public involvement meeting · 2016. 11. 15. · 11/15/2016 i‐39/90/94 study public involvement...

32
11/15/2016 I39/90/94 Study Public Involvement Meeting 1 Public Involvement Meeting November 15, 2016 – Dane County November 16, 2016 – Columbia County

Upload: others

Post on 09-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 1

Public Involvement MeetingNovember 15, 2016 – Dane County

November 16, 2016 – Columbia County

Page 2: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 2

Study Overview• WisDOT is conducting a study to analyze the existing and future conditions of the I‐39/90/94 corridor

• A range of corridor alternatives will be evaluated which will ultimately lead to the identification of a preferred corridor alternative

I‐39/90 north of US 12/18, Dane County

Page 3: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 3

I‐39/90/94 Purpose & Need

• Gathered public input – Last PIMs were held in January 2015

• Study Needs:– Safety– Traffic– Aging Pavement and Bridges

– Economics

I‐39/90/94 Study PIM, January 15, 2015, Lodi, Wisconsin

Page 4: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 4

What our final product will be• Tier 1 Environmental Impact Statement (EIS)– Entire 34 miles– Broad, general analysis– Evaluating corridors– Complete National Environmental Policy Act (NEPA) requirements

– Goals• Identify preferred corridor• Identify Tier 2 sections and appropriate environmental document type for each Tier 2 section.

• Identify preferred alternative from County CS to I‐39/WIS 78

Page 5: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 5

• The Tier 1 EIS will include a more detailed study from County CS to I‐39/WIS 78 – Evaluate detailed alternatives– Goals

• Identify Preferred Alternative• Define footprint, impacts, and cost of Preferred Alternative

• Allows request for funding of new bridge

• Allow final design and  construction of new bridge after completion of the Tier 1 EIS

What our final product will be

Page 6: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 6

Subsequent Environmental Documents

• Tier 2 Documents– Various sections between the south termini and County CS– Detailed analysis– Evaluate alternatives at specific locations within the preferred corridor identified in Tier 1

– Goals• Identify Preferred Alternative• Define footprint, impacts, andcost of Preferred Alternative

I‐39/90 south of Badger Interchange (I‐94/WIS 30), Dane County

Page 7: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 7

Study Process Timeline

Page 8: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 8

Tier 1 vs Tier 2 Level of Detail

Page 9: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 9

Tier 1 Corridor Concepts

Page 10: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 10

Tier 1 Corridor ConceptsI‐39/90/94 ImprovementsNo‐Build Preserve and MaintainReconstruct: No Capacity ExpansionI‐39/90/94 Existing Corridor

Capacity ExpansionNew I‐39/90/94 Grade Separated CrossingsNew I‐39/90/94 Wisconsin River Crossing ‐ East Alternate RoutesEast Reliever: Option 1East Reliever: Option 2East Reliever: Option 3US 51 Expansion: Option 1US 51 Expansion: Option 2US 51 Expansion: Option 3US 51 + East Reliever CombinationCounty AB/Sprecher Rd/Reiner Rd ImprovementsNorth Beltline ‐ North of WaunakeeNorth Beltline ‐ South of Waunakee

TransitLight Rail ‐Middleton to Sun PrairieHigh Speed RailInter City BusBus Rapid TransitMadison Area Bus Route and Bicycle 

ImprovementsCommuter BusTransportation System ManagementRamp MeteringPark‐and‐RideMadison in MotionBicycle and Pedestrian AccommodationsNew Bicycle and Pedestrian CrossingsColumbia County Bicycle Plan

Page 11: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 11

Tier 1 Corridor Screening Process

Page 12: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 12

Corridor Concepts Traffic Screen Process

Page 13: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 13

Traffic Screen Result Categories

• Carry Forward– The corridor concept will move forward to the next phase of analysis

• Eliminate– The corridor concept does not meet the traffic screening, therefore does not meet the purpose and need and is dropped from further consideration

• Eliminate as Stand Alone– The corridor concept does not meet the traffic screening, however the concept may benefit the preferred corridor and be incorporated during Tier 2

Page 14: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 14

Traffic Screen:Alternate Routes Eliminated

Alternate Routes ResultEast Reliever: Option 1East Reliever: Option 2US 51 Expansion: Option 3County AB, Sprecher Rd, & Reiner Rd ImprovementsNorth Beltline ‐ North of WaunakeeNorth Beltline ‐ South of Waunakee

Eliminate Would have a minimal effect on I‐39/90/94 traffic

Concept Category Overview• Construct a new high speed freeway facility North of Lake Mendota or 

east of Sun Prairie• Improve the US 51 corridor through Portage or County AB/Sprecher Rd/ 

