quality plan
TRANSCRIPT
QUALITY PLAN FRAMING FOR CONCRETE
1. QUALITY PLAN FOR CONCRETE
1.1. INTRODUCTIONIn order that the properties of the completed structure be consistent with the requirements
and the assumptions made during the planning and the design, adequate quality assurance
measures shall be taken. The construction should result in satisfactory strength,
serviceability and long-term durability so as to lower the overall life-cycle cost. Quality
assurance in construction activity relates to proper design, use of adequate materials and
components to be supplied by the producers, proper workmanship in the execution of works
by the contractor and ultimately proper care during the use of structure including timely
maintenance and repair by the owner.
Quality assurance measures are both technical and organizational. Some common cases
should be specified in a general Quality Assurance Plan which shall identify the key
elements necessary to provide fitness of the structure and the means by which they are to be
provided and measured with the overall purpose to provide confidence that the realized
project will work satisfactorily in service fulfilling intended needs. The job of quality
control and quality assurance would involve quality audit of both the inputs as well as the
outputs. Inputs are in the form of materials for concrete; workmanship in all stages of
batching, mixing, transportation, placing, compaction and curing; and the related plant,
machinery and equipment; resulting in the output in the form of concrete in place. To ensure
proper performance, it is necessary that each step in concreting which will be covered by the
next step is inspected as the work proceeds.
Each party involved in the realization of a project should establish and implement a Quality
Assurance Plan, for its participation in the project. Supplier’s and subcontractor’s activities
shall be covered in the plan. The individual Quality Assurance Plans shall fit into the
general Quality Assurance Plan. A Quality Assurance Plan shall define the tasks and
responsibilities of all persons involved, adequate control and checking procedures, and the
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
organization and maintaining adequate documentation of the building process and its results.
Such documentation should generally include:
1. Test reports and manufacturer’s certificate for materials, concrete mix design details;
2. Pour cards for site organization and clearance for concrete placement;
3. Record of site inspection of workmanship,
4. Field tests; non-conformance reports, change orders;
1.2. CODES TO BE FOLLOWED
1.2.1. CONCRETE / BLOCKWORK
1.2.1.1. Compaction Requirement1. Sampling : BS 5930 (or as updated), IS
2720
2. Field Dry Density : BS 1377: 1975 Clause 4.4 Test 15 (or as updated)
1. “Determination of the dry density of soil on the site - Sand replacement test”
3. Standard Maximum : BS 1377: 1975 Clause 4.1 Test 12 (or as updated)
4. Dry Density : “Determination of dry density / moisture content relationship” using 2. Kg rammer
5. Moisture Content : BS 1377: 1975 Clause 2.1 Test 1 (or as updated)
“Determination of the moisture content - Standard”
1.2.1.2. Cast in-situ concrete
1. IS - 299 : Specification for Ordinary, rapid hardening and low heat Portland Cement Specification for
2. IS - 455 : Portland blast furnace slag Cement
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
3. IS - 1489 Specification for Portland pozzolona Cement
4. IS - 4031 : Method of physical tests for hydraulic Cement
5. IS - 650 : Specification for Standard sand for testing of Cement
6. IS - 383 : Specification for Coarse and Fine aggregate for use in mass concrete
7. IS - 515 : Specification for natural and manufactured aggregate for use in mass concrete.
8. IS - 2387 : Method of test for aggregates for concrete.
9. IS - 516 : Methods of test for strength of concrete.
10. IS - 1199 : Methods of sampling and analysis of concrete
11. IS - 3025 : Methods of sampling and test (physical and chemical) for water used in
industry.
