ps-1 report

Upload: harsha-dutta

Post on 03-Jun-2018

229 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 PS-1 Report

    1/40

    1 | Harnessing Creativity and Implanting Innovation in a Power Plant

    A REPORT

    ON

    HARNESSING CREATIVITY AND

    IMPLANTING INNOVATION IN A POWER

    PLANT

    BY

    D SATYA SAI HARSHA 2011B3A3430H

    AT

    VADINAR POWER COMPANY LIMITED (ESSAR POWER),

    JAMNAGAR,

    A PRACTICE SCHOOL STATION OF

    BIRLA INSTITUTE OF TECHNOLOGY AND SCIENCE,

    PILANI

    (JULY, 2013)

  • 8/11/2019 PS-1 Report

    2/40

    2 | Harnessing Creativity and Implanting Innovation in a Power Plant

    A REPORT

    ON

    HARNESSING CREATIVITY AND

    IMPLANTING INNOVATION IN A POWER

    PLANT

    BY

    D SATYA SAI HARSHA 2011B3A3430H

    PREPARED IN PARTIAL FULFILLMENT OF THE

    PRACTICE SCHOOL-1 COURSE NO.

    BITS C221/BITSC231/BITS C241/BITS GC221/BITS GC231

    AT

    VADINAR POWER COMPANY LIMITED (ESSAR POWER),

    JAMNAGAR,

    A PRACTICE SCHOOL STATION OF

    BIRLA INSTITUTE OF TECHNOLOGY AND SCIENCE,

    PILANI

    (JULY, 2013)

  • 8/11/2019 PS-1 Report

    3/40

    3 | Harnessing Creativity and Implanting Innovation in a Power Plant

    BIRLA INSTITUTE OF TECHNOLOGY AND SCIENCE,

    PILANI (RAJASTHAN),

    PRACTICE SCHOOL DIVISION

    STATION: VADINAR POWER COMPANY LIMITED (ESSAR POWER)

    CENTER: Jamnagar

    DURATION : From: 22ND

    May 2013 To: 13TH

    July 2013

    TITLE OF THE PROJECT : Harnessing Creativity and Implanting Innovation in a

    Power Plant.

    ID No. Name of the Student Discipline

    2011B3A3430H D SATYA SAI HARSHA M.Sc (Hons.) Economics

    B.E (Hons.) EEE

    NAME OF EXPERT: Mr. Snehal Pandya DESIGNATION: Joint General Manager

    NAME OF PS FACULTY: Dr. Trilok Mathur

    KEYWORDS: Innovation, Creativity, Boilers.

    PROJECT AREA(S): Mechanical, Human Resource

    ABSTRACT:

    This report aims at giving basic understanding of how the processes of

    innovation and creativity are an integral necessity of an organization. It also

    explains how various structural variables and factors affect the aforementioned

    processes.

    Further, a detailed study on all innovations, changes and modifications that

    took place at Phase-II (325 MW Plant) of Vadinar Power Company Limited (A

    Captive Power Plant of Essar Oil, Jamnagar) is done.

    Signature of the Student: Signature of PS Faculty:

    Date: Date:

  • 8/11/2019 PS-1 Report

    4/40

    4 | Harnessing Creativity and Implanting Innovation in a Power Plant

    ACKNOWLEDGEMENT

    This report is a collective effort of many individuals and my gratitude to all of them

    cannot be conveyed in a few sentences.

    Firstly, I would like to thank Mr K.B. Makadia for his crucial role in development of

    Practice School-1 program and also for presenting us an opportunity to work on a project at

    Vadinar Power Company Limited.

    I am hugely indebted to Mr Snehal Pandya, my mentor, and Mr. Sandeep Patel for

    guiding me through this wonderful project and clearing my apprehensions and conceptual

    roadblocks on the way to successfully completing this project.

    I take this opportunity to thank Mr Indranil Ghosh and his team, for providing us with

    professional training on the basic features and components of a Power Plant.

    I also thank the Practice School Division for presenting us with such an opportunity to

    gain professional work exposure. Special Thanks to Mr Trilok Mathur for being a constant

    guide throughout this program.

  • 8/11/2019 PS-1 Report

    5/40

    5 | Harnessing Creativity and Implanting Innovation in a Power Plant

    TABLE OF CONTENTS

    TITLE PAGE ....................................................................................................................................................... 1

    COVER PAGE .................................................................................................................................................... 2

    ABSTRACT ........................................................................................................................................................ 3

    ACKNOWLEDGMENT ........................................................................................................................................ 4

    TABLE OF CONTENTS ........................................................................................................................................ 5

    HARNESSING CREATIVITY AND IMPLANTING INNOVATION ............................................................................. 6

    CREATIVITY......................................................................................................................................... 7

    SUPPORTIVE AND OBSTRUCTIVE FEATURES FOR HARNESSING CREATIVITY............................ 9

    INNOVATION.................................................................................................................................... 10

    INNNOVATION WITHIN THE ORGANIZATION....................................................................... 10

    INNOVATIONS AND MODIFICATIONS DONE AT VADINAR POWER COMPANY LIMITED ................................. 11

    AN OVERVIEW OF VADINAR POWER COMPANY LIMITED................................................................... 12

    CASE ANALYSIS OF VARIOUS INNOVATIONS AND MODIFICATIONS AT VPCL....................................... 14

    CASE NUMBER 1.................................................................................................................. 16

