project management using lean six sigma ... project management using lean six sigma vision from a...
TRANSCRIPT
Pag.1
PROJECT MANAGEMENT USING LEAN SIX SIGMA
VISION FROM A GREEN BELT
Abstract
This work shows the use of Lean Six Sigma methodology at the Green Belt level. According to that objective
it is shown the relevance of its application and also its origin and the main tools used. In complement it
includes the use of Lean Six Sigma in the management of an industrial project for physical defects
reduction. The project objective was 50% reduction in scrap cost due to pieces with physical defects. That
objective equals 5.500€ per month in cost reduction which was projected saving of 35.200€ for the year
2008 and 66.326€ for each of the next two years, considering the production level and spectrum unchanged,
and not taking into account economic factors such inflation.
Upon the project implementation the monthly scrap cost due to physical defects changed to 4.590€. So the
objective was accomplished by achieving a cost reduction of 58%. Concerning the related the savings the
goal was also met with a projected saving of 40.053€ (including the investment costs) for 2008 and 74.126€
for the next two years.
Keywords
Lean Six Sigma
Project Management
Cost Saving
Process
DMAIC
Pag.2
1 – What is Lean Six Sigma
Most of the existing organizations are heavy and burocratic structures. This happened because, in order to
satisfy what was seen as the customer’s requests, companies tend to implement stages to their process. As
a consequence the process chain became extremely big with low added value along it when compared to its
extension. That resulted in price increase due to those costs.
With the birth of more demanding customers who are less willing to pay for the costs of these heavy
structures, the organizations are starting to change their view on the subject. So, they started seeing that
profit will have to be raised from a cost reduction policy instead of the traditional price increase.
Price – Cost = Profit
Born from the need of cost reduction appeared the Lean Manufacturing (usually designated as Lean) and
the Six Sigma methodologies. And from combining both we have Lean Six Sigma.
Lean is the set of tools, knowledge and methodologies used to remove waste and no value added activities.
Waste can be divided in 7 types, known as 7 muda (Japanese word for waste), that are: waiting,
overproduction, rework, motion, transportation, processing and inventory.
As for Six Sigma it is a methodology where the objective is to improve processes and the way the work gets
done in an organization. It mainly consists on reducing variation within the processes in order to improve
them. When we have an organization operating its processes at Six Sigma quality level then it commits no
mores than 3,4 defects per million opportunities for defects. This means that the it has the processes
operating correctly 99,9997% of the time. The core of Six Sigma is that it has a structured stage
methodology for performance problem solving and performance improvement called DMAIC.
It is important to refer that the sigma letter (σ) which, in
statistics, is used to represent standard deviation or
variation of a population must not be confused with the
sigma level in Six Sigma. The sigma level measures the
distance from average to the specification limit of a
characteristic, measured in standard deviations. So, the
essence of Six Sigma is to know how many standard
deviations you can fit between your average and the specification limit.
The Lean Six Sigma combines the speed increase and the performance
improvement related with the reduction of waste and no value added activities,
that come from Lean, with the quality improvement that comes from the
processes improvement and variation reduction using Six Sigma tools. Lean Six
Sigma is more than a toolbox. It’s a way of thinking, acting, organizing ideas and
managing projects directly related with organization and top management
objectives.
CHEAPER
LEAN
FASTER
SIX
SIGMA
BETTER
LEAN
SIX
SIGMA
Figure 1 - Example of a 3 sigma process
Figure 2 - Lean Six Sigma
pillars
Pag.3
Lean Six Sigma consists on performance improvement projects and therefore is concerned on achieving
results. To achieve and maintain its results it defines and acts on the inputs that cause the undesired results.
It can be easily described by the mathematical expression f(X)=Y, where X are the inputs and Y are the
outputs.
2- DMAIC – Define, Measure, Analyse, Implement, Control
The Lean Six Sigma follows a structure called DMAIC, which is the abbreviation for Define-Measure-
Analyse-Implement-Control. As mentioned before, the DMAIC has its origins in the Six Sigma and the
projects follow those stages from the beginning until the end. Along these stages, the projects focus gets
narrower in order to really attack the variables that impact the problem. At the end of each stage there’s a
review, like a toll, usually called “Gate Review”. Here the project follow-up is made and the metrics, the
scorecards, and all the project findings are presented. At these points it is decided if the project shall go on
or stop It also can be set that it needs more work or data in order to go to the next stage.
We can briefly explain the DMAIC stages as follows:
Define: It’s the first step and it’s the project kick-off. Here it’s important to define the project scope, the goal,
the team, the metrics and above all the problem statement. It has to be linked with the organization strategy
and objectives.
