businesses well informed of the Project status.
SIMILARITIES TO I-95
SAFETY IMPROVEMENTS AT ROUTE 3
• Design-Build Delivery• Primary Roadway Widening• Intersection Improvements• Signalization of Eight Intersections• Phased Construction• Maintenance of Traffic• Right-of-Way Acquisition• Environmental Permitting• Utility Relocations & Avoidance• Quality Assurance/Quality Control• Transportation Management Plan• Public Involvement and Outreach• Third Party Stakeholder Communication &
Coordination• Worked with Lead Designer – Dewberry
20
ATTACHMENT 4.2.6(a)
LEAD CONTRACTOR - WORK HISTORY FORM
(LIMIT 1 PAGE PER PROJECT)
I - 95 SAFE T Y I MP ROVE M E NT S AT R OUT E 3 CI T Y O F FRE DE RI C KSB U R G, VI RGI NI A
A DE SI GN- B UI LD PR OJE CT
a. Project Name & Location b. Name of the prime designconsulting firm responsiblefor the overall projectdesign.
c. Contact information of the Client or Owner andtheir Project Manager who can verify Firm’sresponsibilities.
d. ContractCompletionDate (Original)
e. ContractCompletionDate (Actualor Estimated)
f. Contract Value (in thousands) g. Dollar Value of Work Performedby the Firm identified as the LeadContractor for this procurement.(inthousands)
Original Contract Value
Final or Estimated Contract Value
Name: Route 27/244 Interchange
Modifications
Location: Arlington, Virginia
Name: Dewberry Consultants LLC
Name of Client/Owner: Virginia Department of
Transportation
Project Manager: Christiana Briganti-Dunn, PE, CCM Phone: 703-259-2960
Email: [email protected]
8/2015
9/2015*
*Difference Due toOwner added scope
$31,400
$32,550*
*Difference Due toOwner added scope
$32,550
h. Narrative describing the Work Performed by the Firm identified as the Lead Contractor for this procurement. If the Offeror chooses to submit work completed by an affiliated or subsidiary company of the Lead Contractor, identify the full legal name of the affiliate or subsidiaryand the role they will have on this Project, so the relevancy of that work can be considered accordingly. The Work History Form shall include only one singular project. Projects with multiple phases, segments, elements, and/or contracts shall not be considered a single project. If aproject listed includes multiple phases, segments, elements, and/or contracts, the SOQ may be rendered non-responsive. In any case, only the first phase, segment, element, and/or contract listed will be evaluated.
PROJECT NARRATIVE:
In August 2011, the Shirley Design-Build Team comprised of Shirley Contracting Company, LLC (Shirley) as the Lead Contractor, and Dewberry Consultants LLC (Dewberry) as the Lead Designer, was awarded the Route 27/244 Design-Build Project (the Project) by the Virginia Department of Transportation (VDOT). The Project included the complete reconstruction of the existing 70-year-old bridge carrying Route 27 (Washington Boulevard) over Route 244 (Columbia Pike) and replacement of the existing box culvert conveying Long Branch through the middle of the interchange. The new, longer, and wider bridge included significant aesthetic features including decorative parapets and abutment walls, memorial pylons at the bridge corners, and haunched girders with a two-tone paint scheme to mimic the arch structure of the old bridge. A light well separates the westbound and eastbound lanes. The bridge also accommodated the widening of Columbia Pike also constructed as part of the Project. In addition, the project included reconfiguration of the interchange ramps to improve safety and community access, signalization of three intersections, removal of one existing traffic signal along Route 244, overhead sign structures, shared use path and sidewalk facilities with connections to existing facilities on Route 244, retaining walls, box culverts, major drainage structures, right-of-way acquisition, utilities design, coordination, and relocation, sound barrier, storm drainage, storm water management and landscaping.
A significant element of the Project was the replacement of an existing 10’ x 7.5’ box culvert that conveyed Long Branch through the center of the Project and was integral with the substructure of the existing bridge. The Team developed a culvert and bridge design concept with a new double 10’ x 10’ culvert aligned through the new bridges while maintaining structural independence between the design elements. This alignment optimized the culvert length, eliminated the need to tunnel large diameter pipes under Washington Boulevard, and minimized the impacts to the Long Branch Flood Plain. This concept also modified the location of the culvert outfall to minimize erosion that has been a maintenance concern for VDOT and Arlington County for many years.
PROJECT SCOPE: • Bridge construction including decorative parapets and abutment walls• Memorial pylons at bridge corners• Haunched girders with two-tone paint scheme• Widening of Columbia Pike• Reconfiguration of interchange ramps• Signalization of three intersections• Overhead sign structures• Shared use path• Retaining walls• 10’ x 10” Double Box culvert• Drainage structures• Sound Barrier• Storm Water Management
SHIRLEY'S ROLE:
As the Design-Builder and Lead Contractor, Shirley was responsible for management and oversight of construction, including design and engineering, right-of-way acquisitions, permitting, utility relocations, public outreach, overall Project administration and construction management, and QA and QC. Lane restrictions were coordinated by Shirley with VDOT to allow for public notifications of impacts to traffic. Shirley was the primary point of contact with the Owner in public relations and getting notices out to traveling motorists, businesses, home-owners and local politicians. Shirley was also responsible for creating and monitoring the schedule throughout design and construction.
VERIFIABLE EVIDENCE OF GOOD PERFORMANCE: 1. To address these stakeholder concerns, our Team engaged regularly with the community
through meetings where concerns were discussed and solutions were offered. Beloware examples of how our Team addressed concerns:• We changed the sequence of construction to eliminate planned night work that was
allowed by the contract.• The Team modified the design which resulted in changes to the planned Maintenance
of Traffic (MOT) on the Project. This resulted in a reduction of impacts toneighboring residential communities and to the hotel. The Team’s response to thecommunity concerns were above and beyond what was required by the contractand is an example of how we provided value to the Owner and project stakeholders.
2. The presence of Potomac Formation clays and silts presented problems with slopeinstability and excessive shrink/swell characteristics. Increasing the complexity of thesesubsurface materials where the planned fill slopes and varying height retaining walls, upto 25’, required to widen the existing roadways. Our Team selected the most costeffective alternatives. For global stability concerns at fill slopes, H-piles were driven at6’ spacing to achieve the required factor of safety for stability. To save costs, wecoordinated the design of temporary shoring systems at the bridge approaches so shoringpiles could be left in place and double as global stability piles. At larger fills wheresettlement was a concern, we reduced loading on compressible materials through the useof lightweight cementitious fill for the embankment and retaining wall backfill. Thematerial reduced the total loading and expected settlement on the compressible claylayers by more than 50%. It also eliminated the need for long settlement wait timesduring construction enabling the project to proceed on schedule and budget.
3. The Project scope also included modifications to the interchange ramps to improve safetyand address multi-modal transportation issues. Our Team worked closely with VDOT tooptimize the ramp alignment while balancing the need to upgrade the existing interchangeto current design standards with the need to minimize the right-of-way impacts outsideof the current tight urban footprint. Through this effort our Team was able to eliminatedesign exceptions and 21 of the 32 design waivers that VDOT’s RFP indicated wouldbe required. The Project was completed on schedule.
SIMILARITIES TO I-95
SAFETY IMPROVEMENTS AT ROUTE 3
• Design-Build Delivery• Primary Roadway Widening• Signalization of Three Intersections• Phased Construction• Maintenance of Traffic• Right-of-Way Acquisition• Environmental Permitting• Utility Relocations & Avoidance• Quality Assurance/Quality Control• Transportation Management Plan• Public Involvement and Outreach• Third Party Stakeholder Communication &
Coordination• Worked with Lead Designer – Dewberry
21
ATTACHMENT 4.2.6(a)
LEAD CONTRACTOR - WORK HISTORY FORM
(LIMIT 1 PAGE PER PROJECT)
I - 95 SAFE T Y I MP ROVE M E NT S AT R OUT E 3 CI T Y O F FRE DE RI C KSB U R G, VI RGI NI A
A DE SI GN- B UI LD PR OJE CT
a. Project Name & Location b. Name of the prime designconsulting firm responsiblefor the overall projectdesign.
c. Contact information of the Client or Owner andtheir Project Manager who can verify Firm’sresponsibilities.
d. ContractCompletionDate (Original)
e. ContractCompletionDate (Actualor Estimated)
f. Contract Value (in thousands) g. Dollar Value of Work Performedby the Firm identified as the LeadContractor for this procurement.(inthousands)
Original Contract Value
Final or Estimated Contract Value
Name: I-66/Route 29 Linton Hall
Interchange
Location: Gainesville, Virginia
Name: Dewberry Consultants
LLC Name of Client/Owner: Virginia Department of
Transportation
Project Manager: Mehrdad Naderi Phone: 703-259-2217
Email: [email protected]
6/2015
9/2015*
*Difference Due toOwner added scope
$74,389
$78,087*
*Difference Due toOwner added scope
$78,087
h. Narrative describing the Work Performed by the Firm identified as the Lead Contractor for this procurement. If the Offeror chooses to submit work completed by an affiliated or subsidiary company of the Lead Contractor, identify the full legal name of the affiliate or subsidiaryand the role they will have on this Project, so the relevancy of that work can be considered accordingly. The Work History Form shall include only one singular project. Projects with multiple phases, segments, elements, and/or contracts shall not be considered a single project. If aproject listed includes multiple phases, segments, elements, and/or contracts, the SOQ may be rendered non-responsive. In any case, only the first phase, segment, element, and/or contract listed will be evaluated.
PROJECT NARRATIVE:
The Virginia Department of Transportation (VDOT) awarded Shirley Contracting Company, LLC (Shirley) the I-66/Route 29/Linton Hall Interchange Improvements Project in Gainesville, Virginia. This Design-Bid-Build project is one of the largest unit price construction projects in Virginia and is the final phase of the Gainesville/I-66 Improvements project (in which Shirley completed Phase III, $81.4 million I-66 Widening). The $76 million project included a pair of overpasses: one carrying Route 29 over the Norfolk Southern Railroad, and one carrying Linton Hall Road and John Marshall Highway over the railroad and Route 29. To further improve traffic flow, Shirley also widened Route 29 to 6-lanes and eliminated driveway entrances and two traffic signals between I-66 and Virginia Oaks Drive. The new, grade-separated interchange at Route 29/Linton Hall Road created a limited-access facility on Route 29 between Virginia Oaks Drive and Heathcote Boulevard. The phased construction also included construction and removal of several traffic detours during construction; over $1 million of earthwork operations including 105,000 cubic yards of excavation and 947,000 cubic yards of embankment; ground improvements; storm water and water utility installation and relocation(s); approximately 59,100 tons of aggregate base; 123,500 tons of asphalt; signal installation/modifications; roadway lighting, TMS and signage; concrete crash walls; 10 MSE retaining walls consisting of approximately 288,000 SF.
