proposed distribution centre extension …...associated with the proposed extension of the existing...
TRANSCRIPT
LIDL GREAT BRITAIN LIMITED
PROPOSED DISTRIBUTION CENTRE EXTENSION
BRIDGEND
TRANSPORT STATEMENT
19-00657/TS/01/A
MARCH 2020
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 1 of 24
DOCUMENT SIGNATURE AND MODIFICATION SHEET
Project Details
Project Title: Proposed Distribution Centre Extension
Project No: 19-00657 Document No: TS/01/A
Client: Lidl Great Britain Limited
- Name Signature Date
Prepared by
Joseph Cassinelli
March 2020
Checked and
Approved for Issue
by
Matthew Anderson
March 2020
Modification Details
Rev Date Description Checked By
-
A
January ‘20
March ‘20
Original report issued
Report amended to reflect revised layout
JC
JC
Issued By:
Corun Associates Limited
Swansea
T 01792 229155
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 2 of 24
CONTENTS Page
1 INTRODUCTION 4
1.1 Background 4
1.2 Scope 4
2 EXISTING CONDITIONS 5
2.1 Site Summary 5
2.2 Local Highway Network 5
2.3 Pedestrian Facilities 6
2.4 Cycle Facilities 8
2.5 Public Transport Facilities 9
2.6 Local Highway Safety 10
3 LOCAL AND NATIONAL PLANNING GUIDANCE 12
3.1 Overview 12
3.2 Policy Objective 12
3.3 Planning Policy Wales (December 2018) 12
3.4 Bridgend CBC LDP (Adopted September 2013) 16
3.5 Active Travel (Wales) Act 2013 17
3.6 Conclusion 17
4 DEVELOPMENT PROPOSAL 18
4.1 Proposed Development 18
4.2 Access 18
4.3 Parking 18
5 SITE TRAFFIC 20
5.1 Introduction 20
5.2 Existing site traffic 20
5.3 Proposed site traffic 21
5.4 Conclusion 22
6 SUMMARY AND CONCLUSION 23
6.1 Summary 23
6.2 Conclusion 23
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 3 of 24
FIGURES
Figure 2.1 – Site in Local Context (within text)
Figure 2.2 – Site in Strategic Context (within text)
Figure 2.3 – Bridgend Integrated Network Map Extract (within text)
Figure 2.4 – PIA Extract (within text)
APPENDICES
Appendix A – Proposed Site Layout
Appendix B – Existing Site Traffic Survey
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 4 of 24
1 INTRODUCTION
1.1 Background
1.1.1 This Transport Statement (TS) has been produced by Corun Associates Ltd (Corun) on behalf
of Lidl Great Britain Limited, the applicant, to examine the highway and transportation issues
associated with the proposed extension of the existing Lidl distribution centre in Bridgend.
1.1.2 The proposal seeks an extension to the warehouse of 5,065m2 along with an extension to
ancillary areas such as administration (1,336m2), outside seating, driver’s lounge, staff
parking and HGV parking. The total extension therefore amounts to approximately 6,401m2
GFA.
1.1.3 The total proposed building area, as measured from the submitted layout, is approximately
38,775m2 GFA.
1.1.4 The proposed site layout is contained herein as Appendix A.
1.2 Scope
1.2.1 This report will discuss the following key transportation issues arising from the proposals:
(i) the existing site location and transport infrastructure;
(ii) analysis of personal injury traffic accident data;
(iii) the site’s compliance with applicable transport policy;
(iv) the development proposal; and
(v) development-generated vehicular traffic.
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 5 of 24
2 EXISTING CONDITIONS
2.1 Site Summary
2.1.1 The site is located within the existing and well-established Waterton Industrial Estate on
Cowbridge Road in Bridgend, near the border with the Vale of Glamorgan.
2.1.1 The site is shown in a local context in Figure 2.1.
Figure 2.1: Site in Local Context with Distance Isochrones
2.2 Local Highway Network
2.2.1 The site is accessed off a four-arm 40-metre ICD roundabout, which is part of an unnamed
road linking the A48 with the Ford factory. The roundabout also serves Waterton Park on the
same arm and Charnwood Park off the southern arm. Beyond the Ford factory, the road
becomes Moor Road, which links with Brocastle Avenue and the A473.
2.2.2 To the southwest, the unnamed access road connects with the A48 via a three-arm traffic
signal arrangement. The A48 runs eastwards into the Vale of Glamorgan to Cowbridge and
Cardiff.
2.2.3 To the northwest, the A48 forms a four-arm roundabout with the A473. From this junction, the
M4 can be reached westwards at Junction 37 in Pyle, northwards at Junction 36 in Sarn, via
Bridgend, or eastwards at Junction 35 in Pencoed.
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 6 of 24
2.2.1 The site is shown in a wider, strategic context in Figure 2.2.
Figure 2.2: Site in Strategic Context
2.3 Pedestrian Facilities
2.3.1 The unnamed link road benefits from existing footway provision, predominately on the north-
western side, where there is a shared footway/cycleway connecting with the A48.
2.3.2 On the A48, a footway of an approximate 1.5m width runs along the north-eastern side to the
A473 roundabout, and also on the southwestern side from the southeast bound bus stop to
the A473 roundabout.
2.3.3 A key desire line for the site and surrounding areas is likely to be to the retail offerings at Parc
Plaza. However, formal crossing points over the A48 are absent, although pedestrians are
able to make a two-stage crossing, making use of the kerbed central reserve.
2.3.4 As shown in the extract from DfT’s ‘Inclusive Mobility’ document (2002), the aforementioned
widths of 1.5m to 3.0m are more than suitable for a variety of users, including a wheelchair
user and ambulant person side by side.
