Project Selection, Economics, Estimating

Dr. Perkins

CE 438

6 February 05

Page 2: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Today

• 40 Minute Lecture– ESM 401– ESM 450

• General Project Selection Concepts– Economics

• Estimating

• Your Projects

Page 3: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Remember

• Remember Project Life Cycle

• Organizations

Page 4: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05
Page 5: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05
Page 6: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05
Page 7: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Project Selection

Page 8: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

• “Projectized” organization, all work is a project.– But may have some special issues see below

• Functional organization– Must decide if can be done within the

functional area. – If so, project might not be needed, but see

below

Page 9: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Project Selection

• Values, Vision, and Mission

• Objectives and Goals

• Strategy

• Programs and Projects

Page 10: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Project SelectionGeneral Concepts

• Will there be a customer?• Will the project survive competition?

– Internal projects– External

• Is the need for the project recognized as supporting company strategy?

• Can company handle the risk and uncertainty?

Page 11: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Note!!

• The following applies to components and engineering decisions within a project as well.

• If they warrant it

Page 12: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

• Ultimately provide return on investment?

• How about the future?

Page 13: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Project Selection

• Criteria for PS Models• Nature of PS Models• Types of PS Models• Uncertainty Analysis and Risk

Management• Information Base for PS Models• Project Proposal

Page 14: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Overview of PS Process

• Decision Makers: Who will align corporate needs and project goals

• Project Selection: Chose candidate project using Evaluation Criteria

• Dealing with Uncertainty: Risk Analysis• Strategically selecting best Projects: Project

Portfolio Process (PPP)• Locking up the deal: Writing a Project

Proposal

Page 15: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Nature of PS models:Caveats

• Project decisions are made by managers --- NOT by PS model!

• A PS model APPROXIMATES, but does NOT DUPLICATE reality!

Page 16: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Nature of PS Models:Method

• Start with detailed list of firm’s goals

• Create list of project evaluation factors (PEF’s)

• Weigh every element in PEF list

• Compute an overall score for project based on weighted PEF’s

• Select project that has the closest alignment with firm’s goals

Page 17: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Project Evaluation Factors (PEFs)

• Who decides??

• Production Factors

• Marketing Factors

• Financial Factors

• Personnel Factors

• Administrative and Misc. Factors

Page 18: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Nonnumeric PS Models:

• Sacred Cow• Operating Necessity• Competitive Necessity• Product Line Extension• Comparative Benefit

Model

Page 19: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Numeric PS Models:Profit / Profitability

• Average Rate of Return

• Discounted Cash Flow (NPV)

• Internal Rate of Return• Benefit/Cost (Profitability Index)

• Other Profitability Models

Page 20: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Choosing the PS Model

• Dependent on wishes and philosophy of management

• 80% of Fortune 500 firms choose “nonnumeric” PS models

• Firms with outside funding often chose scoring PS models

• Firms without outside funding often chose profit / profitability PS models

Page 21: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Management of Risk:Terminology

• Risk: Decision based on complete information about the probability of each possible outcome.

• Uncertainty: Decision based on incomplete or insufficient data.

• Game: Decision based under conditions of conflict.

Page 22: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Areas of Uncertainty

• Project timing & expected cash flow.

• Direct outcome of project, i.e. what exactly will the project accomplish

• Side effects and unforeseen consequences of project

Page 23: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

PS Models

• Idealized view of reality

• Representing the STRUCTURE of the problem, not the detail

• Deterministic or stochastic

Page 24: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Numeric PS Models:Scoring

• Unweighted 0-1 Factor Model

• Unweighted Factor Scoring Model

• Weighted Factor Scoring Model

• Constrained Weighted Factor Scoring Model

• S = ∑(x)

• S = ∑(s)

• S = ∑(s·w)

• S = ∑(s·w) ∏(c)• [Handout]

Page 25: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

General Cost Terms

• Handout

Page 26: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Estimating

Main types of construction?

Page 27: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

• BuildingsCommercial

OfficesStores

Residential

Single Multi-family,

Hi-rise

• Public OccupancySchoolsHospitalsPolice/fireTransportation terminals

Page 28: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

• Heavy ConstructionRoads

BridgesPorts and AirportsTunnelsPipelines

• IndustrialManufacturing PlantsProcess

Oil and GasChemicalsAgricultural

Power Generation

Page 29: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

• SpecialtiesHazardous Waste

Military Facilities

Communication

Golf Courses

Demolition

Arctic

Page 30: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

• Also might divideNew constructionRenovation/remodel/upgradeDemolition

• Or by• Owner

StateFederalLocalPrivate

Page 31: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Location

• Near industrial centers

• Off highway

• Off shore

• Remote (Bush)

• Foreign– Various Locations

Page 32: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

• By project contracting plan– Traditional– Design-construct– Turnkey– Fast-track– Owner’s forces

Page 33: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

• By contract type– Lump sum (AKA hard dollar)– Cost plus– Cost reimbursable (fixed fee)– Unit price

