proposed modeling updates to chp in the teppc base case december 12, 2011 arne olson, partner nick...
TRANSCRIPT
Proposed Modeling Updates to CHP in the TEPPC Base Case
December 12, 2011
Arne Olson, Partner
Nick Schlag, Consultant
Background
LBNL has funded E3 to investigate the representation and modeling of existing cogeneration in the TEPPC dataset
The scope of E3’s work has included two tasks:
1. Reconciliation of TEPPC dataset with other known databases of CHP power plants (EIA, eGRID, ICF)
2. Recommendations for adjustments to CHP modeling in PROMOD
2
Generator Reconciliation
3
Reconciliation of TEPPC Database with EIA Generator List
The under-representation of CHP capacity in the TEPPC generator set is primarily a result of generators not being correctly identified as cogeneration resources
The remaining gap is roughly evenly split between two components:
1. Large industrial CHP facilities not represented in TEPPC
2. Small facilities that operate predominantly behind-the-meter and so are implicitly accounted for on the load side
4
State EIA 2009TEPPC
Before After
Arizona 146 - -
California 7,233 1,169 6,452
Colorado 1,032 - 834
Idaho 186 - -
Montana 82 - -
Nevada 390 61 381
New Mexico 161 - 122
Oregon 1,734 - 1,438
Utah 117 58 58
Washington 1,104 42 828
Wyoming 160 - -
Total* 12,346 1,330 10,113
CHP Nameplate Capacity by State (MW)
* Total shows CHP in US states only
Results of Reconciliation
Based on the results of the reconciliation, E3 is confident that most of the existing CHP capacity in the WECC is already represented in the TEPPC data set (though may not be flagged as such)
• With the limited time in the current study cycle, E3 does not recommend adding any units to the data set
E3 will provide TEPPC with an updated list of generators that qualify as cogeneration facilities
5
Modeling CHP Operations
6
Challenges in Modeling CHP
Modeling the operations of combined heat and power generators in a production simulation setting is challenging for several reasons:
1. Thermal Load Service: CHP operations are often dictated by the size of the thermal load, so their responsiveness to wholesale market conditions are limited
2. On-Site Electric Use: Many CHP plants are located on-site at industrial facilities, and their generation is split between on-site use (behind-the-meter) and exports to the grid
There is no single rule of thumb that accurately predicts the hourly operations of plants that are operated for cogeneration
7
Data Sources for CHP Operational Modeling
To determine the best methodology to adopt for CHP modeling in PROMOD, E3 has consulted the following sources:
• EIA Forms 860 & 906/920
• EPA Continuous Emissions Monitoring System (CEMS) database
• CPUC 2012 Net Qualifying Capacity (NQC) list
• CAISO Transmission Plan (Xiaobo Wang)
• NWPCC (Jeff King)
• CAISO Integration Analysis
8
Modeling CHP Operations
E3 recommends retaining a default methodology to model CHP operations that designates plants as must-run and dispatches them based on a measure of net heat rate
Based on available data, E3 recommends an adjustment to this default for the following specific regional cases:
• Northwest IPP/Utility CHP plants (based on CEMS profiles)
• CAISO CHP (based on CPUC NQC capacity)
• Non-dispatchable
• Dispatchable
9
Default CHP Assumptions
Characteristics
• Default assumptions would apply to roughly ~2,000 MW of nameplate CHP capacity
• Classified by EIA as either “IPP CHP” or “Electric Utility” (assumed to deliver all generation to the grid; also assumed to have some degree of generation flexibility)
Proposed PROMOD methodology
• Designate plants as must-run
• Adjust plant heat rates to net heat rate based on EIA 906/920 data gathered from 2007-2010
• Use CEMS hourly data to revise minimum operating levels for plants (not available for all units—use a rule of thumb based on available data)
• Retain other plant operating characteristics (max capacity)
10
Default CHP Assumptions
11
Advantages
Use of net heat rate accurately reflects plant emissions attributable to electricity sector
Use of net heat rate captures the true marginal cost to generate electricity (assuming demand for thermal load service is larger than plant capacity)
Must-run designation captures general trends in CHP operations
Disadvantages
Use of average net heat rate based on historical data prohibits the use of a heat rate curve to simulate efficiencies at partial load conditions
For some units, flexibility and responsiveness to wholesale signals may still be overstated—even with must-run designation
Northwest IPP/Utility CHP
In the specific case of the large cogeneration plants in the Northwest (roughly 2,100 MW), data from the Continuous Emissions Monitoring System database maintained by the EPA shows a systematic shutdown of plants during the spring (high hydro months)
• This finding is corroborated by EIA 906/920 data, which shows lower capacity factors for these plants in the spring
For large plants located in the Northwest, E3 recommends allowing full shutdown during high hydro conditions
• Remove must-run designation during spring months
12
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec0
100
200
300
400
500
600
Hou
rly M
W
Chehalis Generation Facility (Non-CHP)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec0
100
200
300
400
500
600
Hou
rly M
W
Coyote Springs (CHP)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec0
100
200
300
400
500
600
Hou
rly M
W
Klamath Cogeneration Project (CHP)
Operation of Northwest Cogeneration Facilities
13
Throughout most of the year, CHP plants maintain
a range of operations between minimum and
maximum load conditions; similarly sized fully flexible gas units show a greater
range of flexibility
The exception to this trend is in the spring, when CHP and flexible gas units alike tend to reduce operations
systematically to accommodate high hydro
conditions
Data Source: EPA Continuous Emissions Monitoring Database (2009)
CAISO Non-Dispatchable Cogeneration
Characteristics
• ~4,900 MW of nameplate CHP capacity
• Classified by CPUC as “Non-Dispatchable” (not responsive to wholesale markets)
• Often responsible for on-site electric load service (only a fraction of generation is exported)
Proposed PROMOD methodology
• Set monthly maximum capacity equal to monthly NQC capacity based on CPUC 2012 Net Qualifying Capacity List
• Set minimum capacity equal to 100% of maximum capacity
• Designate plant as must-run
• Adjust heat rate to net heat rate based on historical plant data from EIA 906/920 (2007-2010)
14
CAISO Non-Dispatchable Cogeneration
15
Advantages
NQC provides a reliable measure of the fraction of plant capacity that will be available for export to grid (NQC methodology used in the CAISO’s Integration Analysis)
Monthly NQC values capture seasonal production trends
Must-run methodology limits flexibility of CHP resources
Use of net heat rate accurately reflects plant emissions attributable to electricity sector
Disadvantages
Flat hourly production profile does not reflect actual hour-to-hour plant operations
CAISO Dispatchable Cogeneration
Characteristics
• ~1,200 MW of nameplate CHP capacity
• Classified by CPUC as “Dispatchable”
• Plants export all generation to grid
Proposed PROMOD methodology
• Adjust heat rate of plants to reflect net heat rate based on EIA 906/920 data
• Do not designate plants as must-run
• Retain other plant operating characteristics (min/max capacities)
16
CAISO Dispatchable Cogeneration
17
Advantages
Use of net heat rate accurately reflects plant emissions attributable to electricity sector
Use of net heat rate captures the true marginal cost to generate electricity (assuming demand for thermal load service is larger than plant capacity)
Disadvantages
Use of average net heat rate based on historical data prohibits the use of a heat rate curve to simulate efficiencies at partial load conditions
Thank You!Energy and Environmental Economics, Inc. (E3)
101 Montgomery Street, Suite 1600
San Francisco, CA 94104
Tel 415-391-5100
Web http://www.ethree.com
Arne Olson, Partner ([email protected])
Nick Schlag, Consultant ([email protected])