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 7 of 24
Extract 2.1: Footway widths (DfT ‘Inclusive Mobility’ 2002)
2.3.5 The Chartered Institution of Highways and Transportation document ‘Providing for Journeys
on Foot’ provides the following suggested acceptable walking distances, as shown in Table
2.1.
2.3.6 Pedestrian isochrones are shown in Figure 2.1 with distance isochrones for 400m, 800m and
1200m which equates to 5, 10 and 15-minute walk times based on an average walking speed
of 4.8 km/h. Figure 2.1 demonstrates that the site lies well within the recommended distances
of several trip attractors.
Table 2.1: Acceptable Walking Distances (IHT)
Town Centres
(m)
Commuting/School/
Sightseeing (m)
Elsewhere/Local
Services (m)
Desirable 200 500 400
Acceptable 400 1000 800
Preferred
Maximum 800 2000 1200
2.3.7 The site lies approximately 2.6km (straight line) from Bridgend Railway Station and the town
centre and as such is outside the recommended maximum walking distance.
2.3.8 Whilst this additional distance is unlikely to form a barrier for most staff members, it is
considered that cycling offers a more favourable form of sustainable travel.
Person with walking stick requires 750mm.
Person with crutches or walking frame requires 900mm.
Blind person with long cane or assistance dog requires 1100mm.
A visually impaired person who is being guided requires 1200mm.
A wheelchair user and an ambulant person side by side need 1500mm.
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 8 of 24
2.3.9 Industrial estate sites, such as this, are required to be located where there is good linkage to
strategic highway infrastructure, as they generate a large number of HGV movements, which
do not mix well within residential catchments.
2.3.10 The site location, which has housed the existing Lidl distribution centre for many years, is
entirely suitable for the proposed extension.
2.4 Cycle Facilities
2.4.1 Cycling in the immediate vicinity of the site is accommodated via a mixture of shared off-road
cycle routes and on-carriageway routes.
2.4.2 There is a shared pedestrian/cycle path along the unnamed access road to the site from the
A48 (ref: BRC13). This route will eventually join with route reference INM-BR-38, which will
connect with the A473/Brocastle Ave roundabout junction. At the time of writing (January
2020), the A473/Brocastle Ave roundabout junction was the subject of significant active travel
investment, with new controlled crossings and new direct routes through the central junction
area under construction.
2.4.3 Figure 2.3. shows an extract of the integrated cycle network map for the area.
Figure 2.3: Bridgend Integrated Network Map 15 Extract
SITE
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 9 of 24
2.4.4 Figure 2.3 highlights that there are plans for a shared-use path along the A48, which would
further improve cycle links to and from the site and the town centre.
2.4.5 LTN1/04 identifies that the mean average length for cycling is 4km (2.4 miles), although
journeys of up to three times this distance are not uncommon for regular commuters. As such,
a 12km (7.4 mile) cycle commuter distance normally applies. A 12km cycle distance covers
virtually the whole of Bridgend.
2.4.6 Cycling could, therefore, provide a viable alternative to private car use.
2.5 Public Transport Facilities
Bus
2.5.1 The application site is served by public transport. The nearest bus stop (southeast-bound) is
on the A48, approximately 430m away. The nearest bus stop for northwest-bound travel is
approximately 750 metres away on the A48. Both are simple flagpole arrangements.
2.5.2 Guidance relating to the accessibility of development proposals to public transport is provided
in the Institution of Highways and Transportation (IHT) document ‘Planning for Public
Transport in Development’ (March 1999). The IHT guidance recommends that:
“‘new developments should be located so that public transport trips involve
a walking distance of less than 400m from the nearest bus stop …”.
2.5.3 The site is just outside the recommended 400m of existing bus stops. However, the additional
walking distance is unlikely to form a barrier to the majority of staff.
2.5.4 The above stops are served by route X2, which operates between Porthcawl and Cardiff via
Bridgend at 30-minute intervals Monday to Friday. The service also runs on a Saturday and
Sunday.
2.5.5 The site is concluded to be reasonably well located to help encourage travel by bus.
Rail
2.5.6 The nearest railway station is found in Bridgend town centre, approximately 2.9km actual
walking distance from the site (2.6km straight line distance). This station is outside typically
acceptable walking distance. However, based on an average walking speed of 4.8km/hr, the
distance represents an approximate walking time of 36 minutes.
2.5.7 The cycle distance is approximately 3.3km, which represents a journey time of 11 minutes,
based on Google Maps.
2.5.8 Bridgend railway station is a main line station serving Bridgend. Passenger services are
operated by Great Western Railway to and from London Paddington and Swansea, with some
services extended to Carmarthen, and by Transport for Wales (TfW) to destinations across
Wales.
2.5.9 To the west, (TfW) trains run along the South Wales Main Line and West Wales Line to
Swansea and then to Carmarthen, Pembroke Dock, Milford Haven or Fishguard Harbour.
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 10 of 24
2.5.10 Mainline services to Swansea and London run hourly (with extra services at peak hours),
whilst the regional trains to Manchester Piccadilly via Shrewsbury and local trains to Maesteg
and over the Vale of Glamorgan Line also run hourly; the Swanline local stopping trains
to/from Swansea run every two hours.
2.5.11 Travel by train as part of a multi-modal trip is therefore an option for staff at the site.
2.6 Local Highway Safety
2.6.1 A review has been carried out on local highway network safety in order to establish whether
there are any current accident clusters in the vicinity of the site that may be exacerbated by
the development proposal. In this instance, a cluster is identified as a closely defined area of
five or more accidents.
2.6.2 The website www.crashmap.co.uk has been interrogated to provide a review of accidents in
the surrounding area.
