pxie lebt commissioning...

22
PXIE LEBT Commissioning Update Lionel Prost on behalf of, R. Andrews, K. Carlson, J.-P. Carneiro, R. D’Arcy, F.G. Garcia, B. Hanna, M. Kucera, A. Saewert, G. Saewert, V. Scarpine, A. Shemyakin, D. Snee, mechanical, electrical and other technical support PIP-II Technical Meeting June 23 rd , 2015

Upload: lynhi

Post on 26-Aug-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

PXIE LEBT Commissioning Update

Lionel Prost on behalf of, R. Andrews, K. Carlson, J.-P. Carneiro, R.

D’Arcy, F.G. Garcia, B. Hanna, M. Kucera, A. Saewert, G. Saewert, V. Scarpine, A. Shemyakin, D. Snee, mechanical,

electrical and other technical support

PIP-II Technical Meeting

June 23rd, 2015

Status summary

• Ready to inject beam into the RFQ• After the current shutdown, the beam line as intended for

FY15 will be complete Design of the bend has started

• Continued beam characterization in different modes of operation Ion source tunes

• Preparation for commissioning MULT, measurements procedures…

• Attempts to improve stability Turn on procedure, regulation loops…

2

Beam line configuration(April 15- June 2)

• LEBT scraper installed April 1st

Emittance scanner (not shown) added ~2 weeks later (end of the beam line)

• Emittance scanner moved to IS vacuum chamber June 9

3

DCCT

Collimator

Chopper

MEBT scrapers(C. Baffes, K. Kendziora) LEBT

scraper

Faraday Cup

Water-cooled donut

T. Hamerla

Ion Source

• Movable isolated electrode with holes Beam measurements and RFQ protection

LEBT ‘scraper’

4

LEBT/RFQ Interface flange

Up/down motion with stepper motor

Scraping edge

Pencil beam aperture

Regular aperture

T. Hamerla

Example of profile measurements with LEBT scraper

• LEBT scraper moved over the full range of motion

5

5-mm hole 14-mm hole D-shape hole (edge)

LEB

T sc

rape

r cur

rent

read

bac

k, m

A

mm

Different traces correspond to different vertical displacements of the beam with the Solenoid #3 correctors

Introductory comment

• The beam line configuration shown previously (i.e. with the LEBT scraper installed) does not allow reliable measurements of the beam with the emittance scanner for nominal settings for the RFQ Beam is too large and too diverging

Scraping on emittance scanner ‘clearing electrode’ Emittance scanner range of motion not enough to capture the entire

beam for ‘matched’ conditions

6

Long runs

• Four instances when the beam was left running over the weekend Monitoring from MCR crews No beam interruption all 4 times

Pulsed operation (low duty factor) With studies taking place before and/or after the ‘long runs’, the

beam typically stayed on for more than 80 hours continuously Filament > 700 hours since last change out !!

• Twiss parameters not constant throughout but varied less than from day-to-day operation 10-20% vs. 2-3× (← worst case scenario) Have not established feedback procedure (yet)

Will attempt to use the LEBT scraper current read back

7

1.7

1.8

1.9

2

2.1

2.2

2.3

2.4

2.5

2.6

‐9.5 ‐9 ‐8.5 ‐8 ‐7.5 ‐7

, m

Long runs vs. Day-to-day

• 5 mA, 1.5 ms IS pulse chopped down to 50 s 1 msafter the start of the IS pulse, 60 Hz EID #1 & #2 at +40 V LEBT scraper &

donut at +50 V Kicker plate at -300V

Sol. #1- #3: 143 A,158 A, 240 A

Beam trajectoryand/or LEBT scraperposition may not beidentical for all datapoints

8

May 8-11 run

May 15-18 run

May 8-29 data

Beam current regulation

9

• Finite State Machine (FSM) adjusts the extraction electrode voltage in order to keep the current read backfrom the DCCT constant

• Does not seem to have anydramatic effect on the beamTwiss parameters stability(positive or negative)• Sensitivity of the beam

parameters to the extractionvoltage is differentdepending on where thenominal voltage lies on theIBeam vs. Vextr. curve (a.k.a.extraction curve)

H2 flow @ HV H2 flow @

ground

0.5 sccm0.5 sccm

0.025 kV0.2 mA

DCCT

Extraction electrode

May 15-18

Summary on beam stability

• Turning on the gas several hours before establishing beam helps maintaining both the beam current and, to a lesser extent, the Twiss parameters more constant Part of the beam parameters variations are likely related to the

gas delivery ‘dynamics’

