quality plan

35
QUALITY PLAN FRAMING FOR CONCRETE 1. QUALITY PLAN FOR CONCRETE 1.1. INTRODUCTION In order that the properties of the completed structure be consistent with the requirements and the assumptions made during the planning and the design, adequate quality assurance measures shall be taken. The construction should result in satisfactory strength, serviceability and long-term durability so as to lower the overall life-cycle cost. Quality assurance in construction activity relates to proper design, use of adequate materials and components to be supplied by the producers, proper workmanship in the execution of works by the contractor and ultimately proper care during the use of structure including timely maintenance and repair by the owner. Quality assurance measures are both technical and organizational. Some common cases should be specified in a general Quality Assurance Plan which shall identify the key elements necessary to provide fitness of the structure and the means by which they are to be provided and measured with the overall purpose to provide confidence that the realized project will work satisfactorily in service fulfilling intended needs. The job of quality control and quality assurance would involve quality audit of both the inputs as CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYA GROUP-III

Upload: shashank-arun

Post on 28-Nov-2014

207 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

1. QUALITY PLAN FOR CONCRETE

1.1. INTRODUCTIONIn order that the properties of the completed structure be consistent with the requirements

and the assumptions made during the planning and the design, adequate quality assurance

measures shall be taken. The construction should result in satisfactory strength,

serviceability and long-term durability so as to lower the overall life-cycle cost. Quality

assurance in construction activity relates to proper design, use of adequate materials and

components to be supplied by the producers, proper workmanship in the execution of works

by the contractor and ultimately proper care during the use of structure including timely

maintenance and repair by the owner.

Quality assurance measures are both technical and organizational. Some common cases

should be specified in a general Quality Assurance Plan which shall identify the key

elements necessary to provide fitness of the structure and the means by which they are to be

provided and measured with the overall purpose to provide confidence that the realized

project will work satisfactorily in service fulfilling intended needs. The job of quality

control and quality assurance would involve quality audit of both the inputs as well as the

outputs. Inputs are in the form of materials for concrete; workmanship in all stages of

batching, mixing, transportation, placing, compaction and curing; and the related plant,

machinery and equipment; resulting in the output in the form of concrete in place. To ensure

proper performance, it is necessary that each step in concreting which will be covered by the

next step is inspected as the work proceeds.

Each party involved in the realization of a project should establish and implement a Quality

Assurance Plan, for its participation in the project. Supplier’s and subcontractor’s activities

shall be covered in the plan. The individual Quality Assurance Plans shall fit into the

general Quality Assurance Plan. A Quality Assurance Plan shall define the tasks and

responsibilities of all persons involved, adequate control and checking procedures, and the

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 2: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

organization and maintaining adequate documentation of the building process and its results.

Such documentation should generally include:

1. Test reports and manufacturer’s certificate for materials, concrete mix design details;

2. Pour cards for site organization and clearance for concrete placement;

3. Record of site inspection of workmanship,

4. Field tests; non-conformance reports, change orders;

1.2. CODES TO BE FOLLOWED

1.2.1. CONCRETE / BLOCKWORK

1.2.1.1. Compaction Requirement1. Sampling : BS 5930 (or as updated), IS

2720

2. Field Dry Density : BS 1377: 1975 Clause 4.4 Test 15 (or as updated)

1. “Determination of the dry density of soil on the site - Sand replacement test”

3. Standard Maximum : BS 1377: 1975 Clause 4.1 Test 12 (or as updated)

4. Dry Density : “Determination of dry density / moisture content relationship” using 2. Kg rammer

5. Moisture Content : BS 1377: 1975 Clause 2.1 Test 1 (or as updated)

“Determination of the moisture content - Standard”

1.2.1.2. Cast in-situ concrete

1. IS - 299 : Specification for Ordinary, rapid hardening and low heat Portland Cement Specification for

2. IS - 455 : Portland blast furnace slag Cement

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 3: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

3. IS - 1489 Specification for Portland pozzolona Cement

4. IS - 4031 : Method of physical tests for hydraulic Cement

5. IS - 650 : Specification for Standard sand for testing of Cement

6. IS - 383 : Specification for Coarse and Fine aggregate for use in mass concrete

7. IS - 515 : Specification for natural and manufactured aggregate for use in mass concrete.

8. IS - 2387 : Method of test for aggregates for concrete.

9. IS - 516 : Methods of test for strength of concrete.

10. IS - 1199 : Methods of sampling and analysis of concrete

11. IS - 3025 : Methods of sampling and test (physical and chemical) for water used in

industry.

