Acknowledgement I owe a great many thanks to many people who helped and supported me during the period of my internship and the writing of this report. My deepest thanks to Mr. Titare, the Project Manager of the Kapurbawdi Bhandup Tunnel Project for allowing me to complete my internship in this particular project. My deep sense of gratitude to Mr. Deshpande, Mr. Andure, Mr. Akre from the Civil Department; Mr. Devidas and the whole Surveyor Group, Mr. Chetan Shetty and Mr. Gunjan Disawal from Planning Department; Mr. Kate from Billing; Mr. Kulkarni from PMC Department; Mr. Hari and Mr. Pandurangarao from the Safety Department for their help and guidance. Thanks and appreciation to all the helpful people on the site and for their constant support. I would also extend my heartfelt thanks to my family and well wishers without whom this project would have been a distant reality. Date: 07/07/2011 Abhishek Sarkar 1

Upload: abhishek-sarkar

Post on 29-Nov-2014

223 views

Category:

Documents


9 download

DESCRIPTION

This is a Project Report of my 1month training as an intern

TRANSCRIPT

Page 1: Project Report for Tunnel Excavation

Acknowledgement

I owe a great many thanks to many people who helped and supported me during the period of my internship and the writing of this report.

My deepest thanks to Mr. Titare, the Project Manager of the Kapurbawdi Bhandup Tunnel Project for allowing me to complete my internship in this particular project. My deep sense of gratitude to Mr. Deshpande, Mr. Andure, Mr. Akre from the Civil Department; Mr. Devidas and the whole Surveyor Group, Mr. Chetan Shetty and Mr. Gunjan Disawal from Planning Department; Mr. Kate from Billing; Mr. Kulkarni from PMC Department; Mr. Hari and Mr. Pandurangarao from the Safety Department for their help and guidance. Thanks and appreciation to all the helpful people on the site and for their constant support.

I would also extend my heartfelt thanks to my family and well wishers without whom this project would have been a distant reality.

Date: 07/07/2011

Abhishek Sarkar

1

Page 2: Project Report for Tunnel Excavation

Table of ContentsAcknowledgement...........................................................................................................................1Details of the project: -....................................................................................................................3Scope of work: -...............................................................................................................................3Daily Activities: -.............................................................................................................................5

Cycle of Daily Activities: -.........................................................................................................5Details of the Daily Activities: -..................................................................................................5

Surveying:...............................................................................................................................5Drilling:..................................................................................................................................6Blasting Material Loading and Charging:..............................................................................6Blasting and Venting: ............................................................................................................7Loose Scaling: .......................................................................................................................7Mucking: ................................................................................................................................7

Geological report of the site: -.........................................................................................................8Execution of project: -.....................................................................................................................9

The shaft:.....................................................................................................................................9Assembly Tunnel and Tail Tunnel:............................................................................................10Placing of Ribs:.........................................................................................................................11Construction of Retaining Wall:................................................................................................12

Planning on site: -..........................................................................................................................13Safety: -..........................................................................................................................................16Conclusion: -..................................................................................................................................19

2

Page 3: Project Report for Tunnel Excavation

PROJECT REPORT

Name of Project: - Tunnel Excavation from Gundovli to Bhandup

Details of the project: -The project is divided mainly in two parts. The first section is called Section A and the next is called Section B. Section A is from Gundovli to Kapurbawdi and Section B is from Kapurbawdi to Bhandup. This is a project report on the section B, i.e., from Kapurbawdi (K2) to Bhandup. The main focus of this report is on the K2 end.

Scope of work: -The scope of work for Section B includes:(a) Construction of 11.8m diameter 108m deep Inlet shaft at Kapurbawdi (K2) and11.8m diameter 125m deep outlet shaft at Bhandup by conventional drilling andcontrolled blasting method including disposal of muck and pumping outseepage water.(b) Excavation for tail tunnel and TBM assembly area, at bottom of the shaft atKapurbawdi (K2) and tail and TBM removal area at Bhandup by drilling andcontrolled blasting method and disposal of muck.(c) Boring of Tunnel from Kapurbawdi(K2) with upward gradient 4.5:1000 byTBM. including communication facilities, safety measures, lighting,ventilation, dewatering, wet/dry mucking and its disposal, RCC lining of thetunnel to a finished 5.5 m diameter, Providing 4.9m diameter steel liners as per IS:2002 instead of RCC lining wherever necessary.(d) Probe hole drilling, pre-grouting and post-grouting with cement and/orchemical to control seepage of sub-soil water.(e) Dismantling of TBM and withdrawal of the same through shaft.(f) Concrete backpacking behind steel liner.(g) Supply, manufacture, laying, jointing and testing MS Pipelines and specialsalong with inside and outside surface treatment including allied civil,mechanical and electrical works. Interconnection of Upper Vaitarna and Diversion Maini to the manifold atKapurbawdi (K2) shaft.Manifold at Bhandup Shaft for connecions to the existing treatment plant, 900Mld treatment plant under construction and provision for connecting to futureGargai and Pinjal treatment plants.(h) Providing, supplying and erecting 2400/1800 mm diameter B/F valves alongwith DMJ, tapers and companion flange. Also providing, supplying anderecting 200 mm diameter Kinetic Air valves.(i) Provide concrete encasement to pipes etc.(j) Cement mortar lining for internal surfaces of liners & pipelines.

