quick response manufacturing documentation · pdf file6.5 reexamine organizational policies to...

41
Quick Response Manufacturing Documentation Release 1.0.0 Abdelkrim BOUJRAF Sep 27, 2017

Upload: dodung

Post on 08-Mar-2018

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response ManufacturingDocumentation

Release 1.0.0

Abdelkrim BOUJRAF

Sep 27, 2017

Page 2: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92
Page 3: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Contents

1 4 core concepts 3

2 A bit of history 5

3 Wrong believes p9 7

4 The Manufacturing Critical-Path Time p12 9

5 Chapter II: Organizational structure of QRM: QRM Cells, Teamwork and Ownership p35 115.1 4 structural changes p48 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 115.2 How to ensure QRM Cells they aren’t unexpected bottlenecks and resulting in job delays? p54 . . . . 115.3 The metrics p60 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 125.4 Prerequisites p63 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 125.5 Process to setup a cell p66 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

6 Chapter III: Understanding and exploiting system dynamics 156.1 Magnifying effect of utilization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156.2 2 types of variability p83 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 166.3 How to reduce the MCT for jobs? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 166.4 QRM Principles p93 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 176.5 Reexamine organizational policies to support the batch size reduction (material management, sales,

accounting) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 176.6 QRM approach to transfer batching . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 176.7 System dynamics compared with MRP, EOQ and other traditional approaches p99 . . . . . . . . . . 176.8 Why companies mistakenly invest in warehouse instead of machines? p102 . . . . . . . . . . . . . . 18

7 Chapter IV: A unified strategy for the whole industry 197.1 Principles of quick response in office operations p105 . . . . . . . . . . . . . . . . . . . . . . . . . 197.2 How to identify an FTMS in the context of office operations p112 . . . . . . . . . . . . . . . . . . . 197.3 Who does the job? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 197.4 How to form effective Q-ROCs? p114 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207.5 Q-ROC design method p121 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207.6 Marketing argument p122 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207.7 Restructure your MPS to support QRM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207.8 POLCA - The shop flow material control strategy . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

8 Paired-Cell Loops of Cards 23

i

Page 4: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

9 Authorization 25

10 Dispatch list p134 27

11 Strict scheduling rules 29

12 Overlapping loops p138 31

13 Benefits realized with POLCA implementations 3313.1 Glossary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3313.2 Contents: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3413.3 Indices and tables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34

ii

Page 5: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

QRM (Quick Response Manufacturing) is a method that emphasizes the beneficial effect of reducing internal andexternal lead times.

This paper is a summary of the book “It’s About Time: The Competitive Advantage of Quick Response Manufactur-ing” by Rajan Suri. The sole aim of this paper is to summarise the finding within the book as training material for ourteams and customers.

Contact us: http://www.amia-systems.com for any inquiry.

Note: All readers should buy the book “It’s About Time” as those notes would be hard to digest in other circumstances.

Contents 1

Page 6: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

2 Contents

Page 7: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 1

4 core concepts

• The power of time

• Organization structure

• system dynamics

• enterprise-wide application

3

Page 8: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

4 Chapter 1. 4 core concepts

Page 9: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 2

A bit of history

21st century: increase demand for low-volume, high variety products with options configured for individual customersor even custom-engineered for each client.

Takt time and Kanban eliminates variability operations.

5

Page 10: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

6 Chapter 2. A bit of history

Page 11: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 3

Wrong believes p9

Everyone has to work harder => reduce the lead-time

In average, the touch time is 5% to 1% of the complete process => Reducing the costs ABC (Activity Based Costing)does not reduce the lead-time!

7

Page 12: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

8 Chapter 3. Wrong believes p9

Page 13: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 4

The Manufacturing Critical-Path Time p12

The MCT (Manufacturing Critical-Path Time)

• Collect data without being overboard by lots of data

• Pay attention to the calendar time: start with the creation of the order

– include order processing, materials planning, scheduling, manufacturing logistics and quantifies wastein system

p16 : MCT includes information such as flow delay, planning time, raw material stocks, suppliers lead-times, logisticstime

p18: VSM: “current state” map has lot of details and it could be hard to get insight on where big opportunities lies“future state” is not immediately clear where improvements have been made.

p24: Reducing MCT will increase the “greys areas” and increase the direct labor costs but reduce warehouse andindirect costs

p13: Make MCT reduction the main performance measure throughout your organization and also for your suppliers

9

Page 14: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

10 Chapter 4. The Manufacturing Critical-Path Time p12

Page 15: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 5

Chapter II: Organizational structure of QRM: QRM Cells, Teamwork andOwnership p35

• cost-based approach focuses on reducing the touch time

• The MCT is 100 when the touch time is 5!