Reiner Rd corridor through the east side of Madison

Traffic Screen Results Overview• Does not remove enough traffic from I‐39/90/94

Page 15: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 15

Traffic Screen:Alternate Routes Carried Forward

Alternate Routes ResultEast Reliever: Option 3US 51 Expansion: Option 1US 51 Expansion: Option 2US 51 + East Reliever Combo

Carry Forward

Concept Category Overview• Construct a new high speed freeway facility from I‐94 east of Sun Prairie 

and connects with I‐39/90/94 north of DeForest• Convert US 51 to a high speed freeway including bypasses of Arlington 

and Poynette

Traffic Screen Results Overview• New freeways serve large volume of vehicles traveling to and from 

the area on I‐94• Reduces traffic volumes on 

I‐39/90/94

Page 16: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 16

Traffic Screen:Transit

Transit ResultLight Rail ‐Middleton to Sun PrairieHigh Speed RailIntercity BusBus Rapid TransitMadison Area Bus Route and Bicycle ImprovementsCommuter Bus

Eliminate Would have a minimal effect on I‐39/90/94 traffic

Concept Category Overview• Improve bus facilities within the Madison Metropolitan area • Provide rail service in the Madison Metropolitan area or regional area Traffic Screen Results Overview• Would not address needs of long distance regional, recreational 

and freight traffic on I‐39/90/94• Transit concepts would address east/west trips, rather than the 

north/south trips served by I‐39/90/94 • Would have a positive 

effect on the overall transportation network

Page 17: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 17

Traffic Screen: Transportation System Management

Transportation System Management ResultRamp MeteringPark and RideMadison in Motion

Eliminate as Stand Alone Does not meet I‐39/90/94 needs, but would have a positive effect on the transportation network

Concept Category Overview• Install ramp meters to restrict the rate at which vehicles enter I‐39/90/94• Improve park‐and‐ride lots to encourage carpooling• Modifications to future land use plans to reduce length of trips and 

encourage trips using other modes

Traffic Screen Results Overview• Would not remove enough traffic from I‐39/90/94 to meet traffic 

screen• Would not accommodate freight trips on I‐39/90/94• Would have a positive effect on 

the overall transportation network

Page 18: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 18

Traffic Screen:Bicycle and Pedestrian Accommodations

Bicycle and Pedestrian Accommodations ResultNew Bicycle and Pedestrian CrossingsColumbia County Bicycle Plan

Concept Category Overview• Improve existing bicycle and pedestrian accommodations• Build new bicycle and pedestrian facilities across and along I‐39/90/94

Traffic Screen Results Overview• Would not address needs of long distance regional, recreational 

and freight traffic on I‐39/90/94• Improvements would encourage the use of alternate modes of 

transportation and would reduce the barrier caused by I‐39/90/94

Eliminate as Stand Alone Does not meet I‐39/90/94 needs, but would have a positive effect on multi‐modal transportation

Page 19: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 19

Traffic Screen:Existing I‐39/90/94 Corridor Improvements

Carry Forward

Concept Category Overview• Improvements within the existing I‐39/90/94 corridor• Includes: capacity expansion, maintain existing capacity, new 

crossings, etc

Traffic Screen Results Overview• Additional capacity would accommodate freight, recreational, and 

commuter traffic growth for the I‐39/90/94 corridor• New Crossings may improve community circulation and reduce traffic 

at interchanges I‐39/90/94 Improvements ResultNo‐Build: Preserve and MaintainReconstruct: No Capacity ExpansionI‐39/90/94 Existing Corridor Capacity ExpansionI‐39/90/94 Grade Separated CrossingsI‐39/90/94 Wisconsin River Crossing ‐ East 

• Maintaining existing capacity was carried forward as a baseline comparison

Page 20: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 20

Corridor Concept Traffic Screen ResultsI‐39/90/94 Improvements ResultNo‐Build: Preserve and MaintainReconstruct: No Capacity ExpansionI‐39/90/94 Existing Corridor

Capacity ExpansionI‐39/90/94 Grade Separated CrossingsI‐39/90/94 Wisconsin River Crossing ‐ East Alternate RoutesEast Reliever: Option 1East Reliever: Option 2East Reliever: Option 3US 51 Expansion: Option 1US 51 Expansion: Option 2US 51 Expansion: Option 3US 51 + East Reliever ComboCounty AB, Sprecher Rd, & Reiner Rd 

ImprovementsNorth Beltline ‐ North of WaunakeeNorth Beltline ‐ South of Waunakee

Transit ResultLight Rail ‐Middleton to Sun PrairieHigh Speed RailIntercity BusBus Rapid TransitMadison Area Bus Route and Bicycle 