2.6.3 CrashMap uses data collected by the police about road traffic crashes occurring on British
roads where someone has been injured. This data is approved by the National Statistics
Authority and reported on by the Department for Transport each year. The website uses data
obtained directly from official sources and compiled in an easy to use format showing each
incident on a map. Incidents are plotted to within 10 metres of their location and the data
includes all incidents up to the end of 2018 (note that at the time of writing, 2019 data had not
been released).
Figure 2.4: PIA Plot Extract
Source: www.crashmap.co.uk - data extracted January 2020
2.6.4 It is evident from Figure 2.4 that there are no accident blackspots near the site access
roundabout as no accidents have occurred in the last five years.
SITE
ACCESS
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 11 of 24
2.6.5 There have been two accidents at the A48 signal junction with the unnamed access road; one
of a ‘slight’ severity and one of a ‘serious’ severity. Both accidents occurred in 2014 so will be
removed from a 5-year assessment once the 2019 dataset is released. As there have been
no incidents since it is concluded that they were sporadic incidents and that there is no
inherent highway safety concern.
2.6.6 There have also been six accidents at the A48/A473 roundabout junction; five of a ‘slight’
severity and one of a ‘serious’ nature. However, no accidents occurred in 2018 or 2017 and
just one of a ‘slight’ severity in 2016. The declining accident rate indicates that highway safety
has been improved as part of the Highway Authority’s on-going road safety improvement
programme.
2.6.7 The initial conclusion drawn however is that the increase in traffic generated by the proposed
development is unlikely to exacerbate the existing safety record to a significant enough level
to warrant concern.
2.6.8 Further commentary is provided later on in this report regarding the likely trip generation,
which is not considered to be significant.
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 12 of 24
3 LOCAL AND NATIONAL PLANNING GUIDANCE
3.1 Overview
3.1.1 With regard to the transportation implications of the proposed development, this assessment
examines the development proposal in the context of relevant planning policy guidance at a
national, regional and local level. The following documents have been reviewed:
• Planning Policy Wales (December 2018);
• Technical Advice Note (Wales) (2007) 18 – Transport;
• Bridgend CBC LDP (Adopted September 2013).
3.1.2 Consideration is also given to the following legislation, which has an emphasis on sustainable
transport provision:
• Active Travel Wales Act 2013;
• Well-being of Future Generations (Wales) Act 2015.
3.2 Policy Objective
3.2.1 The overarching desire at all tiers of planning policy guidance is to influence a modal shift
from single-occupancy car travel towards more sustainable modes such as walking, cycling,
and public transport.
3.2.2 In order to achieve this, it is recognised that development should be located such that the
need to travel is reduced, especially by private car, by locating development where there is
good access to high-quality public transport, walking and cycling provision.
3.3 Planning Policy Wales (December 2018)
3.3.1 Planning Policy Wales (PPW) identifies five ways of working to enhance proposals and ideas
and to maximise their contribution to the well-being goals. It is stated that:
‘Good design is about avoiding the creation of car-based developments.
It contributes to minimising the need to travel and reliance on the car,
whilst maximising opportunities for people to make sustainable and
healthy travel choices for their daily journeys. Achieving these objectives
requires the selection of sites which can be made easily accessible by
sustainable modes as well as incorporating appropriate, safe and
sustainable links (including active travel networks) within and between
developments using legal agreements where appropriate.
Existing infrastructure must be utilised and maximised, wherever
possible. Where new infrastructure is necessary to mitigate transport
impacts of a development and to maximise accessibility by sustainable
non-car modes, it should be integrated within the development layout and
beyond the boundary, as appropriate. This could include works to
connect cycle routes within a site to a wider strategic cycling network or
provision of bus priority measures on highway corridors serving a new
development.’
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 13 of 24
3.3.2 For placemaking in rural areas, PPW states that:
‘For most rural areas the opportunities for reducing car use and
increasing walking, cycling and use of public transport are more limited
than in urban areas. In rural areas most new development should be
located in settlements which have relatively good accessibility by non-car
modes when compared to the rural area as a whole. Development in
these areas should embrace the national sustainable placemaking
outcomes and, where possible, offer good active travel connections to
the centres of settlements to reduce the need to travel by car for local
journeys.’
3.3.3 Planning Policy Wales confirms that transport plays a key role in promoting a healthier Wales,
a more equal Wales, cohesive communities and a globally responsible Wales.
3.3.4 PPW identifies the following active and social trend issues which it aims to address:
‘assisting in the delivery of cohesive communities which will meet the
needs and are accessible to all members of society, including older
people;
tackling inequalities between communities, delivering services and jobs
closer to where people live and acknowledging the importance of
inclusive communities and the wider environment for good health
and well-being;
improve sustainable access to services, cultural opportunities and
recreation facilities to support people to adopt healthy, culturally fulfilled
lifestyles which will assist in improving health and wellbeing;
reducing reliance on travel by private car, and the adverse impacts of
motorised transport on the environment and people’s health, by
prioritising and increasing active travel and public transport; • ensure our
transportation infrastructure is adaptable to future advances in innovation
such as the mainstreaming of electric vehicles or possible advent of
autonomous or driverless vehicles in the next ten to 15 years’.
3.3.5 PPW identifies the following active and social linkages issues which it aims to address:
‘enable sustainable access to housing, employment, shopping,
education, health, community, leisure and sports facilities and green
infrastructure, maximising opportunities for community development and
social welfare;
develop sustainable transportation infrastructure to keep Wales moving
and connect people with jobs, housing and leisure. Ensure that the
chosen locations and resulting design of new developments reduces
reliance on the private car for daily travel, supports sustainable modes of
travel and assists in improving the environment, public health and
community life;
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 14 of 24
require developments to encourage modal shift and be easily accessible
by walking, cycling and public transport, by virtue of their location, design
and provision of on and off site sustainable transport infrastructure’.
