purpa resurgence and avoided costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000...

38
Copyright © 2019 The Brattle Group, Inc. PURPA Resurgence and Avoided Costs PRESENTED TO EUCI Symposium PRESENTED BY Metin Celebi September 9, 2019

Upload: others

Post on 24-Sep-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

Copyright © 2019 The Brattle Group, Inc.

PURPA Resurgence and

Avoided Costs

PRESENTED TO

EUCI Symposium

PRESENTED BY

Metin Celebi

September 9, 2019

Page 2: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 2

Agenda

PURPA Evolution

Changing Mix of Qualifying Facilities

New Challenges in Avoided Cost Calculation

QF Contracting and Competitive Procurement

Page 3: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 3

Background – The Basics

PURPA enacted in 1978 to encourage conservation and small generation facilities

Goal to achieve level playing field with QF sales at incremental cost of alternatives

“Unique federalism” calls for state implementation under FERC guidelines

Rationing by price, not quantity

Plus eligibility/ contract issues:

– Effective scale thresholds

– Contract length/ price structure

– Environmental attributes

– Integration costs

– Dispatchability

– Risk sharing

Has required recurring “but-for” analysis of Avoided Costs, including:

– Next planned (proxy) unit

– Marginal CT capacity and energy

– Comparative system-wide costs

– Fuel Index Rates

With alternative of Auction/ RFP process

Page 4: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 4

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

19

78

19

80

19

82

19

84

19

86

19

88

19

90

19

92

19

94

19

96

19

98

20

00

20

02

20

04

20

06

20

08

20

10

20

12

20

14

20

16

20

18

TWh

Renewables (Non-Hydro)

Hydro

Other

Nuclear

Natural Gas

Oil

Coal

Changing Fundamentals and Policy Goals

1978… and Now

Conservation imperative Climate change imperative

Strong electricity demand Weak load growth

Utility dominance Extensive generation deregulation

Electricity Net Generation

Page 5: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 5

EPAct of 2005

EPAct in 2005 modified the “must purchase” obligation for QFs

This applied to QFs with non-discriminatory access to competitive markets

FERC created a rebuttable presumption to this effect for QFs larger than 20 MW in:

− PJM− Midwest ISO− ISO-NE− NYISO− ERCOT

The full PURPA mandatary purchase continues in the non-RTO West and Southeast

Page 6: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 6

New Technologies, But Old Issues

1. Administratively set avoided costs

Administratively set long-term avoided costs have diverged from actual fuel and capital costs, load growth and technology originally expected to offset

In practice, actual costs have continually dropped below long-term estimates

2. Rationing QF procurement by price

QFs customarily “rationed” based on price, not on quantity

This often led to over-subscription (example of Standard Offer 4 in the 1980s)

Now renewables are price competitive, while load growth stalls

3. Equitable risk sharing under PPAs

FERC supports “reasonable opportunities to attract capital”, but does not define

In the early implementation of PURPA, that could mean life-of-asset PPAs

In changed circumstances, long-term PPAs may no longer be equitable

Page 7: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 7

Push-Back From Some States

States in non-RTO regions:

WestArizonaColoradoIdahoMontanaNevadaNew MexicoOregonUtahWashingtonWyoming

SoutheastAlabamaFloridaGeorgiaKentuckyNorth CarolinaSouth Carolina

Individual states are on the front line, since PURPA leaves them much latitude.

In July 2017, HB 589 codified a PURPA alternative in North Carolina.

Colorado has effectively folded PURPA obligations into state IRP process.

Idaho introduced 2-yr limit to QF contracting.

Regulators in Utah and Montana, and utilities in Arizona have sought shorter QF PPAs.

Page 8: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 8

Recent Federal Actions

FERC held a technical conference to reexamine PURPA in 2016

As a result of the conference, FERC invited comments on:

− Minimum standards for PURPA purchase contracts and

− Potential gaming of the “one-mile” rule.

Numerous utilities and IPPs have weighed in, as well as the NARUC.

Comments remain under consideration by FERC.

The House Energy and Commerce Committee held PURPA hearings:

− September 2017, January 2018

H.R. 4476, the PURPA Modernization Act of 2017, calls for:

− Limiting mandatory purchase obligation if

− Competitive procurement

− No need for capacity

− QFs larger than 2.5 MW

− Tightening one-mile rule.