A schedule challenge was the erection of 172 prestressed concrete girders over the active Norfolk Southern Railway for bridges that spanned the rail. Being unable to alter any train schedules to perform this work, our Team developed a plan which allowed for all equipment to be located outside the active track area. Working closely with Norfolk Southern, we identified a time when there were only two trains during a 10 hour period. Unfortunately, these two trains were critical for Norfolk Southern. Knowing that we could manage the schedule daily, we elected to utilize this 10 hour period as our erection window. Crews successfully completed the erection of all girders without delay or impact to the Norfolk Southern system. We also combined the final two phases of construction and accelerated construction of those phase from three months each to four weeks total. These final phases consisted of connecting two ramps across an existing detour road.
PROJECT SCOPE: • Four new bridges• Retaining walls• TMS and signage/installation• Concrete crash walls• Roadway lighting• Precast concrete panels• Traffic Control• Guardrail• Pedestrian sidewalk• Utility relocation/installation• Traffic detours
SHIRLEY'S ROLE:
As the Design-Builder and Lead Contractor, Shirley was responsible for management and oversight of construction, including design and engineering, right-of-way acquisitions, permitting, utility relocations, public outreach, overall Project administration and construction management, and QA and QC. All construction work was performed on a heavily traveled roadway. Lane restrictions were coordinated by Shirley with VDOT to allow for public notifications of impacts to traffic. Shirley was the primary point of contact with the Owner in public relations and getting notices out to traveling motorists, businesses, home-owners and local politicians. Shirley was also responsible for creating and monitoring the schedule throughout design and construction.
VERIFIABLE EVIDENCE OF GOOD PERFORMANCE: 1. The rail lines were at high skews to traffic flows on both Route 29 and Route 55, which
created challenges for normal design and construction techniques. To overcome thesechallenges, two bridges were designed/constructed with girder elements perpendicular tothe railroad and not parallel to traffic flowing over top of the NSR, which is atypical. Thisresulted in span lengths of the structures being reduced to lengths so that prestressedconcrete girders could be utilized instead of steel girders. If the girders were placedparallel to traffic flowing over top of the railroad, the bridge span distance would havebeen increased over 10 times of that as designed and constructed. This would have createdlarger bridge structures that would have to be constructed and maintained. The use ofprestressed concrete girders also resulted in lower maintenance costs and longer servicelife for the bridges. Since the bridge girders were on a large skew to traffic flowing overthe new bridges, unusual construction techniques had to also be utilized in placing thebridge deck slabs due to the variations in bolsters over the beams so that a smooth uniformriding surface was constructed for traffic. Overall, this innovative approach to the bridgespans being constructed perpendicular to the rail lines resulted in significantly smallerspans, smaller overall structures, and reduced maintenance and increased service life.
2. The project is an award winning project that has been recognized for design innovationand excellence in asphalt pavement. Its phased construction required extensivecoordination and detailed oversight of intricate construction elements to avoid issues asthe phases of construction progressed all the while maintaining a high quality project.
3. The project has improved traffic flow with smooth riding courses, reduced congestion,improved both motorists and pedestrian safety, and is aesthetically appealing.
4. The Teams public outreach efforts included “pardon our dust” meetings with localcommunity associations to provide updates on the Project and upcoming trafficimpacts. Variable message signs were also used to give advance notification to thetraveling public on traffic shifts and project milestones. The Team also communicateddirectly with the adjacent property owners and businesses about construction thatwould impact them as needed. They also coordinated outreach to county officials andsupervisors on a quarterly basis and prior significant traffic switches.
SIMILARITIES TO I-95
SAFETY IMPROVEMENTS AT ROUTE 3
• Design-Bid-Build Delivery• Interstate Construction/Reconstruction• Signalization/Modifications• Maintenance of Traffic• Phased Construction• Right-of-Way Acquisition• Environmental Permitting• Utility Relocations & Avoidance• Quality Assurance/Quality Control• Transportation Management Plan• Public Involvement and Outreach• Third Party Stakeholder Communication &
Coordination• Worked with Lead Designer – Dewberry
22
ATTACHMENT 4.2.6(b) LEAD DESIGNER - WORK HISTORY FORM
(LIMIT 1 PAGE PER PROJECT)
I - 95 SAFE T Y I MP ROVE ME NT S AT R OUT E 3 CI T Y O F FRE DE RI C KSB UR G, VI RGI NI A
A DE SI GN- B UI LD PR OJE CT
a. Project Name & Location b. Name of the prime/ generalcontractor responsible for overallconstruction of the project.
c. Contact information of the Client andtheir Project Manager who can verifyFirm’s responsibilities.
d. ConstructionContract StartDate
e. ConstructionContract CompletionDate (Actual orEstimated)
f. Contract Value (in thousands) g. Design Fee for the WorkPerformed by the Firm identifiedas the Lead Designer for thisprocurement.(in thousands)
Construction Contract Value (Original)
Construction Contract Value (Actual or Estimated)
Name: Interstate 66 Improvements (Single Design Contract) Location: Prince William County, VA
Name: Ph. I General Excavation Ph. II Moore Brothers Ph. III Shirley Contracting Ph. IV General Excavation Ph. V Shirley Contracting
Name of Client.: VDOT Northern Virginia District Office Project Manager: Amir Salahshoor, PE Phone: 703-259-1957 Email: [email protected]
6/2004
Phase I – 2008 Phase II – 2006
Phase III – 8/2010 Phase IV – 10/2011 Phase V – 8/2015
$215,000 (Estimated)
Phase I - IV $217,145*
*Difference Due toOwner added scope
$10,007
h. Narrative describing the Work Performed by the Firm identified as the Lead Designer for this procurement. Include the office location(s) where the design work was performed and whether the firm was the prime designer or a subconsultant. The WorkHistory Form shall include only one singular project. Projects with multiple phases, segments, elements, and/or contracts shall not be considered a single project. If a project listed includes multiple phases, segments, elements, and/or contracts, the SOQmay be rendered non-responsive. In any case, only the first phase, segment, element, and/or contract listed will be evaluated.
PROJECT NARRATIVE: Dewberry’s Fairfax, Virginia office completed the preliminary and final design for the Virginia Department of Transportation to complete the widening of I-66 between Manassas (Exit 47, Route 234 Business) and Gainesville (Exit 43, Route 29). Dewberry had a single design contract for the design of all elements of this project which was broken into five construction contracts based on funding availability. The project included the following elements:
• Widening of I-66 for over 4-miles from 4 to 8-lanes, including one HOV lane in each direction;• Ramp modifications at the Route 234 Business Interchange;• Ramp modifications at the Route 234 Bypass Interchange;• Complete reconstruction of the Route 29 Interchange in Gainesville; and• Traffic analysis and modeling for additional improvements in Gainesville to improve the
operation of I-66.
As part of preliminary design for the I-66/Route 29 Interchange, traffic analysis, projections and modeling indicated that a new interchange was necessary at the Route 29 intersection with Linton Hall Road along with the need to eliminate at-grade railroad crossings on Route 29 and Gallerher Road. Additionally, the scope included a new local road connection (University Boulevard) between Route 29 and Wellington Road, including a new overpass of I-66 and Norfolk Southern Railroad. Dewberry completed final engineering services for both the University Boulevard and I-66/Route 29/Linton Hall Road Interchange, each of which was completed as a stand-alone construction contract.
Due to funding constraints, construction plans were separated into five plan packages and construction phases. The widening of I-66 was separated into two plan sets and advertised in stages, and the Route 29/Linton Hall Road Interchange, including University Boulevard, was advertised in three construction packages. Dewberry worked with VDOT to identify appropriate packaged elements so that phased improvements and added capacity could be completed as quickly as possible.
PROJECT SCOPE: • Field surveys• Geotechnical Investigations• Environmental permit plate preparation• Traffic and operational analysis and documentation (IJR)• Roadway design, including more than 4 miles of interstate widening• Structural design, including ten new interstate and interchange bridges• Traffic management system (TMS) design• TMP and complex temporary traffic control plan design• Lighting and electrical design and traffic signal design• Public meeting preparation, attendance, and support• Coordination with Norfolk Southern Railroad
DEWBERRY'S ROLE: As the Engineer of Record for the improvements, Dewberry was responsible for all services outlined in the “Project Scope” as well as coordination with sub-consultants and VDOT.
In addition to providing all design services, Dewberry prepared presentations and graphics for multiple public hearings, public meetings, and citizen outreach meetings, provided support to VDOT right-of-way acquisition and negotiation staff during acquisition of right-of-way and easements, and coordinated with Norfolk Southern Railroad for the retaining wall and drainage improvements to avoid impacts to the railroad property. During construction, Dewberry’s involvement continued by providing support through shop drawing reviews, responding to RFI’s, attending monthly coordination meetings and detail-specific construction meetings, and participated in formal partnering meetings and workshops.
Similar to the I-95 Safety Improvements at Route 3, ramps at three interchanges on I-66 were modified or reconfigured to improve traffic operations and reduce congestion. Modifications were completed through development of phased temporary traffic control plans so that service was maintained at all times during construction. Signalized intersections on Route 29 and Route 234 were each modified to reflect the changes in lane configurations and the addition of turning or thru lanes, and signal timings were adjusted to reflect the geometric changes and accommodate current traffic volumes and future projections.
VERIFIABLE EVIDENCE OF GOOD PERFORMANCE: 1. Dewberry was awarded the 2015-2016 ACEC of Metropolitan Washington
Engineering Excellence Merit Award in Design for Phase IV of the project.2. Advertisements for each Phase of the project were delivered on-time with
successful construction bids received below the Engineer’s estimate.3. During construction, it became apparent that conditions of several bridges
which were intended to be minimally rehabilitated (deck overlays andwidenings) had deteriorated to the point that more significant improvementswere required. Dewberry was issued a contract modification to completedesigns for the complete reconstruction of the bridge decks (includingstructural steel) and replacement of all bridge piers. Plans were developedduring construction and coordinated with the Shirley Team ensuringconstruction schedules were not impacted. Plans were issued as aconstruction revision, and reconstruction was able to be completed withoutdelaying the project schedule.
SIMILARITIES TO I-95 SAFETY IMPROVEMENTS AT ROUTE 3
• Field Survey and Base Mapping• Environmental Permitting• Roadway Design• Interchange Modification & Ramp Improvements• Hydraulic Design• Traffic Engineering Design• Utility Relocation Design• Public Involvement/Communication• Quality Assurance/Quality Control• Worked with Lead Contractor - Shirley
Relevant Experience from this Project Includes:• Construction value over $10M for roadway work• At-grade improvements at interchanges• Signal and intersection improvements
23
ATTACHMENT 4.2.6(b) LEAD DESIGNER - WORK HISTORY FORM
(LIMIT 1 PAGE PER PROJECT)
I - 95 SAFE T Y I MP ROVE ME NT S AT R OUT E 3 CI T Y O F FRE DE RI C KSB UR G, VI RGI NI A
A DE SI GN- B UI LD PR OJE CT
a. Project Name & Location b. Name of the prime/ generalcontractor responsible for overallconstruction of the project.
c. Contact information of the Client and theirProject Manager who can verify Firm’sresponsibilities.
d. ConstructionContract StartDate
e. ConstructionContractCompletionDate (Actual orEstimated)
f. Contract Value (in thousands) g. Design Fee for the WorkPerformed by the Firm identifiedas the Lead Designer for thisprocurement.(in thousands)
Construction Contract Value (Original)
Construction Contract Value (Actual or Estimated)
Name: Route 7 Westbound Truck Climbing Lane Design-Build
Location: Loudoun County, Virginia
Name: Shirley Contracting Company, LLC
Name of Client: Virginia Department of Transportation Project Manager: Sanjeev Suri, PE, PMP Phone: 703-259-2232 Email: [email protected]
11/2013 12/ 2015 $27,984 $28,780*
* Difference Due toOwner Added Scope
$1,984
h. Narrative describing the Work Performed by the Firm identified as the Lead Designer for this procurement. Include the office location(s) where the design work was performed and whether the firm was the prime designer or a subconsultant. The WorkHistory Form shall include only one singular project. Projects with multiple phases, segments, elements, and/or contracts shall not be considered a single project. If a project listed includes multiple phases, segments, elements, and/or contracts, the SOQmay be rendered non-responsive. In any case, only the first phase, segment, element, and/or contract listed will be evaluated.
