pttchem-sp-p-602-000 underground piping construction.pdf
DESCRIPTION
PTTCHEM-SP-P-602-000 UNDERGROUND PIPING CONSTRUCTION.pdfTRANSCRIPT
PTT CHEMICAL PUBLIC CO., LTD. BRANCH I-1: OLEFINS PLANT
STANDARD SPECIFICATION FOR
UNDERGROUND PIPING CONSTRUCTION WORKS
DOCUMENT NO. PTTCHEM-SP-P-602
REV. ISSUED DATE DESCRIPTION REV. TO
SHEET
ADDED
SHEET
MADE
BY
CHECK
BY
APPROVE
0 7 Dec 05 First Issued Prathanwit Chayan
TOTAL PAGES 39
(INCLUDED THIS PAGE)
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602
PAGE 2 OF 39
REV. 0
SECTION CONTENT PAGE
1. SCOPE 4
2. APPLICABLE CODES 4
3. RELATED ENGINEERING SPECIFICATIONS 4
4. DRAWINGS AND REFERENCES FOR WORKS 5
5. WORK FLOW 5
6. EXCAVATION 6
7. BURYING 6
8. CUTTING AND BENDING 8
9. THREADING 8
10. WELDING 9
11. PREHEATING AND HEAT TREATMENT 18
12. ASSEMBLY 19
13. FLANGED JOINTS 21
14. PROTECTIVE COATING AND WRAPPING 22
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602
PAGE 3 OF 39
REV. 0
SECTION CONTENT PAGE
15. INSPECTION 22
16. PRESSURE TEST 27
17. PRESERVATION 33
18. FLUSHING 35
19. DOCUMENTATION 37
APPENDIX-1 SUPPLEMENTARY RT REQUIREMENTS 38
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602
PAGE 4 OF 39
REV. 0
1. SCOPE
This specification covers the general quality requirements for the fabrication, inspection and testing of
underground piping system on the plant site, excluding transfer pipe line.
2. APPLICABLE CODES
ANSI / ASME B 31.3 : Chemical Plant and Petroleum refinery Piping (up to B31.3b-1986)
3. RELATED ENGINEERING SPECIFICATIONS
The following Engineering Specifications are related to herein :
(1) PTTCHEM-SP-P-
103
Piping Materials (Underground Pipings)
(2) PTTCHEM-SP-P-
605
Welding Procedure Specifications of Underground Pipings
(3) PTTCHEM-SP-P-
805
Welding Performance Qualification Test of Underground Pipings
(4) PTTCHEM-SP-P-
121
Protective Coating and Wrapping for Underground Steel Piping
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602
PAGE 5 OF 39
REV. 0
4. DRAWINGS AND REFERENCES FOR WORKS
4.1 The following drawings and references necessary for the work will be prepared by PTTCHEM.
(1) Plot plan
(2) Piping Arrangement Drawings (Plan and Elevation)
(3) Piping Material Classifications
(4) Notes for Piping Drawings
(5) Others, if any
4.2 All drawings and related documents shall be in English language and the metric units of measurement
shall be used except for pipe sizes, flanges and flange bolting.
4.3 Welding symbols, terms and definitions shall be in accordance with AWS A2.4 and A3.0. (PTTCHEM-
SP-T-003, Par. 4.1)
5. WORK FLOW
Underground construction works shall normally be performed in the following sequence.
Step Work Description
1. Check & confirm the pipe route & measure pipe length & level
2. Coating work for straight pipe & fitting
3. Pin hole test
4. Carry out the excavation work
5. Provide the Bell Hole at the each pipe joint for welding activities
6. Laying the pipe on the temporary support for the welding work
7. Welding work
8. Radiographic & visual inspection for welds
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602
PAGE 6 OF 39
REV. 0
9. Hydrostatic test
10. Proper cleaning on the pipe surface for the wrapping work
11. Coating / wrapping work for joint portion
12. Pin hole test
13. Provide the pipe support & remove the temporary support
14. Backfilling work with proper compaction
6. EXCAVATION
6.1 Depth of burial of pipes shall be as indicated in Piping Arrangement Drawings. Excavation shall be
done considering safety of the work. Especially, if depth of vertical excavation is deep, the piping
works shall be done after protective measure is taken to prevent landslide.
6.2 Before the excavation work, Contractor shall confirm that there is no other buried object around the
place of excavation.
6.3 Pipe casings shall be provided according to the Piping Arrangement Drawings.
7. BURYING
7.1 When works of burying pipe are carried out, protective measures to prevent accident such as
landslide, flooding of water, downfall of workers, ect. shall be taken into consideration fully.
7.2 During underground piping works, full care shall be taken to prevent soil and sand from flowing into
pipes and to prevent pipes from refloating due to underground water or rainwater.