3.3.6 PPW identifies that:
‘The planning system should enable people to access jobs and services
through shorter, more efficient and sustainable journeys, by walking,
cycling and public transport. By influencing the location, scale, density,
mix of uses and design of new development, the planning system can
improve choice in transport and secure accessibility in a way which
supports sustainable development, increases physical activity, improves
health and helps to tackle the causes of climate change and airborne
pollution by: • Enabling More Sustainable Travel Choices – measures to
increase walking, cycling and public transport, reduce dependency on the
car for daily travel; • Network Management – measures to make best use
of the available capacity, supported by targeted new infrastructure; and •
Demand Management – the application of strategies and policies to
reduce travel demand, specifically that of single-occupancy private
vehicles.’
3.3.7 Under the sustainable transport category, PPW identifies that:
‘The Welsh Government is committed to reducing reliance on the private
car and supporting a modal shift to walking, cycling and public transport.
Delivering this objective will make an important contribution to
decarbonisation, improving air quality, increasing physical activity,
improving the health of the nation and realising the goals of the Well-
being of Future Generations Act.
The planning system has a key role to play in reducing the need to travel
and supporting sustainable transport, by facilitating developments which:
• are sited in the right locations, where they can be easily accessed by
sustainable modes of travel and without the need for a car;
• are designed in a way which integrates them with existing land uses
and neighbourhoods; and
• make it possible for all short journeys within and beyond the
development to be easily made by walking and cycling.
Development proposals must seek to maximise accessibility by walking,
cycling and public transport, by prioritising the provision of appropriate
on-site infrastructure and, where necessary, mitigating transport impacts
through the provision of off-site measures, such as the development of
active travel routes, bus priority infrastructure and financial support for
public transport services.
It is Welsh Government policy to require the use of a sustainable
transport hierarchy in relation to new development, which prioritises
walking, cycling and public transport ahead of the private motor vehicles.
The transport hierarchy recognises that Ultra Low Emission Vehicles also
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 15 of 24
have an important role to play in the decarbonisation of transport,
particularly in rural areas with limited public transport services.
The sustainable transport hierarchy should be used to reduce the need to
travel, prevent car-dependent developments in unsustainable locations,
and support the delivery of schemes located, designed and supported by
infrastructure which prioritises access and movement by active and
sustainable transport.
The sustainable transport hierarchy must be a key principle in the
preparation of development plans, including site allocations, and when
considering and determining planning applications.
Different approaches to sustainable transport will be required in different
parts of Wales, particularly in rural areas, and new development will need
to reflect local circumstances.’
3.3.8 With regards to car parking, PPW confirms the widely accepted notion that:
‘Car parking provision is a major influence on how people choose to
travel and the pattern of development. Where and how cars are parked
can in turn be a major factor in the quality of a place.’
3.3.9 It continues that:
‘A design-led approach to the provision of car parking should be taken,
which ensures an appropriate level of car parking is integrated in a way
which does not dominate the development. Parking provision should be
informed by the local context, including public transport accessibility,
urban design principles and the objective of reducing reliance on the
private car and supporting a modal shift to walking, cycling and public
transport. Planning authorities must support schemes which keep parking
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 16 of 24
levels down, especially off-street parking, when well designed. The
needs of disabled people must be recognised and adequate parking
provided for them.
Planning authorities must require good standards of car parking design,
which do not allow vehicles to dominate the street or inconvenience
people walking and cycling. Car parking should be overlooked by
surrounding properties, to provide natural surveillance.
…. Parking standards should be applied flexibly and allow for the
provision of lower levels of parking and the creation of high quality
places.’
3.3.10 PPW promotes walking and cycling for shorter trips and that cycling be encouraged for short
trips and as a substitute for shorter car journeys, or as part of a longer journey when combined
with public transport.
3.4 Bridgend CBC LDP (Adopted September 2013)
3.4.1 The adopted LDP will guide and manage development in the area up to 2021.
3.4.2 Key strategic objectives of the LDP, which are applicable to the application site from a
transport planning perspective, are:
Strategic Policy SP2: Design and Sustainable Place Making
All development should contribute to creating high quality, attractive, sustainable places
which enhance the community in which they are located, whilst having full regard to the
natural, historic and built environment by:
1) Complying with all relevant national policy and guidance where appropriate;
2) Having a design of the highest quality possible, whilst respecting and enhancing local
character and distinctiveness and landscape character;
3) Being of an appropriate scale, size and prominence;
4) Using land efficiently by:
(i) being of a density which maximises the development potential of the land whilst
respecting that of the surrounding development; and
(ii) having a preference for development on previously developed land over
greenfield land;
5) Providing for an appropriate mix of land uses;
6) Having good walking, cycling, public transport and road connections within and
outside the site to ensure efficient access;
7) Minimising opportunities for crime to be generated or increased;
8) Avoiding or minimising noise, air, soil and water pollution;
9) Incorporating methods to ensure the site is free from contamination (including invasive
species);
10) Safeguarding and enhancing biodiversity and green infrastructure;
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 17 of 24
11) Ensuring equality of access by all;
12) Ensuring that the viability and amenity of neighbouring uses and their
users/occupiers will not be adversely affected;
13) Incorporating appropriate arrangements for the disposal of foul sewage, waste
and water;
14) Make a positive contribution towards tackling the causes of, and adapting to the
impacts of Climate Change; and
15) Appropriately contributing towards local, physical, social and community
infrastructure which is affected by the development.