− H.R. 1502 in 2019 calls for similar amendments

Page 9: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 9

Key Issues Going Forward

Workable Targets for QF Supply More Critical

– Load growth has stalled since PURPA inception

– QFs may form excess capacity, not just displace new-build

– NC targets fixed amount of procurement

– Still need to reconcile negotiation and system needs

– Forecasting avoided cost drivers has always been difficult

– Complicated by effects of renewables penetration

– NC and MI partially sidestepped via competitive procurement

– But avoided cost still needed to establish ceiling prices

– PPA terms interactive with avoided costs and QF economics

– QF cost advantages may in some cases warrant shorter PPAs

– NC and MI addresses indirectly, through competitive bidding

– A different issue where long-term avoided costs remain

Estimating Avoided Cost Has More Moving Parts

Risk Sharing Parameters are Changing

Page 10: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 10

Changing Mix of

Qualifying Facilities

Page 11: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 11

Recent Dominance of Renewables

PURPA has a new role as vehicle for renewables (at least for now)

Growth in QF facilities over the last 10 + years has come entirely from renewables

Historical QF Capacity

Source: Velocity Suite, ABB Inc. (2019)

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

19

99

20

00

20

01

20

02

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

Ne

t Su

mm

er

Cap

acit

y (M

W)

Solar

Wind

Thermal

Page 12: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 12

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

QFs Have Contributed Importantly to Historic Renewables Development

But form a much smaller part of overall renewables development today…

Source: Velocity Suite, ABB Inc. (2019)

QF Share of Total U.S. Renewable Capacity Cumulative QF Capacity

0

10

20

30

40

50

60

70

80

90

100

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

GW

CA

TX

NYNJ

LANC

MI

Rest of U.S.

Page 13: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 13

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

RT

O

No

n-R

TO

MW

of

Cap

acit

y

Existing QF Capacity

Other

Natural Gas

Wind

Solar

Current QF Demographics

Operating inventory of 90,000 MW:

Remain mostly thermal (gas, biomass, etc.)

Mostly in RTO regions (much pre-1990s)

Most renewables came online in last ten years

24,000 MW under development:

Dominated by renewables (mostly solar PV)

Mostly in non-RTO regions

Source: Velocity Suite, ABB Inc. (2019)

0

5,000

10,000

15,000

20,000

25,000

30,000

RT

O

No

n-R

TO

MW

of

Cap

acit

y

QF Capacity in Development

Other

Natural Gas

Wind

Solar

Page 14: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 14

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

Sou

thC

aro

lina

No

rth

Ca

rolin

a

Ore

gon

Mic

hig

an

Mo

nta

na

Co

lora

do

Flo

rid

a

Uta

h

Wyo

min

g

Geo

rgia

Ala

ba

ma

Re

st o

f U

S

MW

of C

ap

aci

ty

QF Capacity in Development (by State)

Other

Natural Gas

Wind

Solar

Current QF Demographics (cont’d)

QFs under development are geographically concentrated:

South Carolina 6.9 GW North Carolina 5.3 GW Oregon 3.6 GW Michigan 2.5 GW Montana 2.2 GW Colorado 2.1 GW Florida 1.6 GW

Solar projects make up the majority of QF capacity under development

High insolation, largely non-RTO states

Mix of RPS requirements and potentially reinforcing local incentives

Source: Velocity Suite, ABB Inc. (2019)

Page 15: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 15

Changes in Solar PV Cost and Avoided CostNational Average

EIA estimates solar PV levelized cost (LCOE) at parity with avoided costs on average.

The U.S. average levelized cost of new solar PV units approached reported avoided costs of $45/MWh in 2021.

Recent solar PPAs as low as $20/MWh.

Estimates for New Solar PV Costs vs. Avoided Costs

Source: EIA (https://www.eia.gov/outlooks/aeo/electricity_generation.php).

$0

$20

$40

$60

$80

$100

$120

$140

$160

AEO2013 AEO2015 AEO2017 AEO2019

2018

$/M

Wh

Cost w/ subsidy Avoided Cost

Page 16: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 16

Changes in Solar PV Cost and Avoided CostRegional

Solar PV LCOE is lower than levelized avoided cost in some (high-insolation) regions

Substantial overlap with non-RTO regions

New Solar PV Economics by Region (LCOE Minus LACE)

Source: EIA.