PROJECT NARRATIVE:In 2013, the Shirley-Dewberry design-build Team was awarded the contract to construct a truck climbing lane along westbound Route 7 between the West Market Street Interchange and the Route 9 Interchange. In addition to the truck climbing lane, median access and intersection locations were modified or closed in order to improve the safety of the corridor, and new local roads were completed adjacent to Route 7 to maintain access to local communities and residential properties. The existing West Market Street Interchange was modified to accommodate new turning movements, and the Route 9 Interchange was reconfigured to eliminate stop-controlled interchange ramp intersections and replace them with single-and multi-lane roundabouts.
To further improve safety and operations at the Route 9 Interchange, the Washington and Old Dominion (W&OD) Regional Trail was reconfigured to eliminate at-grade, unsignalized crossings and incorporate a free-flow grade separated facility which now passes beneath Route 9 and an interchange ramp. To provide this new trail alignment, a new single-span arch structure was completed beneath one of the interchange ramps, and architectural treatments and landscaping were incorporated to mimic adjacent trail features and structural elements.
PROJECT SCOPE: • Field surveys• Environmental permitting, wetland delineations, and permit monitoring• Roadway design• Roundabout design and analysis• Structural design including bridge modifications and retaining walls• Hydraulic design and stormwater management• Temporary traffic control and transportation management plan development• Lighting and electrical design• Landscape design• Public meeting preparation, attendance, and support
DEWBERRY'S ROLE:As the Lead Designer, Dewberry’s Fairfax, Virginia office was responsible for completion of all engineering services required by the scope of the project. Additional services completed by Dewberry’s Fairfax office included field surveys and all environmental permitting and documentation. Dewberry also oversaw sub-consultant services to complete updated project aerial mapping, utility designations and test pits, geotechnical investigations, and pipe condition inspections and analysis.
During construction, Dewberry continued to attend public outreach meetings with the local community and regular progress meetings with VDOT and Loudoun County. Dewberry also reviewed all construction submittals, responded to construction RFIs, and completed permit monitoring as required by the environmental permits.
Similar to the I-95 Safety Improvements at Route 3 project, the Route 7 Truck Climbing Lane project included reconfiguration of the Route 7/Route 9 Interchange to improve capacity, and at-grade intersections on Route 7 were eliminated or reconfigured to address safety concerns. Modifications to the interchange ramps at the Route 9 interchange were completed as part of the reconfiguration of the interchange to incorporate roundabouts at each of the ramp terminals on Route 9. During design, Dewberry worked with VDOT to complete additional analysis of the roundabouts, and developed alternate concepts for both single lane and two-lane operations. Original contract requirements were to open the roundabouts in a single lane configuration, but construct the facilities to accommodate future 2-lane roundabout operation in the event that traffic volumes required the added capacity. Based on continued public outreach and additional analysis of the roundabouts, our Team and VDOT recognized the need to immediately open the roundabouts to 2-lane operations. Dewberry worked to update the plans for the 2-lane configuration, which was completed without delay to the project or additional impacts to the traveling public.
VERIFIABLE EVIDENCE OF GOOD PERFORMANCE: 1. The project was completed on-time, including additional scope elements to provide
additional landscaping adjacent to private properties along Route 7 and modify theroundabouts to provide 2-lane operations.
SIMILARITIES TO I-95 SAFETY IMPROVEMENTS AT ROUTE 3
• Design-Build Delivery• Field Survey and Base Mapping• Environmental Permitting• Geotechnical Investigations• Roadway Design• Hydraulic Design• Traffic Engineering Design• Multi-Stages of TTC• Utility Relocation Design• Public Involvement/Communication• Quality Assurance/Quality Control• Worked with Lead Contractor - Shirley
Relevant Experience from this Project Includes:• Construction value over $10M for roadway work• At-grade improvements at interchanges• At-grade intersection improvements
24
ATTACHMENT 4.2.6(b) LEAD DESIGNER - WORK HISTORY FORM
(LIMIT 1 PAGE PER PROJECT)
I - 95 SAFE T Y I MP ROVE ME NT S AT R OUT E 3 CI T Y O F FRE DE RI C KSB UR G, VI RGI NI A
A DE SI GN- B UI LD PR OJE CT
a. Project Name & Location b. Name of the prime/ general contractorresponsible for overall construction of theproject.
c. Contact information of the Client andtheir Project Manager who can verifyFirm’s responsibilities.
d. ConstructionContract StartDate
e. ConstructionContractCompletion Date(Actual orEstimated)
f. Contract Value (in thousands) g. Design Fee for the WorkPerformed by the Firm identifiedas the Lead Designer for thisprocurement.(in thousands)
Construction Contract Value (Original)
Construction Contract Value (Actual or Estimated)
Name: Route 50 Widening
Location: Fairfax and Loudoun Counties, Virginia
Name: Shirley Contracting Company LLC Name of Client: Virginia Department of Transportation Project Manager: Susan Shaw, PE Phone: 703-259-1995 Email: [email protected]
3/2011 (Design-Build
Contract Execution)
12/2015*
*Difference Due toOwner added scope
$67,830 77,337*
*Difference Due toOwner added scope
$4,127
h. Narrative describing the Work Performed by the Firm identified as the Lead Designer for this procurement. Include the office location(s) where the design work was performed and whether the firm was the prime designer or a subconsultant. The WorkHistory Form shall include only one singular project. Projects with multiple phases, segments, elements, and/or contracts shall not be considered a single project. If a project listed includes multiple phases, segments, elements, and/or contracts, the SOQmay be rendered non-responsive. In any case, only the first phase, segment, element, and/or contract listed will be evaluated.
PROJECT NARRATIVE:In 2011, the Design-Build Team of Shirley Contracting and Dewberry was awarded the contract for the widening of Route 50 from 4 to 6-lanes between Poland Road and Route 28, a distance of approximately 5-miles. Dewberry’s Fairfax, Virginia office was responsible for all final design of the project. In addition to widening the road to provide increased capacity, the existing pavement was completely reconstructed and a new roadway alignment was developed to maintain a 50’ median throughout the corridor. Local access points were consolidated and modified, and 8 signalized intersections were either modified or added as part of the Project.
During design, Dewberry worked with VDOT and adjacent property owners to incorporate additional improvements to avoid future reconstruction and impacts to the traveling public. Improvements added to the project included additional turn lanes and auxiliary lanes on Route 50, Avion Parkway, and Stonecroft Boulevard, and a new ramp connection from southbound Route 28 to southbound Lee Road via a new signalized intersection on westbound Route 50.
PROJECT SCOPE: • Field surveys• Environmental surveys, coordination and permitting• Roadway design• Structural design for Route 50 bridge over Cub Run• Structural design for multiple retaining walls• Hydraulic and stormwater management design• Maintenance of Traffic Plan development for seven stages of construction• Traffic signal design and corridor timing development• Right-of-way and utility easement plan development• Sanitary sewer and water main relocation design• Public meeting involvement
DEWBERRY'S ROLE:Dewberry served as the Lead Designer for the Shirley design-build Team and was responsible for all of the items listed in the “project scope” section. In addition to all engineering design, Dewberry also oversaw all design sub-consultant services including aerial mapping, utility designations and test pits, geotechnical investigations and recommendations, and traffic data collection.
At the outset of design, our Team developed an alternate sequence of construction concept which allowed construction to start within existing right-of-way and before utilities were relocated. This allowed construction to begin approximately 12 months in advance of the originally anticipated construction start date. In order to implement this accelerated construction start, Dewberry developed an advance construction plan package which included only the first two stages of construction. This allowed temporary pavement and bridge construction to begin ahead of final plans being approved, and allowed work to be completed on a parallel path with right-of-way acquisitions and utility relocations. Additional details of other design scope of work completed by Dewberry include:
• Five miles of 36” water main relocation design• Layout of all utility easements and utility relocations, which were then detailed by
individual utility companies (power, communication, and gas) for construction• Development and approval of final right-of-way plans• Development of new/updated traffic signal timings after construction due to additional
and unexpected growth west of the project in Loudoun County• Detailed maintenance of traffic plans• Modifications to the Route 28 Interchange to provide signalized access and
channelized turn lanes from southbound Route 28 to southbound Lee Road viawestbound Route 50.
While the original roadway was only 2-lanes in each direction, the rapid development of residential communities in western Loudoun County required the Temporary Traffic Control (TTC) plans to be revised during construction to accelerate the opening of a third lane for the eastern half of the project. Working with VDOT and Shirley, Dewberry developed new TTC plans which minimized the amount of additional temporary paving required while ensuring a third lane could be maintained during the remainder of the project.
VERIFIABLE EVIDENCE OF GOOD PERFORMANCE: 1. The project was completed on-time, including the additional scope which was added
to the contract to provide improved traffic flow at the Lee Road intersection.
SIMILARITIES TO I-95 SAFETY IMPROVEMENTS AT ROUTE 3
• Design-Build Delivery• Field Survey and Base Mapping• Environmental Permitting• Geotechnical Investigations• Roadway Design• Hydraulic Design• Traffic Engineering Design• Signalized Intersection Design & Corridor Timing• Utility Relocation Design• Public Involvement/Communication• Quality Assurance/Quality Control• Worked with Lead Contractor - Shirley
Relevant Experience from this Project Includes:• Construction value over $10M for roadway work• At-grade improvements at an interchange• Signal and intersection improvements
25
4.2.7 - Conceptual Roadway Plans
4.2.7 - Conceptual Roadway Plans
DESIGN FEATURES RELATING TO CONSTRUCTION
OR TO REGULATION AND CONTROL OF TRAFFIC
MAY BE SUBJECT TO CHANGE AS DEEMED
NECESSARY BY THE DEPARTMENT
TYPICAL SECTIONS2A(1)
2A(1)
LB
12'12'2'
SHOULDER
or GS-11SE RATE
AUX. LANE
2% OR SE
1'
B
SHOULDER
8'4'2'
A B C D
3'
L
PGS-11
6'
2'
2% OR SE
2:1 M
AX
GS-11
A B C D
P
U
LEGEND
B
A
D
H
Profile Grade LineP
U Underdrain, St'd. UD-4
M
CCurb, St'd. CG-3
6" Asphalt Concrete, Type BM-25.0A
Asphalt Concrete, Type SM-12.5A @ 220 lbs/sy
Asphalt Concrete, Type IM-19.0D @ 220 lbs/sy
LANE
AUX. /THRU
THRU LANE
EXIST.