3.5 Active Travel (Wales) Act 2013
3.5.1 The Active Travel (Wales) Act 2013 aims to:
make active travel the most attractive option for most shorter journeys. Its
purpose is to enable more people to undertake active travel, meaning
more people can enjoy the benefits of active travel. We want to
encourage people to leave their cars behind and use active travel where
it is suitable for them to do so.
The Act requires local authorities in Wales to produce active travel maps
and deliver year on year improvements in active travel routes and
facilities. It requires highways authorities in Wales to make
enhancements to routes and facilities for pedestrians and cyclists in all
new road schemes and to have regard to the needs of walkers and
cyclists in a range of other highway authority functions. It also requires
the Welsh Ministers and local authorities to promote active travel
journeys in exercising their functions under this Act.
3.6 Conclusion
3.6.1 The proposed use is compatible with adjoining uses and represents an extension to the
existing Lidl distribution centre operation at Waterton Industrial Estate. The site’s compliance
with transport planning policy is therefore already established, which the proposed extension
will maintain.
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 18 of 24
4 DEVELOPMENT PROPOSAL
4.1 Proposed Development
4.1.1 The proposal involves the extension of the existing Lidl distribution centre in Bridgend to
facilitate an extension to the warehouse of 5,065m2 along with an extension to ancillary areas
such as administration (1,336m2), outside seating, driver’s lounge, staff parking and HGV
parking. The total extension therefore amounts to approximately 6,401m2 GFA.
4.1.2 The total proposed building area, as measured from the submitted layout, is approximately
38,775m2 GFA.
4.1.3 An indicative site layout is contained herein as Appendix A.
4.2 Access
4.2.1 The proposed site access will be as per the existing situation. The local highway network was
evidently designed for the industrial nature of the surrounding area, with generous
carriageway widths and geometry to facilitate the swept path requirements of max legal
articulated vehicles.
4.3 Parking
4.3.1 With reference to Bridgend County Borough Council’s adopted parking standards SPG
(September 2011) the site is categorised as Zone 5.
4.3.2 The parking standards require that distribution centres (>1000m2 GFA) provide operational
parking at 25% of the GFA and non-operational parking at 1 space per 80m2.
4.3.3 Therefore, based on the total proposed building area of 38,775m2 GFA, approximately
9,694m2 should be allowed for operational use and a maximum of 485 non-operational parking
spaces provided.
4.3.4 At present, there are 143 standard on-site parking spaces; a maximum of 405 are permitted
by the SPG for the existing GFA (based on 32,374m2). The existing provision is therefore 35%
of the maximum allowed.
4.3.5 The proposal involves increasing the parking provision to 263 on-site spaces. Of these, 11
will be disabled bays and 40 will allow electric vehicle charging. The proposed provision is
therefore 54% of the maximum allowed and therefore offers significant betterment over the
existing parking scenario.
4.3.6 Operational parking is dictated by the business operations and is far in excess of the minimum
requirements advised by the parking standards (i.e. >25% of the GFA).
4.3.7 Planning policy makes it clear than unnecessary parking must be avoided. Planning Policy
Wales (2018) confirms the widely accepted notion (para 4.1.50) that:
‘Car parking provision is a major influence on how people choose
to travel’
4.3.8 Furthermore, in para. 4.1.51 PPW states that:
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 19 of 24
‘Planning authorities must support schemes which keep parking
levels down, especially off-street parking’
4.3.9 Crucially, PPW makes it clear in para. 4.1.53 that:
‘Parking standards should be applied flexibly and allow for the
provision of lower levels of parking and the creation of high quality
places.’
4.3.10 Based on the operator’s knowledge of the existing and proposed site uses, and the guidance
contained in PPW, the proposed level of parking is deemed appropriate for site location.
4.3.11 With regards to cycle parking, the parking standards require one space per 500m2 (75
spaces). The proposal allows for 76 secure, sheltered cycle parking in the form of ‘Sheffield’
style stands, which complies with the parking standards.
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 20 of 24
5 SITE TRAFFIC
5.1 Introduction
5.1.1 In order to determine the forecast levels of additional traffic, a manual classified 12-hour count
was undertaken on 22/01/2020. This provided existing traffic patterns between 07:00-19:00
and an origin/demand matrix at the access roundabout. The results are discussed in greater
detail below and are included in full as Appendix B.
5.2 Existing site traffic
5.2.1 Chart 5.1 below shows the existing vehicle classification at the site.
Chart 5.1: Lidl Distribution Centre Vehicle Classification
5.2.2 As shown above, the existing site traffic, between the hours of 07:00-19:00 on a weekday,
comprises 53% car traffic, 35% OGV2, 7% LGV, 3% OGV1, 1% pedal cyclist and 1% motor
cyclist.
5.2.3 Chart 5.2 shows the arrival and departure profile for the surveyed 12-hour period.
53%
7%3%
35%
0%1% 1%
Lidl Distribution Centre Vehicle Classification (22/01/2020 0700-1900)
Car
LGV
OGV1
OGV2
PSV
Pedal Cycle
Motor Cycle
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 21 of 24
Chart 5.2: Lidl Distribution Centre Traffic Profile
5.2.4 Chart 5.2 shows that the site’s peak hour occurs between 12:00-13:00, where there are 84
movements. It is also evident that the traditional highway network AM peak hour (08:00-09:00)
is busier than the traditional PM peak (17:00-18:00) where there are 73 movements and 42
movements respectively.
5.2.5 The chart shows that HGV traffic is more prominent in the morning, with numbers falling
sharply after 12pm.
5.3 Proposed site traffic
5.3.1 Industry-standard trip forecasting software (TRICS) typically allows for development traffic
forecasts to be calculated according to the building GFA.