12. IS - 2645 : Specification for integral cement water proofing compounds

13. IS - 1791 Specification for batch type concrete mixers

14. IS - 2438 : Specification for roller pan mixer

15. IS - 2505 : Specification for concrete vibrators, immersion type

16. IS - 2506 : Specification for screed board concrete vibrator

17. IS - 2514 : Specification for concrete vibrating tables

18. IS - 3344 : Specification for pan vibrators

19. IS - 4656 : Specification for form vibrators

20. IS - 2722 : Specification for portable swing weigh batchers for concrete (single & double bucket type)

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 4: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

21. IS - 456 : Code of practice for plain and reinforced concrete

22. IS - 1343 : Code of practice for pre-stressed concrete

23. IS - 457 : Code of practice for general construction of plain and reinforce

concrete for dams and other massive structures.

24. IS - 3370 : Code of practice for concrete (Part I to IV structures for storage of liquids

25. IS - 3935 : Code of practice for composite construction

26. IS - 3201 : Criteria for design and construction of pre-cast concrete trusses.

27. IS - 2204 : Code of practice for construction of reinforced concrete shell roof.

28. IS - 2210 : Criteria for the design of R.C. shell structures and folded plates.

29. IS - 3558 : Code of practice for use of immersion vibrators for consolidating concrete

30. IS - 3414 : Code of practice for design and installation of joints in buildings

31. IS - 2571 : Code of practice for laying in-situ cement concrete flooring

32. IS - 12269 : Code of practice for 53 grade cement

1.2.1.3. Reinforcement

33. IS - 432 : Specification for Mild steel and medium tensile bars and hard drawn steel wire.

34. IS - 1139 : Specification for hot rolled mild steel, medium tensile steel and high yield

strength steel deformed bars for concrete reinforcement.

35. IS - 1566 : Specification for plain hard drawn steel wire fabric for concrete reinforcement

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 5: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

36. IS - 1785 : Specification for plain hard drawn steel wire for prestressed concrete.

37. IS - 1786 : Specification for cold twisted steel high strength deformed bars for concrete

reinforcement.

38. IS - 2080 : Specification for high tensile steel bars used in prestressed concrete

39. IS - 2751 : Code of practice for welding of mild steel structures are folded plates

40. IS - 2502 : Code of practice for bending and fixing of bars for concrete reinforcement

1.2.1.4. Steel Grades

1.2.1.4.1. Grade, Description, Conforming to

1. Fe 250 : Mild Steel, IS 432 (Part I)

2. Fe 490 : Hard drawn steel wire, IS 432 (Part II)

3. Fe 415 : High strength deformed/ ribbed steel, IS 1786

4. Fe 500 : High strength deformed / ribbed steel, IS 1786

5. Fe 550 : High strength deformed / ribbed steel, IS 1786

1.2.1.5. Formwork

1. IS - 303 : Specification for Plywood for general purposes

2. IS - 4990 : Specification for plywood for concrete shuttering work

3. IS - 1629 : Rules for grading of cut size of timber

4. IS - 2750 : Specification for steel scaffoldings.

5. IS - 4014 : Code of practice for steel tubular, scaffolding

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 6: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

1.2.1.6. Structural Steel

1. IS-226-1975 : Structural Steel (standard quality) (fifth revision)

2. IS-456-1978 : Code of practice for plain and reinforced concrete (third revision)

3. IS-696-1972 : Code of practice for general engineering drawings (second revision)

4. IS-786-1967 : (Supplement) SI supplement to Indian Standard conversion factors and conversion tables (first revision)

5. IS-812-1957 : Glossary of terms relating to welding and cutting of Metals

6. IS-813-1961 : Scheme of symbols for welding

7. IS-814 : Covered electrodes for metal arc welding of structural steels: 814 (Part 1)-1974 Part 1 for welding products other than sheets (fourth revision)