7.3 When back-filling is carried out, small-grain sand shall be used for the parts directly contacting with
pipes.
7.4 Back-filling work shall be done so that the coated and wrapped surface of the piping will not be
damaged.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602
PAGE 7 OF 39
REV. 0
7.5 Back-filling with small-grain sand shall be done as shown in Fig. 7.5
7.6 Additional soil and sand containing gravel, crushed stone or similar can be used only for upper portion
of underground pipes as shown Fig. 7.5.
7.7 Back filling shall be done with appropriate tamping and to have 5 - 100 mm overheaping. Tamping
method may be any one of the followings.
(1) Water binding method
(2) Rammer method
(3) Vibrator method
(4) Compact roller method
(5) Combination of above method
FIG. 7.5
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602
PAGE 8 OF 39
REV. 0
8. CUTTING AND BENDING
8.1 Pipes and fittings shall be cut with cutting machine and beveled by machine, grinding, etc. according
to the shapes specified in the WPS.
8.2 Cutting surfaces shall be cleaned with grinder.
8.3 Butt weld end preparation is acceptable only if the surface is reasonably smooth and true and all slag
from oxygen or arc cutting is cleaned from flame-cut surfaces. Discoloration which remains on a
flame-cut surface is not considered to be detrimental oxidation. (B31.3, Par. 328.4.2(a) (1))
8.4 Preheating may sometimes be instructed prior to thermal cutting according to Par. 11.
8.5 In case pipe cutter shall be used for piping works, the inner surface of pipe at cut-end shall be well
finished by reamer or file.
8.6 Seamless pipe having nominal size up to 1.1/2 inch shall be bent with a radius of 5 times the outside
diameter of the pipe in cold state as a rule, and this work shall be made by pipe bender.
9. THREADING
9.1 Thread to be used for pipe be "American Standard Taper Pipe thread (NPT)" stipulated in ANSI
B1.20.1.
9.2 Seal tape or liquid gasket shall be used for threaded joints as a rule.
9.3 In case where pipes are seal-welded after screwed-in, lubricant, seal tape, etc. shall not be used, and
all exposed threads shall be covered by the seal weld.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602
PAGE 9 OF 39
REV. 0
10. WELDING
10.1 General
(1) No welding shall be commenced without the welding procedures qualified.
(2) Welders involved shall be qualified by PTTCHEM prior to the start of production welding in
accordance with Engineering Specification PTTCHEM-SP-P-805, Welding Performance
Qualification Test of Underground Pipings.
(3) Welding shall be performed in accordance with Engineering Specification PTTCHEM-SP-P-
605, Welding Procedure Specifications of Underground Pipings.
(4) All welds shall be immediately after completion of welding provided with the welder's
identification stamp. For such cases where stamping will be deleterious to the parent material
(thin materials, notch sensitive materials, stainless steel, non-ferrous materials, ect.) stencil
stamping / marking may be Substituted for such die-stamping and shall be maintained until
PTTCHEM's inspection complete.
(5) Welding materials such as electrodes and fillers shall be properly stored, and shall be properly
heated/dried before use.
(6) Peening is only permitted to the extent necessary to clean the weld. (PTTCHEM-SP-P-T-003,
Par. 7.5)
Peening is not permitted on the root pass and final pass of the weld.
(7) Fillet welds (including socket welds) may vary from convex to concave. The size of fillet weld s
determined as shown on Fig. 10.1.A. (B31.3, Par. 328.5.2)
Typical weld details for slip-on flanges and socket welding components are shown in Fig. 10.1B
and Fig. 10.1C. (B31.3 Par. 328.5.2(a))
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 10 OF 39
REV. 0
(8) No weld shall be covered/concealed by external attachments such as pads.
(9) Grounding wire shall be firmly fastened by screw or clamp to the material to be welded.
(10) The root pass of single butt joints shall be welded such the complete penetration to be attained.
Equal Leg Fillet Weld Unequal Leg Fillet We
NOTE
:
The size of an equal leg fillet weld is
the length of the largest inscribed
isosceles right triangle (theoretical
throat = 0.707 X size).
NOTE : The size of an unequal leg fillet weld leg
lengths of the largest right triangle which
can be inscribed within the weld cross
section (e.g. 1/2 in. x 3/4 in.) (B31.3, Fig.
328.5.2A)
FIG. 10.1A FILLET WELD SIZE
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 11 OF 39
REV. 0
FIG. 10.1B - TYPICAL DETAILS FOR DOUBLE-WELDED SLIP-ON
AND SOCKET WELDING FLANGE ATTACHMENT WELDS
FIG . 10.1C - MINIMUM WELDING DIMENSIONS FOR SOCKET WELDING
COMPONENTS OTHER THAN FLANGES
(11) No welding shall be done if there is impingement on the weld area of any rain, snow, sleet, or
excessive wind, or if the weld area is frosted or wet, unless an appropriate protection s
provided. (B31.3, Par. 328.5.1 (e))
(12) Welding shall not be performed when the ambient temperature is below 5 °C, unless the pipe is
preheated as per Par. 11.