12. IS - 2645 : Specification for integral cement water proofing compounds
13. IS - 1791 Specification for batch type concrete mixers
14. IS - 2438 : Specification for roller pan mixer
15. IS - 2505 : Specification for concrete vibrators, immersion type
16. IS - 2506 : Specification for screed board concrete vibrator
17. IS - 2514 : Specification for concrete vibrating tables
18. IS - 3344 : Specification for pan vibrators
19. IS - 4656 : Specification for form vibrators
20. IS - 2722 : Specification for portable swing weigh batchers for concrete (single & double bucket type)
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
21. IS - 456 : Code of practice for plain and reinforced concrete
22. IS - 1343 : Code of practice for pre-stressed concrete
23. IS - 457 : Code of practice for general construction of plain and reinforce
concrete for dams and other massive structures.
24. IS - 3370 : Code of practice for concrete (Part I to IV structures for storage of liquids
25. IS - 3935 : Code of practice for composite construction
26. IS - 3201 : Criteria for design and construction of pre-cast concrete trusses.
27. IS - 2204 : Code of practice for construction of reinforced concrete shell roof.
28. IS - 2210 : Criteria for the design of R.C. shell structures and folded plates.
29. IS - 3558 : Code of practice for use of immersion vibrators for consolidating concrete
30. IS - 3414 : Code of practice for design and installation of joints in buildings
31. IS - 2571 : Code of practice for laying in-situ cement concrete flooring
32. IS - 12269 : Code of practice for 53 grade cement
1.2.1.3. Reinforcement
33. IS - 432 : Specification for Mild steel and medium tensile bars and hard drawn steel wire.
34. IS - 1139 : Specification for hot rolled mild steel, medium tensile steel and high yield
strength steel deformed bars for concrete reinforcement.
35. IS - 1566 : Specification for plain hard drawn steel wire fabric for concrete reinforcement
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
36. IS - 1785 : Specification for plain hard drawn steel wire for prestressed concrete.
37. IS - 1786 : Specification for cold twisted steel high strength deformed bars for concrete
reinforcement.
38. IS - 2080 : Specification for high tensile steel bars used in prestressed concrete
39. IS - 2751 : Code of practice for welding of mild steel structures are folded plates
40. IS - 2502 : Code of practice for bending and fixing of bars for concrete reinforcement
1.2.1.4. Steel Grades
1.2.1.4.1. Grade, Description, Conforming to
1. Fe 250 : Mild Steel, IS 432 (Part I)
2. Fe 490 : Hard drawn steel wire, IS 432 (Part II)
3. Fe 415 : High strength deformed/ ribbed steel, IS 1786
4. Fe 500 : High strength deformed / ribbed steel, IS 1786
5. Fe 550 : High strength deformed / ribbed steel, IS 1786
1.2.1.5. Formwork
1. IS - 303 : Specification for Plywood for general purposes
2. IS - 4990 : Specification for plywood for concrete shuttering work
3. IS - 1629 : Rules for grading of cut size of timber
4. IS - 2750 : Specification for steel scaffoldings.
5. IS - 4014 : Code of practice for steel tubular, scaffolding
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
1.2.1.6. Structural Steel
1. IS-226-1975 : Structural Steel (standard quality) (fifth revision)
2. IS-456-1978 : Code of practice for plain and reinforced concrete (third revision)
3. IS-696-1972 : Code of practice for general engineering drawings (second revision)
4. IS-786-1967 : (Supplement) SI supplement to Indian Standard conversion factors and conversion tables (first revision)
5. IS-812-1957 : Glossary of terms relating to welding and cutting of Metals
6. IS-813-1961 : Scheme of symbols for welding
7. IS-814 : Covered electrodes for metal arc welding of structural steels: 814 (Part 1)-1974 Part 1 for welding products other than sheets (fourth revision)
8. IS-816-1969 : Code of practice for use of metal arc welding for general construction in mild steel (first revision)
9. IS-817-1966 : Code of practice for training and testing of metal arc welders (revised)