8. IS-816-1969 : Code of practice for use of metal arc welding for general construction in mild steel (first revision)

9. IS-817-1966 : Code of practice for training and testing of metal arc welders (revised)

10. IS-819-1957 : Code of practice for resistance spot welding for light assemblies In mild steel

11. IS-875-1964 : Code of practice for structural safety of buildings: Loading standards (revised)

12. IS-919-1963 : Recommendations for limits and fits for engineering (revised)

13. IS-961-1975 : Structural steel (high tensile) (second revision)

14. IS-962-1967 : Code of practice for architectural and building drawings (first revision)

15. IS-1024-1979 : Code of practice for use of welding in bridges and structures subject to dynamic loading (first revision)

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 7: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

16. IS-1030-1982 : Carbon steel castings for general engineering purposes (second revision)

17. IS-1148-1973 : Hot-rolled steel rivet bars (up to 40 mm diameter) for structural purposes (second revision)

18. IS-1149-1982 : High tensile steel rivet bars for structural purposes

19. IS-1261-1959 : Code of practice for seam welding in mild steel

20. IS-1278-1972 : Filler rods and wires for gas welding (second revision)

21. IS-1323-1962 : Code of practice for oxy- acetylene welding for structural work in mild steel (revised)

22. IS-1363-1967 : Black hexagon bolts, nuts and lock nuts (diameter 6 to 39 mm) and black hexagon screws (diameter 6 to 24 mm) (first revision)

23. IS-1364-1967 : Precision and semi-precision hexagon bolts, screws, nuts and lock nuts (diameter range 6 to 39 mm) (first revision)

24. IS-1367-1967 : Technical supply conditions for threaded fasteners (first revision)

25. IS-1393-1961 : Code of practice for training and testing of oxy-acetylene welders

26. IS-1395-1982 : Molybdenum and chromium molybdenum vanadium low alloy steel electrodes for metal arc welding (second revision)

27. IS-1477 : Code of practice for painting of ferrous metals in buildings: 1477 (Part 1)-1971 Part 1 Pretreatment (first revision)(Part 2)-1971 Part 2 Painting

28. IS-1929-1961 : Rivets for general purposes (12 to 48 mm diameter)

29. IS-1977-1975 : Structural steel (ordinary quality) (second revision)

30. IS-2062-1984 : Weld able structural steel (third revision)

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 8: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

31. IS-2155-1962 : Rivets for general purposes (below 12 mm diameter)

32. IS-3613-1974 : Acceptance tests for wire-flux combinations for submerged-arc welding of structural steels (first revision)

33. IS-3757-1972 : High-tensile friction grip bolts (first revision)

34. IS-4000-1967 : Code of practice for assembly of structural joints using high tensile friction grip fasteners

35. IS-5369-1975 : General requirements for plain washers and lock washers (first revision)

36. IS-5370-1969 : Plain washers with outside diameter 3 x inside diameter

37. IS-6419-1971 : Welding rods and bare electrodes for gas shielded arc welding of structural steel

38. IS-6623-1972 : High tensile friction grip nuts

39. IS-6649-1972 : High tensile friction grip washers

40. IS-7205-1974 : Safety code for erection of structural steel work

41. IS-7215-1974 : Tolerances for fabrication of steel structures

42. IS-7280-1974 : Bare wire electrodes for submerged arc welding of structural steels

43. IS-8500-1977 : Weld able structural steel (medium and high strength qualities)

1.2.1.7. GENERAL ITEMS CHECKLIST:

1. Concrete specifications Before placing concrete - tests, mix design, ingredients, inspections etc.

2. Testing laboratory Notified prior to pour, and testing is arranged at plant and site.

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 9: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

3. All areas to receive concrete Cleaned, wetted or otherwise prepared as required. Foundations are free of frost and water. Previously placed concrete is properly prepared to receive new.