Page 34: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

• Contractor’s Organization– No sub-contractors– All sub-contractors 

• Labor Force– Union (closed shop)– Non-union (open shop)– Mixed– (Double-breasted)– Local vs. Expat (expatriate)

Page 35: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

• Who’s doing the estimate?– Owner– A/E– Contractor– Subcontractor– Government– Consultant

Page 36: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

When (what phase)• Concept• A/E

Components

• 15%, 35%, 65%, 95%• Is the budget fixed?• Cast in concrete

• Contactor’s Bid• Post bid negotiations• Usually non-government• Changes

Page 37: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Non-construction Estimates

• Owners estimate of owners expensesContract administration

Insurance

Lost or interrupted work

Permits and fees

Housing and travel

Page 38: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

A/E estimate of A/E’s expenses

(Contract type)HoursOther expenses

Sub-consultantsSoils

TravelConstruction phase?

InspectionTesting

Page 39: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Types of estimate• Guess

• Educated guess

• SWAGWith or without lanyap

• Historical, similar project

• Historical, unit prices

• Estimating guides

• Crew size and production rate

Page 40: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Cost Items

• Labor

• Supervision

• Installed Materials

• Installed equipment

• Supplies and Consumables

Page 41: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

• Subcontractors• Home Office Expense• Overhead• Bonds, Insurance, Permits• Job Office Expense• Mobilization• Travel• Demobilization

Page 42: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Operating Equipment– Capital cost– Operation costs– Fuel– Permits– Insurance

Page 43: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Project Selection Estimates

• Usually based on conceptual

• Estimate of costs

• Estimate of benefits

• “The future, cloudy it is.” – Master Yoda

Page 44: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Engineering Design Estimates

• Selecting materials

Insulation thickness

Heat loss

Fuel expense• Design life• Economic analysis• Careful with “free money”

Never call it that

Page 45: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Change Orders

• Type I and Type II

• Extra labor, materials, etc.

• Delays

• On critical path?

• Delay job.

• Extra overhead

• Legal and consulting

Page 46: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Steps in contactor’s estimating process

Page 47: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Preliminary• Get resources to bid the job• Decide if you will bid• Get plans, get on bidders list• Engineer’s estimate reasonable• Broad brush estimate, schedule• Subcontracting strategy• Consider your resources

• Call your bonding company• Do you still want to bid?

Page 48: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

 Attend the pre-bid meeting!

Page 49: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Estimate• Manager allocates work• Be sure subs will bid• Take off major installed equipment

Check delivery timesBarge schedules

Schedule for quoteCheck delivery options, FOB

• Take off quantities• Special matters• Pre-bid fly over• Hire consultants• Do your own borings?

Page 50: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Historical unit prices

• Escalate?

• CPI, ENR– Felix work

Page 51: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Fig. 2: AK Highway CCI vs. Anchorage CPI-U for the period 1974 to 1983 (normalized to 1982-84=100)

405060708090

100110120130140150160

19

74

19

75

19

76

19

77

19

78

19

79

19

80

19

81

19

82

19

83

Dates

AK HighwayCCI

AnchorageCPI

Linear(AnchorageCPI)

Linear (AKHighway CCI)

Average Rate of Inflation 1974-1986: 8.0%

Average Rate of inflation 1974-1986: 8.2%

Page 52: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Fig. 5: Alaska HCCI vs. California HCCI

405060708090

100110120130140150160170180190

1974

1976

1978

1980

1982

1984

1986

1988

1990

1992

1994

1996

1998

2000

Dates

Alaska Highway CCI

California Highway CCI

Linear (Alaska HighwayCCI)

Linear (California HighwayCCI)

Page 53: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Fig. 6: Alaska HCCI vs. ENR Construction Cost Index

405060708090

100110120130140150160170180190

1974

1976

1978

1980

1982

1984

1986

1988

1990

1992

1994

1996

1998

2000

Dates

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

Alaska Highway CCI

ENR Construction CostIndex

Page 54: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Estimating guides

Production rate

See next

Unit Price

Read the front!

Factors

Crew size and production rate

Size crew and supervision

Equipment

Page 55: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

All methods

• Is production rate average or high?

• Where do you put you operating factor?

• Read the front!

• Check contract for delays, risk

• Liquidated damages

• Experience with owner, location, etc.

Page 56: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Do you still want to bid??!!

• If so, secure bonding and financing

• Prepare bid documents with prices blank

Page 57: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

• Check subs and major suppliers again?• When, to the minute, will they give you the

price?• How?•  • Develop plan for bid delivery.• Communications• Time

Page 58: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Post bid

• Protest?

• Negotiations

• Intelligence?

• When is a deal a deal?

Page 59: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Plan for changes

• Pre-job photos and videos

• Documenting changes

• Know the contract

• Document everything

Page 60: Project Selection, Economics, Estimating Dr. Perkins CE 438 6 February 05

Ethics

• Never lie, cheat, or participate in any dishonest act• Admit your mistakes forthrightly, if they are mistakes• More often, just state the facts, without blaming

anyone, yourself included• Don’t “trade on the specifications” unless it is in

writing • Nothing unethical about asking for what you have

coming!• Or demanding, if the situation warrants it.