THRU LANE
EXIST.
SHOULDER
EXIST.
LB
12' 2'
SHOULDER
2% OR SE
1'
ABCD
P
U
THRU LANE
EXIST.
THRU LANE
EXIST.
SHOULDER
EXIST.
THRU LANE
EXIST.
AUX. LANE
EXIST. AUX. LANE
G
G Guardrail, St'd. GR-2
VAR. 0'-12'
VAR. 0'-12' VAR. 0'-12'
GS-11
V Variable Depth Overlay/Build-up
J
K Solid Concrete Raised Median Strip, St'd. MS-1A
R Retaining Wall
U1
Underdrain, St'd. UD-2
M
12'
B
SHOULDER
8'4'2'
A B C D
3'
L
PGS-11
6'
2'
2% OR SE
2:1 MAX
GS-11
G
12' 12' VAR. 0'-12'
4: 1 4: 1
4: 1 4: 1 4: 1
VAR. 0'-12' 12'
B
SHOULDER
8'4'
A B C D
L
P
GS-11
2'
2% OR SE GS-114: 1
18'
1' 1'
J
with Flexible Post Delineators
Solid Concrete Raised Median Strip, St'd. MS-1 1
Solid Concrete Raised Median Strip, St'd. MS-1
J
3' 6'
2:1 M
AX
G
2'
A Asphalt Concrete, Type SM-12.5E @ 220 lbs/sy1
C 8" Asphalt Concrete, Type BM-25.0A1
Connected to a Standard UD-4 Edge Drain
8" Aggregate Base Material, Type I, Size No. 21B
D1
to be Extended and Daylighted
8" Aggregate Base Material, Type I, Size No. 21B
Mill Existing Pavement, 2"
A1
A1
4: 1
1
1
D2
Matching Bottom of Exist. Aggregate Base Material
Min. 8" Aggregate Base Material, Type I, Size No. 21B
1AA
1 U A1
A
M
D1
11A A
GS-11
Q Point of Rotation
W Concrete Median Barrier, St'd. MB-8A
W UU
RAMP B DECELERATION LANES
I-95 SOUTHBOUND
RAMP A
I-95 RAMPS
RAMP B
I-95 RAMPS
LOOP RAMP B
I-95 RAMPS
RAMP A ACCELERATION LANES
I-95 NORTHBOUND
U
PROJECT MANAGER
SURVEYED BY, DATE
DESIGN BY
SUBSURFACE UTILITY BY, DATE
STATEREVISED
ROUTE PROJECT
STATESHEET NO.
SHEET NO.PROJECT
0659-053-262
VA.RW-201, C-5010095-111-27895
Accumark, 3/18/16
Dewberry Consultants, LLC - (703) 289-4796
RICE & Associates
26
DESIGN FEATURES RELATING TO CONSTRUCTION
OR TO REGULATION AND CONTROL OF TRAFFIC
MAY BE SUBJECT TO CHANGE AS DEEMED
NECESSARY BY THE DEPARTMENT
TYPICAL SECTIONS
2A(2)
BL
P
THRU LANE
EXIST.
THRU LANE
EXIST.
THRU LANE
EXIST.
4'0'-12'
TURN LANE
A B C D
2% OR SE
1'
2%2:1 MAX.
1'
1' 1'
TURN LANE
A B C D
THRU LANE
EXIST.
THRU LANE
EXIST.
THRU LANE
EXIST.
8'
SHOULDER
EXIST.
2'20' 20''
THRU LANE
EXIST.
TURN LANE
1'
2' BUFFERBL
TURN LANE
2% OR SE2% OR SE
TURN LANE
VAR. 4'-12'
2'
MATCH EXIST.
WIDENING
VAR. WIDTH
8' 2'12'
THRU LANE
GS-11
SHOULDER
5'
2:1 MAX
1'
WIDENING
VAR. WIDTH
MATCH EXIST. MATCH EXIST.
6'
BL
THRU LANE
EXIST.
THRU LANE
EXIST.
THRU LANE
EXIST.
AUX. LANE
EXIST.
8'
SHOULDER
EXIST.
2' VAR. 0'-12' VAR. 0'-12' VAR. 0'-12' VAR. 11'-12' VAR. 11'-12'
THRU LANE THRU LANE
AUX. LANE
EXIST.
8'2'
AUX. LANETURN LANE
0'-11'
SHOULDER
GS-11
1'
WIDENING
VAR. WIDTH
MATCH EXIST.
11'
AUX. LANETURN LANE
1'
WIDENING
VAR. WIDTH
MATCH EXIST.
MATCH EXIST.
11'11'
1'
5'
2'
TURN LANE
12'
2% OR SE
8'2'
SHOULDER
2%
LEGEND
B
A
D
H
Profile Grade LineP
U Underdrain, St'd. UD-4
M
CCurb, St'd. CG-3
6" Asphalt Concrete, Type BM-25.0A
Asphalt Concrete, Type SM-12.5A @ 220 lbs/sy
Asphalt Concrete, Type IM-19.0D @ 220 lbs/syG Guardrail, St'd. GR-2
VAR. 0'-12' VAR. 11'-12' VAR. 11'-12' VAR. 11'-12'
MATCH EXIST.
VAR. 11'-12' VAR. 11'-12' VAR. 11'-12' VAR. 11'-12' VAR. 11'-12' VAR. 11'-12' VAR. 11'-12' VAR. 0'-12'
A B C D
M
V Variable Depth Overlay/Build-up
V
J
K Solid Concrete Raised Median Strip, St'd. MS-1A
A B C DJ
R Retaining Wall
R U
M A M
MM
K A B C D
G
U
U1
Underdrain, St'd. UD-2
U H
4: 1
4: 1
J
with Flexible Post Delineators
Solid Concrete Raised Median Strip, St'd. MS-1 1
Solid Concrete Raised Median Strip, St'd. MS-1
1
B
SHOULDER
A B C
L
P
2'
2% OR SE GS-114: 1
1' 1'
VAR. 0'-16'4'2'
GS-11
4: 1
B
A B C D
L
P
2% OR SE
1'
J
2% OR SE
8' 2'
SHOULDER
2%
RU
VAR. 12'-16'1'-4'
VAR.
1
VAR.
A Asphalt Concrete, Type SM-12.5E @ 220 lbs/sy1
C 8" Asphalt Concrete, Type BM-25.0A1
Connected to a Standard UD-4 Edge Drain
8" Aggregate Base Material, Type I, Size No. 21B
D1
to be Extended and Daylighted
8" Aggregate Base Material, Type I, Size No. 21B
Mill Existing Pavement, 2"
A1
A1
A1
1
1
1
12
D2
Matching Bottom of Exist. Aggregate Base Material
Min. 8" Aggregate Base Material, Type I, Size No. 21B
11A
D1 1
AA MD1
A1
P Q
Q Point of Rotation
1
2A(2)
G
ROUTE 3
ROUTE 3
W Concrete Median Barrier, St'd. MB-8A
SLIP RAMP B
I-95 RAMPS
SLIP RAMP B
I-95 RAMPS
2:1 MAX
G
SHOULDER
2'
8'
8' 5'
2'
PROJECT MANAGER
SURVEYED BY, DATE
DESIGN BY
SUBSURFACE UTILITY BY, DATE
STATEREVISED
ROUTE PROJECT
STATESHEET NO.
SHEET NO.PROJECT
0659-053-262
VA.RW-201, C-5010095-111-27895
Accumark, 3/18/16
Dewberry Consultants, LLC - (703) 289-4796
RICE & Associates
27
T
TC
TC
TV
TT
880013B
T
F
TV
T164 10 C3 6474
Vzn
T
880013A
TC
8800
13C
TC
F
(no #)
Vzn
(Empty Con
duit - VZ
N)
(COX)
(COX)
(PE
G)
Not On Records
(VZN)
(VZN)
(Irr.)
(Irr.)
(Irr.)
(Irr.)
(VZ
N)
#QD77
#109Ductile Iron
Ductile Iron
PVC
PV
C
#110
Per GIS (#112
Inaccessible
)
#112
#111 A
B
8" P
VC
Ductile Iron
Ductile Iron
S
S
S
S
D
D
D
D
D
D
D
#206
#205
#203
#204
#202
#201
#228
#230
#207
#200
15" RCP
15" R
CP
15" R
CP
18" RCP
24" RCP
24" RCP
24" RCP
15" R
CP
#21418" RCP
#229
18" CMP
18" RCP
15" CMP
18" R
CP
D
A
A
B
B
C
Underdrain
D
D
D
D
D
18" RCP
15" RCP
18" R
CP
18" RCP 24" RCP
24" CMP
24" C
MP
15" RCP
A
In. Pl. C
onc. DI
Rim
= 239.12
In. Pl. C
onc. DI
Rim
= 239.6
4
In. Pl. 15"
RCP
B
C
Inv. In=
234.6
0In
v. O
ut= 2
33.0
9
In. Pl. 15"
CM
PIn
v. In=
233.0
7In
v. O
ut= 2
31.54
D
E
In. Pl. 18"
RCP
Inv. In=
230.7
1In
v. O
ut= 2
23.8
0
F
Rim
= 236.10
In. Pl. M
etal
Grate
In. Pl. 2
4"
CM
PIn
v. In=
224.2
0In
v. O
ut= 2
06.2
5
In. Pl. 2
4"
CM
PIn
v. In=
231.98
Inv. O
ut= 2
23.6
6
FEDCBA
G
G
H
H
J
K
LM
N
Rim
= 240.2
6
In. Pl. M
etal
Grate
Rim
= 240.3
0
In. Pl. M
etal
Grate
In. Pl. S
SM
HRim
= 240.3
8
In. Pl. 18"
RCP
Inv. In=
232.6
1
In. Pl. 2
4"
RCP
Inv. In=
236.0
8In
v. O
ut= 2
32.7
4
Inv. In=
239.11
Inv. O
ut= 2
32.15
In. Pl. 18"
RCP
Inv. In=
236.12
Inv. O
ut= 2
32.8
3
O
(Surcharged)
In. Pl. 18"
RCP
with F
ES
J KM
Inv. O
ut= 2
32.14
LN
P
Q
S
O P
In. Pl. C
onc. DI
Rim
= 241.83
In. Pl. C
onc. DI
Rim
= 245.3
6
In. Pl. 15"
RCP
Inv. In=
240.13
Inv. O
ut= 2
36.0
0
Q
R
R S
(S 72°0
6'19" W 94.34'
)
47.58')
(S 87°47'22" W
(N 21°39'4
7"
W 19
5.0
0')
(N 78°26'56"
E 177.17')
(N 78°26'56"
E 315.65')
(S 78°26'56"
W 173.23')
L= 80.44')
(R= 50.00'
L= 76.64')
(R= 50.00')
L= 61.43')
(R= 13
5.00')
L= 6
8.10')
(R= 13
5.0
0')
L= 10.55')
(R= 2830.42')
(L= 63.52')(R= 2830.42')
(N 09°2
2'2
4"
W 89.0
3')
85.3
6')
(S 30°3
9'3
1" E
(S 86°43'23" W 377.75')
(N 05°0
1'16" E 13
5.9
5')
(S 85°51'07" E
5.18')
90.0
1')(S 09°5
1'04" E
(S 85°57'28" E 119.79')
52.13')
(N 29°15'5
6" E
(S 05°2
2'3
1" W 14
9.8
6')
(S 83°07'47" E 99.84')
(N 82°11'29" W 99.84')
(N 04°2
6'13" E 14
9.8
6')
100.16')
(S 82°34'38" E
(N 05°14'3
5" E 14
9.2
0')
DB 199 PG 340
Ex. 30' Ingress/Egress Esmt.