-$50

$0

$50

$100

$150

20

18

$/M

Wh

AEO 2013

AEO 2015

AEO 2017

AEO 2019

ERCO

T

MR

O

NP

CC

RFC

SE

RC

SPP

WEC

C

FRC

C

Page 17: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 17

New Challenges in

Avoided Cost

Calculation

Page 18: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 18

Determining Avoided Cost Historically An Administrative Process

Theoretic controversy over methods, ex ante and ex post.

Practical outcomes:

– Over-abundance of offered QF supply in some regions.

– Departure from actual costs.

– Associated operating and planning problems.

Page 19: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 19

Pros and Cons of “but-for” Analyses

Method

– Next planned unit

– Marginal capacity and energy (“peaker”)

– Comparative system-wide costs

– Fuel index rates

Pros

No modeling

Captures marginal cost

Comprehensive

Transparency

Cons

Scale/ timing mismatch

May require modeling

Requires extensive modeling

Doesn’t capture capacity value

Page 20: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 20

Some Hazards in Avoided Cost Estimates

Long-term forecasting of avoided costs typically suffer from:

▀ Difficulties in estimating the impact of increasing and uncertain amount of

renewable QF penetration in the region on avoided costs, which may result in:

− Overstated avoided energy costs

− Inaccurate estimate for the timing of capacity needs in the future

▀ (in)ability to deduct renewable integration costs for increasing amounts of

“must-take” renewable QF power

▀ Failure to consider avoidable power purchases that could be cheaper than

running utility generation

Page 21: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 21

Past Events of Over Supply

Early California experience a harbinger of today’s challenges.

Standard Offer 4 (SO4) in the 1980s:

– Fixed energy payments for 10 years and capacity payments for up to 30.

– Oil and natural gas prices were high and forecast to grow.

– No cap on potentially eligible QF capacity.

After fostering a huge amount of QF capacity, SO4 was suspended in 1985.

This was repeated elsewhere in the country.

LBNL reported capacity offered by QFs 10-20 times required amounts.

Page 22: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 22

QF Contracting and

Competitive

Procurement

Page 23: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 23

Key Drivers of Solar QF Development

Cost of new solar PV lower than avoided cost of energy and capacity

▀ E.g., Carolinas, Oregon, Utah, Colorado, Montana, Florida, Virginia and California

State/utility policies on QF contracting (duration, pricing, size restrictions, etc.)

▀ Relatively high avoided cost estimates and long contract lengths have attracted developers to these states

▀ Almost all of these states are in non-RTO regions

State policies for new renewables (RPS/carve-out, tax incentives, permitting process)

▀ Most of these states have renewable portfolio standards/goals along with other policies aimed at incentivizing utility-scale solar development

Page 24: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 24

States with High Solar QF Development

State Planned QF Solar Capacity

(MW)

AvoidedCost

Rates($/MWh)

MaxContract

Term(years)

MaxContractCapacity

(MW)

Emerging QF Policies RPSPolicy

SolarCarve-

Out

Other Relevant State Incentives

& Policies

South Carolina

6,874 On: $34-$88Off: $32-$41

10 0.1 - 2 Energy Freedom Act signed into law in May 2019; directs utilities to offer minimum contract length of 10 years

2% by 2021

— —

NorthCarolina

5,201 On: $44-$53Off: $25-$34

10 1 2017 legislation reduced standard offer terms to 10 yearswhile also applying a capacity limit of 1 MW (up to a total capacity of 100 MW). It created a competitive process to solicit up to 2.7 GW from larger projects (> 1 MW) under a 20-year term.

12.5%by 2021

0.2% by 2018

35% state ITC (expired in 2015);

80% of value exempt from property taxes

Oregon 3,436 On: $37-$63(Solar)

Off: $28-$49(Solar)

15-20 3-10 The Oregon PUC has shifted from adjudicatory procedures to rulemaking as the means to implement PURPA

50% by 2040

2.0x RECmultiplier

$5/MWh add’l payment (up to 150 MW)

Avoided cost rates in the table are averaged over the maximum term. The range reflects differences across utilities and contract options.