10. IS-819-1957 : Code of practice for resistance spot welding for light assemblies In mild steel
11. IS-875-1964 : Code of practice for structural safety of buildings: Loading standards (revised)
12. IS-919-1963 : Recommendations for limits and fits for engineering (revised)
13. IS-961-1975 : Structural steel (high tensile) (second revision)
14. IS-962-1967 : Code of practice for architectural and building drawings (first revision)
15. IS-1024-1979 : Code of practice for use of welding in bridges and structures subject to dynamic loading (first revision)
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
16. IS-1030-1982 : Carbon steel castings for general engineering purposes (second revision)
17. IS-1148-1973 : Hot-rolled steel rivet bars (up to 40 mm diameter) for structural purposes (second revision)
18. IS-1149-1982 : High tensile steel rivet bars for structural purposes
19. IS-1261-1959 : Code of practice for seam welding in mild steel
20. IS-1278-1972 : Filler rods and wires for gas welding (second revision)
21. IS-1323-1962 : Code of practice for oxy- acetylene welding for structural work in mild steel (revised)
22. IS-1363-1967 : Black hexagon bolts, nuts and lock nuts (diameter 6 to 39 mm) and black hexagon screws (diameter 6 to 24 mm) (first revision)
23. IS-1364-1967 : Precision and semi-precision hexagon bolts, screws, nuts and lock nuts (diameter range 6 to 39 mm) (first revision)
24. IS-1367-1967 : Technical supply conditions for threaded fasteners (first revision)
25. IS-1393-1961 : Code of practice for training and testing of oxy-acetylene welders
26. IS-1395-1982 : Molybdenum and chromium molybdenum vanadium low alloy steel electrodes for metal arc welding (second revision)
27. IS-1477 : Code of practice for painting of ferrous metals in buildings: 1477 (Part 1)-1971 Part 1 Pretreatment (first revision)(Part 2)-1971 Part 2 Painting
28. IS-1929-1961 : Rivets for general purposes (12 to 48 mm diameter)
29. IS-1977-1975 : Structural steel (ordinary quality) (second revision)
30. IS-2062-1984 : Weld able structural steel (third revision)
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
31. IS-2155-1962 : Rivets for general purposes (below 12 mm diameter)
32. IS-3613-1974 : Acceptance tests for wire-flux combinations for submerged-arc welding of structural steels (first revision)
33. IS-3757-1972 : High-tensile friction grip bolts (first revision)
34. IS-4000-1967 : Code of practice for assembly of structural joints using high tensile friction grip fasteners
35. IS-5369-1975 : General requirements for plain washers and lock washers (first revision)
36. IS-5370-1969 : Plain washers with outside diameter 3 x inside diameter
37. IS-6419-1971 : Welding rods and bare electrodes for gas shielded arc welding of structural steel
38. IS-6623-1972 : High tensile friction grip nuts
39. IS-6649-1972 : High tensile friction grip washers
40. IS-7205-1974 : Safety code for erection of structural steel work
41. IS-7215-1974 : Tolerances for fabrication of steel structures
42. IS-7280-1974 : Bare wire electrodes for submerged arc welding of structural steels
43. IS-8500-1977 : Weld able structural steel (medium and high strength qualities)
1.2.1.7. GENERAL ITEMS CHECKLIST:
1. Concrete specifications Before placing concrete - tests, mix design, ingredients, inspections etc.
2. Testing laboratory Notified prior to pour, and testing is arranged at plant and site.
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
3. All areas to receive concrete Cleaned, wetted or otherwise prepared as required. Foundations are free of frost and water. Previously placed concrete is properly prepared to receive new.
4. Tools / vibrators: all necessary tools on hand are in working conditions. Vibrators and standby vibrators are available and in working condition.
5. Conveying/depositing equipment Capable of reaching all areas of placement without segregation, loss of ingredients, formation of air pockets or cold joints.