(13) internal and external surfaces to be welded shall be clean and free from paint, galvanized paint,
oil, rust, dirt, loose scale, or other material that would detrimental to either the weld or the base
metal under welding conditions. the adjacent base metal surfaces shall be cleaned, too, within
25 mm from the edge of the joint. (B31.3, par. 328.4.1) (PTTCHEM-SP-T-003, Par. 7.3)
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 12 OF 39
REV. 0
(14) Inside of circumferential weld bead shall not have any burr or fragment of welding rod and all
adhering substances shall be removed once located.
(15) Spatter, slag, etc. shall be thoroughly removed.
(16) Weld defects shall be completely removed by chipping, gouging, grinding, or other methods
(suitable for the type of material being repaired) to sound metal, and the excavated area shall
be examined by liquid penetrant methods to assure complete removal of defects.
(17) Repair welds shall be made using the same Welding Procedure used for the original weld or
any other previously approved Welding Procedures.
(18) The repaired welds shall be re-examined as required for the original welding.
(19) Any weld repairs of solid material (plate, forging, pipe, etc.) need the approval of PTTCHEM
and shall be performed using such procedures only, that are approved by PTTCHEM.
(20) All site-welding activities shall be done under proper protection against weather conditions to
the satisfaction of PTTCHEM.
(21) Contractor shall maintain proper records containing all relevant information on each and every
welder performance as the work progresses.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 13 OF 39
REV. 0
10.2 Edge Preparation and Alignment
(1) Circumferential Welds
(a) If component ends are trimmed as shown in Fig. 10.2A. for correcting internal misalignment,
such trimming shall not reduce in a finished wall thickness below the required minimum wall
thickness, "tm". Where necessary, weld metal may be deposited on the inside or outside of the
component to provide alignment. It is also permissible to size pipe ends of the same nominal
size to improve alignment, if the above wall thickness requirements are maintained. When a
girth weld joints components of unequal wall thickness and one is more than 1.1/2 times
components of the other wall, end preparation and geometry shall be in accordance with
acceptable designs for unequal well thickness in ANSI B16.5.
(B31.3, Par. 328.4.2(b) (1), (4) & (5))
FIG. 10.2A - TRIMMING AND PERMITTED MISALIGNMENT
(b) Inside surfaces of components at ends to be jointed in girth or miter groove welds shall be
aligned within the limits in the WPS. If the external surface of the two components are not
aligned, the weld shall be tapered between them. (B31.3, Par. 328.4.3 (a) (1) & (2))
(2) Branch Connection Welds
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 14 OF 39
REV. 0
(a) Branch connections which abut the outside surface of the run wall shall be contoured for grove
welds which meet the WPS requirements. (B31.3, Par. 328.4.3(c) (1)) (See Fig. 10.2B)
FIG. 10.2B PREPARATION FOR BRANCH CONNECTIONS
(b) Run opening for branch connections shall not deviate from the required contour by more than the
dimension "m" in Fig. 10.2B. In no case shall deviations of the shape of the opening cause the root
spacing tolerance limits in the WPS to be exceeded. Weld metal may be added and refinished if
necessary for compliance. (B31.3, Par. 328.4.3(c) (3))
10.3 Tack Welding
Tack welding shall be done as followings :
(1) Avoid unreasonable set-up or other factors which would cause residual stress.
(2) Keep adequate root opening by using spacer, etc.
(3) Select welding rood of appropriate size for tack welding so as to fit the root opening.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 15 OF 39
REV. 0
(4) Adopt dummy plate or start with backstep method when an arc is struck.
(5) Provide jigs (bridges or clamps)) in minimum number necessary for setting up. Use jigs (bridges or
clamps) made of material whose quality is the same as or better than base metal.
(6) Remove the jigs by grinder or gas cutting and, in case of gas cutting, cut it at upper part of its weld toe
and finish by grinder down to the surface of base metal. Jigs shall never be struck down by hammer
or plucked off.
10.4 Branch Connections
All branch attachment welds shall be of full penetration groove type. When the branch pipe is welded
directly to main pipe, welding shall be performed, unless otherwise specified, as shown in the
following figures.
NOTE These sketches show minimum acceptable welds.
Welds may be larger than those shown here.
Remarks:
1. Throat thickness "tc" shall be the lesser of 0.7 x "Tn" or 1/4 in. (6.4 mm).
2. The symbols used herein are as follows:
Th: nominal thickness of main pipe
Tb: nominal thickness of branch pipe
Tr: nominal thickness of reinforcement pad
3. At first, weld the part (a) and finish off the weld surface with grinder and then weld the part (b).
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 16 OF 39
REV. 0
4. Where reinforcement pad is necessary, it is indicated in the Piping Arrangement Drawing and
Notes for Piping Drawings.