4. Tools / vibrators: all necessary tools on hand are in working conditions. Vibrators and standby vibrators are available and in working condition.

5. Conveying/depositing equipment Capable of reaching all areas of placement without segregation, loss of ingredients, formation of air pockets or cold joints.

6. Manpower adequate Available for timely placement

7. Temporary form openings, chutes etc Provided.

8. Pockets Vented to prevent air entrapment.

9. Sub-base Compacted. Membrane is provided and installed as required.

10. Curing, sawed joints and protection Arrangements made.

11. Cube moulds and slump cone At site and samples are properly taken.

12. Standing time Time interval between adding water to concrete and placing in final position is known.

13. Delivery of concrete and sequence of delivery Scheduled to allow continuous placement to prevent cold joints.

14. Grout Added to columns/walls prior to placing concrete.

15. Layers Kept approximately horizontal.

16. Bolts and loose items to be embedded Properly located and installed.

17. Date and location of pours Recorded.

18. Checking during pouring Grades, elevations, alignment, form adjustment and supports

19. Vibration Performed properly, using correct equipment and forms are not damaged.

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 10: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

20. Adding water Approval required.

21. Cubes Cast and stored. Slump and other tests are performed as required.

FINISHING AND CURING

22. Type of finish on unformed surfaces Checked and provided as required (smooth, rubbed, broomed, nonslip, exposed aggregate, coloured etc).

23. Overtroweling To be avoided. (Troweling is not performed while bleed water is on surface).

24. Curing Started as soon as possible. Curing compounds are as required and compatible with subsequent finishes.

25. Finishing methods Provides evenness, smoothness, and levelness of surfaces within tolerance indicated. Slopes are provided to properly drain. Marks left by tools are removed.

26. Joints, edges and corners Carefully finished and/or match.

Table 1.2.1.7-A

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 11: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

METHOD STATEMENT FOR CONCRETING WORKS

OBJECTIVE: To formulate guideline for Mixing, Shifting & Placing of concrete

REFERENCE: 1. Technical Specification of Tender Document

2. "Released For Construction” Drawings 3. IS: 383 - Specification for coarse and fine aggregates from natural sources for concrete. 4. IS: 456-2000: Plain reinforced concrete - code of practice.

MATERIALS REQUIRED: Cement, aggregates, water & admixture

RESPONSIBILITY: QAQC Engineer, Site Engineer & Foreman

Sl. No.

ProcedureResponsibilit

yCheck By Records

1 Within the site area a batching plant shall be erected and

well calibrated, transit mixers shall be used for

transportation of concrete to the area of pour.

P & M

Engineer

QC Engineer

2 Review the condition and sufficiency of equipment for

mixing, transporting, placing, vibrating and

curing.specification

P & M

Engineer

QC Engineer

3 Adequacy supply / availability and suitability of

material, workmen in sufficient nos. shall be ensured

before the commencement of the work.

Admin

Officer / Const

Manager

QC Engineer

4 For concreting works two sets of immersion type

vibrator & needle assembly shall be used and adequate

numbers of needle (60mm / 40mm) shall be kept at

hand.

Site Engineer Section Head

5 Concrete shall be placed as near as possible to its final

location. It shall not be moved over long distances using

vibrator.

Site Engineer QC Engineer

(Random)

6 Whenever pumping of concrete is involved, checks are

to be made to ensure that the pipeline doesn’t disturb

any formwork while carrying concrete.

Site

Enginner /

Foreman

Formwork

Engineer/

Site

Engineer

7 Load the first TM with 0.5 cum slurry for buttering of

concrete pump and its pipeline. The slurry to be

disposed of the foundation area.

Site Engineer QC Engineer

8 The concrete pump shall be cleaned after concreting &

maintenance shall be carried out periodically.

P & M

Engineer

QC Engineer

(Random)

Page 12: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

Table 1.2.1.7-B

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 13: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Pro

jec

t:D

ate

:

28 d

ays

re

sult

s

LT

CD

Cli

en

tR

em

ark

sD

ate

of

Te

stin

gW

eig

ht

(gm

s)L

oa

d (

KN

)C

om

p.