    CASE NUMBER 2.................................................................................................................. 16

    CASE NUMBER 3.................................................................................................................. 16

    CASE NUMBER 4.................................................................................................................. 16

    CASE NUMBER 5.................................................................................................................. 16

    CASE NUMBER 6.................................................................................................................. 16

    CASE NUMBER 7.................................................................................................................. 16

    CASE NUMBER 8.................................................................................................................. 16

    CASE NUMBER 9.................................................................................................................. 16

    CASE NUMBER 10................................................................................................................ 16

    CASE NUMBER 11................................................................................................................ 16

    CASE NUMBER 12................................................................................................................ 16

    CASE NUMBER 13................................................................................................................ 16

    CASE NUMBER 14................................................................................................................ 16

    CASE NUMBER 15................................................................................................................ 16

    CASE NUMBER 16................................................................................................................ 16

    CASE NUMBER 17................................................................................................................ 16

    CASE NUMBER 18................................................................................................................ 16

    CASE NUMBER 19................................................................................................................ 16

  • 8/11/2019 PS-1 Report

    6/40

    6 | Harnessing Creativity and Implanting Innovation in a Power Plant

    TABLE OF CONTENTS

    CASE NUMBER 20................................................................................................................ 16

    REFERENCES ................................................................................................................................................... 16

    GLOSSARY ...................................................................................................................................................... 16

  • 8/11/2019 PS-1 Report

    7/40

  • 8/11/2019 PS-1 Report

    8/40

    8 | Harnessing Creativity and Implanting Innovation in a Power Plant

    Creativity

    Numerous commentators have argued that enhancing the creative performance of an

    organisations employees is essential to it achieving competitive advantage. When employeesperform creatively they suggest novel and useful products, ideas or procedures that provide

    an organisation with important material for subsequent development and possible

    implementation.

    The Work Foundation sees significant benefits to be gained, both directly and

    indirectly, by encouraging creativity in any organisation. New ideas, for example, can benefit

    the organisation directly by leading to process improvements or into business areas that are

    more profitable or cost effective.

    An organisation may benefit indirectly from viewing feedback from the frontline as a

    valuable source of ideas about what is happening, and what may be changing, in the

    marketplace. Specific success indicators of initiatives, such as the number of staff suggestions

    that have been put forward and implemented, may be used to evaluate that particular scheme

    in the organisation.

    However, a lack of suggestions could actually be linked to many factors, such as the

    companys history of consultation, its acceptance of upward feedback or the level of trust

    amongst staff. Wider indicators, such as employee perceptions of communication and culture,

    are, therefore, important in any assessment of whether initiatives may succeed or fail.

    Some of the environmental features of organisations that support or obstruct creativity

    in the organisation will be explored further

  • 8/11/2019 PS-1 Report

    9/40

    9 | Harnessing Creativity and Implanting Innovation in a Power Plant

    Supportive and obstructive features for harnessing creativi ty

    Creativity literature has revealed that there are several key indicators that can be

    audited to establish how an organisation can improve its potential both for creative activityand for the sharing of ideas. These are explored, in brief, in this section, and include:

    Leadership and Strategic fit

    Motivation and Reward

    Organisational Design

    Knowledge and Information Management

    Capability

    LEADERSHIP AND STRATEGIC FIT

    One of the key features of an organisation successfully harnessing creativity is a clear

    leadership strategy. Clear communication of the organisations mission and business goals is

    essential if employees are to have an understanding of their role and engender ideas that fitor to explore customer generated ideas further with them.

    Where the direction is not clear, organisations may receive a high proportion of

    inappropriate ideas. An effective communication strategy here involves ensuring

    understanding of organisational goals, building general business knowledge, celebrating

    creativity and recognising successes.

    Supportive leadership behaviour involves senior managers showing demonstrable

    commitment to ideas, while supportive managers promote and reward innovation, and

    empower their teams.

  • 8/11/2019 PS-1 Report

    10/40

    10 | Harnessing Creativity and Implanting Innovation in a Power Plant

    MOTIVATION AND REWARD

    In addition to a vision, leaders must offer staff an environment that is conducive to

    building their commitment to working towards the organisations long term goals.

    This includes giving staff time and space to be creative. Such an environment relies

    on organisational commitment to positive industrial relations and on smart incentive and

    appraisal systems that accurately reflect the desired behaviour.

    The design of reward systems must, therefore, be carefully considered so as not to

    encourage behaviour damaging to a creative environment.

    An organisation needs to reward front line staff to demonstrate that it values their

    particular relationship with the customer and their understanding of how products and

    services are experienced. These staff should, therefore, have an incentive to be on the alert

    for changes in buying behaviour or for customer concerns.

    Reward systems that focus, for example, on achieving bottom line benefits, or are

    individually focused, can thwart creativity and limit idea-generating discussions between

    staff. Rewards only motivate behaviour if the rewards are valued, if they are closely linked to

    successful performance and if employees believe that they are able to perform successfully.

    Different types of professional groups value, and are motivated by, different rewards

    or recognition. For example, some knowledge workers may value increased status or

    recognition more than financial gain, while younger workers may want work style or

    lifestyle benefits rather than increased remuneration.