4 structural changes p48

1. From functional to cellular

2. From specialized narrowly focused workers to a cross-trained workforce

3. From Top-Down control to team ownership

4. From efficiency/utilization to MCT reduction

FTMS (Focused Target Market Segment)

p50: A QRM Cell is a dedicated, collocated, multifunctional resources selected so that this set a complete sequence ofoperations for all jobs belonging to a specified FTMS. The set of resources include a team of cross-trained people thathas complete ownership of the cell’s operations. The primary goal of the QRM Cell is the reduction of the MCT

p51:

• The resources assigned to a QRM Cell are fully dedicated to that cell.

• The resources that form a QRM Cell must also be located in close proximity to each other in an area that isclearly demarcated as belonging to the cell

How to ensure QRM Cells they aren’t unexpected bottlenecks andresulting in job delays? p54

1. Teamwork

11

Page 16: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

2. Cross Training

3. Choice of metric

4. QRM Approach to capacity planning

The metrics p60

QRM Number =Base period MCT

Current period MCT* 100 (5.1)

For example: QRM Number for the base period =12 days

12= 100

QRM Number if a first improvement is made12 days

10= 120

QRM Number if a second improvement is made12 days

8= 150

Which metrics should you use?

• The Cell’s MCT

Note: QRM Number effectively measure the MCT reduction. Psychologically, the equation (5.1) increases as theMCT is redirected and motivate the teams

Note: QRM number increase faster when the gain is bigger. i.e. Gain = 2 days12 = 17% or 2 days

8 = 25%

Prerequisites p63

1. Define the start and stop conditions “when the clock starts ticking”

2. the clock starts when the team has full ownership of that time period

3. Choose carefully the unit depending if you want to reduce the lead-time for orders or lead-time to stock

Attention: p66: Lean manufacturing is not well suited to the then highly customized highly customized andlow-volume business

Data model

Useful for the dev of an application

• Two products families as the FTMS for a first cell.

12Chapter 5. Chapter II: Organizational structure of QRM: QRM Cells, Teamwork and Ownership p35

Page 17: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

Process to setup a cell p66

1. Select the product that requires similar process and are relatively self contained and use the same collections ofresources

2. Setup an implementation team whose goal is to design the cell and implement it. The team is recruited from allfunctional areas (see the Porter Value Chain)

3. The team task were to come up with an initial design of the cell and the designated area for it

4. Use projections before/after metrics to justify the financial investment needed

5. recruit the cell operator and train them

6. Move the needed machines into the cells

7. Launch the cell

8. Support it until it was operating successfully

(a) To recruit the cell operators, produce colorful flyers on bulletin board presenting an exciting career

(b) Skill needed: attitude, enthusiasm for learning, willingness to engage in team building and teamwork

5.5. Process to setup a cell p66 13

Page 18: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

14Chapter 5. Chapter II: Organizational structure of QRM: QRM Cells, Teamwork and Ownership p35

Page 19: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 6

Chapter III: Understanding and exploiting system dynamics

Machine <-> People <-> Product <-> Machine

• Rethink the capacity planning approach

• lot sizing policies

p74: Read the Case of “Landing Gears”

p75: Case of situations in the supermarket, airport checking, taxi

Magnifying effect of utilization

In QRM, utilization is the ratio of the total time that the machines is occupied for any task over the Total time thefactory is scheduled at work. See utilization

𝑈𝑡𝑖𝑙𝑖𝑧𝑎𝑡𝑖𝑜𝑛 =Total time that the machines is occupied for any task

The Total time the factory is scheduled at work(6.1)

QRM Utilization =11h breaks down + 104h making parts + 26h setup + 3h maintenance

8ℎ𝑑 * 20𝑑

=144ℎ

160ℎ(6.2)

ABC Utilization =104h making parts

8ℎ𝑑 * 20𝑑

=104ℎ

160ℎ(6.3)

p78: The flow time of a job arriving at a resource as the average time that it takes for that resource to finish other workthat may be ahead of this job, start working on this job and finally complete it

p79:

u is a decimal number = 0.9 = 90%of utilization (6.4)

15

Page 20: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

M = Magnifying effect of utilization in days =𝑢

1− 𝑢=

0.9

1− 0.9= 9 days (6.5)

M shows how you queue times will blow up as you try to push your utilization higher. Example: 75% utilization =>0.75

1−0.75 = 3 days delay before to start a, unexpected job

p82: The concept of variability in arrival terms of jobs to resource. i.e. Does the job arrives at the work centerapproximately every 4 hours or in a random manner?