6. Manpower adequate Available for timely placement
7. Temporary form openings, chutes etc Provided.
8. Pockets Vented to prevent air entrapment.
9. Sub-base Compacted. Membrane is provided and installed as required.
10. Curing, sawed joints and protection Arrangements made.
11. Cube moulds and slump cone At site and samples are properly taken.
12. Standing time Time interval between adding water to concrete and placing in final position is known.
13. Delivery of concrete and sequence of delivery Scheduled to allow continuous placement to prevent cold joints.
14. Grout Added to columns/walls prior to placing concrete.
15. Layers Kept approximately horizontal.
16. Bolts and loose items to be embedded Properly located and installed.
17. Date and location of pours Recorded.
18. Checking during pouring Grades, elevations, alignment, form adjustment and supports
19. Vibration Performed properly, using correct equipment and forms are not damaged.
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
20. Adding water Approval required.
21. Cubes Cast and stored. Slump and other tests are performed as required.
FINISHING AND CURING
22. Type of finish on unformed surfaces Checked and provided as required (smooth, rubbed, broomed, nonslip, exposed aggregate, coloured etc).
23. Overtroweling To be avoided. (Troweling is not performed while bleed water is on surface).
24. Curing Started as soon as possible. Curing compounds are as required and compatible with subsequent finishes.
25. Finishing methods Provides evenness, smoothness, and levelness of surfaces within tolerance indicated. Slopes are provided to properly drain. Marks left by tools are removed.
26. Joints, edges and corners Carefully finished and/or match.
Table 1.2.1.7-A
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
METHOD STATEMENT FOR CONCRETING WORKS
OBJECTIVE: To formulate guideline for Mixing, Shifting & Placing of concrete
REFERENCE: 1. Technical Specification of Tender Document
2. "Released For Construction” Drawings 3. IS: 383 - Specification for coarse and fine aggregates from natural sources for concrete. 4. IS: 456-2000: Plain reinforced concrete - code of practice.
MATERIALS REQUIRED: Cement, aggregates, water & admixture
RESPONSIBILITY: QAQC Engineer, Site Engineer & Foreman
Sl. No.
ProcedureResponsibilit
yCheck By Records
1 Within the site area a batching plant shall be erected and
well calibrated, transit mixers shall be used for
transportation of concrete to the area of pour.
P & M
Engineer
QC Engineer
2 Review the condition and sufficiency of equipment for
mixing, transporting, placing, vibrating and
curing.specification
P & M
Engineer
QC Engineer
3 Adequacy supply / availability and suitability of
material, workmen in sufficient nos. shall be ensured
before the commencement of the work.
Admin
Officer / Const
Manager
QC Engineer
4 For concreting works two sets of immersion type
vibrator & needle assembly shall be used and adequate
numbers of needle (60mm / 40mm) shall be kept at
hand.
Site Engineer Section Head
5 Concrete shall be placed as near as possible to its final
location. It shall not be moved over long distances using
vibrator.
Site Engineer QC Engineer
(Random)
6 Whenever pumping of concrete is involved, checks are
to be made to ensure that the pipeline doesn’t disturb
any formwork while carrying concrete.
Site
Enginner /
Foreman
Formwork
Engineer/
Site
Engineer
7 Load the first TM with 0.5 cum slurry for buttering of
concrete pump and its pipeline. The slurry to be
disposed of the foundation area.
Site Engineer QC Engineer
8 The concrete pump shall be cleaned after concreting &
maintenance shall be carried out periodically.
P & M
Engineer
QC Engineer
(Random)
QUALITY PLAN FRAMING FOR CONCRETE
Table 1.2.1.7-B
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
Pro
jec
t:D
ate
:
28 d
ays
re
sult
s
LT
CD
Cli
en
tR
em
ark
sD
ate
of
Te
stin
gW
eig
ht
(gm
s)L
oa
d (
KN
)C
om
p.
Str
en
gth
(N
/mm
2)R
esu
lt
Da
teo
fC
ast
ing
Qu
ali
ty M
an
ag
em
en
t S
yste
m
QA
Co
ncr
ete
Cu
be
Tes
t R
epo
rt
Sr.
N
o.