5.3.2 The same approach is taken here, whereby the proposed GFA of 38,775m2 represents an
increase of 20% over the existing GFA (assumed to be 32,374m2). Surveyed traffic flows have
therefore been factored by 1.20 to derive the forecast traffic levels, as shown in Table 5.1.
16
31
139 11
42
1813
36 6
2
16
25
14 14
85
26 4 5 4 42
69 8 7
27
38
25
1519
25
1112 11
1922
16
106
03
7 7 5
0
10
20
30
40
50
0 7 : 0 0 0 8 : 0 0 0 9 : 0 0 1 0 : 0 0 1 1 : 0 0 1 2 : 0 0 1 3 : 0 0 1 4 : 0 0 1 5 : 0 0 1 6 : 0 0 1 7 : 0 0 1 8 : 0 0
Lidl Distribution Centre (Bridgend) Traffic Profi le
Inbound Car/LGV/MC Inbound OGV1/OGV2
Outbound Car/LGV/MC Outbound OGV1/OGV2
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 22 of 24
Table 5.1: Forecast Site Traffic Increase
Hour beginning
Forecast Site Traffic Increase
Inbound Outbound
Car/LGV/MC OGV1/OGV2 Car/LGV/MC OGV1/OGV2
07:00 3 3 0 2
08:00 6 5 1 2
09:00 3 3 2 4
10:00 2 3 2 4
11:00 2 2 1 3
12:00 8 1 5 2
13:00 4 0 8 1
14:00 3 1 5 0
15:00 1 1 3 1
16:00 1 1 4 1
17:00 1 1 5 1
18:00 0 1 2 1
5.3.3 As shown in Table 5.1, the proposed development is forecast to generate an additional 14
movements in the traditional AM peak hour (0800-0900) and 8 movements in the PM peak
hour (1700-1800).
5.3.4 This amounts to one additional movement every 4-5 minutes in the AM peak hour and one
additional movement every 7-8 minutes in the PM peak hour.
5.3.5 The traffic impact on the local highway network is therefore considered to be negligible.
5.4 Conclusion
5.4.1 The development proposal will result in a negligible quantum of vehicular trips which is unlikely
to have an adverse impact on local highway safety or operation.
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Page 23 of 24
6 SUMMARY AND CONCLUSION
6.1 Summary
6.1.1 This Transport Statement has been produced by Corun Associates Ltd (Corun) on behalf of
Lidl Great Britain Limited, the applicant, to examine the highway and transportation issues
associated with the proposed extension of the existing Lidl distribution centre in Bridgend.
6.1.2 The proposal seeks an extension to the warehouse of 5,065m2 along with an extension to
ancillary areas such as administration (1,336m2), outside seating, driver’s lounge, staff
parking and HGV parking.
6.1.3 The site location, which has housed the existing Lidl distribution centre for many years, is
entirely suitable for the proposed extension. It is accessible by various means of sustainable
transport and is therefore compliant with transport planning policy at a local and national level.
6.1.4 The proposed site access will be as per the existing situation. The local highway network was
evidently designed for the industrial nature of the surrounding area, with generous
carriageway widths and geometry to facilitate the swept path requirements of max legal
articulated vehicles.
6.1.5 Based on the operator’s knowledge of the existing and proposed site uses, the Council’s
adopted parking standards and guidance contained in PPW, the proposed level of parking is
deemed appropriate for site location.
6.1.6 The development proposal will result in a negligible quantum of vehicular trips which is unlikely
to have an adverse impact on local highway safety or operation.
6.2 Conclusion
6.2.1 There are no reasons in highway and transportation terms why the proposed development
should not be granted consent.
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Appendix A
APPENDIX A
Indicative Site Layout
NOENTRY
NO
ENTRY
10000
7000
8500
3468
0
10
10
10
10
10
10
10
10
10
10
10 10
10
GIVE
WAY
GOODSIN
GIVEWAY
HGV STACKINGLANE
HGV STACKINGLANE
HGV STACKINGLANE
HGV STACKINGLANE
HGV STACKINGLANE
KEEP
CLEAR
STOP
CAR
PARK
CAR
PARK
SL OW
CARPARK
STOP
Goods
In
GIVEWAY
STOP
EXIT
EXIT
Canopy over container platform
Disabled carparking &cycle store
70
00
70
00
14
000
4000
20
000
60°
4000
20
000
60°
4000
20
000
60°
GOODS
OUT
Cycle S
helte
r
Smokers Shelters
Adbluefuellingstation
Adbluerefuelingbays
Keep Clear
Keep Clear
GOODS INOFFICES
SmokingShelter
SM
SM
SM
SM
RWP
G
G
LP LP
ER
GGG
RS
ER RWP
ER RWP
ER RWP
ER
RWP
ER RWP
G's G'sG G's
ER
RWP
ER RWP ER ER
RWP
ER ER ER
G'sG's
RS
RWP
ERER R
WP
G's
RWP
ER RWP ER
RWP
LP
G's
G's
RS
ERER
GGG
LP
G
G's
LPLP GV
CONC CONC CONC CONC CONC
CONC
G's G's G's G's
ICCL17.55
SECURITYSENSOR
ICCL17.18
ICCL17.18
DK
G's
G's
G'sIC
CL15.57
IC
CL15.27
ICCL17.21
ICCL17.24
IC CL17.40
1234567891011121314151617181920
ICCL17.17
212526
TARMAC
TARMAC
TARMAC
TARMAC
ICCL17.12
SECURITYSENSOR
G's G's
272830 29313234 33
CONCRE
TE "DR
UMS"
0.8mH
35363738394043 42 4147
ICCL17.22
ICCL17.42
44454648495051
IC'sCL17.39CL17.38
ICCL17.20
52535455
G'sG's
ICCL16.65
TARMAC
TOP OFTANK
CL17.12
ICCL17.13
ICCL17.05
ICCL17.15
IC'sCL17.07CL17.08
LINEOFSTUDS
FIREHOSE
"SMOKERS"CANOPY
PLANTROOMWALKWAY
89
FIREEXIT
METALSTAIRS
90919293
ICCL17.34
9498 97 96 95
TOPOF
FIREEXIT
ICCL17.82
EAVE
LINEOFSTUDS
ICCL17.34
ICCL17.45
ICCL16.62
ICCL16.65
DCH
ICCL16.25
ICCL16.00
ICCL16.12IC
CL16.15
ICCL15.67
GRITBIN
AB0.45
CONC.