5. If pads or saddles are used, a vent hole shall be provided at the side (not at the crotch) in the
ring or saddle to reveal leakage in the weld between branch and main run and to allow venting
during welding. Pads or saddles may be made in more than one piece if joints between pieces
have adequate strength and if each piece has a vent hole. A good fit shall be provided between
reinforcing pads or saddles and the parts to which they are attached.
6. Examination and any necessary repairs of the completed weld between branch and run shall be
made before adding reinforcing pads or saddles. (B31.3, Par. 328.5.4(h))
7. If reinforcement pads for branches should be made out of two segments, the segments shall be
welded in location away from the main pipe and the weld shall not run parallel to the main pipe's
axis.
8. Location of vent hole which is equipped in the reinforcement pad plate is shown is shown as
below;
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 17 OF 39
REV. 0
10.5 Half Coupling Join
Half coupling joint shall be welded as shown in the following figures:
10.6 Miscellaneous
(1) When welded pipe is used in horizontal line, the pipe shall be laid so that the longitudinal weld line
comes to upper side of the pipe (gas side). Arrangement of circumferential,
longitudinal and other (branch, support, etc.) weld lines shall be as shown in the following figures :
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 18 OF 39
REV. 0
Remarks : 1. L and L1 show the distance between both toes of bead.
2. L shall be the larger of three times of the pipe wall thickness or one outer diameter
of opening.
3. L1 shall be five times the pipe thickness or over.
(2) If fabrication aids such as temporary fixtures are removed after welding, the attachment locations on
the main pressure part shall be properly ground to eliminate surface stress risers.
11. PREHEATING AND HEAT TREATMENT
11.1 Pre-heating
(1) Preheating shall be performed by propane flame or by other appropriate method prior to commencing
the welding.
(2) Materials to be preheated and recommended preheating temperature shall be as follows :
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 19 OF 39
REV. 0
TABLE 11.1 - PREHEAT TEMPERATURES
Base Metal
P-Number
Weld Metal
Analysis
A-Number
Base Material
Group
Nominal Wall
Thickness,
(mm)
Minimum
Temperature
(°C)
1 1 Carbon Steel <25.4 10
Remarks :
1. The preheat temperature required according to the Welding Procedure Specifications shall be
checked by use of temperature-indicating crayons or other suitable methods to ensure that the
required preheat temperature is obtained prior to and maintained during the welding operation.
2. Heating width shall be three times the pipe wall thickness to each side from the bevel end. But it
is not necessary to exceed 100 mm.
11.2 Postweld Heat Treatment
No postweld heat treatment is required.
12. ASSEMBLY
12.1 Unless otherwise specified in the Drawings, valves shall normally be mounted with their stems upward
for horizontal line, to access way for vertical line.
12.2 Class designation and construction of each value as mounted in the piping system shall be as shown
in the Piping Arrangement Drawing, Piping Material Classifications and Piping Material Dimensions.
For all materials supplied, confirm that they are in conformity to the description of Piping Materials
Classification.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 20 OF 39
REV. 0
12.3 Each fabricated component of piping shall be cleaned the inner surface and then both ends shall be
protected with suitable caps.
12.4 Valves shall be installed as closed after cleaning, and shall not be opened during installation of piping
systems.
12.5 In installing, flanged joints shall be fastened, after checking for the alignment of flange center and the
parallelness of flange face, so that the gasket contact faces bear force uniformly and then made up
with relatively uniform bolt stress.
12.6 Piping works shall be accurately performed in checking horizontal and vertical directions and mutual
distances between parallel pipelines, using level, plummet, etc.
12.7 When assembling flanged connections, the gasket and bolt nut, shall be give paste for prevention of
seizure, leakage, or adherence. Especially, asbestos sheet gasket be given paste amply.
Recommended pastes are as listed below :
Service of Piping Object Paste
air, steam, hot water
nitrogen, etc.
Joint sheet
gasket
VALQUA #5
oil, gasoline and other
solvents
Metal gasket
VALQUA #6
piping system of low
temperature
LOWTEN PASTE 100
piping system of 100 °C and
over
Bolt, Nut
SMOCON OR MOLY KOTE
piping system of below
100 °C
piping system of low
temperature
LOWTEN PASTE 100
Remark : VALQUA, LOWTEN, PASTE, SMOCON, AND MOLY KOTE are brand names.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 21 OF 39
REV. 0
12.8 When works are done in the vicinity of piping made of, or lined with special materials such as plastic,
rubber, glass, etc., care shall be taken not to give them damage by fire, impact, etc.