Ite
ms
De
scri
pti
on
Siz
eo
fS
pe
cim
en
s (m
m)
Gra
de
of
Co
ncr
ete
Ide
nti
fica
tio
n
Ma
rk
QUALITY PLAN FRAMING FOR CONCRETE
QUALITY FORMAT(To be maintained by respective Site Engineers)PRE POUR INSPECTION CARD
Description Items / Check Required Actual Tolerance Remarks
A. Form work Fixing / bracing
Level +10 mm +10 mm Plumb + 3mm / 1m, max
20mm+ 3mm / 1m,
max 20mm Storey ht.
Cleanliness Free from foreign materials
Form oil application
Uniformly over the surface
Cutouts
Grout tightness
B. Reinforcement Position
No. & size
Anchorage
Spacing + 10mm Lapping + 10mm
Cover + 10mm – 2mm Cleanliness
Dowel bars
Links
Binding / welding
c. General 1.Embedments
2. Water Proofing
3. Construction Jt. Preparation
d. Finished Concrete
1. Dimensions +10 mm, -6mm2. Straightness
3. Flatness + 6mm / 1.5 m4.Plumb +3 mm / 1m
Site Engineer QA Engineer
Loose Bulk Density Quality Management
SystemSl No
Description Formula Test1 Test2
Test3
Remarks
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
1 Weight of the Bulk Density Cylinder (in gms)
A
2 Weight of theCyllinder + Material (in gms)
B
3 Weight of the Material (in gms) B-A
4 Volume of the Bulk Density Cylnder (in cc)
D
5 Bulk Density of the Material Sample (gms/cc)
(B-A)/D
Note: Average Loose Bulk Density of the material is
gms/cc
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
METHOD STATEMENT FOR FORMWORK WORKSOBJECTIVE: To formulate guidelines for moulding concrete to required shape, position in terms of level & dimension
REFERENCE: 1. Good for Construction Drawings 2. Technical Specifications of Tender Documents 3. Inspection and test plan LTCD/ITP/C-001 4. IS (Code) 456 : 2000
MATERIALS REQUIRED: Formwork materials including Staging.
RESPONSIBILITY: Site Engineer & Formwork Engineer/Foreman
Sl. No. Procedure Responsibility Check By Records
1 Analyse type of structures referring approved construction drawings & tender specification.
Form work Engineer Construction Manager
2 Plan materials requirements based on type of approved schemes, decide cycle time based on construction schedule of project, code of practice & tender specification
Form work Engineer Construction Manager
S6A
3 Receive construction drawings & prepare formwork scheme drawings considering technical specifications, supporting system, tying system.
Form work Engineer Regional Form work Co-ordinator
Scheme Drawings
4 For precasting, fabricate as per approved scheme drawings & proper positioning the same during execution.
Foreman Formwork Engineer/ Site
Engineer5 Clean Formwork free from saw dust & any other
foreign materials.Foreman Formwork
Engineer6 Apply releasing agent for formwork ( ply/Steel) before
using the same at site.Foreman Formwork
Engineer7 Check level, line, shape, tightness of formwork Foreman / Site
EngineerQA Engineer (Random)
Check List
8 Check the dimensions after concrete Foreman / Site Engineer
QA Engineer (Random)
Check List
9 Plan deshuttering system/ method in order to avoid damages of concrete.
Foreman Formwork Engineer
10 Deshuttering formwork considering stripping time as per specification.
Foreman Formwork Engineer/ Site
Engineer11 Slab deshuttering shall be done after checking the
cube strength of concreteSite Engineer QC Engineer /
Formwork Engineer
12 Clearance of Pour Before Concreting Site Engineer Client (Random)
13 For construction safety please refer to Safe Work Methods for Formwork in Project HSE Plan
Site Engineer -
ACCEPTANCE CRITERIA:1 Tolerance for cross sectional dimensions of cast in situ & precast elements- +12mm/-6mm2 Tolerance for footing
dimension in plan +50mm/-12mmeccentricity
thickness + 0.05 times thespecified thickness
3 Tolerance for length of the precast elements - upto 3ms +6mm
-3m to 4.5m: ±9mm
-Additional deviation for every subsequent 6m: ±12mm
4 Tolerance for plumb 3mm/m or 20 mm
5 Tolerance for level of the cast in situ elements +10mm
0.02 times the width of the footing in the direction of deviation but not more than 50mm
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
METHOD STATEMENT FOR REINFORCEMENT WORKSOBJECTIVE: To formulate guidelines for cutting, bending & tying of reinforcement.