Measure: In order to determine the actual situation it is necessary to collect data. At this stage it is the team
objective to gather precise and relevant measures related with the problem.
Analyse: After having collected the data it has to be analysed in order to determine the relations between the
variables. To solve the problem one has to understand the cause-effect relations
Implement: Consists on changing the process supported with the measures and analysis done previously. It
is time to improve the process assuring that defects are reduced and the processes are optimized.
Control: It is DMAIC’s last stage. To control is to assure that the process is working under control and within
the specification. It also consists in deploying solutions that guarantee that in case a defect it is detected and
alert is given.
3-The project
The project included in this work concerns an electronic component. That component consists of a metallic
nucleus obtained by pressing and sintering a metallic powder that afterwards is submitted to an
electrochemical process that confers him the desired electric proprieties. After that, the electric terminals are
assembled and the nucleus is covered by an epoxy resin that confers physical and humidity protection.
Follows a stage where all pieces are laser marked printing its electrical characteristics, the manufacturer
name and the date code.
Pag.4
At the end of the line all pieces are verified concerning their electrical
and physical proprieties before shipping. The approved components go
to the customer and the other are rejected as scrap.
4-Define
The objective of this phase is to set the project scope, goal, financial outcome, metrics, team and duration
based on the problem definition.
The first step is to choose the project. The difficulty is not to find projects but to select the best one. In Lean
Six Sigma the best is the one that allows greater savings in a short period of time, with the available
resources and with effect in the future. As for the objective it is common to be cost reduction, scrap
reduction, process variation reduction, process speed increase, amongst many others.
It is now time to select the team. A usual Lean Six Sigma team is multidisciplinary and contains several
positions within the organization structure that includes a champion that reports directly to the top
management, a sponsor that supports the changes and the solutions implementation, several Lean Six
Sigma levels where the Black belt is the highest and is the team leader, and some experts and stakeholders
may also join the team.
Now the team is expected to define the problem by making an early evaluation and estimation of the
potential savings, main problems and focus. It is followed by the collection of the Voice of the Customer. It
implies knowing which the important requisites for the customer are. The customer can be either internal or
external. After knowing the customer requisites the team has to know what are the inputs and outputs of the
process and to check if they are correctly defined and controlled, since they are potential causes of
variation. That activity consists in the construction of a matrix called SIPOC1.
In the project the problem analysed consisted on the reduction of
scrapped pieces due to physical defects. That amount of scrap costs on
average 11.000€ per month and the objective is to reduce that cost in
50% which correspond to a projected saving of 66.000€ per year
considering a fixed production level and spectrum and not taking into
account any financial factors.
From the problem analysis the team concluded that product family 95x
represented most of the cost (21%). The costs were divided amongst all
1 SIPOC is the abbreviation of Suppliers-Inputs-Process-Outputs-Customers
Figure 3 - Electronic component scheme
Figure 4 - Physical loss by product
Pag.5
products and the differences are mainly related to its production costs. Collecting the Voice of the Costumer
3 main requisites/defects arose: Visible nucleus, poor encapsulation and bad marking. During the SIPOC
construction it was found that there was no work instruction for the cameras inspection and adjustment.
One was created by the team.
The Define phase, as all the phases in Lean Six Sigma, ends with the Gate Review. Here is expected that
the team presents the project definition, scope, objective, and expected financial impact. Also to present all
findings that may help deciding if the project should go forward or not. In the studied project the main finding
was a process input that hasn’t controlled but didn’t impact the project in order to make it stop.
5-Measure
The objective of the Measure phase is to collect reliable data that allows to know and understand the
process performance.
In order to collect significant data for the project at this stage the team has to study the process and choose
the important characteristics that shall provide information for the project. To accomplish this task a map of
the product value chain is made to better understand the process and its variables. It is called Value Stream
Mapping. After it is done the team can easily elaborate a Data Collection Plan for the selected variables and
characteristics. Before starting to gather the data the team first has to be sure that the measure system is
adequate for desired information. So, at this point is the team performs studies on the measuring system
usually analysis of variance
Figure 5 - 2nd R&R study for "step angle" characteristic
During the project the team elaborated a measure plan that included all the requisites defined in Voice of the
Customer and all its critical variables. While analysing the measure system it was found that for the measure
of the “step angle” it wasn’t consistent since it lacked repeatability and reproducibility. The team concluded
that the procedure instructions weren’t clear. That caused different interpretations amongst the operators
that resulted in a poor measure system. The instructions were reviewed and a new R&R test was performed.
This time the results were consistent, having a variation lower than 10% that was the maximum acceptable.
This allowed the data to be collected.
Pag.6
At the Measure Gate Review was presented the Value Stream Map, the Data Collection Plan, the Measure
System Analysis and also the data collected. Those were the expected items to be shown. The fact that the
detected problems were solved allowed it to be successfully approved for the next stage.