12.9 All general aspects such as cleanliness and safety requirements as regard fabrication including
welding and cutting shall be ensured in accordance with standard and sound engineering practices, to
the satisfaction of PTTCHEM.
12.10
13. FLANGED JOINTS
13.1 Before bolting up, flange faces shall be aligned to the design plane to within 1/16 in./ft (0.5%)
maximum measured across any diameter; flange bolt (B31.3, par. 335.1.1(c))
13.2 Any damage to the gasket seating surface which would prevent gasket seating shall be repaired, or
the flange shall be replaced. (B31.3, Par. 335.2.1)
13.3 In assembling flanged joints, the gasket shall be uniformly compressed to the proper design loading.
(B31.3, Par. 335.2.2(a))
13.4 Bolts should extend completely through their nuts. Bolts that fail to do so are considered acceptably
engaged if the lack of complete thread engagement is not more than one thread. (B31.3, Par.
335.2.3)
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 22 OF 39
REV. 0
13.5 The bolt holes of flanges shall be located symmetrically from vertical center line in horizontal piping
line, and from plant north-south center line in vertical piping line, unless otherwise indicated in the
drawing.
Vertical Centerline Plant North-South Centerline
Horizontal Piping Vertical Piping
14. PROTECTIVE COATING AND WRAPPING
Protective coating and wrapping shall be in accordance with Engineering Spec. PTTCHEM-SP-P-121,
Protective Coating and Wrapping for Underground Steel Piping.
15. INSPECTION
15.1 General
(1) Safety requirements as regards testing and inspection including radiography shall be ensured
in accordance with standard and sound engineering practices to the satisfaction of
PTTCHEM.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 23 OF 39
REV. 0
(2) PTTCHEM's final inspection shall be performed in accordance with PTTCHEM's drawings
and Engineering Specifications. Contractor shall not be released from his responsibility
before getting approval by PTTCHEM, even after the completion of the inspection.
(3) Prior to, during and after completion of the works, the tests and inspection as listed in Table
15.1 shall be performed by the Contractor.
TABLE 15.1
Stage Inspection and Test Check Points
(1) Prior to commenting work (a) Check of materials 1) Color Code, Material Designation,
Lot No. REQ. No.
(b) Welder's performance
qualification
1) Welder's performance qualification
certificates
(c) Welding procedure
qualification
(d) Welding rod 1) Brand name & size
(2) Prior to welding work (a) Edge preparation 1) Shape & dimensions
2) Cleanliness
(b) Shape of Pipe end 1) Out of roundness
2) Thickness
(c) Tack welding 1) Misalignment, Root opening
(d) Preheating 1) Method of preheating
2) Width of heating
3) Temperature measurement
4) Heating temperature
(e) Welding rod 1) Drying temperature
2) Drying time
3) Brand name & size
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 24 OF 39
REV. 0
Stage Inspection and Test Check Points
(3) During Welding (a) Welding condition 1) Welding parameters
2) Protecting measure for welding
3) Weather condition
(4) After completion of
welding work
(a) Visual examination 1) Inside surface misalignment, if
accessible
2) Outer surface misalignment
3) Inside surface weld protrusion, if
accessible
4) Wave irregularity
5) Uneven leg length
6) Irregular height of bead
7) Undercut
8) Overlap
9) Bead center shift
10) Height of reinforcement deposit
11) Throat thickness of fillet welds
(b) Non-destructive
examination
1) radiography (RT)
(5) During and after
completion of work
(a) Visual inspection
(6) After (a) Hydrostatic test
completion of work
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 25 OF 39
REV. 0
15.2 Non-Destructive Examination & Visual Examination of Welds
(1) Extent of Required Examination
The required weld examination shall be in accordance with Table-15.2.
TABLE 15.2
Type of weld Examined
Material Flange
Class
Type
Examination
Girth Butt
Weld
Branch
Weld
Socket
Weld
Attachment
Weld
Piping Class
Description
Carbon
Steel
150 Visual
RT
100%
2%
100%
-
100%
100%
-
150B13
150B03
Remarks : 1. Non-destructive examination is not required for the piping system designed for internal
pressure less than 1.0 kg/cm2g, such as vents, drains, etc.
2. Percentage figures indicated shall be the sampling of welds made by each welder. The entire
length of the selected welds shall be examined.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 26 OF 39
REV. 0
(2) Radiographic Examination (RT)
(a) Method :
Radiography of welds shall be in accordance with ASME Code Sec. V, Article 2 and
the supplementary procedures described in Appendix-1.
(b) Acceptance criteria :
Limitations on imperfections in welds shall be as stated in ANSI/ASME B31.3, Par.
341.3.2 for the degree of service condition involved.
(c) Visual Examination
After completion of welding, all welds shall be visually inspected on the outside and
to the maximum extent possible also on the inside. The sequential execution of the
welding operations shall be such as to enable maximum possible extent of visual
inspection of the welds on the inside: for example, welding the pipe onto a socket
coupling only after the weld between the coupling and the main pipe has been
visually inspected on the inside for freedom from defects.