Standard Contract

Page 25: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 25

States with High Solar QF Development

State Planned QF Solar Capacity

(MW)

AvoidedCost

Rates($/MWh)

MaxContract

Term(years)

MaxContractCapacity

(MW)

Emerging QF Policies RPSPolicy

SolarCarve-

Out

Other Relevant State Incentives

& Policies

Michigan 2,489 Based on highest priced proposal from

competitivesolicitation

10-15 or what is offered in competitivesolicitation

0.1 - 2 Consumers Energy IRP approved in June 2019• Annual competitive bidding for capacity,

including 1,200 MW of new solar from 2019-2021. Consumers can own up to half of the capacity; any capacity not filled by solicitation will be available to QFs

• Consumers is authorized to earn an FCM (financial compensation mechanism) equal to the product of PPA payments in that year multiplied by the WACC

In a separate proceeding, Consumers Energy agreed in August 2019 to contract with QFs for 170 MW of energy and capacity at “full avoided cost.” In addition, Consumers Energy will enter into contracts with QFs for 414 MW of energy and capacity at the “energy plus MISO PRA” rate

15% by 2021

2.0x multiplier prior to

2017

Montana 986 On: $41 (Solar)Off: $32 (Solar)

15-25 3 Montana state court ruled against PSC in April 2019, reverting contract length back to 25 years and requiring inclusion of carbon adder in avoided cost

New LEO standard no longer requires QFs to have signed interconnection and signed PPA

15%by 2015

— 50% property tax abatement

(for new renewables)

Avoided cost rates in the table are averaged over the maximum term. The range reflects differences across utilities and contract options.

Standard Contract

Page 26: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 26

QFs with capacities above the limits allowed for standard contracts have signed long-term contracts through bilateral negotiations with the utilities.

Bilateral QF Contracts

Source: Calculated based on data compiled by ABB Inc. 2019.

State MaxContract

Term(years)

MaxContractCapacity

(MW)

Range ofContract

Term(years)

Range ofContractCapacity

(MW)

# of Solar QF

Contracts(count)

TotalExisting Capacity

(MW)

South Carolina 10 0.1 – 2 — 1-20 30 229

North Carolina 10 1 10-25 1-80 563 4,016

Oregon 15-20 3 – 10 25 1-15 37 262

Michigan Other 0.1 – 2 25 1-11 3 20

Montana 15-25 3 — 3 5 15

Standard Contract Bilateral Contract

Page 27: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 27

Advantages of Competitive Procurement

Competitive bidding under PURPA has been a natural consideration to:

Replace administrative methods with market process.

Limit the amount of QF capacity to utility capacity needs.

Rank QF operating and other characteristics.

Page 28: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 28

FERC weighed in with “Bidding NOPR” in 1988 (RM88-5)

Suggested that bidding could:

– Eliminate debates over avoided cost.

– Achieve lowest cost.

– Not necessarily conflict with PURPA.

Proposed guidance to states:

– All sources—QFs, self-supply, and wholesale purchases.

– No portion of capacity needs reserved for non-QFs.

– Evaluate fuel diversity, dispatchability and reliability.

– Certify process.

The “Bidding NOPR” was not implemented, but conveyed the signal that state bidding mechanisms had potential to be used.

Page 29: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 29

States Have Experimented With Competitive Procurement

In the late 1980s, some states replaced or augmented administrative processes with RFPs or bidding mechanisms.

By the 1990s, approximately 10 states had some type of bidding mechanism.

QFs were ranked in terms of price and other criteria.

Bidding systems varied among states and utilities.

– Transparent “self-scoring” systems (ultimately verified).– Non-public evaluation processes.

State bidding programs appear to have been generally consistent with FERC proposed criteria, except for legal/regulatory challenges on:

– Compliance with the all-source bidding requirement– Requirement to bid & win at the RFP process for QF contract

Recent Consumers Energy settlement to use competitive procurement for new QF contracts (with utility owning up to 50%, and incentives for PPAs)

Page 30: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 30

Montana Experience

2014 - Montana controversy drew FERC Declaratory Order:

− Since 1992 the “Montana Rule” had required competitive bidding.

o LEOs effectively contingent on winning RFP.

o For QFs > 10 MW after 2007.

− FERC order ruled the Montana Rule posed “Unreasonable Obstacles”:

o Exclusive path to LEO.

o MT solicitations not regularly held.

o Bidding NOPR never adopted.

o But MT rules not specified in any case.