ELECTRICSLIDINGGATE
PLANTING
TARMAC
CONC
MESH
2.2mH
SECURITY
FENCE
WM2.2mH
SECURITYFENCE
MESH2.2mH
SECURITYFENCE
TARMAC
TARMAC
GR0.2
GR0.2
GR0.2
GR0.2
AB.45
GR0.2
GR0.2
GR0.2
(ONEWAY)
FIREEXIT FIRE
EXITFIRE
HOSE
PLANTINGONSLOPE
PLANTINGONSLOPE
CH1.2
MESH2.2mH
SECURITYFENCE
MESH2.2mH
SECURITYFENCE
MESH2.2mH
SECURITYFENCE
ER
ER
GR0.2
BD
BD
BD
WMF
4.5
ARMCO BARRIER
0.7
WMF
4.5
ASH
TOP
OF
PYLON
TOP
OF
PYLON
OVERHEAD
WIRES(BRACKETS)
MEASURED
6/10/2015
AT 16 DEG
C.
OVERHEAD
WIRES(BRACKETS)
MEASURED
6/10/2015
AT 16 DEG
C.
BUSH
IC
CB
1.8
BIN
STORE
U/S
CANOPY
IC
U/S
CANOPY
CPS
G
ORDNANCE SURVEY
DETAIL
ORDNANCE SURVEY
DETAIL
PROPOSED SITEBOUNDARYFROM PLAN PROVIDED BYLIDL
MESH
2.2mH
SECURITY
FENCE
RAILWAY
LINES
No.3
TARMAC
ORDNANCE SURVEY
DETAIL
RWP
G
G
LP LP
ER
GGG
RS
ER RWP
ER RWP
ER RWP
ER
RWP
ER RWP
G's G'sG G's
ER
RWP
ER RWP ER ER
RWP
ER ER ER
G'sG's
RS
RWP
ERER R
WP
G's
RWP
ER RWP ER
RWP
LP
G's
G's
RS
ERER
GGG
LP
G
G's
LPLP GV
CONC CONC CONC CONC CONC
CONC
G's G's G's G's
ICCL17.55
SECURITYSENSOR
ICCL17.18
ICCL17.18
DK
G's
G's
G'sIC
CL15.57
IC
CL15.27
ICCL17.21
ICCL17.24
IC CL17.40
1234567891011121314151617181920
ICCL17.17
212526
TARMAC
TARMAC
TARMAC
ICCL17.12
SECURITYSENSOR
G's G's
272830 29313234 33
CONCRE
TE "DR
UMS"
0.8mH
35363738394043 42 4147
ICCL17.22
ICCL17.42
44454648495051
IC'sCL17.39CL17.38
ICCL17.20
52535455
G'sG's
ICCL16.65
TARMAC
TOP OFTANK
CL17.12
ICCL17.13
ICCL17.05
ICCL17.15
IC'sCL17.07CL17.08
LINEOFSTUDS
FIREHOSE
"SMOKERS"CANOPY
PLANTROOMWALKWAY
89
FIREEXIT
METALSTAIRS
90919293
ICCL17.34
9498 97 96 95
FIREEXIT
ICCL17.82
EAVE
LINEOFSTUDS
ICCL17.34
ICCL17.45
ICCL16.62
ICCL16.65
DCH
ICCL16.25
ICCL16.00
ICCL16.12IC
CL16.15
ICCL15.67
GRITBIN
AB0.45
CONC.
ELECTRICSLIDINGGATE
PLANTING
TARMAC
CONC
MESH
2.2mH
SECURITY
FENCE
WM2.2mH
SECURITYFENCE
MESH2.2mH
SECURITYFENCE
TARMACTARMAC
TARMAC
GR0.2
GR0.2
GR0.2
GR0.2
AB.45
GR0.2
GR0.2
GR0.2
(ONEWAY)
FIREEXIT FIRE
EXITFIRE
HOSE
PLANTINGONSLOPE
PLANTINGONSLOPE
CH1.2
MESH2.2mH
SECURITYFENCE
MESH2.2mH
SECURITYFENCE
MESH2.2mH
SECURITYFENCE
ER
ER
GR0.2
BD
BD
BD
WMF
4.5
ARMCO BARRIER
0.7
WMF
4.5
TOP
OF
PYLON
TOP
OF
PYLON
OVERHEAD
WIRES(BRACKETS)
MEASURED
6/10/2015
AT 16 DEG
C.
OVERHEAD
WIRES(BRACKETS)
MEASURED
6/10/2015
AT 16 DEG
C.