Followings shall be met, checking visually or in using measuring instrument.
(a) Inside surface misalignment : 1.5 mm or less
(b) Outside surface misalignment : 3.0 mm or less
(c) Under cut :
Undercut shall be finished smoothly with grinder or file not to leave any notch,
even when the value is within the limit. After finishing, the thickness of pipe
shall not be less than the minimum design thickness.
(d) Overlap : Grinding off
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 27 OF 39
REV. 0
15.3 Visual Inspection
Visual inspection shall be made for :
(1) Correction for jig mark
(2) Removal of spatter and slag
(3) Any harmful flaw on the flange face, inner and outer surface of pipe
(4) Shape and size of branches and other attachments shall comply with the Drawings.
16. PRESSURE TEST
16.1 GENERAL
(1) Prior to initial operation, each piping system shall be pressure tested to ensure tightness.
(B31.3, Par. 345.1)
(2) If any weld of a piping system remains concealed, gas leak test at test pressure equal to that
for a pneumatic test shall be conducted in lieu of hydrostatic test for the concealed weld.
(3) In case partial hydraulic pressure tests are applied for sections of underground piping,
connection points between the two parts (sections) may be checked using non-destructive
examination method, after obtaining approval by PTTCHEM.
16.2 Test Fluid
Hydrostatic testing shall be performed using clean water in general for all cases steels.
(1) If there is a possibility of damage due to freezing, or if the operating fluid or piping material
would be adversely affected by water, any other suitable liquid may be used.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 28 OF 39
REV. 0
(2) If hydrostatic testing is not considered practicable, a pneumatic test maybe substituted, using
air or another nonflammable gas.
16.3 Test Preparation
(1) All joints, including welds, are to be left uninsulated and exposed for examination during the
test, except that joints previously hydro tested in accordance with the Code may be insulated
or covered.
(B31.3, Par. 345.3.1)
(2) Piping designed for vapor or gas shall be provided with additional temporary supports, if
necessary, to support the weight of the test liquid. (B31.3, Par. 345.3.2)
(3) Expansion joints shall be provided with temporary restraint if required for pressure load during
the test, or shall be isolated from the test. (B31.3, Par.345.3.3)
(4) Equipment which is not to be subjected to the pressure test shall be either disconnected from
the piping or isolated by blinds during the tests. A valve may be used provided the valve
(including its mechanism) is suitable for the test pressure. (B31.3, Par. 345.3.4)
(5) A flanged joint at which a blind plate is inserted to isolate other equipment during the test
need not be pressure tested.
(6) If a pressure test is to be maintained for a period of time and the test liquid in the system is
subject to thermal expansion, precautions shall be taken to avoid excessive pressure. (B31.3,
par. 345.2.1 (b))
(7) In case where the piping to be tested is connected to other piping in outside of battery limit,
the piping shall be isolated by blind plate or valve.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 29 OF 39
REV. 0
(8) In case where orifice, control valve, positive displacement type of area type flow meter,
strainer, etc. are installed in the piping line to be tested, Contractor shall, prior to the test,
obtain instruction of PTTCHEM.
(9) When the test of piping system is to be carried out separately for each part divided at the
position of flanged joint, blind plate shall be inserted between the flanges. Minimum thickness
of such blind plates shall be as shown in Table 16.3.
(10) All piping and equipment shall be properly provided with vents to remove air completely when
filled with water. Provide vent and drain connections at the highest and lowest part of the line,
respectively. These connections may be closed with blind flange after completion of the test.
(11) At least two pressure gauges, having the range of 1.5 - 2 times the test pressure, shall be
provided, one of them being installed at the pump discharge. However, for piping within 1.0
m of length, one or more pressure gauge(s) shall be used.
Pressure gauges shall be installed at those high and low points as near as possible to the
highest and lowest of the piping to be tested, on order to prevent overstress in the piping.
(12) In case of piping with check valve, the source of pressure shall be located in the upstream of
the check valve. If this is not possible, check valve disc shall be removed or lifted up by lever
(the latter is in case of valve equipped with lever) before the test. If valve disc was removed,
it shall be confirmed, after completion of the test, that the disc was restored perfectly.