DB 248 P
G 457
Ex. 20' In
gress/
Egress Es
mt.
(Approximate Location)
DB 197 PG 135
Ex. VEPCO Esmt.
(S 78°26'56"
W182.55
')
L= 47.34')(R= 26
8.22'
24.94')
(N 68°
20'13"
E
31.50')(N
68°20'
13" E
81.18')
(N 21°39'4
7"
W
97.12')
(N 18°4
6'3
7"
W82.2
6')
(S 21°39'4
7" E
77.0
4')
(N 21°39'4
7"
W
(N 21°39'4
7"
W 233.4
6')
PB 7 P
G 54
Ex. 2
0' S
anita
ry Sewer Es
mt
PB 9 P
G 33
Ex. W
aterlin
e Esmt.
Ex. 15' In
gress/
Egress Es
mt. PB
9 PG 3
3
PB 7 P
G 54
Ex. W
aterlin
e Esmt.
PB 9 PG 33Ex. 20
' Waterline Es
mt.
PB 7 PG 54
Sewer Esmt.
Ex. 20' Sanita
ry
78.32')
(N 5
9°20'2
9" E
(S 09°2
2'2
4" E 203.2
5')
61.77')(S 78°
38'18" W
9.45')(S
72°06'19
" W
L=
66.3
1')
(R=
90.0
0'
66.9
2')
(S 09°2
2'2
4" E
PB 9 P
G 13
0
Ex. 20' Sanitary Sewer Es
mt.
PB 9 P
G 20
Ex. 20' Sa
nitary
Sewer
Esmt.
(N 03°16'3
7"
W 336.2
8')
(S 03°16'3
7" E 317.0
9')
135.12')
(N 86°43'23" E
60.8
8')
(S 11°3
3'0
4" E
80.3
5')
(S 03°16'3
7" E
48.60')
(N 86°43'23" E
22.18')
(S 03°16'3
7" E
24.03')
(S 87°28'49" E
36.04')
(N 86°43'23" E
54.7
3')
(S 03°16'3
7" E
23.5
0')
(S 05°3
9'3
0"
W
28.5
0')
(S 03°16'3
7" E
PB 8 PG 27Ex. Sa
nitary Sewer
Esmt.Ex. 15'
Sanitary Sew
er Esmt. PB 8 P
G 53
PB 8 PG 27Ex. Wa
terline Esmt.
(S 86°43'23" W 132.00')
DB 290 PG 659
Ex. Bell Atlantic Esmt.
(Approx. L
ocation)
DB 276 P
G 12
4Ex. 15'
Vir
ginia Power Es
mt.
(Approx. L
ocation)
DB 290 P
G 700
Ex. 15'
Vir
ginia Power Es
mt.
PB 9 P
G 33
Ex. 24' In
gress/
Egress Es
mt.
PB 9 PG 3
3
Ex. 24' Ing
ress/E
gress
Esmt.
PB 9 PG 33Ex. 15'
Ingress/Egr
ess Esmt.PB 9 P
G 130Ex. 15' Ingres
s/Egress Es
mt.
PB 8 PG 27& Stor
m Sewer Eas
ementEx. 50
' Ingress/Eg
ress Esmt.
PB 9 P
G 10
3
Ex. 24' In
gress/
Egress Es
mt.
PB 9 P
G 10
3
Ex. 12' In
gress/
Egress Es
mt.
PB 8 P
G 69
Ex. 12' In
gress/
Egress Es
mt.
Ir
Ir
Ir
Ir
Ir Ir Ir
Ip
Ir
Ir
RW
Mon.
RW
Mon.
Ir Ir
Ir Ir
Ir
RW
Mon.
Ir
(N 06°4
9'2
8" E 277.7
8')
(N 25°51'56"
W 18
2.72')
18.94')(S 89°
53'21" W
(S 88°12'23" W 142.39')
18.38')
(S 36°58'2
9" E
155.66')
(N 64°21'06
" E
PB 5 P
G 22
Ex. 30' In
gress/
Egress Es
mt.
(S 06°4
9'2
8"
W)
Existing VDOT Limited Access R/W per Plans 0095-089-101
PB 9 P
G 40-4
7Varia
ble
Width R/
WCarl
D. Silver Parkway
Existing VDOT R/W per Plans 0095-089-101
per Plans 00
95-089-101Existin
g VDOT R/W
DB 316 PG 723
DB 288 PG 536
for Public Use
City of Fredericksburg
Dedicated to the
Commerce Street
N 03°0
5'3
4"
W
S 03°0
5'3
4" E
S 11°2
2'0
1" E
N 59°31'3
2" E
S 30°2
8'2
8" E
N 21°26'4
7"
W
N 21°26'4
7"
W
S 01°46'18" E
N 01°54'17"
W
N 04°3
6'3
1" W
N 02°0
7'3
6"
W
N 36°58'19"
W
N 89°20'21" W
N 85°27'26" E
S 04°16'5
4" E
N 89°24'21" W (N 83°11'47" W 105.32')
(S 82°15'29" E 105.32')
N 68°
33'13" E
(S 68°
20'13"
W 109.17')
PB 5 PG 22Ex. 20
' Ingress/Egr
ess Esmt.
Ir
Existing VDOT R/W per Plans 0095-089-101
Existing VDOT R/W per Plans 0095-089-101
Ir
End Limited Access
End Limited AccessLimited Access Line per Plans 0095-089-101
E
T
T
T
T
T
T
E
T
A
B
CENTRAL PARK 1218, LLCInst.# 050001917PB 11 PG 90-91
1.755 AC.GPIN# 7769-62-4664
CENTRAL PARK 1223, LLCInst.# 050001919PB 11 PG 90-91
1.434 AC.GPIN# 7769-62-7720
D
CENTRAL PARK 1200, LLCInst.# 050001909
PB 8 PG 69-70
GPIN# 7769-72-0750
FREDERICKSBURG 35, LLCInst.# 020003407PB 9 PG 102-103
0.990 AC.GPIN# 7769-62-9730
PB 10 PG 159
GPIN# 7769-6
2-9857
CARL D. SILVER, ESTATE
PB 8 PG 27-3
1
2.32 AC. (Per
GIS)
Inst.# 060003016
GPIN# 7769-62-5175
DEVELOPMENT, LLC
FREDERICKSBURG
0.3430 AC.
PB 7 PG 54
0.643 AC.
GPIN# 7769-62-0541
FREDERICKSBURG 35, LLCInst.# 020003400
PB 9 PG 33
0.932 AC.
GPIN# 7769-62-1652
C
D
DB 300 PG 489
0.111 AC.
GPIN# 7769-62-4532
OWNERS ASSOCIATION, INC.THE CENTRAL PARK PROPERTY
Inst.# 150003110
PB 9 PG 130-132
1.396 AC.
GPIN# 7769-62-0862
OWNER ONE, LLCMACH II MCB SILVER PORTFOLIO
Inst.# 060003016
9.8445 AC.GPIN# 7769-71-1827
FREDERICKSBURG DEVELOPMENT, LLC
Inst.# 150000201
2.4231 AC.GPIN# 7769-61-6928
PB 14 PG 72
FREDERICKSBURG DEVELOPMENT, LLCInst.# 060003016
GPIN# 7769-62-5175
DEVELOPMENT, LLC
FREDERICKSBURG
0.3430 AC.
RICHARD A. PRUITTInst.# 030004267
.5063 AC.GPIN# 7769-62-4137
PB 5 PG 22PB 12 PG 43A
Inst.# 030004264PB 12 PG 43A
1.0815 AC. (Per GIS)GPIN# 7769-62-2163
RICHARD A. PRUITT
Inst.# 030004264
0.57 AC. (Per GIS)GPIN# 7769-62-1142
RICHARD A. PRUITT
PB 12 PG 43A
Denotes Construction Limits in Cuts
Denotes Construction Limits in Fills
VA.
STATE
ROUTE PROJECT
REVISEDSTATE
STATE
ROUTE PROJECTSHEET NO.
PROJECT SHEET NO.
PROJECT MANAGER
SURVEYED BY, DATE
DESIGN BY
SUBSURFACE UTILITY BY, DATE
VA.
0
SCALE
50' 100'
3
Denotes Full Depth Pavement
Denotes Existing Pavement
Denotes Milling and Overlay/Build-Up
Denotes Proposed Shoulder
Denotes Existing Bridge
0095-111-278
RW-201, C-501
0095-111-278
Dewberry Consultants, LLC - (703) 289-4796
RICE & Associates
Accumark, 3/18/16
or Obscuring of Roadway
Denotes Demolition of Pavement
ST'D. RW-3
RETAINING WALL
ROUTE 3 EB
ROUTE 3 WB
INSET A
MAT
CH
LIN
E - S
EE IN
SE
T
A
MAT
CH
LIN
E - S
EE
AB
OVE
3
3
CA
RL
D. SIL
VE
R
PA
RK
WA
Y
ROUTE 3
EB
ROUTE 3
WB
ROUTE 3
BL
ROUTE 3 BL
MA
TC
H
LIN
E -
ST
A. 36+5
0 -
SE
E
SH
EE
T 4
19
20
21
PC S
TA 19
+72.2
5
22
23
24
25
26
27
28 2
9 30
31
32
33
34
35
36
PT STA 30+91.47
308
309
310
PC S
TA 308+6
7.5
2
PT STA 310+45.99
28
E
E
E
E
F
E
E
TT
EB
WM
#SE9
OH
Sig
n #880023
OH Sign #880015
OH Sign
OH Sign
S#100
PVC
PVC
PVC
#101
PVC
#102PVC
S
S
SNOW
#223
#222
18" RCP
In. Pl. M
etal
Grate
In. Pl. 2
4"
CM
P
Inv. In=
239.6
0
Inv. O
ut= 2
39.17
Conc. E
nd
wall
Top=
242.0
0
Rim
= 241.48
24" C
MP
L= 212.76')
(R= 497.96'
L= 358.19')
(R= 497.96'
(S 03°16'3
7" E 13
8.0
0')
(S 03°16'3
7" E 217.2
4')
(S 86°43'23" W 120.00')
10.33')
(N 86°43'23" E
10.03')
(S 86°43'23" W
(S 5
9°35'59" W 119.