REFERENCE: 1. Good for Construction Drawings 2. Technical Specifications of Tender Documents 3. Inspection and test plan LTCD/ITP/C-001 4. IS : 2502-1963: Code of Practice for Bending & Fixing of bars for concrete reinforcement.
Sl. No. Procedure Responsibility Check By Records
A Reinforcement Handling1 Receive Reinforcement along with MTC & submit to
the client if requiredStores In-Charge Reinforcement
EngineerMTC
2 Check the quantity of Reinforcement corresponding to the weigh slip,transport & unload the same at reinforcement yard
Stores In-Charge -
3 Hand Gloves & other Protective equipments shall be used while handling reinforcement
Reinforcement Engineer
Safety Co-ordinator
4 Unusable cut rods & scrap reinforcement shall be transferred to a well identified scrap yard.
Reinforcement Engineer
-
B Bar Bending schedule1 BBS shall be prepared based on the latest GFC
DrawingsSite Engineer/ Section Head
Reinforcement Engineer/ Client
BBS
2 BBS shall specify bar marks, bar dia, number of bars, shape, cut length, bends & shape etc as per GFC Drawing.
Site Engineer/ Section Head
Reinforcement Engineer/ Client BBS
3 BBS shall specify lap lengths, their location and staggering of laps. It shall take into account the Development length/ Anchorage Length.
Site Engineer/ Section Head
Reinforcement Engineer/ Client BBS
C Bar Cutting, Bending & Placing1 Rebar shall be clean & free from rust, mud & oil. Site Engineer QA Engineer /
Client (Random)Check List
2 The details like Bar Spacing, cranks, hooks & their location shall be in commensuration with the GFC drawings
Site Engineer / Reinforcement
Engineer
QA Engineer / Client (Random) Check List
3 Gauge of the Binding wire shall be 16-20 SWG (1 to 1.6 mm) annealed steel wire
Reinforcement Engineer
-
4 The Number of chairs, spacers & cover blocks shall be adequate
Site Engineer QA Engineer / Client (Random)
Check List / BBS
5 In walls place accurately bent spacer bars wired to vertical or horizontal bars between successive rows.
Site Engineer
D Clearnace of Pour Before Concreting Site Engineer Client (Random)
Check List
E For Construction safety Please refer to Safe Work Methods for Reinforcement in Project HSE Plan
Site Engineer -
ACCEPTANCE CRITERIA:1 Reinforcement shall be placed in the following tolerences:
For effective depth< 200mm tolerence in spacing +10mm
For effective depth > 200 mm tollerence in spacing +15mm
2 Provision to Cover to Reinforcement shall be +10mm / -2 mm from specified.
RESPONSIILITY: Site Engineer, Reinforcement Engineer & Stores Incharge
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
METHOD STATEMENT FOR REINFORCEMENT WORKS
OBJECTIVE: To formulate guidelines for cutting, bending & tying of reinforcement.
REFERENCE: 1. Good for Construction Drawings 2. Technical Specifications of Tender Documents 3. Inspection and test plan LTCD/ITP/C-001 4. IS : 2502-1963: Code of Practice for Bending & Fixing of bars for concrete reinforcement.
RESPONSIILITY: Site Engineer, Reinforcement Engineer & Stores Incharge
Sl. No.