ImprovementsCommuter BusTransportation System ManagementRamp MeteringPark and RideMadison in MotionBicycle and Pedestrian AccommodationsNew Bicycle and Pedestrian 

CrossingsColumbia County Bicycle Plan

Page 21: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 21

DRAFT Range of Corridor Alternatives

• Seven Corridor Alternatives– No‐Build: Preserve & 

Maintain– Reconstruct: No Capacity 

Expansion– I‐39/90/94 Capacity 

Expansion– East Reliever: Option A– East Reliever: Option B– East Reliever: Option C– East Reliever: Option D

• Two Options – Wisconsin River Crossing: 

Option 1– Wisconsin River Crossing: 

Option 2

Page 22: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 22

• Does not increase capacity of I‐39/90/94

• Reflects costs and impacts to repair          I‐39/90/94 infrastructure 

• Repairs pavement and bridge needs through the year 2050

• Does not address deficiencies along           I‐39/90/94

No Build:Preserve & Maintain

NB

Page 23: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 23

• Does not increase capacity of I‐39/90/94

• Reflects costs and impacts to repair and replace I‐39/90/94 infrastructure 

• Addresses pavement and bridge needs through the year 2050

• Does not address deficiencies along           I‐39/90/94

Reconstruct: No Capacity Expansion

R

Page 24: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 24

• Add capacity to existing I‐39/90/94 to accommodate future traffic volumes

• Reconstruct interchanges as needed to improve traffic operations and safety

Capacity Expansion CECE

Page 25: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 25

• New freeway east of Madison, Sun Prairie, north of DeForest and Windsor

• Connects I‐94 near Cottage Grove toI‐39/90/94 north of DeForest

• Reconstruct: No Capacity Expansion between East Reliever: Option A limits

• Capacity expansion of      I‐39/90/94 north and south of East Reliever: Option A limits

AEast Reliever

Page 26: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 26

• Converts US 51 to a freeway north of DeForest

• Creates a new freeway that bypasses Arlington and Poynette

• Connects to I‐39/90/94 between County CS and WIS 78

• Reconstruct: No Capacity Expansion between East Reliever: Option B limits

• Capacity expansion of  I‐39/90/94 north and south of East Reliever: Option B limits

BEast Reliever

Page 27: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 27

• New freeway east of Madison, Sun Prairie, DeForest and Windsor

• Similar to East Reliever A, but also bypasses Arlington and Poynette

• Connects I‐94 near Cottage Grove to I‐39/90/94 northwest of Poynette

• Reconstruct: No Capacity Expansion between East Reliever: Option B limits

• Capacity expansion of    I‐39/90/94 north and south of East Reliever: Option Climits

CEast Reliever

Page 28: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 28

• Converts US 51 to a freeway north of DeForest

• Creates a new freeway that bypasses Arlington and Poynette

• Creates an additional Wisconsin River Crossing

• Ties in at the I‐39 / WIS 78 interchange

• Reconstruct: No Capacity Expansion between East Reliever: Option D limits

• Capacity expansion of    I‐39/90/94 north and south of East Reliever: Option D limits

DEast Reliever

Page 29: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 29

Next Steps to Select a Preferred Corridor

• Draft Range of Corridors– Fall 2016

• Evaluate Range of Corridor Alternatives– Thru Spring 2017

• Select Preferred Corridor– Summer 2017

Page 30: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 30

Your Feedback and Input is Important

Page 31: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 31

Future Study Activities2016 – 2017  Refine corridor alternatives for detailed study Identify preferred corridor Identify range of alternatives for Wisconsin River area Outreach: PAC, TAC, agencies, interest groups, property owners Public involvement meetings and online surveys

2018  Identify preferred alternative for Wisconsin River area

Complete Tier 1 EIS document 

2021 – 2023 Complete first Tier 2 NEPA document

2023+  Subsequent Tier 2 NEPA documents

I‐39/90/94 north of County U, Columbia County

Page 32: Public Involvement Meeting · 2016. 11. 15. · 11/15/2016 I‐39/90/94 Study Public Involvement Meeting 3 I‐39/90/94 Purpose & Need • Gathered public input – Last PIMs were

11/15/2016

I‐39/90/94 Study Public Involvement Meeting 32

Study Contacts

I‐39/90 south of Badger Interchange (I‐94/WIS 30), Dane County

Rob Knorr – Study Manager(608) 246‐[email protected]

Larry Barta – Deputy Study Manager(608) 246‐[email protected]