07')
47.13')
(S 45°16'29" W
(S 33°42'16"
W 332.70')
(S 5
6°17'44" E 150.81')
(N 03°16'3
7"
W 316.3
6')
(S 45°16'29" W
63.60')
(S 03°16'3
7" E 290.2
6')
DB 300 P
G 361
Ex. 15'
Vir
ginia Power Es
mt.
DB 300 P
G 361
Ex. 15' Virginia Pow
er E
smt.
DB 341 P
G 190
Gas Pipeline E
smt.
Ex. 15' Colum
bia Gas of Virginia
DB 341 P
G 190
Gas Pipeline
Esmt.
Ex. 15' Columbia Gas of Virginia
PB 11 P
G 17
Ex. 20' Sanitary S
ewer E
smt.
DB 284
PG 403
Ex. 15' V
irginia P
ower Esm
t.
PB 9 P
G 10
2
Ex. 24' In
gress/
Egress Es
mt.
PB 9 P
G 119
Ex. 24' In
gress/
Egress Es
mt.
Ir Ir
RW
Mon.
Ir
Ir
Ir
N 56°06'58" W
S 03°0
5'3
4" E
S 03°0
5'3
4" E
N 09°2
7'3
0" E
CENTRAL PARK 1200, LLCInst.# 050001909
PB 8 PG 69-70
1.002 AC.GPIN# 7769-72-0750
Inst.# 150003102
PB 11 PG 16-17
1.525 AC.GPIN# 7769-72-3980
OWNER ONE, LLC
MACH II MCB SILVER PORTFOLIO
CE
NT
RA
L P
AR
K 12
09, LLC
Inst.# 0500019
26
PB 9 P
G 118-119
1.093
AC.
GPIN
# 7769-7
2-2
713
CE
NT
RA
L P
AR
K 12
09, LLC
Inst.# 0500019
26
PB 9 P
G 118-119
1.093
AC.
GPIN
# 7769-7
2-2
713
Denotes Construction Limits in Cuts
Denotes Construction Limits in Fills
VA.
STATE
ROUTE PROJECT
REVISEDSTATE
STATE
ROUTE PROJECTSHEET NO.
PROJECT SHEET NO.
PROJECT MANAGER
SURVEYED BY, DATE
DESIGN BY
SUBSURFACE UTILITY BY, DATE
VA.
0
SCALE
50' 100'
3
Denotes Full Depth Pavement
Denotes Existing Pavement
Denotes Milling and Overlay/Build-Up
Denotes Proposed Shoulder
Denotes Existing Bridge
0095-111-278
RW-201, C-501
0095-111-278
Dewberry Consultants, LLC - (703) 289-4796
RICE & Associates
Accumark, 3/18/16
or Obscuring of Roadway
Denotes Demolition of Pavement
MA
TC
H
LIN
E -
ST
A. 36+5
0 -
SE
E
SH
EE
T 3
ROUTE 3 EB
ROUTE 3 WB
ROUTE 3 BL
MA
TC
H
LIN
E -
ST
A. 51+50 -
SE
E
SH
EE
T 5
RA
MP
B
SLIP R
AMP B
LO
OP
B
I-95 S
B
I-95
NB
I-95 S
B
BL
I-95
NB
BL
RA
MP
B
BL
LO
OP
B
B L
SLIP
RA
MP
B
BL
MAT
CH LIN
E - S
TA. 2
19+50 - S
EE SHEET 7
MATCH LINE - STA. 99+00 - SEE SHEET 7
MATCH LINE - STA. 93+00 - SEE SHEET 6
4
4
LOOP C
ST'D. RW-3
RETAINING WALL
I-95
I-95
94
95
96
97
98
99
POB STA 94+00.00
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
10
11
12
13
14
15
16
PC S
TA 10
+00.0
0
PC
C S
TA 11+2
0.3
7
PCC STA
13+38.1
8
PCC STA 15+89.82
300
301
302
303
304
305
306
307
POB STA 3
00+00.00
PC S
TA 3
03+75.72
PT
ST
A 306+5
4.7
0
93
94
95
96
97
98
99
220
221
222
223
224
225
PT STA 223+53.23
POE STA 225+48.28
29
T
E TC
T
E
T
T
T
TC
F
F
F
F
WM
TT
Na
EB
EBW
W
G
G
Storm Pumpstation
Storm Pumpstation
EB
DVP #
XD77
(SIG)
FO1
OH Sign
F
(SIG)
(SIG)
(SIG)
(CO
X)
(COX)
PVC
PV
C
#113
#114
Ductile Iron
Ductile IronDuctile Iron
6"
D. I.
S
S
PILES
SNOW
SNOW
SNOW
SN
OW
D
D
D
D
D
#212
#213
#211
#210
#20860" RCP
60" RCP
Unknown Siz
e
&
Type
#236
A
B
#209
#216 #217
36" R
CP
36" RCP
18" R
CP
#218#219
30" R
CP
30" R
CP
Unknown Size & Typ
e
(N 04°2
0'4
3"
W 222.17')
(N 04°2
0'4
3"
W 228.18')
(N 86°35'39" E 64.51')(N 86°35'39" E 93.30')
(N 04°2
0'4
3"
W 214.4
1')
L= 75.93')
(R= 310.00'
L= 2
10.82')
(R= 310.00'
(S 87°57'54" W 178.75')
(N 02°0
2'0
6"
W 112.7
1')
(N 87°57'54" E 194.01')
(S 01°54'0
3" E 254.4
7')
(N 01°55'15"
W 251.80')
(N 08°19'0
3" E 679.7
6')
(S 00°3
3'15" E 864.4
3')
(N 74°51'01" W 151.97')
(S 02°0
8'4
9" E
48.0
0')
(N 10°4
3'5
1" W 10
1.16')
(S 02°15'2
7" E 324.6
4')
DB 576 PG 321
Ex. 12' C&P Tele. Esmt.
PB 10 P
G 95
Ex. 20' Private Stor
m
Drain
age Es
mt.
RW
Mon.
Ir
Ir
RW
Mon.R
W
Mon.
Ramseur Street
Existing VD
OT R/
W per Plans 0095-0
89-101
N 04°19'18"
W
N 04°19'18"
W
S 00°4
0'2
3" E
S 01°37'5
8" E
S 02°14'0
6" E
N 06°0
2'5
8"
W
N 87°45'54" E
S 87°45'54" W
per Plans 0095-088-109
Existing VDOT R/W
(Approx. Location)
DB 18
5 P
G 15
3Ex. 40'
Access Es
mt.
DB 19
3
PG 15
5
Ex. 20'
Constr
uction Es
mt.
RW
Mon.
Ir
Limite
d Access Line per
Plans
0095-089-10
1
Limited Access Line per Plans 0095-089-101
End Limited Access
Existing VDOT R/W per Plans 0095-089-101
Suspected Location Limited Access Line per Plans 0095-089-101 (See Note #3)
(See Note #3)
End Limited Access
T
T
T
T
AREC 14, LLCInst.# 110002074
PB 10 PG 94-95
2.703 AC.
GPIN# 7769-92-3876
AREC 14, LLC,Inst.# 110002074
GPIN# 7769-93-3025
0.428 AC. (Measured)
AREC 14, LLCInst.# 110002074
PB 10 PG 94-95
2.703 AC.
GPIN# 7769-92-3876
AREC 14, LLC,Inst.# 110002074
GPIN# 7769-93-3025
0.428 AC. (Measured)
ESS PRISA III OWNER, LLCInst.# 050002951
3.00 AC.
GPIN# 7769-93-5150
PB 10 PG 94-95
ESS PRISA III OWNER LLC,Inst.# 050002951
3.546 AC.
GPIN# 7769-93-7122
DB 188 PG 443 (Plat)
DB 193 PG 153 (Plat)
Inst.# 080001550
LJS GATEWAY STORE, LLC
1.187 AC.
GPIN# 7769-92-7057
PB 10 PG 51
Inst.# 080001430
PROPERTIES II LLC
WALLACE
PB 10 PG 43-44
1.489 AC.
GPIN# 7769-92-6214
FIVE HANDS, LLCInst.# 150000915
Denotes Construction Limits in Cuts
Denotes Construction Limits in Fills
VA.
STATE
ROUTE PROJECT
REVISEDSTATE
STATE
ROUTE PROJECTSHEET NO.
PROJECT SHEET NO.
PROJECT MANAGER
SURVEYED BY, DATE
DESIGN BY
SUBSURFACE UTILITY BY, DATE
VA.
0
SCALE
50' 100'
3
Denotes Full Depth Pavement
Denotes Existing Pavement
Denotes Milling and Overlay/Build-Up
Denotes Proposed Shoulder
Denotes Existing Bridge
0095-111-278
RW-201, C-501
0095-111-278
Dewberry Consultants, LLC - (703) 289-4796
RICE & Associates
Accumark, 3/18/16
or Obscuring of Roadway
Denotes Demolition of Pavement
67
PT
ST
A 67+6
9.17
MA
TC
H
LIN
E -
ST
A. 51+50 -
SE
E
SH
EE
T 4
MA
TC
H
LIN
E -
SE
E
AB
OVE
INSET A
ROUTE 3 BL
5
5
MATCH
LINE - S
TA. 15+5
0 - S
EE SHEET
8
ROUTE 3 BL
ROUTE 3 EB
ROUTE 3 WB
RA
MP
AR
AM
P
A
BL
MA
TC
H
LIN
E -
SE
E IN
SE
T
A
MATCH LINE - SEE SHEET 6
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
PC S
TA 61+53.7
1
11
12
13
14
15
POB STA 10+00.00
PC STA 10+59.93
PT STA 11+06.83
99
PC STA
12+07.3
8
PRC STA 13
+16.05
30
#238
24" R
CP
36" R
CP
24" RCP
#237
#240
#239
#242
#241
18"
RCP
36" R
CP
D
In. Pl. 3
6" RCP
In. Pl. F
ES
Inv. = 19
3. 09
In. Pl. S
SMH Rim= 2
09. 78 Inv.
In= 189. 66 (3
6" RCP)
Inv. In= 189. 90 (3
0" HDP)
Inv. Out
= 189. 5
4
In. Pl. 3
6" R
CP
In. Pl. 3
6"
RCP
In. Pl. 30
" Plastic Pipe
(S 88°02'34" W 269.97')
(S 04°3
0'4
8" E 338.6
5')
(N 04°3
0'4
8"
W 243.9
3')
(N 33°49'55" E 94.63')
DB 197 P
G 370
Ex. 50' Vepco / C
&P Telep
hone
Esmt.
RW Mon.
RW Mon.
RW
Mon.
RW
Mon.
Ir
PB 10 P
G 110-113
Variable Width R/W
Gate
way
Boulevar
d
Existing VD
OT Li
mited Access R/
W per Plans 0095-0
89-101
Existing VD
OT R/
W per Plans 0095-0
89-101
S 88°04'14" W
S 04°2
9'2
3" E
1.014 AC.
GPIN# 7769-92-2021
PB 10 PG 110-113
KAL, LLCInst.# 120002610
GPIN# 7769-92-3095
ENELA CORNER, LLC
HOME DEPOT U.S.A. INC
19.729 AC.
GPIN# 7769-91-0210
DB 331 PG 814
PB 10 PG 110
HOME DEPOT U.S.A. INC
19.729 AC.
GPIN# 7769-91-0210
DB 331 PG 814
PB 10 PG 110
Denotes Construction Limits in Cuts
Denotes Construction Limits in Fills
VA.