    If there is no incentive to devise and discuss new ideas, such activity will be perceived

    as time wasted and inevitably, all staff time will be devoted to achieving those performance

    targets that are rewarded or recognised.

  • 8/11/2019 PS-1 Report

    11/40

    11 | Harnessing Creativity and Implanting Innovation in a Power Plant

    ORGANIZATIONAL DESIGN

    There is no specific organisational structure identified as being creative, and this is

    unlikely to happen as organisational structures work best when they support the

    organisations business strategy. That said, an inappropriate organisational structure could act

    as a barrier to creativity, especially if it is bureaucratic and inflexible.

    Structural change, include outsourcing, corporate restructuring, and making the firm

    lean and mean, can also have a negative impact on the creativity process. Employee

    experience of poorly communicated and managed change can result in fear and uncertainty.

    The design of individual roles within the organisations overall structure should

    provide challenge, stimulation, a level of freedom, an opportunity to exercise discretion, to

    take initiative on a day-to-day basis, and to define elements of the role independently.

    Complex roles and lateral career paths both feature in creative organisations. Team

    building and team review activities should be in place to enable effective working and

    communication within teams. Communication flow between teams can be encouraged

    through various mechanisms such as cross functional team working, where virtual teams can

    meet together.

    Additionally, physical space can be designed to encourage group debate, though, for

    example, the creation of a place where individuals can elaborate on and test new ideas with

    peers before taking action. This can include open plan offices or relaxed areas away from the

    main office where small groups can discuss ideas together.

  • 8/11/2019 PS-1 Report

    12/40

    12 | Harnessing Creativity and Implanting Innovation in a Power Plant

    KNOWLEDGE AND INFORMATION MANAGEMENT

    Information systems should be in place that allows employees to store and share

    information and knowledge. This way, an individual may find creative solutions to a problem

    by looking at what is happening elsewhere in the organisation. They can also build on the

    current intellectual capital and add to it by offering different perspectives.

    Additionally, information systems should allow the company to be look beyond the

    boundaries of the organisation, accessing and storing market intelligence and by establishing

    a formal future watching process. Potential opportunities or problems needing suitable

    solutions can then be identifiable.

    An important barrier to creativity is idea ownership. One problem with idea

    ownership is that staff can be less inclined to be creative if they are suspicious that their ideas

    will be stolen by the company and they will receive no credit or reward, whilst conversely,

    the employer is concerned that the employee will leave with their ideas

    CAPABILITY

    Its vital that organisations do all they can to have the right people in the right places.

    This means starting with the right recruitment strategy, and hiring people with the potential

    for creativity. It is a misconception to believe that training can make people more creative,

    the organisation is better to recruit the right people with the right capability.

    Often people enter the workplace untrained to think laterally or search for alternative

    approaches to issues, and need to be encouraged to develop these skills. Support and

    encouragement may be provided through, for example, personal development plans,

    coaching, mentoring, learning groups, peer coaching or through the creation of other

    opportunities for sharing of learning. Opportunities for networking and sharing knowledge

    and ideas both internally and, as appropriate, externally, should be maximised by, for

    example, building communities of practice.

  • 8/11/2019 PS-1 Report

    13/40

    13 | Harnessing Creativity and Implanting Innovation in a Power Plant

    Innovation

    Many managers state that generating ideas isnt the problem, what actually poses the

    main dilemma is translating those ideas into relevant business solutions, i.e. implantinginnovation in their organisation.

    Prioritisation of investment for innovation requires central coordination and a good

    understanding of the whole business direction. Where the innovation involves market

    products, the pressure for innovation to be fast, good quality and low risk means that

    organisations need to be careful when selecting which ideas they are going to pursue, as they

    may need to invest significantly in development and testing.

    To manage risk and uncertainty, some leaders have had to look to alternative

    strategies, including pursuing licensing, joint ventures, strategic alliances or outsourcing, in

    order to gain the innovations that they require and, as this business-to-business interaction is

    growing, the speed, cost and quality of innovation in the external market are often better than

    can be guaranteed in-house.

    The open market can offer a lower risk strategy and a faster pace of innovation than

    an in-house process. This is especially so for those organisations which are not currently very

    innovative, where the option of buying innovative solutions when needed (rather than

    investing in high risk in-house projects) is attractive. Of course, this demand for innovation

    from the open market means that those organisations that pursue innovation as a core

    competency or market product can make big financial gains from the solutions market. For

    example, IBM and Disney make billions of dollars from selling innovation to other

    companies.

    It appears, therefore, that business success is not necessarily determined by how

    innovation wealthy an organisation is. Instead, what is important is the organisations

    ability to identify what innovation is needed and where it is able to purchase this

    innovation in the most cost-effective way.

  • 8/11/2019 PS-1 Report

    14/40

    14 | Harnessing Creativity and Implanting Innovation in a Power Plant

    I nnovation within the Organisation (I n-house)

    It is found that most of the factors pertinent to employee-led creativity also apply to

    in-house innovation. However, a few alternative or additional processes should be considered

    to support innovation in the organisation.

    ADDITIONAL SUPPORTIVE AND OBSTRUCTIVE FEATURES

    Constant liaison between the design (creative) and development (innovative)

    functions and the front line is important, especially to ensure staff buy in to the

    development process. Therefore good knowledge and information processes are needed to

    support the link between the creative and innovative sections of the organisation.