6 -Analyse
The objective of this phase is to identify the main cause-effect relations that explain the results for the inputs.
Based on the information gathered in the previous stage the team has now to establish the cause-effect
relations that explain the outputs according to the inputs. Usually it starts to use subjective evaluation based
on team experience and knowledge of the process. In this kind of tools we can find the brainstorming and
the Ishikawa’s Diagram (also known as the fishbone diagram). Both consist on gathering as many probable
causes as possible. In the Ishikawa’s diagram the causes are organized in 6 main groups: Mother Nature;
men; machine; method; measure; material. After it the probable causes refined and analysed using more
objective tools. These tools have a stronger statistical component that allows the team to be confident on the
presented conclusion. In such tools are included the Regression and the Hypothesis Test.
Using the FMEA (Failure Modes and Effects Analysis) it can also be possible to establish why an output
occurs and why it is not detected/avoid.
In the Physical Defects projects the team started by separating the problem according to the different failure
modes and building Ishikawa’s Diagrams for them. Those diagrams gave birth to an action list that consisted
in a group of actions and analysis to be performed in order to determine if those probable causes were valid.
Table 1 - Main actions and result for the defects in study
Pag.7
It included simple actions, such as to verify if the established parameters were being respected and that they
weren’t changed by the operators and some more complex actions as material analysis in an external
laboratory. Most of the probable causes were considered not valid but some remained and resulted in
process changes.
The table 1 summarizes the results of Analyse phase, presenting the relevant probable causes from all that
were studied.
The Gate Review consisted on the presentation data analysis and also the cause-effect relations determined
by the team. The project was allowed continue with the advise that a deeper analysis could be needed.
7-Implement
Needless to say, at this phase the team is expected to implement solution according to the analysis made
earlier. Each project is different and there are no standard solutions.
The DOE (Design Of Experiments) is considered to be part of the implementation phase. It consists in
creating a matrix of tests (experiments) in order to obtain outputs of the manipulation of variables. This
statistical tool allows to see the effects of changing more than one variable at once, which goes further than
the usual tests.
When dealing with problems related to process speed and product flow it is common the need to implement
solutions such was Kanban cards that organizes the workstations in order to produce just what is needed
and the Pull flow that focus on the product leadtime reduction. Also solutions or actions as SMED or 5S
campaigns may be implemented during this stage.
Concerning the project under analysis, for the poor encapsulation problem the solution implemented was
maintenance to the equipment which detected several pieces with excess wear that had to be changed and
a DOE as made and resulted in a parameters optimization.
Table 2 - New parameters values
The root cause for this problem was the fact that the epoxy was now being delivered from a new location
due to the supplier factory change. Despite having the same chemical composition and having the
parameters within the control limits, the epoxy viscosity was lower. This caused the problems to occur
because the machines parameterization was not on its optimal point.
Pag.8
Regarding the visible nucleus defect the
team implemented a new parameter
verification. This verification consisted on
checking the density of the bath of nitrate
and solvent during its operation time and not
only when it was prepared. When detected
out of specification it has to be corrected. In
this case the root cause consisted on the
evaporation of the solvent that caused a
higher density of the bath. This results in a
thicker nucleus cathodic layer that
overcomes the epoxy encapsulation making
it appear outside of the encapsulation.
For the last situation, bad marking, the decision was to change the consumption pressure limit for the CO2
bottles. The root cause in this case was the fact that the equipment did not preformed as expected with such
a low pressure.
It is important to notice that the number of defects in ppm went from 1467 to 937 ppm of defects/day and
then to 91 ppm of defects/day with the new parameters in the encapsulation problem. As for the Marking
issue using a CO2 pressure greater than 2,0 bar the number of effects came down to near zero against the
600 ppm that occurred when using lower pressures
This phase gate review consisted on showing the results obtained with it actions implemented.
8-Control
Here the selected solution is replicated whether applicable and error proof systems are designed, also
FMEA and Control Plan are reviewed or created.
The theory behind error-proof systems and detection systems is quite simple. It consists on avoiding the
error or detecting it as soon as possible because quality cost increases along a product value chain. So the
solution is whenever possible to design systems where it is impossible to commit mistakes, when it isn’t
possible the mistake must be detected as soon as possible. In order to help accomplish this objective the
work instructions have to be clear and updated, the control plan has to exist in such a way that guarantees
that the critical parameters are checked and that the defects are detected.
In the project the team reviewed all the mentioned documentation, that for the bad encapsulation problem
included a maintenance program review. For this case was also developed a software tool that warns when
the maintenance date is approaching and blocks the equipment when it reaches that date.