STATE
ROUTE PROJECT
REVISEDSTATE
STATE
ROUTE PROJECTSHEET NO.
PROJECT SHEET NO.
PROJECT MANAGER
SURVEYED BY, DATE
DESIGN BY
SUBSURFACE UTILITY BY, DATE
VA.
0
SCALE
50' 100'
3
Denotes Full Depth Pavement
Denotes Existing Pavement
Denotes Milling and Overlay/Build-Up
Denotes Proposed Shoulder
Denotes Existing Bridge
0095-111-278
RW-201, C-501
0095-111-278
Dewberry Consultants, LLC - (703) 289-4796
RICE & Associates
Accumark, 3/18/16
or Obscuring of Roadway
Denotes Demolition of Pavement
MATCH LINE - STA. 93+00 - SEE SHEET 4
MATCH LINE - SEE SHEET 5I-95 S
B
I-95
NB
I-95
NB
BL
LOOP D
RAM
P D
6
6
88
89
90
91
92
93
POB STA 87+50.00
31
54" R
CP
36" R
CP
48" R
CP
#225
18" R
CP
#226
#224
#227
#221
DB 286 PG 505
Ex. 15' Virginia Power Esmt.
(N 45°00'0
0"
W 832.13')
L= 304.28')
(R= 1145.67'
(S 45°00'0
0" E 15
8.2
5')
11.44')
(S 52°11'14" W
DB 286 P
G 699
Ex. 7' GTE
Esmt.
PB 8 P
G 31
Ex. 20'
Waterline Esmt.
PB 8 PG 5
Ex. 20' Waterline Esmt.
PB 8 PG 5
Ex. 20' Storm Sewer Esmt.
DB 287 PG 671
Ex. 15' Virginia Power Esmt.
PB 8 P
G 5
Ex. 20' Utility E
smt.
(N 45°00'0
0"
W 268.12')
(S 52°11'14" W 560.22')
L= 211.00')
(R= 953.62'
(S 45°00'0
0" E 917.19')
(S 14°55'04" W 235.00')
L= 377.02')
(R= 953.62'
L= 106.71')
(R= 953.62'
85.5
9')
(S 68°15'2
2" E
39.96')
(N 45°00'0
0"
W
40.03')
(S 45°05'0
6" E
(N 45°01'38" E 109.92')
47.98')
(S 44°5
5'4
6" E
(N 45°04'14" E 216.93')
(N 45°00'00" E 145.97')
PB 17 PG 148
Access Esmt.
Private Stormwater Management
PB 17 PG 148
Management Esmt.
Ex. Private Stormwater
PB 17 P
G 14
8
Management
Access Esmt.
Ex. 24' Private Storm
water
PB 17 PG 148
Management Access Esmt.
Ex. 24' Private Stormwater
PB 17 PG 148
Management Esmt.
Ex. Private Stormwater
PB 17 PG 148
Management Esmt.
Ex. Private Stormwater
PB 17 PG 148
Ex. 15' Waterline Esmt.
PB 17 P
G 148
Ex. 2
0' Private S
anitary Sew
er Esmt.
PB 17 PG 148
Ex. 10' Private Sanitary Sewer Esmt.
PB 8 P
G 5
Ex. 15'
Waterline Esmt.
PB 17 P
G 14
8
Ex. 15'
Waterline Esmt.
RW
Mon.
Ir
Ir
Ir
Ir
Existing VDOT Limited Access R/W per Plans 0095-089-101
Existing VD
OT Limited Access R
/W per P
lans 0095-089-101
N 45°12'24" E
85.6
1')
(N 68°2
0'3
4"
W
S 44°49'14" E
S 44°49'14" E
N 44°49'14"
W
E
SANDPIPER FREDERICKSBURG LLCInst.# 130003228
PB 17 PG 148-149
1.686 AC.
GPIN# 7769-83-3867
LOWE'S HOME CENTERS, INC.
DB 282 PG 261
PB 8 PG 5
15.4659 AC.
GPIN# 7769-73-7735
1.096 AC.GPIN# 7769-73-5163
PB 10 PG 159-161
PB 11 PG 16-17
PB 10 P
G 15
9
GPIN
# 7769-6
2-9
857
CAR
L D. SIL
VE
R, EST
ATE
PB 8 P
G 27-3
1
2.3
2
AC. (Per GIS)
VA.
STATE
ROUTE PROJECT
REVISEDSTATE
STATE
ROUTE PROJECTSHEET NO.
PROJECT SHEET NO.
PROJECT MANAGER
SURVEYED BY, DATE
DESIGN BY
SUBSURFACE UTILITY BY, DATE
VA.
0
SCALE
50' 100'
3
0095-111-278
RW-201, C-501
0095-111-278
Dewberry Consultants, LLC - (703) 289-4796
RICE & Associates
Accumark, 3/18/16
MAT
CH
LIN
E - S
TA. 219
+50 - S
EE
SH
EE
T 4
MA
TC
H
LIN
E - S
TA. 9
9+5
0 - S
EE
SH
EE
T 4
MA
TC
H
LIN
E - S
TA. 112
+50 - S
EE
SH
EE
T 9
RAMP B
RAMP B BL
I-95 SBI-95 SB BL
7
7
MATCH LINE - SEE SHEET 8
Denotes Full Depth Pavement
Denotes Existing Pavement
Denotes Milling and Overlay/Build-Up
Denotes Proposed Shoulder
Denotes Existing BridgeDenotes Construction Limits in Fills
Denotes Construction Limits in Cuts
or Obscuring of Roadway
Denotes Demolition of Pavement
I-95
100
101
102
103
104
105
106
107
108
109
110
111
112
PO
B
ST
A 300+0
0.0
0
204
205
206207
208
209
210
211
212
213
214
215
216
217
218
219
PC STA 204+91.25
PT STA 211+57.63
PC STA 217+55.63
32
F
#235
54" R
CP
48" R
CP
42" R
CP
36" RCP
#234
#246
#245
#243
#258
#233
#231
#232
#259
(N 02°
02'06" W 111.08')
L= 32
5.03')
(R= 9
54.93'
(N 2
3°05'03
" W 66
4.25')
RW
Mon.
RW
Mon.
Existing
VDOT Li
mite
d Access R/
W per
Plans 0
095-08
9-101
HYLT
ON
VE
NT
UR
E
LLC,
Inst.# 060000272
75.5
3247
AC. (T
otal)
66.13
611 A
C.
GPIN
# 7769-9
4-7
825
HYLT
ON
VE
NT
UR
E
LLC,
Inst.# 060000272
75.5
3247
AC. (T
otal)
66.13
611 A
C.
GPIN
# 7769-9
4-7
825
HYLTON VENTURE LLC,Inst.# 060000272
GPIN# 7769-94-7825
75.53247 AC. (Total)
66.13611 AC.
Denotes Construction Limits in Cuts
Denotes Construction Limits in Fills
VA.
STATE
ROUTE PROJECT
REVISEDSTATE
STATE
ROUTE PROJECTSHEET NO.
PROJECT SHEET NO.
PROJECT MANAGER
SURVEYED BY, DATE
DESIGN BY
SUBSURFACE UTILITY BY, DATE
VA.
0
SCALE
50' 100'
3
Denotes Full Depth Pavement
Denotes Existing Pavement
Denotes Milling and Overlay/Build-Up
Denotes Proposed Shoulder
Denotes Existing Bridge
0095-111-278
RW-201, C-501
0095-111-278
Dewberry Consultants, LLC - (703) 289-4796
RICE & Associates
Accumark, 3/18/16
or Obscuring of Roadway
Denotes Demolition of Pavement
I-95 NBI-95 NB BL
RAM
P A R
AMP A
BL
LOOP A
MATCH LINE - SEE SHEET 7
SE
E
SH
EE
T 4
MA
TC
H
LIN
E - S
TA. 9
9+0
0 -
MA
TC
H
LIN
E -
ST
A. 112
+00 -
SE
E
SH
EE
T 9
MATCH LIN
E - S
TA. 15
+50 - S
EE S
HEET 5
8
8
16
17
18
19
20
21
22
23
24
25 26
PT ST
A 16
+89.81
PC STA 19+68.61
PT STA 25+80.46
99
100
101
102
103
104
105
106
107
108
109
110
111
112
33
F
55.9
9')
(N 76°19'3
2"
W
99.8
6')
(N 76°4
3'4
1" W
54.5
5')
(S 89°11'28"
W
32.6
2')
(S 85°4
4'4
4"
W
L= 717.90'')
(R= 5842.58'
45.0
1')
(S 88°2
9'5
0" E
57.10')
(N 84°5
5'3
4" E
77.6
0')
(N 87°5
6'4
3" E
RW Pin
RW Pin
RW Pin
RW Pin
RW Pin
RW Pin
RW Pin
Varia
ble
Width R/
WCowan Boule
vard
Existing VDOT Lim
ited Access R
/W per Plans
0095-089-10
1
F
E
E
F
E
(SIG)
(SIG)
OH
Sig
n
42" R
CP
42" R
CP
12" Iron
15" RCP
15" RCP
#249
#248
#247
#253#254
#252#250
#2609
(S 14°55'04" W 235.00') (S 14°55'04" W
50.25')
(N 75°0
4'5
6"
W 10
0.0
0')
(S 75°0
4'5
6" E 10
0.0
0')
15.00')
(S 14°55'04" W
100.0
0')
(N 75°0
4'5
6"
W
79.56')
(S 14°55'04" W
(N 45°00'00" E 334.39')
(S 14°55'04" W 561.29') L= 5.47')
(R= 5442.71'
(N 06°27'31"
E 154.07')
(N 20°56'17" E 149.75')
(N 15°04'22" E 204.07')
(N 11°06'17" E 250.11')
(N 13°51'19" E 700.22')
PB 11 PG 30
Ex. 20' Ingress/Egress Esmt.
RW
Mon.
RW
Mon.
RW
Mon.
RW
Mon.
RW
Mon.
IrIr
Existing VDOT Limited
Access R/W per Pla
ns 0095-088-109
Existing VDOT Limited Access R/W per Plans 0095-089-101 Existing VDOT Limited Access R/W per Plans 0095-088-109
Existing VDOT Limited Access R/W per Plans 0095-089-101
S 74°5
4'0
8" E
S 74°5
4'0
8" E
HYLTON VENTURE LLC,
Inst.# 06000027
2
GPIN# 7769-94-
782575.5324
7 AC. (Total)66.13611
AC.
HYLTON VENTURE LLC,Inst.# 060000272
GPIN# 7769-94-7825
75.53247 AC. (Total)
66.13611 AC.
Denotes Construction Limits in Cuts
Denotes Construction Limits in Fills
VA.
STATE
ROUTE PROJECT
REVISEDSTATE
STATE
ROUTE PROJECTSHEET NO.