3

Page 4: Project Report for Tunnel Excavation

(k) Backfilling the shafts, assembly and the tail tunnel areas with murum /earth /tunnel muck /plum concrete.(l) Demolition of existing structure(m) Steel Bridge for pipeline.(n) Testing and Commissioning of the Tunnel.

4

Page 5: Project Report for Tunnel Excavation

Daily Activities: -

Cycle of Daily Activities: -1. Surveying2. Drilling3. Blasting Material loading4. Charging5. Blasting6. Venting7. Loose scaling8. Mucking

Details of the Daily Activities: -

Surveying:Surveying is the most essential activity in the daily cycle. Surveying includes checking the reduced levels at 1.00m chainage intervals. It also includes determining the undercut and overcut portions of the tunnel cross-section. Surveying also helps determine how much excavation has been completed and how much is remaining. It also checks the centre line alignment of the excavation to determine and to avoid the excavation going out of route.

Surveying in ProgressInstruments used for surveying:Surveying is done with some equipment. The main and the most important equipments are:

1. Total Station:A total station is an electronic/optical instrument used in modern surveying. The total station is an electronic theodolite (transit) integrated with an electronic distance meter (EDM) to read slope distances from the instrument to a particular point.

The major functions of total station are:a. Coordinate measuringb. Distance measuringc. Angle measuringd. Data processing

5

Page 6: Project Report for Tunnel Excavation

Total Station Tripod for Total Station

2. Auto Level: An automatic level or builder's auto level includes an internal compensator mechanism (a swinging prism) that, when set close to level, automatically removes any remaining variation from level. This reduces the need to set the instrument truly level, as with a dumpy or tilting level.

Automatic LevelSelf-leveling instruments are the preferred instrument on building sites, construction and surveying due to ease of use and rapid setup time.

3. Telescopic Staff:telescopic staff is used for taking the measurement with dumpy levels and to find out the vertical distance of a point with respect to a horizontal plane.

4. Steel Tapes: Steel tapes are used to measure chainage accurately and to take measurements of small objects accurately.

Drilling:After surveying is completed the next step is drilling. Drilling is done pneumatically with the help of compressed air and water. Both compressed air and water is supplied from the ground surface with the help of pipes and is distributed with the help of manifolds. The drillers drill hole on the rock surfaces according to the plan set by the engineers which is according to the amount of overcut or undercut or how much pull is required. Pull refers to the horizontal progress achieved after blasting.

Blasting Material Loading and Charging:After the drillers have completed the number of holes required up to the depth specified by the engineers, the next step is to fill those holes with blasting material. The blasting material used here is Super Power Gel 90 which is basically an aluminum nitrate

6

Page 7: Project Report for Tunnel Excavation

compound and it comes in thin straight packages. These gels are inserted into the holes and the LDD (long delay detonators) are used to charge the material. LDD is a type of electronic detonator which is designated by numbers, for e.g. No 1 LDD where the number indicates the delay in milliseconds. The holes are then packed with packing material and are made air tight. The site is cleared and then after giving the warning siren the blasting is done.

Blasting and Venting: After the sirens are given for warning, the blasts are done using the detonators. The blasts are to be done only between sunrise and sunset. After blasting a time period of 1.30 hrs to 2 hrs is allowed before entering the shaft and tunnel. After the specified time, the safety personnel enter the shaft with a gas detector and check the H2S and CO levels along with oxygen levels. The normal oxygen level is 20.8 and the H2S and CO content are zero. If the gases go beyond optimal levels the gas detectors gives a warning sound and the shaft is cleared again for another half an hour. The process is repeated until it is fit to work in the shaft.

Loose Scaling: Loose scaling of rocks means to check whether any loose pieces of rocks are attached to the tunnel walls. If this is not checked, then it may cause a safety hazard or an accident for the workers in the tunnel. Hence this is a very important step in the daily cycle.