Procedure Responsibility Check By Records
A Reinforcement Handling1 Receive Reinforcement along with MTC &
submit to the client if requiredStores In-Charge
Reinforcement Engineer
MTC
2 Check the quantity of Reinforcement corresponding to the weigh slip,transport & unload the same at reinforcement yard
Stores In-Charge
-
3 Hand Gloves & other Protective equipments shall be used while handling reinforcement
Reinforcement Engineer
Safety Co-ordinator
4 Unusable cut rods & scrap reinforcement shall be transferred to a well identified scrap yard.
Reinforcement Engineer
-
B Bar Bending schedule1 BBS shall be prepared based on the latest
GFC DrawingsSite Engineer/ Section Head
Reinforcement Engineer/ Client
BBS
2 BBS shall specify bar marks, bar dia, number of bars, shape, cut length, bends & shape etc as per GFC Drawing.
Site Engineer/ Section Head
Reinforcement Engineer/ Client
BBS
3 BBS shall specify lap lengths, their location and staggering of laps. It shall take into account the Development length/ Anchorage Length.
Site Engineer/ Section Head
Reinforcement Engineer/ Client
BBS
C Bar Cutting, Bending & Placing1 Rebar shall be clean & free from rust, mud
& oil.Site Engineer QA
Engineer / Check List
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
Client (Random)
2 The details like Bar Spacing, cranks, hooks & their location shall be in commensuration with the GFC drawings
Site Engineer / Reinforcement Engineer
QA Engineer / Client (Random)
Check List
3 Gauge of the Binding wire shall be 16-20 SWG (1 to 1.6 mm) annealed steel wire
Reinforcement Engineer
-
4 The Number of chairs, spacers & cover blocks shall be adequate
Site Engineer QA Engineer / Client (Random)
Check List / BBS
5 In walls place accurately bent spacer bars wired to vertical or horizontal bars between successive rows.
Site Engineer
D Clearnace of Pour Before Concreting Site Engineer Client (Random)
Check List
E For Construction safety Please refer to Safe Work Methods for Reinforcement in Project HSE Plan
Site Engineer -
ACCEPTANCE CRITERIA:1 Reinforcement shall be placed in the following tolerances:
For effective depth< 200mm tolerance in spacing +10mm For effective depth > 200 mm tolerance in spacing +15mm
2 Provision to Cover to Reinforcement shall be +10mm / -2 mm from specified.
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
Testing of Concrete Quality Management System
Brand of Cement:- Date:-
Suppling Batch No:-
Physical Properties :-
Normal Consitency Initial Setting Time Final Setting Time28 Day Cube Strenth
3 Days 7 Days 28 Days
Average Compressive StrengthTable 1.2.1.7-C
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
Impact Value Test
Project :
Material : Date:Sr. No.
