r . garoby for

20
SPL R. Garoby for S. Atieh, I. Aviles Santillana, G. Arnau Izquierdo, R. Bonomi, S. Calatroni, O. Capatina, J. Chambrillon, F. Gerigk, M. Guinchard, T. Junginger, M. Malabaila, L. Marques Antunes Ferreira, S. Mikulas, V. Parma, F. Pillon, T. Renaglia, K. Schirm, T. Tardy, M. Therasse, A. Vacca, N. Valverde Alonso, A. Vande Craen SPL R&D AT CERN

Upload: oren

Post on 23-Feb-2016

47 views

Category:

Documents


0 download

DESCRIPTION

SPL R&D at CERN. R . Garoby for S . Atieh, I. Aviles Santillana, G. Arnau Izquierdo, R. Bonomi, S. Calatroni, O. Capatina, J . Chambrillon, F. Gerigk, M . Guinchard, T . Junginger, M. Malabaila, L. Marques Antunes Ferreira, S. Mikulas, - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: R .  Garoby for

SPL

R. Garoby for

S. Atieh, I. Aviles Santillana, G. Arnau Izquierdo, R. Bonomi, S. Calatroni, O. Capatina, J. Chambrillon, F. Gerigk, M. Guinchard,

T. Junginger, M. Malabaila, L. Marques Antunes Ferreira, S. Mikulas,V. Parma, F. Pillon, T. Renaglia, K. Schirm,

T. Tardy, M. Therasse, A. Vacca, N. Valverde Alonso, A. Vande Craen

SPL R&D AT CERN

Page 2: R .  Garoby for

SPL

R.G. 2 SPL R&D 2013

• Preserve the possibility of new injectors in the future (HE-LHC…)

PSB

SPS

Linac4

LP-SPL

PS

LHC

160 MeV

1.4 GeV4 GeV

26 GeV50 GeV

450 GeV

7 TeV

Linac250 MeV

Proton flux / Beam power

PS2

Present Typical Future

1978

1975

1959

2008

LP-SPL: Low Power-Superconducting Proton Linac PS2: High Energy PS (~ 5 to 50 GeV – 0.3 Hz)

PS2

SPL

LINAC4

SPS

PS

CERN motivation for the SPL R&D(1/3)

Page 3: R .  Garoby for

SPL

R.G. 3 SPL R&D 2013

• Options for neutrinos physics and/or Radioactive Ion Beam Ex.: tentative layout of neutrino factory at CERN

CERN motivation for the SPL R&D(2/3)

Page 4: R .  Garoby for

SPL

R.G. 4 SPL R&D 2013

• Update of CERN competencies in superconducting RF

• Upgrade of CERN infrastructure for superconducting RF (SM18 clean room, High Power RF, High Pressure Water Rinsing facility, Diagnostics for SC RF, New e-beam welding machine, Electropolishing installation, etc.)

• Synergy with other applications at CERN (LHeC electron linac, LEP-3… ) as well as outside of CERN (ESS, ADS…)

CERN motivation for the SPL R&D(3/3)

Page 5: R .  Garoby for

SPL

R.G. 5 SPL R&D 2013

• SC-linac [160 MeV ® 5 GeV] with ejection at intermediate energy

• Medium beta cavities beta = 0.65• High beta cavities beta = 1

Length: ~500 m

Medium b cryomodule

High b cryomodules

Ejec

tion

20 x 3b=0.65 cavities

10 x 8b=1 cavities

13 x 8b=1 cavities

2.5

GeV

Debunchers

5 Ge

V –

4 M

W

High b cryomodules

From

Lina

c4

0 m0.16 GeV

129 m0.73 GeV

280 m2.5 GeV

505 m5 GeV

SPL

SPL block diagram

Page 6: R .  Garoby for

SPL

R.G. 6 SPL R&D 2013

• Medium beta cavities b = 0.65• Developed by IPN Orsay (Guillaume Olry et al.) to be tested at CEA

Saclay in Cryho-lab

• High beta cavities b = 1• Developed by CEA Saclay (Guillaume Devanz et al.) to be tested at CEA

Saclay in Cryho-lab

• Developed by CERN for tests at CERN (SM18) in Short cryo-module of 4 cavities

SPL developments for cavities

Page 7: R .  Garoby for

SPL

R.G. 7 SPL R&D 2013

• 4 Niobium cavities fabricated and delivered by RI

Niobium cavities from industry (RI)

Page 8: R .  Garoby for

SPL

R.G. 8 SPL R&D 2013

Niobium cavities at CERN

Tooling for EB welding of Nb cavity is fabricated.CAVITY FABRICATION AT CERN

REPAIR OF FIRST MONOCELLMaterial defects observed after

electro-polishing.Repaired with new e-beam welding

machine from outside (W#1 and W#3) and inside (W#2)

Half-cells and beam tubes fabricated by spinning.

RF measurements.

