project management in practice, fourth edition prepared by scott m. shafer, updated by william e....

28
Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University Copyright 2011 John Wiley & Sons, Inc. 5-1 Mantel, Meredith, Shafer, and Sutton John Wiley and Sons, Inc.

Upload: gideon-denham

Post on 31-Mar-2015

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Project Management in Practice, Fourth Edition

Prepared byScott M. Shafer,

Updated by William E. Matthews and

Thomas G. Roberts, William Paterson University

Copyright 2011 John Wiley & Sons, Inc. 5-1

Mantel, Meredith, Shafer, and Sutton

John Wiley and Sons, Inc.

Page 2: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

PERT and CPM

Copyright 2011 John Wiley & Sons, Inc.

5-2

Program Evaluation and Review Technique (PERT)• U.S. Navy, Booz-Allen Hamilton, and Lockheed Aircraft• probabilistic activity durations

Critical Path Method (CPM)• Dupont De Nemours Inc.• deterministic activity durations

Page 3: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

The Language of PERT/CPM

Copyright 2011 John Wiley & Sons, Inc.

5-3

Activity• a task or set of tasks• uses resources and time

Event• an identifiable state resulting from completion of one

or more activities• consumes no resources or time• predecessor activities must be completed

Page 4: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

The Language of PERT/CPM continued

Copyright 2011 John Wiley & Sons, Inc.

5-4

Milestones• identifiable and noteworthy events that mark

significant progress

Network• a diagram of nodes (activities or events) and arrows

(directional arcs) that illustrate the technological relationships of activities

Path• a series of connected activities between two events

Page 5: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

The Language of PERT/CPM concluded

Copyright 2011 John Wiley & Sons, Inc.

5-5

Critical Path• the set of activities on a path (from the project’s start

event to its finish event) that, if delayed, will delay the completion date of the project

Critical Time• the time required to complete all activities on the

critical path

Page 6: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Building the Network

Copyright 2011 John Wiley & Sons, Inc.

5-6

There are two ways of displaying a project network

• Activities on Arrows (AOA) network … in which the activities are shown as arrows and events as nodes

• Activities on Nodes (AON) network … in which each task is shown as a node and the technological relationship is shown by the arrows

Page 7: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

AON Network Stage 1

Copyright 2011 John Wiley & Sons, Inc.

5-7

Page 8: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

AON Network - Stage 2

Copyright 2011 John Wiley & Sons, Inc.

5-8

Page 9: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

AON Network - Complete

Copyright 2011 John Wiley & Sons, Inc.

5-9

Page 10: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

AOA Network – Stage 1

Copyright 2011 John Wiley & Sons, Inc.

5-10

Page 11: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

AOA network – Stage 2

Copyright 2011 John Wiley & Sons, Inc.

5-11

Page 12: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

AOA Network - Complete

Copyright 2011 John Wiley & Sons, Inc.

5-12

Page 13: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

AOA Network – Showing The Use of a Dummy Task

Copyright 2011 John Wiley & Sons, Inc.

5-13

Page 14: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Information Contents in an AON Node

Copyright 2011 John Wiley & Sons, Inc.

5-14

ES EF

ES - Earliest start timeEF - Earliest finish time LS - Latest start timeLF - Latest finish time

LS LF

Activity Activity name duration

Page 15: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Calculating Activity Slack

Copyright 2011 John Wiley & Sons, Inc.

5-15

Latest Start Time (LS) – Earliest Start Time (ES) = Slack

Latest Finish time (LF) – Earliest Finish time (EF) = Slack

Page 16: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Calculating Probabilistic Activity Times

Copyright 2011 John Wiley & Sons, Inc.

5-16

Page 17: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

The Statistical Distribution of all Possible Times for an Activity

Copyright 2011 John Wiley & Sons, Inc.

5-17

Page 18: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Activity Expected Time and Variance

Copyright 2011 John Wiley & Sons, Inc.

5-18

22

E

6

)(Var

6

)(

6

)4(T

ab

ab

bma

Page 19: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

95 Percent Level

Copyright 2011 John Wiley & Sons, Inc.

5-19

Task will be a or lower 5 percent of the time

Task will be b or greater 5 percent of the time

3.3

)( ab

Page 20: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

90 Percent Level

Copyright 2011 John Wiley & Sons, Inc.

5-20

Task will be a or lower 10 percent of the time

Task will be b or greater 10 percent of the time

6.2

)( ab

Page 21: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

The Probability of Completing the Project on Time

Copyright 2011 John Wiley & Sons, Inc.

5-21

2

)(

D

Z

=NORMDIST(D,,,TRUE)

Note: NORMDIST is a function within Excel when using the spreadsheet method

Page 22: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Selecting Risk and Finding D

Copyright 2011 John Wiley & Sons, Inc.

5-22

2 ZD

NORMINV(probability,,,TRUE)Note: NORMMINV is a function within Excel when using the spreadsheet method

Page 23: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Traditional Statistics Versus Simulations

Copyright 2011 John Wiley & Sons, Inc.

5-23

Similarity• both procedures assume that task durations are

statistically independent and the paths are independent

Difference• a simulation can circumvent the assumption of

statistical independence by including the activity or path dependencies as part of the model

Page 24: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Gantt Chart of a Sample Project

Copyright 2011 John Wiley & Sons, Inc.

5-24

Page 25: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Gantt Chart of Sample Project Showing Critical Path, Path Connections, Slack, ES, LS, EF, and LF

Copyright 2011 John Wiley & Sons, Inc.

5-25

Page 26: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Extensions to PERT/CPM

Copyright 2011 John Wiley & Sons, Inc.

5-26

Finish to Start (F to S)• finish of Activity A to start of Activity B

Start to Start (S to S)• start of Activity A to start of Activity B

Finish to Finish (F to F)• finish of Activity A to finish of Activity B

Start to Finish (S to F)• start of Activity A to finish of Activity B

Page 27: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Precedence Diagramming Conventions

Copyright 2011 John Wiley & Sons, Inc.

5-27

Page 28: Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University

Copyright

Copyright 2011 John Wiley & Sons, Inc.

5-28

Copyright John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work

beyond that permitted in Section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information herein.