    Where there is a lack of shared knowledge, or where information processes actually

    prevent information from being shared, an organisations innovation potential can be

    restricted -resulting in limited or poor quality, innovation outputs that are not suitable for

    certain needs.

    Responsibility for decision-making and accountability for innovation need to be

    placed high in the organisation, and senior managers must be prepared to provide resources

    and ratify appropriate structures, whilst employee capability within the organisation must be

    flexible and arranged to be adaptable to react quickly to new market conditions and customer

    needs.

    Decision-making criteria for selecting the innovation projects to be pursued should be

    market-driven, and directed at the present rather than the future. These should also start

    small, specific, simple and focused, while at the same time building on existing

    organisational strengths. Identifying the necessary employee skills required, scoping likely

    timescales, and costing an innovation project to be produced in-house are all processes that

    are plagued with difficulty.

  • 8/11/2019 PS-1 Report

    15/40

    15 | Harnessing Creativity and Implanting Innovation in a Power Plant

    WORK PROCESSES

    Project structures, rather than functional ones, are more likely to foster innovation.

    Whilst innovation in some places may be organised as a separate process in the organisation,

    or conducted by a specific department, there needs to be a joined-up approach across the

    whole organisation. Integration between different disciplines is therefore vital, with a

    strongly team-focused approach.

    Innovation activities also need to be fully integrated into policies and practices. At the

    same time, flexibility needs to be applied in rules and guidelines. Once an innovation project

    is at the stage of further exploration and investment, systematic analysis and review should be

    planned repeatedly into the project process.

    A number of hard strategies need to be in place to provide structure and rigorous

    thinking. Repeated evaluation means time and money can be spent efficiently. End user needs

    are most likely to be met where processes are in place to gather, and listen to, customer

    inputs. The processes in place need to be sensitive to, and flexible around, the speed of

    change in the market.

    BENEFITS AND WEAKNESSES OF INNOVATION WITHIN THE ORGANISATION

    In-house innovation means that those who have ideas in the organisation can have

    input into the development of their ideas. Where activities are in-house, there is less need for

    broader strategic involvement and coordination. Innovation can occur at a local level.

    Research suggests that where rigorous and staged processes are introduced, hard benefits

    result.

    However, one of the main stumbling blocks for organisations building an in-house

    innovation capability is that there are commonly too few processes to support staff and

    resourcing. Building the right culture can also be very difficult. Speed can also be an issue:

    market changes can render knowledge and understanding of whats needed and how to do it

    obsolete as fast as such knowledge and understanding can be mastered.

  • 8/11/2019 PS-1 Report

    16/40

    16 | Harnessing Creativity and Implanting Innovation in a Power Plant

    INNOVATIONS AND MODIFICATIONS

    DONE AT

    VADINAR POWER COMPANY LIMITED

    An Overview of Vadinar Power Company Limited:

    Vadinar Power Company Ltd is a captive power plant of Essar Oil Ltd at Jamnagar,

    Gujarat. Recently VPCL has commissioned its coal based thermal power plant with

    pulverized coal fired boilers and extraction cum condensing turbines. VPCL is also unique

    because its the only power plant in the entire world to use all three types of firing in the

    same power plant.

    Collaborations with renowned foreign companies like Siemens Bruno, Yokogawa,

    Mitsubishi etc. ensure that VPCL uses the state-of-the-art technology for power production.

    Initially, VPCL was a 77MW oil fired plant catering to the steam and power needs of

    the refinery. This plant could also be run on gas in case of an emergency situation in the oil

    fired boiler or the oil fuel lines. The plant has 2 Turbines of 38.5MW capacity which provide

    power and 3 boilers of 175TPH capacity for providing steam. These boilers are horizontallyfired boilers and use natural circulation providing latent heat. The commonly used fuels are

    Light Diesel Oil (LDO), Heavy Furnace Oil (HFO).

    As the need rose, VPCL was expanded to phase-1 (Gas-fired) and consecutively to

    phase-2 (solid-fired). Phase-1 is a Gas Turbo Generator, which uses fuel like Natural Gas,

    Naphtha etc. These GTGs work on the principle of Brayton cycle. The main purpose of

    phase-1 is to switch load immediately without any time lag, in case of any tripping in other

    plants. This plant has 2 GTG of 110MW capacity and 2 Heat Recovery Steam Generator of

    315TPH capacity.

    The plant was further expanded to a larger capacity plant, the Phase-2. Phase-2 is coal

    cum oil fired plant. During start-up oil is used and coal is used after the plant becomes stable.

    This plant is the current supplier to the refinery. The load goes onto the GTG in case of any

    tripping in this plant. This plant has 2 STG of 110MW capacity and 1 STG of 92.8MW

    capacity which function on the steam produced from 3 Boilers of 715TPH capacity. The

    boilers are horizontal fired boilers and use assisted circulation owing to their higher capacity.

  • 8/11/2019 PS-1 Report

    17/40

    17 | Harnessing Creativity and Implanting Innovation in a Power Plant

    Another reason for switching to phase-2 was the rising price of Natural Gas.

    Production using coal was approximately twice as cheap as producing using Gas. But the

    start-up time for coal based plants are high, so the GTGs have been kept under shutdown but

    have not been replaced. The phase-1 plant is not meant for continuous running but for smooth

    transition of load from phase-2 to base plant when the phase-2 plant trips.