Str

en

gth

(N

/mm

2)R

esu

lt

Da

teo

fC

ast

ing

Qu

ali

ty M

an

ag

em

en

t S

yste

m

QA

Co

ncr

ete

Cu

be

Tes

t R

epo

rt

Sr.

N

o.

Ite

ms

De

scri

pti

on

Siz

eo

fS

pe

cim

en

s (m

m)

Gra

de

of

Co

ncr

ete

Ide

nti

fica

tio

n

Ma

rk

Page 14: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

QUALITY FORMAT(To be maintained by respective Site Engineers)PRE POUR INSPECTION CARD

Description Items / Check Required Actual Tolerance Remarks

A. Form work Fixing / bracing

Level +10 mm +10 mm Plumb + 3mm / 1m, max

20mm+ 3mm / 1m,

max 20mm Storey ht.

Cleanliness Free from foreign materials

Form oil application

Uniformly over the surface

Cutouts

Grout tightness

B. Reinforcement Position

No. & size

Anchorage

Spacing + 10mm Lapping + 10mm

Cover + 10mm – 2mm Cleanliness

Dowel bars

Links

Binding / welding

c. General 1.Embedments

2. Water Proofing

3. Construction Jt. Preparation

d. Finished Concrete

1. Dimensions +10 mm, -6mm2. Straightness

3. Flatness + 6mm / 1.5 m4.Plumb +3 mm / 1m

Site Engineer QA Engineer

Loose Bulk Density Quality Management

SystemSl No

Description Formula Test1 Test2

Test3

Remarks

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 15: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

1 Weight of the Bulk Density Cylinder (in gms)

A

2 Weight of theCyllinder + Material (in gms)

B

3 Weight of the Material (in gms) B-A

4 Volume of the Bulk Density Cylnder (in cc)

D

5 Bulk Density of the Material Sample (gms/cc)

(B-A)/D

Note: Average Loose Bulk Density of the material is

gms/cc

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 16: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

METHOD STATEMENT FOR FORMWORK WORKSOBJECTIVE: To formulate guidelines for moulding concrete to required shape, position in terms of level & dimension

REFERENCE: 1. Good for Construction Drawings 2. Technical Specifications of Tender Documents 3. Inspection and test plan LTCD/ITP/C-001 4. IS (Code) 456 : 2000

MATERIALS REQUIRED: Formwork materials including Staging.

RESPONSIBILITY: Site Engineer & Formwork Engineer/Foreman

Sl. No. Procedure Responsibility Check By Records

1 Analyse type of structures referring approved construction drawings & tender specification.

Form work Engineer Construction Manager

2 Plan materials requirements based on type of approved schemes, decide cycle time based on construction schedule of project, code of practice & tender specification

Form work Engineer Construction Manager

S6A

3 Receive construction drawings & prepare formwork scheme drawings considering technical specifications, supporting system, tying system.

Form work Engineer Regional Form work Co-ordinator

Scheme Drawings

4 For precasting, fabricate as per approved scheme drawings & proper positioning the same during execution.

Foreman Formwork Engineer/ Site

Engineer5 Clean Formwork free from saw dust & any other

foreign materials.Foreman Formwork

Engineer6 Apply releasing agent for formwork ( ply/Steel) before

using the same at site.Foreman Formwork

Engineer7 Check level, line, shape, tightness of formwork Foreman / Site

EngineerQA Engineer (Random)

Check List

8 Check the dimensions after concrete Foreman / Site Engineer

QA Engineer (Random)