Figure 6 - Poor encapsulation defects evolution
02-06-2008
25-05-2008
17-05-2008
09-05-2008
01-05-2008
23-04-2008
15-04-2008
07-04-2008
30-03-2008
22-03-2008
2500
2000
1500
1000
500
0
data
Individual Value
_X=91UCL=232
LCL=-50
1 32
1
Chart of ppm defeitos
BEFORE MAINTENANCE AFTER MAINTENANCE NEW PARAMETERS
Average = 1467 defects/day
Average = 937 defects/day Average = 91 defects/day
Pag.9
9 -Financial outcome
During the Lean Six Sigma projects then team can never lose track of the financial metrics and indicators in
order for the project to be successful. The results achieved were very successful has can be seen in the
tables. The project met its goal of 50% cost reduction due to
physical loss, achieving a global reduction of 58% ( from
11.061€ to 4.590€ monthly).
Taking into account that some investments were made the
project return was also calculated. In this calculation the term
“investment” refers to equipment acquisition and the
“implementation cost” contains the costs related directly with
the project implementation such as the cost of using less CO2,
the cost of nitrate+solvent bath analysis, and others. As
mentioned before the calculation does not consider financial
factors. But it should be noticed that the scrap cost considered
is the value of the product in the area where it is scrapped,
with both direct and inderect cost associated and that depends
on the product family.
The projected return is higher than the initial prediction so, the
project was also successful in this matter.
Jan Fev Mar Abr Mai Jun Jul Ago Set Out Nov Dez
Implem
entatio
n anual
costs TOTAL
Savings 0 0 0 542 2364 4214 6471 6471 6471 6471 6471 6471 --- 45946
Investements related
with the project (year
2008)
0 0 0 0 1789 2143 0 0 0 0 0 0 --- 3932
Savings 2008 0 0 0 542 575 2071 6471 6471 6471 6471 6471 6471 1961 40053
Savings 2009 6471 6471 6471 6471 6471 6471 6471 6471 6471 6471 6471 6471 3526 74126
Savings 2010 6471 6471 6471 6471 6471 6471 6471 6471 6471 6471 6471 6471 3526 74126
Values in €
Table 4 - Yearly project return
Product
FamilyDefect
Average
Monthly
Physical
Loss Cost
Before
Project
Average
Monthly
Physical
Loss Cost
After
Project
Poor encapsulation 1.232 € 314 €
Bad marking 369 € 152 €
Visible nucleus 688 € 271 €
Poor encapsulation 452 € 187 €
Bad marking 348 € 166 €
Visible nucleus 798 € 241 €
Poor encapsulation 924 € 297 €
Bad marking 252 € 111 €
Visible nucleus 34 € 16 €
Poor encapsulation 528 € 214 €
Bad marking 437 € 211 €
Visible nucleus 33 € 14 €
Poor encapsulation 232 € 96 €
Bad marking 487 € 196 €
Visible nucleus 147 € 74 €
Poor encapsulation 123 € 66 €
Bad marking 429 € 166 €
Visible nucleus 321 € 133 €
Poor encapsulation 524 € 259 €
Bad marking 122 € 52 €
Visible nucleus 21 € 10 €
Poor encapsulation 154 € 76 €
Bad marking 197 € 111 €
Visible nucleus 344 € 124 €
Poor encapsulation 211 € 114 €
Bad marking 23 € 12 €
Visible nucleus 54 € 26 €
Others global 1.577 € 881 €
TOTAL 11.061 € 4.590 €
91 X
95 U
95 D
10 X
91 B
95 X
91 D
91 C
20 V
Table 3 - Monthy savings by product family
Pag.10
BIBLIOGRAPHY
1-The Black Belt Memory Jogger; Six Sigma Academy; 1st Edition; Goal\QPC
2-Gestão da Produção; Coutois,Alain; Pillet, Maurice; Martin-Bonnefous, Chantal; 5ª Edição; Lidel
3-The Machine That Changed The World; Womack, James P.; Jones, Daniel T.; Roos, Daniel; Free
Press
4-Gestão de Operações – na indústria e nos serviços; Pinto, Paulo João; 2ª Edição; Lidel
5-What is Lean Six Sigma?; George, Mike; Rowlands, Dave; Kastle, Bill; George Group
6-Lean Six Sigma Pocket Toolbook; Michael, George L.; Rowlands, David; Price, Mark; Maxey, John;
McGraw Hill
7-The LSS Academy Guide to: Lean Manufacturing; Pereira, Ron; LSS Academy
8 – Estatística Aplicada Vol.2; Reis, Elisabeth; Melo, Paulo; Andrade, Rosa; Calapez, Teresa; Edições
Sílabo