    The start-up time of a GTG is only 15 seconds but running costs are high. So the plant

    is run until the base plant comes into operation. In case of failure of all three, power is drawn

    from the grid until either of the plant goes into running. This kind of fuel flexibility is also

    unique to VPCL. Another advantage of the base plant is that it can run on refinery oil, which

    is a by-product of refinery. This also proves advantageous as the running costs are low when

    refinery oil is used, but efficiency is low.

    Case Analysis of Various Innovations and Modifications at VPCL:

    Since the inception of Phase-II at Vadinar Power Company Limited, the plant has

    faced many technical roadblocks in its pursuit of maintaining consistency. To address these

    issues, many creative ideas were put forward and corresponding modifications and

    innovations have been done.

    The Case Analysis of such innovations and modifications done at Phase-II of VPCL is

    given below.

    The analysis includes:

    Identification of the Problem

    Introduction to the Problem and its Consequences

    The modifications or changes implemented to solve the problem

    Current status of the problem in-analysis.

  • 8/11/2019 PS-1 Report

    18/40

    18 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 1:

    Problem I dent i f i cat ion:

    BED ash hopper level, furnace flame and bottom un-burnt ash inspection was notpossible.

    I ntr oduction to th e Pr oblem and i ts Consequences

    Bottom ash is part of the non-combustible residue of combustion in a furnace.

    In an

    industrial context, it usually refers to coal combustion. When pulverized coal is burned in a

    dry bottom boiler, approximately 80 per cent of the unburned material is captured from the

    chimney as fly ash. The remaining 20 per cent is bottom ash, which is collected in a water-

    filled hopper at the bottom of the furnace. In wet bottom boilers, bottom ash is kept in a

    molten state and collected when it flows into the ash hopper below. The water in the ash

    hopper immediately fractures the molten material into crystallized pellets. Hence inspection

    of bottom ash is quite important.

    Solu ti on Done / Acti ons Taken

    Peep Holes were arranged on both RHS and LHS of the boiler at 9 metre elevation, hence

    making it easy for Inspection and taking further course actions.

    Cur r ent Status

    Peep Holes have been installed in both the boilers; this has led to an easy and safe monitoring

    of BED ash hopper level and also the furnace flame.

  • 8/11/2019 PS-1 Report

    19/40

    19 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 2:

    Problem I dent i f i cat ion:

    Only Economiser filling was not possible after identifying economiser tube leakage.

    Note: Economiser filling starts after boiler water wall fill up to 38 meters.

    I ntr oduction to th e Pr oblem and i ts Consequences

    The economiser is a heat exchanger through which the feed-water is pumped. The

    feed-water thus arrives in the boiler at a higher temperature than would be the case if no

    economiser was fitted. Less energy is then required to raise the steam.

    But, during start-up feed water starts filling the boiler from below. Hence, it would

    take very long time for feed-water to reach the Economizer. There was no provision given to

    test Economiser leakage, when the plant was running.

    Solu ti on Done / Acti ons Taken

    A separate line was erected from boiler filling header into the Economiser through its

    drain.

    Cur r ent Status

    New lines were erected in both the boilers. During economiser tube leakage, onlyEconomizer filling is now possible in order to identify them.

  • 8/11/2019 PS-1 Report

    20/40

    20 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 3:

    Problem I dent i f i cat ion:

    There was no tapping point given to perform Boiler Hydro Static test in the initialscheme.

    I ntr oduction to th e Pr oblem and i ts Consequences

    In a large Thermal Power Plant there are about Ten Thousand tons of steel tubes, pipes,

    drums and other vessels that contain the high pressure steam. More than Sixty Thousand weld

    joints make the Boiler an integrated vessel to produce steam. Design calculations,

    metallurgical inspections and manufacturing inspections assure the integrity of every part and

    every weld joint. Hydrostatic Testis the last of the test to ensure completion, compliance

    and safety before the boiler produces steam.

    The test consists of filling the Boiler with water and pressurizing the water to at least one

    and half times the maximum operating pressure for a short time. Every part is subject to more

    than the maximum stress it will normally encounter. This is an endurance test; any weak link

    fails during the test.

    Solu ti on Done / Acti ons Taken

    A permanent arrangement was made, in order to execute a Hydrostatic Test. A

    tapping was taken from the valve of Intermittent Blow Down line.

    Cur r ent Status

    Without much modification, hydro-pump can now be used to execute Boiler

    Hydrostatic Test during the annual shut down.

  • 8/11/2019 PS-1 Report

    21/40

    21 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 4:

    Problem I dent i f i cat ion:

    The Platen Super heater in Boiler No. 4 was failing repeatedly.

    I ntr oduction to th e Pr oblem and i ts Consequences

    The Platen Super-heater is located just above the combustion zone at the top of the

    furnace. Mainly it receives radiant heat from the furnace and the steam is further superheated.

    There are hanging panels arranged in rows across the width of the furnace. Each panel is

    connected with its own small inlet and outlet headers, which are in turn is connected to big

    and long common headers, on both inlet and outlet sides.

    Initially some metal coins were left inside the super-heater, which were left inside the

    super-heater during erection. The presence the coins causes steam to accumulate at certain

    points, thereby causing cavitation.

