7/28/2019 Project Summary Given by CDA (Hekemian) to Judge Chrystal for Initial Receptor Evaluation for 215 Birchwood Av
1/1
Project Summary
June 2013 Initial Receptor Evaluation
Cranford Development Associates, LLC
215 Birchwood Avenue (Block 292, Lot 2)
Cranford, New Jersey
Block 292, Lot 2
NJDEP Case #120208140107, NJDEP PI# 573212
In 2012, Cranford Development Associates, LLC (CRDA) removed 1,014 tons of debris/fill in accordance with the
Minor Landfill Disruption Approval Application (MLDAA) prepared by H2M Associates, Inc. and approved by the
NJDEP in November 2011. The fill/debris layer consisted of approximately 65% soil/fill and 35% debris, was located
four (4) to five (5) feet below site grade (bsg), was approximately four (4) feet thick, and extended over an area
that is approximately 16,400 square feet in size. The MLDAA required that any fill/debris material considered
suspect were to be held for subsequent characterization and disposal.
The results of the fill/debris material site investigation sampling identified one area of lead impacted debris/fill.
This area of lead impacted fill/debris has been designated as area of environmental concern ( AOC) 1. Based on
conversations with the NJDEP, the original intention was to address the removal of the small area of lead impacted
soils within the Sanitary Landfill Closure Report that has been prepared for the Property. However, during the final
stages of the debris/fill removal, an area of what appeared to be buried crushed 55 gallon capacity drums was
encountered. The drums and surrounding impacted soils were designated as AOC 2. Since the drums were
required to be addressed using a Licensed Site Remediation Professional (LSRP), it was decided that both AOCs
would be addressed by the LSRP through the preparation and submission of a Remedial Action Report.
The impacted soils were excavated, and the results of post excavation sampling performed in accordance with the
applicable NJDEP guidance and the Technical Regulations for Site Remediation demonstrated compliance with the
NJDEP Soil Remediation Standards, the NJDEP default Impact to Groundwater Screening Levels (dIGWSL), and the
sitespecific Impact to Groundwater Soil Remediation Standards (IGWSRS) (where applicable).
Based upon the depth of the former soil contamination in AOCs 1 and 2, and the anticipated depth to
groundwater, a Site Investigation of groundwater is required. This investigation has been partially completed
through the installation and sampling of a temporary ground water sampling point. The results of the sampling
demonstrated compliance with the NJDEP Ground Water Quality Standards. The installation of a permanent well
has been scheduled to complete the Site Investigation of groundwater.