The concept of variability in the time that it takes for the resource to work on each job.

setup time + total time to work on all work pieces in the job.

2 types of variability p83

1. Arrival time variability

2. Job time variability

𝐴𝑉 = Average variability =𝐴𝑇𝑉 2 + 𝐽𝑇𝑉 2

2

𝑇𝐽 = Average time for a job = setup time + time to work on all the work pieces

𝑄𝑇 = Queue time = Average time the job waits in queue

𝑄𝑇 = 𝐴𝑉 *𝑀 * 𝑇𝐽

Flow time = (𝐴𝑉 *𝑀 * 𝑇𝐽) + 𝑇𝐽 = Average queue time + average time to perform the job

How to reduce the MCT for jobs?

Reduce the AV, Average Variability p84

• Read 6 tips to reduce the availability in arrivals

• Read 7 tips to reduce the variability in job times

Reduce the M, Magnifying effect of utilization p85

• QRM proposes that resources aren’t loaded up beyond 85%

• Read the 7 tips to reduce utilization and create spare capacity

Reduce the TJ, The time per job p92

• Time based approach to batch sizing

The resources are fixed (machines and people only the batch size varied

16 Chapter 6. Chapter III: Understanding and exploiting system dynamics

Page 21: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

How to find the batch size

1. Batch sizes in use at most companies are invariability too large

(a) But don’t reduce the batch size if any of your products go through a resource that is a severe bottleneck

(b) Reduce the batch size in small steps

2. Use a formula in Appendix D (simple version)

3. Analysis of specific data for the resource and the details are in Appendix D

4. Use of complex dynamic modeling software

QRM Principles p93

1. Create the right organization structure

2. Use the concept of FTMS and organize into QRM Cells

3. Don’t try to reduce the batch size within the existing organization structure

4. Find the right batch size after the reorganization

5. Alleviate the bottlenecks after the decrease of the batch size

Setup reduction - insight from the system dynamics p95

Impact of batch size reduction combined with setup reduction You need to add capacity at few resources and reduceM to enable the batch size reduction

Reexamine organizational policies to support the batch size reduc-tion (material management, sales, accounting)

• Material management policies

– Parts being made to stock, consider making smaller quantities

• Sales policies Reduce the batch sizes

• Costing policies Setup time redirection and overhead allocation reduction

QRM approach to transfer batching

First priority for the teams should be the reduction of overall batch size along with setup reduction or other supportingimprovements if needed and the transfer batching should come in only after those efforts are in place. POLCA is usedto transfer parts between cells, helping the material control strategy

System dynamics compared with MRP, EOQ and other traditional ap-proaches p99

MRP material requirement planning MRPII manufacturing resource planning ERP Enterprise Resource planning

6.4. QRM Principles p93 17

Page 22: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

Why companies mistakenly invest in warehouse instead of ma-chines? p102

Case study aerospace industry

• high variability in their operations

• high utilization

• incentive to run large batch sizes => long lead-times => necessitate large finished goods stock

18 Chapter 6. Chapter III: Understanding and exploiting system dynamics

Page 23: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 7

Chapter IV: A unified strategy for the whole industry

Principles of quick response in office operations p105

• See Appendix A

• Shift from cost-based thinking to the time-based thinking

Apply 4 principles

1. Reorganize functional departments into Q-ROCS (Quick Response Office Cells) (read Queue rocks)

2. Move from Top-down control to ownership by the Q-ROCs

3. Progress from specialized to cross-trained team members in the Q-ROCs

4. Replace your efficiency/utilization goals by MCT reduction measured via the QRM Number for each Q-ROCs

How to identify an FTMS in the context of office operations p112

1. Market; an internal or external customer that requires shorter response time

2. Examine office-processing steps for this segment and be sure to identify the product of these steps

3. Is there a subset of this product that can be attacked with simpler processing steps

4. See if the subset represents a significant enough demand that it is pursuing as a focus

5. Proceed with the design of the Q-ROC

Who does the job?