    Solu ti on Done / Acti ons Taken

    After studying the foreign materials found in the Platen Super Heater Inlet header and

    the Primary Outlet and Secondary inlet header. All headers were inspected and foreign

    materials were removed.

    Cur r ent Status

    Boiler is now running without super-heater tube failure.

  • 8/11/2019 PS-1 Report

    22/40

    22 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 5:

    Problem I dent i f i cat ion:

    Unsafe operation approaches used for operating Mill Service Water line (Fogging andSwirling).

    I ntr oduction to th e Pr oblem and i ts Consequences

    Pulveriser mills are cleaned during the Annual shut down. Firstly inert cleaning is

    done to remove fumes and poisonous gases by using steam. After this water is pumped

    through the Mill Service Water Line, which is used to clean the un-burnt coal and other

    debris.

    Solu ti on Done / Acti ons Taken

    The mill service water line was modified and re-routed. The valve location was also

    shifted to ground floor for easy, fast and safe operation.

    Cur r ent Status

    The valve operation is now done safely and also at a quicker pace.

  • 8/11/2019 PS-1 Report

    23/40

    23 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 6:

    Problem I dent i f i cat ion:

    Regular fires noticed in Mills air duct bellow.

    I ntr oduction to th e Pr oblem and i ts Consequences

    The presence of combustible materials in the pulveriser is usually the largest

    contributor to pulveriser fires. In most cases, pulveriser fires begin in the under bowl area of

    the pulveriser that is a very hot environment with an abundance of air. Accumulations of

    debris or coal anywhere in the pulveriser will increase the chance of a mill fire.

    The pyrite removal chute should be inspected often to ensure rejected material isremoved from the under bowl area. Stoppage of pyrite chute flow can cause debris and-or

    coal to back-up into the primary air ducting.

    Solu ti on Done / Acti ons Taken

    The location of mills air ducting valve wasshifted from shut off damper i.e. bellow

    out inlet to mill inlet duct. This is done so that coal dust and water do not accumulate on

    millsinlet bellow.

    Cur r ent Status

    After relocation of air-ducting valve, bellow fires have been stopped.

  • 8/11/2019 PS-1 Report

    24/40

    24 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 7:

    Problem I dent i f i cat ion:

    Regular fires noticed in Mills air duct bellow.

    I ntr oduction to th e Pr oblem and i ts Consequences

    The presence of combustible materials in the pulveriser is usually the largest

    contributor to pulveriser fires. In most cases, pulveriser fires begin in the under bowl area of

    the pulveriser that is a very hot environment with an abundance of air. Accumulations of

    debris or coal anywhere in the pulveriser will increase the chance of a mill fire.

    The pyrite removal chute should be inspected often to ensure rejected material is

    removed from the under bowl area. Stoppage of pyrite chute flow can cause debris and-or

    coal to back-up into the primary air ducting.

    Solu ti on Done / Acti ons Taken

    Special coverage was procured and installed within the bellow. This is done to reduce

    the accumulations of debris or coal on the bellow, thus avoiding fires with the bellow

    Cur r ent Status

    After relocation of air-ducting valve, bellow fires have been stopped.

  • 8/11/2019 PS-1 Report

    25/40

    25 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 8:

    Problem I dent i f i cat ion:

    There was a leakage in yoke seal bellow of Mill 1C.

    I ntr oduction to th e Pr oblem and i ts Consequences

    A bellow is a device constructed to furnish a strong blast of air. It has many

    applications, in particular blowing on a fire to supply it with air.

    Yoke seal bellow is used to protect the mill gear box by acting as a shock absorber. It

    also gives allowance for mill expansion and contraction caused by fluctuations in

    temperature.

    Solu ti on Done / Acti ons Taken

    The bellow leakage was rectified by applying special tools and ideas.

    Cur r ent Status

    Without much availability of material, mill bellow is repaired and mill is kept in

    service.

  • 8/11/2019 PS-1 Report

    26/40

  • 8/11/2019 PS-1 Report

    27/40

    27 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 10:

    Problem I dent i f i cat ion:

    There was no spare pump available for lube oil pump during its failure in Mill B of

    Boiler no. 4.

    I ntr oduction to th e Pr oblem and i ts Consequences

    The liquid lubricant is used to cool the system by being constantly circulated to and

    from a cooler part of the system.

    Lube oil pumping applications demand a pump that provides reliability and extended

    service life with a minimum of maintenance. The typical Lube Oil pump must also be capable

    of operation over a wide range of temperature and liquid viscosity conditions.

    Solu ti on Done / Acti ons Taken

    A spare lube oil pump from Boiler no. 5 was retro fitted at Mill B of Boiler no. 4. This

    pump was henceforth used as a back-up.

    Cur r ent Status

    A spare pump is available in case of emergency. The mill has been continuously

    available for operation.

  • 8/11/2019 PS-1 Report

    28/40

    28 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 11:

    Problem I dent i f i cat ion:

    There were abnormal sounds from Rotatory Air Pre-Heater and both the drives were

    shifted outside.

    I ntr oduction to th e Pr oblem and i ts Consequences

    The Rotating air pre heater consists of a central rotating-plate element installed within

    a casing that is divided into two (bi-sectortype), three (tri-sectortype) or four (quad-

    sectortype) sectors containing seals around the element. The seals allow the element to rotate

    through all the sectors, but keep gas leakage between sectors to a minimum while providingseparate gas air and flue gas paths through each sector.