Description Unit Wt Remarks
1 Total Weight of Aggregate taken gms
2 Weight of aggregates passing through 12.5 mm & retained on 10mm IS Sieves.
gms
3 Weight of the mould 1 (A) gms
4 Weight of the mould 1 + aggregate sample (B) gms
5 Weight of the aggregate sample (B-A) gms
6 Weight of the material passing through 2.36mm IS Sieve. ( C)
gms
7 Impact Value of aggregate (C / (B-A)) gms
Remarks:Table 1.2.1.7-D
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
3. SIZE OF AGGREGATE :
1 63 50
2 50 40
3 40 31.5
4 31.5 25
5 25 20
6 20 16
7 16 12.5
8 12.5 10
9 10 6.3
TOTAL
Quality Management systemELONGATION INDEX
Elongation INDEX :
No of particles passing through Elongation gauge
(X1*Y1)/100
2. SOURCE / QUARRY :
Total Weihght of Particles
% of weight of particles to the total wt taken
(Y1)
PASSING THROUGH
SIEVE (MM)
RETAINED ON
SIEVE (MM)
No of particles retained on Elongation
Gauge
TOTALSL NO
SIZE OF AGGREGATE NO. OF PARTICLES % of Nos of particles retained
on Gauge (X1) (%)
Date
4. TOTAL WEIGHT OF SAMPLE :
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
Date:-
4. TOTAL WEIGHT OF SAMPLE :
X1 (%)
(%) X1 x Y1
100
1 63 50
2 50 40
3 40 31.5
4 31.5 25
5 25 20
6 20 16
7 16 12.5
8 12.5 10
9 10 6.3
TOTAL
RETAINED ON Flakiness Gauge
TOTAL
SIZE OF AGGREGATE NO. OF PARTICLES
Quality Management System
FLAKINESS INDEX :
3. SIZE OF AGGREGATE :
WEIGHT OF PARTICLES
SL NO
2. SOURCE / QUARRY :
FLAKINESS INDEX
(%)of Wt of Particles to the total wt taken
PASSING THROUGH
SIEVE (MM)
RETAINED ON
SIEVE (MM)
PASSING THROUGH
Flakiness Gauge
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
Sieve Analysis of 20mm AggregatesQuality Management
System
Project:
Source of Material: Date:
Weight of the Sample:
Sl NoSize Of IS
Seive in mm
Retained Weight (gms)
Cum. Weight retained
(gms)
Cummulative % Weight Retained % Passing
As Per IS 383 Remarks
1 40 100
2 2085-100
3 10 0-20
4 4.75 0-5
5 Pan 0Table 1.2.1.7-E
Sieve Analysis of 10mm AggregateQuality Management
SystemProject:
Source of Material: Date:
Weight of the Sample:
Sl No
Size Of IS Seive in
mm
Retained Weight (gms)
% Weight retained
Cummulative % Weight Retained % Passing
As Per IS 383 Remarks
1 12.5 100
2 10 85-100
3 4.75 0-20
4 2.36 0-5
5 Pan 0Table 1.2.1.7-F
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
Quality Management System
Sieve Analysis of SandProject:
Source of Material : Date:
Weight of the Sample:
Sl No
Size Of IS
Seive in mm
Retained Weight (gms)
% Weight retained
Cummulative % Weight Retained
% Passing
As Per IS 383
(Zone II)Remarks
1 10 100
2 4.75 90-100
3 2.36 75-100
4 1.18 55-90
5 0.6 35-59
6 0.3 8-30
7 0.15 0-10
8 PanTable 1.2.1.7-G
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
Silt Content in SandQuality
Management System
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
Project : Date:
Material:
Source:
Sl No Description Formula Test1 Test2 Test3 Remarks
1Level of sand in measuring jar A
2
Level of sand & water in measuring jar B
3
Observation of silt level after full settlement C
4 Silt Content (%)C * 100 /
AAverage Silt content percent in sand
Table 1.2.1.7-H
Specific Gravity of Aggregate Quality Management System
Project :
Material: Date:
Source:
Sl No Description Formula Test1Remark
s
1Weight of the Empty Pycnometer (in gms) A
2Weight of the Pycnometer filled with Material (in gms) B
3Weight of the Pycnometer filled with Material & Water(in gms) C
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III
QUALITY PLAN FRAMING FOR CONCRETE
4Weight of the Pycnometer & Water(in gms) D
5 Weight of the dry sample (in gms) E
6 Specific Gravity(B-A) / [ (C-B)-(D-
A) ]
6 Water Absorption (%) E * 100 / (B-A)Table 1.2.1.7-I
Project :
Material:
Source:
Sl No Test1 Test2 Test3
1
2
3
4
5
Note: Average Loose Bulk Density of the material is
Quality Management SystemLoose Bulk Density
Date:
Bulk Density of the Material Sample (gms/cc) (B-A)/D
Weight of the Material (in gms)
Description Formula Remarks
Weight of the Bulk Density Cylinder (in gms) A
B-A
Weight of theCyllinder + Material (in gms) B
gms/cc
Volume of the Bulk Density Cylnder (in cc) D
CHANDAN, HARI OM, PRASHANSA, SHASHANK, VIDHYAGROUP-III