Check List

9 Plan deshuttering system/ method in order to avoid damages of concrete.

Foreman Formwork Engineer

10 Deshuttering formwork considering stripping time as per specification.

Foreman Formwork Engineer/ Site

Engineer11 Slab deshuttering shall be done after checking the

cube strength of concreteSite Engineer QC Engineer /

Formwork Engineer

12 Clearance of Pour Before Concreting Site Engineer Client (Random)

13 For construction safety please refer to Safe Work Methods for Formwork in Project HSE Plan

Site Engineer -

ACCEPTANCE CRITERIA:1 Tolerance for cross sectional dimensions of cast in situ & precast elements- +12mm/-6mm2 Tolerance for footing

dimension in plan +50mm/-12mmeccentricity

thickness + 0.05 times thespecified thickness

3 Tolerance for length of the precast elements - upto 3ms +6mm

-3m to 4.5m: ±9mm

-Additional deviation for every subsequent 6m: ±12mm

4 Tolerance for plumb 3mm/m or 20 mm

5 Tolerance for level of the cast in situ elements +10mm

0.02 times the width of the footing in the direction of deviation but not more than 50mm

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 17: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

METHOD STATEMENT FOR REINFORCEMENT WORKSOBJECTIVE: To formulate guidelines for cutting, bending & tying of reinforcement.

REFERENCE: 1. Good for Construction Drawings 2. Technical Specifications of Tender Documents 3. Inspection and test plan LTCD/ITP/C-001 4. IS : 2502-1963: Code of Practice for Bending & Fixing of bars for concrete reinforcement.

Sl. No. Procedure Responsibility Check By Records

A Reinforcement Handling1 Receive Reinforcement along with MTC & submit to

the client if requiredStores In-Charge Reinforcement

EngineerMTC

2 Check the quantity of Reinforcement corresponding to the weigh slip,transport & unload the same at reinforcement yard

Stores In-Charge -

3 Hand Gloves & other Protective equipments shall be used while handling reinforcement

Reinforcement Engineer

Safety Co-ordinator

4 Unusable cut rods & scrap reinforcement shall be transferred to a well identified scrap yard.

Reinforcement Engineer

-

B Bar Bending schedule1 BBS shall be prepared based on the latest GFC

DrawingsSite Engineer/ Section Head

Reinforcement Engineer/ Client

BBS

2 BBS shall specify bar marks, bar dia, number of bars, shape, cut length, bends & shape etc as per GFC Drawing.

Site Engineer/ Section Head

Reinforcement Engineer/ Client BBS

3 BBS shall specify lap lengths, their location and staggering of laps. It shall take into account the Development length/ Anchorage Length.

Site Engineer/ Section Head

Reinforcement Engineer/ Client BBS

C Bar Cutting, Bending & Placing1 Rebar shall be clean & free from rust, mud & oil. Site Engineer QA Engineer /

Client (Random)Check List

2 The details like Bar Spacing, cranks, hooks & their location shall be in commensuration with the GFC drawings

Site Engineer / Reinforcement

Engineer

QA Engineer / Client (Random) Check List

3 Gauge of the Binding wire shall be 16-20 SWG (1 to 1.6 mm) annealed steel wire

Reinforcement Engineer

-

4 The Number of chairs, spacers & cover blocks shall be adequate

Site Engineer QA Engineer / Client (Random)

Check List / BBS

5 In walls place accurately bent spacer bars wired to vertical or horizontal bars between successive rows.

Site Engineer

D Clearnace of Pour Before Concreting Site Engineer Client (Random)

Check List

E For Construction safety Please refer to Safe Work Methods for Reinforcement in Project HSE Plan

Site Engineer -

ACCEPTANCE CRITERIA:1 Reinforcement shall be placed in the following tolerences:

For effective depth< 200mm tolerence in spacing +10mm

For effective depth > 200 mm tollerence in spacing +15mm

2 Provision to Cover to Reinforcement shall be +10mm / -2 mm from specified.

RESPONSIILITY: Site Engineer, Reinforcement Engineer & Stores Incharge

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 18: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

METHOD STATEMENT FOR REINFORCEMENT WORKS

OBJECTIVE: To formulate guidelines for cutting, bending & tying of reinforcement.

REFERENCE: 1. Good for Construction Drawings 2. Technical Specifications of Tender Documents 3. Inspection and test plan LTCD/ITP/C-001 4. IS : 2502-1963: Code of Practice for Bending & Fixing of bars for concrete reinforcement.