    Solu ti on Done / Acti ons Taken

    After inspection it was found that one of the sector joints was found open. The same

    was repaired as per procedure. In both the boilers each and every joint of all the Rotatory Air

    Pre Heaters were inspected and defects in the joints were repaired as per procedure.

    Cur r ent Status

    All the Rotatory Air Pre-Heaters are working in good condition.

  • 8/11/2019 PS-1 Report

    29/40

    29 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 12:

    Problem I dent i f i cat ion:

    While in operation, the man-hole was inaccessible as it was not being fully opened

    due to its interference with the platform beam.

    I ntr oduction to th e Pr oblem and i ts Consequences

    Manholes are an oval access door into the boiler shell, used for maintenance and

    cleaning. Manholes are sealed with a removable door from the inside. As they are oval, this

    door may be turned and lifted out through the hole. Doors are clamped in place from the

    outside with one or two bridge clamps spanning the hole and tightened down with a nut on astud.

    Solu ti on Done / Acti ons Taken

    Platform beam was shifted so that man-hole could be opened fully and is accessible

    while the boiler is running.

    Cur r ent Status

    An activity such as bottom ash hopper chock-age removal / trimming is now possiblewithout stoppage, even while the plant is running.

  • 8/11/2019 PS-1 Report

    30/40

    30 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 13:

    Problem I dent i f i cat ion:

    There was no coal sampling arrangement given at coal feeder. Pipe is made up of SS.

    Any hot work would have resulted in longer downtime and coal ignition because of heat.

    I ntr oduction to th e Pr oblem and i ts Consequences

    Sampling of coal is an important part of the process control. Continuous measurement

    of ash, moisture, kCal (BTU), Sulphur Fe, Ca, Na, and other element constituents of the coal

    are to be reported.

    Solu ti on Done / Acti ons Taken

    Without any hot work or any extra opening made into SS pipe, special arrangement

    for coal sampling with valve fitted into coal feeder through MOV pocking window.

    Cur r ent Status

    Coal sampling is now possible without any hot work or extra opening in SS coal pipe.

    Samples can be obtained whenever required.

  • 8/11/2019 PS-1 Report

    31/40

    31 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 14:

    Problem I dent i f i cat ion:

    There was space constraint for the soot blower station and also spillage of condensate

    from the station.

    I ntr oduction to th e Pr oblem and i ts Consequences

    Soot is impure carbon particles resulting from the incomplete combustion

    of hydrocarbons.

    A soot blower is a system for removing the soot that is deposited on the furnace tubes

    of a boiler during combustion. Steam is normally used as a medium for blowing away the

    soot since capital cost of steam pressure reducing equipment and drain is less than the cost

    of compressors, motors and control of air systems.

    Solu ti on Done / Acti ons Taken

    Soot blower drain station is shifted to 4 metres elevation from ground floor and extra

    condensate is now diverted to IBD tank.

    Cur r ent Status

    The problem of space constraint is now solved. Ground floor is now clean and better

    looking. Condensate spillage problem solved.

  • 8/11/2019 PS-1 Report

    32/40

    32 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 15:

    Problem I dent i f i cat ion:

    There was space constrained at 8 metres elevation on both LHS and RHS of boiler

    during sky climber erection, dismantling, storage and chock-ages cleaning in bed ash hopper.

    I ntr oduction to th e Pr oblem and i ts Consequences

    Preparation and assembly of sky climbers is required for the purpose of inspection or

    repair of boiler pressure parts. Sufficient and skilled workers are deployed for erection and

    safe operation making of Sky climber. Bottom ash is kept in a molten state and collected

    when it flows into the ash hopper below. The water in the ash hopper immediately fracturesthe molten material into crystallized pellets. Hence inspection of bottom ash is quite

    important.

    Solu ti on Done / Acti ons Taken

    A new platform installed and modified at 8 meters elevation on both LHS and RHS.

    There are also interconnecting platforms installed between LHS and RHS.

    Cur r ent Status

    Easy shifting and storage of sky climbers is possible well advance so as to save

    shutdown time. Bed ash hopper chock-age removal is now easily possible. Movement from

    LHS to RHS is possible, without the usage of staircase.

  • 8/11/2019 PS-1 Report

    33/40

    33 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 16:

    Problem I dent i f i cat ion:

    Boiler Drum, Boiler and second pass expansion scales were difficult to read.

    I ntr oduction to th e Pr oblem and i ts Consequences

    The boiler expands and contracts with heating and cooling. Hence, expansion joints

    are built into the refractory to allow for the thermal expansion and contraction. Expansion

    scales are used to measure the magnitude of expansion.

    Solu ti on Done / Acti ons Taken

    All expansion scale were modified and installed at an easily approachable location.

    Cur r ent Status

    It is now possible to read all expansion scales are being read easily and with safer

    approach.

  • 8/11/2019 PS-1 Report

    34/40

    34 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 17:

    Problem I dent i f i cat ion:

    Bend erosion on both front and rear sides of economiser

    I ntr oduction to th e Pr oblem and i ts Consequences

    Water is supplied at the inlet manifold of Economiser, which after passing through the

    tubes, goes into the Economiser outlet manifold. In the process water picks up heat from the

    flue gas. Hot water then goes into the steam drum.