2016 – FERC repeated concerns raised in MT in Windham Solar LLC and Allco Finance Ltd., 156 FERC ¶ 61,042

Page 31: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 31

Solar QFs in North Carolina

Explosive growth over last 5 years

Dominated by QFs

Spurred also by 35% state tax credit

– Cumulative upon Federal ITC

– Expired after 2015

0

1,000

2,000

3,000

4,000

5,000

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

MW

QF Non-QF

Source: Velocity Suite, ABB Inc. (2019)

Cumulative Solar Capacity in North Carolina

Page 32: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 32

In July 2017, Competitive Energy Solutions for North Carolina Act (“HB 589”) became law after extensive negotiation

An alternative to PURPA-based implementation to reflect current market realities:

– Mandates competitive procurement

– A fixed amount of renewable capacity (2,660 MW)

– 45 month procurement

– Long-term PPAs

– 30% limit on utility-owned assets

– Managed by Independent Administrator

An example for other regions?

HB 589 in North Carolina

Page 33: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 33

Michigan Experience

Recent Consumers Energy settlement (Mar 2019) uses competitive procurement for new QFs

▀ Annual RFPs to procure new capacity based on the needs identified in the most recent IRP

▀ Any remaining capacity needs can be met by QFs at avoided cost rates set by the highest accepted bid in the RFP

− Impact on incentives to participate in the RFP??

▀ Utility can own up to 50% of the new capacity procured through RFP

▀ Utility earns an incentive for new PPAs (including QF contracts) procured through RFP

▀ Small QFs (< 150 kW) receive standard offer PPA based on full avoided cost rate, regardless of capacity need; larger QFs (< 2 MW) either participate in RFP or receive MISO capacity rate plus forecasted/actual LMPs

an example for other regions?

Page 34: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 34

Presenter Information

METIN CELEBIPrincipal │ Boston, MA

[email protected]

+1.617.864.7900

Dr. Celebi provides expertise in electricity markets and analysis of environmental and climate policy. He has consulted primarily in the areas of electricity spot pricing and market design, and has experience in developing and analyzing climate policies, resource planning, power plant valuation, cost/benefit analyses for joining RTOs, LMP modeling, and merger analysis.

Dr. Celebi received his Ph.D. degree in Economics at Boston College, M.A. degree in Economics at Bilkent University, Turkey, and B.Sc. Degree in Industrial Engineering at METU, Turkey.

The views expressed in this presentation are strictly those of the presenter(s) and do not necessarily state or reflect the views of The Brattle Group, Inc.

Page 35: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 35

The Brattle Group provides consulting and expert testimony

in economics, finance, and regulation to corporations, law

firms, and governments around the world. We aim for the

highest level of client service and quality in our industry.

About Brattle

OUR SERVICES

Research and Consulting

Litigation Support

Expert Testimony

OUR PEOPLE

Renowned Experts

Global Teams

Intellectual Rigor

OUR INSIGHTS

Thoughtful Analysis

Exceptional Quality

Clear Communication

Page 36: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 36

Our Practices and Industries

ENERGY & UTILITIESCompetition & Market

Manipulation

Distributed Energy Resources

Electric Transmission

Electricity Market Modeling & Resource Planning

Electrification & GrowthOpportunities

Energy Litigation

Energy Storage

Environmental Policy, Planningand Compliance

Finance and Ratemaking

Gas/Electric Coordination

Market Design

Natural Gas & Petroleum

Nuclear

Renewable & Alternative Energy

LITIGATIONAccounting

Analysis of Market Manipulation

Antitrust/Competition

Bankruptcy & Restructuring

Big Data & Document Analytics

Commercial Damages

Environmental Litigation& Regulation

Intellectual Property

International Arbitration

International Trade

Labor & Employment

Mergers & Acquisitions Litigation

Product Liability

Securities & Finance

Tax Controversy& Transfer Pricing

Valuation

White Collar Investigations & Litigation

INDUSTRIESElectric Power

Financial Institutions

Infrastructure

Natural Gas & Petroleum

Pharmaceuticals& Medical Devices

Telecommunications, Internet, and Media

Transportation

Water

Page 37: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

brattle.com | 37

Our Offices

BOSTON

NEW YORK SAN FRANCISCO

WASHINGTONTORONTO

LONDON MADRID

ROME SYDNEY

BRUSSELS

Page 38: PURPA Resurgence and Avoided Costs...brattle.com | 4 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 Wh Renewables (Non-Hydro) Hydro

THE POWER OF ECONOMICS

brattle.com