A cross-functional group that includes people from Marketing & Sales, engineering, purchasing departments

• See Appendix B for the brainstorming

19

Page 24: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

How to form effective Q-ROCs? p114

1. Cut through functional boundaries buy forming Q-ROCs which is closed-loop, collocated, dedicated multifunc-tional, cross-trained team responsible for the office processing of all jobs belonging to a specific FTMS

2. The team has complete ownership

3. Primary goal of the team is the cell’s MCT

4. Provide team members with expertise via cross training

5. Empower the team to make necessary decisions in order to server the particular FTMS

6. Change reporting structures as people aren’t separated functionally

7. Eliminate steps that become useless due to the cross-functional team (p116)

8. Redesign the steps p117

Q-ROC design method p121

1. Strategically plan for spare capacity

2. Reduce variability in terms of both job arrivals time and for tasks performed

3. Convert multiple tasks from being sequential to overlapping or parallel

4. Minimize batching by creating standardized templates or forms people will do the task right away

Marketing argument p122

A major advantage that this has over applying QRM to the shop floor is that moving people and desks is much lesscostly than moving machines and creating shop floor cells

Note: Use the case study Alexandria Extrusion Company

Restructure your MPS to support QRM

Align your MRP structure with your QRM strategy

1. Restructure the organization into QRM Cells

2. Use MRP for higher level planning of material flow from suppliers and between cells

3. Complement with POLCA, the QRM material control method that coordinates flows between cells in order tomeet delivery dates

Implement a high-level MRP (HL/MRP) p125

1. Create QRM Cells

2. As you use cells for various parts, rethink the BOM (Bill of Material) for this new structure of production with the goal of reducing MCT

20 Chapter 7. Chapter IV: A unified strategy for the whole industry

Page 25: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

• Rethink design

• material choices

• and make/buy decisions to flatten bills of material and eliminate operations

3. Use HL/MRP to plan flow of materials from suppliers and across cells in order to meet delivery dates

4. Inform the cells teams of the expected start and finish dates for the part and it will manage the details of howand when the operations would be performed

5. The cells teams communicate with the planner as conditions change

6. The POLCA system is used to coordinate the flow between cells if a part needs to go through multiple cells

• The POLCA uses actually your existing MRP system and build on it to make it more effective

POLCA - The shop flow material control strategy

Kanban is designed for shop floor coordination and control of high-volume production of similar product and with afairly stable demand Takt time cycle time within which that operation must be completed in order to keep up with theaverage rate of sales

POLCA (Paired-Cell Overlapping Loops of Cards with Authorization)

7.8. POLCA - The shop flow material control strategy 21

Page 26: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

22 Chapter 7. Chapter IV: A unified strategy for the whole industry

Page 27: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 8

Paired-Cell Loops of Cards

1. If material flows between 2 cells, then they are connected by a POLCA Loop

2. POLCA Cards circulate in the loop

• these cards are specific to the loop and are labeled based on the origin and the destination cell i.e. A/BCard

3. If a card is available, the job is started and the card is kept with the job into Cell A

4. When Cell A completes the job, it sends the job along with the A/B Card to Cell B

5. When Cell B finishes working on this job, the A/B Card is sent to Cell A

6. Returning POLCA Card signify the availability of capacity in downstream cells

Note: POLCA is a capacity signal

23

Page 28: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

24 Chapter 8. Paired-Cell Loops of Cards

Page 29: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 9

Authorization

Based on the HL/MRP, a job can start if start date is today or earlier but not dates of tomorrow or later

25

Page 30: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

26 Chapter 9. Authorization

Page 31: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 10

Dispatch list p134

1. Take the first authorized job on the list

2. The team looks up where this job is going after their cell

3. The cell team checks to see if they have a A/X POLCA Card

4. If the POLCA Card is available, they start the job

5. If the POLCA Card is not available they skip the job

27

Page 32: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

28 Chapter 10. Dispatch list p134

Page 33: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 11

Strict scheduling rules

Every time you put capacity into a job that is not needed

1. You steal capacity from another job that might have needed it

2. You create more WIP (Work In Progress)

3. You add to time to your MCT

29

Page 34: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

30 Chapter 11. Strict scheduling rules

Page 35: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 12

Overlapping loops p138

You can see that except in the first and last cells in routing, a job will always have 2 POLCA Cards with it when it isbeing actively worked on in any of the intermediate cells in its routing

Advantages:

1. This feature recognizes that each cell in the routing is a supplier or a customer to another cell

2. The jobs with problems are not continually pushed aside in favor of starting new jobs

31

Page 36: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

32 Chapter 12. Overlapping loops p138

Page 37: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

CHAPTER 13

Benefits realized with POLCA implementations

TO BE FILLED SOON

Glossary

Alleviate Make less severe

Closed-loop When the job enter the Q-ROC, the team has both expertise and authority to complete the processing ofthose jobs

Collocated Physically locating the team members together in one area. Moving the team members our of theirdepartments and into this new area sends a strong message to the whole organization

ERP Enterprise resource planning (ERP) is a business management software—usually a suite of integrated appli-cations—that a company can use to collect, store, manage and interpret data from many business activities,including: Product planning, cost. Manufacturing or service delivery. Marketing and sales.