    Erosion caused near the pipe bends in the economiser is termed as Bend Erosion.

    Erosion of tubes by localised high flue gas velocity.

    Solu ti on Done / Acti ons Taken

    Crimped wire mesh was installed on both front and rear sides of economizer to

    prevent erosion at bend. This doesnt allow localisation of high temperature flue gas. Thus,

    greatly reducing the chances of bend erosion.

    Cur r ent Status

    This has reduced the chances of economiser bend erosion to a large extent.

  • 8/11/2019 PS-1 Report

    35/40

    35 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 18:

    Problem I dent i f i cat ion:

    Shear pin in all the Multi Louver Dampers used to get sheared, also damper flap used

    to dislodge from the shaft

    I ntr oduction to th e Pr oblem and i ts Consequences

    Multi Louver Damper is a damper, having multiple blades which are mechanically

    linked so that they open or close simultaneously.

    A shear pin is a safety device designed to shear in the case of a mechanical overload,

    preventing other, more-expensive parts from being damaged. As a mechanical sacrificial part

    Solu ti on Done / Acti ons Taken

    All the MLD shafts to spigot. Shaft and flap welded and locked from both inside and

    outside.

    Cur r ent Status

    Damper passing and flap dislodge problem is now solved and it is now fullyoperational.

  • 8/11/2019 PS-1 Report

    36/40

    36 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 19:

    Problem I dent i f i cat ion:

    Discharge bellow leakages found in Primary Air fan 1B.

    I ntr oduction to th e Pr oblem and i ts Consequences

    A bellow is a device constructed to furnish a strong blast of air. It has many

    applications, in particular blowing on a fire to supply it with air.

    Solu ti on Done / Acti ons Taken

    It was not possible to patch the bellow from outside with any type of solution because

    of special bellow material, hence patching was done inside by using extra joint sheet to arrest

    leakages.

    Cur r ent Status

    Leakages are henceforth arrested and the PA fan is working in a satisfactory

    condition.

  • 8/11/2019 PS-1 Report

    37/40

    37 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CASE NUMBER 20:

    Problem I dent i f i cat ion:

    Air-line connecting the view glass of the coal feeder was purging.

    I ntr oduction to th e Pr oblem and i ts Consequences

    Coal dust is generally accumulated over the view glass. Hence air-line is used to clear

    this accumulated coal-dust.

    Solu ti on Done / Acti ons Taken

    The purging air-line of the coal feeder view glass rubber hose was replaced with SS

    flexible hose and a quick coupler was also provided for easy opening and closing of door.

    Cur r ent Status

    Air-line hose need not be replaced every time and is consistently available.

  • 8/11/2019 PS-1 Report

    38/40

    38 | Harnessing Creativity and Implanting Innovation in a Power Plant

    CONCLUSION

    With stakeholder expectations and environmental factors changing fast, ideas for

    adaptation and advantage are invaluable to organisations. Stakeholders are now multiplying

    in number, and the demands that they place on an organisation may range from keeping up

    with the needs of talented staff, and offering customers more choice and better service, to

    boosting the bottom line for shareholders. At the same time, companies are also being placed

    under greater pressure by numerous external changes in an increasingly competitive

    marketplace, as is very well reported in business management discourse.

    The need for Harnessing Creativity and Implanting Innovation at work-places is

    now higher than ever. Respondents now see innovation as increasingly important to the future

    of their companies, and that a growing number of organisations identify it as their most

    dominant business strategy.

    Vadinar Power Company Limited has done a brilliant job, in being able to implant in-

    house innovations. The employees here have addressed various issues and identified solutions

    to many problems, sometimes during erection of the plant itself. They have successfullymanaged to channel creative ideas into useful outcomes. Hence being able to nurture and

    stimulate creative thoughts and innovation.

  • 8/11/2019 PS-1 Report

    39/40

  • 8/11/2019 PS-1 Report

    40/40

    Glossary

    Blow-down: Periodic venting of water from the boiler. This water contains the most

    concentrated precursors for sludge build-up, so by venting it whilst still dissolved, the build-up is reduced. When early marine boilers were fed with salt water, they would be blown-

    down several times an hour.

    Cladding: The layer of insulation and outer wrapping around a boiler shell, particularly that

    of a steam locomotive. In early practice this was usually wooden strips held by brass bands.

    Later and modern practice is to use asbestos insulation matting (or other, less hazardous,

    fibres) covered with rolled steel sheets. The outer shape of the cladding is often a

    simplification of the underlying boiler shell.

    Damper: An adjustable flap controlling the air admitted beneaththe fire-bed.

    Down-comer: Large external pipes in many water-tube boilers, carrying unheated cold water

    from the steam drum down to the water drum as part of the circulation path.

    Hand-hole: A small manhole, too small for access but useful for inspection and washingout the boiler.

    Manhole: An oval access door into the boiler shell, used for maintenance and cleaning.

    Manholes are sealed with a removable door from the inside.

    Scale: Dissolved minerals from hard water that precipitate out in the steam space around

    the water-level.

    Steam drum: A cylindrical vessel mounted at a high point of a water-tube boiler, where dry

    steam may separate above the water level, so that it may be drawn off without risk

    of priming.

    Water-wall: A furnace or other wall within a boiler enclosure that is composed of numerous

    closely set water-tubes.