Mucking: Mucking refers to the removal of the rocks after the blasting is completed. This clears the work zone so that the next cycle can start again. Mucking is done with the help of poclains and loaders. The rocks are collected and then loaded in muck buckets. These are then brought up to the ground level with the help of gantry crane. After the mucking is completed, the next cycle starts. Surveying is done to determine the pull of the blast and how much work is left.

7

Page 8: Project Report for Tunnel Excavation

Geological report of the site: -Extensive geological survey was done at the site during the excavation of the shaft to map the rock details. This geological mapping was aided by petrography examination. The types of rocks encountered were identified and the geological properties of the rocks were also determined. The joints and faults in the rocks were also identified. It was found that there are a total of six sets of joints in the rock mass and it was mapped. The rock type was identified basically as basalt.

Thin Layered Amygdaloidal Basalt with Parallel Quartz Filling

Different types of basalts were encountered like compact basalt, amygdaloidal basalt, small deposit of quartz, tuff basalt and a little amount of volcanic ash. It was determined that the rocks were created during the Upper Cretaceous to Plaegene age. This lies in the Deccan trap and was created by a volcanic eruption.Amygdaloidal basalt is often confused with vesicular basalt. Amygdaloidal basalt has no air gaps, all the gaps are filled with a secondary mineral and it often gives a spotted look. Vesicular basalt on the other hand has air gaps and allows water percolate through it.In geology the term joint refers to a fracture in rock where the displacement associated with the opening of the fracture is greater than the displacement due to lateral movement in the plane of the fracture (up, down or sideways) of one side relative to the other.Basalt is a very common igneous rock. In fact it is the most common rock in the Earth's crust. Almost all oceanic crust is made of basalt and basalt is a common extrusion from many volcanic regions around the world. It forms from the melting of the upper mantle and its chemistry closely resembles the upper mantle's composition. It is generally silica poor and iron and magnesium rich. Basalt originates from "hot spot" volcanoes, massive basalt flows and mid oceanic ridges. Basalt also comes from extensive lava flows. Basalt lava flows are not very viscous (a measure of resistance to flow) and so can flow easily and quickly across great distances delivering great volumes of basaltic rock.

8

Page 9: Project Report for Tunnel Excavation

Execution of project: -The project is being executed in the following steps.

The shaft:The shaft at Kapurbawdi end of the tunnel is 108.6 meters deep. The shaft was excavated with the help of drilling and controlled blasting. The initial portion of the shaft was done by excavators and well sinking. Well sinking is done with the help of force of gravity. The first step of well sinking is the making of the cutting edge and the liner plate. Then the reinforcement is done and the concreting of the first lift. An excavator is placed in the the well and the excavation starts. As the excavation proceeds, the well starts sinking and lifts are added. After the well reaches the rock bed, grouting is done to fill the cracks through the annular plugs. The rest of the shaft is excavated by drilling and controlled blasting. During blasting, the opening of the shaft is covered with metal cover so that the debris does not come out of the shaft and does not damage machineries or the people working on the site. After blasting the muck is collected in the muck bucket and is taken out of the shaft and dumped on the site. From there it is loaded on dumpers and is dumped in specified dumping places. The lead to these dumping sites is measured and is later used for planning and billing purposes. This is done till the shaft reaches the required depth.

The shaft at the Kapurbawdi end is 108.6 meters deep.As the shaft is excavated, arrangements for dewatering is also done so that the seepage water is pumped out and does not deteriorate the progress of the project. As the shaft increases in depth, provisions for air and water is made so that the people working in the shaft do not face any problems in breathing. The shaft walls are stabilised with shotcrete where ever necessary and rock bolts are also used. Shotcrete is done with steel fabrics and without steel fabrics depending on the nature of the shaft wall. If fabrics are used with shotcrete then its depth is 100 mm and it 50 mm if the shotcrete is done without fabrics.

9

Page 10: Project Report for Tunnel Excavation

Assembly Tunnel and Tail Tunnel:According to the tender, an assembly tunnel of 100 meters length and a tail tunnel of 50 meters have to be excavated. Both the assembly tunnel and tail tunnel have been excavated with the drilling and blasting method. The assembly and tail tunnels are excavated with heading and benching method. In this method, the tunnels are not excavated completely at one go. The tunnel face is divided into heading and benching portions. After that, the excavation of the heading is done and after it proceeds to a certain length, the excavation of the benching portion is done.