• Keeping the beam running reduces the variations of the beam parameters In particular, the relatively large variations seen the first few

hours after turning on On the other hand, the beam current regulation loop did not

prevent the beam parameters to wander

10

Position and angle bump MULTs for RFQ transmission tuning

• Using TRACK, Jean-Paul created position & angle bumps “Correctors in solenoidal field” model to take into account the

rotation from solenoid focusing field Accuracy: ~10%

Within measurements errors

• For tuning with RFQ: Center the beam in LEBT

scraper hole, then changethe angle without changingthe position to maximizetransmission

11

y = 0.9733x ‐ 0.198R² = 0.9999

‐6

‐4

‐2

0

2

4

6

‐6 ‐4 ‐2 0 2 4 6

x meas., m

m

x calc., mm

Data from phase space measurements

E.g.: Horizontal MULT

05/28/15

Beam size vs. Solenoid #1 current vs. extraction voltage

• Characterized different IS tunes Acquired data for fine tuning and support optimization of the

beam line with theRFQ

Two families ofcurves: Low side of

the extractionvoltage ‘spread out’

High side of theextractionvoltage ~overlap

12

Beam Size measured with the right MEBT scrapers as a function of Solenoid #1 current for different extraction voltage at the ion source

Started measurements with emittance scanner in the IS vacuum chamber

• Neutralization (or lack thereof) may be very different from normal operation when doing the measurements at this location Measurements of

the first few sshould helpdeterminehow importantit may be

13

Current shutdown

• Final configuration before RFQ commissioning Remove MEBT scrapers Install beam stop and vacuum valve Improve alignment of EDI #2 and LEBT scraper

Misalignment of EID #2 determined with beam measurements Replace LEBT scraper bracket, which had to be shimmed

14

Before the RFQ delivery

15

• Test beam stop

• Test Machine Protection System Most hardware has been installed and it is almost ready to go Quite rudimentary at first but designed to be built upon

• Test beam size feedback loop FSM is ready

• Long run in DC mode• Continue measurement of the ion source with the

emittance scanner Possible input for better simulations

Cut-off date for running the LEBT

• July 17, 2015 ~2 weeks before RFQ scheduled delivery for prep work in the

cave E.g.: move cable trays, racks…

Turn off could take place any time once we have verified beam operation following this shutdown Will take more time for measurements if given to us… i.e. RFQ

delivery delays

16

17

Additional slides

Role of LEBT in PXIE

• Prepare beam for RFQ (i.e. , ) and machine protection• DC operation

5 mA, reliable and ‘stable’ n,rms ≤ 0.18 mm mrad

Uncontrolled losses <10%

• Pulse operation 1-16667 s, 60 Hz Twiss functions representative of DC beam operation

To transition from short pulse (commissioning) to DC (normal operation) If not the same, DC Twiss functions should be predictable from short pulse

measurements

18

Beam dumpHEBTMEBTRFQLEBTIon

Source HW & SSR1

LEBT scraper pictures

19

Beam current regulation

20

• Finite State Machine (FSM) adjusts the extraction electrode voltage in order to keep the current read backfrom the DCCT constant

H2 flow @ HV H2 flow @

ground

0.5 sccm0.5 sccm

0.025 kV0.2 mA

DCCT

Extraction electrode

May 15-18

Donut

0.5 mA0.1 mA0.6 mA0.4 mA

FCLEBT scraper

DCCT

Last MEBTscrapers move

May 8-11

Beam sensitivity to H2 flow

• Part of the beam parameters variations are likely related to the gas delivery ‘dynamics’ Turning on the gas several hours

before establishing beam helpsmaintaining both the beamcurrent and, to a lesser extent,the Twiss parameters moreconstant The filament does not need

to be on i.e. not a thermaleffect

21

10-5 torr10-6 torr0.5 sccm

H2 flow

IS US IG

IS DS IG

~5 h

Reminder: Ion source tunes

• Electrodes near the extraction region determine not only the extraction current but also the current density distribution And, to some extent the

Twiss parameters andemittance

22

Several currents vs. extraction voltageFaraday cupIsolated diaphragm #1DonutDCCT

4.5 mA

‘Low side’ ‘High side’

5 kV