PROJECT SHEET NO.
PROJECT MANAGER
SURVEYED BY, DATE
DESIGN BY
SUBSURFACE UTILITY BY, DATE
VA.
0
SCALE
50' 100'
3
Denotes Full Depth Pavement
Denotes Existing Pavement
Denotes Milling and Overlay/Build-Up
Denotes Proposed Shoulder
Denotes Existing Bridge
0095-111-278
RW-201, C-501
0095-111-278
Dewberry Consultants, LLC - (703) 289-4796
RICE & Associates
Accumark, 3/18/16
or Obscuring of Roadway
Denotes Demolition of Pavement
PIER PROTECTIO
N SYSTEM REQ'D
41
42
43
44
45
46
47
126 12
7 128 12
9
130
131
132
133
I-95
113
114
115
116
117
118
119
120
121
122
PC STA 122+18.22
35
36 37 38 39 40
PC STA 34+93.60
27
28
29
30
31
32
33
34
35
112
113
114
115
116
117
118
119
120
121
122
123
124 125 12
6
PC STA 121+37.70
201
202
203
204
POB STA 200+00.00
I-95 NBI-95 NB BL
MA
TC
H
LIN
E - S
TA. 112
+50 - S
EE
SH
EE
T 8
MA
TC
H
LIN
E - S
TA. 12
6+0
0 - S
EE
AB
OVE
MA
TC
H
LIN
E - S
TA. 12
6+0
0 - S
EE
BE
LO
W
ST
A. 112
+50 - S
EE
SH
EE
T 7
MA
TC
H
LIN
E -
9
9
I-95 SB
I-95 SB BL
I-95 NB
I-95 NB BL
ULTIMATE NB CD-ROAD BL
ULTIMATE NB CD-ROAD BLULTIMATE NB CD-ROAD
ULTIMATE NB CD-ROAD
MAT
CH
LIN
E - S
TA. 13
3+0
0 - S
EE
SH
EE
T 10
And Associated Improvements
Noise Barrier (Option 1)
34
F
F
E
E
#461
TC
Box (2)
F
#W
B74
(SIG)
(SIG)
(SIG)
Fall H
ill Avenue - R
te 639
Fall H
ill Avenue - R
te 639
(U
nder Constr
uctio
n)
Approxim
ate Locatio
n of New
Brid
ge
Activ
e Constr
uctio
n
Area
under constr
uctio
n in the sa
me general lo
catio
n.
This Brid
ge has been removed, a new brid
ge is currently
(S 25°3
2'28" E 147
.20')
(R = 280.00')
(A = 231.86')
LR070001847
Ex. 15' Public Waterline Easement DB 319 Pg. 185
Ex. 15' Storm Sewer Easement
(S 09°32'28" E 314.30')(S 07°57'28" E 63.90')
(N 84°0
6'2
8"
W 839.5
8')
N84°0
5'5
7"W
(S 84°0
6'2
8" E 86.5
8') R
W
Pin
(S 78°3
0'3
3"
W 10
1.35')
(N 78°3
0'3
3" E 10
1.35')
DB 300 Pg. 367
Ex. 20'
Utility Ease
ment
(N 06°10'49" W 240.1
9')
(S 06°10'49" E 240.19')
N78°4
1'13
"E
(S 85°0
5'0
0"
W 13
3.15')
(N 78°4
0'4
2" E 13
3.18')
(N 10°55'34" W 383.52')
(N 64°3
0'0
0" E 16
4.8
0')
(N 04°35'00" W 192.60')
PB 395 Pg 109Ex. VEPCO EasementApprox. Location
Inst. 150001983Ex. VEPCO Easement
Proj. U
000-111-2
33, R
201, C
501
Ex. T
emp. C
onst. E
smt.
BE
GIN
L/
A LIN
E
Existing VDOT Limited Access R/W per Plans 0095-089-101
ir
(N 10°55'34" W 680.89')
PB 8 Pg. 23
Ex. 10' VEP
CO Easement
PB 8 Pg. 23Ex. 10' Utility Easement
(62.85')
Inst. #16
0000009
For VEP
CO
Ex.
VD
OT
Utility E
smt.
Begin L/
A Line
Ex.
R/
W
RW
Mon.
E
10
WEYMOUTH, L. L. C.Inst.# 010001353
0. 715 AC.
TAX MAP# 7769-98-1731
FRED II LIMITED PARTNERSHIPInst.# 030001034
1. 037 AC.
GPIN# 7769-98-1474
FRED II LIMITED PARTNERSHIPInst.# 030001034
6. 000 AC.
GPIN# 7769-98-4384
THE PRESERVE AT SMITH RUN
HOMEOWNERS ASSOCIATIONInst.# 120000712
0. 955 AC.
TAX MAP# 7769-98-2024
FRED II LIMITED PARTNERSHIPInst.# 030001034
1. 037 AC.
GPIN# 7769-98-1474
F
(SIG)
F
(SIG)
Ductile Ir
on
#116
Ductile Ir
on
Ductile Ir
on
Ductile Ir
on
PVC
#117
6" D. I.
#118
PVC
S
S
S
S
S
#255
#256
6' x 8' B
ox Culvert
Preserve Lane
D
D
D
Inv.
Out
= 238. 3
5'
In Pl. 15"
Conc. Pip
e
Rim
= 245. 8
8'
In Pl. C
DI
Inv.
Out
= 236. 8
0'
In Pl. 15"
Conc. Pip
e
Inv. In =
237. 0
9'
Rim
= 244. 0
7'
In Pl. C
DI
Inv.
Out
= 206. 0
8'
In Pl. 4
8"
Conc. Pip
e
In Pl. E
nd
wall
In Pl. 4
8"
Conc. Pip
e
Inv. In =
212. 0
0'
In Pl. H
ead
wall
66.8
2')
(N 74°2
9'0
3" E
15.6
2')
(N 86°2
8'0
0" E
24.27')
(N 05°09'39" W
86.52')
(S 4
5°27'06" E
100.6
3')
(S 83°5
7'2
5" E
32.3
2')
(N 73°2
9'5
3" E
L= 82.26')
(R= 5842.58'
(N 09°08'22" E 206.18')
RW
Mon.
RW
Mon.
RW
Mon.
RW Pin
Existing VDOT Limited Access R/W per Plans 0095-088-109
Existing VDOT Limited Access R/W per Plans 0095-089-101N 74°3
0'2
4" E
(S 86°0
7'2
5" E 208.6
9')
LR070001120
Ex. Per
manent
Preservation Ease
ment
DB 293
Pg. 10
3
Ex. 20' San. Sewer Ease
ment
S86°0
6'5
3"E
(S 25°14'20" E 263.66')
(S 04°16'29" E 159.25')
S05°12'05"W
(S 05°11'33" W 218.08')
(R = 280.00')
(A = 196.76')
(R = 5842.58')
(A = 228.73')THE PRESERVE AT SMITH RUNHOMEOWNERS ASSOCIATIONInst.# 1200007122. 436 AC.
TAX MAP# 7769-96-4560
THE PRESERVE AT SMITH RUN
HOMEOWNERS ASSOCIATION
Inst.# 120000712
2. 436 AC.
TAX MAP# 7769-96-4560
HYLTON VENTURE, LLC
Inst.# 060000272
GPIN# 7769-94-7825
75.53247 AC. (Total)
9.39636 AC.
Denotes Construction Limits in Cuts
Denotes Construction Limits in Fills
VA.
STATE
ROUTE PROJECT
REVISEDSTATE
STATE
ROUTE PROJECTSHEET NO.
PROJECT SHEET NO.
PROJECT MANAGER
SURVEYED BY, DATE
DESIGN BY
SUBSURFACE UTILITY BY, DATE
VA.
0
SCALE
50' 100'
3
Denotes Full Depth Pavement
Denotes Existing Pavement
Denotes Milling and Overlay/Build-Up
Denotes Proposed Shoulder
Denotes Existing Bridge
0095-111-278
RW-201, C-501
0095-111-278
Dewberry Consultants, LLC - (703) 289-4796
RICE & Associates
Accumark, 3/18/16
or Obscuring of Roadway
Denotes Demolition of Pavement
will determine wall size and location.
Final Plan Design and Noise Analysis
Sound Wall location is preliminary.
Ultimate CD Road Ultimate CD Road
62
63
64
65
66
67
68
69
70
71
72
73
74
75
POE STA 75+45.66
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
MA
TC
H
LIN
E -
ST
A. 14
7+0
0 -
SE
E
BE
LO
W
MA
TC
H
LIN
E -
ST
A. 14
7+0
0 -
SE
E
AB
OV
E
10
10
I-95 NBI-95 NB BL
I-95 NBI-95 NB BL
ULTIMATE NB CD-ROAD
ULTIMATE NB CD-ROAD BL
ULTIMATE NB CD-ROADULTIMATE NB CD-ROAD BL
MAT
CH
LIN
E -
ST
A. 13
3+0
0 -
SE
E
SH
EE
T 9
And Associated Improvements
Noise Barrier (Option 1)
And Associated Improvements
Noise Barrier (Option 1)
End Proposed Noise Barrier (Option 1)
48
49
50
51
52
53
54
55
56
57
58
59
60
61
PCC STA 47+45.32
PT STA 59+56.78
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
PT STA 146+72.86
35
Response to Request for Proposals
I-95 SAFETY IMPROVEMENTS AT ROUTE 3City of Fredericksburg, Virginia
State Project No.: 0095-111-278Federal Project No.: OC-095-2(535)Contract ID Nmber: C00107715DB91
PRICE PROPOSAL
Submit ted by:
in ASSociAtion With:
ORIGINAL
4.0.1.2 - Price Proposal Checklist
4.0.1.2 - Price Proposal Checklist
1 of 1
ATTACHMENT 4.0.1.2
DESIGN-BUILD PRICE PROPOSAL CHECKLIST
Addendum No. 3 Project Name: I-95 Safety Improvements at Route 3
Contract ID Number: C00107715DB91
Contents of Price Proposal:
Cost Breakdown Summary in whole numbers and the Proposal Price, in both numbers and words which is the sum (Total Price) for the Base Scope and Option 1 (Attachment 4.3.1)
Price Adjustment Information and Forms for Fuel and Asphalt for the Base Scope and Option 1, including identification of pay items and associated quantities eligible for adjustment (Part 3, Section 6.3, and Attachments 6.3)
Proposal Guaranty (C-24) required by Section 102.07 of Part 5, Division I Amendments to the Standard Specifications for the Base Scope and Option 1
Sworn Statement Forms (C-104, C-105, Attachments 4.3.4(a) and 4.3.4(b))
CD-ROM containing the entire Price Proposal in a single cohesiveAdobe PDF file
X
X
X
X
X
4.3.1 - Proposal Price
4.3.1 - Proposal Price
4.3.2 - Adjustment to Asphalt & Fuel Prices
4.3.2 - Adjustment to Asphalt & Fuel Prices
4.3.3 - Proposal Guaranty
4.3.3 - Proposal Guaranty
4.3.4 - Sworn Statem
ent Forms
4.3.4 - Sworn Statement Forms