(13) A grip shall be fixed to outside of each blind plate to be used for the test, and shall be painted
in red to distinguish them from those for other use. A list of all blind plates and blind flanges
installed for the purpose of the test shall be made and , before start-up of the plant, it shall be
checked according to the list, whether such blind plates and blind flanges were removed
without fail.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 30 OF 39
REV. 0
Table 16.3 Minimum thickness of blind plates for pressure testing unit : mm
Test
Pressure
Flange Size (B)
kg/
cm2
1-
1/2
2 3 4 6 8 10 12 14 16 18 20 24
7 1.6 2.3 3.0 3.2 5.0 6.0 7.5 8.5 9.5 10.5 12.0 13.0 15.5
14 2.3 2.6 4.5 5.0 7.0 8.5 10.5 12.0 13.0 15.0 17.0 18.5 21.5
21 3.2 3.2 5.0 6.0 8.5 10.5 12.5 15.0 16.0 18.5 20.5 22.5 26.5
28 3.2 4.0 6.0 7.0 9.5 12.0 14.5 17.0 18.5 21.0 23.5 26.0 30.5
35 4.0 4.5 6.5 7.5 11.0 13.5 16.5 19.0 20.5 23.5 26.5 29.0 34.5
42 4.0 4.5 7.0 8.5 12.0 15.0 18.0 21.0 22.5 26.0 29.0 31.5 37.5
49 4.5 5.0 7.5 9.0 12.5 19.0 19.0 22.5 24.5 28.0 31.5 34.5 40.5
56 5.0 5.5 8.5 9.5 13.5 17.0 20.5 24.0 26.0 29.5 33.5 36.5 43.5
63 5.0 5.5 9.0 10.0 14.5 18.0 21.5 25.5 27.5 31.5 35.5 39.0 46.0
70 6.0 7.0 10.5 12.0 17.5 21.5 26.5 31.0 33.5 38.5 43.0 47.0 56.0
77 6.5 7.0 11.0 13.0 18.5 23.0 27.5 32.5 35.0 40.0 45.5 49.5 58.5
84 6.5 7.5 11.5 13.5 19.0 24.0 29.0 34.0 36.5 42.0 47.0 51.5 61.0
91 7.0 8.0 12.0 14.0 20.0 25.0 30.0 35.0 38.0 43.5 49.0 53.5 63.5
98 7.0 8.0 12.5 14.5 20.0 26.0 31.0 36.5 39.5 45.5 51.0 56.0 66.0
105 7.5 8.5 13.0 15.0 21.5 27.0 32.5 38.0 41.0 47.0 53.0 58.0 68.5
112 7.5 8.5 13.5 15.5 22.0 27.5 33.5 39.0 42.5 48.5 54.5 59.5 70.5
119 8.0 9.0 14.0 16.0 22.5 28.5 34.5 40.0 43.5 50.0 56.0 61.5 73.0
126 8.0 9.0 14.0 16.5 23.5 29.5 35.5 41.5 45.0 51.5 58.0 63.5 75.0
133 8.5 9.5 14.5 17.0 24.0 30.0 36.5 42.5 46.0 53.0 59.5 65.0 77.0
140 8.5 9.5 15.0 17.0 24.5 31.0 37.0 43.5 47.0 54.0 61.0 66.5 79.0
175 9.5 11.0 16.5 19.0 27.5 34.5 41.5 48.5 53.0 60.5 68.0 74.5 88.0
210 10.5 12.0 18.0 21.0 30.0 38.0 45.5 53.5 58.0 66.0 74.5 81.5 96.5
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 31 OF 39
REV. 0
Remarks 1. In case where piping diameter is 1B or under,
Test Pressure (kg/cm2) Thickness of Blind Plate (mm)
40 or under 2.3
41 - 60 3.2
61 - 115 4.5
116 - 210 6.0
2. In case where piping diameter is 26B or over, following formula shall be applied to determine the
thickness of blind plate.
-
thickness of blind plate (t) mm = D ( 3P / 16SE )1/2
where,
D : Outer diameter of gasket (mm)
P : test pressure (kg/cm2)
SE : allowable stress (kg/cm2)
16.4 Hydrostatic Test
(1) The pump for pressure test shall be attended constantly during the test by suitable members
of operators.
(2) Procedures for hydrostatic pressure test shall be as follows.
(a) After filling the piping to be tested with water and purging air from there, the pressure
shall be increased gradually in the steps as shown in table 16.4, maintaining for at
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 32 OF 39
REV. 0
least 3 minutes in each step and no abnormal conditions such as leakage, etc. shall be
confirmed.
(b) After the pressure test, the pressure value shall be decreased down to max. operating
pressure x 1.1. Then welded joints shall be checked against leakage.
16.5 Test Pressure
The hydrostatic pressure at any point in the system shall be as shown in Piping Line Schedule.
16.6 Pressure Releasing and Draining
(1) After completion of the test, pressure shall be released by opening the valve gradually so as
not to endanger personnel or damage equipment.
16.7 Others
(1) Piping always open to atmosphere, such as vent pipe, drain pipe, outlet pipe of safety valve,
etc. are not tested.
16.8 Test Records
Records shall be made of each piping system during the testing period.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 33 OF 39
REV. 0
17. PRESERVATION
17.1 Preservation with Full Water
After completion of the hydrostatic test, the piping shall be kept preservation with full water until water
flushing carries out, in order to prevent inside rust of piping.