Page 9: R .  Garoby for

SPL

R.G. 9 SPL R&D 2013

New e-beam welding machine

Page 10: R .  Garoby for

SPL

R.G. 10 SPL R&D 2013

- Cathode and tooling manufacturing- Improve main pump flow control and compressed air connection - Allow crane direct acces to the electropolishing hut

- MONOCELL TESTS:- A second set of electropolishing sessions were done to bring the

total removed thickness to 200 microns.- It was possible to set different working temperatures and compare

them with the simulation data- Working at lower temperatures results in less pitting.- Cavity is currently undergoing RF test- Paper TUP047 bat SRF with all multiphysics simulation details

Temperature Total current inward / A

Simulation Real cavity10 °C 21 1815 °C 37 3625 °C 70 57

- 5 CELL ELECTROPOLISHING PREPARATION:Tooling for EP

Electro-Polishing (EP)

Page 11: R .  Garoby for

SPL

R.G. 11 SPL R&D 2013

Helium tank designed by CERN (Stainless steel). 5 items under fabrication by CEA (with SDMS).

Stainless Steel He tank (CEA)

Helium tank

Page 12: R .  Garoby for

SPL

R.G. 12 SPL R&D 2013

CEA test bench withtwo SPL cylindrical window couplers,

Double Walled Tubes and Test Box cavity

Test of RF couplers (CEA)

RF tests on couplers at CEA

Cylindricalwindow

Diskwindow

Development oftwo types of couplers

Page 13: R .  Garoby for

SPL

R.G. 13 SPL R&D 2013

Cell-by-cell tuning system with RF bead-pull and mechanical measurements.

Cavity tuner: measurement of cavity detuning versus mechanical deformation.

Tooling for test in vertical cryostat: fabricated and

available at CERN

Reception area in bdg.252

Tests systems and cavity reception area (Bdg. 252)

Page 14: R .  Garoby for

SPL

R.G. 14 SPL R&D 2013

Cavity

Helium tank

Inter-cavitysupport

Thermal shieldVacuum vessel

RF coupler

Thermal shield tie-rod

Cold-to-warmtransition

Magnetic shielding

Insulation vacuum relief plate

Cryogenic circuit burst disk

Gate valve

Two-phase pipe

Cavity tuner

Double-walledtube

He phase separator

Cryogenic lines port

Cryomodule

Assembly of supporting system

mock-up

Inner part of supporting system

mock-up

Page 15: R .  Garoby for

SPL

R.G. 15 SPL R&D 2013

Cryo-module Assembly toolingCNRS-IPNO

Blocs BétonsSystème de levage

Cadre de manutentionSupports de réglage Poutre principale

Vérins LHC

Page 16: R .  Garoby for

SPL

R.G. 16 SPL R&D 2013

1. Cryogenics– New cryogenic transfer line: commissioned December 2013– Modification of 2 Vertical Cryostats for 2K Operation: completed March 2013– Specifications of He distribution for Horizontal Cryostats (2K and 4.5 K operation) completed

2. SRF processing infrastructure– Main Clean Room Upgrade and Extension: to be finished in December 2013

– Ultra-Pure Water Station delivered and commissioned: October 2013– Rinsing Cabinet delivered: October 2013– Diagnostics

• 2nd sound measurement by OSTs: operational (more work required for interpretation…)• Temperature mapping system for SPL cavities: work in progress…

SM18 infrastructure upgrade

Page 17: R .  Garoby for

SPL

R.G. 17 SPL R&D 2013

Valve box

RFdistribution

Cryo line interface

Cryo-module

with support from program

SM18 Bunker Infrastructure

Page 18: R .  Garoby for

SPL

R.G. 18 SPL R&D 2013

• 1.5 MW klystron – delivery beginning 2014 • Klystron modulator – delivery beginning 2014• New Low Level RF at 704 MHz – by end of 2014

SM18 High Power RF upgrade (704 MHz)

Page 19: R .  Garoby for

SPL

R.G. 19 SPL R&D 2013

2014 2015

Preparation of components Assembly of CM

Master Schedule

Page 20: R .  Garoby for

SPL

R.G. 20 SPL R&D 2013

• Design and development of a new type of multi-cavity cryomodule,• Design and development of “cheap” high power couplers (8 built; 2

successfully tested today).• Extensive investment for superconducting cavities fabrication and test (e-

beam welding machine, ep bench, optical bench…)• 2 five-cell copper cavities, one bulk-niobium monocell produced,• 4 five-cell bulk Niobium manufactured by industry (RI),• One five-cell bulk Niobium in fabrication at CERN with an R&D approach,• Equipment for testing at high RF power (704 MHz) a string of 4 cavities

cooled at 2 K in SM18

A string of four SPL 704 MHz b =1 cavities will start being tested in a short cryo-module at the end of 2015.

Summary

Update of CERN competencies

in superconducting RF.