BUSH
IC
CB
1.8
BIN
STORE
U/S
CANOPY
IC
U/S
CANOPY
CPS
G
ORDNANCE SURVEY
DETAIL
ORDNANCE SURVEY
DETAIL
PROPOSED SITEBOUNDARYFROM PLAN PROVIDED BYLIDL
ORDNANCE SURVEY
DETAIL
MESH
2.2mH
SECURITY
FENCE
RAILWAY
LINES
No.3
TARMAC
ORDNANCE SURVEY
DETAIL
RWP
GR0.2RWP
22
GR0.2
TARMACTARMAC
ST6
ST8
ST9ST10
ST11
ST12
ST13
ST1 ST2
ST2A
ST5A
ST10A
ST12A
ST6
ST8
ST9ST10
ST11
ST12
ST13
ST1 ST2
ST2A
ST5A
ST10A
ST12A
KEEP CLEAR
ProposedUnsecured
Admin Car Park252 Spaces
HaulierCabins
Height restrictionbarrier
Exist
ing si
te ac
cess
gates
retai
ned
Sliding gate & heightrestriction barrier
Existing bundingreconfigured as necessary toaccomodate new site layout
HGV STACKING29 parking bays
Existing bundingreconfigured as necessary toaccomodate new site layout
Existing bundingreconfigured as necessary toaccomodate new site layout
Spee
d bum
p
Turnstile
Turnstile
With foul drainand oil bunding
212 Regular Spaces20 Electric Spaces& 20 Future Electric Spaces14 Motorbike Spaces
HGV STACKING63 parking bays
BREAKOUT BREAKOUT
PLANT ROOM ACCESS
20755
4000
60.0
0°
19
971
DE
LIVE
RIE
S,
VIS
ITO
R &
C
YCLE
P
AR
KIN
GUN
LOA
DIN
G
2
15200 3
15200
5
15200
EXISTING ROOF PLANT
PLANTERS
PLAN
TER
S
11 A
CC
ES
SIB
LES
PA
CE
S
LEGEND
PROPOSED EXTENSION
N
ZZ
NOTES
KEY PLAN
THE COPYRIGHT OF THIS DRAWING OR PART THEREOF BELONGS TO BAMBER & REDDAN ARCHITECTS LTD. CONTRACTOR TO CHECK ALL DIMENSIONS PRIOR TO COMMENCING WORK - DO NOT SCALE.
TITLE:
PROJECT
20 Shepherdess Walk,London N1 7LBT 020 3227 0800 E [email protected]
DRAWING NO:
SCALE @ A0CHK:BY: DATE:
Rev:
As indicated
LIDL RDC BRIDGEND
PROPOSED SITE PLAN
PLANNINGGR MM
GB-P580BRE-XX-PLA-DR-ZZ-ZZ-INF-13200-P01
20.12.19
1 : 50013200
14100
1
1 PROPOSED SITE PLAN
0
SCALE 1:
25
500
20151055
m
Rev By/Chk Date Description
P01 GR/MM 20.12.2019 PRELIMINARY ISSUE
Bridgend Distribution Centre
Lidl Great Britain Limited Transport Statement
19-00657/TS/01/A Corun Associates Ltd
March 2020 Appendix B
APPENDIX B
Existing Site Traffic Survey
Date: 22/01/2020
Location: Lidl Distribution Centre, Waterton, Bridgend
Time Interval: 07:00-19:00
Count type: All motor vehicles (Car, LGV, OGV1, OGV2, PSV, M/C)
07:00 0 4 0 0 0 3 3 0
07:15 0 3 1 0 0 5 2 0
07:30 0 2 1 0 0 2 1 0
07:45 0 3 0 0 0 13 3 0
08:00 0 3 1 0 0 20 2 0
08:15 0 0 1 0 0 5 1 0
08:30 0 2 2 0 0 14 2 0
08:45 0 5 3 0 0 10 2 0
09:00 0 2 1 0 0 6 1 0
09:15 0 3 0 0 0 3 0 0
09:30 0 8 1 0 0 7 0 0
09:45 0 9 3 1 0 10 0 0
10:00 1 3 0 0 0 8 2 0
10:15 0 5 1 0 0 3 1 0
10:30 0 6 0 0 0 1 1 0
10:45 1 13 0 0 0 4 2 1
11:00 0 6 1 0 0 9 0 0
11:15 0 6 1 0 0 3 2 0
11:30 0 5 1 0 0 2 1 0
11:45 0 3 0 0 0 1 1 0
12:00 0 9 5 0 0 5 5 1
12:15 0 5 1 1 0 4 3 0
12:30 0 9 1 0 0 9 2 0
12:45 0 3 3 0 0 12 6 0
13:00 0 6 5 0 0 3 2 0
13:15 0 3 2 0 0 3 0 0
13:30 0 13 11 0 0 2 2 0
13:45 0 2 1 1 0 6 2 0
14:00 0 4 2 0 0 1 0 0
14:15 1 5 2 0 0 1 3 0
14:30 0 4 2 0 0 5 0 0
14:45 0 3 2 0 0 7 2 0
15:00 0 3 2 0 0 1 0 0
15:15 0 1 0 0 0 1 0 0
15:30 0 5 0 0 1 4 0 0
15:45 0 5 2 0 0 0 0 0
16:00 0 10 0 0 0 1 1 0
16:15 0 4 2 0 0 2 1 0
16:30 0 4 1 0 0 2 1 0
16:45 0 5 0 0 0 3 0 0
17:00 1 5 4 0 0 4 1 0
17:15 0 5 0 0 0 0 0 0
17:30 0 11 0 0 0 3 0 0
17:45 0 5 1 0 0 2 0 0
18:00 0 6 1 0 0 1 1 0
18:15 0 1 2 0 0 1 0 0
18:30 0 3 1 0 0 0 1 0
18:45 0 2 0 0 0 1 1 0
Approach A: Lidl Distribution Centre
Approach B: Charnwood Park
Approach C: Link to A48
Approach D: Unnamed access road
Approach E: Waterton Park
From ETime
Outbound from A Inbound to A
To B To C To D To E From B From C From D