This method is very effective when the excavation has to be done with limited resources. This also gives us the example of the type of rock ahead, so that before benching, one can take measures accordingly. The assembly tunnel is directed towards the Bhandup end.The measurements of the assembly and tail tunnel at different sections and its progress is taken by the survey department after 1 meter chainage. The overcut and undercut is also recorded by the survey department. After the blasting is done, the tunnel sections are checked for loose rocks and if found they are scaled. The next stage is taking out the muck. Poclains and loaders are placed in the shaft with the help of gantry crane. The poclain and loader collect and put the muck in the muck bucket which is then taken out by the gantry crane. The muck bucet is emptied on the dumping place on the site and after that the muck is dumped at specified dumping grounds.

10

Page 11: Project Report for Tunnel Excavation

Placing of Ribs:Ribs are placed where the tunnel section is weak and there are changes of loose rock debris falling. The ribs are placed over there for support to the section. The ribs are steel structure. The ribs are made on the ground surface and then lowered in the tunnel with the help of gantry cranes.

The space between the ribs and the tunnel section is then filled with concrete. The ribs used till date is made from ISMB200 steel sections and the steel plates used are 3mm thick. The steel used in each and every structure has to be calculated and kept in record for the reconcilation which is used by the Planning department.

11

Page 12: Project Report for Tunnel Excavation

Construction of Retaining Wall:A retaining wall was constructed at site. This retaining wall was constructed because the space available on site was less. This created a need for more space and hence the retaining wall was constructed. Retaining walls are constructed to stabilize slopes or to give support to the ground behind it and not allowing it to move downwards and outwards. The land was thus expanded using rubble and soil and creating a retaining wall in front of it tohold it in place.

12

Page 13: Project Report for Tunnel Excavation

Planning on site: -Planning is one of the most important part of any project. Without proper planning, a project can face any number of problems and hurdles. Planning means completing a project within the time, cost and scope of the project. These three parameters a make planning a complete process.

Project Triangle

Planning is the most essential step in project management.

Here are a few reasons why planning is important for a project: -1. Happy customers:

The main aim of any project is to get happy and satisfied customers. With proper planning, one can get happy customers or clients for each and every project. If clients get happy, then the reputation of the company or firm increases and thus in turn helps the company get more projects.

2. Achievement of Objectives:Planning is also important to know what the objectives or deliverables of a project is. It is also required to know whther they have been achieved or not.

3. Timely Completion of the Project:Time is one of the major factors in the project management triangle and hence has to be always kept in mind. Timely completion of projects gives happy clients whch is the end result wanted for every project.

4. Flexibility of Project:A project may sometime face hurdles in the form of resource availability or some other factor. In these cases, proper planning can avert the time and cost overrun which would be faced otherwise. Thus planning makes a project flexible. It gives alternate paths to complete a project and not be stuck with a single path.

5. Better Financial Performance:Better planning means better financial performance.

6. More Productivity:More productivity means happier workers.

13

Page 14: Project Report for Tunnel Excavation

After the initiation stage, a project is planned to the appropriate level of detail. The main purpose of planning is to plan time, cost and resources adequately to estimate the work needed and to effectively manage risk during project execution. A failure to adequately plan a project greatly reduces the project's chances of successfully accomplishing the goals.Project planning generally consists of

1. Determining how to plan (e.g. By level of detail or rolling wave)2. Developing the scope statement3. Selecting the planning team4. Identifying the deliverables and creating the work breakdown structure5. Identifying the activities needed to complete those deliverables and networking the

activities in their logical order6. Estimating the resource requirements for the activities7. Estimating the time and cost for the activities8. Developing the schedule9. Developing the budget10. Risk planning11. Gaining formal approval to begin work

Additional processes such as planning for communications and scope management, identifying roles and responsibilities, determining what to purchase and holding a kick-off meeting are generally advisable.For new product development projects, conceptual design of the operation of the final product may be performed concurrent with the project planning activities, and may help to inform the planning team when identifying deliverables and planning activities.Once the project is in the execution stage, the main role of the planning engineer is to monitor and control the progress of the project. Monitoring the project means to check the daily achievement of progress to the progress planned. This is done by updating the progress in the Microsoft Project using the Update Task tool. The progress is checked with the baseline which was approved when the plan was approved. If there are any discrepancies or problems with resource availability, the plan can be changed accordingly. That is why a plan should be flexible. The daily cash flow is also checked wih the original stipulated cash flow.All these data are collected in the form of Daily Progress Report (DPR). The DPR of each day is then consolidated and a monthly report is made. This monthly report is called the Monthly Progress Report. Similarly there are Quarterly Progress Report and Annual Progress Report. Another major document in monitoring and controlling of the project is the Daily Labour Report. This report gives the summary of the number of labors and the number of hours they have worked. This makes it easier to pay the labors and also update the cash flow accordingly.Reconcilation:Reconcilation is veryimportant planning activity on site during execution stage. Reconcilation gives an idea on the stock which is available on site or in the stores. This also makes it possible to know the amount of the stock that has already been used in the

14

Page 15: Project Report for Tunnel Excavation

construction activities. For instance, the amount of steel is known when it is first delivered. But after using it to make different structures, it becomes necessary to know the amount of steel left. This is done by precise calculation of the weight of the steel used. Similarly it is done for other materials too, like, shotcrete material, cement bags, etc. The amount of scrap generated is also calculated so that the amount of steel used is accurate and all the wastage is also accounted for.