RESPONSIILITY: Site Engineer, Reinforcement Engineer & Stores Incharge

Sl. No.

Procedure Responsibility Check By Records

A Reinforcement Handling1 Receive Reinforcement along with MTC &

submit to the client if requiredStores In-Charge

Reinforcement Engineer

MTC

2 Check the quantity of Reinforcement corresponding to the weigh slip,transport & unload the same at reinforcement yard

Stores In-Charge

-

3 Hand Gloves & other Protective equipments shall be used while handling reinforcement

Reinforcement Engineer

Safety Co-ordinator

4 Unusable cut rods & scrap reinforcement shall be transferred to a well identified scrap yard.

Reinforcement Engineer

-

B Bar Bending schedule1 BBS shall be prepared based on the latest

GFC DrawingsSite Engineer/ Section Head

Reinforcement Engineer/ Client

BBS

2 BBS shall specify bar marks, bar dia, number of bars, shape, cut length, bends & shape etc as per GFC Drawing.

Site Engineer/ Section Head

Reinforcement Engineer/ Client

BBS

3 BBS shall specify lap lengths, their location and staggering of laps. It shall take into account the Development length/ Anchorage Length.

Site Engineer/ Section Head

Reinforcement Engineer/ Client

BBS

C Bar Cutting, Bending & Placing1 Rebar shall be clean & free from rust, mud

& oil.Site Engineer QA

Engineer / Check List

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 19: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

Client (Random)

2 The details like Bar Spacing, cranks, hooks & their location shall be in commensuration with the GFC drawings

Site Engineer / Reinforcement Engineer

QA Engineer / Client (Random)

Check List

3 Gauge of the Binding wire shall be 16-20 SWG (1 to 1.6 mm) annealed steel wire

Reinforcement Engineer

-

4 The Number of chairs, spacers & cover blocks shall be adequate

Site Engineer QA Engineer / Client (Random)

Check List / BBS

5 In walls place accurately bent spacer bars wired to vertical or horizontal bars between successive rows.

Site Engineer

D Clearnace of Pour Before Concreting Site Engineer Client (Random)

Check List

E For Construction safety Please refer to Safe Work Methods for Reinforcement in Project HSE Plan

Site Engineer -

ACCEPTANCE CRITERIA:1 Reinforcement shall be placed in the following tolerances:

For effective depth< 200mm tolerance in spacing +10mm For effective depth > 200 mm tolerance in spacing +15mm

2 Provision to Cover to Reinforcement shall be +10mm / -2 mm from specified.

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 20: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

Testing of Concrete Quality Management System

Brand of Cement:- Date:-

Suppling Batch No:-

Physical Properties :-

Normal Consitency Initial Setting Time Final Setting Time28 Day Cube Strenth

3 Days 7 Days 28 Days

Average Compressive StrengthTable 1.2.1.7-C

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 21: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

Impact Value Test

Project :

Material : Date:Sr. No.

Description Unit Wt Remarks

1 Total Weight of Aggregate taken gms

2 Weight of aggregates passing through 12.5 mm & retained on 10mm IS Sieves.

gms

3 Weight of the mould 1 (A) gms

4 Weight of the mould 1 + aggregate sample (B) gms

5 Weight of the aggregate sample (B-A) gms

6 Weight of the material passing through 2.36mm IS Sieve. ( C)

gms

7 Impact Value of aggregate (C / (B-A)) gms

Remarks:Table 1.2.1.7-D

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 22: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

3. SIZE OF AGGREGATE :

1 63 50

2 50 40

3 40 31.5

4 31.5 25

5 25 20

6 20 16

7 16 12.5

8 12.5 10

9 10 6.3

TOTAL

Quality Management systemELONGATION INDEX

Elongation INDEX :

No of particles passing through Elongation gauge

(X1*Y1)/100

2. SOURCE / QUARRY :

Total Weihght of Particles

% of weight of particles to the total wt taken

(Y1)

PASSING THROUGH

SIEVE (MM)

RETAINED ON

SIEVE (MM)