Flow time Flow time of a job arriving at a resource as the average time that it takes for that resource to finish otherwork that may be ahead of this job, start working on this job and finally complete it

FTMS Focused Target Market Segment, Clear choice of the area where we want to make a start with the implemen-tation of QRM.

HL/MRP

High Level MRP performs the planning The higher level MRP (HL/MRP) has the following functions:

1. Prediction of the need for, and ordering materials from external suppliers;

2. Coordination of material delivery across internal cells.

Kanban Method designed for shop floor coordination and control of high-volume production of similar product andwith a fairly stable demand

Lead-time for orders Period between placing an order and receiving the ordered item.

33

Page 38: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

Lead-time to stock Period between placing a forecast and stocking the forecasted item. Products are manufacturedbased on demand forecasts. Since accuracy of the forecasts will prevent excess inventory and opportunity lossdue to stockout, the issue here is how to forecast demands accurately.

M Magnifying effect of utilization shows how you queue times will blow up as you try to push your utilization higher.Example: 75%utilization => 0.75

1−0.75 = 3 days delay before to start a, unexpected job

MCT Manufacturing Critical-Path Time is a precise QRM metric for lead time designed to capture how order pro-cessing, manufacturing, raw material procurement and shipping are linked while fulfilling customer orders.

MRP Material requirements planning (MRP) is a production planning, scheduling, and inventory control system usedto manage manufacturing processes. Most MRP systems are software-based, while it is possible to conduct MRPby hand as well.

MRPII Manufacturing resource planning (MRP II) is defined as a method for the effective planning of all resourcesof a manufacturing company. Ideally, it addresses operational planning in units, financial planning, and has asimulation capability to answer “what-if” questions and extension of closed-loop MRP.

POLCA POLCA is a capacity signal

Porter value chain In Porter’s value chains, Inbound Logistics, Operations, Outbound Logistics, Marketing andSales and Service are categorized as primary activities. Secondary activities include Procurement, Human Re-source management, Technological Development and Infrastructure

QRM Quick Response Manufacturing is a method that emphasizes the beneficial effect of reducing internal andexternal lead times.

QRM Cell A dedicated, collocated, multifunctional resources selected so that this set a complete sequence of opera-tions for all jobs belonging to a specified FTMS. The set of resources include a team of cross-trained people thathas complete ownership of the cell’s operations. The primary goal of the QRM Cell is the reduction of the MCT

QRM Number Effectively measure the MCT reduction. Psychologically, the equation (5.1) increases as the MCT isredirected and motivate the teams. QRM number increase faster when the gain is bigger. i.e. gain 2 days

12 = 17%

or 2 days8 = 25%

Q-ROC See Q-ROCs

Q-ROCs Quick Response Office Cells a closed-loop, collocated, multi-functional, cross-trained team responsiblefor a family of products. It empowers office workers to make necessary decisions. - See more at: http://www.alexandriaindustries.com/qrmnewsletters/qroc.php#sthash.IOj9AObI.dpuf

Takt time Cycle time within which that operation must be completed in order to keep up with the average rate ofsales

Touch time The time that a person or a machine is actually working on a product

Utilization The ratio of the total time that the machines is occupied for any task over the Total time the factory isscheduled at work. See the equation (6.1)

VSM Value stream mapping is a lean-management method for analyzing the current state and designing a future statefor the series of events that take a product or service from its beginning through to the customer. At Toyota, it isknown as “material and information flow mapping”

Contents:

Indices and tables

• genindex

34 Chapter 13. Benefits realized with POLCA implementations

Page 39: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

• search

13.3. Indices and tables 35

Page 40: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Quick Response Manufacturing Documentation, Release 1.0.0

36 Chapter 13. Benefits realized with POLCA implementations

Page 41: Quick Response Manufacturing Documentation · PDF file6.5 Reexamine organizational policies to support the batch size reduction ... (Activity Based Costing) ... The time per job p92

Index

AAlleviate, 33

CClosed-loop, 33Collocated, 33

EERP, 33

FFlow time, 33FTMS, 33

HHL/MRP, 33

KKanban, 33

LLead-time for orders, 33Lead-time to stock, 34

MM, 34MCT, 34MRP, 34MRPII, 34

PPOLCA, 34Porter value chain, 34

QQ-ROC, 34Q-ROCs, 34QRM, 34QRM Cell, 34

QRM Number, 34

TTakt time, 34Touch time, 34

UUtilization, 34

VVSM, 34

37