15

Page 16: Project Report for Tunnel Excavation

Safety: -Safety on site is the most important aspect of a project. Without safety equipments no one is safe on the site. Every body is issued Personal Protective Equipments. These include helmets, safety shoes, nose masks, reflective jackets.

Protective Helmets Reflective Jackets

There are other safety equipments according to the class of worker one falls in. For example, riggers get safety hooks and gloves. Every member on the site has to go through a process called Safety Induction. In this safety induction they are told about the do's and dont's on the site. They are told about the proper use of their safety equipments, on how to use them and what they are supposed to do during an emergency. All the equipments are issued by the name of the individual and a proper record of these equipments are kept in a record-book with the Stores department.

An assembly point is defined, which is a safe place to gather during an emergency. Every body is issued a role they have to play during an emergency. People are grouped in different groups according to the role they have to play. This is absolutely essential as otherwise there would be a confusion. Confusion is the last thing needed during an emergency. There are groups like the evacuation group, the fire fighting froup, the head count group, etc.

Proper areas are marked as smoking or no smoking areas. Every explosive materials are kept in specified spots and are locked when not in use. The Safety department is also responsible for the ERP or Emergency Rescue Plan. This is the procedure to be followed when ever there is an emergency. The plan also includes the proper positioning of fire extinguishers so that it is within the reach of every individual. Fire extinguishers are classified according to the type of fire they help put out. Generally they are classified as type A,B,C or D. However now-a-days fire extinguishers also come in type ABC, which puts out fire of all the type A, B and C. This is the main type of extinguisher used in this project.

16

Page 17: Project Report for Tunnel Excavation

The fire extinguishers are checked periodically to see whether the required pressure is maintained in the can otherwise the squeeze of the extinguisher is reduced which can cause a hazard during fire fighting. Proper alarm installation is also taken care of by the safety department. Intercom facility also lies in the ERP. Intercom is the main method of communication between people of different departments. Emergency numbers are installed over each telephone set so that the right people can be contacted when needed. This list includes the phone numbers of the Police, the Firefighting Department, the Hospital, Ambulances, etc.

The euipments used on site is also checked periodically by 3 rd parties to see whether they are in working condition or not. As most of the work on this project is done by cranes, the shackles, wire ropes and other tools are checked every six months and are certified to be capable of taking the amount of load it was meant to take. Another safety measurement taken is that every vehicle that comes in or goes out of the site have to submit a copy of their Licences, R.C papers, PUC paers and also have to give details regarding where they are coming from or where they are going to. This way all the vehicles can be tracked and in case of any accident or emergency the whereabouts of the vehicle will be known.

HIRA or Hazard Identification and Risk Analysis is an important process done by the Safety department with all the other departments to identify the hazards and risk that might crop out during the period of the project. This meeting also discusses on how to overcome these risks and hazards.

All the places where the work is going on is cordoned off with help of barriers. The barrication type depends on the type of the project going on. For instance if it is a road project, then the barrication used is G I sheets, in cases of building projects wooden rails are used, in this project barrier tapes are used.

The safety department also keeps a record of the explosive materials going in the tunnel and the number of explosives returned along with the LDD (long delay detonators).

17

Page 18: Project Report for Tunnel Excavation

After a period of 1 hour to 1 hour 30 minutes, a safety personnel goes down in the shaft with a gas detector to check whether the conditions were ideal to work in.

Mine Safety Appliances Co. Multi Gas Detector

The otpimal levels safe for working conditions are:

1. O2 : 29.5 to 20.8

2. H2S: 50 ppm

3. CO: 10 ppm

18

Page 19: Project Report for Tunnel Excavation

Conclusion: -In conclusion, I would like to emphasise the fact that a rpoject is successful when all the different departments work together. All the departments are like a cog wheel in a machine. Separately they are useles, but when used together they make a very useful machine. In this particular project, I can say it sets a wonderful example of the above thought and I sincerely wish this project a successful end!