Table 16.4
PRESSURIZING STEP AND HOLDING TIME OF HYDROSTATIC PRESSURE TEST
Steps Pressure(kg/c
m2g)
Pressurizing Method Measuring
Instrument
Holding Time
(minutes)
Step 1 2 by test pump, etc. Pressure gauge in each step : 3
at least press. : 30
Step 2 10 “ “ “
Step 3 20 “ “ “
Step 4 30 “ “ “
Step 5 40 “ “ “
Step 6 60 “ “ “
Step 7 100 “ “ “
Step 8 200 “ “ “
Step 9 300 “ “ “
Remarks: 1. Holding time may be extended if checking is not completed within the specified
holding time.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 34 OF 39
REV. 0
2. The piping shall not be left at pressurized condition for a long period.
17.2 Curing
(1) Nozzle of aboveground shall be covered with metal sheet to prevent incoming dust.
(2) The red-colored protection box shall be placed to the following parts, in order to prevent
damage during construction.
- Valve stem of aboveground
- Nozzle of aboveground
- Cathodic protection cable of aboveground (lead to test box)
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 35 OF 39
REV. 0
18. FLUSHING
18.1 Flushing Method
Flushing shall be made by water flushing method.
18.2 General Requirements for Cleaning and Flushing
(1) Cleaning at Fabrication Work
(a) Vinyl caps or other end protections which cover ends of pipes shall not be removed
until the fabrication work is started.
(b) For valves, fittings and other parts, the same as above item (a) shall be observed.
(c) Inside surface of fabricated piping shall be made free from slag, scale and other foreign
matter, with grinder, chisel, wire brush, etc. After completion of cleaning, ends of the
piping shall be covered with caps until the installation in the field.
(2) Preparation for Flushing
(a) Following preparation works shall be carried out according to Flushing Plan.
1) Temporary piping work
2) Countermeasure for safety
3) Coordination procedure and assignment of man concerned
4) Prevention of pubic nuisance
5) Cooperation with operator
6) Judgment criteria of flushing
7) Treatment of piping accessories
8) Confirmation of support (slide or fix)
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 36 OF 39
REV. 0
(b) Support shall be attached to exhaust piping to prevent accident caused by the reaction
force during flushing.
18.3 Water Flushing
(1) Water for Flushing
As a rule, industrial water will be used.
(2) Degree of Water Flushing
Flushing shall be performed till the water becomes free from foreign materials, scale, etc.
This shall be decided by PTTCHEM upon observing turbidity of water taken out into beaker or
cup.
(3) Procedure for Water Flushing
(a) Water flushing shall be perform in the method of running by pressurized water, or rapid
draining with water filled.
(b) Where instruments are including in the piping system to be flushed, the instruments
shall, as a rule, be removed and spool pipe (distance piece) shall be inserted of the
instrument. When flushing is carried out in the condition with instrument. When
flushing is carried out in the condition with control valve connected, the procedure shall
be as follows.
1) Disconnect the companion flange at upstream side of the control valve and cover
opening of the control valve.
2) Flush the piping of upstream side.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 37 OF 39
REV. 0
19. DOCUMENTATION
The records pertaining to all inspection and testing activities shall be diligently and meticulously
maintained by the Contractor.
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 38 OF 39
REV. 0
APPENDIX-1
SUPPLEMENTARY RT REQUIREMENTS
1. Personnel Qualification
Technicians who perform the radiographic inspection of welds must have the knowledge of method
and apparatus there of and, at the same time, the sufficient Technique and experience of taking and
processing of photograph. Those who make the judgment for non-destructive inspection shall be
those appointed by PTTCHEM.
2. Safety (Radiation Protection)
Prior to the radiographic examination, the scattering radiogractive ray around the area shall be
measured and the controlled area of the radioactive ray shall be established, providing the sufficient
countermeasure to prevent hazard of radioactive ray.
3. Recommended Identification System (Marking)
A permanent identification system is preferred to provide on the radiograph as follows :
UNDERGROUND PIPING CONSTRUCTION WORKS PTTCHEM-SP-P-602 PAGE 39 OF 39
REV. 0
Where,
(a) Diameter of pipe (inch)
(b) Weld No. (Isome Dwg. No.)
(c) Thickness (mm)
(d) Put symbols A, B, C... in clockwise sequence, looking in the direction same as that of flow, starting
from the top (horizontal pipe) or the plant north (vertical pipe).
(e) In case of re-photographing, put symbol "R" which means re-inspection and for cut out is "C O"
(f) Date
(g) Welder No.
(h) Arrow mark
(i) A-lead marked tape
(j) Penetrameter
(k) Effective length mark (Location Markers)
(l) Contractors symbol mark