Qafco V Steering a Major Fertilizer Project to Completion

Gianluca AliottaCommercial Development Manager

Gas MonetizationSaipem S.p.A.

e-mail: [email protected]

Page 2: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion 2

Table of Contents

Introduction

Scope of Work

Technology Scheme & Design Approach

Contractual Scheme & Execution Approach

Page 3: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion 3

Saipem – Leadership in the Fertiliser Sector Trend on Highest Capacity Ammonia/Urea Complexes

Design 3250 T/DRecord 3719 T/D

Profertil, Argentina

Single Train

EPCIn operation since 2000

Single Train

Engro, PakistanQafco 5 & 6, QatarMatix, India

Design 3850 T/D Revamp Target 4200 T/D

Profertil, Argentina

EPC & EPCSFirst Start-up 2010

Fertinitro, VenezuelaOmifco, Oman

Two Trains

Design Fertinitro 2x2200 T/DDesign Omifco 2x2530 T/D

EPCIn operation since 2001In operation since 2005

Snamprogetti™ 5000+ T/D

Snamprogetti™5000+ T/D

Same performancewith one train

as two world’s largesttwo trains complexwith many savings

Design ready, based on well proven process lay-out scheme as well as proven and referenced design for all major critical machines and equipments

Introduction

Page 4: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion 4

Ammonia & Urea World Scale Project Location: Mesaieed, Qatar

Existing Qafco’s PlantsQafco5 + Qafco 6 plants area

Introduction

Page 5: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion 5

Project Scope of Work

Process UnitsAmmonia 2 x 2300 (MTPD)

Urea Synthesis 1 x 3850 (MTPD)

Urea Granulation 1 x 3850 (MTPD)

UF85 1 x 85 (MTPD)

U&OsPower & Steam Generation 200 (MVA) / 840 (T/H)

SW / CW 125,000 (M3/H) / 64,000 (M3/H)

Potable water 36 (M3/H)

BFW 840 (M3/H)

Desalination Water 225 (M3/H)

Plant Instrument air 10,390 (NM3/H)

Page 6: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion 6

Project Scope of Work

U&OsSolid Urea Storage 1 x 100,000 (MT)

Solid Urea Handling Facilities 1 x 1000 (MTPH)

Liquid Ammonia Storage & Pumping Facilities 2 x 50,000 (MT)

Ammonia Loading System 1 x 1000 (MTPH)

Extension of the existing berth of Jetty no 1 5,000 to 70,000 (DWT)

Page 7: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion

2 Ammonia Plants

1 Urea Plant

Cogen2 Plant

Sea Water Cooling Unit Urea bulk Hall

Project Scope of Work

7

QAFCO-V Site

Page 8: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion

Ammonia Storage

Cogen 1

Jetty Expansion

Project Scope of Work

8

QAFCO Existing Facilities Site

Page 9: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion 9

Project Scope of Work

Description U/m Quantity

Buildings Nr. 12

Earth Movement m3 2.250.000

R.C. Concrete m3 120.000

Concrete Paving m2 163.000

Piping Tons 23.200

Steel Structures Tons 33.000

Equipment/Packages Tons 54.000

Electrical Cables km 2.850

Instrument Cables km 3.660

Insulation m2 262.000

Painting m2 713.000

MAIN QUANTITIES

Page 10: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion 10

AMMONIA: HALDOR TOPSOE A/S

UREA: SNAMPROGETTITM

GRANULATION: UFT

UF85: PERSTOP

Technology Scheme & Design Approach

10

Page 11: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion 11

Technology Scheme & Design Approach

Haldor Topsoe A/S Ammonia Process

Page 12: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion 12

CARBONDIOXIDE

VACUUMSYSTEM

WWT

TO LP SECTION

FEED

PC AS BFW

AMMONIA UREASOLUTION

HIGH PRESSURE SECTION LOW PRESSURE SECTIONMEDIUM PRESSURE SECTION VACUUM SECTION

WASTE WATER TREATMENT SECTION

Technology Scheme & Design Approach

SnamprogettiTM Urea Process

Page 13: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion 13

UFT Granulation Process

Technology Scheme & Design Approach

Page 14: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion 14

Contractual SoW EPCC

Contractual Mode LSTK

Awarded to Saipem / HDEC(as Consortium)

Consortium’s Leader Saipem

Contractual Scheme & Execution Approach

Page 15: Qafco Process 1

Qafco V – Steering a Major Fertilizer Complex to Completion 15

Contractual Scheme & Execution Approach

Activity by

License & Basic Engineering Design

SaipemDetailed Engineering

Procurement

Construction HDEC

Commissioning & Start-up Saipem