No of particles retained on Elongation

Gauge

TOTALSL NO

SIZE OF AGGREGATE NO. OF PARTICLES % of Nos of particles retained

on Gauge (X1) (%)

Date

4. TOTAL WEIGHT OF SAMPLE :

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 23: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

Date:-

4. TOTAL WEIGHT OF SAMPLE :

X1 (%)

(%) X1 x Y1

100

1 63 50

2 50 40

3 40 31.5

4 31.5 25

5 25 20

6 20 16

7 16 12.5

8 12.5 10

9 10 6.3

TOTAL

RETAINED ON Flakiness Gauge

TOTAL

SIZE OF AGGREGATE NO. OF PARTICLES

Quality Management System

FLAKINESS INDEX :

3. SIZE OF AGGREGATE :

WEIGHT OF PARTICLES

SL NO

2. SOURCE / QUARRY :

FLAKINESS INDEX

(%)of Wt of Particles to the total wt taken

PASSING THROUGH

SIEVE (MM)

RETAINED ON

SIEVE (MM)

PASSING THROUGH

Flakiness Gauge

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 24: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

Sieve Analysis of 20mm AggregatesQuality Management

System

Project:

Source of Material: Date:

Weight of the Sample:

Sl NoSize Of IS

Seive in mm

Retained Weight (gms)

Cum. Weight retained

(gms)

Cummulative % Weight Retained % Passing

As Per IS 383 Remarks

1 40 100

2 2085-100

3 10 0-20

4 4.75 0-5

5 Pan 0Table 1.2.1.7-E

Sieve Analysis of 10mm AggregateQuality Management

SystemProject:

Source of Material: Date:

Weight of the Sample:

Sl No

Size Of IS Seive in

mm

Retained Weight (gms)

% Weight retained

Cummulative % Weight Retained % Passing

As Per IS 383 Remarks

1 12.5 100

2 10 85-100

3 4.75 0-20

4 2.36 0-5

5 Pan 0Table 1.2.1.7-F

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 25: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

Quality Management System

Sieve Analysis of SandProject:

Source of Material : Date:

Weight of the Sample:

Sl No

Size Of IS

Seive in mm

Retained Weight (gms)

% Weight retained

Cummulative % Weight Retained

% Passing

As Per IS 383

(Zone II)Remarks

1 10 100

2 4.75 90-100

3 2.36 75-100

4 1.18 55-90

5 0.6 35-59

6 0.3 8-30

7 0.15 0-10

8 PanTable 1.2.1.7-G

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 26: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

Silt Content in SandQuality

Management System

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 27: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

Project : Date:

Material:

Source:

Sl No Description Formula Test1 Test2 Test3 Remarks

1Level of sand in measuring jar A

2

Level of sand & water in measuring jar B

3

Observation of silt level after full settlement C

4 Silt Content (%)C * 100 /

AAverage Silt content percent in sand

Table 1.2.1.7-H

Specific Gravity of Aggregate Quality Management System

Project :

Material: Date:

Source:

Sl No Description Formula Test1Remark

s

1Weight of the Empty Pycnometer (in gms) A

2Weight of the Pycnometer filled with Material (in gms) B

3Weight of the Pycnometer filled with Material & Water(in gms) C

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III

Page 28: Quality Plan

QUALITY PLAN FRAMING FOR CONCRETE

4Weight of the Pycnometer & Water(in gms) D

5 Weight of the dry sample (in gms) E

6 Specific Gravity(B-A) / [ (C-B)-(D-

A) ]

6 Water Absorption (%) E * 100 / (B-A)Table 1.2.1.7-I

Project :

Material:

Source:

Sl No Test1 Test2 Test3

1

2

3

4

5

Note: Average Loose Bulk Density of the material is

Quality Management SystemLoose Bulk Density

Date:

Bulk Density of the Material Sample (gms/cc) (B-A)/D

Weight of the Material (in gms)

Description Formula Remarks

Weight of the Bulk Density Cylinder (in gms) A

B-A

Weight of theCyllinder + Material (in gms) B

gms/cc

Volume of the Bulk Density Cylnder (in cc) D

CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III